tender document package-1

Upload: umesh-koranga

Post on 01-Mar-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Tender Document Package-1

    1/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    SCHEME

    UDP-78 YR/2015-16

    NAME OF WORK

    (1)

    CONSULTANT

    INFINITE CIVIL SOLUTIONS PVT. LTD.AHMEDABAD

    Mob. : 99250 30601

  • 7/26/2019 Tender Document Package-1

    2/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    /

    ,

    (1)

    YEAR 2016-2017

    ISSUED BY : ________________________________

    Date :

    Consultant :

    Infinite Civil Solutions Pvt. Ltd.

    Infinite House, F.P. 25, Nr. Aditya Elegance, CIMS Hospital

    road, Ahmedabad.

    Mobile-9925030601

  • 7/26/2019 Tender Document Package-1

    3/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    Notice Inviting On-line Tender

    Department Name Nagarpalika

    IFB No / Tender Notice No. 2/2016-2017

    Name of Project UDP-78 YR/2015-16

    Name of WorkConstructing CC road in various areas @ Anklav under

    UDP-78 (package-1)

    Estimated Contract Value (INR) 4181550.78

    Period Of Completion(in Months) 3 Month

    Bidding Type Open

    Joint Venture Not Applicable

    Rebate Not Applicable

    Bid Document Fee : Rs. 5000.00

    Bid Document Fee Payable To : Chief Officer Anklav Nagar Seva Sadan

    Bid Security/EMD (INR) : Rs. 42000.00

    Bid Security/EMD In Favour Of : Chief Officer Anklav Nagar Seva Sadan

    Bid Document Downloading EndDate

    24/06/2016 18 :00 Hrs.

    Pre Bid Meeting 21/06/2016

    Last Date & Time for Receipt ofBids

    24/06/2016 18 :00 Hrs.

    Bid Validity Period 120 Days

    RemarksPhysical submission of Tender fee, EMD and otherdocuments up to date 29/06/2016 in the office of ChiefOfficer Anklav Nagar Seva Sadan during office hours.

    Preliminary Stage 30/06/2016 12 :00 Hrs.

    Pre-qualification Stage 30/06/2016 14 :00 Hrs.

    Commercial Stage 30/06/2016 15 :00 Hrs.

  • 7/26/2019 Tender Document Package-1

    4/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    ,

    , .

    .

    : (1)

    D ,

    / /

    ( ) .

    / ,

    .

    / 42000.00 ( ) 1 % ( )

    D.D./ .D.. . D

    C C, AA AA A ADA, AA.

    ,

    D C

    D:

    :

    A:

  • 7/26/2019 Tender Document Package-1

    5/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    1. .

    2. .

    3. C .

    4. C .

    5. .

    6. C . (

    3A) .

    7. C &B . &

    &B.

    8. 20% .

    9. , , &

    .

    10. .. . C

    & D

    .

    11.C & .

    12.C &C

    & .

    Checked by

    A

    A

    A

  • 7/26/2019 Tender Document Package-1

    6/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    (1).

    : 24 ( )

    :

    :

    : 3 ()

    : . 500.00 / . .

    : . .

    ( ) : (1) 1 %

    ( ../...)

    (2) 1.5 %

    (3) 2.5 %

    : 2.24 % ( ) / .

    : 1 % ( )

    : 5 % ( ) (

    )

    : 5 % ( )

    : 15 ()

  • 7/26/2019 Tender Document Package-1

    7/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    APPENDIX

    : 24 ( )

    : :

    : 3 ()

    : 4181550.78

    : 42000.00 /...

    , .

    ( ) : (1) 1 %

    ( ../...)

    (2) 1.5 % (3) 2.5 %

    /

    : 5 % ( )

    : 24/06/2016

    .... : 29/06/2016

    : .

    &

    ++

    :

  • 7/26/2019 Tender Document Package-1

    8/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    GENERAL CONDITION OF CONTRACT

    1. The contractor shall have to attach a list of works executed so far.

    2. The quality and nature of all the materials to be used shall b according

    to the specifications. The samples of these materials shall have to be

    approved by the consultant before ordering them.

    3. Proper arrangements for the labours and workmen for all different types

    of work shall be made by the contractor.

    4. The contractor shall bring to the Engineers or consultant knowledge in

    writing for any extra terms during the works before execution and it

    shall be charged reasonably according to the present market rates in

    case of dispute consultant decision shall be final to both the parties

    without appeal.

    5. The Contractor shall have to pay all the charges livable by authorities

    concerned in connection with the work.

    6. the contractor shall have to deposit an amount stated in the appendix

    (Rupees thirty one thousand against EMD) with the owner bearing no

    interest as security for the due exaction of the work and completion of

    the contract. The same will be returned to the contractor after one

    month of the date of completion of the work.

    7. The owner will be at liberty to cancel some of the item from the contract

    and hand over to some other contractor approved by the Engineer and

    Consultant.

    8. The contractor shall be responsible for all damage to property and for

    injury caused by the work or workmen or person. Animals or things

    and to the supervisory staff of the Owner, Engineer & Contractor and to

    the authorized visitors to the site. He shall offset any insurance

    necessary, and hold the owner entirely fee from all responsibility.

  • 7/26/2019 Tender Document Package-1

    9/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    9. The contractor will at his own expenses clear the site, set out all work

    and provide all necessary labour, page, string, etc. to enable Engineer &

    consultant to check all setting out contractor will correct all errors.

    10. The contractor shall have to enclose a Nationalize bank F.D.R.

    amounting to 1 % of the cost of tender as Earnest money deposit in

    favor of chief officer, Anklav Ngarpalika.

    11. Defect liability period will be of 24 month. i.e. 5% P.G.MONEY will be

    released after 24 month. if there is any damage occurs, contractor

    should have repaired immediately on his own cost. If he fails to do so

    Nagar Palika will repair on behalf of the contractor and deduct the same

    from P.G MONEY. Defect liability period will be after completion of

    work.

    12. The contractor shall have to give binding for completing the work as per

    specification & verbal instruction of the engineer to owner on a required

    stamp paper.

    13. Contractor shall have to finish up the work within the stipulated time

    limit it the contractor fails to do so, then the Engineer and owner are at

    liberty to executer the work at the risk and cost of the contractor after

    issuing the notice will in advance.

    14. Contractor shall have to provide all facilities to laborers as required

    under labour Act. Of Government.

    15. The contractor shall have to keep First Aid Box on site.

    16. Necessary warning signal and caution boards shall have to be provide

    the maintained by the contractor in order to avoid unexpected accident.

    17. The contractor shall not assign the agreement for sublet any portion of

    the work without written consent of the Engineer.

  • 7/26/2019 Tender Document Package-1

    10/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    18. The contractor shall have to engage an authoresss agent who may be

    quite conversant with the technical supervision and to whom Engineer

    or owner may pass instruction for work.

    19. No compensation shall be paid to the contractors for any bad quality of

    work or workmanship rejected by the consultant.

    20. The water used in the work shall be drinkable and it should provided by

    the contractor.

    21. The contractor shall on the request of the Engineer immediately dismiss

    from the work person employed thereon by him who may in the opinion

    of the Engineer be incompetent or misconduct himself and such person

    not be again employed on the work without the permission of the

    Consultant.

    22. The work shall not be considered as completed until the consultant has

    certified in writing that they have been virtually completed and defects

    liability period shall commence from the date of such certificated.

    23. General technical specifications attached with tender. What ever

    applicable to project form the book in considered as tender application.

    24. All necessary drawing of project will be given by consultant.

    25. All the petty items of this work shall be carried out in workman like

    manner.

    26. No Claim of contractor for any extra item shall be ascertained unless

    the extra item done is claiming of clearly distinguishable form the item

    of agreement and is carried out as per instruction of the Engineer in

    charge and consultant.

    27. The contractor shall engage an experienced and qualified supervisor as

    his authoresses agent for this work. They shall be responsible for taking

  • 7/26/2019 Tender Document Package-1

    11/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    from time to time orders regarding work from the engineer in charge

    and carrying them properly.

    28. The contractor shall maintain work order book on work site and design

    and carryout property the orders given by the engineer. This work order

    book shall be surrendered to the department on completion of work.

    29. The contractor shall have to clear the site of work before commencing

    the work and after completion of work without any extra claim.

    30. The contactor shall provide at his own cost all labour and adequate

    facilities for lining out. Setting and checking his work and tacking

    measurement of the same.

    31. The contractor shall have to maintain a regular account of receipt and

    use of controlled materials purchased by him.

    32. The contractor shall provide at his own cost necessary accommodation

    water supply and sanitary arrangement for his staff and labour and

    shall pay direct to the authority concerned royalties and other charges.

    He shall also comply with the regulation of the health department

    regarding materials measures etc.

    33. Water required for execution work shall have to be supplied by

    contractor at his own cost.

    34. Dewatering of trenches, foundation etc. shall be done by contractor at

    his own cost during execution or all item of his work completion in all

    respect.

    35. The contractor shall have to cart at his own cost, pipes specials and

    other materials to site of work.

    36. The contractor shall provide diversion to the existing road if required as

    directed by the Engineer in charge.

  • 7/26/2019 Tender Document Package-1

    12/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    37. In addition to requisite store he contractor shall have to provide at his

    cost suitable temporary office with covered area of 20 sqmt. With

    necessary furniture for use of inspection staff whole on work. The office

    and furniture on completion of the work shall be removed by the

    contractor at his cost.

    38. The contractor shall be responsible to pay complete compensation to

    his staff and to his labours according to labour compensation rules on

    account of accidents and loss of lives etc. due to the accident.

    39. Any item not covered in the schedule-B but required to be executed be

    out by the contractor at the rate for such item available in divisional

    schedule of rates in forces in time of giving order for extra item.

    40. The details specification for materials unless otherwise specified in the

    description of item shall apply and binding to contactor as narrated in

    his tender.

    41. In case any dispute regarding specification works the specification as

    per R & B department of state and other concerned department if any

    standard specification for relevant shall be final and binding to the

    contractor.

    42. In case in excavation line any disturb of telephone line, Electric line,

    Drainage line, water supply line or any other shall be managed for

    remove and reinstating with necessary materials by the contractor at

    his own cost.

    43. In case in excavation for line or chamber necessary of dewatering

    contractor shall be provide arrangement at his own cost.

    44. The Contractor shall bind for quality of work and his 5% (Five Percent)

    deposit shall released after One Years of completion if work is satisfied

    that times & after getting NOC from consultant.

  • 7/26/2019 Tender Document Package-1

    13/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    45. Condition of administrative order must bind the contractor.

    46. Payment should be released as per the availability of grants.

    47. All the terms condition and technical specification of G.W.S.S. B/ PWD

    hand book in force must bind the contractor.

    48. In the case of work for which there is no such specification, such work

    shall be carried out in accordance with the standard specification or as

    directed by E.I.C. and Consultant.

    49. In the even of a discrepancy between description in words and figures

    quoted by a tenderer in the rates column, the description in words shall

    prevail.

    50. Definition :

    a.The contract document consists of the Agreement, The General

    condition of the contract, specification and Bills of Quantities

    including all modification thereof incorporated in the document

    before the execution and the contract drawings prepared by the

    Architect form time to time. These form the contract.

    b.The Employer : The President/Chief officer

    Anklav Nagarpalika, Anklav.

    Dist Anand.

    The Consulting Engineer/

    Architect : Infinite Civil Solution Pvt. Ltd.

    Ahmedabad.

    Are those mentioned as such in the agreement and shall include

    their legal representatives, assignees or successors. They are

    treated through our contract document as if each were of the

    singular number and masculine gender.

    c.The date of virtual completion of a project or specified area of a

    project is the date when construction is sufficiently completed in

    accordance with the contract document as modified by any change

  • 7/26/2019 Tender Document Package-1

    14/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    or variation orders agreed by the parties, so that the owner can

    occupy the project for the use it was intended.

    51. Schedule of Quantities :

    The Schedule of quantities given in the contract bill are provisional and

    are meant to indicate the intent of the work and to provide a uniform

    basis for tendering, The employer reserves the right to increase or

    decrease any of the quantities or to totally omit any item of work and

    the contract shall not claim any extra or demand on these a rounds.

    52. Contract Drawing :

    a. In general the drawings shall indicate dimensions positions and type

    of constructions: the specifications shall indicate the quantities and

    the methods : the bill of quantities shall indicate the quantum and

    the rate for each item of work. Any work indicated on the drawings

    and not mentioned in the specifications or vice versa shall e

    furnished as through fully set forth in both. Work not specifically

    detailed, called for, marked of the specified shall be the same as

    similar parts that are detailed, marked or specified.

    b.The contractors work shall not deviate form the drawing and the

    specifications. The consulting Engineer / Architects interpretation of

    these document shall be final and without appeal.

    c. Errors or inconsistencies shall be promptly brought to the attention

    of the consulting Engineer / Architects interpretation or corrections.

    Local conditions which may affect attention. If at any time, it is

    discovered that work is done which is not in accordance with the

    contract drawings and specifications. The contractor of defective

    work shall not be a basis for any claim for extension of time.

    53. Scope and intent :

    a. Scope :

    The general charter and the scope of the work in illustrated and

    defined by the specifications and the Bills of quantities herewith

    attached and by the signed drawings. If the contractor shall find

    any discrepancy and/or the contract bills be shall immediately

  • 7/26/2019 Tender Document Package-1

    15/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    give to the employer a written notice specifying the discrepancy or

    divergence and the consulting Engineer shall issue instruction in

    regard thereto.

    54. Samples :

    a. After the award of the contract, the contractor shall furnish for the

    approval of the Employer, Consulting Engineer, with such

    promptness as to cause no delay in his work or in that of any other

    sub-contractor, samples required by the specifications shall e

    delivered as directed by the Employer, consulting Engineer.

    b.The Employer Consulting Engineer / Architect Shall Check and

    approve such samples, with reasonable promptness only for

    conformity with the design concept of the project and for compliance

    with the information in the contract Documents. The work shall be

    in accordance with approved samples.

    55. Progress Chart :

    The Contractor shall prepare progress chart and submit the same for

    approval of the authorities and for his record within twenty-one days

    of the Award of the Contract. The Charts shall indicate the expected

    date of commencement and completion of each of the items of the

    work and shall be in form approved by the scheduling of samples

    and approvals.

    56. Architect, Consulting Engineer, Status and Decision :

    a. Consulting Engineer: Consulting Engineer shall periodically visit the

    site to familiarize himself generally with the progress and the quality

    of the work and to determine in general if the work is proceeding in

    accordance with the contract Document. He shall not be required to

    make exhaustive or continuous on site inspection to check the

    quality or quantity of the work and he shall note be responsible for

    the contractors failure to carry the construction work in accordance

    with the contract documents During such visits the contract

    document, during such visits and on basis of his observations while

  • 7/26/2019 Tender Document Package-1

    16/20

  • 7/26/2019 Tender Document Package-1

    17/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    to have infringed any patent rights in relation to any such articles

    processes and inventions.

    60. Claim for Extra :

    When any instruction or decision at site involve an extract or where by

    the contractor may plan to claim extra, it shall be the responsibility of

    the contractor to inform the employer, consulting Engineer/Architect of

    the extra amount and get written authorization from the said persons

    before proceeding with the work involved. Any modification carried out

    for expenditure of simplifying work at the request of the contractor or

    his representatives shall not be taken as the basis for claiming an extra.

    61. Fluctuations :

    The Contractor shall not claim any extra for fluctuations of prices and

    the contract prices shall not be subject to any rise or fall of prices.

    62. Materials and Workmanship:

    a. All materials and workmanship shall be as per the relevant code of

    I.S.I. specifications and of approved type and the contractor shall

    immediately remove form the works any material and / or

    workmanship which in the opinion of the consulting

    Engineer/Architect are defective or unsuitable and shall substitute

    proper material and/or workmanship at his own cost. The terms

    approval used in connection with this contract shall mean the

    approval of the consulting Engineer/Architect.

    63. Virtual Completion and defects Liability Period :

    a. When in the opinion of the consulting Engineer the works are

    practically completed, he shall forthwith issue a certificate to that

    effect and Virtual completion of the works shall be deemed for all the

    purpose of this contract to have taken place on the day named in

    such certificates.

    b. Any defects shrinkage or other faults which shall appear within theDefects liability Period Stated in the appendix to these conditions

  • 7/26/2019 Tender Document Package-1

    18/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    and which are due to material and workmanship not in accordance

    with this contract shall be specified not in by the employer in a

    schedule of Defects which he shall deliver to the contract not later

    than 14 days after the expiration of the said defects liabilities period

    and within a reasonable time after receipt of such schedule the

    defects shrinkages and other faults therein specified shall be made

    good by the contractor and (unless the consulting Engineer shall

    otherwise instruct in which case, the contract sum shall be adjusted

    accordingly). Entirely at his own cost.

    c. Not withstanding sub-clause (2) of this condition the consulting

    Engineer may whenever he considers it necessary so to do, issue

    instructions requiring any defect, shrinkages or other faults which

    shall appear within the defects liability period named in the

    appendix to these condition and which is due to materials and

    workmanship not in accordance with this contract to be made good

    and the contractor shall within a reasonable time after receipt of

    such instructions comply with the same (and unless the consulting

    Engineer shall otherwise instruct in which case the contract sum

    shall be adjusted accordingly entirely at his own cost, provided that

    no such instructions shall be issued after 14 days form the

    expiration of the said Defects liability period.

    d. When in the opinion the consulting Engineer any defects shrinkages

    or other defaults which he may have required to be made good under

    sub-clause (2) and (3) of this condition shall have been made good he

    shall issue a certificate to that effect, and completion of making good

    defects shall be deemed for all the purposes of this contract to have

    taken place on the day named in such certificates.

    e. In on case shall be contractor be required to make good at his own

    cost any damage which may appear after virtual completion of the

    work, unless the consulting Engineer shall certify that such damage

    is due to injury which took place before virtual completion of the

    works.

  • 7/26/2019 Tender Document Package-1

    19/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    64. Payment employer may withhold or on account of a subsequently

    discovered evidence nullify the whole or a part of any certificate to such

    extent as may be necessary in his reasonable opinion to protect the

    employer form loss on account of :

    a. Defective work not remedied.

    b. Failure of the contractor to make payments properly to sub-

    contractor or for materials or labour.

    c. A reasonable doubt that the contract can be completed for the

    balance then unpaid.

    d. Damage to another contractor or sub-contractor.

    e. Claims failed on reasonable evidence indication probable filling

    of claims.

    65. Guarantee :

    a. Besides guaranties required elsewhere, the contractor shall

    guaranties the work in general for one year as noted under clause of

    the conditions.

    66. Arbitrator :

    All dispute and differences of any kind whatever arising out of or in

    connection with the contract or the carrying out of the works (whether

    during the progress of the works or after their completion and progress

    of the works or after the determination, abandonment or breach of the

    contract shall be referred to and settled by the consulting

    Engineer/Architect/The President who shall state his decision in

    writing. Such decision may be in the form of a final certificate or

    otherwise. The decision of the Consulting Engineer/Architect/The Chief

    Manager with respect of any of the excepted matters shall be final and

    without appeal.

    67. Decision:

    The Consulting Engineer: The Consulting Engineer/Architect within a

    reasonable time make decisions on all claims of the employer or the

    contractor and all other matters relating to the execution and progress

    of the work or the interpretation of the contract document. The

  • 7/26/2019 Tender Document Package-1

    20/20

    INFINITE CIVIL SOLUTIONS PVT. LTD.

    consulting Engineer/Architect may in his absolute discretion and from

    time to time issue further drawings. Details and/or written

    instructions, written directions and written explanations in regard to:

    1. Variation or modification of the design.

    2. The quality or quantity of works or the additions or omission or

    substitution of any work.

    3. Any discrepancy between the drawings and/or specifications.

    4. The removal and/or re-execution of any works executed by the

    contractor.

    5. The dismissal from the works of any persons employed thereon.

    6. The opening up tor inspection of any work covered up.

    7. The amending and making good of any defects under defect liability

    period.

    8. Assignment and sub letting.

    9. Delay and extension time.

    10.The postponement of any work to be executed under the provision

    of this Contract.

    68. Damages for non-completion:

    If the contractor fails to complete the works by the time specified in

    these conditions or with any extended time fixed by authority and the

    employer certifies in writing that in his opinion the same ought

    reasonably so to have been completed, the contractor shall pay or allow

    to the Employer a sum calculated at the rate stated in the appendix as

    agree liquidated damages for the period during which the said work

    shall so remain or have remained form any movies otherwise payable to

    the contractor under this contract.

    69. Nagar Palika G. TERMS & Condition/act will be consider.

    Dated Sign of Contractor