technical support guidelines module 3 - atoms for peace ... · technical support guidelines module...
TRANSCRIPT
IAEA International Atomic Energy Agency
Technical Support Guidelines Module 3
IAEA Training Workshop on Severe Accident Management Guideline Development using the IAEA SAMG-D Toolkit
Jeff Gabor
IAEA
Technical Support Guidance
• What are TSGs? • Evolution of TSGs • Is there a regulatory driver? • Why are TSGs needed? (additional expertise /
Fukushima) • Relationship of TSGs to Plant Procedures • What are the key elements of TSGs? • Who implements them? – Responsibilities • Calculational Tools • TSG Development • Summary
2
IAEA
TSG Purpose
• Specify engineering support activities • Implement by the Emergency Response
Organization (ERO) staff • Directly assist the control room operating
crew and TSC evaluators and decision makers
• Support execution of Emergency Operating Procedures (EOPs) and the Severe Accident Guidelines (SAGs).
3
IAEA
TSG Historical Evolution • Severe accident closure 1992 – NUMARC 92-01 • BWR products
• TSGs were implemented to varying levels of detail and rigor (1996-1998) examples of full implementation include: • DAEC • Fermi • Columbia • Fitzpatrick • NMP
BWROG Generic Products
Plant Specific Products
EPGs EOPs SAGs SAGs TSGs TSGs
IAEA
TSG Development
• There currently is no rule, regulation, or generic letter specifying the contents of accident management documents.
• Documents that are referenced: • NRC SECY 88-147 - 1988 • NRC SECY 89-012 - 1989 • NUMARC 91-04 - 1992 • NRC Response to PWR AMGs - 1994 • NRC Presentation Slides from the NEI Workshop - 1994
• Concept Tested: DAEC in 1994 hosted a full drill scenario with U.S. and foreign observers to demonstrate the feasibility of the TSG concept – result successful demonstration
5
IAEA
TSG Development (cont’d)
• BWROG developed EPG/SAG Rev. 3 • Broadened the decision-making requirements in SAG • Specifically, BWROG noted the value of the TSGs to
support this broader functional level decision-making • Rev. 3 of BWROG SAGs focused decision making
on functional determination not strictly “observed symptoms”. This requires greater cognizance of the accident progression, its identification, and use of calculational aids
• BWROG has developed a simplified TSG to support EPG/SAG Rev. 3
6
IAEA
TSG Development (cont’d)
• BWROG TSGs for use with Rev. 3 EPG/SAG are formulated to address decision-making and its inputs for both: • EOPs • SAGs
• NTTF Recommendation 8 (Onsite Emergency Response Capabilities) has been rolled into a consolidated rulemaking with SBO response
• This presentation highlights key decisions in the SAGs that could be optimized by TSG inputs
7
IAEA
Impetus for TSGs from Fukushima Daiichi Accident Insights
• Data input is critical to support decision-making • Trending assists in prioritization • Understanding severe accident phenomena and
timelines assist in recognizing critical events • System operability assessment
• Allows projection of time to future needs • Identifies support systems necessary
• Interpretation of SAGs in light of current and projected plant conditions -- Examples: • Functional situations (containment impaired) • Core debris may not be retained in RPV • RPV breached
8
IAEA
Recommendation 8 from NTTF on Fukushima: On-Site Emergency Response Capabilities (DRAFT)
• Reinforce and be consistent with site command and control structure • NEI 13-06: Enhancements to emergency response capabilities for
beyond design basis accidents and events • NEI 14-01: Development of Mitigation and Management Guidelines
for Severe Accidents and Extreme Events • NRC: On-site Emergency Response Capabilities
• EOPs • SAMGs • SAMG support procedures • EDMGs
However, there is no specific reference to TSGs in any of these documents
9
* Note Rec 8 has the following: Section 4.5 also makes open-ended references to the use of simulators and enhancement of simulators including the following:
“Licensees’ plant reference simulators should be further developed to simulate a severe accident by simulating the response of accident monitoring instrumentation during severe accidents”.
IAEA
Why are TSGs Needed?
• BWROG EPG/SAG Rev. 3 has a large number of decisions that need to be made
• Many decisions have introduced a substantial degree of Engineering evaluation to optimize the decisions given the potential competing effects
10
IAEA
Critical Decision-Making Junctures in EPG/SAG: Examples
• EOPs • Adequate core cooling • Anticipatory containment venting • RCIC survivability • Emergency Depressurization
• Limited when turbine driven systems are all that is available (Select pressure band)
• Use of alternate systems • RPV water level above TAF • Transition to SAGs
11
IAEA
Critical Decision Making Junctures in EPG/SAG: Examples (cont'd)
• SAGs • RPV breach • RPV injection flow > MDRIR
• MDRIR = Minimum Debris Retention Injection Rate • Pressure suppression required • RPV water level above BAF • DW sprays can be initiated and controlled
• Initiation • Flow Rate • Termination
• DWSIL curve no longer included in SAGs • DWSIL = Drywell Spray Initiation Limit
12
IAEA
• Venting • Initiation • Pathway selection • Control band specification • Coordination with containment flood • Coordination with RPV breach
• Core debris can be maintained within RPV • Core debris cannot be maintained within RPV • Containment flooding
• Decision to initiate • Coordination with RPV pressure control • Coordination with containment venting
13
Critical Decision Making Junctures in EPG/SAG: Examples (cont'd)
IAEA
• Containment water level control band • Containment pressure level control band • Water management
• Injection • Discharge
• RPV venting • Default actions given loss of indication
14
Critical Decision Making Junctures in EPG/SAG: Examples (cont'd)
IAEA
RPV Breach Signature Flow Chart
15
RelationshipEOP.pptx 10-07-2015
Relationship: Accident Management Guidelines and Plant Procedures
• Establish communications • Perform notifications • Actions to shutdown the reactor • Actions to inject into the reactor • Damage assessment • Transition to other Ops Procedures when
ERO manned
Extreme Damage Mitigation Guidelines (EDMGs)
Abnormal Operating Procedures
• Integrated Response Plan for Large Scale events
Emergency Management Guidelines (EMGs)
• SAG 1 – RPV and Primary Containment Flooding Severe Accident Guideline
• SAG 2 – Containment and Radioactivity Release Severe Accident Guideline
• SAG 3 – Hydrogen Control Guideline
Severe Accident Management Guidelines (SAMGs)
• EOP 1 – RPV Control • EOP 2 – Primary Containment Control • EOP 3 – Secondary Containment Control • EOP 4 – Radiation Release Control • ALC – Alternate Level Control • ED – Emergency RPV Depressurization • ATWS RPV Control • RPV/F – RPV Flooding
Emergency Operating Procedures (EOPs)
• 100 – Rod Insertion Procedures (RIPs) • 200 – EOP Defeats • 300 – Supplemental Emergency
Procedures (SEPs) • 400 – Alternate Injection Procedures (AIPs) • 500 – EOP Flowchart Supporting CALCs • 600 – EOP Flowchart Supporting Graphs
(GRAPHs) • 700 – Severe Acc Mgmt Procedures
(SAMPs)
EOP/SAG Support Procedures
• Control Parameter Assessment Guideline (CPAG)
• System Status Assessment Guideline (SSAG)
• Plant Status Assessment Guideline (PSAG) • EOP/SAG Action Assessment Guideline
(EAAG)
Technical Support Guidelines
16
IAEA
Structure of Technical Support Guidelines (TSGs)
Guideline Purpose Control Parameter Assessment Guideline (CPAG)
Identify best estimate value for each EOP and SAG control parameter
Plant Status Assessment Guideline (PSAG)
Forecast the future values of control parameters
System Status Assessment Guideline (SSAG)
Establish operability and reliability of plant systems
EOP/SAG Action Assessment Guideline (EAAG)
Priority and timing for actions directed by the EOPs/SAGs
17
IAEA
Products and Supporting Elements of TSGs
18
IAEA
CPAG: Monitor Key Control Parameters Using Available Instrumentation
ERIS
PIS Number
Readout
Range
Power Supply
Isometric
Other Limitations and Adjustments
Sensor Location
Transmitter Location
Environmental Limitations [1]
Temp. Limit (°F) Reading °F Adjusted °F
PRIMARY PT#259 T50N404A T50-R800A
PT#11 H11-P601
0-400°F (SD-2861-2B)
TORUS Temp. DIV I AZ 2700
RB/Bsmnt Grid 2700 El. 551’04”
365
T50N405A T50-R800A PT#12 H11-P601
0-400°F (SD-2861-2B)
TORUS Temp. DIV I AZ 00
RB/Bsmnt Grid 00 El. 551’04”
365
T50N405B T50-R800B PT#12 H11-P602
0-400°F (SD-2861-2A)
TORUS Temp. DIV II AZ 900
RB/Bsmnt Grid 900 El. 551’04”
365
PT#111 T23N001 T23-R800 CH 1 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 220
DW Grid 220 El. 551’01”
365
PT#112 T23N002 T23-R800 CH 2 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 670
DW Grid 670 El. 556’01”
365
PT#112 T23N003 T23-R800 CH 3 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 1120
DW Grid 1120 El. 556’01”
365
PT#4 T23N004 T23-R800 CH 4 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 1570
DW Grid 1570 El. 556’01”
365
PT#115 T23N005 T23-R800 CH 5 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 2020
DW Grid 2020 El. 556’01”
365
PT#116 T23N006 T23-R800 CH 6 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 2470
DW Grid 2470 El. 556’01”
365
PT#117 T23N007 T23-R800 CH 7 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 2920
DW Grid 2920 El. 556’01”
365
PT#118 T23N008 T23-R800 CH 8 H11-P601
0-100°F (I-2860-9)
TORUS Wtr. Temp. AZ 3370
DW Grid 3370 El. 556’01”
365
ALTERNATE E11N004A E11-R601A
Red Pen H11-P601
0-400°F
RHR Ht. XGHR “A” Inlet Temp. DIV I
365
E11N004B E11-R601B Red Pen H11-P602
0-400°F
RHR Ht. XGHR “B” Inlet Temp. DIV II
365
19
Example: Torus Water Temperature
IAEA
CPAG Trending Example Torus Temperature Forecasting
20
IAEA
Example: Torus Level Forecasting (Wide Range)
21
IAEA
Example: Containment Water Level Forecasting
22
IAEA
System Status Assessment Guideline (SSAG): Toolbox of Accident Management Actions to Prolong RCIC Operation Under ELAP Conditions: Pinch Points
23
RCIC Critical “Pinch Point” Accident Management Actions Maintain DC Power • Perform DC load shed
• Install portable generator
• Recover AC power (offsite/EDG)
• Cross tie TSC EDG
Maintain Adequate Lube Oil Cooling via the Working Fluid
• Prefer CST as the suction source (see Attachment YA)
• Replenish CST if necessary
• Cool torus
• Anticipatory vent to minimize the maximum torus temperature
Maintain Adequate RPV Pressure • Maintain adequate steam pressure band when depending on RCIC for adequate core cooling
Maintain High Turbine Speed • Maintain high RPMs on turbine to ensure adequate lubrication if high temperature water source is being used. (>3500 RPM at suction temperatures >200°F)
Maintain Adequate NPSH • Control torus water level
• Make up for vented non-condensables with non-combustibles
• Minimize torus temperature increase
IAEA 24
RCIC Critical “Pinch Point” Accident Management Actions Ensure Adequate Room Cooling and Prevent High Room Temperature Trips
• Open door on the RCIC room
• Provide portable gas powered fan
• Bypass high room temperature trips
Prevent High Steam Line Temperature Trip
• Insert temperature isolation interlock DEFEAT 18
Prevent RCIC Room Flooding • ARP 1C14A<A-4> and, <B-4> (above max safe, above max normal, respectively) direct monitoring and refer operators to EOP-3.
• EOP-3 to verify that all available sump pumps are operating to lower water level.
(There is no installed equipment that could be used to limit flooding or arrest the rate of water level rise besides the sump pump.)
Prevent High Turbine Exhaust Pressure Trip
• Provide a set point change that permanently increases the high pressure trip to ~100 psig as recommended by GEH
Implement Authorized Bypasses of RCIC Protective Isolations and Trips
• Bypass the high RPV water level trip (DEFEAT 8)(1)
• Bypass the low RPV pressure isolation (DEFEAT 1)
• Bypass the high room temperature isolation (DEFEAT 18)
Note to Table: (1) For HPCI this is Defeat 7; in addition, the high torus water level suction transfer is Defeat 2.
System Status Assessment Guideline (SSAG): Toolbox of Accident Management Actions to Prolong RCIC Operation Under ELAP Conditions: Pinch Points (cont'd)
IAEA
SSAG System Indications: Toolbox of Information Inputs to Prolong RCIC Operation During SBO
25
RCIC Functional Concern Indications Functional Alternatives Notes
Loss of Control Power
• Annunciator 1C04C<B-9>
• No battery charger operating for 125 VDC Div 2
• Restore battery charger per OI 302
• Restore battery charging using TSC Generator per AOP 301.1 Attachment 10
• Restore Battery Charging using SAMP 704
• Operating RCIC manually using SAMP 703
• Emergency SRV Operation using Portable DC – SAMP 707
High Oil Temperature
• Annunciators(4) 1C04C<B-5> and 1C04C<B-7>
• Switch to CST • Lower torus temperature
(3)
High Room Temperature
• Annunciator(5) 1C04B<B-4>
• Bypass high temperature trip per EOP Defeat 18
• Open Door 219 • Establish Portable ventilation
(3)
High Exhaust Back Pressure
• Annunciator 1C04C<B-8>
• Computer Point B511
• Vent containment • Jumper out the isolation
signal (not yet defined)
(1)
Low Net Positive Suction Head
• Annunciator(6) 1C04C<D-5>
• Close containment vent • Add non-condensable • Add water to torus
(3)
IAEA 26
SSAG System Indications: Toolbox of Information Inputs to Prolong RCIC Operation During SBO (cont’d)
RCIC Functional Concern Indications Functional Alternatives Notes
High Suppression Pool Temperature
• Use anticipatory vent to limit suppression pool temperature
• Add water to torus
(3)
Low Condensate Storage Tank Level
• Annunciators(7) 1C06C<B-8>, <B-9>, C-8>, <C-9>
• Annunciator(8) 1C03C<D-3>
• Transfer suction to Torus per OI 150
• Replenish CST inventory using SAMP 710
• Transfer hotwell inventory to CST per OI 644(9)
(3)
High Bearing Vibration
(10) (3)
Turbine Over Speed Trip
• Annunciator 1C04C<A-5>
• Need to avoid the mechanical overspeed because local reset is required.
(3)
High Water Level in RCIC Room(11)
• Annunciators 1C14A<A-4>, <B-4>
• Use portable sump pump to remove water (not yet defined)
(3)
High Torus Water Level
• Annunciator 1C03B<D-9>
• Discharge water to radwaste
• Discharge water to over flow (not yet defined)
(3)
IAEA
RCIC Functional Concern Indications Functional Alternatives Notes
Low Torus Water Level
• Annunciator 1C03B<D-9>
• Add water to torus (3)
Adequate Turbine Speed
• SI-2284 (RCIC Turbine Speed)
• Increase RPMs if suction temperature increases [Y-1]
(2)
HCL • RPV pressure • Torus water
temperature
• Open ADS SRVs • Open MSL drains to
condenser
PSP • Containment pressure
• Torus water level
• DW sprays • Open ADS SRVs • Open MSL drains to
condenser
DW/T • DW temperature • DW sprays
27
SSAG System Indications: Toolbox of Information Inputs to Prolong RCIC Operation During SBO (cont’d)
IAEA
Responsibilities of the Accident Management Team (AMT)
Accident Management Team (Proposed)
Responsibilities Primary Backup
Parameter Monitor and Trending (CPAG and PSAG)
• Trending Control Parameters • Estimate RPV Injection • Forecasting • Control Parameter Assessment • Instrument Assessment • System Status Assessment
Technical Analysis (SSAG and EAAG)
• Confirm Rx Shutdown • Identify RPV Breach • Identify Fuel Damage • Estimate Release Rates
• Optimize Timing of EOP/SAG Actions
Operations Liaison (EAAG) • Follow SAGs • Decision Making • Forecast Actions • Identify Transition to SAGs • Determine SAG Branch • Assess Containment Flood Implications • Identify SAG steps with Flexibility • Optimize Timing of EOP/SAG Actions
― Containment Flooding ― Torus Spray ― DW Spray ― Venting ― Boron Initiation ― Alternate Room Cooling
• Prioritize System Restoration
• H2 Control Method Assessment
• Anticipate Actions
28
IAEA
EAAG: Operations Liaison - Integrator
29
SYSTEM STATUS
IAEA
Example Calculational Tools
• Containment water volume • Containment overview – wall chart • Vent checklist – wall chart Other examples included in generic BWROG TSG: • MPSPCWL change as function of
temperature • RPV Water level correction vs. pressure • Reactor power vs. Rx pressure for SRV or
TBV
30
IAEA
Calculation Tools: Primary Containment Level Determination
31
IAEA
RPV Volume Versus Elevation (Example)
32
IAEA
Parameter Display Figure
33
Elevation Water Volume
Level
IAEA
Who Implements TSGs? Accident Management Team in TSC
34
IAEA
TSG Development
35
Plant SpecificTSG
Development Calculational Tools
IAEA
Emphasis on Training
• Assistance in EOP/SAG implementation requires knowledge of: • Plant Procedures • Plant Responses • Available mitigative equipment and actions • Limitations on actions • Accident phenomena • Accident progression signatures • Accident progression timing
36
IAEA
Areas of Concern for TSGs
• Development costs • Maintenance of the documentation
• Guidance • Data tables • Drawings
• Staffing of TSC/AMT • Training on the TSGs • Implementation proficiency • Fidelity of testing
• Table top • Simulator • PC based/Severe accident case driven
37
IAEA
Insights
• TSC appears to be a desirable location to be implemented by trained Engineers/SROs
• TSGs can be used to: • Set priorities for mitigative actions under
conditions of limited resources • Identify timing of mitigative actions • Select systems/pathways/sources to be used for:
• Vent • RPV injection • Containment injection
38
IAEA
Insights (cont’d)
• Monitor portable equipment deployment and alignment (track progress, timing, resources compared with accident progression)
• Address issues as a result of containment impairment • Leakage locations • Loss of water • Hydrogen release and impacts • Lost access • Management of water injected • Compromised SAG specified actions:
• Inject from internal sources • Flood containment
39
IAEA
Summary
• TSGs support implementation of complex strategies
• TSGs have been developed by BWROG • There is no regulatory requirement for TSGs • Operating accident at Fukushima identified
potential benefit of additional guidance on degraded plant conditions
• TSGs include • Control parameter monitoring • Trending of control parameters • System readiness evaluation • Assessment of strategies and prioritization
40
IAEA
Questions?