technology maturation plan for the management of … 1 shows the major operations (and components)...

31
CHPRC-03403 Revision 0 Technology Maturation Plan for the Management of the Cesium and Strontium Capsules Project (W-135) Prepared for the U.S. Department of Energy Assistant Secretary for Environmental Management Contractor for the U.S. Department of Energy under Contract DE-AC06-08RL14788 P.O. Box 1600 Richland, Washington 99352 Approved for Public Release; Further Dissemination Unlimited

Upload: phamdung

Post on 17-Mar-2019

212 views

Category:

Documents


0 download

TRANSCRIPT

CHPRC-03403Revision 0

Technology Maturation Plan for the Managementof the Cesium and Strontium Capsules Project(W-135)

Prepared for the U.S. Department of EnergyAssistant Secretary for Environmental Management

Contractor for the U.S. Department of Energyunder Contract DE-AC06-08RL14788

P.O. Box 1600 Richland, Washington 99352

Approved for Public Release; Further Dissemination Unlimited

CHPRC-03403Revision 0

EDC#: ECR-18-000163

Technology Maturation Plan for the Management of the Cesium andStrontium Capsules Project (W-135) Project No: W-135 Program/Project: WFMP

CH2M HILL Plateau Remediation Company

Date PublishedJanuary 2018

Prepared for the U.S. Department of EnergyAssistant Secretary for Environmental Management

Contractor for the U.S. Department of Energyunder Contract DE-AC06-08RL14788

P.O. Box 1600 Richland, Washington 99352

Release Approval Date Release Stamp

Approved for Public Release; Further Dissemination Unlimited

Jan 25, 2018DATE:

CHPRC-03403Revision 0

TRADEMARK DISCLAIMERReference herein to any specific commercial product, process, or service bytradename, trademark, manufacturer, or otherwise, does not necessarilyconstitute or imply its endorsement, recommendation, or favoring by theUnited States Government or any agency thereof or its contractors orsubcontractors.

This report has been reproduced from the best available copy.

Printed in the United States of America

Total pages: 31

CHPRC-03403, Rev. 0

i

Contents

1 Introduction ......................................................................................................................................... 1

1.1 Purpose of the Project ................................................................................................................... 1

1.2 Purpose of the TMP ...................................................................................................................... 2

2 Technology Assessments of the Project ............................................................................................. 2

2.1 Summary of Previous Technology Readiness Assessment(s) ...................................................... 2

2.1.1. MCSC-TRSA ........................................................................................................................ 3

2.1.2. DOE-TRA ............................................................................................................................. 3

2.2 Technology Heritage ..................................................................................................................... 3

2.3 Current Project Activities and Technology Maturation ................................................................ 4

2.4 Management of Technology Maturity .......................................................................................... 4

3 TMP ...................................................................................................................................................... 4

3.1 Development of Technology Maturation Requirements ............................................................... 4

3.1.1. MCSC-TRSA ........................................................................................................................ 4

3.1.2. DOE-TRA ............................................................................................................................. 5

3.2 Life-Cycle Benefit ........................................................................................................................ 5

3.3 Specific TMPs ............................................................................................................................... 5

3.3.1. MCSC-TRSA CTE No. 2A_2B ............................................................................................ 5

3.3.2. DOE-TRA CTE #1, #2 and #4 .............................................................................................. 6

4 Plan to Mature System Integration ................................................................................................... 7

5 Technology Maturity Schedule .......................................................................................................... 7

6 Summary Technology Maturity Budget ........................................................................................... 7

7 References ............................................................................................................................................ 8

Attachments

A MCSC-TRSA Technology Elements Spreadsheet…………………………………….………… A-1 B DOE-TRA Technology Elements Spreadsheet……………………………………….…………. B-1 C DOE-TRA Identified Gaps Spreadsheet………………………………………………………… C-1 D DOE-TRA Functional System Verification and Design Activities……………………………… D-1

Figures

Figure 1. MCSC Project System Components and Major Operations for CSS Loading ............................. 2

Tables

Table 1. DOE-TRA CTE Maturation Schedule ........................................................................................... 7

CHPRC-03403, Rev. 0

ii

Terms

CoC certificate of compliance

CD critical decision

CSA Capsule Storage Area

CSS Cask Storage System

CTE critical technology element

DCSS dry cask storage system

DOE Department of Energy

DSA documented safety analysis

DTS Dry Transfer System

EM Environmental Management

ISI in service inspection

MCSC Management of the Cesium and Strontium Capsules

NPP nuclear power plant

SIP Shielded Indexer Plate

SNF spent nuclear fuel

TE technology element

TMP technology maturation plan

TRA technology readiness assessment

TRL technology readiness level

TRSA technology readiness self-assessment

TSC Transportable Storage Canister

UCS Universal Capsule Sleeve

VCC Vertical Concrete Cask

VCT Vertical Cask Transporter

WESF Waste Encapsulation and Storage Facility

CHPRC-03403, Rev. 0

1

1 Introduction 1.1 Purpose of the Project The Management of the Cesium and Strontium Capsule (MCSC) Project is being executed in accordance with the requirements of DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets. DOE O 413.3B provides the programmatic and project direction needed to successfully deliver projects within their original performance baseline, cost and schedule, and the capability to meet mission performance and safety goals and considerations. This Technology Maturation Plan (TMP) was prepared in accordance with the requirements of DOE O 413.3B.

The Waste Encapsulation and Storage Facility (WESF) is located in the 200 East Area of the U. S. Department of Energy (DOE) Hanford Site north of Richland, Washington. WESF stores 1,312 cesium capsules, 23 Type-W capsules (overpacked cesium capsules), and 601 strontium capsules underwater in pool cells. The capsules are currently managed as mixed, high-level waste and are regulated under the Resource Conservation and Recovery Act of 1976.

The MCSC Project will provide the capability for retrieval of the cesium and strontium capsules from WESF pool cell storage and placement into a Cask Storage System (CSS) as an interim storage configuration pending final disposition.

The CSS is expected to consist of the following major components: Transportable Storage Canister Basket, Transportable Storage Canister (TSC), and Vertical Concrete Cask (VCC). In addition, Universal Capsule Sleeves (UCS) will be fabricated to hold the capsules and various pieces of equipment and tools will be procured to perform capsule loading and transfer activities. These components and equipment are typical of standard Dry Cask Storage System (DCSS) technology and are routinely employed in the Nuclear Power Plant (NPP) industry at Independent Spent Fuel Storage Installations for Spent Nuclear Fuel (SNF) interim storage.

The MCSC Project scope includes the following three major activities to prepare for transfer and placement of the cesium and strontium capsules, currently stored at WESF, into an interim storage configuration:

1. Acquire storage and transfer systems, and associated equipment necessary to support retrieval, loading, and transfer of the capsules to extended storage – (CSS scope)

2. Perform WESF modifications necessary to support retrieval, loading, and transfer of capsules to the Capsule Storage Area (CSA) from WESF – (WESF Modifications scope)

3. Construct the CSA, including storage pad, fencing, lighting, and road access to the CSA – (CSA Construction scope)

Demonstration of MCSC Project readiness will be followed by capsule transfer operations, including retrieval from existing storage, loading, transfer to the CSA, and emplacement into a dry-storage configuration for an extended period of time (300 years).

Figure 1 shows the major operations (and components) to be performed to load the CSS once the capsules are retrieved from their current storage configuration:

CHPRC-03403, Rev. 0

2

Vertical Concrete Cask (VCC) Transportable Storage Canister (TSC) Basket

Transportable Storage Canister (TSC)

Universal Capsule Sleeve

(UCS)

Dry Transfer System (DTS)

Figure 1. MCSC Project System Components and Major Operations for CSS Loading

1.2 Purpose of the TMP This TMP outlines the activities to be performed in response to recommended actions identified in the [Ref. 1] DOE Technology Readiness Assessment (DOE-TRA) report. It provides the strategy to mature Critical Technology Elements (CTE) to a Technology Readiness Level (TRL) 6. It also outlines the activities to be performed in response to recommendations from the MCSC Technology Readiness Self-Assessment (MCSC-TRSA) [Ref. 2].

The TMP is a living document and will be periodically reviewed and revised when required to ensure that development and maturation activities successfully lead to a TRL 6 status.

2 Technology Assessments of the Project DOE O 413.3B [Ref. 3] states that TRAs are used as a management tool to reduce the technical and cost risks associated with the introduction of new technologies. The TRA is an assessment of how far project technology development has proceeded (maturity) and its readiness for insertion into the project design and execution schedule. The DOE-Environmental Management (EM) TRA/TMP Guide [Ref. 4] recommends that projects conduct a self-assessment of technology readiness (TRSA) prior to an independent TRA to help inform the project on technology status and to assist DOE with the independent TRA.

2.1 Summary of Previous Technology Readiness Assessment(s) In support of Critical Decision (CD) -1, both the MCSC-TRSA and the DOE-TRA activities were performed during CY 2017. The MCSC-TRSA was performed by MCSC Project Engineering personnel and the DOE-TRA by a team consisting of subject and technical matter experts from within the complex, to include the Office of the Chief Engineer in the DOE-EM. Recommended actions from both assessments centered primarily on activities at the capsule loading stage. Additional recommendations from the DOE-TRA addressed concerns with maturity of the thermal and heat transfer design.

1. Loading of capsules into the UCS

2. Transfer of the loaded UCS to the TSC

3. Inserting the loaded UCS into an already assembled TSC Basket/TSC/VCC staged in the Truck Port.

4. Transfer of the loaded CSS to the CSA pad (CSA).

CHPRC-03403, Rev. 0

3

Maturity gaps identified in project technology, and system design and analysis, are addressed in this TMP. Details of both the MCSC-TRSA and DOE-TRA can be found in the [Ref. 2 and 1] reports, respectively. The following summarizes the two assessments:

2.1.1. MCSC-TRSA Reference 5 provides a detailed description of the overall process that will be used for transfer of the capsules and placement into dry storage. Based on this description, major project activities and functions were determined from which nineteen individual Technology Elements (TE) were identified; a brief description of each is provided in Attachment A. Three of the nineteen TEs were determined to be CTEs as follows:

1. CTE No. 2A_2B: UCS and Equipment for Welding, Drying, Inspection and Testing (TEs 2A and 2B were combined for CTE evaluation)

2. CTE No. 2C: Capsule Cooling Equipment

3. CTE No. 5A: Temperature Modeling and Capsule Temperature Monitoring

The TRSA-CTEs were evaluated against both TRL 4 and TRL 6 calculator criteria and found to satisfy the requirements with exception of CTE No. 2A_2B. This CTE failed to meet Criterion 12 (from the TRL 4 Calculator [Ref. 4]): Technology demonstrates basic functionality in simulated environment. It was concluded that this CTE has not been sufficiently demonstrated in the relevant environment and was therefore assessed a TRL 4 (-) level.

The [Ref. 2] report concluded that a TMP is needed to mature CTE No. 2A_2B to a TRL 6 level prior to final design.

2.1.2. DOE-TRA The DOE-TRA Team reviewed the MCSC-TRSA approach to organizing the project activities / functions and identification of TEs but took a different approach by grouping the nineteen TEs into four functional systems as shown in Attachment B. These functional systems were evaluated against the [Ref. 4] CTE calculator criteria and three of the four systems (TE #1, #2 and #4) were identified as CTEs:

1. CTE #1: Capsule Loading System

2. CTE #2: UCS Insertion into TSC and Cask

3. CTE #4: Extended Storage at CSA

The DOE-CTEs were evaluated against the [Ref. 4] TRL 3 and 4 calculator criteria and found to be at a TRL 3 (-). Based on the [Ref. 1] report, these functional systems have not yet been either sufficiently demonstrated and / or some design analysis (thermal analysis) is required to move them to a TRL 4 and 6 level.

The [Ref. 1] report concluded that a “cold mock-up demonstration” along with “refined thermal analysis” would quickly drive the DOE-CTEs towards a TRL 4 and 6 level.

2.2 Technology Heritage The technologies employed by the MCSC Project are routinely used in the NPP industry for interim storage of SNF. These technologies are considered mature for this application. Reference 6 provides a listing of the commercial locations these technologies have been used, along with applicable NRC

CHPRC-03403, Rev. 0

4

certificates of compliance (CoC). With exception of the “relevant” environment discussed in Section 2.1.1, these technologies are considered mature for the MCSC Project.

Regarding system design (and associated technologies), the project is taking an existing and commercially available, NRC-licensed SNF DCSS system and adapting it to accommodate the MCSC capsules. Some design changes will be made to reflect unique capsule dimensions, thermal and radiation levels.

2.3 Current Project Activities and Technology Maturation This TMP was prepared to address specific technology, and system demonstration and design activities needed to bring the immature CTEs identified by the MCSC-TRSA and DOE-TRA to a TRL 6 level.

2.4 Management of Technology Maturity The CH2M Hill Plateau Remediation Company (CHPRC), Richland, WA, is responsible for managing the activities identified in this TMP. MCSC Project Engineering will manage and provide oversight for all TMP activities including those that may be subcontracted. The activities identified herein will be tracked on the MCSC Project schedule.

3 TMP This section describes the specific activities planned for the MCSC-TRSA and DOE-TRA CTEs requiring maturation, demonstration and analysis.

3.1 Development of Technology Maturation Requirements 3.1.1. MCSC-TRSA Based on the design at the time the MCSC-TRSA was conducted, CTE No. 2A_2B was assessed to not have been adequately demonstrated in the relevant environment, that is, the WESF G Cell where welding will be performed under fully-remote and time-constrained conditions. The concern is with reliability. This technology is prone to some process and equipment upset, but when applied in an environment where physical access to the weld joint is possible, resolution of these upsets can be accomplished in a reasonable and timely manner. Addressing these upsets under fully-remote operations however, will significantly impact the ability (and time) to efficiently resolve issues.

To address reliability concerns in the relevant environment, the project identified the following four welding improvement options:

1. Welding Technology Optimization – Technology Development

2. Failed Weld Consequence Mitigation – Operations Investigation

3. Solid State Welding Technology – Technology Development

4. Containment Closure Welding in Truck Port vs. G Cell – Programmatic Investigation

In response to the CTE No. 2A_2B reliability concerns, the MCSC Project and the CSS design contractor decided to move the closure weld from the UCS to the TSC. TSC closure welding will be performed in the Truck Port, where physical access to the weld joint can be accommodated. This effectively addresses the reliability issue with CTE No. 2A_2B technology by changing the environment to one where the technology has been successfully demonstrated – see Reference 6 for a listing of these applications. The technology, applied in an environment allowing for physical access to the weld joint, is considered to meet the required TRL 6 level.

CHPRC-03403, Rev. 0

5

With this design change, the CTE No. 2A_2B technology meets the required TRL 6 level, thus eliminating the need to perform the above welding improvement options. Therefore, no additional actions will be taken to respond to the MCSC-TRSA recommendations.

3.1.2. DOE-TRA The DOE-TRA CTEs (#1, #2 and #4) failed to meet functional system and design maturation criteria as reported in the DOE-TRA report [Ref. 1]. The concern is that the systems, and associated technology, have not been adequately demonstrated, and the thermal and heat removal design not sufficiently refined. To address these concerns, the following activities are planned:

1. Equipment Testing – to address system functionality of CTEs #1 and #2.

The MCSC Project Test Plan [Ref. 7] describes the testing that will be performed during the project. In general, factory acceptance testing (including fit testing) will be performed by equipment fabricators / vendors prior to acceptance of the equipment by the MCSC Project. On-site mock-up activities will be performed to optimize processing steps, train personnel, and develop procedures for normal and off-normal operations. Dry-run integrated testing will be performed to demonstrate readiness for operations. Additionally, dimensional checks of the capsules will be performed during the design phase to demonstrate that the capsules will fit into the UCS.

2. Thermal and Heat Removal Design – to address design refinement for CTEs #1, #2 and #4.

As the design progresses beyond the current conceptual design phase, thermal and aging management analyses will be refined. Additional design reviews are planned at the preliminary and final design stages.

The above activities will be identified in the project schedule.

3.2 Life-Cycle Benefit The benefits of using the TRA approach for technology maturation are as follows:

1. Increased confidence the technology will be ready for project insertion at the CD-2/3 phase of the project

2. Efficient and timely resolution of technology maturity issues to reduce project costs and potential delays in the project schedule

3. Increased confidence that production transfer operations, including loading and welding of UCSs, will meet the overall project schedule

The cost of implementing a TRA maturation process, to ensure project technologies are mature and successfully perform their intended function, is small compared to the cost of potential project delays and operations re-work.

3.3 Specific TMPs 3.3.1. MCSC-TRSA CTE No. 2A_2B Section 3.1.1 discusses a change in the design subsequent to performing the MCSC-TRSA that effectively brings the CTE No. 2A_2B to the required CD-2/3 TRL 6 level. As such, no maturation activities are required for this technology nor will there be any additional actions taken to respond to the MCSC-TRSA recommendations.

CHPRC-03403, Rev. 0

6

3.3.2. DOE-TRA CTE #1, #2 and #4 Key Technology Addressed The DOE-TRA report identified two functional systems (CTE #1 and #2) as requiring demonstration and refined thermal analysis, and one functional system (CTE #4) requiring refined thermal analysis and a technical basis for design life extension.

Objective The objective or purpose of the three DOE-TRA identified CTEs are as follows:

1. CTE #1 – Capsule Loading System

This system and associated technologies will retrieve capsules from the pool and load them into the UCS. Activities include UCS drying, inert gas backfilling, welding, testing and examination, along with the potential need for local cooling of capsules in the G Cell. The technologies associated with this system are mature and have been previously demonstrated in other applications in industry [Ref. 6]. It is important however, to ensure that the specific configuration of the capsule loading system technologies “work together” and that thermal analyses adequately consider the need and ability to maintain capsule design temperatures.

2. CTE #2 – UCS Insertion into TSC and Cask

This system and associated technologies will transfer the loaded UCS from the G Cell to the Truck Port for insertion into the assembled TSC / VCC. Activities include UCS transfer from G Cell to the Canyon using the Dry Transfer System (DTS), UCS insertion into the TSC using the Shielded Indexer Plate (SIP), and miscellaneous equipment – rigging, lifting and handling equipment. The technologies associated with this system are mature and have been previously demonstrated in other applications in industry [Ref. 6]. It is important however, to ensure that the specific configuration of the system technologies “work together” and that thermal analyses adequately consider the need and ability to maintain capsule design temperatures.

3. CTE #4 – Extended Storage at CSA

This system and associated technologies will monitor cask system temperatures to ensure capsule temperature requirements are met over the design storage term. Canister (TSC) aging management and strategy are also a part of this system. The technologies associated with this system are mature and have been previously demonstrated in industry [Ref. 6]. There is however, opportunity to further develop the bases for long-term aging and thermal management.

Current State of Art The technologies associated with CTE #1, #2 and #4 are routinely used for commercial SNF DCSSs. The MCSC Project CSS will be similar to the SNF systems; however, there will be some differences in design to accommodate unique capsule dimensions, thermal and radiation levels. The MCSC Project completed conceptual design for the capsule CSS in late 2017 and is currently (as of early 2018) performing preliminary design.

This TMP outlines the activities (design and system demonstration) required to address the maturity gaps identified for CTE #1, #2 and #4.

Technology Development Approach Based on review of the DOE-TRA report [Ref. 1], MCSC Project Engineering prepared a listing of the DOE-TRA identified gaps and recommended actions. Attachment C provides the following:

CHPRC-03403, Rev. 0

7

1. DOE-TRA identified gaps

a) With reference to the specific section or paragraph in the DOE-TRA report

2. DOE-TRA recommended actions to address the gaps

3. MCSC Project resolution that addresses the gaps

4. Estimated schedule for resolution implementation.

Attachment C provides the structure and approach needed to successfully address and mature the gaps identified by the DOE-TRA Team. Attachment D provides additional detail regarding the planned testing for each individual TE. Together, these two tables provide the path forward required to mature the DOE-TRA identified CTEs.

4 Plan to Mature System Integration As the MCSC Project progresses, design and testing activities as outlined in Reference 7 and Attachments C and D will demonstrate how individual technologies, components and equipment work together.

5 Technology Maturity Schedule Technology maturation activities, along with resolution of DOE-TRA identified technology gaps, are identified in Attachments C and D. Estimated schedule dates are also addressed in these attachments. The following table provides anticipated dates for addressing the specific DOE-TRA CTEs, #1, #2 and #4. Schedule dates are subject to funding and priority constraints and may change. Any changes will be documented on the project schedule.

Table 1. DOE-TRA CTE Maturation Schedule

CTE #1 , #2, and #4

Activity 2018 2019 2020 2021 2022

Functional System Demonstration

Capsule Dimension

Checks Vendor Testing

On-Site Mock-up Testing

On-Site Integrated

Testing

Refined Thermal Analysis CSS Design

WESF Modifications

Design

6 Summary Technology Maturity Budget Technology maturation activities identified herein are included in the MCSC Project baseline.

CHPRC-03403, Rev. 0

8

7 References [1] Technology Readiness Assessment Report, Management of the Cs/Sr Capsule Project at the Hanford

Site, January 2018.

[2] CHPRC-03402, Rev. 0, Technology Readiness Self-Assessment for the Management of the Cesium and Strontium Capsules Project (W-135), August 2017.

[3] DOE O 413.3B, Rev. 11-29-2010, Program and Project Management for the Acquisition of Capital Assets, November 2010.

[4] U.S. DOE Office of Environmental Management TRA/TMP Process Implementation Guide, Revision 1, August 2013.

[5] CHPRC-03326, Rev. 0, Cask Storage System Conceptual Design Report (Project W-135), September 2017.

[6] NAC International Application of DCSS Technology – NRC CoC No. 72-1025 [Attachment L, CHPRC-03402, Rev. 0, Technology Readiness Self-Assessment Plan for the Management of the Cesium and Strontium Capsules Project (W-135)], August 2017.

[7] CHPRC-03452, Rev. 0, Management of the Cesium and Strontium Capsules Project (W-135) Test Plan, January 2018.

CHPRC-03403, Rev. 0

A-i

Attachment A

MCSC-TRSA Technology Elements Spreadsheet

CHPRC-03403, Rev. 0

A-ii

This page intentionally left blank.

CHPRC-03403, Rev. 0

A-1

Attachment A. MCSC-TRSA Technology Elements Spreadsheet G

RO

UP

Activity / Function Technology Element

GR

P N

o.

Description of Technology Element

1 Loading Capsules into the UCS

Remote Handling Equipment 1A Remote Handling Equipment: Equipment used to retrieve capsules from the pool and place into the Capsule Loading Tray

Capsule Evaluation Equipment 1B Capsule Evaluation Equipment: Ring lock, inspection, and other equipment used to evaluate suitability of capsule for loading into the UCS

Capsule Loading Tray 1C Capsule Loading Tray: Facilitates insertion of capsules into the UCS (horizontal orientation)

Upender 1D Upender: Houses the UCS during capsule loading. When loaded, the Upender rotates the UCS to the vertical position preparatory to loading - welding, drying, etc.

2 Sealing or Processing of the Loaded UCS

UCS 2A Container that houses the capsules and is credited as the primary confinement barrier

Equipment for UCS Welding, Drying, Inspection and Testing 2B

Fully remote UCS processing equipment: Welding machine/system; vacuum drying system, Visual Inspection system and Helium Leak Test equipment

Capsule Cooling Equipment 2C Cooling equipment for capsule temperature control from pool retrieval to insertion into the TSC to include capsule temperature verification

Video / Audio Equipment 2D Video and audio recording equipment to be used during capsule loading into the UCS - to ensure capsule location and traceability

3 UCS Insertion into the TSC

TSC 3A Container that houses the basket in which the sleeves are placed and provides a cooling function

DTS 3B Equipment / system used to transfer the loaded UCS from the G Cell into the Canyon for loading into the TSC

SIP 3C Equipment / system used to align the DTS with the individual cells or tubes into which the UCS is loaded into the TSC basket

TSC Shielded Lifting Device 3D Equipment / system used to install the TSC lid onto the loaded TSC

VCC 3E Outer shielding ring of the Cask (assembled UCS, TSC and VCC)

Canyon Rigging and Handling Equipment 3F Rigging and handling equipment and fixturing used in the Canyon to move and place equipment and components

4 Cask Transport from WESF to CSA

Air Pallet Transporter 4A Equipment / system used to lift and move the Cask from WESF to the CSA

Vertical Cask Transport (VCT) 4B Trailer / system used to transport the Cask from WESF to the CSA

VCT-GT50 (VCT Tug) 4C Vehicle / system used to move loaded VCT from WESF to the CSA

5 Extended Storage at the CSA

Temperature Modeling and Capsule Temperature Monitoring 5A

Temperature monitoring equipment

Aging Management 5B

In-Service Inspection (ISI) equipment and procedures Maintenance equipment and procedures TSC mitigation and repair techniques, equipment and procedures

CHPRC-03403, Rev. 0

A-2

This page intentionally left blank.

CHPRC-03403, Rev. 0

B-i

Attachment B

DOE-TRA Technology Elements Spreadsheet

CHPRC-03403, Rev. 0

B-ii

This page intentionally left blank.

CHPRC-03403, Rev. 0

B-1

Attachment B. DOE-TRA Technology Elements Spreadsheet

TE Functional System Technology Element [1] GRP

N

o.

Description of Technology Elements

#1 Capsule Loading System

Remote Handling Equipment 1A Remote Handling Equipment: Equipment used to retrieve capsules from the pool and place into the Capsule Loading Tray Capsule Evaluation Equipment 1B Capsule Evaluation Equipment: Ring lock, inspection, and other equipment used to evaluate suitability of capsule for loading into the UCS Capsule Loading Tray 1C Capsule Loading Tray: Facilitates insertion of capsules into the UCS (horizontal orientation) Upender 1D Upender: Houses the UCS during capsule loading. When loaded, the Upender rotates the UCS to the vertical position preparatory to loading -

welding, drying, etc. UCS 2A Container that houses the capsules and is credited as the primary confinement barrier Equipment for UCS Welding, Drying, Inspection and Testing

2B Fully remote UCS processing equipment: Welding machine/system; vacuum drying system, Visual Inspection system and Helium Leak Test equipment

Capsule Cooling Equipment 2C Cooling equipment for capsule temperature control from pool retrieval to insertion into the TSC to include capsule temperature verification Video / Audio Equipment 2D Video and audio recording equipment to be used during capsule loading into the UCS - to ensure capsule location and traceability G Cell Ventilation and Cooling [1]

#2 UCS Insertion Into TSC & Cask

TSC 3A Container that houses the basket in which the sleeves are placed and provides a cooling function

DTS 3B Equipment / system used to transfer the loaded /processed UCS from the G-Cell into the Canyon for loading into the TSC SIP 3C Equipment / system used to align the DTS with the individual cells or tubes into which the UCS is loaded into the TSC basket TSC Shielded Lifting Device 3D Equipment / system used to install the TSC lid onto the loaded TSC VCC 3E Outer shielding ring of the Cask (assembled UCS, TSC and VCC) Canyon Rigging and Handling Equipment 3F Rigging and handling equipment and fixturing used in the Canyon to move and place equipment and components

WESF Truck Bay Infrastructure, Cooling and HVAC [1]

#3 Cask Transport from WESF to CSA

Air Pallet Transporter 4A Equipment / system used to lift and move the Cask from WESF to the CSA

Vertical Cask Transport (VCT) 4B Trailer / system used to transport the Cask from WESF to the CSA VCT-GT50 (VCT Tug) 4C Vehicle / system used to move loaded VCT from WESF to the CSA

Road Capability and Site Infrastructure [1]

#4 Extended Storage at CSA

Temperature Modeling and/or Capsule Temperature Monitoring

5A Temperature monitoring equipment

Aging Management

5B In-Service Inspection (ISI) equipment and procedures Maintenance equipment and procedures TSC mitigation and repair techniques, equipment and procedures

Pad design to withstand temperature and radiation, accommodate instrumentation and provide capability to retrieve and place in new containers if casks do not last 300 years

[1]

Notes: [1] The TEs shown in italics are included in the TRA but not in the TRSA.

CHPRC-03403, Rev. 0

B-2

This page intentionally left blank.

CHPRC-03403, Rev. 0

C-i

Attachment C

DOE-TRA Identified Gaps Spreadsheet

CHPRC-03403, Rev. 0

C-ii

This page intentionally left blank.

CHPRC-03403, Rev. 0

C-1

Attachment C. DOE-TRA Identified Gaps Spreadsheet Item No.

TRA Identified Gap TRA Ref / CTE TRA Recommendation MCSC Project Resolution Schedule

1 “G Cell HVAC and ventilation system are likely not capable of providing sufficient cooling in its current configuration.” … “The G Cell … is not equipped to provide a confinement ventilation function, particularly in the presence of a significant heat load.”

Sect. 3.1.5 / CTE #1 NA Thermal analysis will be performed and refined during CSS preliminary and final design. If required, additional cooling capability will be designed as a part of the WESF Modifications design.

CSS final design is scheduled to complete in September 2018. WESF Modifications design activities are expected to complete in 2019, pending funding availability.

2 “Documented Safety Analysis (DSA) specifies a maximum material at risk (MAR) of 5 capsules in G Cell at one time, while the current waste processing system design would require 12 capsules.”

Sect. 3.1.5 / CTE #1 NA Final determination of the number of capsules required in the G Cell will be addressed and resolved during CSS preliminary and final design. Any required changes to inventory controls will be incorporated into the WESF DSA.

CSS final design is scheduled to complete in September 2018. WESF DSA revision will be performed following completion of the CSS and WESF Modifications design activities. WESF Modifications design activities are expected to complete in 2019, pending funding availability.

3 “The TRA Team re-evaluated the three new CTEs against the DOE CTE TRL 3 and TRL 4 Technology Readiness Level Calculators and found that CTE #1 could be described as a TRL 3 (-) in maturity.”

Sect. 3.1.6 / CTE #1 1) Perform mock-up demonstration

2) Perform refined

thermal analysis

1) CSS mock-up testing, including an integrated mock-up test, will be performed by the equipment vendor after fabrication and prior to acceptance by the MCSC Project. Additional mock-up testing will be performed by the MCSC Project to support training and procedure development. An integrated dry-run will be performed as a part of readiness activities.

2) Thermal analysis will be performed and refined during CSS preliminary and final design.

1) Vendor testing is scheduled to be performed in 2020. On-site mock-up testing is schedule to be performed in 2020 and 2021. 2) CSS final design is scheduled to complete in September 2018.

4 “The TRA Team re-evaluated the three new CTEs against the DOE CTE TRL 3 and TRL 4 Technology Readiness Level Calculators and found that CTE #2 could be described as a TRL 3 (-) in maturity.”

Sect. 3.2.5 / CTE #2 Perform mock-up demonstration

CSS mock-up testing, including an integrated mock-up test, will be performed by the equipment vendor after fabrication and prior to acceptance by the MCSC Project. Additional mock-up testing will be performed by the MCSC Project to support training and procedure development. An integrated dry-run will be performed as a part of readiness activities.

Vendor testing is scheduled to be performed in 2020. On-site mock-up testing is schedule to be performed in 2020 and 2021.

5 “The resulting 602°F temperature was only 1°F below the design requirement of 603°F. No discreet design margin is specified in the calculation, so the margin is in the conservatism of assumptions.”

Sect. 3.4.3 / CTE #4 The thermal analysis should be revised with realistic assumptions to inform design of the casks, internals, and the concrete pad.

Thermal analysis will be performed and refined during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

CHPRC-03403, Rev. 0

C-2

Item No.

TRA Identified Gap TRA Ref / CTE TRA Recommendation MCSC Project Resolution Schedule

6 “The simplifying assumption that the ambient temperature is 94°F, and neglecting solar load, is not realistic or bounding.”

Sect. 3.4.3 / CTE #4 The thermal analysis should be revised with realistic assumptions to inform design of the casks, internals, and the concrete pad.

Thermal analysis will be performed and refined during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

7 “The ends of the cask were treated as adiabatic, which is not representative in terms of forecast heat load to the Interim Canister Storage Pad concrete, solar load to the container, or natural ventilation cooling and heat transfer design information regarding the components within the canister.”

Sect. 3.4.3 / CTE #4 The thermal analysis should be revised with realistic assumptions to inform design of the casks, internals, and the concrete pad.

Thermal analysis will be performed and refined during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

8 “The thermal analysis included a result that predicted a component interference fit due to differential thermal expansion between the stainless steel and aluminum components, but no stress analysis could be located to verify that this had been addressed in design.”

Sect. 3.4.3 / CTE #4 The thermal analysis should be revised with realistic assumptions to inform design of the casks, internals, and the concrete pad.

Thermal analysis will be performed and refined during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

9 “The cask selected for this project has a design life of 50 years, yet the project requires a 100 year design life. The team was not able to locate a technical basis for the 50 year extension in design life.”

Sect. 3.4.3 / CTE #4 NA Will clarify discrepancy in design life during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

10 “The truck bay heat load is not yet modelled, but with the current low ventilation airflow the heat load associated with a full cask would result in approximately a 70°F temperature rise, resulting in a 140°F leaving air temperature, assuming perfect mixing. It is likely that the cask and basket area would be significantly hotter.”

Sect. 3.4.3 / CTE #4 A recirculating cooling system will be required and flow should be pulled from near the cask to ensure maximum convection heat transfer.

Thermal analysis will be performed and refined during CSS preliminary and final design. If required, a supplemental cooling system will be designed as a part of the WESF Modifications design.

CSS final design is scheduled to complete in September 2018. WESF Modifications design activities are expected to complete in 2019, pending funding availability.

11 “The team also recognized opportunities to address capsule temperature monitoring challenges in Interim Canister Storage Pad design.”

Sect. 3.4.3 / CTE #4 Suggest arranging all casks within line of site of the fence line, such that an infrared camera could be utilized to periodically check temperatures, should instruments fail.

This will be considered during CSS preliminary and final design. The cask arrangement specified during conceptual design was chosen to minimize radiation dose at the CSA fence. The CSA will be accessible during normal operation.

CSS final design is scheduled to complete in September 2018.

12 “Canister and cask cooling technology and components have been certified for use in the nuclear industry [NRC Certificate of Compliance No. 72-1025] and successfully demonstrated in a commercial NPP DCSS environment. However, the technology has not been demonstrated for long-term aging management.”

Sect. 3.4.4 / CTE #4 NA Aging management design and strategy will be performed and refined during preliminary and final design.

CSS final design is scheduled to complete in September 2018.

CHPRC-03403, Rev. 0

C-3

Item No.

TRA Identified Gap TRA Ref / CTE TRA Recommendation MCSC Project Resolution Schedule

13 “The TRA Team re-evaluated the three new CTEs against the DOE CTE TRL 3 and TRL 4 Technology Readiness Level Calculators and found that CTE #4 could be described as a TRL 3 (-) in maturity.”

Sect. 3.4.5 / CTE #4 A refined thermal analysis and technical basis of design life extension of CTE #4 “Extended Storage” would drive CTE #4 towards TRL 4 and TRL 6 quickly.

Thermal analysis will be refined and design life analysis will be performed during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

14 “The integrated Waste Processing System (WPS), was found not to be at TRL 4 by the TRA Team … The CTEs were all found to be at TRL 3(-). Therefore, the integrated WPS was found to be at TRL 3(-).”

Sect. 3.5 This finding is a direct result of the fact that none of the three CTEs identified by the TRA Team was found to be at TRL 4. (Mature the CTEs and the WPS TRL will mature as well)

This will be resolved when other gaps are resolved. No specific action will be taken.

NA

15 Lack of TRL maturity Sect. 4.2 The TRA Team recommends that the project regroup the identified TEs from TRA Self-Assessment according to functional system.

The MCSC Project will not update the TRSA performed at the conceptual design. Application of 413.3B requirements to the MCSC Project are currently under review due to a recent revision of 413.3B and redefinition of the capital asset project portion of the Project. If a future TRSA is required, it will consider this recommendation.

If a future TRSA is required, it will be performed after the CSA, WESF Modifications, and CSS preliminary design are complete. According to the current schedule, the earliest the TRSA would start is August 2018.

16 Lack of TRL maturity Sect. 4.2 The project should then re-evaluate the new TEs to determine CTEs and perform TRL 3, TRL 4 and TRL 6 calculator evaluations.

The MCSC Project will not update the TRSA performed at the conceptual design. Application of 413.3B requirements to the MCSC Project are currently under review due to a recent revision of 413.3B and redefinition of the capital asset project portion of the Project. If a future TRSA is required, it will consider this recommendation.

If a future TRSA is required, it will be performed after the CSA, WESF Modifications, and CSS preliminary design are complete. According to the current schedule, the earliest the TRSA would start is August 2018.

17 Lack of TRL maturity Sect. 4.2 The project should then develop a technology maturation plan (TMP) to address the gaps between TRL 3 and TRL 6.

The MCSC Project will not update the TRSA performed at the conceptual design. Application of 413.3B requirements to the MCSC Project are currently under review due to a recent revision of 413.3B and redefinition of the capital asset project portion of the Project. If a future TRSA is required, it will consider this recommendation.

If a future TRSA is required, it will be performed after the CSA, WESF Modifications, and CSS preliminary design are complete. According to the current schedule, the earliest the TRSA would start is August 2018.

CHPRC-03403, Rev. 0

C-4

Item No.

TRA Identified Gap TRA Ref / CTE TRA Recommendation MCSC Project Resolution Schedule

18 Lack of TRL maturity Sect. 4.2 Team also recommends that thermal analysis be refined to better understand heat transfer requirements, and that a technical basis for the 100 year life be developed, allowing sufficient time for operations and to further develop design.

Thermal analysis will be refined and design life analysis will be performed during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

19 Lack of TRL maturity Sect. 4.2 A time and motion study should be performed on the integrated process, factoring in thermal limits, to establish capsule inventories in G Cell and the Truck Port and to evaluate impact of component failures on throughput and define recovery operations.

A time and motion study will be performed to refine operational activities, to include thermal constraints during CSS preliminary and final design.

CSS final design is scheduled to complete in September 2018.

CHPRC-03403, Rev. 0

D-i

Attachment D

DOE-TRA Functional System Verification and Design Activities

CHPRC-03403, Rev. 0

D-ii

This page intentionally left blank.

CHPRC-03403, Rev. 0

D-1

Attachment D. DOE-TRA Functional System Verification and Design Activities

TE Functional System Technology Element [1] G

RP

No.

Description of Functional System Elements Test Type [2] Design Activity Test Timing Scheduled Date

#1 Capsule Loading System

Remote Handling Equipment 1A Remote Handling Equipment OAT NA Prior to declaration of readiness

1st Qtr 2022

Capsule Evaluation Equipment 1B Capsule Evaluation Equipment Development Test / OAT

NA During design / Prior to declaration of readiness

2nd Qtr 2018 / 1st Qtr 2022

Capsule Loading Tray 1C Capsule Loading Tray FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

Upender 1D Upender FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

UCS 2A Capsule Container FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

Equipment for UCS Welding, Drying, Inspection and Testing

2B UCS Loading Equipment Process Test NA During on-site mock-up activities

3rd Qtr 2020 / 1st Qtr 2022

Capsule Cooling Equipment 2C Cooling Equipment FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

1st Qtr 2021 / 1st Qtr 2022

Video / Audio Equipment 2D Video / Audio Equipment FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

1st Qtr 2021 / 1st Qtr 2022

G Cell Ventilation and Cooling [1] NA Thermal Analysis NA 1st Qtr 2019

#2 UCS Insertion Into TSC & Cask

TSC 3A Canister FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

DTS 3B UCS Transfer System FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

SIP 3C DTS UCS / TSC Alignment Equipment FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

TSC Shielded Lifting Device 3D TSC Lid Lifting Device FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

VCC 3E Concrete Cask CAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

Canyon Rigging and Handling Equipment 3F Rigging and Handling Equipment OAT NA Prior to declaration of readiness

1st Qtr 2022

WESF Truck Bay Infrastructure, Cooling and HVAC

[1] NA Thermal Analysis NA 1st Qtr 2019

CHPRC-03403, Rev. 0

D-2

TE Functional System Technology Element [1] G

RP

No.

Description of Functional System Elements Test Type [2] Design Activity Test Timing Scheduled Date

#3 Cask Transport from WESF to

CSA

Air Pallet Transporter 4A Equipment / system used to lift and move the Cask from WESF to the CSA

FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

VCT 4B Cask Transport OAT NA Prior to declaration of readiness

1st Qtr 2022

VCT-GT50 (VCT Tug) 4C VCT Tug OAT NA Prior to declaration of readiness

1st Qtr 2022

Road Capability and Site Infrastructure [1] OAT NA Prior to declaration of readiness

1st Qtr 2022

#4 Extended Storage at CSA

Temperature Modeling and/or Capsule Temperature Monitoring

5A Temperature Monitoring Equipment FAT / OAT NA Prior to equipment turnover / Prior to declaration of readiness

3rd Qtr 2020 / 1st Qtr 2022

Aging Management

5B ISI Equipment / Procedures OAT NA Prior to declaration of readiness

1st Qtr 2022

Maintenance Equipment / Procedures OAT NA Prior to declaration of readiness

1st Qtr 2022

TSC mitigation and repair Equipment / Procedures

OAT NA Prior to declaration of readiness

1st Qtr 2022

Pad design to withstand temperature and radiation, accommodate instrumentation and provide capability to retrieve and place in new containers if casks do not last 300 years

[1] NA Thermal and Aging Management Analysis

NA 4th Qtr 2018

Notes: [1] The TEs shown in italics are included in the TRA but not in the TRSA. [2] See the MCSC test plan (Ref. 7) for a complete list of testing that will be performed.

Legend:

1) FAT – Factory Acceptance Test 2) CAT – Construction Acceptance Test 3) OAT – Operations Acceptance Test 4) Development Test (Defined in PRC-PRO-EN-286, Testing of Equipment and Systems) 5) Process Test (Defined in PRC-PRO-EN-286)