terramin australia limited angas zinc project. the angas zinc project: noise noise issue is a...

23
TERRAMIN AUSTRALIA Limited TERRAMIN AUSTRALIA Limited Angas Zinc Angas Zinc Project Project

Upload: barnaby-osborne

Post on 28-Dec-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

TERRAMIN AUSTRALIA LimitedTERRAMIN AUSTRALIA Limited

Angas Zinc Angas Zinc ProjectProject

Page 2: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

The Angas Zinc Project: The Angas Zinc Project: noisenoise

• Noise issue is a “work in progress”

– Final noise outcomes and decisions

awaiting final designs.

– These hinge on the Mining Lease and

MARP approvals.

– Work on noise will be ongoing.

Page 3: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Noise: What is it?Noise: What is it?

• Noise and soundNoise and sound• Made up of different componentsMade up of different components

– Loudness (measured in decibels; dB(A))Loudness (measured in decibels; dB(A))– Frequency (or pitch)(measured in hertz; Frequency (or pitch)(measured in hertz;

Hz)Hz)• CharacteristicsCharacteristics

– Tone, fluctuation, impulsivenessTone, fluctuation, impulsiveness

Page 4: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Noise: legislative frameworkNoise: legislative framework

• Environment Protection (Industrial noise) Environment Protection (Industrial noise) Policy (INP)Policy (INP)

• Area of development adjacent to existing Area of development adjacent to existing residences is “Urban residential with some residences is “Urban residential with some manufacturing industry…”manufacturing industry…”

• Prescribed limit: 58 dB(A) (day), 50 dB(A) Prescribed limit: 58 dB(A) (day), 50 dB(A) (night)(night)

• General duty of care under Environment Protection Act

Page 5: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

INP: penalties

• Penalties are applied by the INP for tone, impulsiveness, fluctuation

• Planning penalty: 5 dB(A)

• Characteristic penalty: 5 dB(A)

• Gives new maximum allowable limits:

• Day 48 dB(A)

• Night 40 dB(A)

Page 6: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Noise: indicative measures

• Boeing 747 140 dB• Jack hammer 120 dB• Lawn mower 100 dB• Garbage truck 80 dB• Normal conversation 60 dB• Background noise 40 dB• Whispering 30 dB

Page 7: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Current noise studies

• Noise monitoring at two sites (site office and rear of site)

• 7 day period September 2005

• Average noise 50 dB during the day, 30-40 dB at night

• Does not include quarry noise

Page 8: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Current ambient noise

Page 9: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Angas Zinc Project: potential issues

• Variety of noise sources• Mine

– Vent rise fan– Trucks

• Mill– Crushing Plant– Front-end-loaders– Grinding Mill– Air blower and compressor– Pumps and stirrers

Page 10: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Benchmarking

• Visit to mines located in towns• Stawell

– Underground vent rise fans– Use of topography

• Kagara zinc– Use of sheds to minimise noise– Low noise blowers

• Ballarat Gold– Approach to noise containment

Page 11: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Angas Zinc Project: General mitigation

• Sound mounds (bunds)• Use of natural topography as noise barrier • Vegetation visual screens• Enclosed sheds for plant • Mufflers on machinery• White noise generation on reversing sounds• Day time only operation for some plant and

machinery• Day time truck delivery & despatch

Page 12: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Mine: Current design initiatives

• Twin underground vent rise fans.• Selection of “low noise” volvo trucks.• Deeper boxcut to contain vehicle noise.• Use of “white noise” reversing indicators.• Sound mounds around boxcut and roadways.• Underground noise not an issue.

Page 13: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Mill Design

• The design of mill is heavily influenced by environmental considerations

• Final location still to be finalised, work in progress• Natural lie of land will be used to help attenuate

sound• Mill forced out of pit, crusher to remain• Buildings positioned to minimise noise transmission• Engineering contract specifies noise performance

criteria

Page 14: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Mill Design

• Buildings positioned to cut noise transmission

Page 15: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Mine Design

• Crushing on day shift only(cost $2-3 million)

Page 16: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Mill: Current design initiatives

• Crushing only on day shift (cost $2-3 million)• Sound attenuation on compressor• Roof & wall on SAG mill• Roof & walls on flotation circuit• Low noise air blower• Sound mounds• Capital allowance for more attenuation during

commissioning

Page 17: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Current quarry

Page 18: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Current Quarry: Status

• Monday 22nd May 2006 site audit• Volvo trucks• Loader• Crusher• Screens

Page 19: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Noise modelling: Bassett Acoustic

• Matthew Stead; National Manager Acoustics– Penrice Soda Products solids recovery– Holden Paint Shop noise– AWB Rain Bulk Stores– Penola Bypass

• Noise modelling performed using SA EPA accepted models

• Indicative- based on initial scenarios• Based on noise produced by mill, trucks & vent rise fan• Based on climate for region: typical worst case scenario

winds

Page 20: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Modelled noise: Daytime

Page 21: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Modelled noise: Night time

Page 22: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Noise modelling: Bassett Acoustic

• New round of modelling underway using – current configuration of plant– based on noise provided by mill, selected

trucks & underground suppliers– Still based on typical worst case scenario for

winds

Page 23: TERRAMIN AUSTRALIA Limited Angas Zinc Project. The Angas Zinc Project: noise Noise issue is a “work in progress” –Final noise outcomes and decisions awaiting

Standards and Targets

• Proposed allowable limits– 48 dB(A) Day time (7.00 am- 10.00 pm)– 40 dB(A) Night time (10.00 pm – 7.00 am)

• Outcome is to prevent public nuisance impacts from noise emanating from the operating site

• The monitoring points to be reviewed from time to time with the CCC

• The plant will be designed to better these targets