tes-p-107-01-r0

119
February 26, 2013 TESP10701R0/KSB

Upload: srinivasaphanikiran

Post on 12-Sep-2015

407 views

Category:

Documents


27 download

DESCRIPTION

SAS standard

TRANSCRIPT

  • February 26, 2013

    TESP10701R0/KSB

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 2 OF 119 Date of Approval: February 26, 2013

    TABLE OF CONTENTS

    1. SCOPE

    2. INTRODUCTION

    3. SYSTEM DESIGN

    3.1 General System Design 3.2 System Architecture 3.3 Ethernet Topology

    4. FUNCTIONAL REQUIREMENTS

    4.1 General SAS Functionality 4.2 Bay Level Functions 4.3 System/Station Level Functions

    5. PERFORMANCE REQUIREMENTS

    5.1 Message Performance 5.2 System Performance

    6 RELIABILITY AND SYSTEM DESIGN

    6.1 Reliability Aspects

    6.2 General Design Requirements

    7. IEC 61850 AND IEC 62439-1 COMMUNICATION PROFILE

    7.1 Introduction Related to IEC 61850

    7.2 Typical Architecture and Required Communication Services Related to IEC 61850

    8. CONFIGURATION TOOLS/SERVICE AND SUPPORT SYSTEM

    9. GENERAL REQUIREMENTS

    9.1 Compliance With Standards 9.2 Vendors/SOLUTION PROVIDERS experience and Proposal for the SAS

    10. PROJECT EXECUTION

    10.1 Engineering

    10.2 Factory Acceptance Test (FAT)

    10.3 SAT (Site Acceptance Test)/Pre-commissioning and Commissioning

    10.4 Design and Operating Requirements

    10.5 Services, After Sales and Maintenance

    11. DOCUMENTATION

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 3 OF 119 Date of Approval: February 26, 2013

    12. CYBER SECURITY REQUIREMENTS

    13. KEMA CERTIFICATION

    14. ADDITIONAL SUBSTATION AUTOMATION SYSTEM

    15. DRAWINGS

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 4 OF 119 Date of Approval: February 26, 2013

    1.0 SCOPE

    This Transmission Engineering Standard (TES) specifies Substation Automation System

    (SAS) required for 110kV through 380kV system voltage for the transmission system of

    National Grid, Saudi Arabia.

    2.0 INTRODUCTION

    2.1 The Substation Automation System (SAS) shall be installed to monitor, control and protect all the substation equipment connected to SAS. Monitoring and control shall

    be from the remote control center (Power Control Center/SCADA Master Stations)

    as well through local means within the substation (e.g. Bay Oriented Local Control

    with Mimic, Local HMI contained in the Control IED and Station HMI).

    The Substation Automation System (SAS) comprises full station and bay protection

    as well as control, monitoring and communication functions and provides all

    functions required for the safe and reliable operation of the substation. It shall enable

    local station control via a PC by means of a human machine interface (HMI) and

    control software package, which shall contain an extensive range of Supervisory

    Control and Data Acquisition (SCADA) functions. It shall include Communications

    Gateway, station bus, inter-bay bus, time synchronization system and intelligent

    electronic devices (IEDs) for bay control & protection.

    The attached diagram entitled, Substation Automation System Diagram (Conceptual), Fig 07-01, is conceptual drawings for substation SAS configuration.

    The Communications Gateway shall enable and secure the information flow with

    remote Power Control Center and other remote Master Stations. Besides performing

    protocol conversion, the Communications Gateway will perform Network/Port

    Address Translation from internal SAS IP/Port addresses to external IP/Port

    addresses in integrated units/computers.

    The station bus shall provide the interconnections between the station level

    subsystems (Front End/Station computer, Operators Workstation, Engineers Workstation, printer etc.). The inter-bay bus shall provide independent station-to-bay

    and bay-to-bay data exchange. The bay level intelligent electronic devices (IEDs) for

    protection and control shall provide the direct connection to the switchgear without

    the need of interposing components and perform control, protection, and monitoring

    functions.

    The SAS control and monitoring system (SCMS) shall implement a network

    redundancy based on IEC62439-3 PRP 1 (Parallel Redundancy Protocol) as shown

    in the attached Substation Automation System Diagram (Conceptual), Drawing Fig 07-01, and as further explained in this Standard. Implementation of IEC62439-3 PRP

    1 (Parallel Redundancy Protocol) applies to both the station LAN and bay LAN at all

    voltage levels.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 5 OF 119 Date of Approval: February 26, 2013

    2.2 All the SAS components shall comply with latest revision of SEC standards wherever applicable.

    2.3 Summary of Main Functional Parts of SAS

    2.3.1 As a summary, the SAS shall contain (but may not be limited) to the

    following main functional parts:

    2.3.2 Bay Control Intelligent Electronic Devices (Control IEDs) for control and monitoring.

    2.3.3 Bay Protection Intelligent Electronic Devices (Protection IEDs) for the internal substation's protection applications as well as for protection of

    external equipment connected to the substation.

    2.3.4 Unless otherwise specified, combined control/protection IEDs with the control IED function and protection IED function (for each item of

    switchgear to be controlled) may be combined into one unit. Combined

    control/protection IEDs are to be used at the medium voltage levels only

    (34.5 kV and below).

    2.3.5 Redundant Managed hardened Ethernet switches providing managed Ethernet Local Area Networks communications infrastructure.

    2.3.6 Supporting Power Supply equipment such as inverters UPS, etc.

    2.3.7 Peripheral equipment like printers, display units, key boards, Mouse, KVM switches, etc.

    2.3.8 Station Human Machine Interface (Station HMI)/ Station with process database. The Station HMI shall contain as minimum: fully redundant two (2)

    Front End/ Station Computers, fully redundant two (2) Operator's

    Workstation, fully redundant one (1) Engineering Workstation, and related

    applications software, operating systems and firmware to support full Station

    HMI operation.

    2.3.9 Separate Redundant Communications Gateway for remote supervisory control via SCADA Master Station(s) and for interconnecting external SOE

    Master Stations. One side of each Communications Gateway shall face the

    internal SAS Inter-bay bus using IEC 61850 and the other side of each

    Communications Gateway shall face the external SCADA and SOE Master

    Stations which will communicate using IEC 60870-5-101, IEC 608705-104

    protocols, and support IEC 61850 communication with SCADA master

    stations for future use.

    2.3.9 Redundant GPS Receivers (e.g. Master Clock).

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 6 OF 119 Date of Approval: February 26, 2013

    2.3.10 Redundant standalone Firewalls to provide one of the means for cyber

    security for the SAS.

    2.3.11 Quantities of VF Modems to support the IEC-101 interconnections between

    the SCADA Master Stations and the redundant Communications Gateways.

    2.3.12 Collection of the relevant data concerning the substation and distribution of

    the data where needed.

    2.3.13 Data exchange between the different system components via the inter-bay

    bus (for data exchange between bay level IEDs) and other communications

    buses (such as station bus for interconnecting the station level subsystems:

    Operators Workstations, Engineering Workstation, Front End Computers,

    and Printers etc).

    2.3.14 Bay-oriented local control panels with mimic diagram. One of the functions

    of the Bay-Oriented local control panels with mimic diagram is to provide

    emergency local operation of related Bay switchgear in the event of failure

    and/or disabling of the Bay Control IED(s).

    2.3.15 Local Control Cubicles (LCCs) for all High Voltage (above the medium voltage (34.5 kV and below) level) switchgear which will be installed in the

    related High Voltage GIS Switchgear Rooms which will house/contain the

    Control IEDs, Bay-oriented local control panels with Mimic Diagram and required Annunciator Panels.

    2.3.16 For the Medium Voltage level (34.5 kV voltage and below), unless otherwise specified differently in other sections/appendices of the main PTS,

    combined Control/Protection IEDs which are to be mounted/installed in the Low Voltage Compartments of the Metal Clad Medium Voltage Switchgear

    as specified in latest revision of 32-TMSS-01 (for Metal Clad Switchgear)

    and as specified in latest revision of 32-TMSS-03,( Metal Clad GIS

    Switchgear), and with these IEDs fully integrated into this Metal Clad Switchgear by the SAS Solution provider /Sub Solution provider .

    2.3.17 SAS Cubicles/Panels which will contain SAS equipment which includes, computers, Ethernet switches, firewalls/routers, VF modems, maintenance

    displays, common alarm panels and related annunciators, terminal blocks,

    MCBs, internal cabling/wiring, etc.

    2.3.18 Protection Cubicles/Panels which will contain Protection IEDs. terminal

    blocks, physical switches, MCBs, auxiliary relays, internal cabling/wiring,

    etc.

    2.3.19 All cabling/wiring/terminations required to provide for a fully functional

    SAS installation to be provided/installed by the SAS Solution provider and

    interconnected between SAS equipment as well as any SAS equipment and

    external Communications/WAN/LAN equipment. The only exception to this

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 7 OF 119 Date of Approval: February 26, 2013

    cabling/wiring requirement will be the cabling/wiring between the Control

    IEDs and external switchgear, the Protection IEDs and external switchgear, and thecombined Control/Protection IEDs and the external switchgear which can be run and terminated at the switchgear end by the Substation Solution

    Provider . (however for the IED to switchgear cable connections at the IED

    end and this cable termination shall be performed by the SAS Solution

    provider).

    2.3.20 Other devices, equipment and software (not mentioned above) which will

    provide for a fully integrated and operational SAS at the substation.

    2.4 Definition of Terms

    2.4.1 HMI Human Machine Interface: Display screen, either part of an IED or as a

    stand-alone device, presenting relevant data in a logical format, with which

    the user interacts. An HMI will typically present windows, icons, menus,

    pointers, and may include a keypad to enable user access and interaction.

    2.4.2 IED Intelligent Electronic Device: Any device incorporating one or more

    processors, with the capability to receive or send, data/control from, or to an

    external source, for example electronic multifunction meters, digital relays,

    controllers. Device capable of executing the behavior of one, or more,

    specified logical nodes in a particular context and delimited by its interfaces.

    Also see definitions relating to Protection IED, and Control IED.

    2.4.3 Bay

    A substation consists of closely connected sub parts with some common

    functionality. Examples are the switchgear between an incoming or outgoing

    line, and the bus bar, the bus coupler with its circuit breaker and related

    isolators and earthing switches, the transformer with its related switchgear

    between the two bus bars representing the two voltage levels. The bay

    concept may be applied to 1 1/2 breaker and double bus substation

    arrangements by grouping the primary circuit breakers and associated

    equipment into a virtual bay. These bays comprise a power system subset to

    be protected, for example a transformer of a line end, and the control of its

    switchgear that has some common restrictions such as mutual interlocking or

    well-defined operation sequences. The identification of such subparts is

    important for maintenance purposes (what parts may be switched off at the

    same time with minimum impact on the rest of the substation) or for

    extension plans (what has to be added if a new line is to be linked in). These

    subparts are called 'bay' and may be managed by devices with the generic

    name 'bay controller' and have protection systems called 'bay protection'. The

    bay level represents an additional control level below the overall station

    level.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 8 OF 119 Date of Approval: February 26, 2013

    2.4.4 Bay Level Functions

    Functions that use mainly the data of one bay and act mainly on the primary

    equipment of that bay. Bay level functions communicate via logical interface

    3 within the bay level and via logical interfaces 4 and 5 to the process level,

    i.e. with any kind of remote input/output or with intelligent sensors and

    actuators. Control and data acquisition functions related to the bay level

    functions may be performed at the bay level Control IED(s)/Local

    HMI(s)/Bay-oriented Local Control Panel with Mimic Diagram, or indirectly

    through the station HMI interface or the SCADA Master Station(s).

    Protection functions related to the bay level functions are performed through

    the bay level Protection IED(s) dedicated specifically for protective relaying

    function(s).

    2.4.5 Station Level Functions Functions applying to the whole substation. There are two classes of station

    level functions i.e. process related station level functions and interface related

    station level functions. Control and data acquisition functions which are

    related to the station level functions for each substation indicated in Section

    2.1 and which may include control and data acquisition from the local HMI,

    Station HMI, and with the SCADA Master Station(s) providing external

    (outside the substation) control and data acquisition capabilities.

    2.4.6 Process:

    The scheme which contains the actual conventional switchgear which

    includes Breakers, Disconnect Switches, Tap Changers, Instrument

    transformers and all instrumentation like Gas Density Monitors, etc.

    2.4.7 Process Level Functions

    All functions interfacing to the process, i.e. binary and analogue input/output

    functions for example data acquisition (including sampling) and the issuing

    of commands. These functions communicate via the logical interfaces 4 and 5

    to the bay level.

    2.4.8 Process Related Station Level functions Use data from more than one bay, or from each whole substation and act on

    the primary equipment of more than one bay, or on the primary equipment of

    each whole substation. Examples of such functions are: station wide

    interlocking, automatic sequencers, and bus bar protection. These functions

    communicate mainly via logical node 8.

    2.4.9 Station HMI The set of computers/workstations and other equipment inside each

    substation where control, data acquisition, monitoring, configuration of SAS

    equipment and other SAS functions on a station level takes place.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 9 OF 119 Date of Approval: February 26, 2013

    2.4.10 Front End Computers/Station Computers The set of computers where data gets directly transferred between the IEDs

    (for recording/data acquisition and control functionality), and where

    interfaces are provided for the Operator's and Engineering Workstations.

    2.4.11 Local HMI

    The set of equipment inside each substation where control, data acquisition,

    alarms, configuration of SAS equipment, and other SAS functions on a bay

    level takes place.

    2.4.12 Operator Workstation

    The computer (s),which are contained as part of the Station HMI and where

    substation control/data acquisition, alarms/events/trends/disturbance records

    recording/retrieval and other SAS equipment manufacturers recommended

    functions are displayed and takes place. It is noted that the Operator's

    Workstations and Engineering Workstation shall be dedicated separate

    computers with separate dedicated displays, keyboards, and mice.

    2.4.13 Engineering Workstation The computer (s) where equipment configurations supported and other SAS

    equipment manufacturers functions related to SAS Engineering is allowed to take place. It is noted that the Operator's Workstation and Engineering

    Workstation shall be dedicated separate computers with separate dedicated

    displays, keyboards, and mice.

    2.4.14 Control IED An intelligent electronic device that provides for control functions on a bay

    level. Depending on the equipment manufacturer's design, data acquisition

    functions may also be provided as part of the Control IED. Also, depending

    on the equipment manufacturer's design, a Local HMI may be integrated as

    part of the Control IED, or the Control IED may be separate from the Local

    HMI. As part of the design of the Control IED, there shall be a requirement

    for IEC 61850 compatibility. For the purposes of this standard, Control IEDs

    shall be physically separate devices from Protection IEDs, with dedicated

    Control IEDs being installed for all voltage levels above the Medium Voltage level, and where related Appendix of the main PTS specifies

    dedicated Control IEDs at the Medium Voltage Level.

    2.4.15 Protection IED An intelligent electronic device that provides for protective relay functions,

    primarily on a bay level. Depending on the equipment manufacturer's design,

    the Protection IED may provide for a single protective relay function, or

    multiple protective relay functions in the same Protection IED unit. Also,

    depending on the equipment manufacturer's design, additional

    features/functions of the Protection IED may include status recording

    functions (such as fault recording and other status recording functions), data

    acquisition and other features. Also, Protection IED's shall be considered as

    Protective Relays which are integrated in the SAS and with IEC 61850

    connectivity/functionality. For the purposes of this standard, Protection IEDs

    shall be physically separate devices from Control IEDs, with dedicated

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 10 OF 119 Date of Approval: February 26, 2013

    Protection IEDs being installed for all voltage levels above the Medium Voltage level, and where related Appendix of the main PTS to this standard

    specifies dedicated Protection IEDs at the Medium Voltage Level.

    2.4.16 Combined Control/Protection IED

    An intelligent electronic device that provides for combined control and

    protection functions on a bay level. Depending on the equipment

    manufacturer's design, data acquisition functions may also be provided as

    part of the Combined Control/Protection IED. Also, depending on the

    equipment manufacturer's design, the combined Control/Protection IED may

    provide for a single protective relay function, or multiple protective relay

    functions in the same combined Control/Protection IED unit. Also,

    depending on the equipment manufacturer's design, additional

    features/functions of the combined Control/Protection IED may include

    status recording functions (such as fault recording and other status recording

    functions), and other features. Also, combined Control/Protection IED's shall

    be considered as Protective Relays which are integrated in the SAS and with

    IEC 61850 connectivity/functionality Also, depending on the equipment

    manufacturer's design, a Local HMI may be integrated as part of the

    combined Control/Protection IED, or the combined Control/Protection IED

    may be separate from the Local HMI. For the purposes of this Standard,

    combined Control/Protection IEDs shall be provided for all Medium Voltage (34.5 kV and below) applications, unless separate dedicated Control IEDs, and separate dedicated Protection IEDs are specified for some or all of the Medium Voltage applications in the main PTS.

    2.4.17 Station Bus

    The medium through which communications takes place among the station

    level subsystems such as Operators Workstation, Engineering Workstation, Front End Computers, Printers etc. Station bus shall be fully compliant with

    IEC 62439-3 (PRP1).

    2.4.18 Inter-Bay Bus:

    The medium through which communications takes place between the bay-

    level IEDs and the station HMI interface and which protection, control and

    data acquisition/monitoring signals for the SAS pass through. The Inter-Bay

    Bus shall be fully compliant with IEC 61850 for all voltage levels of the

    substation, and also will be fully compliant with IEC-62439-3 PRP1 for all

    voltage levels of the substation.

    2.4.19 Bay-oriented Local Control Panel with Mimic Diagram

    A panel, which is installed on a bay level which provides for local indication

    of switchgear status, limited alarm indication, other sets of limited readings,

    and local switchgear control (on an emergency basis upon failure of a Control

    IED and/or local HMI.

    2.4.20 Time Synchronization System: A redundant set of GPS receivers which

    provide for time synchronization data to all equipment contained as part of

    the SAS within each substation.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 11 OF 119 Date of Approval: February 26, 2013

    2.4.21 Communications Gateway

    A set of redundant equipment which will provide for communications

    interfacing between the SAS and equipment outside of each substation, and

    which will also provide for required protocol conversions as needed for the

    SAS to communicate with Master Station equipment outside each substation.

    2.4.22 SCADA Master Station(s) The station(s) (outside of each substation) where remote control and remote

    data acquisition functions are performed for each substation. For purposes of

    the SAS, interfacing between the station SAS and the SCADA Master

    Station(s) will be through the Communications Gateways.

    2.4.23 SOE Master Station The station (outside of each substation) where SOE (Sequence of Events)

    information which eventually gets routed to. For purposes of the SAS,

    interfacing between the station SAS and the SOE Master Station will be

    through Communications Gateways.

    2.4.24 PTS Project Technical Specification, which is the same as the Scope of Work and

    Technical Specifications (SOW/TS).

    Additional Definitions Relating to IEC 61850

    For additional definitions relating to IEC 61850, refer to the latest revision of IEC

    TS 61850-2.

    3.0 SYSTEM DESIGN

    3.1 General System Design

    3.1.1 The Substation Automation System (SAS) shall be suitable for operation,

    monitoring, and maintenance of each complete substation including future

    extensions which are identified in this entire standard document. The offered

    products shall be suitable for efficient and reliable operation under the

    environmental conditions specified in Section 14.

    3.1.1 The systems shall be: State-of-the art based on IEC61850 for operation under electrical conditions present in high-voltage substations, follow the latest

    engineering practice & ensure long term compatibility requirements,

    continuity of equipment supply and the safety of the operating staff.

    3.1.2 The offered SAS shall support remote control and monitoring from remote SCADA Master Stations via Communications Gateways.

    3.1.3 The offered SAS shall provide for SOE (Sequence of Events) points support and overall SOE functions, with SOE monitoring information forwarded to

    both the Station HMI and the external SOE Master Station (which is located

    outside of the substation) through the Communications Gateways.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 12 OF 119 Date of Approval: February 26, 2013

    3.1.4 The offered SAS shall provide for Protective Relay functions, (through bay-level Protection IEDs) for each substation.

    3.1.5 The offered SAS shall provide for the substations interlocking functions, both through hard-wired interlocks in the substation as well as a system of

    software/GOOSE interlocks.

    3.1.6 The offered SAS shall provide for other miscellaneous functions related to substation control, data acquisition, protection and other functions as

    described elsewhere in this Standard and the related Main PTS and other

    Appendices to the Main PTS.

    3.1.7 The system shall be designed such that personnel with little background knowledge in microprocessor-based technology are able to operate the

    system easily after having received some basic training.

    Installation/Maintenance/Operating Manuals/ documentation describing the

    features and functions of the system shall be provided. Necessary 'HELP'

    files shall be built into the HMI and database software. Also, the Operator

    Interface (through the Engineering Workstation and Operator's Workstation)

    shall be intuitive such that operating personnel shall be able to operate the

    system easily after having received basic training on the SAS.

    3.1.8 Cubicles shall incorporate the control, monitoring and protection functions specified, self-monitoring, signaling and testing facilities, measuring as well

    as memory functions, event recording and disturbance recording. The basic

    control functions are to be derived from a modular standardized and type-

    tested software library.

    3.1.9 Maintenance, modification or extension of components may not cause a shut-down of the whole SAS. Self-monitoring of single components, modules and

    communication shall be incorporated to increase the availability and the

    reliability of the equipment and minimize maintenance. In the cases of

    modification or extension of components, if a shutdown of the SAS is

    required, features, functions and configurations shall be provided to keep the

    shutdown time of all or part of the SAS to an absolute minimum.

    3.1.10 Preference will be given to suppliers who are in a position to provide protection and control devices and other devices freely adaptable to the

    required application functionality.

    3.1.11 The SAS shall be expandable as and when required at the Bay, Station and Process levels.

    3.1.12 As part of the general system design of the SAS, alarm features shall be included which shall forward alarms to the SCADA Master Station(s) (as

    well as the SAS Central Alarm Unit and/or substation Annunciator system

    which will be included as part of the SAS) if the SAS determines that any

    component of the SAS is not operating properly (with such components

    including the station HMI, local HMI, IEDs, Communications Gateways,

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 13 OF 119 Date of Approval: February 26, 2013

    inter-bay bus, Ethernet switches, GPS receivers and other components of the SAS). For further details refer to Section 14.26 as well as latest revision of

    TES-P-119.27 for SCADA points list and 38-TMSS-05 for Alarms list. It

    should be noted that these are minimum requirements and the complete lists

    to be provided by the SOLUTION PROVIDER which will be subject to

    review and acceptance.

    3.1.13 Generally, part or all of the SAS will be installed inside the substation building, which will be air conditioned. However in some cases, where

    outdoor switchyards are used (refer main PTS) all bay-level unit hardware

    (such as Bay Control IEDs and Bay Oriented Local Control Panels with

    Mimic Operation) which need to be co-located with the outdoor switchgear

    shall be designed and constructed to meet and fully operate without failure in

    the outdoor environmental conditions in Saudi Arabia at the substation's

    location. Refer to latest revision of standard 01-TMSS-01 (Outdoor

    Environmental Conditions) for further details. However in the case of SAS

    equipment located inside the substation building, the SAS equipment shall be

    operational during both normal indoor conditions, and emergency indoor

    conditions for a minimum 12 hour period where there is no heating/air

    conditioning inside the substation building (for this matter, refer section 14.

    of this standard for further detail on these requirements).

    3.2 System Architecture

    3.2.1 For safety and availability reasons the Substation Automation System shall be based on a decentralized architecture and on a concept of bay-oriented

    distributed intelligence.

    3.2.2 Functions shall be decentralized, object-oriented and located as close as possible to the process.

    3.2.3 The main process information of the station shall be stored in distributed databases.

    3.2.4 The proposed SAS layout shall be structured in three levels, i.e. a Station, a Bay and a Process level.

    3.2.5 The Station level shall provide all the station level functions related to monitoring, control and protection. It shall consist of the station level

    subsystems such as operators workstations, engineering workstation, front end computers, printers, etc. interconnected via the Station Bus. At bay level

    the IEDs shall provide all bay level functions regarding control, monitoring

    and protection, inputs for status indication and outputs for commands. The

    inter-bay bus shall provide the interconnection between the bay level IEDs

    and other bay level IEDs, the bay level IEDs and SAS front end computers/Communications Gateways, and between SAS front end

    computers and SAS Communications Gateways. The IEDs should be directly

    connected to the switchgear without any need for additional interposition or

    transducers. It shall be the responsibility of the SAS

    Manufacturer/SOLUTION PROVIDER to determine the proper layout for

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 14 OF 119 Date of Approval: February 26, 2013

    the SAS and the independent from each other and its functioning shall not be

    affected by any fault occurring in any of the other bay control units of the

    station. The only exception to this section will be for GOOSE interlocks,

    where GOOSE interlocking information from one bay control unit to other

    bay control units and in the event of the failure of the bay control unit

    (Control IED) GOOSE interlocks may not be functional.

    3.2.6 The communication buses shall be realized using fiber-optic cables and substation hardened Ethernet switches thereby guaranteeing disturbance free

    communication. To maximize the physical protection of the fiber optic cables,

    the fiber optic cables shall be run in GI Conduit pipes or other means

    acceptable to the National Grid Saudi Arabia.. Furthermore for the redundant

    schemes using Fiber Optic cables, routing of Fiber Optics cables shall be such

    that "collapsed ring" schemes and routing of the redundant schemes in the

    same routing media shall be avoided.

    3.2.7 The communication buses (both station communications bus and inter-bay communications bus) shall be designed in dual redundant fault-tolerant rings

    at all voltage levels. For the links between individual bay IEDs to Ethernet

    switches a "star" scheme shall be used. It shall be such that failure of one set

    of fibers shall not affect the normal operation of the SAS. However failure of

    any fibers shall be alarmed in SAS. Additionally, fiber optics cable

    connection shall provide sufficient fibers for the actual connection plus 20%

    of overall fibers provided (along with the required fiber optics

    termination/connectors) to support ease of replacement in event of failures of

    individual working fibers.

    3.2.8 To increase system performance and availability the cable routing/communication buses requirement shall be as follows:

    a. The inter-bay busses shall be independent and redundant at each voltage level.

    b. Inter-bay buses shall be independent of each other for each voltage level, as shown in the conceptual diagram, Substation Automation System Diagram (Conceptual), Drawing Fig 07-01. The detailed requirements related to the required common interconnections at the different levels

    shall be designed by the Manufacturer/Solution provider .

    3.2.9 The Station bus shall be fully redundant. At station level, the entire station

    shall be controlled and supervised from the station HMI. It shall be possible

    to control and monitor the bay from the bay level equipment in the event that

    the communication link fails. The station wide interlocking shall also be

    available when the station computer, IED(s), communications link, or other

    component of the SAS fails. To support station wide interlocking upon failure

    of the station computer, IED(s), communications link, or other component,

    there shall be hard wired interconnection both within a bay and between the

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 15 OF 119 Date of Approval: February 26, 2013

    required bays for keeping the interlocking intact. For the substation's

    interlocking requirements, manufacturer/SOLUTION PROVIDER shall meet

    the latest revision requirements of 32-TMSS-01 for metal clad switchgear

    (11kV, 13.8kV, 33kV or 34.5kV), 32-TMSS-02 for SF6 GIS (69kV through

    380kV) and 32-TMSS-03 for metal clad gas insulated medium voltage

    switchgear (11kV, 13.8kV, 33kV OR 34.5kV).

    3.2.10 To provide highest reliability the station HMI and the Communications

    Gateways shall work completely independent, i.e. the process data can be

    retrieved directly from the bay level devices. Additionally the

    Communications Gateway, Station HMI, communication buses (inter-bay bus

    and station bus), GPS Receiver (which are part of the Time Synchronization

    System) and Front End / Station Computer Unit, Firewalls and other related

    hardware shall be built and configured fully redundant to ensure full

    functionality and avoid single point of failure.

    3.2.11 Clear control priorities shall prevent the initiation of operation of a single

    switch at the same time from more than one of the available control levels, i.e.

    SCADA Master Station(s), station level, bay level or apparatus level. To

    ensure that clear control priorities exist, a hierarchy scheme between the

    various control levels shall exist.

    3.2.12 The priority shall always be on the lowest enabled control level. The station

    level contains the station-oriented functions, which cannot be realized at bay

    level, e.g. alarm list or event list related to the entire substation's SAS and

    Communications Gateway required for the communication with remote

    control centers.

    3.2.13 Dedicated master clock (GPS Receivers which are part of the Time

    Synchronization System) for the synchronization of the entire system shall be

    provided. This master clock should be independent of all station computer

    equipment and of the Communication Gateway and should synchronize all

    devices via the communication buses

    3.3 Ethernet Topology

    The following described criterias have to be fulfilled concerning the Ethernet switches and the topology.

    3.3.1 Ethernet Switches

    a. The proposed Ethernet (LAN) Switches shall be modular, industrially hardened, fully manageable and specifically designed to build Ethernet

    networks for mission critical, real-time control applications in utility

    substation environments.

    b. These hardened requirements include. (but may not be limited to) temperature, EMC and power supply (DC from the station battery) which

    are suitable to be installed in the substation operating at the voltage

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 16 OF 119 Date of Approval: February 26, 2013

    levels of the substation (indicated in Section 1 of this Standard, are

    included in this specification.

    c. The proposed LAN switches shall be equipped with dual DC (125 VDC)

    power supplies.

    d. The switches shall support priority tagging and open standards for ring

    management.

    e. External switches are required as they have the advantage that there is no interruption or reconfiguration of the Ethernet ring if one or several bay

    devices are taken out of service.

    f. Ethernet switches for inter-bay buses shall have 100Base-FX technology

    (fiber optic-100MBPS) for inter connection of all IEDs (control,

    protection and combined protection/control IEDs) with EHV/HV and

    MV inter bay buses (PRP1- Bay LAN) and have Gigabit Ethernet

    1000Mbps to connect Ethernet switches inside each ring EHV/HV and

    MV inter-bay buses (PRP1-Bay LANs) and each ring of station buses

    (PRP1-Station LANs) provided by SOLUTION PROVIDER. There shall

    be consistency throughput for all inter-bay signals being provided from

    the IEDs located throughout the substation and shall be consistent with

    IEC 61850 requirements.

    g. Security Features:

    Should provide multilevel security/user passwords to prevent

    unauthorized users from altering the switch configuration.

    SNMPv3 encrypted authentication and access security

    Support authentication/Centralized password management

    (RADIUS)

    IEEE 802.1q VLANs to segregate and secure network traffic

    Port based Network access control (IEEE 802.1x)

    Secure Shell (SSH)/Secure Sockets Layer (SSL) encryption.

    h. Management Features:

    Support enhanced traffic management, monitoring, and analysis,

    through Embedded Remote Monitoring (RMON) software agent

    supporting at least four RMON groups (history, statistics, alarms,

    and events).

    Telnet, CLI, LAN Switch Vendor GUI, and Web based

    management interfaces.

    Support for SNMP v3 interface to deliver comprehensive in-band

    management.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 17 OF 119 Date of Approval: February 26, 2013

    3.3.2 System Architecture

    The system architecture shall be based on completely distributed approach

    also concerning the connection of any device to the system. Meaning any

    device protection as well as control and station level devices shall be directly

    connected to the Ethernet backbone.

    3.3.3 Redundant Networks

    a. To ensure maximum performance and availability the network shall

    b. For the inter-bay bus level of the SAS which contains the Ethernet

    Switch connections for the Control IEDs, the Protection IEDs, the

    SAS Front End Computers, and Communications Gateways, as a

    minimum, redundant LAN configuration shall be provided by the

    SOLUTION PROVIDER at all voltage levels, with separate redundant

    networks provided for the IEDs at each voltage level.

    c. The separate redundant networks at all voltage levels shall be

    provided where the redundant inter-bay bus is interconnected with the

    redundant station bus.

    d. Refer to Section 14 of this Standard for further redundancy

    implementation requirements which is to be implemented by the

    SOLUTION PROVIDER .

    e. The Bid proposal shall fully describe the proposed networks scheme.

    This shall be supported by detailed network block/schematic

    diagrams.

    4.0 FUNCTIONAL REQUIREMENTS

    4.1 General SAS Functionality

    4.1.1 Control Scheme Hierarchy

    a. A scheme with a predetermined hierarchy shall be provided for the

    operation of the high-voltage apparatus. As such, the high voltage

    apparatus within the station shall be operated from different places

    (from the lowest level to the highest level):

    Bay-oriented Local Control Panel with Mimic Diagram (Mimic)

    Control IED

    Combined Control/Protection IED

    Station HMI

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 18 OF 119 Date of Approval: February 26, 2013

    Power Control Center (PCC/SCADA Master Station/LDC):

    b. In the scheme shown above, operation of a specific piece of high

    voltage apparatus shall be allowed to be performed by only one

    operation at a time. To insure this, double operation interlocking shall

    be employed. Double operation interlocking shall be employed as part

    of the hard-wired interlocking scheme, as well as the

    Software/GOOSE interlocking scheme resident in the Control IEDs and the combined Control/Protection IEDs.

    4.1.2 Control Scheme-Select-before Operate

    For safety and security reasons the command execution is always to be given

    in two stages, with the first stage being the selection of the object that is to

    be controlled, and the second stage being the operation (execution) of the

    object being selected. This select before operate scheme shall be applicable

    for the Control IED level, the combined Control/Protection IED level, and

    the Station HMI level Also, depending on the SAS Equipment

    Manufacturers design, and National Grid Saudi Arabia requirements/standards, either a direct select before operate scheme, a direct operate scheme, or a modified two handed select-before-operate scheme may be applicable for emergency operation through the Bay

    Oriented Local Control Panels with Mimic.

    4.1.3 Self Supervision

    The entire SAS shall be designed with continuous self-supervision features

    of the entire SAS installation, with self-diagnostic features for the SAS to

    specifically pinpoint trouble/mal-operation areas of the SAS. Generally, the

    self-diagnostic features will be built into the Station HMI, with displays

    available for these diagnostics on the Operator's Workstation and/or

    Engineering Workstation.

    4.1.4 User Configuration

    a. The monitoring, controlling and configuration of all input and output

    logical signals and binary inputs and relay outputs for all built-in

    functions and signals shall be possible both locally and remotely.

    b. It shall also be possible to interconnect the built-in functions using

    additional logics (AND-gates, OR-gates and timers) as well as to

    configure additional functions such as over-current, over-voltage,

    etc.(multi-activation of these additional functions should be possible).

    4.1.5 Division of Functional Requirements

    a. The functional requirements shall be divided into two areas which are

    shown in the two paragraphs below.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 19 OF 119 Date of Approval: February 26, 2013

    b. The Bay level functions shall comprise of operations within one bay

    only, with the bay comprising of one circuit breaker, associated

    disconnectors (isolation switches), earthing (grounding switches) and

    associated instrument transformers (PTs and CTs).

    c. System Level functions which look at the SAS and the substation as a

    whole.

    4.1.6 Direct Connection between PTs/CTs to SAS IEDs for Analog inputs

    Analogue inputs for voltage transformers (PTs/VTs) and current

    transformers (CTs) measurements shall be connected directly to the voltage

    transformers (PTs/VTs) and the current transformers (CTs) without

    intermediate transducers. The values of active power (W), reactive power

    (VAR), frequency (Hz), and the rms values for voltage (U) and current (I)

    shall be calculated on the Control IEDs, combined Control/Protection IEDs

    and Protection IEDs. All readings on all SAS equipment shall be direct on all

    displays, taking into account the scaling factors for each device (CTs and

    PT/VTs).

    4.2 Bay Level Functions

    4.2.1 In a decentralized architecture the functionality shall be as close to the process as possible.

    4.2.2 In this respect, the following functions shall be allocated at bay level:

    a. Bay control functions including data acquisition/data collection

    functionality in Bay Control IED's .and combined Control/Protection

    IEDs

    b. Bay protection functions including data acquisition/data collection

    functionality in Bay Protection IED's. and combined

    Control/Protection IEDs

    c. Data collection functionality.

    4.2.3 Bay control functions

    a. Overview

    Basic functions

    Control mode selection(Local/Off/Emergency/Remote)

    Select-before-execute principle

    Command supervision: o Interlocking and blocking

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 20 OF 119 Date of Approval: February 26, 2013

    o Double command

    Autoreclosing (may be considered as either a control function or protection function, depending on National Grid Saudi

    Arabia requirements)

    Synchrocheck, voltage selection (may be considered as either a control function or protection function, depending on

    National Grid Saudi Arabia requirements)

    Interruption of drive latching in case runtime is exceeded

    Monitoring pole discrepancy and trip function, if applicable

    Transformer tap changer control raise/lower (for power transformer bays)

    Operation counters for circuit breakers and pumps, if applicable

    Hydraulic pump control and runtime supervision, if applicable

    Pump start cascading, if applicable

    Anti pumping of circuit breaker (open/close)

    Operating pressure supervision through digital contacts only

    Display of interlocking and blocking

    Breaker position indication on a three phase basis with indication showing pole discrepancy conditions/alarms where

    pole discrepancy between the phases is detected/indicated

    Alarm annunciation

    Measurement display

    Local HMI (local guided, emergency mode)

    Interface to the station level

    Data storage for at least 200 events

    Run Time Command cancellation

    Extension possibilities with additional I/O's inside the unit, installation of additional units and/or via fiber optic

    communication and process bus

    Additional functions, if any, specified in Main PTS/SCADA & Protection Appendices.

    Advanced functions

    Disturbance recording with capabilities for all analogue and binary values

    Extension possibilities with additional I/O's inside the unit or via fiber-optic inter-bay communications and process bus

    b. Control Mode Selection

    As soon as the operator receives the operation access at bay level the operation is normally performed via the local HMI.

    During normal operation the local HMI is guided and allows

    the safe operation of all switching devices via the bay control

    IED or the combined control/protection IED.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 21 OF 119 Date of Approval: February 26, 2013

    It will be ensured that Protection features for the station (through the Protection IED's or the combined

    control/protection IED used for the station protection function)

    shall be functioning irrespective of the Control Mode.

    In the event that the bay control IED or a combined control/protection IED fails, the operator shall have access to

    the essential bay switchgear via a separate bay-oriented local

    control panel with mimic diagram for High Voltage

    switchgear, or via the Low Voltage Compartment for Medium

    Voltage switchgear. This is an emergency function.

    i. OFF Mode

    It is not possible to operate any object, neither locally

    nor remotely.

    ii EMERGENCY Mode

    A. The position indication shall be directly from

    the primary equipment bay switchgear being

    controlled.

    B. On the bay-oriented local control panel with

    mimic diagram, for the two handed operate principle, the device selection push button and

    either the ON or OFF push button has to be

    pushed simultaneously in order to close or open

    the primary equipment bay switchgear. For the

    single handed operate principle, as indicated in latest revision of 32-TMSS-02 each device

    will have its own OFF or ON push button to press, and the operator will not be required to

    use two hands to operate a device. Control

    operation from other places (e.g. from

    REMOTE or LOCAL) shall not be possible in

    this operating mode.

    iii. LOCAL (BCU) Mode

    A. On the HMI the object has first to be selected.

    In case of a blocking or interlocking conditions

    the selection will not be possible and an

    appropriate alarm annunciation shall occur.

    B. If a selection is valid the position indication will

    show the possible direction and the appropriate

    ON or OFF button shall be pressed in order to

    close or open the corresponding object.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 22 OF 119 Date of Approval: February 26, 2013

    C. Control operation from other places (e.g.

    REMOTE) shall not be possible in this

    operating mode.

    iv. REMOTE-STATION LEVEL mode

    Control authority in this mode is given to the next

    highest level (the Station HMI level) and the

    installation can be controlled only remotely via the

    Station HMI. Control operation from lower levels shall

    not be possible in this operating mode.

    v. REMOTE-PCC LEVEL mode

    Control authority in this mode is given to the highest

    level (SCADA Master Station) via the Station HMI and

    the installation can be controlled only remotely via the

    PCC (SCADA Master Station/LDC). Control operation

    from lower levels shall not be possible in this operating

    mode. National Grid Saudi Arabia notes that control

    from this mode shall also be available in the event of

    failure of even the (redundant) Station HMI Front End

    computers, in which PCC Control and Data Acquisition

    information will be transmitted and received directly

    from the Communications Gateways to the applicable

    Control IEDs and combined Control/Protection IEDs through the IEC 61850 Inter-bay bus.

    c. Command supervision

    Bay/station interlocking and blocking

    i. Interlocking facilities have to be installed in the

    switchgear to prevent damages and accidents in case of

    false operation.

    ii. Within the bay itself, a system of hard-wired interlocks and software/GOOSE interlocking controlled only

    through the Bay Control IEDs (in conjunction with the

    Bay Oriented Local Control Panel with Mimic) shall be

    used. However, upon failure of a bay Control IED(s)

    and/or combined Control/Protection IED(s) or

    communications link(s), the hard-wired interlocking

    shall operate and prevail. The SOLUTION PROVIDER

    's proposed solution shall describe the bay interlocking

    scenario in event of switching off or failure of a bay

    Control SAS component(s) (Control IED(s) or

    combined Control/Protection IED(s)),or other SAS

    components.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 23 OF 119 Date of Approval: February 26, 2013

    iii. Station interlocking systems shall be provided via hardwired or inter-bay bus. However, upon failure of

    station computer, IED(s), communications link (inter-

    bay bus), or other component of the SAS, the

    hardwired station interlock shall operate and prevail. It

    shall be a simple layout, easy to test and simple to

    handle when upgrading the station with future bays.

    The SOLUTION PROVIDER's proposed solution shall

    describe the station interlocking scenario in event of

    switching off or failure of a bay Control SAS

    component(s) (Control IED(s) or combined

    Control/Protection IED(s)),or other SAS components.

    iv. Software/GOOSE "interlock override" functionality

    shall be available as part of the SAS. However, there

    shall be methods available to disable such a

    software/GOOSE bay/station "interlock override scheme and/or to allow only access to this

    software/GOOSE "interlock override" scheme by

    privileged users using strong passwords and other

    security features.

    Double operation interlocking

    i. Double operation interlocking prevents the operation of

    two or more switches at the same time. The double

    operation interlocking is a part of the station

    interlocking; it shall preferably be hard-wired, but

    provisions shall also be made in the SAS design for

    software (GOOSE) double operation interlocking. It

    shall be included for all the switches in the station. It

    should be noted that unless interlocked for some

    specific purpose (other than for Double Operation

    Interlocking), there is no need of preventing

    simultaneous operation of switches located in different

    bays.

    ii. With a hard-wired solution the interlocking is independent from the control authority of the station. If

    a control IED and/or a combined Control/Protection

    IED fails, the double operation interlocking does not

    block the operation of the station. It shall still be

    controlled from all the control authorities. Refer to

    above Section i (under double operation interlocking) of

    this Standard for further details pertaining to the overall

    requirements for Double Operation Interlocking.

    iii. The proposed solution shall describe the double

    operation interlocking scenario while an IED of

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 24 OF 119 Date of Approval: February 26, 2013

    another bay or another component of the SAS is

    switched off or fails.

    Other General Interlocking requirements

    i. For software/GOOSE interlocks, schemes which use

    the Station HMI (or other Front End) Computer

    equipment to make ANY software/GOOSE

    interlocking decisions or transfer software/GOOSE

    interlocking data shall NOT be used..

    Software/GOOSE interlocking scheme shall ONLY

    utilize the Bay Control IED equipment, the combined

    Control/Protection IED equipment, and

    intercommunications (through GOOSE messages)

    between Control IEDs and combined

    Control/Protection IEDs to support software/GOOSE

    interlocking requirements.

    ii. For the backup hard wired interlocking scheme/solution, Solution provider shall consult with

    National Grid Saudi Arabia during the Base Design

    stage of the project to determine if there is a need to

    incorporate hard-wired interlock bypass/override in the related SAS design.

    iii. For interlocking signals which are required between voltage levels in each substation which will be used for

    software/GOOSE interlocking, these interlocking

    signals described in this paragraph shall be transmitted

    and received between voltage levels in hardwired form

    and inputted/outputted to the other voltage levels

    through GGIOs/Digital Inputs/Digital Outputs between

    the related Control IEDs. This is required to guarantee

    that separate dedicated IP Subnets can be allocated for

    each voltage level in each substation.

    iv. For the relation between software/GOOSE and backup hard wired interlocks, a series downstream principle will be used. This series downstream principle will first check the conditions of the

    software/GOOSE interlocks and if the interlocking

    conditions are satisfied at the software/GOOSE level at

    the control or combined control/protection IED, then

    the control signal will then pass to the hard wired interlocks, and if it is determined at the hard wired interlocking level that the interlocking conditions are

    satisfied, the control signal will then pass to the related

    switchgear device.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 25 OF 119 Date of Approval: February 26, 2013

    v. Finally, the hard wired interlock scheme shall be configured in such a way that, once the National Grid

    Saudi Arabia obtains enough satisfactory operating

    experience with the software/GOOSE interlocking

    scheme, then National Grid Saudi Arabia personnel can

    later easily disable the hard wired interlock scheme and later only rely on software/GOOSE interlocking for

    the bay/station interlocking functionality.

    Synchronism and energizing check

    i. The synchronism and energizing check functions shall

    be bay-oriented and distributed to the bay control

    and/or protection devices. These features are:

    A. Adjustable voltage, phase angle and frequency difference.

    B. Energizing for dead line-live bus, live line-dead bus or dead line-dead bus with no synchro-check

    function.

    C. Synchro-check between live line and live bus with synchro-check function.

    D. Settings for manual close command and autoreclose command shall be adaptable and adjustable for the

    operating times of the specific switchgear.

    E. Determination of a live line/dead line or a live bus/dead bus shall be provided automatically at the

    IED level for the particular bays where the IED's

    are installed by looking at the configuration of

    related circuit breakers, disconnects (isolators) and

    earthing (grounding) switches.

    F. Furthermore, use of "sampled value" messages from adjacent IED's to transmit analog information

    from PTs (VTs) (either line or bus PTs (VTs)) shall

    NOT be accepted for performing synchro-check

    inside an IED.

    G. Depending on National Grid Saudi Arabia requirements as stated in the related Appendix of

    the main PTS, synchronism and energizing check

    may be required to be performed by dedicated

    Synchrocheck Relays/IEDs and NOT Control or combined Control/Protection IEDs

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 26 OF 119 Date of Approval: February 26, 2013

    ii. Voltage selection

    A. The voltages relevant for the synchro-check functions are dependent on the station topology, i.e.

    on the positions of the circuit breakers and/or the

    isolators.

    B. The correct voltage for synchronizing and energizing is derived from the auxiliary switches of

    the circuit breakers, the isolator, and earthing

    switch and related PTs and shall be selected

    automatically by the Bay Control IEDs and/or

    Protection IEDs. The correct voltage selection shall

    also be dependent on the bay/station one-line

    scheme (e.g. double bus bar-single breaker, breaker

    and one-half, double bus, etc.) for each substation

    to be equipped with SAS.

    C. Voltage selection (which is required for synchronism and energizing check as described

    Section i under Synchronism and energizing check)

    shall be an integral function of the IED or

    Synchrocheck Relay, and NOT through external

    means.

    D. Depending on National Grid Saudi Arabia requirements as stated in related Appendix of the

    main PTS, voltage selection may be required to be

    performed by dedicated Synchrocheck

    Relays/IEDs and NOT Control IEDS or combined Control/Protection IEDs

    Auto-reclosing and related synchro-check functions

    i. These functions can be considered as either control or

    protection functions.

    ii. Depending on the National Grid Saudi Arabia

    requirements as indicated in related Appendix of the

    main PTS, autoreclosing and synchro-check (related to

    auto-reclosing) may be implemented in a general

    Control IED or combined Control/Protection IED (used

    for general substation switchgear control) or a

    dedicated Autoreclosing functional unit (Control IED

    or combined Control/Protection IED or

    Autoreclosing/related Synchro-Check built into a

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 27 OF 119 Date of Approval: February 26, 2013

    Protection IED) integrated into the Protection portion

    of the SAS.

    iv. The autorecloser should be settable for the following modes of operation:

    A. First autoreclosure sequence:

    Three-phase autoreclosure Single/three-phase autoreclosure Single-phase autoreclosure

    B. Further auto-reclosure sequences:

    No further auto-reclosure sequences Further auto-reclosure sequences (totally 2, 3 or

    4 sequences), always three-phase sequences

    iv. It shall be possible to perform all three-phase

    autoreclosure sequences with or without synchro-

    check.

    v. If synchro-check is required for any autoreclosure

    sequence, refer the sub heading Synchronism and energizing check above and its subsections for a description of the synchro-check, and voltage selection

    functionality

    Run Time Command cancellation

    If the control action is not completed within a specified time,

    the command shall get cancelled, and an alarm/event shall be

    raised at the Station HMI level (which may be reported to the

    PCC (SCADA Master Station level). For operation of

    switchgear which involves drive latching the latching shall be

    interrupted by the Control IED or combined Control/Protection

    IED and the drive motor power (for the latched device) shall

    be interrupted also by the Control IED or the combined

    Control/Protection IED. National Grid Saudi Arabia requires

    that the Run-Time Command Cancellation functionality and

    the Command cancellation execution timer be embedded in the

    Control IEDs and combined Control/Protection IEDs either through the use of dedicated IEC 61850 Logical Nodes, or

    general timer/logic gates which are incorporated in the IED

    which can be configured by the user/manufacturer (by

    software) through the IED configuration process.

    Pole discrepancy monitoring/relaying (if applicable)

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 28 OF 119 Date of Approval: February 26, 2013

    A Pole Discrepancy monitoring function, based on the

    measurement of phase over-currents and current differences

    between phases as well as on breaker pole status (which is

    determined by reading the auxiliary contacts on each pole of

    the breaker) has to be provided. Also, depending on the SAS

    Equipment manufacturer's design, additional Pole Discrepancy

    Relaying may be included in the SAS as an integrated

    function. If the additional Pole Discrepancy Relaying is

    provided as part of the SAS, the Pole Discrepancy Relaying

    feature integrated into the SAS shall support Stage I and Stage

    II Pole Discrepancy Relaying functions, as well as being able

    to initiate Pole Discrepancy Trip signals to remote substations

    via Protection Signaling equipment (PSE), and

    Communications equipment (PSE and Communications

    provided by other parts of the project, as applicable). Refer to

    related Appendix of the main PTS to determine additional

    information on whether Pole Discrepancy monitoring/relaying

    will be through separate Pole Discrepancy Relays, or

    integrated into the functionality of SAS (Note: If main PTS

    specifies separate dedicated external Pole Discrepancy Relays,

    there will still be a requirement to monitor Stage I and Stage II

    Pole Discrepancy from the external Pole Discrepancy Relay(s)

    through SAS as part of the alarm function of SAS.).

    Transformer tap changer control

    i. Voltage regulation for single transformers or parallel

    transformers with on-load tap-changer shall either be

    included in the numerical control unit for the power

    transformer or located in a separate tap changer control

    device which is associated with the power transformer.

    ii In the event that a separate tap-changer control device

    is selected, this shall be an integral part of the SAS like

    any bay oriented Control IED or Protection IED.

    iii. OLTC scheme shall be .accomplished by the Control

    IED's and/or dedicated Tap Changer IEDs (which have IEC 61850 interfaces) which will be performing

    the regulation and tap changing function.

    iv. National Grid Saudi Arabia notes that a built-in

    numerical control unit is preferred instead of a separate

    tap changer unit. Also, the Transformer tap changer

    control scheme shall meet latest revision of TES-P-

    119.26 for control schemes for each Substation's

    Equipment.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 29 OF 119 Date of Approval: February 26, 2013

    d. Interface between Control IEDs and Maintenance Laptop Computer

    and also between combined Control/Protection IEDs and Maintenance

    Laptop Computer:

    All IEDs used for the Control functions shall be provided with a serial,

    Ethernet RJ45 and/or optical front connector for connection to a

    Maintenance Laptop Computer.

    e. Interface between the Control IEDs, the combined Control/Protection

    IEDs and the inter-bay Bus pertaining to IEC 61850 and IEC 62439-3

    PRP1:

    For IEDs used for dedicated control, and/or combined

    control/protection, each Control IED and combined Control/Protection

    IED shall have full interfacing to the inter-bay communications bus

    only through IEC 61850 and IEC 62439-3 PRP 1. Use of Protocol

    Converters to convert from legacy protocols (e.g. DNP 3.0,

    MODBUS, IEC-103, etc.) to IEC 61850/IEC 62439-3 PRP 1 will

    NOT be accepted by the National Grid Saudi Arabia. REDBOX is not

    acceptable for IEDs. For other equipment it is subjected to National

    Grid Saudi Arabia review and acceptance. Refer enclosed drawing Fig

    07.01 which shows where REDBOX is acceptable.

    4.2.4 Bay protection functions

    a. General

    For all voltage levels except for the Medium Voltage level, the protection functions shall be independent of the control

    functions (i.e. the Protection IED will NOT be performing

    Control IED functions). For the Medium Voltage level, unless

    specified in the main PTS, both control functions and

    protection functions for a bay can be provided in one IED

    (which will be known as a combined Control/Protection IED).

    Refer to the related Appendix of the main PTS involving Relay

    and Protection for further details on the functionalities

    involved, as well as other details.

    Furthermore, at the High Voltage level, for trip applications/trip commands, where there is a dedicated

    Protection IED, the Protection IED shall perform the tripping

    functions ONLY, and this tripping function shall NOT be

    passed on to a Control IED (either through hard-wired means

    and/or through use of GOOSE messages).

    The protection functions are an integral part of the Substation Automation System.

    All protection functions realized in the IEDs should be based on numerical technology.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 30 OF 119 Date of Approval: February 26, 2013

    All IEDs shall be serial integrated for data sharing and meet the real-time communication requirements for automatic

    functions. The data presentation and the configuration of the

    various IEDs shall be compatible with the overall system

    communication and data exchange requirements.

    All IEDs used for the protection functions (Protection IEDs and the combined Control and Protection IEDs) shall also be

    provided with a serial, Ethernet RJ 45 and/or optical front

    connector for connection to a Maintenance Laptop Computer.

    For IEDs used for dedicated protection and/or combined control/protection, each Protection IED and combined

    Control/Protection IED shall have full interfacing to the inter-

    bay communications bus only through IEC 61850 and IEC

    62439-3 PRP 1. Use of Protocol Converters to convert from

    legacy protocols (e.g. DNP 3.0, MODBUS, IEC-103, etc.) to

    IEC 61850/IEC 62439-3 PRP 1 will NOT be accepted by the

    National Grid Saudi Arabia. REDBOX is not acceptable for

    IEDs. For other equipment it is subjected to National Grid

    Saudi Arabia review and acceptance. Refer enclosed drawing

    Fig 07-01 which shows where REDBOX is acceptable.

    This Standard only describes general Protection Requirements, with more specific protection requirements outlined in related

    portions of the main PTS/standards. Refer to the related

    Appendix of the main PTS/standards for Protection (Protective

    Relaying) functions for the IEDs.

    b. Self-supervision

    Continuous self-supervision function with self-diagnostic possibilities

    shall be included.

    c. Event and disturbance recording function

    Each Protection IED and combined Control/Protection IED shall contain an event recorder capable of storing at least 256

    time-tagged events. A Protection IED and combined

    Control/Protection IED shall also provide the user, either

    locally or remotely, with complete information on the last ten

    disturbances.

    A disturbance recorder with a minimum of 5 seconds recording time for at least 10 disturbances shall provide the user with

    time-tagged disturbance records.

    At least the analogue inputs as well as 16 binary signals must be recorded.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 31 OF 119 Date of Approval: February 26, 2013

    The pre-fault and fault currents and voltages shall be recorded for each disturbance and be made available for further

    evaluation purposes.

    d. Local HMI

    The local human machine interface (HMI) shall be front-mounted and based on a user-friendly, menu-structured

    program, and performed with the use of a permanently

    installed human machine interface unit, type-tested together

    with the protection terminal.

    In addition service values of current and voltages as well as active and reactive power (if voltage measurements included)

    shall be available. Also the characteristic analogue values

    related to the activated functions (e.g. impedance in case of

    distance protection) should be available.

    4.2.5 Line protection

    a. General

    The Protection IED and combined Control/Protection IED devices which incorporate numerical line protection shall be

    selected for the protection of lines according to specific

    network configurations and conditions. The scheme must

    ensure reliable isolation for all kind of faults that might occur

    on the specific line as per protection requirements stipulated in

    Protective Relaying Appendix to the main PTS/Protective

    Relay Standard.

    Depending on the voltage level and complexity, the following line protection functions may be required:

    b. Distance function

    Distance function requirements shall be compatible to the relay

    requirements indicated in Protective Relaying Appendix to the main

    PTS/Protective Relay Standard.

    c. Differential function

    Differential function requirements shall be compatible to the relay

    requirements indicated in Protective Relaying Appendix to the main

    PTS/Protective Relay Standard.

    d. Earth fault function

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 32 OF 119 Date of Approval: February 26, 2013

    Earth fault function requirements shall be compatible to the relay

    requirements indicated in Protective Relaying Appendix to the main

    PTS/Protective Relay Standard.

    e. Fault location

    Fault location function requirements shall be compatible to the relay

    requirements indicated in Protective Relaying Appendix to the main

    PTS.

    f. Transformer protection

    General

    i. The transformer protection shall be suitable for the

    protection of two- or three-winding transformers,

    auto-transformers, reactors, and generator-transformer

    block units, as per protection requirements stipulated

    in Protective Relaying Appendix to the main PTS or

    standard.

    ii. The numerical transformer terminal shall be designed

    to operate correctly over a wide frequency range and to

    accommodate for system frequency variations and

    block generator start-ups.

    Current differential function

    Refer to the Protective Relaying Appendix to the main PTS or

    Protective Relay Standard for further details.

    Other functions

    Refer to the Protective Relaying Appendix to the main PTS or

    Protective Relay Standard for further details.

    Breaker failure protection

    i. The breaker failure protection shall comprise two time

    stages. The first stage shall be bay-oriented and shall

    re-trip the local circuit breaker.

    ii. The second stage shall be station-oriented, requiring

    information from other bays, and shall trip the circuit

    breakers in adjacent bays.

    iii. Refer to the Protective Relaying Appendix to the main PTS or Protective Relay Standard for further details.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 33 OF 119 Date of Approval: February 26, 2013

    4.3 System/Station level functions

    4.3.1 Control

    a. The different high-voltage switchgear and medium voltage switchgear

    within the station shall be operated from different places:

    from the remote control centers (SCADA Master Station(s))

    from the station level

    For High Voltage switchgear from the Control IED(s) in the LCC(s) (in the bays)

    For High Voltage switchgear from the Bay-Oriented Local Control Panel(s) with Mimic Diagram

    For Medium Voltage switchgear from the Control IED(s)/combined Control/Protection IED(s)

    For Medium Voltage switchgear from the Low Voltage Compartment(s)

    b. Operation shall only possible by one operator at a time.

    c. The operation shall depend on the conditions of other functions, such

    as interlocking, synchrocheck, etc. (see description in chapter Bay control functions).

    4.3.2 Status supervision

    a. The position of each switchgear, e.g. circuit breaker, isolator, earthing

    switch, transformer tap changer etc., shall be supervised permanently.

    Every detected change of position shall be immediately visible in the

    single-line diagram on the station HMI screen, recorded in the event

    list, and a hard copy printout shall be produced. Alarms shall be

    initiated in the case of spontaneous position changes.

    b. The switchgear positions shall be indicated by two auxiliary switches,

    normally closed (NC) and normally open (NO), which shall give

    relevant signals. An alarm shall be initiated if these position

    indications are inconsistent or if the time required for operating

    mechanism to change position exceeds a predefined limit.

    c. The SAS shall also monitor the status of substation auxiliaries (which

    will include, but not be limited to auxiliary relays such as trip current

    supervision, DC supervision, etc.).. The status and control of

    auxiliaries shall be done through separate one or more Control IEDs

    and all alarm and analogue values shall be monitored and recorded

    through the respective Control IEDs. It is noted also by the National

    Grid Saudi Arabia that monitoring of the status of auxiliaries shall

    NOT be performed from dedicated Protection IEDs or combined Control/Protection IEDs.

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 34 OF 119 Date of Approval: February 26, 2013

    4.3.3 Measurements

    a. The measured values shall be displayed locally on the Local HMI

    contained as part of an IED, Station HMI and in the control center

    (SCADA Master Station(s)). At the Station HMI level, facilities shall

    exist to discard abnormal values (through the Station HMI Filtering

    functions) and when an abnormal value is reached, generate an

    alarm/event indicating that an abnormal value (s) has been detected.

    b. All analogue values shall be updated (both in Local HMIs (contained

    as part of the IEDs), and Station HMI equipment every 2 seconds, or

    faster.

    c. Threshold limit values shall be selectable for alarm indications.

    4.3.4 Event and alarm handling

    a. Events and alarms shall be generated either by the switchgear, by the

    control IEDs, by the protection IEDs, by the combined

    control/protection IEDs, or by the station level unit.

    b. They shall be recorded in an event list in the station HMI. Alarms

    shall be recorded in a separate alarm list and appear on the screen. All,

    or a freely selectable group of events and alarms shall also be printed

    out on an event printer.

    c. The alarms and events shall be time-tagged with a time resolution of 1

    ms National Grid Saudi Arabia notes that the time tagging of the

    alarms and events shall be performed at the IED itself only, and NOT

    through SAS Computer equipment..

    d. During the Base Design Stage, the Solution provider shall submit the

    Events and Alarms List (Signals List) for National Grid Saudi Arabia

    approval, and once approved the Solution provider will use this

    approved list as a basis for development of his SCD files for SAS.

    e. As a minimum, the Signals and Events List shall contain all applicable

    points as identified in TES-P-119.27 the SOE Points List and the

    approved Annunciator Alarms List for the Substation. Also, in

    development of the Events and Alarms List, separate dedicated lists

    shall be generated for SOE, SCADA, and the Station HMI contained

    as part of the Substation Automation System for review and approval.

    f. Finally as part of the events and alarms handling requirement, when

    there are cases where IEC 61850 DOES NOT provide for

    alarms/events as part of the logical node (LN) signals definitions

    (under IEC 61850) and where these alarms/events signals are required

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 35 OF 119 Date of Approval: February 26, 2013

    under latest revision of Engineering Standard TES-P-119.27 (for

    SCADA) the SOE Points List, and the National Grid Saudi Arabia

    approved Annunciator Alarms List for the Substation, the SOLUTION

    PROVIDER shall provide suitable auxiliary binary input contacts

    (and/or binary outputs) as part of each IED design to extend non IEC

    61850 alarms/events by hard-wired means to other components of the

    SAS (which will appear as one of the GGIOs included as part of the

    SAS Data Acquisition function which will be reported to the Station

    HMI, the SCADA Master Stations and other equipment).

    g. In/Out facility for the protection is isolating trip out put only during

    maintenance of relays. However during this condition all alarms to

    remote Master stations shall be isolated in order to avoid receiving any

    nuisance alarms during maintenance. Facility for isolating alarms shall

    be provided as part of relays or at the Gateways.

    4.3.5 Time Synchronization System

    a. A dedicated clock synchronization unit shall set the time within the

    SAS. Time synchronization of all SAS equipment shall be

    independent of the station level equipment e.g. station computer or

    Communications Gateway. Time Synchronization shall be from

    redundant GPS receivers located on the property of each substation.

    The time shall then be distributed to the control IEDs, combined

    Control/Protection IEDs and protection IEDs and other SAS

    equipment via the communication buses. An accuracy of 1ms (from

    the actual time) within the substation (and for ALL SAS components

    within the substation which require time signals) is required.

    b. Hardware/Firmware for the GPS receivers supplied by the

    SOLUTION PROVIDER shall provide for a antenna, decoder, other

    hardware, interfaces with the SAS and Firmware as per the latest IRIG

    B122 or other National Grid Saudi Arabia approved standard time

    code format (e.g. SNTP and others).

    c. Software for the GPS receivers shall include a software package to

    implement GPS-based time as per at least IRIG B122 standard time

    code format (Day of Year and Time update rate of once per second,

    AM 1 KHz carrier, resolution of + 1 mS, expressed in hh, mm, ss,

    ddd) or other National Grid Saudi Arabia approved standard time code

    format and able to synchronize time and date into the SAS, with all

    components of the SAS receiving consistent time and date

    information.

    d. Upon failure of any GPS receiver in the time synchronization system,

    the GPS receiver shall transmit an alarm to both the Station HMI

    equipment in the SAS, and the remote SCADA Master Station(s).

  • TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0

    TESP10701R0/KSB

    PAGE 36 OF 119 Date of Approval: February 26, 2013

    e. In the event of failures of both GPS clock receivers which are beyond

    the control of the GPS clock receivers (e.g. shutdown of the GPS

    satellite network, atmospheric conditions blocking reception of GPS

    signals at the GPS receivers, etc.) there shall be a means of time

    synchronization by the use of either internal SAS clocking sources

    (e.g. internal clocks inside the IED(s), etc). or tertiary clocking

    sources from the respective SCADA Master Station(s). In this respect,

    during the Base Design Stage, the SOLUTION PROVIDER shall state

    the holdover clocking accuracy of the internal SAS clocking sources,

    the clocking drift of these internal SAS clocking sources and the

    maximum allowable time which the SOLUTION PROVIDER feels

    that the infernal SAS clocking sources will provide accurate (+ 1 ms

    accuracy from real time) timing. If in the event that based on the

    SOLUTION PROVIDER provided information, that the internal SAS

    clocks will NOT provide accurate time information in the event of

    both GPS receivers failing, the National Grid Saudi Arabia during the

    Base Design will instruct the SOLUTION PROVIDER to utilize the

    existing SCADA Master Station(s) Clocks as a tertiary

    clocking/synchronization source and incorporate this SCADA Master

    Station(s) clock as a tertiary clocking/synchronization source.

    4.3.6 Telecontrol

    Remote access to each substation data shall be enabled via the control centers

    (SCADA Master Stations) upon request. The respective owners in the utility

    organization may use some or all information related to the conditions of high

    voltage apparatus.

    4.3.7 Station HMI-Presentation and Dialogues and Design

    a. General

    The operator Station HMI shall provide basic functions for supervision and control within the substation.

    The Station HMI shall be fully redundant and shall provide the functions for supervision and control of the substation. Access

    to the redundant Front End Computers shall be through the

    Operator's Workstations and the Engineer's Workstation.

    However to meet the redundancy requirements a backup

    workstation (included as part of a Maintenance Laptop

    Computer) shall be provided with software and firmware fully

    loaded which can be used to act as either the Operator's

    Workstation or Engineering Workstation in the event of failure

    of either the Operator's Workstations or Engineering

    Workstation contained as part of the SAS.

    The operator shall give commands to the switchgear on the screen via mouse clicks.

  • TRANSMISSION ENGINEERING STANDARD T