tekle k.mariam first payment
TRANSCRIPT
-
7/31/2019 Tekle K.mariam First Payment
1/34
Take-off No_____________
Project:ECD
No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h
A-Sub -Structure 2-Masonry work
1-Excavation and earth work 2.1-50cm thick masonery fn
1.1-site clearance Foundn_ Ditto as item no1.3
20.00 L=18+2=20m W=7.5+2=9.5m 18.00 Avg Depth = 0.62+0.55+0.64+0.74+0.70= 0.659.50 190.00 m2 0.65 5
190.00 m2
NET TOTAL 2 0.50 11.7 m3
6.50 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m1.3 Bulk excavation 0.74 4
4 0.50 9.62 m3
0.00 4.00 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m1.3Trench excavation 0.74 4Avg Depth = 0.62+0.55+0.64+0.74+0.70 1 0.50 1.48 m3
18.00 5 22.80 m3 NET TOTAL0.65 = 0.65m
2 0.48 11.23 m3 2.2-Ditto as item2.1 but6.50 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m ANGL (Average Height =50cm)
0.74 4 18.00 Avg D = 0.60+0.40+0.20+0.00 = 0.3 m4 0.48 9.24 m3 0.30 4
4.00 Avg D = 0.60+0.78+0.87+0.70 = 0.74 m 1 0.50 2.7 m3
0.74 4 18.00 Avg D = 0.55+0.30+0.28+0.20 = 0.33m1 0.48 1.42 m3 0.33 4
21.89 m3 NET TOTAL 1 0.50 2.97 m3
1.4 Back fill Avg D = 0.60+0.56+0.55+0.20+0.20+0.006.00 Avg D = 0.60+0.56+0.55+0.30 = 0.5 m 6.50 46.50 4 0.35 = 0.35m
1 0.50 19.5 m3 4 0.50 4.55 m3
6.00 Avg D = 0.28+0.20+0.00+0.0.20 = 0.17m 4.00 Avg D = 0.35m6.50 4 0.35
1 0.17 6.63 1 0.50 0.7 m3 NET TOTAL
4.00 Avg D = 0.28+0.20+0.40+0.30 = 0.3m 10.923.00 42 0.30 7.2 m3
33.33 m3NET TOTAL
6.00 1.5Hard coring
2 6.50 78 m2
4.002 3.00 24 m2
102 m2
NET TOTAL
1.6Cart away
0.00
0.20 0.00DITTO AS ITEM 1.1 BUT MELTI- BY0.20 CM
0.00 DITTO AS ITEM 1.3 trench excavtion0.00 m3 NET TOTAL
Take-off No_____________
Tekle K/mariam B.C.Site : Aragure Kebele/H/Wejerat Woreda
Block: ECD
contractor_________________ supervisor_________________
-
7/31/2019 Tekle K.mariam First Payment
2/34
Project:ECD
No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h
6.00 3-Concrete Work B.SUPER STRUCTURE
6.503.1 -10cm thick reinforced concrete
floofslab 4.Concrete work0 0.10 0.00 m
34.1 reinforced concrete c-20
4.00 a) -50*20cm top tie beam c-203.00 18.00
0 0.10 0.00 m3
0.50
0.00 m3
NET TOTAL 2 0.20 3.60 m3
3.2 -50*20cm grade beam c-20 6.5018.00 0.50
0.50 4 0.20 2.60 m3
2 0.20 3.60 m3
4.006.50 0.500.50 1 0.20 0.40 m3
4 0.20 2.60 m3
6.60 m3
NET TOTAL
4.00
0.50
B.In 6cm thick reinforcement concretewindow sills. Here price includes form work
& 8mm deformed bars c/c 20cm both way
1 0.20 0.40 m3
0 1.60 0.00
6.60 m3NET TOTAL 0 1.15 0.00
3.3 Steel reinforcement
(a)Q6mm 0.00 mNET TOTAL#REF! Kg 4.2 Steel reinforcement
(a)Q6mm#REF! b)Q8mm #REF! Kg
b)Q12mmC)Q12mm #REF! Kg
#REF! Kg 4.3 -form work
3.4 -form work 18.00 External18.00 External 2 0.20 7.202 0.20 7.20 7.50
7.50 2 0.20 3.002 0.20 3.00 6.50 Internal
6.50 Internal 4 0.20 5.204 0.20 5.20 6.00
6.00 4 0.20 4.804 0.20 4.80 3.00
3.00 4 0.20 2.404 0.20 2.40 4.00
4.00 4 0.20 3.204 0.20 3.20 ` 25.80 m
2NET TOTAL
25.80 m2
NET TOTAL
3.5.concrete ancillaries expantion joint
0 6.50 0.000 6.00 0.000 4.00 0.000 3.00 0.00
0.00 M NET TOTAL
Take-off No_____________
Tekle K/mariam B.C.
Tekle K/mariam B.C.Site : Aragure Kebele/H/Wejerat Woreda
Block: ECD
contractor_________________ supervisor_________________
-
7/31/2019 Tekle K.mariam First Payment
3/34
Site : Aragure Kebele/H/Wejerat Woreda
contractor_________________ supervisor_________________
-
7/31/2019 Tekle K.mariam First Payment
4/34
Project:ECD
No Size Qty Description No Size Qyt Descriptionl*w*h l*w*h
5-Walling
18.00 5.1-50cm thick dressed0.50 stone masonry
2 2.80 50.40 m3
6.500.50
4 2.80 36.40 m3
4.000.50
1 2.80 5.60 m3
1.00 Dedaction (To be checked again)0.50 Doors
4 2.80 5.60 m3
1.15 W 20.50
8 1.80 8.28 m3
1.60 W10.60
4 0.50 1.92 m3
76.6 m3 NET TOTAL
Block: ECD
contractor_________________ supervisor_________________
-
7/31/2019 Tekle K.mariam First Payment
5/34
3.250.65
2.950.7375
1.20.3
2.01 1.330.5025 0.3325
0.680.17 2.11
0.351667
1.18
0.295
contractor_________________ supervisor_________________
-
7/31/2019 Tekle K.mariam First Payment
6/34
Contractor:-Tekle K/mariam B.C.
construction Type;-Natural StoneBuilding;-Childhood Development Center(ECD)
Location;-Enderta sitesSite name ;-Aragure
Contrat ExcutedA-SUB STRUCTURE
1 Excavation &Earth Work1.1 Site clerance m 0.001.2 Bulk Excavation m3 0.001.3 Trench excavation m3 0.001.4 Fill under hard core borrowed m3 0.001.5 Hard cring 25cm thick m2 0.001.6 Cart away m3 0.00
Sub total(1) -2 Masonry work2.1 50cm thick masoneryBNGL m3 0.002.2 Dittoas2.1butANGL m3 0.00
Sub total(2) -3 .Concrete work
3.1 10cm Thick RC floor slab m2
0.003.2 RC for 50*20cmgrade beam m3 0.003.3 Steel reinforcement 0.00
(a)Q6mm plain bars kg 0.00b)12mmDeformed bars k 0.00
12mmDeformed bars k 0.003.4 Form work for grade beam m2 0.003.5 concrete ancillaries expansion joint m 0.00
-
4.1m3 0.00
m0.00
4.20.00
kg 0.00kg 0.00
4.3 m2 0.00
-
5.1 50cm thick dressed masonery 0.005.2 Ditto5.1 above top tie beam m3 0.00
Sub total(5) m3 -
6.1 0.00m2 -
Contractor:-Tekle K/mariam B.C.
construction Type;-Natural Stone
Building;-Childhood Development Center(ECD)
Location;-Enderta sitesSite name ;-Aragure
Quantity
Unit Price Total Price
Sub total (3)
UnitNo Description
Provide cut and fix in position sawn pine wood orequivalent formwork for upper tie beam.
Sub total 4
6. Roofing
G-30 galvanized corrugated iron sheet roofing fixedSub total 6
B. Super Structure
4. Concrete work
Reinforced concrete class C-20,320kga)In 50x20cm upper tie beamb)In 6cm thick reinforced concrete window sills.Here price includes form work & 8cm deformedbars c/c 20cm both ways.Steel reinforcement for upper T. beam cut bent &placed in position unit price includes cuttingbending placing in position & tying bars.
a) 6mm plain bars
b) 12mm deformed bars
_________________________CONTRACTOR
_________________________SUPERVISOR
-
7/31/2019 Tekle K.mariam First Payment
7/34
No Unit TotalContrat Excuted Price Price
7.1 M 350 0.00 13 0.00M 250 0.00 12 0.00
M 300 0.00 40 0.007.2 M 50 0.00 60 0.00-
8metal windows &doors LTZ
8.1 Type D1,size 100*280cm No. 4 0 2000 0.008.2 Type W1, size 115*180 No. 10 0 1800 0.00
TypeW2, size 160*60 wire mesh No. 4 0 1500 0.008.3 Security grill LtZ size 115*180cm No. 9 0 1000 0.00
-
9.1 m2
259 #REF! 50 #REF!
9.2 m2
30 #REF! 20 #REF!
9.3 m2
26.4 #REF! 500 #REF!#REF!
10.1 m2 107 0 50 0.0010.2 m2 36 #REF! 180 #REF!10.3 m2 19 #REF! 180 #REF!
#REF!
#REF!
Quantity
Sub total(8)
Metal work
Description Unit
c)5x7cm treated pinewood purlins c/c 90cm.Supply and fix 25x2.5cm carraro or equivalent
cement mortar 1:3pavement, concrete quality C-15,290 KGDitto as 10.3 above but 80cm wide to gable sidesSub total 10
Grand Total
9.PLASTERING AND POINTING
Apply three coats of cement mortar plaster 1:3 toall internal walls including above top tie beam.andbeam surfacesAll external stone masonry foundation wall above
NGL shall be raked out to a depth of 25mm andpointed in cement mortar 1:3
Ditto as 9.2 above but external wall above gradebeam
Sub total 9
10.PAVING AND FLOORING
Sub total 7
7.Carpentry and joinery
All timber & eucalptus structural members shall be
a) 10-12cm eucalyptus lower/upperb) 8-10cm eucalyptus bracing and internal
_________________________CONTRACTOR
_________________________SUPERVISOR
-
7/31/2019 Tekle K.mariam First Payment
8/34
Contractor:-Tekle K/mariam B.C.
construction Type;-Natural Stone
Building;-Childhood Development Center(ECD)
Location;-Enderta sitesSite name ;-Aragure
No Discription PriceA-sub structure Contrat Excuted
1 Excavation &Earth work2 Masonry work3 Concrete work
B-SUPER_STRUCTURE
4 Concrete work5 Walling6 Roofing7 Carpenrty&joinery8 Metal work
9 Plastering&pointing10 Paving &Flooring11 Glazing12 Paainting
Total for class Room Building At Hawatsu 0.00 0.00
_________________________CONTRACTOR
_________________________SUPERVISOR
-
7/31/2019 Tekle K.mariam First Payment
9/34
Site-Hawatsu
Unit Total
Contrat Excuted Price Price
A-SUB STRUCTURE
1 Excavation &Earth Work
1.1 Site clerance m
2
190 #REF! 2.50 #REF!1.2 Bulk Excavation m3 45 0.00 1.00 0.001.3 Trench excavation m3 45 #REF! 4.00 #REF!1.4 Fill under hard core borrowed m3 120 #REF! 1.00 #REF!1.5 Hard cring 25cm thick m2 108 #REF! 150.00 #REF!1.6 Cart away m3 128 #REF! 15.00 #REF!
Sub total(1) #REF!2 Masonry work2.1 50cm thick masoneryBNGL m3 45 #REF! 300.00 #REF!2.2 Dittoas2.1butANGL m3 25 #REF! 400.00 #REF!
Sub total(2) #REF!3 .Concrete work
3.1 10cm Thick RC floor slab m2
10.8 #REF! 1350 #REF!
3.2 RC for 50*20cmgrade beam m3 6.4 #REF! 1350 #REF!3.3 Steel reinforcement 0.00
(a)Q6mm plain bars kg 80 #REF! 23 #REF!b)12mmDeformed bars kg 310 #REF! 19 #REF!12mmDeformed bars kg 260 #REF! 19 #REF!
3.4 Form work for grade beam m2 22 #REF! 100 #REF!3.5 concrete ancillaries expansion joint m 86 #REF! 60 #REF!
Sub total (3) #REF!
4.1m3 6.4 #REF! 1350 #REF!m 14.4 #REF! 140 #REF!
4.2 0.00kg 98 #REF! 19 #REF!kg 260 #REF! 19 #REF!
4.3 m2
42 #REF! 100 #REF!#REF!5.1 50cm thick dressed masonery 86.8 #REF! 580 #REF!5.2 Ditto5.1 above top tie beam m3 14.1 #REF! 580 #REF!
Sub total(5) m3 #REF!
6.1 190 #REF! 210 #REF!m2 #REF!
Unit
Description Quantity
G-30 galvanized corrugated iron sheet roofing fixedSub total 6
6. Roofing
Reinforced concrete class C-20,320kga)In 50x20cm upper tie beamb)In 6cm thick reinforced concrete window sills.Steel reinforcement for upper T. beam cut bent &a) 6mm plain barsb) 12mm deformed barsProvide cut and fix in position sawn pine wood orequivalent formwork for upper tie beam.Sub total 4
B. Super Structure4. Concrete work
No
_________________________CONTRACTOR
_________________________SUPERVISOR
-
7/31/2019 Tekle K.mariam First Payment
10/34
Site-Hawatsu
No Description Unit Total
Contrat Excuted Price Price
7.1 M 350 #REF! 13 #REF!M 250 #REF! 12 #REF!M 300 #REF! 40 #REF!
7.2 M 50 #REF! 60 #REF!#REF!
8 Metal workmetal windows &doors LTZ
8.1 Type D1,size 100*280cm No. 4 #REF! 2000 #REF!8.2 Type W1, size 115*180 No. 10 #REF! 1800 #REF!
TypeW2, size 160*60 wire mesh No. 4 #REF! 1500 #REF!8.3 Security grill LtZ size 115*180cm No. 9 #REF! 1000 #REF!
Sub total(8) #REF!
9.1 m2 259 #REF! 50 #REF!9.2 m2 30 #REF! 20 #REF!9.3 m2 26.4 #REF! 500 #REF!
#REF!
10.1 m2 107 50 0.0010.2 m2 36 #REF! 50 #REF!10.3 m2 19 #REF! 180 #REF!
#REF!
#REF!
Quantity
9.PLASTERING AND POINTINGall internal walls including above top tie beam.andNGL shall be raked out to a depth of 25mm and
All timber & eucalptus structural members shall bea) 10-12cm eucalyptus lower/upperb) 8-10cm eucalyptus bracing and internalc)5x7cm treated pinewood purlins c/c 90cm.
beam
Ditto as 10.3 above but 80cm wide to gable sides
Sub total 9
10.PAVING AND FLOORINGcement mortar 1:3pavement, concrete quality C-15,290 KG
Supply and fix 25x2.5cm carraro or equivalentSub total 7
7.Carpentry and joinery
Sub total 10
Grand Total
_________________________CONTRACTOR
_________________________SUPERVISOR
-
7/31/2019 Tekle K.mariam First Payment
11/34
Contractor:-Tekle K/mariam B.C.
Building;-Childhood Development Center(ECD)
Site- Aragure
Location Bar Length No bars No of Total No
Description Dia Schedule M Mem of bars Q 6 Q 8 Q 12
Top 12 18.78 2.00 2 4 75.12Bottom 12 18.48 2.00 2 4 73.92stiraps C/C 20 6 1.30 91.00 2 182 236.60
Top 12 7.80 2.00 4 8 62.40Bottom 12 7.50 2.00 4 8 60.00stiraps C/c 20cm 6.5 1.30 34.00 4 136 176.80
Top 12 5.30 2.00 1 2 10.60Bottom 12 5.00 2.00 1 2 10.00stiraps C/c 20cm 6 1.30 21.00 1 21 27.30
Total Length 440.70 292.04
Weight Kg/m 0.222 0.395 0.888
Total Weight 97.84 259.33
Contractor:-Tekle K/mariam B.C.
Building;-Childhood Development Center(ECD)Site- Aragure
SUB TOTALNo.Bars Elem Tot.No Dia.6 Dia.8 Dia.10 Dia.12
Top 12 18.78 2.00 2 4 75.12Bottom 12 18.48 2.00 2 4 73.92stiraps C/C 20 6 1.30 91.00 2 182 236.60
Top 12 7.80 2.00 4 8 62.40Bottom 12 7.50 2.00 4 8 60.00stiraps C/c 20cm 6.5 1.30 34.00 4 136 176.80
Top 12 5.30 2.00 1 2 10.60Bottom 12 5.00 2.00 1 2 10.00stiraps C/c 20cm 6 1.30 21.00 1 21 27.30
440.7 292.040.222 0.395 0.617 0.888
97.84 259.33
Length(mete
r)
No.of Bars
TOTAL WT.(KG)
Reinforcement bar Schedule
Total Length
NIT WEIGHT(KG\M
Reinforcement bar Schedule
BAR SCHEDULE FOR GRADE BEAM
BAR SCHEDULE FOR TOP TIE BEAM
Location Shape
Dia(m
m)
-
7/31/2019 Tekle K.mariam First Payment
12/34
-
7/31/2019 Tekle K.mariam First Payment
13/34
Project:Dry Latrine
No. LXWXH Quantity Description No. LXWXH QuantityA-Sub-structure
1-Excavation & Earth work
1.1.Clear the site and remove top
soil at an average depth of 20cm
7.5 L= 3.5 + 2 *2=7.5 m 2.301 6.00 45.00 W= 2+2*2= 6 m 0.80
45.00 m2
2 0.70 2.58
1.3 Excavation in ordinery soilfor the dry laterine pit up to 1.50a depth of 5.2 and for foundation 0.80trenches 2 0.70 1.68
2.403.20
1 4.00 30.72 M3 pit excavation
2.40 foundation trench in two sides 4.262 0.80
0.70 2.48 m 3.101.6 0.60
2 0.80 2 5.20 19.340.70
1.79 1.1034.99 m
3NET TOTAL 0.60
1.4 Excavation in rock formation 2 5.20 6.86for the dry laterine pit up to 26.20a depth of 5.2 and for foundation 30.46
trenches
2.403.20
1 1.209.22
1.5 Selected Excavated fillunder Hard core
1.001 1.00 1.00 m
3NET TOTAL
0.253.00 2.00
1.5 m3
NET TOTAL
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
Block: Dry Latrine
1.6 25cm thick basaltic or
equivalent stone hard core well
roled ..
-
7/31/2019 Tekle K.mariam First Payment
14/34
1.5 Cart away surples excavated0.00 0.00 materials
0.00
0.00 m3
NET TOTAL
Project:Dry Latrine
No. LXWXH Quantity Description No. LXWXH Quantity
3.CONCRETE WORK
3.1. 15 CM thick reinforced
concrete floorslab concrete
quality c-20,320Kg/m3
5.60 15.861 2.33 13.05 M2 1 0.20 3.17
5.60
1 2.33 13.0513.05 M2 Total 2.40
3.2.STEEL REINFORCEMENT FOR
GRADE BEAM 1 0.20 0.48
0.601 0.60 0.36
16.34a) 10mm deformed bars
52.28 KG NET TOTAL
b) 12mm deformed bars138.28 KG NET TOTAL
Project:Dry Latrine
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
Block: Dry Latrine
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
Block: Dry Latrine
-
7/31/2019 Tekle K.mariam First Payment
15/34
No. LXWXH Quantity Description No. LXWXH Quantity
4.CONCRETE WORK4.1. e n orce concrete c ass c-
20 5.60A.in 20*20 cm elevation col 2 0.25 2.80
0.200.20 5.406 2.80 0.67 m
4 0.25 5.40
0.67 m3
NET TOTAL
5.30 b.in 20*20 cm upper tie beam 2.330.20 2 0.25 1.17
2 0.20 0.42 m
1.93 1.930.20 8 0.25 3.86
1 0.20 0.08 m
0.60
1.94 2 0.20 0.240.202 0.15 0.12 m
0.75
1.20 4 0.15 0.450.15 1.00
4 0.20 0.14 2 0.20 0.400.66 m
3NET TOTAL 14.32
C.In 6cm thick reinforcementconcrete window sills. Here priceincludes form work & 8mmdeformed bars c/c 20cm both ways 2.38
2 0.89 1.78 0.254 2.80 11.20 4 2.38
12.98 ml NET TOTAL 16.70
4.2.STEEL REINFORCEMENT FOR
UPPER TIE BEAM
a) 6mm plain bars29.68 KG NET TOTAL
b) 12mm deformed bars138.28 KG NET TOTAL
Project:Dry Latrine
No. LXWXH Quantity Description No. LXWXH Quantity
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
Block: Dry Latrine
-
7/31/2019 Tekle K.mariam First Payment
16/34
5.HOLLOW CONCRETE BLOCK WALL5.1.20 20 40cm c ass a ow
concrete block
4.702 3.15 29.61 m
6 3.85 23.103 5.3 15.90
3.60 39.00
2 3.60 25.92 m2
0.5 Above Top Tie Beam 3 3.00 9.002 4.70 3 5.00 15.00
0.75 3.53 24.00deduction
10 2.23 22.30m Windows 22.30
1.00 2 2.23 4.462 2.58 5.16 m Doors 4 1.0 4.00
above beam 8.46
m2
53.90 m2
NET TOTAL 10
0
m 2.002 1.70
2.80 9.524.70
3.15 2 3.15 29.611 2.80 8.82 m
18.34 m2
NET TOTAL 3.606.ROOFING 2 3.60 25.926.1. G-30 galvanazed C.I.S 0.5
2 4.70L=5.3+1*2+0.1*2=7.5M 0.75 3.53
W=2.33-0.05*2=2.23M 1.007.50 2 2.58 5.16
2 2.23 33.45 53.90
5.2.15*20*40cm class "B" hallow
concrete block
-
7/31/2019 Tekle K.mariam First Payment
17/34
33.45 m2
NET TOTAL
Project:Dry Latrine
No. LXWXH Quantity Description No. LXWXH Quantity
3.15 Internal wall 0.894 2.80 35.28 2 0.60 1.07
4.702 2.80 26.32 m2 1.00
2 2.38 4.761.45
4 2.80 16.24 m2 1.932 0.35 1.35
2.00
4 2.80 22.40 m2 4 1.19 4.76Deduction 2.80
1.00 4 0.20 2.242 2.58 5.16 m2
95.08 m2
NET TOTAL 0.892 0.20 0.36
14. Painting
14.1Apply three coats of approved
plastic paint to all internal walls &
plastered beam surfaces 1.00a)To external wall 2 0.20 0.40
53.90 Ditto But as item No. 9.1,a53.90 M2 otal 0.77
b)To internal wall 4 0.15 0.4695.08 Ditto But as item No. 9.1,b95.08 M2 otal 2.15
4 0.15 1.29
2.382 0.20 0.95
0.604 0.20 0.48
18.12
68.00
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
Block: Dry Latrine
Tekle K/mariam B.C.Site : Egri Hariba P/school/ Enderta Woreda
-
7/31/2019 Tekle K.mariam First Payment
18/34
-
7/31/2019 Tekle K.mariam First Payment
19/34
Take-off No_____________
Description2.MASONRY WORK. . asa c or equ va en c
stone masonry foundation trench, wall
thickness varries acccorrding to the
drawing
FOR foundation trenchfor pit
m
m
m
M3 Total
Masonry For The wall of the pit
m
M3 TotalM3 Total
-
7/31/2019 Tekle K.mariam First Payment
20/34
Take-off No_____________
Description
3.4 Provide cut and fix in position sawn
pine wood or equivalent form work for
sides of Floor slab
P=(2.33+5.6)*2=15.86Mm
m for slab
For man holeDeduction
For man Coverm
2NET TOTAL
Take-off No_____________
-
7/31/2019 Tekle K.mariam First Payment
21/34
Description
4.3.provide cut & fix in position swan pine
wood form work for upper tie beam
TOP TIE BEAMm2 external
m external
m internal
m soffit of windows
m soffit of doors
m2
NET TOTAL
for columnsm
2NET TOTAL
m2
NET TOTAL 28.6
Take-off No_____________
Description
-
7/31/2019 Tekle K.mariam First Payment
22/34
7. Carpentry and Joinery7.1.all timber & ecuallyptus structuremembers shall be well seasonedA. 10-12cm eucalyptus lower/upper
members(trusses)
ML NET TOTAL. 8-10cm euca yptus nterna
members(trusses)
L=(0.22+0.56)*2+0.9=2.46L=(1.15+1.35)*2=5.00ML NET TOTAL
C.5*7 cm purlins c/c 90cm
ML NET TOTAL7.2,Supply & fix 25*2.5cm facia board
ML NET TOTAL
7.3,Supply & fix 50mm PVC vent pipe
PC7.4 40x50 cm z g a or equ va ent s as
shown on the drawing to cover the dry
latrine pit holes)
PC
8.METAL WORKa meta w n ows an oors s a e
fabricated of locally manufactured frameLTZ profile
8.1.Type D2 size .80*2.80cm
pcs
9.PLASTERING AND POINTING
9.1.Apply three coats of cement mortar
plaster 1:3 to all internal walls including
above top tie beam.and beam surfaces
m
m
Above Top Tie Beam
deductionm2 Doors
Total M2
-
7/31/2019 Tekle K.mariam First Payment
23/34
Take-off No_____________
Description
deduction
m2 windows
m2 doors
above t.t .beamm2
A=0.5*0.9*2.65
=1.19above roof
soffit of window
soffit of doors
sied of doors
sied of window
m2
NET TOTAL
m2
NET TOTAL
Take-off No_____________
-
7/31/2019 Tekle K.mariam First Payment
24/34
Description
10.PAVING AND FLOORING10.1.5 t c smoot oor n s e
cement screed in cement mortar 1:3
m2
m2
DOORSm
2
m2
m2
NET TOTAL10.2. 100cm w e & 10cm t c mass
concrete pavement, concrete quality C-
15,290 KG cement/m3
of concrete,
m2
m2
NET TOTAL
10.3. Ditto as 10.3 above but 80cm wide togable sides
m2
NET TOTAL
10.4 30 w e resse stone ra n water
ditch
m2
NET TOTAL
11. Apply three coats of approved
plastic paint to all internal walls &
plastered beam surfacesDitto But as item No. 9.1
m2
NET TOTAL
-
7/31/2019 Tekle K.mariam First Payment
25/34
Sno Project Type Location Contract Executed1 ECD Aragure #REF!2 Dry Latrine Egri Hariba 0.00
0 #REF!
Contractor Supervisor
Summary Of Projects
Total
-
7/31/2019 Tekle K.mariam First Payment
26/34
|W
Project
W
Location
xsW m/b@T
y| t+
Contractor
x mN!S
Consultant
X bnW yKF snD _q& m\rT XSk DrS t+ y\W |/ qrbW : U
yKF M/w/l/ Certf. No qNDate
ygNzb# LK(BR)AMOUNT
BIRR
Previouse payments
Investor
Tekle K/mariam B.C.
Save the Children, USA
As per the attached measurements the Value of work executed and/or materialshundred four thousand one hundred eighty sex Birr and 38/100 cent
Construction of Upgrading of
Aragure ECD and Egri hariba Dry Latrine EnRegion
Save the Children, USA
-
7/31/2019 Tekle K.mariam First Payment
27/34
ypDM KF BR
Amount of Advance Taken (birr)
XSk ytmls ypDM KF BR
Amount of Advance Repaid to-date (birr)
MRm ___________________________________________________________
Remarks ______________________________________________________________
Budget Code T1 T2 T3
23112 2311101 84004000
DMR TOTAL
-
7/31/2019 Tekle K.mariam First Payment
28/34
trUG**LCertified
Regional Coordinator/Officer
Sub Office Manager
_______________________________ __________________
ateate
Prepared
zUjW
-
7/31/2019 Tekle K.mariam First Payment
29/34
W WL
Main Contract w/o VAT
tq{ WL
Supplementary Contract
ylW_ | T:C
Variation orders
VAT 15%
.-Q DMR
Total sum with VAT
1. xSqD ytkfl
Previous payments
tq> DEDUCTIONS
supplied to-date is 204186.38 (Twos)
yKF MSKR wrqT q$_R- 01
First payment certificate - 01
rimary School
erta Woreda in Tigray
-
7/31/2019 Tekle K.mariam First Payment
30/34
2. Q>
Rebate % 15%
3. m
4. Contract amount after rebate
5. Value add tax 15%
6. Total amount with 15% VAT
Retention 5%
7. mq
Penalty
8. kQD KF
Deduction for Advance payment Recovery (20%)9. l@
Others
DMR TOTAL
yt lt+ ykfL gNzB
l| t+ BR 189612.58 l!kfL ml#N XrUGlN::
__________________________________
________________________________
T4 T5 T6
Net Sum due to the Contractor
We certify that the contractor is now entitled to the sum of Birr189612.58 (Two
hundred twelve Birr and 58/100 cents)
-
-
-
7/31/2019 Tekle K.mariam First Payment
31/34
ymrmrw trUG**LRectified Certified
WatSan & Infrastructures
Coordinator
Program Manager
/Technical
Manager/
__________________ ________________
ate ate
Operations Manager
__________________
-
7/31/2019 Tekle K.mariam First Payment
32/34
ygNzb# LK (BR)AMOUNT BIRR
-
-
ygNzb# LK (BR)AMOUNT (BIRR)
ygNzb# LK (BR)AMOUNT (BIRR)
-
204,186.38
0.00
-
-
-
-
7/31/2019 Tekle K.mariam First Payment
33/34
-
7/31/2019 Tekle K.mariam First Payment
34/34
ate
Approved
Country Director
__________________
[DL