tep sundt plant generation modernization project...• this rice project is the lowest cost option...
TRANSCRIPT
TEP Sundt PlantGeneration Modernization Project
Conrad SpencerProject Director
February 14, 2018
TEP’s Future Generation
• Arizona Corporation Commission(ACC) mandate is 15% retail sales from renewable resources by 2025
• TEP Submitted its Integrated Resource Plan (IRP) to the ACC in April 2017
• Goal to have 30% retail sales from renewable resources by 2030
2
Intermittent Generation Requirements
3The chart above represents the change in retail load on a 10-minute basis (52,560 intervals) over the course of a year.
+ 50 MW
- 50 MW
+ 100 MW
-100 MW
2016 Historical Requirements10‐minute changes based on retail load only. No renewables.
2016 Requirements10‐minute changes in both retail load and renewable resources
275 MWac Utility Scale50 MWac Distributed Generation
325 MWac Total Renewables
Intermittent Generation Requirements
4The chart above represents the change in retail load on a 10-minute basis (52,560 intervals) over the course of a year.
+ 50 MW
- 50 MW
+ 175 MW
-175 MW
2016 Historical Requirements10‐minute changes based on retail load only. No renewables.
2024 Requirements10‐minute changes in both retail load and renewable resources
600 MWac Utility Scale200 MWac Distributed Generation800 MWac Total Renewables
Renewable Generation Fluctuations
14:25, 220
14:34, 172
14:45, 227
16:21, 251
16:51, 114
14:25, 20
14:34, -60
16:24, 54
16:47, -91
-300
-250
-200
-150
-100
-50
0
50
100
0
50
100
150
200
250
30012
:01
12:0
912
:17
12:2
512
:33
12:4
112
:49
12:5
713
:05
13:1
313
:21
13:2
913
:37
13:4
513
:53
14:0
114
:09
14:1
714
:25
14:3
314
:41
14:4
914
:57
15:0
515
:13
15:2
115
:29
15:3
715
:45
15:5
316
:01
16:0
916
:17
16:2
516
:33
16:4
116
:49
16:5
717
:05
17:1
317
:21
17:2
917
:37
17:4
517
:53
18:0
118
:09
18:1
718
:25
August 8, 2017 Renewable Fluctuations
Macho Springs Red Horse Total City Utility Renew UNSE Utility Renew TOT_RENEW_MW ACE
48 MW drop followed by 55 MW rise in Total Renewables
137 MW drop in Total Renewables
80 MW drop in ACE
145 MW drop in ACE
Typical 2030 Winter Day Load Profile
6Source: TEP IRP page 68
TEP Internal study
• TEP Generation and Resource Planning performed high level economic study with internal resource planning models
• Used replacement of two steam units with reciprocating capacity as fundamental assumption
• Benefits were substantial improvement in heat rates and ramp rates
• Approval given to pursue possible sites and air permit modeling
7
TEP Technology Assessment
• Technology assessment to review the lowest cost options to assist in the integration of renewables conducted by Burns and McDonnell Engineering
• Options considered were large frame gas turbines, aeroderivative gas turbines, combined cycle, reciprocating engines(10 MW and 20 MW class), wind, solar, batteries
• Reciprocating engines were the lowest cost option that met all of TEP’s needs. Reliability minimum generation requirement and fast response.
8
Typical Reciprocating Engine Generator
Site Selection Criteria
• Five sites in the Tucson area were evaluated
11
Environmental/Air Permit RequirementsFuel SupplyLand RequirementsCommunity ImpactTransmission RequirementsSystem Control & Reliability Impact
LOCATION OF RICE PROJECT
13
Large Generator Interconnection
• TEP Generation filed a Large Generator Interconnect application on March 31, 2017 with TEP LGIP department
• System Impact study was completed Oct 31, 2017• Interconnection Facilities study is competed and
design is underway to meet a January 2019 energization of Generator Step-up transformers(GSU)
14
Recip Vendor Bid Process
• Only two vendors offered 20 MW class machines. FairbanksMorse(MAN) and Wartsila
• TEP team went to Germany, France, & Italy to see manufacturing facilities of both vendors
• RFP went out June 1, 2017. Scope of supply was broken into each major system from tip of the stack to the low side of the GSU.
• Both vendors submitted bids on August 17, 2017
• Wartsila was selected on cost basis from the tip of the stack to low side of the GSU.
EPC Bid Process –Final Engineering Construction
• Accion Power hired as independent monitor and website host
• RFP went out July 7, 2017
• Bid walk held July 21, 2017
• Technical specs for project with Wartsila scope of supply posted on Sept 6, 2017
• Bids were due October 20, 2017
• Selection of Ashton Construction (local Tucson firm)
• Sargent & Lundy engineering
Schedule
• Break ground April 2018
• Engines on site Oct 2018
• First five engines in commercial operation June 1, 2019
• Second five engines in commercial operation Oct 1, 2019
Site Arrangement
3 D Model of TEP RICE Project
19
Certificate of Environmental Compatibility
• Application for a Certificate of Environmental Compatibility filed with the Arizona Power Plant and Transmission Line Siting Committee of the Arizona Corporation Commission(ACC), Filed December 8, 2017
• Public Hearings were held on January 17-19, 2018 in Tucson
• Vote was 8-0 in favor of issuing the CEC• The ACC commissioners will vote in next Open
meeting March2018
20
Air Quality Permitting Process• Sundt site is a major stationary source for purposes of the Prevention of
Significant Deterioration (PSD) program and holds a Class I Air Quality Permit issued by Pima County Dept. of Environmental Quality.
• RICE project requires preconstruction PSD review and a Significant Revision of the Class I Permit.
• Permitting process includes the following key steps:• TEP requests accelerated permit process from PDEQ March 2017• TEP submits permit application (8/3/2017)• PDEQ determines application is administratively complete
(8/23/2017)• PDEQ performs technical review and prepares draft permit and
supporting documentation • Public notice and comment process• PDEQ transmits proposed action to U.S. EPA for review• Final action by PDEQ
21
Status of Significant Permitting Process • 8/23/2017– 2/9/2018– Technical Review Period
• Technical Review Working Group Meetings with PDEQ, PDEQ Consultant, EPA Region 9, National Park Service, TEP, and TEP Consultants
• The Technical Review Working Group has held approximately 20 teleconference meetings
2/9/2018: Began public notice and comment process and concurrent review by U.S. EPA2/15/2018: Open House3/1/2018: Public Hearing3/12/2018: End public notice and comment process3/26/2018: End U.S. EPA review period4/16/2018: Final decision issued by Pima DEQ
22
Air Study Results • Dispersion modeling of the RICE project unambiguously
demonstrates de minimis air quality impacts (i.e., project will not cause or contribute to violations of ambient standards or PSD increments)
• Modeling performed using required modeling software and procedures
• Analysis conservatively did not consider emission reduction from retiring Units 1 & 2
• Modeling demonstrates project will cause no impairment to visibility, including especially rigorous analyses in Saguaro National Park and Galiuro Wilderness
• Analysis conservatively did not consider emission reduction from retiring Units 1 & 2
23
Comparison of Tucson Area NOx Emissions
24
0
100
200
300
400
500
600
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032
Tons
Per
Yea
r
(Sum of all units at Sundt, DeMoss Petrie, and North Loop)
Existing Steam Turbines Simple-Cycle Gas Turbines RICE
Benefits
• Project Benefits:• Fast start < 5 minutes (allows integration of more
intermittent renewables)
• 40% better fuel efficiency than steam units that will be retired
• 60% reduction in NOx emissions from total plant with the retirement of steam units 1 & 2 and reduced use of units 3 & 4
• 70% reduction in ground water usage (current usage is 685,000,000 gallons per year, new usage will be less than 230,000,000 gallons per year
2017 2019 2020 2021 2023 2030
December 2017San Juan Unit 2
Retirement-170 MW
2018Gila River
Unit 2550 MW
June 2022San Juan Unit 1
Retirement-170 MW
2019Reciprocating
Engines200 MW
July 2031Four Corners Power
Plant Retirement-110 MW
2017Battery Storage 20 MW
2030Target 30%
Renewables by 20301,000 MW
December 2019Navajo Generation Station Retirement
-168 MW
2020Wind
Project100 MW
2020Solar-Battery
Project100 MW - Solar
30 MW - Storage
2021Wind
Project150 MW
TEP Long Term Resource Plan
Conclusions
• This RICE project is the lowest cost option for TEP to provide fast flexible generation to allow for
- the additional integration of renewables - provide Reliability minimum generation
requirements-provide a bridge to the future use of additional battery technologies
TEP
• Questions?
28