tekle k.mariam first payment

Upload: samson-ngusse

Post on 05-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Tekle K.mariam First Payment

    1/34

    Take-off No_____________

    Project:ECD

    No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h

    A-Sub -Structure 2-Masonry work

    1-Excavation and earth work 2.1-50cm thick masonery fn

    1.1-site clearance Foundn_ Ditto as item no1.3

    20.00 L=18+2=20m W=7.5+2=9.5m 18.00 Avg Depth = 0.62+0.55+0.64+0.74+0.70= 0.659.50 190.00 m2 0.65 5

    190.00 m2

    NET TOTAL 2 0.50 11.7 m3

    6.50 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m1.3 Bulk excavation 0.74 4

    4 0.50 9.62 m3

    0.00 4.00 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m1.3Trench excavation 0.74 4Avg Depth = 0.62+0.55+0.64+0.74+0.70 1 0.50 1.48 m3

    18.00 5 22.80 m3 NET TOTAL0.65 = 0.65m

    2 0.48 11.23 m3 2.2-Ditto as item2.1 but6.50 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m ANGL (Average Height =50cm)

    0.74 4 18.00 Avg D = 0.60+0.40+0.20+0.00 = 0.3 m4 0.48 9.24 m3 0.30 4

    4.00 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 1 0.50 2.7 m3

    0.74 4 18.00 Avg D = 0.55+0.30+0.28+0.20 = 0.33m1 0.48 1.42 m3 0.33 4

    21.89 m3 NET TOTAL 1 0.50 2.97 m3

    1.4 Back fill Avg D = 0.60+0.56+0.55+0.20+0.20+0.006.00 Avg D = 0.60+0.56+0.55+0.30 = 0.5 m 6.50 46.50 4 0.35 = 0.35m

    1 0.50 19.5 m3 4 0.50 4.55 m3

    6.00 Avg D = 0.28+0.20+0.00+0.0.20 = 0.17m 4.00 Avg D = 0.35m6.50 4 0.35

    1 0.17 6.63 1 0.50 0.7 m3 NET TOTAL

    4.00 Avg D = 0.28+0.20+0.40+0.30 = 0.3m 10.923.00 42 0.30 7.2 m3

    33.33 m3NET TOTAL

    6.00 1.5Hard coring

    2 6.50 78 m2

    4.002 3.00 24 m2

    102 m2

    NET TOTAL

    1.6Cart away

    0.00

    0.20 0.00DITTO AS ITEM 1.1 BUT MELTI- BY0.20 CM

    0.00 DITTO AS ITEM 1.3 trench excavtion0.00 m3 NET TOTAL

    Take-off No_____________

    Tekle K/mariam B.C.Site : Aragure Kebele/H/Wejerat Woreda

    Block: ECD

    contractor_________________ supervisor_________________

  • 7/31/2019 Tekle K.mariam First Payment

    2/34

    Project:ECD

    No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h

    6.00 3-Concrete Work B.SUPER STRUCTURE

    6.503.1 -10cm thick reinforced concrete

    floofslab 4.Concrete work0 0.10 0.00 m

    34.1 reinforced concrete c-20

    4.00 a) -50*20cm top tie beam c-203.00 18.00

    0 0.10 0.00 m3

    0.50

    0.00 m3

    NET TOTAL 2 0.20 3.60 m3

    3.2 -50*20cm grade beam c-20 6.5018.00 0.50

    0.50 4 0.20 2.60 m3

    2 0.20 3.60 m3

    4.006.50 0.500.50 1 0.20 0.40 m3

    4 0.20 2.60 m3

    6.60 m3

    NET TOTAL

    4.00

    0.50

    B.In 6cm thick reinforcement concretewindow sills. Here price includes form work

    & 8mm deformed bars c/c 20cm both way

    1 0.20 0.40 m3

    0 1.60 0.00

    6.60 m3NET TOTAL 0 1.15 0.00

    3.3 Steel reinforcement

    (a)Q6mm 0.00 mNET TOTAL#REF! Kg 4.2 Steel reinforcement

    (a)Q6mm#REF! b)Q8mm #REF! Kg

    b)Q12mmC)Q12mm #REF! Kg

    #REF! Kg 4.3 -form work

    3.4 -form work 18.00 External18.00 External 2 0.20 7.202 0.20 7.20 7.50

    7.50 2 0.20 3.002 0.20 3.00 6.50 Internal

    6.50 Internal 4 0.20 5.204 0.20 5.20 6.00

    6.00 4 0.20 4.804 0.20 4.80 3.00

    3.00 4 0.20 2.404 0.20 2.40 4.00

    4.00 4 0.20 3.204 0.20 3.20 ` 25.80 m

    2NET TOTAL

    25.80 m2

    NET TOTAL

    3.5.concrete ancillaries expantion joint

    0 6.50 0.000 6.00 0.000 4.00 0.000 3.00 0.00

    0.00 M NET TOTAL

    Take-off No_____________

    Tekle K/mariam B.C.

    Tekle K/mariam B.C.Site : Aragure Kebele/H/Wejerat Woreda

    Block: ECD

    contractor_________________ supervisor_________________

  • 7/31/2019 Tekle K.mariam First Payment

    3/34

    Site : Aragure Kebele/H/Wejerat Woreda

    contractor_________________ supervisor_________________

  • 7/31/2019 Tekle K.mariam First Payment

    4/34

    Project:ECD

    No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h

    5-Walling

    18.00 5.1-50cm thick dressed0.50 stone masonry

    2 2.80 50.40 m3

    6.500.50

    4 2.80 36.40 m3

    4.000.50

    1 2.80 5.60 m3

    1.00 Dedaction (To be checked again)0.50 Doors

    4 2.80 5.60 m3

    1.15 W 20.50

    8 1.80 8.28 m3

    1.60 W10.60

    4 0.50 1.92 m3

    76.6 m3 NET TOTAL

    Block: ECD

    contractor_________________ supervisor_________________

  • 7/31/2019 Tekle K.mariam First Payment

    5/34

    3.250.65

    2.950.7375

    1.20.3

    2.01 1.330.5025 0.3325

    0.680.17 2.11

    0.351667

    1.18

    0.295

    contractor_________________ supervisor_________________

  • 7/31/2019 Tekle K.mariam First Payment

    6/34

    Contractor:-Tekle K/mariam B.C.

    construction Type;-Natural StoneBuilding;-Childhood Development Center(ECD)

    Location;-Enderta sitesSite name ;-Aragure

    Contrat ExcutedA-SUB STRUCTURE

    1 Excavation &Earth Work1.1 Site clerance m 0.001.2 Bulk Excavation m3 0.001.3 Trench excavation m3 0.001.4 Fill under hard core borrowed m3 0.001.5 Hard cring 25cm thick m2 0.001.6 Cart away m3 0.00

    Sub total(1) -2 Masonry work2.1 50cm thick masoneryBNGL m3 0.002.2 Dittoas2.1butANGL m3 0.00

    Sub total(2) -3 .Concrete work

    3.1 10cm Thick RC floor slab m2

    0.003.2 RC for 50*20cmgrade beam m3 0.003.3 Steel reinforcement 0.00

    (a)Q6mm plain bars kg 0.00b)12mmDeformed bars k 0.00

    12mmDeformed bars k 0.003.4 Form work for grade beam m2 0.003.5 concrete ancillaries expansion joint m 0.00

    -

    4.1m3 0.00

    m0.00

    4.20.00

    kg 0.00kg 0.00

    4.3 m2 0.00

    -

    5.1 50cm thick dressed masonery 0.005.2 Ditto5.1 above top tie beam m3 0.00

    Sub total(5) m3 -

    6.1 0.00m2 -

    Contractor:-Tekle K/mariam B.C.

    construction Type;-Natural Stone

    Building;-Childhood Development Center(ECD)

    Location;-Enderta sitesSite name ;-Aragure

    Quantity

    Unit Price Total Price

    Sub total (3)

    UnitNo Description

    Provide cut and fix in position sawn pine wood orequivalent formwork for upper tie beam.

    Sub total 4

    6. Roofing

    G-30 galvanized corrugated iron sheet roofing fixedSub total 6

    B. Super Structure

    4. Concrete work

    Reinforced concrete class C-20,320kga)In 50x20cm upper tie beamb)In 6cm thick reinforced concrete window sills.Here price includes form work & 8cm deformedbars c/c 20cm both ways.Steel reinforcement for upper T. beam cut bent &placed in position unit price includes cuttingbending placing in position & tying bars.

    a) 6mm plain bars

    b) 12mm deformed bars

    _________________________CONTRACTOR

    _________________________SUPERVISOR

  • 7/31/2019 Tekle K.mariam First Payment

    7/34

    No Unit TotalContrat Excuted Price Price

    7.1 M 350 0.00 13 0.00M 250 0.00 12 0.00

    M 300 0.00 40 0.007.2 M 50 0.00 60 0.00-

    8metal windows &doors LTZ

    8.1 Type D1,size 100*280cm No. 4 0 2000 0.008.2 Type W1, size 115*180 No. 10 0 1800 0.00

    TypeW2, size 160*60 wire mesh No. 4 0 1500 0.008.3 Security grill LtZ size 115*180cm No. 9 0 1000 0.00

    -

    9.1 m2

    259 #REF! 50 #REF!

    9.2 m2

    30 #REF! 20 #REF!

    9.3 m2

    26.4 #REF! 500 #REF!#REF!

    10.1 m2 107 0 50 0.0010.2 m2 36 #REF! 180 #REF!10.3 m2 19 #REF! 180 #REF!

    #REF!

    #REF!

    Quantity

    Sub total(8)

    Metal work

    Description Unit

    c)5x7cm treated pinewood purlins c/c 90cm.Supply and fix 25x2.5cm carraro or equivalent

    cement mortar 1:3pavement, concrete quality C-15,290 KGDitto as 10.3 above but 80cm wide to gable sidesSub total 10

    Grand Total

    9.PLASTERING AND POINTING

    Apply three coats of cement mortar plaster 1:3 toall internal walls including above top tie beam.andbeam surfacesAll external stone masonry foundation wall above

    NGL shall be raked out to a depth of 25mm andpointed in cement mortar 1:3

    Ditto as 9.2 above but external wall above gradebeam

    Sub total 9

    10.PAVING AND FLOORING

    Sub total 7

    7.Carpentry and joinery

    All timber & eucalptus structural members shall be

    a) 10-12cm eucalyptus lower/upperb) 8-10cm eucalyptus bracing and internal

    _________________________CONTRACTOR

    _________________________SUPERVISOR

  • 7/31/2019 Tekle K.mariam First Payment

    8/34

    Contractor:-Tekle K/mariam B.C.

    construction Type;-Natural Stone

    Building;-Childhood Development Center(ECD)

    Location;-Enderta sitesSite name ;-Aragure

    No Discription PriceA-sub structure Contrat Excuted

    1 Excavation &Earth work2 Masonry work3 Concrete work

    B-SUPER_STRUCTURE

    4 Concrete work5 Walling6 Roofing7 Carpenrty&joinery8 Metal work

    9 Plastering&pointing10 Paving &Flooring11 Glazing12 Paainting

    Total for class Room Building At Hawatsu 0.00 0.00

    _________________________CONTRACTOR

    _________________________SUPERVISOR

  • 7/31/2019 Tekle K.mariam First Payment

    9/34

    Site-Hawatsu

    Unit Total

    Contrat Excuted Price Price

    A-SUB STRUCTURE

    1 Excavation &Earth Work

    1.1 Site clerance m

    2

    190 #REF! 2.50 #REF!1.2 Bulk Excavation m3 45 0.00 1.00 0.001.3 Trench excavation m3 45 #REF! 4.00 #REF!1.4 Fill under hard core borrowed m3 120 #REF! 1.00 #REF!1.5 Hard cring 25cm thick m2 108 #REF! 150.00 #REF!1.6 Cart away m3 128 #REF! 15.00 #REF!

    Sub total(1) #REF!2 Masonry work2.1 50cm thick masoneryBNGL m3 45 #REF! 300.00 #REF!2.2 Dittoas2.1butANGL m3 25 #REF! 400.00 #REF!

    Sub total(2) #REF!3 .Concrete work

    3.1 10cm Thick RC floor slab m2

    10.8 #REF! 1350 #REF!

    3.2 RC for 50*20cmgrade beam m3 6.4 #REF! 1350 #REF!3.3 Steel reinforcement 0.00

    (a)Q6mm plain bars kg 80 #REF! 23 #REF!b)12mmDeformed bars kg 310 #REF! 19 #REF!12mmDeformed bars kg 260 #REF! 19 #REF!

    3.4 Form work for grade beam m2 22 #REF! 100 #REF!3.5 concrete ancillaries expansion joint m 86 #REF! 60 #REF!

    Sub total (3) #REF!

    4.1m3 6.4 #REF! 1350 #REF!m 14.4 #REF! 140 #REF!

    4.2 0.00kg 98 #REF! 19 #REF!kg 260 #REF! 19 #REF!

    4.3 m2

    42 #REF! 100 #REF!#REF!5.1 50cm thick dressed masonery 86.8 #REF! 580 #REF!5.2 Ditto5.1 above top tie beam m3 14.1 #REF! 580 #REF!

    Sub total(5) m3 #REF!

    6.1 190 #REF! 210 #REF!m2 #REF!

    Unit

    Description Quantity

    G-30 galvanized corrugated iron sheet roofing fixedSub total 6

    6. Roofing

    Reinforced concrete class C-20,320kga)In 50x20cm upper tie beamb)In 6cm thick reinforced concrete window sills.Steel reinforcement for upper T. beam cut bent &a) 6mm plain barsb) 12mm deformed barsProvide cut and fix in position sawn pine wood orequivalent formwork for upper tie beam.Sub total 4

    B. Super Structure4. Concrete work

    No

    _________________________CONTRACTOR

    _________________________SUPERVISOR

  • 7/31/2019 Tekle K.mariam First Payment

    10/34

    Site-Hawatsu

    No Description Unit Total

    Contrat Excuted Price Price

    7.1 M 350 #REF! 13 #REF!M 250 #REF! 12 #REF!M 300 #REF! 40 #REF!

    7.2 M 50 #REF! 60 #REF!#REF!

    8 Metal workmetal windows &doors LTZ

    8.1 Type D1,size 100*280cm No. 4 #REF! 2000 #REF!8.2 Type W1, size 115*180 No. 10 #REF! 1800 #REF!

    TypeW2, size 160*60 wire mesh No. 4 #REF! 1500 #REF!8.3 Security grill LtZ size 115*180cm No. 9 #REF! 1000 #REF!

    Sub total(8) #REF!

    9.1 m2 259 #REF! 50 #REF!9.2 m2 30 #REF! 20 #REF!9.3 m2 26.4 #REF! 500 #REF!

    #REF!

    10.1 m2 107 50 0.0010.2 m2 36 #REF! 50 #REF!10.3 m2 19 #REF! 180 #REF!

    #REF!

    #REF!

    Quantity

    9.PLASTERING AND POINTINGall internal walls including above top tie beam.andNGL shall be raked out to a depth of 25mm and

    All timber & eucalptus structural members shall bea) 10-12cm eucalyptus lower/upperb) 8-10cm eucalyptus bracing and internalc)5x7cm treated pinewood purlins c/c 90cm.

    beam

    Ditto as 10.3 above but 80cm wide to gable sides

    Sub total 9

    10.PAVING AND FLOORINGcement mortar 1:3pavement, concrete quality C-15,290 KG

    Supply and fix 25x2.5cm carraro or equivalentSub total 7

    7.Carpentry and joinery

    Sub total 10

    Grand Total

    _________________________CONTRACTOR

    _________________________SUPERVISOR

  • 7/31/2019 Tekle K.mariam First Payment

    11/34

    Contractor:-Tekle K/mariam B.C.

    Building;-Childhood Development Center(ECD)

    Site- Aragure

    Location Bar Length No bars No of Total No

    Description Dia Schedule M Mem of bars Q 6 Q 8 Q 12

    Top 12 18.78 2.00 2 4 75.12Bottom 12 18.48 2.00 2 4 73.92stiraps C/C 20 6 1.30 91.00 2 182 236.60

    Top 12 7.80 2.00 4 8 62.40Bottom 12 7.50 2.00 4 8 60.00stiraps C/c 20cm 6.5 1.30 34.00 4 136 176.80

    Top 12 5.30 2.00 1 2 10.60Bottom 12 5.00 2.00 1 2 10.00stiraps C/c 20cm 6 1.30 21.00 1 21 27.30

    Total Length 440.70 292.04

    Weight Kg/m 0.222 0.395 0.888

    Total Weight 97.84 259.33

    Contractor:-Tekle K/mariam B.C.

    Building;-Childhood Development Center(ECD)Site- Aragure

    SUB TOTALNo.Bars Elem Tot.No Dia.6 Dia.8 Dia.10 Dia.12

    Top 12 18.78 2.00 2 4 75.12Bottom 12 18.48 2.00 2 4 73.92stiraps C/C 20 6 1.30 91.00 2 182 236.60

    Top 12 7.80 2.00 4 8 62.40Bottom 12 7.50 2.00 4 8 60.00stiraps C/c 20cm 6.5 1.30 34.00 4 136 176.80

    Top 12 5.30 2.00 1 2 10.60Bottom 12 5.00 2.00 1 2 10.00stiraps C/c 20cm 6 1.30 21.00 1 21 27.30

    440.7 292.040.222 0.395 0.617 0.888

    97.84 259.33

    Length(mete

    r)

    No.of Bars

    TOTAL WT.(KG)

    Reinforcement bar Schedule

    Total Length

    NIT WEIGHT(KG\M

    Reinforcement bar Schedule

    BAR SCHEDULE FOR GRADE BEAM

    BAR SCHEDULE FOR TOP TIE BEAM

    Location Shape

    Dia(m

    m)

  • 7/31/2019 Tekle K.mariam First Payment

    12/34

  • 7/31/2019 Tekle K.mariam First Payment

    13/34

    Project:Dry Latrine

    No. LXWXH Quantity Description No. LXWXH QuantityA-Sub-structure

    1-Excavation & Earth work

    1.1.Clear the site and remove top

    soil at an average depth of 20cm

    7.5 L= 3.5 + 2 *2=7.5 m 2.301 6.00 45.00 W= 2+2*2= 6 m 0.80

    45.00 m2

    2 0.70 2.58

    1.3 Excavation in ordinery soilfor the dry laterine pit up to 1.50a depth of 5.2 and for foundation 0.80trenches 2 0.70 1.68

    2.403.20

    1 4.00 30.72 M3 pit excavation

    2.40 foundation trench in two sides 4.262 0.80

    0.70 2.48 m 3.101.6 0.60

    2 0.80 2 5.20 19.340.70

    1.79 1.1034.99 m

    3NET TOTAL 0.60

    1.4 Excavation in rock formation 2 5.20 6.86for the dry laterine pit up to 26.20a depth of 5.2 and for foundation 30.46

    trenches

    2.403.20

    1 1.209.22

    1.5 Selected Excavated fillunder Hard core

    1.001 1.00 1.00 m

    3NET TOTAL

    0.253.00 2.00

    1.5 m3

    NET TOTAL

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

    Block: Dry Latrine

    1.6 25cm thick basaltic or

    equivalent stone hard core well

    roled ..

  • 7/31/2019 Tekle K.mariam First Payment

    14/34

    1.5 Cart away surples excavated0.00 0.00 materials

    0.00

    0.00 m3

    NET TOTAL

    Project:Dry Latrine

    No. LXWXH Quantity Description No. LXWXH Quantity

    3.CONCRETE WORK

    3.1. 15 CM thick reinforced

    concrete floorslab concrete

    quality c-20,320Kg/m3

    5.60 15.861 2.33 13.05 M2 1 0.20 3.17

    5.60

    1 2.33 13.0513.05 M2 Total 2.40

    3.2.STEEL REINFORCEMENT FOR

    GRADE BEAM 1 0.20 0.48

    0.601 0.60 0.36

    16.34a) 10mm deformed bars

    52.28 KG NET TOTAL

    b) 12mm deformed bars138.28 KG NET TOTAL

    Project:Dry Latrine

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

    Block: Dry Latrine

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

    Block: Dry Latrine

  • 7/31/2019 Tekle K.mariam First Payment

    15/34

    No. LXWXH Quantity Description No. LXWXH Quantity

    4.CONCRETE WORK4.1. e n orce concrete c ass c-

    20 5.60A.in 20*20 cm elevation col 2 0.25 2.80

    0.200.20 5.406 2.80 0.67 m

    4 0.25 5.40

    0.67 m3

    NET TOTAL

    5.30 b.in 20*20 cm upper tie beam 2.330.20 2 0.25 1.17

    2 0.20 0.42 m

    1.93 1.930.20 8 0.25 3.86

    1 0.20 0.08 m

    0.60

    1.94 2 0.20 0.240.202 0.15 0.12 m

    0.75

    1.20 4 0.15 0.450.15 1.00

    4 0.20 0.14 2 0.20 0.400.66 m

    3NET TOTAL 14.32

    C.In 6cm thick reinforcementconcrete window sills. Here priceincludes form work & 8mmdeformed bars c/c 20cm both ways 2.38

    2 0.89 1.78 0.254 2.80 11.20 4 2.38

    12.98 ml NET TOTAL 16.70

    4.2.STEEL REINFORCEMENT FOR

    UPPER TIE BEAM

    a) 6mm plain bars29.68 KG NET TOTAL

    b) 12mm deformed bars138.28 KG NET TOTAL

    Project:Dry Latrine

    No. LXWXH Quantity Description No. LXWXH Quantity

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

    Block: Dry Latrine

  • 7/31/2019 Tekle K.mariam First Payment

    16/34

    5.HOLLOW CONCRETE BLOCK WALL5.1.20 20 40cm c ass a ow

    concrete block

    4.702 3.15 29.61 m

    6 3.85 23.103 5.3 15.90

    3.60 39.00

    2 3.60 25.92 m2

    0.5 Above Top Tie Beam 3 3.00 9.002 4.70 3 5.00 15.00

    0.75 3.53 24.00deduction

    10 2.23 22.30m Windows 22.30

    1.00 2 2.23 4.462 2.58 5.16 m Doors 4 1.0 4.00

    above beam 8.46

    m2

    53.90 m2

    NET TOTAL 10

    0

    m 2.002 1.70

    2.80 9.524.70

    3.15 2 3.15 29.611 2.80 8.82 m

    18.34 m2

    NET TOTAL 3.606.ROOFING 2 3.60 25.926.1. G-30 galvanazed C.I.S 0.5

    2 4.70L=5.3+1*2+0.1*2=7.5M 0.75 3.53

    W=2.33-0.05*2=2.23M 1.007.50 2 2.58 5.16

    2 2.23 33.45 53.90

    5.2.15*20*40cm class "B" hallow

    concrete block

  • 7/31/2019 Tekle K.mariam First Payment

    17/34

    33.45 m2

    NET TOTAL

    Project:Dry Latrine

    No. LXWXH Quantity Description No. LXWXH Quantity

    3.15 Internal wall 0.894 2.80 35.28 2 0.60 1.07

    4.702 2.80 26.32 m2 1.00

    2 2.38 4.761.45

    4 2.80 16.24 m2 1.932 0.35 1.35

    2.00

    4 2.80 22.40 m2 4 1.19 4.76Deduction 2.80

    1.00 4 0.20 2.242 2.58 5.16 m2

    95.08 m2

    NET TOTAL 0.892 0.20 0.36

    14. Painting

    14.1Apply three coats of approved

    plastic paint to all internal walls &

    plastered beam surfaces 1.00a)To external wall 2 0.20 0.40

    53.90 Ditto But as item No. 9.1,a53.90 M2 otal 0.77

    b)To internal wall 4 0.15 0.4695.08 Ditto But as item No. 9.1,b95.08 M2 otal 2.15

    4 0.15 1.29

    2.382 0.20 0.95

    0.604 0.20 0.48

    18.12

    68.00

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

    Block: Dry Latrine

    Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda

  • 7/31/2019 Tekle K.mariam First Payment

    18/34

  • 7/31/2019 Tekle K.mariam First Payment

    19/34

    Take-off No_____________

    Description2.MASONRY WORK. . asa c or equ va en c

    stone masonry foundation trench, wall

    thickness varries acccorrding to the

    drawing

    FOR foundation trenchfor pit

    m

    m

    m

    M3 Total

    Masonry For The wall of the pit

    m

    M3 TotalM3 Total

  • 7/31/2019 Tekle K.mariam First Payment

    20/34

    Take-off No_____________

    Description

    3.4 Provide cut and fix in position sawn

    pine wood or equivalent form work for

    sides of Floor slab

    P=(2.33+5.6)*2=15.86Mm

    m for slab

    For man holeDeduction

    For man Coverm

    2NET TOTAL

    Take-off No_____________

  • 7/31/2019 Tekle K.mariam First Payment

    21/34

    Description

    4.3.provide cut & fix in position swan pine

    wood form work for upper tie beam

    TOP TIE BEAMm2 external

    m external

    m internal

    m soffit of windows

    m soffit of doors

    m2

    NET TOTAL

    for columnsm

    2NET TOTAL

    m2

    NET TOTAL 28.6

    Take-off No_____________

    Description

  • 7/31/2019 Tekle K.mariam First Payment

    22/34

    7. Carpentry and Joinery7.1.all timber & ecuallyptus structuremembers shall be well seasonedA. 10-12cm eucalyptus lower/upper

    members(trusses)

    ML NET TOTAL. 8-10cm euca yptus nterna

    members(trusses)

    L=(0.22+0.56)*2+0.9=2.46L=(1.15+1.35)*2=5.00ML NET TOTAL

    C.5*7 cm purlins c/c 90cm

    ML NET TOTAL7.2,Supply & fix 25*2.5cm facia board

    ML NET TOTAL

    7.3,Supply & fix 50mm PVC vent pipe

    PC7.4 40x50 cm z g a or equ va ent s as

    shown on the drawing to cover the dry

    latrine pit holes)

    PC

    8.METAL WORKa meta w n ows an oors s a e

    fabricated of locally manufactured frameLTZ profile

    8.1.Type D2 size .80*2.80cm

    pcs

    9.PLASTERING AND POINTING

    9.1.Apply three coats of cement mortar

    plaster 1:3 to all internal walls including

    above top tie beam.and beam surfaces

    m

    m

    Above Top Tie Beam

    deductionm2 Doors

    Total M2

  • 7/31/2019 Tekle K.mariam First Payment

    23/34

    Take-off No_____________

    Description

    deduction

    m2 windows

    m2 doors

    above t.t .beamm2

    A=0.5*0.9*2.65

    =1.19above roof

    soffit of window

    soffit of doors

    sied of doors

    sied of window

    m2

    NET TOTAL

    m2

    NET TOTAL

    Take-off No_____________

  • 7/31/2019 Tekle K.mariam First Payment

    24/34

    Description

    10.PAVING AND FLOORING10.1.5 t c smoot oor n s e

    cement screed in cement mortar 1:3

    m2

    m2

    DOORSm

    2

    m2

    m2

    NET TOTAL10.2. 100cm w e & 10cm t c mass

    concrete pavement, concrete quality C-

    15,290 KG cement/m3

    of concrete,

    m2

    m2

    NET TOTAL

    10.3. Ditto as 10.3 above but 80cm wide togable sides

    m2

    NET TOTAL

    10.4 30 w e resse stone ra n water

    ditch

    m2

    NET TOTAL

    11. Apply three coats of approved

    plastic paint to all internal walls &

    plastered beam surfacesDitto But as item No. 9.1

    m2

    NET TOTAL

  • 7/31/2019 Tekle K.mariam First Payment

    25/34

    Sno Project Type Location Contract Executed1 ECD Aragure #REF!2 Dry Latrine Egri Hariba 0.00

    0 #REF!

    Contractor Supervisor

    Summary Of Projects

    Total

  • 7/31/2019 Tekle K.mariam First Payment

    26/34

    |W

    Project

    W

    Location

    xsW m/b@T

    y| t+

    Contractor

    x mN!S

    Consultant

    X bnW yKF snD _q& m\rT XSk DrS t+ y\W |/ qrbW : U

    yKF M/w/l/ Certf. No qNDate

    ygNzb# LK(BR)AMOUNT

    BIRR

    Previouse payments

    Investor

    Tekle K/mariam B.C.

    Save the Children, USA

    As per the attached measurements the Value of work executed and/or materialshundred four thousand one hundred eighty sex Birr and 38/100 cent

    Construction of Upgrading of

    Aragure ECD and Egri hariba Dry Latrine EnRegion

    Save the Children, USA

  • 7/31/2019 Tekle K.mariam First Payment

    27/34

    ypDM KF BR

    Amount of Advance Taken (birr)

    XSk ytmls ypDM KF BR

    Amount of Advance Repaid to-date (birr)

    MRm ___________________________________________________________

    Remarks ______________________________________________________________

    Budget Code T1 T2 T3

    23112 2311101 84004000

    DMR TOTAL

  • 7/31/2019 Tekle K.mariam First Payment

    28/34

    trUG**LCertified

    Regional Coordinator/Officer

    Sub Office Manager

    _______________________________ __________________

    ateate

    Prepared

    zUjW

  • 7/31/2019 Tekle K.mariam First Payment

    29/34

    W WL

    Main Contract w/o VAT

    tq{ WL

    Supplementary Contract

    ylW_ | T:C

    Variation orders

    VAT 15%

    .-Q DMR

    Total sum with VAT

    1. xSqD ytkfl

    Previous payments

    tq> DEDUCTIONS

    supplied to-date is 204186.38 (Twos)

    yKF MSKR wrqT q$_R- 01

    First payment certificate - 01

    rimary School

    erta Woreda in Tigray

  • 7/31/2019 Tekle K.mariam First Payment

    30/34

    2. Q>

    Rebate % 15%

    3. m

    4. Contract amount after rebate

    5. Value add tax 15%

    6. Total amount with 15% VAT

    Retention 5%

    7. mq

    Penalty

    8. kQD KF

    Deduction for Advance payment Recovery (20%)9. l@

    Others

    DMR TOTAL

    yt lt+ ykfL gNzB

    l| t+ BR 189612.58 l!kfL ml#N XrUGlN::

    __________________________________

    ________________________________

    T4 T5 T6

    Net Sum due to the Contractor

    We certify that the contractor is now entitled to the sum of Birr189612.58 (Two

    hundred twelve Birr and 58/100 cents)

    -

    -

  • 7/31/2019 Tekle K.mariam First Payment

    31/34

    ymrmrw trUG**LRectified Certified

    WatSan & Infrastructures

    Coordinator

    Program Manager

    /Technical

    Manager/

    __________________ ________________

    ate ate

    Operations Manager

    __________________

  • 7/31/2019 Tekle K.mariam First Payment

    32/34

    ygNzb# LK (BR)AMOUNT BIRR

    -

    -

    ygNzb# LK (BR)AMOUNT (BIRR)

    ygNzb# LK (BR)AMOUNT (BIRR)

    -

    204,186.38

    0.00

    -

    -

    -

  • 7/31/2019 Tekle K.mariam First Payment

    33/34

  • 7/31/2019 Tekle K.mariam First Payment

    34/34

    ate

    Approved

    Country Director

    __________________

    [DL