technical specifications 28mva, 115/12.47 kv substation

60
Specifications BID NO. 18-67 Page 1 of 30 TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation Power Transformer TABLE OF CONTENTS 1.0 GENERAL REQUIREMENTS .............................................................................. 2 1.1 DELIVERY ........................................................................................................ 2 1.2 COORDINATION AND MEETINGS .................................................................. 3 1.3 DRAWINGS, DATA, AND SUBMITTALS .......................................................... 4 1.4 STANDARDS .................................................................................................... 6 1.5 MATERIALS...................................................................................................... 8 1.6 UNITS OF MEASURE ...................................................................................... 8 1.7 AUXILIARY EQUIPMENT ................................................................................. 8 1.8 EQUIPMENT IDENTIFICATION ....................................................................... 9 1.9 WIRE AND CABLE IDENTIFICATION .............................................................. 9 1.10 CONDUIT AND PIPING .................................................................................... 9 1.11 METAL FASTENERS ..................................................................................... 10 2.0 DETAILED TECHNICAL REQUIREMENTS ...................................................... 10 2.1 SCOPE ........................................................................................................... 10 2.2 USUAL SERVICE CONDITIONS .................................................................... 10 2.3 RATINGS ........................................................................................................ 10 2.4 CORE ............................................................................................................. 12 2.5 WINDINGS...................................................................................................... 12 2.6 BUSHINGS ..................................................................................................... 13 2.7 CURRENT TRANSFORMERS ....................................................................... 14 2.8 TANK .............................................................................................................. 14 2.9 OIL PRESERVATION SYSTEM ..................................................................... 16 2.10 RADIATORS ................................................................................................... 17 2.11 ACCESSORIES .............................................................................................. 17 2.12 DE-ENERGIZED TAP CHANGER (DETC) ..................................................... 20 2.13 LOAD TAP CHANGER AND CONTROLS (LTC) ............................................ 21 2.14 WIRING AND CABINETS ............................................................................... 22 2.15 TRANSFORMER OIL ..................................................................................... 24 3.0 TESTING ............................................................................................................ 25 3.1 SHORT CIRCUIT CAPABILITY ...................................................................... 25 3.2 FACTORY TESTS .......................................................................................... 25 3.3 FIELD TESTS ................................................................................................. 27 4.0 SPECIAL SHIPPING INSTRUCTIONS .............................................................. 27 4.1 PREPARATION FOR SHIPMENT .................................................................. 27 4.2 IMPACT RECORDERS .................................................................................. 28 4.3 NOTIFICATION............................................................................................... 28 APPENDIX A ................................................................................................................ 29 APPENDIX B ................................................................................................................ 30 SECTION 013524.45 – SAFETY REQUIREMENTS

Upload: others

Post on 16-Oct-2021

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 1 of 30

TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation Power Transformer

TABLE OF CONTENTS

1.0  GENERAL REQUIREMENTS .............................................................................. 2 1.1  DELIVERY ........................................................................................................ 2 1.2  COORDINATION AND MEETINGS .................................................................. 3 1.3  DRAWINGS, DATA, AND SUBMITTALS .......................................................... 4 1.4  STANDARDS .................................................................................................... 6 1.5  MATERIALS ...................................................................................................... 8 1.6  UNITS OF MEASURE ...................................................................................... 8 1.7  AUXILIARY EQUIPMENT ................................................................................. 8 1.8  EQUIPMENT IDENTIFICATION ....................................................................... 9 1.9  WIRE AND CABLE IDENTIFICATION .............................................................. 9 1.10  CONDUIT AND PIPING .................................................................................... 9 1.11  METAL FASTENERS ..................................................................................... 10 

2.0  DETAILED TECHNICAL REQUIREMENTS ...................................................... 10 2.1  SCOPE ........................................................................................................... 10 2.2  USUAL SERVICE CONDITIONS .................................................................... 10 2.3  RATINGS ........................................................................................................ 10 2.4  CORE ............................................................................................................. 12 2.5  WINDINGS ...................................................................................................... 12 2.6  BUSHINGS ..................................................................................................... 13 2.7  CURRENT TRANSFORMERS ....................................................................... 14 2.8  TANK .............................................................................................................. 14 2.9  OIL PRESERVATION SYSTEM ..................................................................... 16 2.10  RADIATORS ................................................................................................... 17 2.11  ACCESSORIES .............................................................................................. 17 2.12  DE-ENERGIZED TAP CHANGER (DETC) ..................................................... 20 2.13  LOAD TAP CHANGER AND CONTROLS (LTC) ............................................ 21 2.14  WIRING AND CABINETS ............................................................................... 22 2.15  TRANSFORMER OIL ..................................................................................... 24 

3.0  TESTING ............................................................................................................ 25 3.1  SHORT CIRCUIT CAPABILITY ...................................................................... 25 3.2  FACTORY TESTS .......................................................................................... 25 3.3  FIELD TESTS ................................................................................................. 27 

4.0  SPECIAL SHIPPING INSTRUCTIONS .............................................................. 27 4.1  PREPARATION FOR SHIPMENT .................................................................. 27 4.2  IMPACT RECORDERS .................................................................................. 28 4.3  NOTIFICATION ............................................................................................... 28 

APPENDIX A ................................................................................................................ 29 APPENDIX B ................................................................................................................ 30  SECTION 013524.45 – SAFETY REQUIREMENTS

Page 2: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 2 of 30

1.0 GENERAL REQUIREMENTS

These Contract documents define the requirements for furnishing, delivering, placement on existing pad, field assembly, oil filling, and testing of two (2) three-phase, 60 Hz., 28 MVA, 115/12.47 kV oil immersed outdoor substation power transformers in September 2019 as specified. This Contract reserves the right to purchase up to five (5) additional transformers during the Contract Term and is subject to the same Contract requirements. The Contractor shall perform in strict accordance with the detailed requirements all work necessary to design, manufacture, test, transport, deliver and commission the transformer as described in these Contract Documents. Commissioning shall include the final assembly, oil filling, and field testing of the transformer to ensure performance guarantees and Warranty requirements are achieved when placed into service. The Contractor shall provide, at no additional cost to the District, any cranes or other devices to offload equipment as well as all rigging and jacks, rollers, etc. required for offloading and assembly.

1.1 DELIVERY

1.1.1 Location

The first two transformers furnished under this Contract shall be delivered FOB transformer pad to the project site located at 3475 Highway 97A, Wenatchee, WA 98801.

1.1.2 Delivery Date

The first two (2) power transformers shall be delivered between September 9 - September 30, 2019.

Delivery before the earliest date listed above will not be accepted without prior approval by the Engineer. Following delivery to the pad, Contractor shall be responsible for the storage and maintenance of the transformers in suitable condition to prevent damage or contamination until field testing is completed, and accepted by the District.

Field assembly, oil filling, and testing shall be completed by the Contractor within twenty (20) business days following the latest date in the delivery date range shown above.

Page 3: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 3 of 30

1.2 COORDINATION AND MEETINGS

1.2.1 Contractor’s Address

The Contractor shall inform the Engineer in writing of the address for sending official correspondence and the contact information for the Contractor’s project manager.

1.2.2 Meetings

Appropriate members of the Contractor’s team shall attend a preproduction review meeting with the Engineer and other District representatives. This meeting may be held via conference call. The Contractor shall present and discuss Contract Specifications, manufacturing and testing schedule, quality control, and other relevant items. The preproduction review meeting shall be arranged at a mutually agreeable date and time prior to submittal of approval drawings.

Periodic progress meetings may be scheduled over the course of the work, as mutually agreed by District and Contractor. The Contractor shall participate in planned and unplanned meetings with the District and Engineer to properly coordinate the work.

1.2.3 Progress Updates

The Contractor shall prepare notes of each meeting and submit them to the Engineer for review and comment within five days of the meeting. The Contractor shall provide progress and action item updates to the Engineer, at a minimum on a monthly basis.

1.2.4 Site Working Hours

During delivery and field testing at the substation site, Contractor shall observe normal District work hours and holidays, unless coordination outside these hours is prearranged and Approved by the District. Normal working hours are 7:00 a.m. to 3:30 p.m. Monday through Friday.

1.2.5 Contractor’s Project Manager

The Contractor’s project manager shall be fluent in the English language, both oral and written. The Contractor’s project manager shall provide one single point of contact within the Contractor’s organization for all interfaces and communication with the District and others relevant to the successful design, manufacture, testing, delivery, and commissioning of the transformers.

Page 4: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 4 of 30

1.3 DRAWINGS, DATA, AND SUBMITTALS

1.3.1 Project Schedule

The Contractor shall submit a detailed Project schedule, including field assembly and testing, for review and approval by the District.

1.3.2 Required Drawings

At a minimum, the Contractor shall supply:

1.3.2.1 Transformer outline drawing with weights and component bill of material indicating quantity, description, and part number.

1.3.2.2 Transformer nameplate drawing.

1.3.2.3 Control cabinet layout drawing.

1.3.2.4 Schematic diagram with device legend including manufacturer, quantity, manufacturer part number and description.

1.3.2.5 LTC schematic.

1.3.2.6 Wiring diagrams.

1.3.2.7 Bushing outlines and data.

1.3.2.8 Lightning arrester outlines and data.

1.3.3 Approval Drawings

Approval outline drawings shall be supplied to the Engineer not later than 8 months prior to the required delivery date of the transformers.

1.3.4 Construction Drawings

Prior to fabrication, three (3) copies of certified for construction drawings for each transformer shall be submitted to the Engineer.

1.3.5 As-Built Drawings

Upon completion of factory testing and inspection procedures, the Contractor shall submit to the Engineer a complete set of As-Built Drawings.

Provide three (3) sets each of full size plotted reproducible drawings “D size” measuring approximately 34-inch x 22-inch, and reduced photocopies “A size” approximately 11-inch x 17-inch. Digital files in AutoCAD 2010 (*.dwg) format shall also be provided on CD.

Page 5: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 5 of 30

1.3.6 Test Reports

The Contractor shall furnish three (3) certified copies of test reports including all tests performed on the transformers, and certification verifying the oil used in filling each transformer has non-detectable (less than 1 ppm) levels of PCB’s.

1.3.7 Manuals

1.3.7.1 General

Contractor shall furnish three (3) bound and indexed copies of handling, storage, installation, operation, and maintenance instructions for all new equipment furnished under this contract. Contractor shall be responsible for ensuring complete submittals on individual interrelated equipment components provided by Subcontractors, suppliers, and manufacturers. All information included in the manuals shall be specific for the transformer. Use of standard bulletins or instructions shall be permitted, provided the Contractor identifies the sections or portions that pertain to the specific transformer.

1.3.7.2 Format

Indexes shall be provided for each manual, including dividers and tabs to separate sections of each manual. Vinyl binder sheets for CD media and full size drawings shall be provided as appropriate.

1.3.7.3 Organization

Each volume shall be identified with typed or printed cover and title page including the following:

PUBLIC UTILITY DISTRICT No. 1 OF CHELAN COUNTY 28MVA, 115/12.47 KV SUBSTATION POWER TRANSFORMERS (INSTALLATION/OPERATIONS AND MAINTENANCE) MANUAL

VOLUME x OF y CONTRACT No. 18-67

[DATE] [NAME AND ADDRESS OF EQUIPMENT SUPPLIER]

The table of contents shall contain all volumes, chapters, appendixes, and a master index. Where more than one volume is required, each subsequent volume shall contain an index for the contents within that respective volume. Chapters, appendixes, and indexes shall not be divided between volumes.

Page 6: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 6 of 30

1.3.7.4 Drawings

Final manuals shall contain As-Built drawings, either full-size folded and placed in appropriate vinyl binder sheets, or reduced to 11-inch x 17-inch size, or both. Drawing sizes shall be selected to ensure information shown thereon is legible and readable without magnification.

1.3.7.5 Electronic Copies

Final manuals, once approved, shall also be provided electronically on CD.

1.3.7.6 Submittals

A Manual outline and/or preliminary Manual shall be submitted to the Engineer for Approval prior to preparation of the final Manuals.

One (1) final Manual shall ship with the transformer.

The remaining two (2) final Manuals shall be addressed and shipped, separately, as follows:

Public Utility District No. 1 of Chelan County Attn: Tom Kelly P.O. Box 1231 Wenatchee, WA 98807

1.4 STANDARDS

The transformer shall be designed, fabricated, and tested in accordance with this specification and the latest applicable industry standards and codes. If a conflict between standards, or a standard and this Contract Document occurs, then the one which has the most restrictive requirements shall govern, as deemed by the District, unless otherwise stated in writing by the District. Notwithstanding the provision of any standard or code applicable to the Work, Contractor shall be exclusively responsible for proper design, manufacture, inspection, and testing of the Work to assure that it meets all requirements of the Contract. The transformer supplied shall conform to the latest adopted and recommended Standards of the IEEE, ANSI, NEMA and ASTM, including but not limited to the following:

Page 7: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 7 of 30

Standard Number Title NEMA TR-1 Transformers, Regulators and Reactors NFPA 70 National Electrical Code ANSI C2 National Electrical Safety Code

ANSI C57.12.00 IEEE Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers

ANSI C57.12.10

American National Standard for Transformers – 230 kV and Below 833/958 through 8333/10417 kVA, Single-Phase, and 750/862 through 60,000/80,000/100,000 kVA, Three Phase without Load Tap Changing; and 3750/4687 through 60,000/80,000/100,000 kVA with Load Tap Changing – Safety Requirements

ANSI C57.12.90 IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers

ANSI C57.13 IEEE Standard Requirements for Instrument Transformers ANSI C57.13.1 IEEE Guide for Field Testing of Relaying Current Transformers

ANSI C57.19.00 IEEE Standard General Requirements and Test Procedures for Outdoor Power Apparatus Bushings

ANSI C57.19.01 IEEE Standard Performance Characteristics and Dimensions for Outdoor Apparatus Bushings

ANSI C57.19.100 IEEE Guide for Application of Power Apparatus Bushings ANSI C57.91 IEEE Guide for Loading Mineral-Oil-Immersed Transformers ANSI C57.93 IEEE Guide for Installation of Liquid-Immersed Power Transformers

ANSI C57.100 IEEE Standard Test Procedures for Thermal Evaluation of Oil-Immersed Distribution Transformers

ANSI C57.106 IEEE Guide for Acceptance and Maintenance of Insulating Oil in Equipment ANSI C57.131 IEEE Standard Requirements for Load Tap Changers

ANSI C57.149 IEEE Guide for the Application and Interpretation of Frequency Response Analysis for Oil-Immersed Transformers

ANSI C62.11 IEEE Standard for Metal-Oxide Surge Arresters for AC Power Circuits

ANSI C62.22 IEEE Guide for the Application of Metal-Oxide Surge Arresters for Alternating Current Systems

ANSI Z535.1 American National Standard for Safety Color Code ANSI Z535.2 American National Standard for Environmental and Facility Safety Signs ANSI Z535.3 American National Standard Criteria for Safety Symbols ANSI Z535.4 American National Standard for Product Safety Signs and Labels AWS D1.1 Structural Welding Code AWS D1.2/D1.2M Structural Welding Code

ASTM A123 Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

ASTM A153 Specification for Zinc Coating (Hot-Dip) on Iron and Hardware ASTM D3487 Mineral Insulating Oil Used in Electrical Apparatus IEEE 693 Recommended Practices for Seismic Design of Substations SSPC SP-6 Commercial Blast Cleaning SSPC SP-8 Pickling

Page 8: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 8 of 30

1.5 MATERIALS

1.5.1 Material Condition

All materials incorporated in the equipment furnished shall be of new and of first class commercial quality, free from defects and imperfections.

1.5.2 Undesignated Materials

Materials not specifically designated herein shall be suitable for the purpose intended and shall comply with the latest Specifications of the American Society for Testing and Materials (ASTM), or other Approved standard.

1.6 UNITS OF MEASURE

Drawings, test data, manuals, and written instructions shall be in the English language. All dimensions shall be in U.S. customary units (feet, inches, pounds, gallons, etc.). Instrumentation for measuring pressure shall be calibrated in pounds per square inch (psi) and have ½ in. NPT thread. Dual units of measure showing U.S. Customary units and SI System units are acceptable provided the U.S. Customary units are prominently displayed. Pressure gauges and gauge attachments shall comply with ASME B40.100. Instrumentation for measuring temperature shall be in degrees Celsius. All other materials, parts, etc. used in the Work, except as noted, shall be generally in the same system of units, either U.S. Customary or International Standard.

1.7 AUXILIARY EQUIPMENT

1.7.1 Auxiliary Relays

Auxiliary relays shall meet the requirements of ANSI C37.90, with contacts suitable for the application and current and voltage ratings applied in the control circuits.

Contacts intended for use in the control circuits shall be electrically independent, ungrounded, dry contacts, field changeable from normally-open to normally-closed.

1.7.2 Instrumentation

Instrumentation shall be provided for complete monitoring of all equipment. Instruments of the same type shall all be of the same manufacturer and series

Page 9: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 9 of 30

except as Approved by the Engineer. All instrumentation shall be of a grade suitable for use in a utility substation application.

1.7.3 Transducers

Unless otherwise specified, transducers shall have a 0-1 mAdc output. Other transducer outputs will be considered at the sole discretion of the Engineer.

1.7.4 Process Switches

Process switches (e.g. temperature switch, level switch, pressure switch, etc.) shall have a minimum of two “form a” and two “form b”, or two “form c” switches. Contacts shall be rated for use at 48 Vdc. Switch accuracy shall be at least 0.25% of setpoint.

1.7.5 Indicating Lamps

Indicating lamps shall be GE series ET-16 with LED lamps, or Approved Equal.

1.7.6 Switchboard Wire

Switchboard wire used for terminal-to-terminal connections within termination enclosures shall be type SIS rated 600 V.

1.8 EQUIPMENT IDENTIFICATION

Each device, instrument, panel, cable, wire and enclosure shall be uniquely identified. Contractor shall submit a detailed list of all equipment identification labels to the Engineer for Approval. Identification tags or labels shall be permanently affixed. Nameplates shall be securely fastened with self-tapping screws. Each junction box and enclosure shall be provided with a nameplate as appropriate.

1.9 WIRE AND CABLE IDENTIFICATION

Identification markers shall be provided for the ends of each cable and shall be provided at the ends of each conductor.

1.10 CONDUIT AND PIPING

All conduit and piping shall utilize standard U.S. trade sizes and fittings, and shall be suitable for their intended use.

Page 10: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 10 of 30

1.10.1 Conduit Strength

All conduits shall be rigidly supported, and where exposed to possible use for climbing, adequate to support at least 250 Lbs.

1.11 METAL FASTENERS

Bolts, studs, nuts and screws shall conform to ASME standard thread forms and dimensions and be of high quality material suitable for their intended use. Any exposed unpainted metal parts shall be fabricated of corrosion resisting metal. All external fasteners shall be stainless steel or galvanized according to ASTM standards. Zinc plated fasteners are prohibited.

2.0 DETAILED TECHNICAL REQUIREMENTS

2.1 SCOPE

This Specification is intended to define requirements for the design, manufacture, delivery, and testing of three-phase, 60 Hz., 28 MVA, 115/12.47 kV oil immersed outdoor substation power transformers.

2.2 USUAL SERVICE CONDITIONS

The usual service conditions listed in ANSI C57.12.00 shall apply. All components shall be suitable for wind loadings of 100 MPH in any direction, and shall be suitable for one (1) inch radial ice. All material supplied under this contract shall meet seismic requirements in accordance with IEEE 693.

2.3 RATINGS

2.3.1 MVA Ratings:

16.8/22.4/28 MVA at 65⁰ C average winding temperature rise.

2.3.2 Voltage Ratings and Connection:

Primary Voltage: 115,000 volts, Delta connected Secondary Voltage: 12,470 volts, Wye connected, neutral solidly grounded

and fully insulated. The secondary windings shall lag the primary windings electrically by 30⁰.

Page 11: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 11 of 30

2.3.3 Temperature Rise

The average winding temperature rise above ambient shall not exceed 65⁰C. The top oil liquid temperature rise shall not exceed 65⁰ C. The winding hottest spot temperature shall not exceed 80⁰ C.

2.3.4 Cooling Class

The transformer cooling shall be ONAN/ONAF/ONAF.

2.3.5 Impedance

The impedance of the transformer at the self-cooled rating shall be 9.0%, with a tolerance of +/- 1% of this value. It is desired that the transformer impedance be between 8.9% and 9.1%. Note that this is more restrictive than the tolerance specified in ANSI C57.12.00.

2.3.6 De-Energized Tap Changer (DETC)

A DETC with two (2) 2.5% taps above and two (2) 2.5% taps below the nominal 115,000 volt tap shall be supplied on the high voltage side.

2.3.7 Load Tap Changer (LTC)

A vacuum type LTC with a neutral position and with approximately ± 10-percent regulation in 16-steps above and 16-steps below rated voltage shall be supplied on the low voltage side.

2.3.8 Capability and Loading

The transformer shall be capable of operating above rated voltage or below rated frequency, and of loading at other than rated conditions, in accordance with the latest applicable ANSI standards. All current carrying components shall be suitable for and shall not limit these loading capabilities.

2.3.9 Control Voltage Ratings

Control equipment shall be designed for operation at the following voltages:

Nominal 48 Vdc ungrounded, with an operating range of ±15%.

Single-phase 120/240 Vac, 60 Hz grounded, with an operating range of ±10%.

Page 12: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 12 of 30

2.4 CORE

The core shall be constructed of the highest quality, non-aging, cold-rolled, grain-oriented, stress-free, thin-silicon-steel laminations with high permeability and low hysteresis loss. The steel shall be properly annealed and shall have smooth surfaces at the edges. The insulated surfaces of each sheet shall be impervious to hot transformer oil. The core shall be rigidly clamped and blocked to prevent deteriorating vibrations, interference with oil circulation, objectionable noise conditions, short circuit and shipment distortions.

2.4.1 Core Ground

A means shall be provided for isolating the core from ground for testing. This device shall not utilize any loose or non-captive hardware that could be dropped into tank, and core ground leads shall be made accessible by locating it within twenty-four (24) inches of an inspection manhole location. Access shall also be possible without lowering the insulating oil level. Protected bushings shall be used to allow external access to each core ground connection. The items that provide external core ground bushing protection shall have a bonded, removable, gasketed top cover. Each core ground bushing shall be clearly labeled with UV resistant labels and printing.

2.4.2 Resistance

The resistance between the core and the tank shall exceed 1000 megohms with the unit oil filled and the core ground open.

2.4.3 Sound Level

Each transformer’s sound level shall not exceed NEMA Standard, TR1-0.05.

2.5 WINDINGS

2.5.1 Winding Material

The winding material shall be copper.

2.5.2 Winding Insulation

The insulation of each winding shall be designed to meet the minimum withstand requirements of the latest revision of ANSI C57.12.00.

Page 13: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 13 of 30

DESCRIPTION Terminals

H1H2H3 X1X2X3 Xo BIL (kV) 450 110 110 Chopped Wave Impulse (kV) 495 120 120 Switching Impulse (kV) 375 --- --- Induced Voltage Test, 1-hour (kV, L-G) 105 --- --- 7200 Cycle Induced Potential (kV, L-G) 120 --- --- One Minute Applied Potential (kV) 185 34 34

2.6 BUSHINGS

2.6.1 Standard

Bushing shall be in accordance with ANSI Standards C57.19.00, C57.19.01, and C57.19.100.

2.6.2 Ratings and Location

Bushings shall meet or exceed the following requirements:

DESCRIPTION BUSHINGS

H1H2H3 X1X2X3 Xo Insulation Class (kV) 115 25 25 BIL (kV Crest) 550 150 150 Continuous Current (Amps)

800 2,000 2,000

Minimum Creep (Inches)

79 17 17

Connection Type Draw Lead Bottom Connected Bottom

Connected Location Segment 3 Segment 1 Segment 1

2.6.3 Bushing Height – 25kV Bushing

The requirement for 25kV class bushings is to obtain additional distance between flange and live parts. In some cases 15kV class bushings meet these requirements, and will be approved at the discretion of the Engineer.

2.6.4 Material

Bushings shall be porcelain with a color that meets the requirements of ANSI No. 70, Light Gray.

2.6.5 Clearances

Bushing clearances shall be in accordance with ANSI C57.12.00 and the following table:

Page 14: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 14 of 30

Bushing Voltage Rating (kV)

Minimum Centerline Spacing Between Tops of Bushings

(Inches)

Minimum Clearance Between Top Shed of Insulator of Bushings of

Different Phases (Inches) 25 28 12

115 60 36

2.6.6 Terminals

Each bushing shall be supplied with tin plated, 4 hole NEMA terminals.

2.6.7 Bushing Turrets

Each bushing shall be mounted on a turret to elevate the bushing flange above the lid of the transformer.

2.7 CURRENT TRANSFORMERS

Multi ratio bushing current transformers shall be installed and furnished as follows:

DESCRIPTION BUSHINGS

H1H2H3 X1X2X3 Xo Required number of current transformers per bushing

2 2 1

Full winding ratio 600:5 2000:5 1200:5Minimum relaying accuracy on the full winding

C800 C400 C400

2.7.1 Rating Factors

All relay current transformers shall have a minimum rating factor of 1.5.

2.8 TANK

The transformer tank and all apparatus shall be in accordance with ANSI C57.12.00, C57.19.00 and ANSI C57.12.10

2.8.1 Finish

Surfaces shall be properly prepared, cleaned, primed and painted with a total minimum dry film thickness of 5 mils, or as Approved by Engineer.

2.8.2 Exterior Paint Color

The tank exterior finish shall be ANSI No. 70, Light Gray.

Page 15: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 15 of 30

2.8.3 Interior Paint Color

The tank interior finish shall be painted with a bright white finish that is suitable for continuous immersion in transformer oil.

2.8.4 Touch-Up Paint

Suitable labeled containers of matching paint shall be furnished to touch up after installation.

2.8.5 Tank Lid and Covers

The top lid of the main tank shall be made of suitable steel plate, having welded attachment to the main tank, with one or more manholes. The tank lid and manhole covers shall be crowned or sloped to prevent standing water. The entire walkable surface of the top lid, top of the LTC tank, and manhole covers shall include a non-skid surface suitable for safe personnel movement in wet conditions. All manhole covers on the transformer lid shall include handles for lifting, and shall be mounted on a throat that is a minimum of two inches (2”) in height, to minimize the possibility of loose parts being knocked accidentally into the opening.

2.8.6 Base

The base shall be sufficiently strong and properly constructed to permit rolling the transformer in forward, backward, and sideways directions.

2.8.7 Anchorage

The transformer will be anchored with welds to embedded steel in the foundation pad. Size, location, and type of welds required for anchoring the transformer shall be shown on manufacturer’s drawings. The installation of welds to anchor the transformer is not within the scope of this contract.

2.8.8 Lifting and Jacking

Lifting and jacking lugs shall be provided for lifting and jacking of the completely assembled transformer, including bushings, arresters, equipment brackets, oil and radiators. Provisions shall be made for pulling the transformer parallel to either the length or width centerlines.

Page 16: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 16 of 30

2.8.9 Lifting Eyes for Cover and Core/Coil

Separate lifting eyes for lifting the cover and for lifting the core and coil assembly from the tank shall be provided.

2.8.10 Vacuum Withstand

The main tank and all oil-filled compartments shall be suitable for filling under full vacuum.

2.8.11 Welding

All welding shall be in accordance with AWS D1.1

2.8.12 Ground Pads

NEMA 2-hole ground pads shall be located within 12 inches of the base on all four corners of the tank.

2.8.13 Drain and Fill Valves

Upper, lower, and cover fill and drain valves shall include pipe plugs on open ends. The cover valve shall have a splash baffle installed below the valve. Valve sizes shall be 2-inches. The upper and cover 2-inch valves shall include 1-1/2 inch removable pipe thread reducer fittings with plug at the open end.

2.8.14 Fall Restraints

An anchor plate for fall restraint shall be installed near the center of the tank cover or as approved by Engineer. Anchor plates for standard District fall restraints are available from:

UCL Safety Systems Phone: (204) 694-7432 www.UCLsafetysystems.com Part number 17412, bare steel uni-anchor plate with tie off anchor

2.9 OIL PRESERVATION SYSTEM

The transformer shall be furnished complete with a positive pressure oil preservation system that is of the "Inert Gas Pressure System" type, Waukesha, ABB, Or Approved Equal.

2.9.1 Enclosure

The equipment shall be enclosed in a weather-proof and dust-resistant housing that meets the requirements of NEMA 3R.

Page 17: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 17 of 30

2.9.2 Mounting Height

The floor of the cylinder enclosure should be no more than three inches (3”) above the transformer base.

2.9.3 Access

All valves, knobs, and disconnectable fittings shall be readily accessible from the front of the enclosure.

2.9.4 Gas Cylinder

One (1) cylinder of gas shall be provided. The cylinder shall remain the property of the District and shall be so marked by the Contractor. The cylinder shall be per District Specifications.

2.9.1 Alarm Contacts

Circuit closing alarm contacts suitable for operation on a 48 volt DC ungrounded system shall be provided to indicate gas pressure above and below normal, and cylinder low pressure. Alarm contacts shall be wired to a terminal strip in the transformer control cabinet.

2.10 RADIATORS

Each radiator panel shall be removable, with suitable valves between each radiator panel and the transformer tank on both the oil inlet and outlet. Each valve shall have a lockable handle with provision for locking in the open position. The outboard side of each radiator panel shall be furnished with ball valves and removable plugs for the bottom drain valves, and with removable plugs on the top, of each panel for filling and draining.

2.11 ACCESSORIES

2.11.1 Arresters

Station class metal-oxide arresters shall be provided on both the high voltage and low voltage sides, mounted on suitable brackets attached to the transformer. The arresters shall be rated as follows:

Winding MCOV Quantity

HV 76 kV 3 LV 8.4 kV 3

Page 18: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 18 of 30

2.11.2 Neutral/Ground Bus Bar

Copper bus bar shall be installed from the cover to the transformer base at two corners to facilitate connection of arrestors and neutral to the station ground grid.

2.11.3 Pressure Relief Devices

Pressure relief devices shall be installed on the main tank cover, on the top of the LTC compartment, and on the top of each separate oil-filled compartment. Each pressure relief device shall be equipped with an operation indicator that is visible from the ground, and shall also include alarm contacts suitable for operation on a 48 volt DC ungrounded system. The alarm contacts shall be wired to terminal blocks in the control cabinet. Piping shall be installed to direct oil toward the base of the transformer and away from control cabinets and other devices. Piping shall be screened at the open end.

2.11.4 Sudden Pressure Relay

A sudden pressure relay in the air space or the oil space shall be provided on the main tank, LTC tank, and each separate oil-filled compartment, Qualitrol Series 900 Or Approved Equal. A seal in relay, Qualitrol 909-200-01 Or Approved Equal, shall be provided in the control cabinet for each sudden pressure relay, and shall provide separate alarm and trip contacts for operation on a 48 volt DC ungrounded system. All trip and alarm contacts shall be wired to terminal blocks in the control cabinet.

Sudden pressure relays installed in the oil space shall have a valve for maintenance purposes.

2.11.5 Winding Temperature Gauge

A winding temperature gauge with maximum temperature indication shall be supplied. It shall be located adjacent to the top oil temperature gauge, and at a height allowing viewing and resetting the maximum temperature drag hand from the ground. An analog 0-1 mA output shall be provided for remote indication, and wired to terminal blocks in the control cabinet for District use.

Page 19: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 19 of 30

In addition to any contacts for activating cooling stages, two (2) adjustable alarm contacts suitable for operation on a 48 volt DC ungrounded system shall be provided. The alarm contacts shall be wired to terminal blocks in the control cabinet.

2.11.6 Top Oil Temperature Gauge

A top oil temperature gauge with maximum temperature indication shall be supplied. It shall be located adjacent to the winding temperature gauge, and at a height allowing viewing and resetting the maximum temperature drag hand from the ground. An analog 0-1 mA output shall be provided for remote indication, and wired to terminal blocks in the control cabinet for District use.

A minimum of two (2) adjustable alarm contacts suitable for operation on a 48 volt DC ungrounded system shall be provided. The alarm contacts shall be wired to terminal blocks in the control cabinet.

2.11.7 Thermal Wells

All thermal elements shall be housed in wells, located in the tank and LTC wall, to permit inspection and replacement without removing oil or gas from the transformer. Each thermal well shall be located below the minimum oil level.

2.11.7.1 Quantity

A minimum of two (2) wells shall be provided on the main tank, for hottest spot winding temperature, and liquid temperature.

One (1) well shall be provided in the LTC, for future use.

2.11.8 Oil Level Monitoring

Dial type oil level gauges shall be mounted on each oil-filled compartment, to include main tank(s) and LTC compartment.

Alarm contacts suitable for operation on a 48 volt DC ungrounded system shall be provided and wired to terminal blocks in the control cabinet.

The gauge face shall be of a size and orientation that is easily viewable from ground level.

Page 20: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 20 of 30

2.11.9 Transformer Nameplate

A nameplate, diagrammatic type, conforming to nameplate requirements of ANSI C57.12.00 shall be provided.

2.11.10 Fans

All fans shall be supplied complete with automatic control equipment, conduit, wiring and other equipment necessary for operation.

Fan motors shall be 60 Hz., and rated for 240 volt AC single phase power from the station service.

Alarm contacts suitable for operation on a 48 volt DC ungrounded system shall be provided to indicate a loss of AC power. Contacts shall be wired to terminal blocks in the control cabinet.

2.11.10.1 Fan Wiring and Controls

All fan wiring and conduit runs shall conform to NEC requirements. Cooling equipment controls, including contactors and switch controls, shall provide Stage 1, Stage 2, Off, and Manual Control of fans. A "Manual-Off-Automatic" mode selector switch shall be provided in the control cabinet, for each cooling group, so that each group can be started for test, or run continuously. A selector switch shall be provided in the control cabinet to select one or the other group of fans to be the first to come “ON”.

2.11.10.2 External Relay Interaction

Terminals shall be provided, in the control circuit, for connecting contacts to trip the cooling equipment automatically upon operation of the external protective relays.

2.12 DE-ENERGIZED TAP CHANGER (DETC)

The transformer high voltage winding shall have a manually operated, DETC. The transformer shall be equipped with standard full capacity taps, two (2) 2.5% taps above and two (2) 2.5% taps below nominal voltage. The tap changer shall be designed for convenient operation by one person standing on the same level as the transformer base, and shall include an operating hand wheel, or handle, indicating pointer and dial, and means for locking the tap changer in any desired position. The locking device shall be arranged to prevent locking the tap changer between positions.

Page 21: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 21 of 30

2.13 LOAD TAP CHANGER AND CONTROLS (LTC)

The load tap changer shall be a vacuum type on-load tap changer with a neutral position and with approximately ± 10-percent regulation in 16-steps above and 16-steps below rated voltage load tap. The LTC winding shall regulate the low voltage winding, and shall be designed and constructed in accordance with ANSI C57.131. All controls and alarms shall be wired out to their respective terminal blocks, located in the transformer main control cabinet.

2.13.1 Drive Motor Output Shaft Extension

The LTC drive motor compartment must be at least eighteen (18) inches below the LTC compartment. An output shaft extension may be needed to meet this requirement.

2.13.2 Supply Voltage

The LTC motor shall be rated for proper and continuous operation at 240 volts AC single phase, 60 Hz.

2.13.3 Limit Switches

The LTC mechanism shall include mechanically operated electric limit switches to prevent over-travel beyond maximum raise and lower positions. Separate switches shall be provided and wired to the control cabinet for maximum raise and lower limit alarms and shall be suitable for a 48 volt DC ungrounded system.

2.13.4 LTC Automatic Control

A Reinhausen TAPCON 250 Or Approved Equal tapchanger control shall be installed in the transformer main control cabinet. Tap positon input and paralleling feature shall be included. Communications protocol shall be DNP3.0 with RS232, RS485, and RJ45 for Ethernet and Fiberoptics. Space around LTC controller shall be left open to allow for the bending of a fiber optics cable, 8-inch bending radius.

Page 22: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 22 of 30

2.13.5 Back-Up Control

A LTC control back-up relay, Beckwith Model M0329 Or Approved Equal, shall be installed to prevent a defective LTC control from running past high or low limit.

2.13.6 Potential Source

Single phase potential for the automatic tapchanger control shall be obtained from the District's potential transformer.

2.13.7 Voltmeter

An analog voltmeter, 1 percent accuracy, 0-150 volt scale (for operation at a nominal 120 volts AC), type AB-40 Or Approved Equal shall be installed in the control cabinet near LTC controls to indicate potential serving the automatic control.

2.13.8 Operation Counter

A mechanical operation counter shall be provided in order to register the accumulated number of tap changes performed.

2.14 WIRING AND CABINETS

2.14.1 General Wiring

Wiring and components shall be arranged so that instruments or devices may be removed and/or serviced without disturbing the wiring. No wires shall be routed across the face or rear of an instrument, junction box, or other device in a manner which will prevent the opening of covers or obstruct access to leads, terminals, devices, or instruments. All internal wiring connections shall be accessible without removing any component.

2.14.2 Field Wiring Space

Contractor's wiring shall be clear of assigned field wiring space. One side of the terminal blocks shall be reserved for incoming field wiring.

2.14.3 Minimum Wire Sizes

General control wiring shall be stranded copper and shall not be smaller than No. 14 AWG with the following exceptions:

Page 23: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 23 of 30

CT Leads: The secondary leads of current transformers shall not be smaller than No. 10 AWG.

240 Vac Supply: Main 240 Vac wiring shall be no smaller than #8 AWG.

Convenience Wiring: Wiring to convenience outlets or lights shall be no smaller than #12 AWG.

2.14.4 Terminals

All internal control wiring terminations shall be made with insulated, brazed barrel, ring tongue type, compression lugs.

2.14.5 Use of Terminal Blocks

All external wiring leaving the control cabinet shall leave from terminal blocks (not from other devices in the enclosure). Spare contacts on relays and similar devices shall be wired to accessible terminal blocks in control cabinet for future connections.

2.14.6 Splices

No splices are allowed between the terminals of any devices, or between any terminal blocks, or between any devices and any terminal blocks (conductors shall be continuous from point to point).

2.14.7 Identification

Permanent and durable identification shall be provided on each end of each conductor (marking to indicate the opposite-end destination of conductor).

2.14.8 Cabinet

The control/terminal cabinet shall be of a weather-proof and dust-proof construction that meets the requirements of a NEMA class 3RX enclosure. The bottom access cover shall be clear for the District’s conduit entrance.

2.14.9 Cabinet Doors

Hinged doors shall be equipped with latch, handle, padlocking provisions, inside pocket for storage of instruction books, and drop type wind gust latch, which holds the door securely when open. Cabinets in excess of thirty-six (36) inches wide shall be provided with multiple doors such that no single door exceeds this width.

Page 24: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 24 of 30

2.14.10 Cabinet Ground Bus

A copper bar ground bus shall be installed inside each cabinet. The ground bus shall be accessible with provision for bonding with the transformer and the station ground grid.

2.14.11 Location

The control cabinet shall be located so that the top is no more than eighty-four (84) inches above the transformer base. The arrangement and location of the cabinet shall allow free and safe access for a worker standing at ground level.

2.14.12 Accessories

The following shall be provided in the control cabinet: Heater strips with protective guards and thermostatic control. Convenience outlet, 120 volt AC, three wire duplex, 20 amp, GFCI

type, located for clear access away from exposed energized terminals. Convenience light(s), 120 volt AC with door switch(es).

2.14.13 Terminal Blocks

Terminal blocks shall be rated not less than 600 volts and shall accommodate up to No. 8 AWG wire. Marking strips shall be provided for all terminal designations. Not more than two wires shall be connected to one terminal.

Each termination enclosure shall have a spare 12 position terminal block or similar spare terminal block capacity.

2.14.14 Shorting Blocks

Terminals for current transformer wiring shall be equipped with devices for short circuiting the secondary.

2.15 TRANSFORMER OIL

Transformer oil shall be furnished and delivered to the delivery site, except oil which may be shipped in the transformer. Oil shall be new and unused napthenic ASTM Type II mineral oil, 0.3% DBPC inhibited, meeting the characteristics prescribed in ANSI standards IEEE C57.106/D7. The oil shall be tested and certified “Non-PCB (< 1 ppm PCB)”, which shall be stated on the transformer nameplate and test report. “ND” (non detectable) designation is not acceptable; “less than 1 ppm PCB” must be clearly stated.

Page 25: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 25 of 30

2.15.1 Test Reports

The Contractor’s certified oil test report shall be supplied to the District prior to delivery of the oil.

2.15.2 Test Oil

A certified, EPA approved test report shall state the amount of polychlorinated biphenyls (PCB), in parts per million, of the oil in which the transformer was tested.

3.0 TESTING

3.1 SHORT CIRCUIT CAPABILITY

The transformer furnished under this specification shall meet the short circuit requirements as specified in ANSI C57.12.00 and C57.12.90. A certified short circuit test demonstrating that a transformer of essentially the same MVA size, voltage, and design as proposed has successfully passed the short circuit test shall be supplied on request to confirm requirements of this section.

3.2 FACTORY TESTS

3.2.1 Witness

The District reserves the right to have representatives present and observe all tests, and any assembly or assembly steps. The Contractor shall give the Engineer a minimum of 10 business days advance written notice of factory tests.

The Contractor shall have engineering, manufacturing, quality control, and operational factory personnel available who speak technical and conversational English without the need for an interpreter.

3.2.2 Required Tests

All routine tests specified in ANSI C57.12.00 for Class II transformers shall be completed at the factory. Routine tests shall include:

Resistance of all windings Winding insulation resistance Core insulation resistance Turns ratio Polarity and phasing Insulation power factor

Page 26: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 26 of 30

No-load, load, and auxiliary losses Excitation current Impedance voltage Lightning impulse Radio Influence Voltage (RIV) and/or Apparent Charge Dissolved Gas Analysis (DGA) Bushing tests Vacuum and leak tests

The following ANSI tests shall also be included:

Zero Phase Sequence impedance voltage Temperature Rise Audible Sound SFRA

All manufacturer’s standard tests shall be completed and reported in addition to any other tests required.

3.2.3 District’s Bushings

All tests shall be made with the actual bushings that will be sent to the District with the transformer.

3.2.4 Oil Analysis

Oil samples shall be taken and analyzed for dissolved gasses both before and after testing.

3.2.5 Efficiency

The manufacturer shall perform and record the results of transformer efficiency tests at the following load levels: Full ¾ ½ ¼

3.2.6 Regulation Calculations

Documentation of the transformer’s regulation, in accordance with ANSI C57.12.00 and C57.12.90, shall be provided on the test reports.

Page 27: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 27 of 30

3.3 FIELD TESTS

The transformer shall be delivered FOB transformer pad, and dressed and field tested by the Contractor or Contractor’s service personnel.

3.3.1 Required Tests

All Contractor’s required tests shall be completed, including the following: Core insulation resistance Winding and winding insulation resistance Ratio/Polarity/Phase Excitation current Insulation power factor Bushing power factor Arrester test Oil test (screen and DGA, before filling) Oil test (DGA, after completion of field testing) Instruments/Accessories LTC SFRA

Certified tests of each of the items listed above are required in total before final payment will be considered.

4.0 SPECIAL SHIPPING INSTRUCTIONS

4.1 PREPARATION FOR SHIPMENT

After completion of factory assembly and testing, the transformer shall be disassembled into the minimum number of parts practicable. All equipment and materials shall be suitably crated, boxed, or otherwise prepared for shipment to prevent damage during handling and shipping. All openings, including oil piping and accessories, if dismantled for shipment, shall be capped or otherwise properly sealed to protect them from contamination or corrosion and to prevent the entrance of dirt or debris. Spare parts shall be packed and crated firmly enough to withstand long term storage indoors. The spare parts shall be packed separately from other articles, and shall clearly indicate that the contents are spare parts. Packaging shall include a list of contents and directions for storing.

Page 28: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 28 of 30

All valves shall be factory sealed, safety-wired, and protected from vandalism when transformer are shipped. If the transformer oil will be shipped separately from the transformer, the transformer tank shall be sealed hermetically and filled with dry air or nitrogen. Transformer shall be shipped with a slight positive pressure. Tank pressure, temperature, dew point (if applicable), and date of preparation shall be listed and certified, and a record of same shall be fastened inside the control cabinet.

4.2 IMPACT RECORDERS

The transformer shall be fitted with a minimum of two (2) three-axis impact recorders. Recorders must record the entire trip from the factory to the final destination, and must be sealed before shipment. Additional impact recorders shall be installed if inspection is required prior to delivery at the substation site. Impact recorders shall be opened and inspected upon delivery in the presence of a District representative. One recorder chart shall remain with the District for permanent record. Impact recordings shall indicate the date and time of removal and by whom, as well as the date, time, and name of the person inspecting the chart. If electronic impact recorders are used, they shall be waveform recorders, and the settings shall be reviewed with the Engineer prior to shipment of the transformer. If the recorder stops before reaching the destination, or if any data is not retrievable due to electronic failure, a thorough internal and external inspection of the transformer shall be made by the Contractor. A thorough internal and external inspection shall be made by the Contractor if the impact recorder(s) indicate an impact in excess of recommended limits has occurred.

4.3 NOTIFICATION

The Contractor shall notify the District at least three (3) business days in advance of shipment from the factory and in advance of arrival at the final destination.

Page 29: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 Page 29 of 30

APPENDIX A

Data to be submitted with bid:

1. Outline drawings with overall dimensions. 2. Guaranteed No-Load losses (kW). 3. Guaranteed Load losses (kW). 4. Guaranteed Auxiliary losses (kW). 5. Transformer rating data. 6. HV and LV bushing details. 7. Information and details of oil preservation system. 8. Information and details of core, winding, and tank construction and finish,

including proposed paint process. 9. Quantity and weight of oil. 10. Total weight of completely assembled and oil filled transformer. 11. Impedance at rated load. 12. Manufacturing facility location and ISO 9001 certification. 13. Repair facility location within the contiguous U.S. 14. Users list for 10 similar sized transformers manufactured at the stated

facility in the last five years. 15. Documentation that bidder has a minimum of five (5) years experience

with successful design, manufacture, delivery, service, and maintenance of the type of equipment specified from the plant specified.

Page 30: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Specifications

BID NO. 18-67 APPENDIX B – SUPPLEMENTAL PROPOSAL DATA SHEET Page 30 of 30

APPENDIX B

TRANSFORMER LOSSES EVALUATION FORM

Qty. Description Bid Price Each

(exclusive of Washington State

Sales Tax) EACH 115-12.47 kV, 16.8/22.4/28 MVA

Power Transformer with LTC Per Technical Specifications

A) $____________

CORE LOSS (kW) at nominal voltage B) X $4628.00 / kW

WINDING LOSS (kW) at nominal voltage C) X $1894.00 / kW

AUXILIARY EQUIP. LOSS (kW) D) X $1333.00 / kW The Evaluated Price will be the unit Bid Price, plus the results of B + C + D.

Page 31: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 1 of 21

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 013524.45 – SAFETY REQUIREMENTS

Table of Contents

PART 1 – GENERAL ..................................................................................................................... 2 

1.01  INTRODUCTION ................................................................................................................ 2 

1.02  SCOPE ............................................................................................................................... 2 

1.03  RELATED DOCUMENTS .................................................................................................. 2 

1.04  SUBMITTALS (Where Applicable) ..................................................................................... 2 

A.  Accident Prevention Program, if applicable. ...................................................................... 2 

B.  Site Specific Safety Plan (with Job Safety Analysis) .......................................................... 2 

C.  Safety Data Sheets (SDS) ................................................................................................. 2 

D.  Crane and Crane Operator Certifications, if applicable ...................................................... 2 

1.05  EXPECTATIONS AND RESPONSIBILITES ...................................................................... 2 

1.06  SITE SAFETY RESPONSIBILITIES AND ACCOUNTIBILITIES ........................................ 6 

1.07  CONTRACTOR WORKPLACE SAFETY REQUIREMENTS (General) ............................. 8 

1.08  CONTRACTOR WORKPLACE SAFETY REQUIREMENTS (Specific) ........................... 11 

1.10  OCCUPATIONAL HEALTH AND INDUSTRIAL HYGIENE Hazard Communication (HAZCOM) - WAC 296-802-200, WAC 296-901-140....................................................... 17 

1.11  PERSONAL PROTECTIVE EQUIPMENT (PPE) (WAC 296-24 Part L, WAC 296-45-25505, WAC 296-800-160): ............................................................................................. 18 

PART 2 – PRODUCT (NOT USED) ............................................................................................ 21 

PART 3 – EXECUTION (NOT USED) ......................................................................................... 21 

APPENDICES .............................................................................................................................. 21 

 

Page 32: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 2 of 21

DIVISION 01 – GENERAL REQUIREMENTS

SECTION 013524.45 – SAFETY REQUIREMENTS

PART 1 – GENERAL

1.01 INTRODUCTION

The Public Utility District #1 of Chelan County (District) is committed to providing a safe and healthy workplace for its employees and those of its Contractors and Subcontractors. The District believes the safety and health of the Contractors is essential to the long-range success of our business. The District expects Contractors to join in providing a workplace free of uncontrolled hazards to people, the environment and District facilities. Job safety is considered a critical driver in the District’s aim to achieve operational excellence as we strive for an incident-free culture.

1.02 SCOPE

A. These Requirements apply to all Contractors and Subcontractors performing Work on District Generation, Transmission and Distribution facilities and properties where WAC 296-45 is applied. The District does not control Contractors’ safety programs nor relieve them of its safety responsibilities. Instead, the District supports Contractors to improve overall safety and health

B. As a host employer, the District has the right to request from Contractors, for review, written safety and health plans covering Work to be performed. Contractors’ safety and health plans shall meet all safety and health standards required by this Contract and all applicable laws and regulations and maintain safe and healthful workplaces.

1.03 RELATED DOCUMENTS

Contract Drawings, if any, and other provisions of the Contract Documents, including but not limited to General Conditions (GC-) and Specific Requirements (SR-) apply to all sections.

1.04 SUBMITTALS (WHERE APPLICABLE)

A. Accident Prevention Program, if applicable.

B. Site Specific Safety Plan (with Job Safety Analysis)

C. Safety Data Sheets (SDS)

D. Crane and Crane Operator Certifications, if applicable

1.05 EXPECTATIONS AND RESPONSIBILITES

A. Contractor Safety Expectations (Washington Administrative Code (WAC) 296-45-067, WAC 296-800): Contractor’s and their employees will perform individual duties in a manner that is not injurious or otherwise dangerous to themselves or others. Each Contractor and by default, Contractor personnel, Subcontractors and its personnel are solely responsible for its own safety. It is each person’s responsibility to report unsafe behaviors and/or conditions as encountered and to effect

Page 33: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 3 of 21

immediate remediation of the problem in order to prevent adverse impact to property and personnel.

B. Contractor and Subcontractor Responsibilities (WAC 296-45-055, WAC 296-800):

1. Contractors and Subcontractors shall conduct business in manners that comply with both the letter and spirit of all laws, rules and regulations.

2. Contractors shall be responsible for all elements of required training, planning, safe behavior, personal protective equipment (PPE) and supervision required to allow them to perform the Work free from injury, illness, or impact to District and Contractor employees, visitors, the public, District facilities or the environment.

3. Where relevant and per contracted function, the Contractor’s responsibilities include:

a. Assigning a safety representative to each project;

b. Developing a Project Site Specific Safety Plan;

c. Ensuring that all Contractor and Subcontractor personnel have the appropriate qualifications and training to perform the contracted Work in a safe and healthful manner. Copies of current training documentation and certifications may be requested by the District;

d. Communicating (both oral and written) site-specific safety information to all Contractor and Subcontractor personnel, including: site-specific hazard information, emergency, and evacuation procedures, the location and operating procedures of safety and emergency equipment, and other relevant safety information;

e. Ensuring that all local regulatory requirements are met, and any necessary certificates or approvals pertaining to training, work procedures, equipment, permits and any other required approvals are obtained before conducting Work;

f. Providing all required personal protective equipment (PPE) necessary to conduct Work safely and in accordance with required local regulations (health and safety, electrical, fire and building codes, environmental, etc.);

g. Follow safe work practices;

h. Conduct safety meetings (e.g. tailgate or toolbox meetings) per WAC regulations;

i. Performing safety inspections and ensuring that any deficiencies noted are addressed immediately. The Contractor’s inspection may be conducted jointly with representatives of the District. If addressing deficiencies immediately is not possible, then the task where the deficiency was found shall be temporarily stopped until the deficiency is adequately addressed;

j. Immediately reporting any incidents, accidents, near misses, unsafe conditions, or unsafe acts involving any Contractor, Subcontractor or District personnel that could result in an injury;

Page 34: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 4 of 21

k. Properly storing and labeling waste designated as “dangerous waste”. Work with the District’s environmental personnel to ensure proper transfer of the waste at the point of generation. Remove unused hazardous material product from the Project site at the end of the job;

l. The Contractor will be responsible for all subcontractors hired, including review of applicable portions of this document.

C. Noncompliance with Safety and Health Requirements

1. During the course of the Contract situations, non-compliance with the Safety Requirements identified in the contract will be brought to the attention of the Districts Project Representative verbally and will immediately be followed-up in writing. Failure to correct the violation or continued violations may be grounds for termination of the Contract.

2. If, after notifying the District Project representative in writing of deficiencies of any health and safety violations which could pose an imminent danger, an immediate order to stop work may be issued. Should this occur, the matter will be brought to the immediate attention of the Director of Engineering and Project Management (EPM). Such violations may result in the default of the Contract.

D. Accident Prevention Program (WAC 296-800-130, WAC 296-800-140):

1. All Contractors are contractually obligated to comply with all applicable federal, state, local and District safety and health rules and regulations procedures. Therefore, it shall be the responsibility of each Contractor and/or Subcontractor to develop a formal Accident Prevention Program. The Contractor’s Accident Prevention Program (if applicable) must be available for review no more than 14-days after the execution of the Notice to Proceed and prior to starting any site Work.

2. At a minimum the Accident Prevention Program should include:

a. A safety orientation program describing the Contractor’s safety program and including:

1) How, where, and when to report injuries, including instruction as to the location of first-aid facilities.

2) How to report unsafe conditions and practices.

3) The use and care of required personal protective equipment.

4) The proper actions to take in event of emergencies, including the routes of exiting from areas during emergencies.

5) Identification of the hazardous gases, chemicals, or materials involved along with the instructions on the safe use and emergency action following accidental exposure.

6) A description of the employer’s total safety program.

7) An on-the-job review of the practices necessary to perform the initial job assignments in a safe manner.

b. How to conduct crew safety meetings.

Page 35: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 5 of 21

1) At the beginning of each job, and at least weekly thereafter.

2) Tailored to the particular operation.

c. What safety meetings must address:

1) A review of any walk-around safety inspection conducted since the last safety meeting.

2) A review of any citation to assist in correction of hazards.

3) An evaluation of any accident investigations conducted since the last meeting to determine if the cause of the unsafe acts or unsafe conditions involved were properly identified and corrected.

4) Documentation of attendance.

5) Documentation of subjects discussed.

d. Minutes of each crew safety meeting shall be prepared and a copy shall be maintained at the location where the majority of the employees of each construction site report for work each day.

e. Minutes of the crew safety meetings shall be made available for review by personnel of the District upon request.

f. Contractor’s shall conduct walk-around safety inspections as follows:

1) At the beginning of each job, and at least weekly thereafter.

2) At least once a month jointly by one member of Contractor management and one District representative.

3) Walk-around safety inspections must be documented and such documentation shall be available for inspection by personnel of the District.

3. Records of walk-around inspections shall be maintained by the Contractor until the Completion of the Project.

E. Site Specific Safety Plan (WAC 296-45-067, WAC 296-800-140)

1. The Contractor shall review all tasks and hazards associated with the Work and provide analysis on how the hazards will be addressed in a Site Specific Safety Plan. The plan shall be tailored to the needs of the particular operation and to the type of hazards involved with strategies and procedures identified to mitigate or eliminate risks. The Contractor shall update the Site Specific Safety Plan as the scope of Work develops throughout the duration of the Project. Contractors are required to submit Site Specific Safety Plans to the District at least 14-days prior to the Pre-Construction Meeting or 14-days after the execution of the Notice of Award.

2. The Site Specific Safety Plan should include:

a. Contractors Name

b. Brief description of Contractors Safety Policy

c. General description of the objective of this document

d. Site Information (Project Address)

Page 36: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 6 of 21

e. Project Duration

f. Key Personnel (Project Manager, Project Engineer, Superintendent, Safety Officer, Foreman, etc.)

g. Project Specifics (Scope of Work, Site Conditions, Site Surroundings, etc.)

h. Health and Safety Responsibilities (Project Manager, Superintendent, Safety Officer, Foreman, Employees, etc.)

i. Brief description of Contractors Safety Standards. Items should include but is not limited to: Safety Meetings, New Hire Orientation, Drug and Alcohol Policy, PPE, Housekeeping, Assured Grounding Program, JSA, Hot Work, Hazard Communication

j. Job Safety Analysis (JSA) for the Work being performed

k. Resources (Medical, Fire, Chemical, Administration)

l. Emergency (Emergency Protocol, Emergency Map, Emergency Numbers)

m. Nearest Fire Department

n. Employee Training

o. Safety Data Sheets (SDS) Inventory

3. All Site Specific Safety Plans shall detail how health and safety aspects of the Project will be managed and the systems that will be employed to maintain compliance with District, federal, state, and local requirements. Procedures and processes developed to satisfy the requirements of this plan must work in concert with the existing safety management processes at each affected facility.

4. In addition to the site-specific plans, all Contractors shall have and adhere to its own core health and safety plans, which must contain rules and procedures that apply to and mitigate the perceived hazards associated with the Contractor’s specialty.

5. The Contractor shall meet with the representatives of the District prior to the start of construction for the purpose of reviewing safety requirements and discussing implementation of all health and safety provisions pertinent to the Work under Contract.

6. The District representative will review the Contractor's Site Specific Safety and Health Plan with the Contractor as well as review all required SDS’s submitted for proposed products to be used by the Contractor.

1.06 SITE SAFETY RESPONSIBILITIES AND ACCOUNTIBILITIES

A. The Contractor is ultimately accountable for the safety at its worksite, although Contractors, Subcontractors and District representatives have authority to stop unsafe acts or conditions.

B. Contractors and Subcontractors shall appoint competent persons for each work crew. A competent person is one who has the capability of identifying existing and

Page 37: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 7 of 21

potential worksite hazards and has the authority to take prompt corrective measures to control or eliminate them.

1. Stop Work Authority (SWA)

a. All District, Contractor, and Subcontractor employees have Stop Work Authority that empowers each with the individual responsibility, authority, and obligation to immediately suspend a task or operation if it’s reasonable to believe that themselves, other persons, equipment, or the environment are at risk; or when there are concerns or questions about the health, safety and environmental risk controls in place.

b. No Work will resume until all issues and concerns are addressed. Reprimand, intimidation, or any type of retribution against any individual or company for invoking SWA will not be allowed.

c. If SWA interventions cannot be resolved on-site, the District representatives will follow chain of command to facilitate resolution.

2. Reporting Incidents (WAC 296-45-115WAC 296-800-12005)

a. Incidents involving equipment or employee(s) resulting in or having the potential of resulting in injury to employees or damage to equipment occurring on District Project sites shall be reported to the Project Manager or designee verbally and immediately after such incident.

b. When reporting an incident, Contractors must supply as much of the relevant information that is available as soon as possible to the District Project Manager or representative.

1) Name of injured person;

2) How incident occurred;

3) Place, Date, Time;

4) Description of Injury or equipment damage;

5) Medical treatment administered;

6) Where taken to and how transported;

7) Current status of equipment;

8) Current status of injured person.

c. Incidents going unreported is not allowed. Contractors will present a written report within 24-hours of the incident to the District.

3. Safety Training (WAC 296-45-065, WAC 296-800-14020): Contractors shall ensure that its employees receive required training that meets regulatory requirements and allows them to perform its duties safely. All Contractor employees shall be trained to recognize and avoid unsafe acts and conditions, and to control or eliminate hazards. Employee safety training shall include new hire safety and health orientation and ongoing safety and health training. All training shall be conducted, refreshed, and documented in accordance with applicable regulatory requirements.

4. District Contractor Safety Orientation (District Contractor Safety Orientation Checklist, reference Appendix 013524-1, Example Contractor Safety

Page 38: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 8 of 21

Orientation Checklist): Prior to Work, all Contractor employees are required to complete Contractor Safety Orientation. A District representative will facilitate orientation by leading the Contractors in a review of the District’s “Contractor Safety Orientation Checklist”. Orientations cover the minimum safety requirements expected of all Contractor employees. Contractor employee orientation must be renewed annually on a 12-month rolling basis.

5. District Energy Isolation Lockout/Tagout Program (WAC-296-45, WAC 296-24, WAC 296-803, District Energy Isolation LOTO Program): Prior to Work activities that require contractors to control or eliminate potential hazards, such as: electrical, pneumatic, hydraulic, mechanical energy, shall be trained and tested on the Districts Energy Isolation Lockout/Tagout Program. A District representative will facilitate the training and testing. Contractor employee LOTO training and testing must be renewed annually on a 12-month rolling basis.

1.07 CONTRACTOR WORKPLACE SAFETY REQUIREMENTS (General)

This section, along with all applicable laws and regulations, defines District's minimum workplace safety requirements for all Contractors and Subcontractors

A. Job Safety Analysis (WAC 296-45-135):

1. Before the Project begins, the Contractor shall identify the hazards associated with the work; and shall perform and complete a JSA.

2. A JSA can be used to identify, analyze and record the following:

a. The task involved in performing the Work,

b. The existing or potential safety and health hazards associated with each task, and

c. The recommended action(s)/procedure(s) that will eliminate or reduce these hazards and the risk of a workplace injury or illness.

3. Contractor shall develop and submit a completed JSA with the Site Specific Safety Plan. If the activities of any Work are significantly different from those listed in the original JSA, a separate JSA will be developed by the Contractor and submitted to the District’s Project Manager or its designee for review prior to start of the Work.

4. JSAs must also be reviewed with new contractor personnel introduced to the Project worksite (including Subcontractors). The JSA will be reviewed at the Pre-Construction Meeting.

B. Pre-Task Plans (WAC 296-45-135:

1. Each shift, before Work begins, all crewmembers must participate in a job task planning process that identifies hazards and provides a safe way of accomplishing each task. New crewmember shall review the documented PTP before starting work. This process of planning may be referred to as a construction work plan, job briefing, tailgate or other site specific nomenclature.

2. PTP’s should identify:

Page 39: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 9 of 21

a. Date, time and name of who is conducting the meeting and the names of the crew members present.

b. Hazards involved in the Work and steps on how to mitigate.

c. Energy isolation source controls.

d. Additional PPE needed (face shield, insulated gloves, life jackets, etc.).

3. The PTP should also verify the roles and responsibilities and the understanding of safe work practices.

4. Copies of the PTP’s are to be submitted or made available to the District daily.

C. Incident Reporting and Analysis (WAC 296-45-115, WAC-296-800-320,:

1. Contractors shall immediately report any of the following incidents to the District Representative that occur during District work:

a. Any Contractor employee injury or work related.

b. Any Contractor employee first aid incident.

c. Any fire resulting in the discharge of a fire .

d. Any spill of hazardous product.

e. Any event resulting in damage to District or third party property or equipment.

f. Other incidents that should be immediately reported include:

1) Any security breach or observation of suspicious activity.

2) Any safety near-misses. A “safety near-miss” is considered a situation that had potential to result in serious personal injury, health exposure, or a vehicle incident, but due to various circumstances, the consequences did not occur.

2. A written incident report is required within 24-hours of occurrence of the following types of incidents:

a. Any OSHA recordable injury or illness that occurs during District Work.

b. Any significant property damage that occurs during District Work.

3. An Incident Analysis (IA) by the Contractor may also be required for any event deemed appropriate by the District.

4. A District Representative may participate in the IA. Upon completion of the IA, the Contractor shall furnish a copy of the completed IA report to the District Representative.

D. Medical Services and First Aid (WAC 296-45-125, WAC-296-800-150):

1. Contractors shall provide its employees with first aid services and provisions for medical care. In the absence of professional medical services in near proximity to the worksite, the Contractor shall ensure there are adequately trained persons to render first aid.

2. Emergency medical information including phone numbers and driving instructions to worksites for medical response personnel shall be posted and readily available with GPS coordinates (if available).

Page 40: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 10 of 21

3. On a voluntary basis, personnel with allergies to such things as insect stings, vegetation, or medication, should be identified.

4. First aid supplies must be readily available. First aid kits shall comply with ANSI Z308.1 and WAC 480-62-999.

5. “Minimum Requirements for Workplace First-Aid Kits”. When larger operations or multiple operations are being conducted at the same location, Contractors should determine the need for additional first aid kits, equipment, or supplies.

6. Where the eyes and the body of any person may be exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body must be provided within the Work area for immediate emergency use.

E. Site Safety and Health Plans (for non-HAZWOPER Work) (WAC 296-843-12005): Site Safety and Health Plans may be required for Work involving lead, asbestos, emergency response not involving a release, or as otherwise deemed necessary by District.

F. Housekeeping and Sanitation (WAC 296-800-23020): All worksites shall be kept neat and orderly to the extent that the nature of the Work allows. Portable drinking water dispensers shall be designed, constructed, and serviced so that sanitary conditions are maintained.

1. Adequate toilet and hand-washing facilities shall be provided in accordance with WAC 296-800-23020 regulations. For mobile crews, transportation shall be made readily available to nearby facilities.

2. Lunch and/or eating areas shall be maintained clean and free of food scraps.

G. Motor Vehicle Safety (WAC 296-865): Contractors and Subcontractors shall operate motor vehicles in accordance with all federal, state, local, and site-specific requirements. Vehicles shall be operated in accordance with manufacturers’ recommendations.

1. Driving at excessive speeds or in unsafe manners while on District property will not be tolerated.

2. The use of cellular phones or other communication devices while driving on District property is prohibited except during emergency response.

H. Emergency Evacuation Plans (WAC 296-824):

1. During orientation or pre-job safety meetings, the District representative (or designee) will review site-specific emergency evacuation procedures with each Contractor and Subcontractor employee.

2. The review shall include, but is not limited to:

a. The method of notifying individuals of the evacuation (alarm system).

b. Actions to be taken by them in the event of an evacuation.

c. Evacuation routes and assembly points (both primary and alternate).

d. Method of accounting for all personnel.

e. Any contacts or telephone numbers that may be needed.

Page 41: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 11 of 21

f. All personnel are responsible for following site-specific evacuation procedures.

I. Drugs, Alcohol, and Firearms (WAC 296-45-095, WAC 296-800, Drug-Free Workplace and Fitness for Duty Policy No. 706, Violence in the Workplace and No Weapons Policy No. 118):

1. Using, being under the influence of, possessing, transporting, promoting, or selling illegal drugs or drug paraphernalia, and/or otherwise legal but illicitly used substances by anyone while on District property or District business is strictly prohibited.

2. Using, being under the influence of, possessing, or transporting alcoholic beverages on District property is prohibited.

3. The use, possession or transportation of firearms, explosives, and/or other types of weapons on District property is prohibited.

4. Contractor personnel who are found in violation of these prohibitions will not be allowed on District’s property and may be referred to law enforcement agencies.

5. To help ensure a safe, healthy and productive work environment, District reserves the right to carry out reasonable searches of individuals and its personal effects, and Contractors’ vehicles and equipment when entering District property, while on District property, and/or when leaving District property. Such searches may be initiated by District without prior announcement and will be conducted at such times and locations as deemed appropriate by the District. Cooperation is voluntary; however, refusal of an individual to cooperate will be caused for not allowing Contractor employee(s) on District property.

J. Smoking (WAC 296-800, District No Smoking Policy No.119): Smoking is prohibited in District facilities and vehicles. Anyone smoking near a District facility shall do so at a distance of no less than 25-feet from entrances, exits, windows that open, and ventilation intakes.

K. Contractor Security (District Security Measures Policy No. 708, District Sabotage Recognition and Reporting Procedure):

1. Contractors and Subcontractors are responsible for its own equipment and accountable for controlling the actions of its employees while working for the District. All personnel shall possess current Contractor Identification (ID) badges when working inside hydro security areas and inside District facilities. Personnel shall clearly display the badges unless unsafe to do so; in which cases ID’s shall be carried on its person and provided upon request.

2. All Contractors are encouraged to proactively support the security initiative by immediately reporting suspicious activities observed.

1.08 CONTRACTOR WORKPLACE SAFETY REQUIREMENTS (Specific)

A. Hazardous Waste Operations and Emergency Response (HAZWOPER) (WAC 296-843): Contractors engaged in hazardous waste operations shall ensure all its employees have successfully completed the training and field experience. Documentation of training for each employee must be provided upon request. If the

Page 42: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 12 of 21

Contractor is given control of the post emergency clean up, the Contractor shall prepare the emergency response plan. If District retains control, District shall prepare this plan. In either case, cleanup Contractors are responsible for:

1. Complying with the Site Safety and Health Plan,

2. Training its employees,

3. Informing its Subcontractors of the provisions and requirements of the Site Safety and Health Plan,

4. Complying with all applicable laws and regulations.

B. Portable Fire Extinguishers (WAC 296-800-300):

1. Contractors and Subcontractors must provide and maintain portable fire extinguishers in good working order and in proper locations. Fire extinguishers shall be of proper type for the fire hazard. Portable fire extinguishers shall only be used if the fire is discovered by a person ready, willing and trained to use the extinguisher.

2. Extinguishers must be inspected and serviced on a regular basis. Contractor and Subcontractors shall document monthly inspections of portable fire extinguishers.

C. Powered Industrial Trucks (Forklifts) (WAC 296-863):

1. All forklifts shall be inspected, used, and maintained in accordance with manufacturer’s guidelines. Forklifts shall only be operated by personnel who are properly trained and qualified. Only the authorized operator is allowed to ride the forklift during use. No other riders are permitted unless the unit is designed for other occupants.

2. Documented inspections shall be completed prior to use each day for all forklifts. All controls, indicators, instrumentation, and markings shall be in-place and legible. All forklifts shall be equipped with fire extinguisher, horn, backup alarm, and seatbelt (not required if rollover protection is not installed).

D. Aerial Lifts (WAC 296-869): All aerial lifts shall be inspected, used, and maintained in accordance with manufacturer’s guidelines. Equipment shall only be operated by personnel who are properly trained and qualified. Equipment shall not be used as a crane or material hoist.

E. Fall Protection (WAC 296-45-25510):

1. Fall protection is required for fall exposures of 4-feet or greater.

2. If applicable to the Project, any Work activities where fall hazards of 10-feet or more exist, the Contractor shall develop and implement a Fall Protection Work Plan in accordance with WAC 296-155-24611. Contractor shall submit the Fall Protection Work Plan to the District prior to beginning the Work.

3. Personnel shall be protected from fall exposures at all times when working atop roofs of buildings and other structures. This requirement includes work activities atop roofs with parapet walls.

4. Where personal fall arrest (PFA) are used, personnel rescue must be planned and accounted for in case of a fall.

Page 43: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 13 of 21

5. All fall protection systems used must meet or exceed ANSI Z359.1 - 2016 requirements. Use of body belts for fall restraint/arrest is prohibited.

F. Ladders (WAC 296-45-275, WAC 296-876):

1. All ladders shall be maintained in safe conditions and shall be inspected regularly and prior to each use. Ladders with defects must be immediately removed from service.

2. Within District facilities, only nonconductive ladders (fiberglass, wood etc.) are to be used in and around District hydro facilities, substations and switchyards.

3. Ladders may be used only in accordance with manufacturers operating instruction and in the applications for which they were designed.

G. Scaffolding (WAC 296-874):

1. All scaffolding shall be erected, used, maintained, and disassembled under the direction of a competent person and in accordance with the manufacturer’s guidelines for the system being used. Competent persons shall complete documented inspections on scaffolding systems prior to each shift.

2. Damaged, bent, corroded, or weakened scaffolding components shall be replaced prior to using the system.

H. Cranes, Hoists, and Slings (WAC 296-24 Part D):

1. All cranes shall be inspected, operated, and maintained in accordance with manufacturer’s guidelines and in compliance with requirements for WAC 269-155-Part L. Crane operators must be certified with a valid crane operator certificate for the type of crane to be operated and issued by a crane operator testing organization recognized by the Washington State Department of Labor and Industries. Cranes must be inspected and certificated by a third party annually. Riggers and signal persons must be properly trained and qualified.

2. Critical lift plans/checklists (reference Appendix 013524-3, Example Crane/Hoisting Pre-Lift Plan Form) must be completed if:

a. The item being lifted were to be damaged or upset could result in a release of hazardous material;

b. The load being lifted is 75% or more of the crane’s rated capacity;

c. Two mobile cranes are lifting the load and the load share equals more than 70% of one or both crane’s rated capacity;

d. The District Representative or crane operator deems it necessary.

3. Contractors or Subcontractors shall supply its own critical lift plans/checklists.

4. Proper clearance from overhead power lines shall be established based on safe approach distances. Appropriate signs shall be in place to warn of the presence of overhead power lines. All lifting equipment and hoist hooks must have working safety latches.

5. All rigging (slings, chains, spreader bars, etc.) must be inspected prior to each use. Load capacities shall be clearly marked. Damaged or defective rigging shall be immediately removed from service, clearly marked “DO NOT USE”

Page 44: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 14 of 21

and destroyed/discarded as soon as possible. Taglines shall be used to control the swing of lifted materials.

I. Flammable and Combustible Liquids (WAC 296-24-330, NFPA 30 9.4.1(2),):

1. All chemical containers must be marked with the contents, and in a manner that warns of the hazards associated with the chemicals’ hazards.

2. Safety cans used for refueling equipment (such as generators and mowers) must be approved (stamped) by a nationally recognized testing laboratory (UL or FM). Safety cans shall be constructed of metal, equipped with spring-closing lids and spout covers, and designed to safely relieve internal pressure when subjected to fire exposure.

J. Compressed Gas Cylinders (WAC 296-24-68203):

1. Each gas cylinder shall be marked with its contents.

2. Cylinders must remain on level, fireproof surfaces, away from heat, electrical sources or stairs. They shall be secured upright by a chain, cable or similar security device.

3. When not in use, oxygen and acetylene cylinders shall be stored separately 20-feet or more apart, or separated by a non-combustible barrier at least 5-feet high.

4. Except for SCBA tanks, compressed gas cylinders are not allowed in confined spaces.

5. Compressed gas cylinders shall be handled, loaded and transported in safe manners.

6. Each cylinder shall be inspected for damage prior to use. Damaged cylinders shall be immediately removed from service then removed from the facility or worksite by the vendor that supplied it.

K. Lockout/Tagout (LOTO) (WAC-296-45-17505,WAC 296-803, District Energy Isolation LOTO Program ):

1. Lockout/Tagout is managed through the District’s Energy Isolation Program. This program applies to all personnel who supervise, order, perform and direct switching, clearances and/or work within the boundaries of the facilities of the District or its equipment.

2. The purpose of this program shall be to establish the minimum energy isolation requirements necessary to ensure a safe working environment for all District employees and outside Contractors. The program shall be used to provide guidance and outline procedures to control or eliminate potential hazards, such as: electrical, pneumatic, hydraulic, mechanical, or other, prior to the commencement of any repair, testing or maintenance activity.

3. District’s written LOTO program is available to Contractors and Subcontractors upon request.

L. Confined Space Entry (WAC 296-809): All confined spaces must first be treated as a Permit Required Confined Space. A confined space may be reclassified as a non-permit confined space. The Contractor is responsible to determine the extent of its Work scope and Work activities, and the appropriate designation of the

Page 45: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 15 of 21

Confined Spaces for its employees and Subcontractors to perform Work safely. All Work in confined spaces must meet the requirements of and employees must be properly trained in accordance with this regulation. Contractors entering confined spaces must submit a confined space program.  

M. Atmospheric Monitoring (WAC 296-809): Contractors are responsible for providing proper atmospheric monitoring devices as necessary for the work activities performed. All devices shall be inspected, calibrated, used, and maintained in accordance with manufacturer’s guidelines. Operators shall be properly trained and qualified in accordance with manufacturers’ guidelines.

N. Hand and Power Tools (WAC 296-24 Part L, WAC 296-45-285, WAC 296-800-280):

1. Hand and power tools shall be used in accordance with manufacturers’ guidelines. Tools shall be maintained in overall good condition. Damaged or defective tools shall be immediately removed from service. Tools, including grinders, manufactured with guards shall not be used unless guards are in place.

2. Tool power cords and extension cords must be free from damage. Repairs to cords must provide equal or greater protection than the original insulation. Job-made extension cords are prohibited.

3. Extension cords shall be equipped with or plugged in to ground fault circuit interrupters (GFCI) at the power source.

4. Cords shall be secured with non-conductive materials; and routed in safe manners. Air hoses shall be in good condition, connections secured, and routed in safe manners. Safety clips and whip checks shall be installed at each compressed air connection point.

O. Electrical Safety (WAC 296-45-055): Contractors shall ensure that its electrical equipment is free from recognized hazards. Only trained and authorized personnel shall work on electrical equipment. Working near high voltage transmission lines requires grounding of equipment. Appropriate steps shall be taken to ensure there is no induced voltage on exposed metal when working near high voltage transmission lines.

P. Heavy Equipment (WAC-296-155-Part M):

1. All equipment (dozers, track hoes, etc.) shall be inspected, used, and maintained in accordance with manufacturer’s guidelines. Equipment operators shall be properly trained and qualified in accordance with applicable WAC standards;

2. Passengers are not allowed on heavy equipment;

3. Seatbelts are required to be worn in all vehicles and equipment with roll-over protection. Spotters should also be used as-needed when operating in near proximity to facility equipment such as pumps or valves. Spotters shall maintain line-of-sight contact with equipment operators at all times during operation;

4. All running lights, work lights, backup alarms, and horns shall be operational. All winch cables shall be of proper rating and maintained in good condition;

Page 46: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 16 of 21

5. Proper clearance from overhead power lines shall be established based on safe approach distances. Appropriate signs shall be placed to warn of the presence of overhead power lines; and

6. Equipment shall be parked/staged in safe manners. Wheels shall be chocked when parked on inclines.

Q. Tank Work (WAC 296-809): Prior to beginning Work, the tanks shall be isolated from all connected lines, energy sources and equipment. Tank isolation devices must be locked and tagged out and tested.

1. All tank work shall be closely coordinated with District employees;

2. Contractors shall ensure its personnel engaged in tank work activities have the understanding, training and skills to safely perform assigned duties;

3. Tanks are considered permit-required confined spaces until emptied, cleaned, and determined to be gas-free. Tanks are considered gas-free once atmospheric monitoring results indicate safe work levels (respirators not required and no flammable vapors present); and

4. Continuous air monitoring is required at all times while personnel are performing activities inside of tanks.

R. Working Near Public Roadways (Washington State Department of Transportation’s (WSDOT) Manual on Uniform Traffic Control Devices):

1. Contractor supervisors shall ensure that temporary traffic control (TTC) measures are implemented as-needed to help ensure worker and public safety in roadway work zones. TTC elements include signs, barricades, markings, flaggers and its devices, and other measures. All safety precautions (signs, barricades, markings, etc.) for all activities completed near, along, or adjacent to public roadways shall be implemented in accordance with the Washington State Department of Transportation’s (WSDOT) “Manual on Uniform Traffic Control Devices.”

2. A Job Safety Analysis (JSA)/Pre-Task Plan shall be completed and shall be reviewed during pre-job safety and daily before Work starts.

3. Development of the Job Safety Analysis (JSA)/Pre-Task Plan shall include, at a minimum, the following considerations:

a. Appropriate placement and use of temporary traffic barriers and flaggers;

b. Reduction of vehicular traffic speed, mainly through regulatory speed zoning, funneling, lane reduction, or the use of uniformed law enforcement officers or flaggers;

c. Planning the internal work activity area to minimize backing-up maneuvers of construction vehicles should be considered to minimize the exposure to risk; and

d. A basic hazard assessment for the worksite and job classifications required in the activity area.

4. Flaggers shall be trained and certified in safe traffic control practices and public contact techniques.

5. Flaggers shall be able to satisfactorily demonstrate the following abilities:

Page 47: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 17 of 21

a. Ability to receive and communicate specific instructions clearly, firmly, and courteously;

b. Ability to move and maneuver quickly in order to avoid danger from errant vehicles;

c. Ability to control signaling devices (such as paddles and flags) in order to provide clear and positive guidance to drivers approaching a TTC zone in frequently changing situations;

d. Ability to understand and apply safe traffic control practices, sometimes in stressful or emergency situations;

e. Ability to recognize dangerous traffic situations and warn workers in sufficient time to avoid injury; and

f. All personnel working within public roadway ROW’s shall wear high-visibility safety apparel.

1.10 OCCUPATIONAL HEALTH AND INDUSTRIAL HYGIENE HAZARD COMMUNICATION (HAZCOM) - WAC 296-802-200, WAC 296-901-140

A. The Globally Harmonized System of Classification and Labeling of Chemicals (GHS) requires that employers inform its workers of the presence, identity, and hazards of workplace materials through a written hazard communication program, labels, substance lists, SDS’s, and training. Prior to commencing Work, District representatives will inform Contractors regarding District owned hazardous chemicals to which Contractor employees may be exposed; and will provide Contractor employees’ access to the SDS’s for these chemicals. The Contractor shall disseminate such information to its employees and Subcontractors and assure that appropriate precautions are followed.

B. Contractors and Subcontractors shall establish and maintain lists of chemicals used on District worksites and make the lists available to the District representatives. Chemicals brought to or used at District facilities and worksites shall be properly labeled, tagged, or marked to identify all of the following: chemical or product name; the name and address of the chemical manufacturer, shipper, or other responsible party and appropriate hazard warnings.

C. Contractor is prohibited from using halogenated solvents/oils, asbestos, dioxins, PCB’s, mercury and chlorinated chemicals (e.g. tetrachloroethylene, methylene chloride, trichloroethylene, trichloroethane) unless approved in writing by the Safety and Health Division of the District.

D. Spill Response. Any release (spill) of a chemical or petroleum product to the ground, open waterway, sanitary sewer, storm drain or air, requires quick action on the part of those involved or anyone who notices the release. The District’s Inspector shall be contacted immediately if there is a spill or if emergency conditions develop as a result of a spill. Promptly reporting and initiating a cleanup of the spill will mitigate further damage and prevent potential fines or penalties. The District’s Inspector will review the initial response and advise what additional response actions may be necessary. This includes contacting the necessary regulatory authorities, dispatching cleanup crews and fulfilling any reporting requirements.

Page 48: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 18 of 21

E. Contractor shall be fully responsible for all cleanup expenses and any and all fines associated with spills caused by Contractor. No extension or changes in Contract Time shall result from spills caused by Contractor.

1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE) (WAC 296-24 Part L, WAC 296-45-25505, WAC 296-800-160):

A. Contractors are required to provide its employees with all necessary PPE. PPE assessments must be completed prior to performing Work.

B. All Contractor and Subcontractors shall:

1. Wear and maintain assigned PPE as required

2. Immediately report any damaged or defective PPE to the supervisor

C. All PPE shall be maintained and stored in a clean and sanitary condition per the manufacturers’ recommendations.

D. When possible, administrative and engineering controls shall be used to eliminate or mitigate hazards. PPE shall be used when administrative and/or engineering controls do not remove the potential exposure hazards to employees.

E. Normal Duty Apparel : Dangling sleeves or other loose clothing or jewelry shall not be worn when working on or around machinery. Contaminated clothing shall be changed as soon as practical. Contaminated clothing shall not be worn in eating areas. Jewelry shall not be worn during the performance of activities that involve electrical hazards. Long hair shall be pulled up or back to prevent entanglement when working on or around machinery. No shorts or sleeveless shirts are allowed.

F. High-Visibility Apparel (WAC 296-800-16020: All personnel within the right-of-way of public roadways who are exposed either to traffic (vehicles using the highway for purposes of travel) or to work vehicles and construction equipment within temporary traffic control zones shall wear high-visibility safety apparel that meets the Performance Class 2 or 3 requirements of the ANSI/ISEA 107–2004 publication entitled “American National Standard for High-Visibility Safety Apparel and Headwear,” or equivalent revisions, and labeled as meeting the ANSI 107-2004 standard performance for Class 2 or 3 risk exposure.

G. Working Over or Near Water (WAC 296-16070: Personnel shall wear U.S. Coast Guard approved Personal Flotation Devices (PFD’s) when performing activities within 10-feet of water that is three (3) or more feet deep. Personnel shall wear PFD’s at all times while in or on watercraft.

H. Head Protection (WAC 296-16055:

1. Hard hats shall be worn whenever there is a potential exposure to danger of flying or falling objects to persons working or occupying the area or in designated areas. Hard hats are not required to be worn indoors unless where exposures to head injuries are present.

2. Personnel shall wear hard hats that meet ANSI Z89.1 Class E specifications for Type I and II protection while performing any activity on or near exposed energized electrical circuits 50 volts or higher.

Page 49: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 19 of 21

3. Personnel shall inspect, wear, maintain and store its hard hats in accordance with manufacturers’ guidelines. Modification of a hard hat, which may include drilling holes, trimming, painting, or any way altering its protective properties, is prohibited. Stickers may be displayed but shall not make inspection of the hard hat shell difficult.

I. Eye Protection (WAC 296-800-16050):

1. Eye protection is required when performing activities or working in areas that may expose employees to eye hazards.

2. Personnel are required to wear eye protection that meets ANSI Z87 specifications.

3. Safety glasses or goggles provide minimum protection and are required while performing any activity that has a potential exposure of flying debris. Non-conductive safety glasses shall be worn at all times when working on or in close proximity to potentially energized conductors or exposed non-insulated parts.

4. Face shields provide secondary protection. Depending on the exposure, face shields shall be used in addition to primary protection.

5. Personnel shall select and wear appropriate specially tinted lenses while welding, cutting or helping during these activities.

6. Personnel shall wear arc-rated face shields or flash hoods as part of the arc flash protective clothing ensembles when engaged in activities that require elevated arc flash protection.

J. Hearing Protection (WAC 296-800-817)

1. Hearing protection is required in designated areas and when performing activities or working in areas that do or may expose personnel to noise hazards.

2. Personnel shall properly wear, inspect, maintain, and store its hearing protection. Personnel shall wear ear plugs as part of the arc flash protective clothing ensembles when engaged in activities that require elevated arc flash protection.

K. Foot Protection (WAC 296-800-16060): Footwear appropriate to the hazards shall be worn at all times on District facilities and Project worksites. At a minimum, sturdy leather boots with a 5-inch top measured from the ground are required at Hydro/Generation facilities with the exception of Administration offices, areas open to public access, or designated areas. Cold weather work (ice and snow) and working in water will be exceptions to the all leather portion of the foot wear standard.

L. Chainsaw Boots and Safety Chaps (WAC 296-45-295, District PPE Standard): Personnel who operate chainsaws shall wear footwear specifically designed to provide protection from chainsaw cuts to the feet and lower legs. Boots shall be either constructed of multi-layered Kevlar or meet ASTM F1818-2004 specifications. Personnel shall also wear chainsaw safety chaps that meet ASTM F-1897-08.

M. Hand Protection (WAC 296-800-16065):

Page 50: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 20 of 21

1. Hand protection is required when performing activities or working in areas that do or may expose personnel to hand hazards. The appropriate hand protection must be selected for the Work being performed.

2. Personnel shall wear rubber insulating gloves with protectors as part of the arc flash protective clothing ensembles when engaged in activities that require elevated arc flash protection.

N. Respiratory Protection (WAC 296-842):

1. Respirators are selected based on the contaminant(s) to which Contractors will be exposed. Examples of jobs or tasks that typically require respiratory protection include but are not limited to:

a. permit-required confined space entry;

b. abrasive blasting;

c. coating/painting;

d. removal of asbestos-containing material;

e. lead abatement; and

f. working in areas with benzene (or other VOC) exposures.

2. Contractors that engage in activities that require respiratory protection shall have and shall work in accordance with its own written respiratory protection programs.

O. Arc Flash Protection (WAC 296-45-325NFPA 70e 2015):

1. Contractors exposed to electrical arc hazards, where it is necessary to be exposed, shall follow these requirements before beginning the task.

a. Determine if Work will be performed within the flash protection boundary. If needed an arc flash analysis may be required.

b. Determine if the arc flash hazard can be mitigated by de-energizing or if Work can be performed outside the arc flash boundary.

c. Identify if a site specific arc flash analysis has been performed and/or an arc flash warning label is present before performing Work. If location specific arc flash analysis has not been performed and no warning label is present, then utilize general guidelines in this program and contact supervisor and/or engineering for an arc flash analysis.

d. Determine appropriate PPE (face shields, gloves, hardhat, etc.) by identifying the task to be performed and/or arc flash warning label.

2. For such activities, personnel shall properly wear appropriate arc flash PPE that is designed and constructed for the specific part of the body to be protected and for the hazards associated with the Work to be performed. Personnel shall properly wear, inspect, maintain, and store all arc flash PPE.

Page 51: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Section 013524.45 – Safety Requirements Page 21 of 21

PART 2 – PRODUCT (NOT USED)

PART 3 – EXECUTION (NOT USED)

APPENDICES

Appendix 013524-1, Example Contractor Safety Orientation Checklist Appendix 013524-2, Example Job Safety Analysis Appendix 013524-3, Example Crane/Hoisting Pre-Lift Plan Form Appendix 013524-4, Example Hot Work Permit

END OF SECTION

Page 52: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 1 of 6 

Contractor Safety Orientation Checklist  

Project Name & Location:  __________________________________________________________________ 

Activity/Scope of Work:  ___________________________________________________________________ 

Contract # / PO:  __________________________________________________________________________ 

District Project Sponsor (Manager):  __________________________________________________________ 

Company Contracted:  _____________________________________________________________________ 

Orientation Presented By:  ___________________________________ Date:  ________________________ 

Contractor Owners and employees attending: 

PRINT NAME    

SIGNATURE  

     

     

     

     

     

     

Orientation given by: __________________________________________Date: _______________________ 

 

 

The Chelan County PUD (“District”) has developed the following checklist to promote a general understanding of safety standards, guidelines and procedures that must be followed while working on District property.  As used herein, the word “Contractor” includes consultants.  Contractors must complete the checklist prior to commencement of work and maintain documentation of completion, as well as documentation of Contractor‐employee safety plans, inspections, and meetings.  Accident prevention programs submitted by the contractor must meet the requirements of WAC 296‐800‐140.  

This orientation will be required annually and if necessary repeated if new information and/or work location changes.  This orientation does not address all procedural items that a Chelan County PUD employee overseeing a project would typically review with the contractor.   

Contractors are responsible for reviewing checklist information and procedures with their employees.  This checklist is not designed to cover every safety issue applicable to Contractors’ work.  Contractors are responsible for observing and educating their employees with regard to any and all safety regulations, procedures and equipment requirements applicable to employment in general, as well as those specifically applicable to their type of work.  The Contractor is solely responsible for the safety of the Contractor’s employees and the work site.   

   

Route original document or electronic copy once completed to the Safety/HR Dept. Admin. 

Page 53: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 2 of 6 

Initials are required in each section by staff providing the orientation. (If section(s) do not apply, write N/A.) 

CHECKLIST 

X

 

INTRODUCTIONS The Contractor shall be introduced to the applicable facility supervisors, safety and maintenance personnel associated at the work location.  

X

 

STOP WORK AUTHORITY Communicate “Stop Work” to co‐workers and ensure everyone present stops work. Put equipment and job site in a safe condition and communicate to those affected. Use the chain of command until resolution is accomplished.  

X

 

CONTROL ROOM – IF APPLICABLE The Contractor shall be made aware of the location of the Hydro Facility Control Room and the role of the Operators.  Contractor shall provide the Control Room an emergency contact phone list and list of on‐site employees.  An accurate copy of the contract work plan will be provided to the Control Room.  

X

 

EMERGENCY NUMBERS Contractors working at Hydro plants will notify the Hydro Facility Control Room.  The Operators will call 911 and coordinate escorts for EMS to the emergency site through the security check points and gates.   

  Hydro Facility Control Room Phone Numbers 

Location  Outside number  From Plant telephone 

Rocky Reach Dam  509‐662‐8705  Ext. 6000 

Rock Island Dam  509‐661‐4007  Ext. 5000 

Chelan Dam  509‐682‐2612  Ext. 4227 

System Operations  509‐661‐4000  Ext. 4000  

X

 

Emergency number from a district phone is 9–911. 

X

 

MEDICAL FACILITIES  Discuss the location of the nearest first aid station or medical facility. 

  Confluence Health (Wenatchee Valley Hospital, aka “The Clinic”) 

820 N Chelan Ave.  Wenatchee  509‐663‐8711 

Confluence Health (Central Washington Hospital) 

1201 S Miller St.  Wenatchee  509‐662‐1511 

Cascade Medical Center  871 Commercial St.  Leavenworth  509‐548‐5815 

Lake Chelan Community Hospital  503 E Highland Ave.  Chelan  509‐682‐3300  

  If work is being conducted at other or remote District sites call 911.  Contractors are to establish procedures per WAC 296‐800‐31075 

X

 

EMERGENCY RESPONSE PLAN (ERP)  Contractors will be made aware of the facility’s ERP.  The ERP deals with major emergencies that may arise such as fire or a major accident.  Discuss assembly areas, primary and secondary evacuation routes.  In the event of an emergency, contractors will be notified by District staff, radio or audible alarm and they are to report to the emergency meeting area.  Once all employees and contractors are accounted for, they may be able to leave the site should the situation warrant.   

Page 54: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 3 of 6 

Contractors shall also communicate to the District any company specific emergency response plan or signals (audible or visual) that could affect District workers in the area.  

If the Contractor is using a portable radio on a District approved frequency to communicate with their workers one radio with charger shall be supplied to the Control Room so that Operators can communicate with contract employees in the case of an emergency. 

X

 

CHECK‐IN/CHECK‐OUT The Contractor shall be instructed on proper check‐in/check‐out procedures, where applicable. 

X

 

PARKING The Contractor will be shown where to park vehicles.  Coordinate special arrangements (i.e. work at RI /spillway and/or RR forebay) with appropriate plant supervisor.  Specific locations may require contractors to leave keys in vehicles if they need to be moved.  

X

 

VEHICLES, TOOLS & EQUIPMENT WAC 296‐155‐009 It is the employer's responsibility to ensure that any defective equipment or tools are not used.  When any tool or piece of equipment fails to meet the requirements of any safety standard or recognized safe practice, the tool or equipment shall not be used.  

X

 

PRE TASK PLAN/ CREW LEADER‐CREW SAFETY WAC 296‐155‐110(5) Perform daily meetings to ensure hazards are identified, discussed, addressed and recorded before work begins. 

X

      

SAFETY EQUIPMENT (PPE) All safety equipment will be supplied by the contractor.  Unless agreed upon Chelan County PUD will not loan or provide any safety and health equipment.  Contractor must provide their own employees with PPE and enforce the use on projects.  Other Minimum PPE required may consist of hard hats, eye protection and sturdy leather footwear. 

X

 

INCIDENT REPORT  Any injury, property damage, safety concern, or close call must be immediately reported to the Project Manager or designee.  

X

 

FIRE EXTINGUISHERS  The Contractor will familiarize their employees with the location of District fire extinguishers if available.  Contractors must provide fire extinguishers as required by their work scope activities or contract for all hot work.   

X

 

FLAMMABLES WAC 296‐24‐33009  Flammable liquids in excess of 60 gallons will be stored in approved storage cabinets.  Flammable liquids shall be stored in and dispensed from approved containers.  Secondary containers are to be labeled.   

Oxygen/Acetylene & Other Gas Cylinders WAC 296‐24‐68203 Cylinders shall be kept away from sources of heat and at least 20 feet from highly combustible materials. Cylinders must be secured from falling or tipping over and protective valve caps are to be in place when cylinders are not in use. Cylinders containing oxygen or acetylene or other fuel gas shall not be taken into a confined space. Oxygen/Acetylene torches and hoses must be removed from a confined space at the end of each shift if not in use. (WAC 296‐155‐400(2)(d) & WAC 296‐155‐410(7). 

Page 55: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 4 of 6 

X

 

HOUSEKEEPING The contractor shall control accumulations of flammable and combustible waste materials and residues so that they do not contribute to a fire emergency.  This includes daily removal of trash & rubbish and removal of all unused chemicals, paints, etc. from the site when the work activity is completed.  CCPUD reserves the right to request cleaning of work sites.  

X

 

LADDERS/ SCAFFOLDING Ladders must be inspected prior to use and in good safe working condition.  Nonconductive ladders (fiberglass, wood etc.) are to be used in and around energized electrical equipment.  Ladders may be used only in applications for which they were designed.  Scaffolding shall be of substantial construction with guardrails, midrails and toe boards installed – meeting WAC 296‐155 requirements.  

X

 

FALL PROTECTION WAC 296‐155‐240 PART C‐1 The contractor shall ensure that the appropriate fall protection system is provided, installed and implemented according to the requirements in this part when employees are exposed to fall hazards of four feet or more to the ground or lower level when on a walking/working surface.  

Fall arrest systems may comprise of personal fall arrest, positioning device systems (fall restraint) or safety net systems.  

X

 

OVERHEAD WORK  Communicate the hazards of overhead work and the potential of falling materials to both workers and personnel below the work activity.  Area(s) underneath the work operation shall either be barricaded off and labeled with appropriate warning signs or documented in writing the method of providing overhead protection & communicate to workers who may be in or pass through the area below the overhead work site.  

X

 

SAFETY BARRIERS/BARRICADES AND SIGNAGE  Barriers at the District may include but are not limited to a physical obstruction, such as a rope with or without flagging, a chain, the use of colored tapes, screens or cones, or “A” frame type wood sawhorses and/or metal structures intended to warn and limit access to a work area.  A Sign may or may not be present or posted upon barriers/barricades.  Contractor employees are to stop at all barriers and ask the workers who installed the barrier for permission to enter before traveling through a barricaded area.  Contractors may install barriers and District personnel are to stop and ask permission to enter before traveling through contractor’s barricaded areas.   

Safety signs and/or symbols shall be used where necessary to warn employees of the relevant hazards which are present or that they may become exposed to.  

X

 

SPILL PREVENTION  Spill prevention and District procedures for spill clean‐up, including notification of Chelan County PUD personnel, will be reviewed with contractors who will be using any petroleum‐based products or hazardous materials on District property.  The contractor is to ensure that the spill is contained before leaving the area.  Contractors are responsible for providing spill containment kits for their products.  Spills will be reported to the Control room at Generation Facilities, or to Project Managers at other locations. 

Page 56: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 5 of 6 

X

 

HAZARDOUS MATERIALS WASTE Waste that is generated on District property that is designated “Dangerous Waste” per WAC 173‐303 needs to be stored & labeled properly by the contractor.  The contractor needs to work with the District Environmental Department to ensure proper transfer of the waste at the point of generation.  Unused hazardous material product(s) need to be removed at the end of the job by the contractor.  

X

 

RIGHT‐TO‐KNOW WAC‐296‐800‐170 WAC’s Right to Know (Hazard Communication) requires the District to ensure all employees, including all contractors onsite, are aware of any hazards that they may be exposed to in the workplace.  Contractors must provide to the Project Manager prior to the start of work SDS Sheets for all products brought onto District Facilities and communicate where hazardous products are being used. SDS’s must be current, legible and in English.  All chemical and secondary containers must be properly labeled.  

XSUBSTATION/SWITCHYARD TRAINING/ORIENTATION (If applicable) Anyone entering a District substation for any reason is required to receive this training on an annual basis.  Contact Safety and Health Dept. on how to become authorized. 

DISTRICT PERMITS/CLEARANCES 

Permits/clearances must be obtained for the following operations BEFORE work begins: 

X

 

ENERGY ISOLATION (Lockout /Tag out) WAC 296‐45‐175  Required for work on any equipment that may have live or stored energy that could cause injuries or property damage if started accidentally or released.  When at Hydro Projects do not shut off or make connections to live electric, gas, air, water, or process lines without the prior authorization from the Control Room Operator.  Work with your Project Manager to identify the specific orientation for your work activities.   

X

 

CONFINED SPACE PERMIT – WAC 296‐809 A permit is required for any workers who enter Permit Required Confined Spaces.  Confined spaces must be cleaned, purged, and ventilated before employees are allowed to enter them.  Life lines, harnesses, and supplied air respirators may be required.  An attendant will be required for all permit confined space entries.  All work in confined spaces must meet WAC requirements and employees must be properly trained in accordance with this regulation. Contractors entering confined spaces must submit a confined space program.  

X

 

HOT WORK PERMIT WAC 296‐24‐69503 Required for all open flame, spark‐producing, or heat producing activities on‐site.  This includes, but is not limited to:  welding, cutting, grinding, soldering, brazing, and heat producing chemicals.  Control Room must be notified before work begins.  

Other permits may be required for special procedures or unusual work conditions.  Your District contact will coordinate permit requests for the specific area where the work is being performed.  

X

 

REGULATORY COMPLIANCE  All federal, state, local and District safety, health and environmental regulations and rules must be observed by all employees of outside contractors.  Contractor supervisors shall ensure that all of their employees are aware of and comply with rules and regulations.  VIOLATORS WILL NOT BE PERMITTED TO WORK AT DISTRICT FACILITIES 

Page 57: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Appendix 013524-1, Example Contractor Safety Orientation Checklist Exhibit S – Specifications Bid 18-67

Revised:  August 29, 2017    Appendix 013524-1, Example Contractor Safety Orientation Checklist 28 MVA, 115/12.47 kV Substation Power Transformers    Page 6 of 6 

X

 

ADDITIONAL INFORMATION/REQUEST: Dam operations can be changed or disrupted in many ways with large unintended results. Therefore, it is critical for you and your employees to occupy only those areas assigned to you and to avoid disrupting or operating any equipment, circuits, or controls that are outside your scope of work.  

If you notice anything that appears to be damage to the dam, or to the equipment used to operate the dam (e.g. a spillway gate), please notify your District contact, immediately.  

If, during your time working on the dam, you notice what appear to be negative changes in the dam’s condition, please notify your District contact, immediately.  Examples of such changes are increases in the amount of leakage or seepage, progressive cracking in concrete, or offsets in linear structures. 

Please Remember:  

 Route original document or electronic copy once completed to the Safety/HR Dept. Admin. 

Page 58: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Appendix 013524-2, Example Job Safety Analysis Form Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Appendix 013524-2, Example Job Safety Analysis Form Page 1 of 1

JOB SAFETY ANALYSIS FORM

Job Description: Various; See Activity/Job Date of Analysis: 00/00/0000

ACTIVITY/JOB HAZARD Recommended Action/Procedure

1. Mobilization/Excavation

1. Large Equipment

1. Back-up warning alarm 2. Extra awareness of equipment

location 3. Safety cones, warning tape to keep

unauthorized people out

2. Form/Rebar

1. Power tools

1. Use GFCI on all power tools 2. Do not remove guards 3. Safety goggles when cutting or

grinding 4. Mushroom cap all rebar 5. Wear gloves

3. Concrete

1. Concrete trucks 2. Concrete hazards

1. Back up warning alarm 2. Proper flagging 3. Wear proper gloves 4. Safety glasses 5. Get help when lifting heavy loads;

use proper lifting techniques

4. Framing

1. Power tools 2. Sharp objects 3. Heavy loads

1. Use GFCI on all power tools. 2. Wear gloves; watch pinch points 3. Don’t lift over 50lbs w/o help; use

proper lifting techniques

END OF ANALYSIS

Submitted by: ___________________ Read & Understands: _____________________ Contractor (sign and date) Project/Construction Manager (sign and date) Read & Understands: ___________ Read & Understands: _____________________ Inspector (sign and date) Other: (sign and date)

Page 59: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Appendix 01 35 24-3 Page 1 of 1

Appendix 01 35 24-3, Example Crane/Hoisting Pre-Lift Plan

This form is to be filled out by the crane operator and/or rigging supervisor for all lifts. Lifts greater than 75% but not exceeding 90% of rated capacity for the boom length/radius combination to be used. Superintendent or Project Manager signature is required. Lifts exceeding 90% require an Engineered Lift Plan.

Date: Time: Temp: Wind Speed:

Job Description:

Crane Make: Counterweight:

Boom Length: Boom Type:

No. Parts Line: Block:

Jib Length: Jib Type:

LOAD SUMMARY: MAX RADIUS:

Load:

Main Block:

Load Line:

Jib:

Ball:

Rigging:

Slings: Each Dia. Length = Lbs

Each Dia. Length = Lbs

Each Dia. Length = Lbs

Shackles: Each Pin Dia. Capacity = Lbs

Each Pin Dia. Capacity = Lbs

Each Pin Dia. Capacity = Lbs

Spreaders & Misc. Lbs

Total Erection Load: = Lbs

ADDITIONAL REQUIREMENTS:

Yes No Ensure the proper chart is selected for the configuration used (i.e.: outriggers, on rubber, 360 degrees). Yes No Crane must be level and set on well-compacted material. Yes No For cold weather lifts, de-rate the crane capacity as per the manufacturers specification (do not include wind

chill). Yes No When calculating jib % capacity, the jib weight can be deleted from the total load. Yes No Reviewed by Rigging Supervisor when required

Max Radius: ________________(ft) Crane Capacity: ______________(lbs) Jib Capacity: _________ lbs.

% Capacity = Total Load = ________ x 100 = ________ %

Crane or Jib Capacity

Supervisor/Foreman (Print Name) Signature Date

Operator (Print Name) Signature Date

Superintendent/Project Manager (Print Name) Signature Date

Page 60: TECHNICAL SPECIFICATIONS 28MVA, 115/12.47 kV Substation

Exhibit S – Specifications Bid 18-67

28 MVA, 115/12.47 kV Substation Power Transformers Appendix 01 35 24-4 Page 1 of 1

Appendix 01 35 24-4, Example Hot Work Permit

CHELAN COUNTY PUD - HOT WORK PERMIT Revised August 2012

All temporary operations involving open flames or producing heat and/or sparks require a Hot Work Permit. This includes, but is not limited to: brazing, cutting, grinding, soldering, thawing, welding and work with heat producing chemicals (epoxies). etc.

INSTRUCTIONS

1. Verify precautions listed at right or do not proceed with work.

2. Complete the hot work permit and forward the top copy to your supervisor.

3. Post the bottom copy in the vicinity of the work.

The above location has been examined, the precautions checked on the checklist have been taken to prevent fire and it is safe to begin hot work procedures.

SIGNED:

(Person Doing Hot Work)

TIME WORK STARTED:

Date Time AM/PM

TIME WORK ENDED:

Date Time AM/PM

PERMIT EXPIRES:

Date Time AM/PM

THIS PERMIT VALID FOR NO MORE THAN

24 HOURS!

DATE WORK ORDER #

LOCATION (BUILDING & FLOOR)

BRIEF DESCRIPTION OF WORK

NAME OF PERSON DOING WORK

SIGNED:

(Fire Watch)

HOT WORK CHECKLIST Sprinklers and hose streams serviceable/operable Hot work equipment in good condition (leads, cords,

torches, etc.) Fire extinguisher available and charged. Smoke alarms disabled if necessary. Control room/system operations/facility management

contacted. REQUIREMENTS WITHIN 35 FEET OF WORK

Dust, lint, debris, flammable liquids and oil/oil deposits removed

Explosive atmosphere in area eliminated. Combustible floors (wood, tile) wet down or covered with

fire blankets Flammable and combustible material removed where

possible. Otherwise, materials are protected with fire blankets, guards or metal shields.

All floor and wall openings covered. Areas beneath hot work are protected.

WORK ON WALLS OR CEILINGS Combustibles/flammables moved away from other side

of wall. WORK IN CONFINED SPACES

Confined space cleaned of all combustibles (grease, oil, vapors). See Coatings & Lead- Heavy Metals below.

Containers purged of flammable liquids/vapors. Follow confined space procedures.

FIRE WATCH/HOT WORK AREA MONITORING Fire watch will be provided during and for 30 minutes

after work, including lunch and coffee breaks. Fire watch is supplied with an extinguisher. Fire watch is trained in the use of extinguishing

equipment and is familiar with emergency evacuation procedures.

Fire watch may be required for opposite side of walls, and above or below floors and ceilings.

COATINGS All coated surfaces must be considered hazardous until

proved otherwise. No grinding, welding or cutting is permitted on coated surfaces until the coating has been removed using lead binding chemical methods (no Methylene Chloride) or the use of the DCM Needle Scaler or low speed sander with HEPA VAC attachment.

LEAD – HEAVY METALS Poured Sockets, Soldering of Copper Piping, Soldering,

Silver Soldering, Lead/Oakum Pipe Joints. These tasks are known to pose health risks & follow CCPUD Respirator Guidelines. Lead Awareness training must be followed.

WELDING CCPUD Respirator Guidelines must be followed.

VENTILATION Smoke Eater, Negative Air Machine, etc.