tes-p-107-01-r0
DESCRIPTION
SAS standardTRANSCRIPT
-
February 26, 2013
TESP10701R0/KSB
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 2 OF 119 Date of Approval: February 26, 2013
TABLE OF CONTENTS
1. SCOPE
2. INTRODUCTION
3. SYSTEM DESIGN
3.1 General System Design 3.2 System Architecture 3.3 Ethernet Topology
4. FUNCTIONAL REQUIREMENTS
4.1 General SAS Functionality 4.2 Bay Level Functions 4.3 System/Station Level Functions
5. PERFORMANCE REQUIREMENTS
5.1 Message Performance 5.2 System Performance
6 RELIABILITY AND SYSTEM DESIGN
6.1 Reliability Aspects
6.2 General Design Requirements
7. IEC 61850 AND IEC 62439-1 COMMUNICATION PROFILE
7.1 Introduction Related to IEC 61850
7.2 Typical Architecture and Required Communication Services Related to IEC 61850
8. CONFIGURATION TOOLS/SERVICE AND SUPPORT SYSTEM
9. GENERAL REQUIREMENTS
9.1 Compliance With Standards 9.2 Vendors/SOLUTION PROVIDERS experience and Proposal for the SAS
10. PROJECT EXECUTION
10.1 Engineering
10.2 Factory Acceptance Test (FAT)
10.3 SAT (Site Acceptance Test)/Pre-commissioning and Commissioning
10.4 Design and Operating Requirements
10.5 Services, After Sales and Maintenance
11. DOCUMENTATION
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 3 OF 119 Date of Approval: February 26, 2013
12. CYBER SECURITY REQUIREMENTS
13. KEMA CERTIFICATION
14. ADDITIONAL SUBSTATION AUTOMATION SYSTEM
15. DRAWINGS
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 4 OF 119 Date of Approval: February 26, 2013
1.0 SCOPE
This Transmission Engineering Standard (TES) specifies Substation Automation System
(SAS) required for 110kV through 380kV system voltage for the transmission system of
National Grid, Saudi Arabia.
2.0 INTRODUCTION
2.1 The Substation Automation System (SAS) shall be installed to monitor, control and protect all the substation equipment connected to SAS. Monitoring and control shall
be from the remote control center (Power Control Center/SCADA Master Stations)
as well through local means within the substation (e.g. Bay Oriented Local Control
with Mimic, Local HMI contained in the Control IED and Station HMI).
The Substation Automation System (SAS) comprises full station and bay protection
as well as control, monitoring and communication functions and provides all
functions required for the safe and reliable operation of the substation. It shall enable
local station control via a PC by means of a human machine interface (HMI) and
control software package, which shall contain an extensive range of Supervisory
Control and Data Acquisition (SCADA) functions. It shall include Communications
Gateway, station bus, inter-bay bus, time synchronization system and intelligent
electronic devices (IEDs) for bay control & protection.
The attached diagram entitled, Substation Automation System Diagram (Conceptual), Fig 07-01, is conceptual drawings for substation SAS configuration.
The Communications Gateway shall enable and secure the information flow with
remote Power Control Center and other remote Master Stations. Besides performing
protocol conversion, the Communications Gateway will perform Network/Port
Address Translation from internal SAS IP/Port addresses to external IP/Port
addresses in integrated units/computers.
The station bus shall provide the interconnections between the station level
subsystems (Front End/Station computer, Operators Workstation, Engineers Workstation, printer etc.). The inter-bay bus shall provide independent station-to-bay
and bay-to-bay data exchange. The bay level intelligent electronic devices (IEDs) for
protection and control shall provide the direct connection to the switchgear without
the need of interposing components and perform control, protection, and monitoring
functions.
The SAS control and monitoring system (SCMS) shall implement a network
redundancy based on IEC62439-3 PRP 1 (Parallel Redundancy Protocol) as shown
in the attached Substation Automation System Diagram (Conceptual), Drawing Fig 07-01, and as further explained in this Standard. Implementation of IEC62439-3 PRP
1 (Parallel Redundancy Protocol) applies to both the station LAN and bay LAN at all
voltage levels.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 5 OF 119 Date of Approval: February 26, 2013
2.2 All the SAS components shall comply with latest revision of SEC standards wherever applicable.
2.3 Summary of Main Functional Parts of SAS
2.3.1 As a summary, the SAS shall contain (but may not be limited) to the
following main functional parts:
2.3.2 Bay Control Intelligent Electronic Devices (Control IEDs) for control and monitoring.
2.3.3 Bay Protection Intelligent Electronic Devices (Protection IEDs) for the internal substation's protection applications as well as for protection of
external equipment connected to the substation.
2.3.4 Unless otherwise specified, combined control/protection IEDs with the control IED function and protection IED function (for each item of
switchgear to be controlled) may be combined into one unit. Combined
control/protection IEDs are to be used at the medium voltage levels only
(34.5 kV and below).
2.3.5 Redundant Managed hardened Ethernet switches providing managed Ethernet Local Area Networks communications infrastructure.
2.3.6 Supporting Power Supply equipment such as inverters UPS, etc.
2.3.7 Peripheral equipment like printers, display units, key boards, Mouse, KVM switches, etc.
2.3.8 Station Human Machine Interface (Station HMI)/ Station with process database. The Station HMI shall contain as minimum: fully redundant two (2)
Front End/ Station Computers, fully redundant two (2) Operator's
Workstation, fully redundant one (1) Engineering Workstation, and related
applications software, operating systems and firmware to support full Station
HMI operation.
2.3.9 Separate Redundant Communications Gateway for remote supervisory control via SCADA Master Station(s) and for interconnecting external SOE
Master Stations. One side of each Communications Gateway shall face the
internal SAS Inter-bay bus using IEC 61850 and the other side of each
Communications Gateway shall face the external SCADA and SOE Master
Stations which will communicate using IEC 60870-5-101, IEC 608705-104
protocols, and support IEC 61850 communication with SCADA master
stations for future use.
2.3.9 Redundant GPS Receivers (e.g. Master Clock).
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 6 OF 119 Date of Approval: February 26, 2013
2.3.10 Redundant standalone Firewalls to provide one of the means for cyber
security for the SAS.
2.3.11 Quantities of VF Modems to support the IEC-101 interconnections between
the SCADA Master Stations and the redundant Communications Gateways.
2.3.12 Collection of the relevant data concerning the substation and distribution of
the data where needed.
2.3.13 Data exchange between the different system components via the inter-bay
bus (for data exchange between bay level IEDs) and other communications
buses (such as station bus for interconnecting the station level subsystems:
Operators Workstations, Engineering Workstation, Front End Computers,
and Printers etc).
2.3.14 Bay-oriented local control panels with mimic diagram. One of the functions
of the Bay-Oriented local control panels with mimic diagram is to provide
emergency local operation of related Bay switchgear in the event of failure
and/or disabling of the Bay Control IED(s).
2.3.15 Local Control Cubicles (LCCs) for all High Voltage (above the medium voltage (34.5 kV and below) level) switchgear which will be installed in the
related High Voltage GIS Switchgear Rooms which will house/contain the
Control IEDs, Bay-oriented local control panels with Mimic Diagram and required Annunciator Panels.
2.3.16 For the Medium Voltage level (34.5 kV voltage and below), unless otherwise specified differently in other sections/appendices of the main PTS,
combined Control/Protection IEDs which are to be mounted/installed in the Low Voltage Compartments of the Metal Clad Medium Voltage Switchgear
as specified in latest revision of 32-TMSS-01 (for Metal Clad Switchgear)
and as specified in latest revision of 32-TMSS-03,( Metal Clad GIS
Switchgear), and with these IEDs fully integrated into this Metal Clad Switchgear by the SAS Solution provider /Sub Solution provider .
2.3.17 SAS Cubicles/Panels which will contain SAS equipment which includes, computers, Ethernet switches, firewalls/routers, VF modems, maintenance
displays, common alarm panels and related annunciators, terminal blocks,
MCBs, internal cabling/wiring, etc.
2.3.18 Protection Cubicles/Panels which will contain Protection IEDs. terminal
blocks, physical switches, MCBs, auxiliary relays, internal cabling/wiring,
etc.
2.3.19 All cabling/wiring/terminations required to provide for a fully functional
SAS installation to be provided/installed by the SAS Solution provider and
interconnected between SAS equipment as well as any SAS equipment and
external Communications/WAN/LAN equipment. The only exception to this
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 7 OF 119 Date of Approval: February 26, 2013
cabling/wiring requirement will be the cabling/wiring between the Control
IEDs and external switchgear, the Protection IEDs and external switchgear, and thecombined Control/Protection IEDs and the external switchgear which can be run and terminated at the switchgear end by the Substation Solution
Provider . (however for the IED to switchgear cable connections at the IED
end and this cable termination shall be performed by the SAS Solution
provider).
2.3.20 Other devices, equipment and software (not mentioned above) which will
provide for a fully integrated and operational SAS at the substation.
2.4 Definition of Terms
2.4.1 HMI Human Machine Interface: Display screen, either part of an IED or as a
stand-alone device, presenting relevant data in a logical format, with which
the user interacts. An HMI will typically present windows, icons, menus,
pointers, and may include a keypad to enable user access and interaction.
2.4.2 IED Intelligent Electronic Device: Any device incorporating one or more
processors, with the capability to receive or send, data/control from, or to an
external source, for example electronic multifunction meters, digital relays,
controllers. Device capable of executing the behavior of one, or more,
specified logical nodes in a particular context and delimited by its interfaces.
Also see definitions relating to Protection IED, and Control IED.
2.4.3 Bay
A substation consists of closely connected sub parts with some common
functionality. Examples are the switchgear between an incoming or outgoing
line, and the bus bar, the bus coupler with its circuit breaker and related
isolators and earthing switches, the transformer with its related switchgear
between the two bus bars representing the two voltage levels. The bay
concept may be applied to 1 1/2 breaker and double bus substation
arrangements by grouping the primary circuit breakers and associated
equipment into a virtual bay. These bays comprise a power system subset to
be protected, for example a transformer of a line end, and the control of its
switchgear that has some common restrictions such as mutual interlocking or
well-defined operation sequences. The identification of such subparts is
important for maintenance purposes (what parts may be switched off at the
same time with minimum impact on the rest of the substation) or for
extension plans (what has to be added if a new line is to be linked in). These
subparts are called 'bay' and may be managed by devices with the generic
name 'bay controller' and have protection systems called 'bay protection'. The
bay level represents an additional control level below the overall station
level.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 8 OF 119 Date of Approval: February 26, 2013
2.4.4 Bay Level Functions
Functions that use mainly the data of one bay and act mainly on the primary
equipment of that bay. Bay level functions communicate via logical interface
3 within the bay level and via logical interfaces 4 and 5 to the process level,
i.e. with any kind of remote input/output or with intelligent sensors and
actuators. Control and data acquisition functions related to the bay level
functions may be performed at the bay level Control IED(s)/Local
HMI(s)/Bay-oriented Local Control Panel with Mimic Diagram, or indirectly
through the station HMI interface or the SCADA Master Station(s).
Protection functions related to the bay level functions are performed through
the bay level Protection IED(s) dedicated specifically for protective relaying
function(s).
2.4.5 Station Level Functions Functions applying to the whole substation. There are two classes of station
level functions i.e. process related station level functions and interface related
station level functions. Control and data acquisition functions which are
related to the station level functions for each substation indicated in Section
2.1 and which may include control and data acquisition from the local HMI,
Station HMI, and with the SCADA Master Station(s) providing external
(outside the substation) control and data acquisition capabilities.
2.4.6 Process:
The scheme which contains the actual conventional switchgear which
includes Breakers, Disconnect Switches, Tap Changers, Instrument
transformers and all instrumentation like Gas Density Monitors, etc.
2.4.7 Process Level Functions
All functions interfacing to the process, i.e. binary and analogue input/output
functions for example data acquisition (including sampling) and the issuing
of commands. These functions communicate via the logical interfaces 4 and 5
to the bay level.
2.4.8 Process Related Station Level functions Use data from more than one bay, or from each whole substation and act on
the primary equipment of more than one bay, or on the primary equipment of
each whole substation. Examples of such functions are: station wide
interlocking, automatic sequencers, and bus bar protection. These functions
communicate mainly via logical node 8.
2.4.9 Station HMI The set of computers/workstations and other equipment inside each
substation where control, data acquisition, monitoring, configuration of SAS
equipment and other SAS functions on a station level takes place.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 9 OF 119 Date of Approval: February 26, 2013
2.4.10 Front End Computers/Station Computers The set of computers where data gets directly transferred between the IEDs
(for recording/data acquisition and control functionality), and where
interfaces are provided for the Operator's and Engineering Workstations.
2.4.11 Local HMI
The set of equipment inside each substation where control, data acquisition,
alarms, configuration of SAS equipment, and other SAS functions on a bay
level takes place.
2.4.12 Operator Workstation
The computer (s),which are contained as part of the Station HMI and where
substation control/data acquisition, alarms/events/trends/disturbance records
recording/retrieval and other SAS equipment manufacturers recommended
functions are displayed and takes place. It is noted that the Operator's
Workstations and Engineering Workstation shall be dedicated separate
computers with separate dedicated displays, keyboards, and mice.
2.4.13 Engineering Workstation The computer (s) where equipment configurations supported and other SAS
equipment manufacturers functions related to SAS Engineering is allowed to take place. It is noted that the Operator's Workstation and Engineering
Workstation shall be dedicated separate computers with separate dedicated
displays, keyboards, and mice.
2.4.14 Control IED An intelligent electronic device that provides for control functions on a bay
level. Depending on the equipment manufacturer's design, data acquisition
functions may also be provided as part of the Control IED. Also, depending
on the equipment manufacturer's design, a Local HMI may be integrated as
part of the Control IED, or the Control IED may be separate from the Local
HMI. As part of the design of the Control IED, there shall be a requirement
for IEC 61850 compatibility. For the purposes of this standard, Control IEDs
shall be physically separate devices from Protection IEDs, with dedicated
Control IEDs being installed for all voltage levels above the Medium Voltage level, and where related Appendix of the main PTS specifies
dedicated Control IEDs at the Medium Voltage Level.
2.4.15 Protection IED An intelligent electronic device that provides for protective relay functions,
primarily on a bay level. Depending on the equipment manufacturer's design,
the Protection IED may provide for a single protective relay function, or
multiple protective relay functions in the same Protection IED unit. Also,
depending on the equipment manufacturer's design, additional
features/functions of the Protection IED may include status recording
functions (such as fault recording and other status recording functions), data
acquisition and other features. Also, Protection IED's shall be considered as
Protective Relays which are integrated in the SAS and with IEC 61850
connectivity/functionality. For the purposes of this standard, Protection IEDs
shall be physically separate devices from Control IEDs, with dedicated
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 10 OF 119 Date of Approval: February 26, 2013
Protection IEDs being installed for all voltage levels above the Medium Voltage level, and where related Appendix of the main PTS to this standard
specifies dedicated Protection IEDs at the Medium Voltage Level.
2.4.16 Combined Control/Protection IED
An intelligent electronic device that provides for combined control and
protection functions on a bay level. Depending on the equipment
manufacturer's design, data acquisition functions may also be provided as
part of the Combined Control/Protection IED. Also, depending on the
equipment manufacturer's design, the combined Control/Protection IED may
provide for a single protective relay function, or multiple protective relay
functions in the same combined Control/Protection IED unit. Also,
depending on the equipment manufacturer's design, additional
features/functions of the combined Control/Protection IED may include
status recording functions (such as fault recording and other status recording
functions), and other features. Also, combined Control/Protection IED's shall
be considered as Protective Relays which are integrated in the SAS and with
IEC 61850 connectivity/functionality Also, depending on the equipment
manufacturer's design, a Local HMI may be integrated as part of the
combined Control/Protection IED, or the combined Control/Protection IED
may be separate from the Local HMI. For the purposes of this Standard,
combined Control/Protection IEDs shall be provided for all Medium Voltage (34.5 kV and below) applications, unless separate dedicated Control IEDs, and separate dedicated Protection IEDs are specified for some or all of the Medium Voltage applications in the main PTS.
2.4.17 Station Bus
The medium through which communications takes place among the station
level subsystems such as Operators Workstation, Engineering Workstation, Front End Computers, Printers etc. Station bus shall be fully compliant with
IEC 62439-3 (PRP1).
2.4.18 Inter-Bay Bus:
The medium through which communications takes place between the bay-
level IEDs and the station HMI interface and which protection, control and
data acquisition/monitoring signals for the SAS pass through. The Inter-Bay
Bus shall be fully compliant with IEC 61850 for all voltage levels of the
substation, and also will be fully compliant with IEC-62439-3 PRP1 for all
voltage levels of the substation.
2.4.19 Bay-oriented Local Control Panel with Mimic Diagram
A panel, which is installed on a bay level which provides for local indication
of switchgear status, limited alarm indication, other sets of limited readings,
and local switchgear control (on an emergency basis upon failure of a Control
IED and/or local HMI.
2.4.20 Time Synchronization System: A redundant set of GPS receivers which
provide for time synchronization data to all equipment contained as part of
the SAS within each substation.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 11 OF 119 Date of Approval: February 26, 2013
2.4.21 Communications Gateway
A set of redundant equipment which will provide for communications
interfacing between the SAS and equipment outside of each substation, and
which will also provide for required protocol conversions as needed for the
SAS to communicate with Master Station equipment outside each substation.
2.4.22 SCADA Master Station(s) The station(s) (outside of each substation) where remote control and remote
data acquisition functions are performed for each substation. For purposes of
the SAS, interfacing between the station SAS and the SCADA Master
Station(s) will be through the Communications Gateways.
2.4.23 SOE Master Station The station (outside of each substation) where SOE (Sequence of Events)
information which eventually gets routed to. For purposes of the SAS,
interfacing between the station SAS and the SOE Master Station will be
through Communications Gateways.
2.4.24 PTS Project Technical Specification, which is the same as the Scope of Work and
Technical Specifications (SOW/TS).
Additional Definitions Relating to IEC 61850
For additional definitions relating to IEC 61850, refer to the latest revision of IEC
TS 61850-2.
3.0 SYSTEM DESIGN
3.1 General System Design
3.1.1 The Substation Automation System (SAS) shall be suitable for operation,
monitoring, and maintenance of each complete substation including future
extensions which are identified in this entire standard document. The offered
products shall be suitable for efficient and reliable operation under the
environmental conditions specified in Section 14.
3.1.1 The systems shall be: State-of-the art based on IEC61850 for operation under electrical conditions present in high-voltage substations, follow the latest
engineering practice & ensure long term compatibility requirements,
continuity of equipment supply and the safety of the operating staff.
3.1.2 The offered SAS shall support remote control and monitoring from remote SCADA Master Stations via Communications Gateways.
3.1.3 The offered SAS shall provide for SOE (Sequence of Events) points support and overall SOE functions, with SOE monitoring information forwarded to
both the Station HMI and the external SOE Master Station (which is located
outside of the substation) through the Communications Gateways.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 12 OF 119 Date of Approval: February 26, 2013
3.1.4 The offered SAS shall provide for Protective Relay functions, (through bay-level Protection IEDs) for each substation.
3.1.5 The offered SAS shall provide for the substations interlocking functions, both through hard-wired interlocks in the substation as well as a system of
software/GOOSE interlocks.
3.1.6 The offered SAS shall provide for other miscellaneous functions related to substation control, data acquisition, protection and other functions as
described elsewhere in this Standard and the related Main PTS and other
Appendices to the Main PTS.
3.1.7 The system shall be designed such that personnel with little background knowledge in microprocessor-based technology are able to operate the
system easily after having received some basic training.
Installation/Maintenance/Operating Manuals/ documentation describing the
features and functions of the system shall be provided. Necessary 'HELP'
files shall be built into the HMI and database software. Also, the Operator
Interface (through the Engineering Workstation and Operator's Workstation)
shall be intuitive such that operating personnel shall be able to operate the
system easily after having received basic training on the SAS.
3.1.8 Cubicles shall incorporate the control, monitoring and protection functions specified, self-monitoring, signaling and testing facilities, measuring as well
as memory functions, event recording and disturbance recording. The basic
control functions are to be derived from a modular standardized and type-
tested software library.
3.1.9 Maintenance, modification or extension of components may not cause a shut-down of the whole SAS. Self-monitoring of single components, modules and
communication shall be incorporated to increase the availability and the
reliability of the equipment and minimize maintenance. In the cases of
modification or extension of components, if a shutdown of the SAS is
required, features, functions and configurations shall be provided to keep the
shutdown time of all or part of the SAS to an absolute minimum.
3.1.10 Preference will be given to suppliers who are in a position to provide protection and control devices and other devices freely adaptable to the
required application functionality.
3.1.11 The SAS shall be expandable as and when required at the Bay, Station and Process levels.
3.1.12 As part of the general system design of the SAS, alarm features shall be included which shall forward alarms to the SCADA Master Station(s) (as
well as the SAS Central Alarm Unit and/or substation Annunciator system
which will be included as part of the SAS) if the SAS determines that any
component of the SAS is not operating properly (with such components
including the station HMI, local HMI, IEDs, Communications Gateways,
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 13 OF 119 Date of Approval: February 26, 2013
inter-bay bus, Ethernet switches, GPS receivers and other components of the SAS). For further details refer to Section 14.26 as well as latest revision of
TES-P-119.27 for SCADA points list and 38-TMSS-05 for Alarms list. It
should be noted that these are minimum requirements and the complete lists
to be provided by the SOLUTION PROVIDER which will be subject to
review and acceptance.
3.1.13 Generally, part or all of the SAS will be installed inside the substation building, which will be air conditioned. However in some cases, where
outdoor switchyards are used (refer main PTS) all bay-level unit hardware
(such as Bay Control IEDs and Bay Oriented Local Control Panels with
Mimic Operation) which need to be co-located with the outdoor switchgear
shall be designed and constructed to meet and fully operate without failure in
the outdoor environmental conditions in Saudi Arabia at the substation's
location. Refer to latest revision of standard 01-TMSS-01 (Outdoor
Environmental Conditions) for further details. However in the case of SAS
equipment located inside the substation building, the SAS equipment shall be
operational during both normal indoor conditions, and emergency indoor
conditions for a minimum 12 hour period where there is no heating/air
conditioning inside the substation building (for this matter, refer section 14.
of this standard for further detail on these requirements).
3.2 System Architecture
3.2.1 For safety and availability reasons the Substation Automation System shall be based on a decentralized architecture and on a concept of bay-oriented
distributed intelligence.
3.2.2 Functions shall be decentralized, object-oriented and located as close as possible to the process.
3.2.3 The main process information of the station shall be stored in distributed databases.
3.2.4 The proposed SAS layout shall be structured in three levels, i.e. a Station, a Bay and a Process level.
3.2.5 The Station level shall provide all the station level functions related to monitoring, control and protection. It shall consist of the station level
subsystems such as operators workstations, engineering workstation, front end computers, printers, etc. interconnected via the Station Bus. At bay level
the IEDs shall provide all bay level functions regarding control, monitoring
and protection, inputs for status indication and outputs for commands. The
inter-bay bus shall provide the interconnection between the bay level IEDs
and other bay level IEDs, the bay level IEDs and SAS front end computers/Communications Gateways, and between SAS front end
computers and SAS Communications Gateways. The IEDs should be directly
connected to the switchgear without any need for additional interposition or
transducers. It shall be the responsibility of the SAS
Manufacturer/SOLUTION PROVIDER to determine the proper layout for
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 14 OF 119 Date of Approval: February 26, 2013
the SAS and the independent from each other and its functioning shall not be
affected by any fault occurring in any of the other bay control units of the
station. The only exception to this section will be for GOOSE interlocks,
where GOOSE interlocking information from one bay control unit to other
bay control units and in the event of the failure of the bay control unit
(Control IED) GOOSE interlocks may not be functional.
3.2.6 The communication buses shall be realized using fiber-optic cables and substation hardened Ethernet switches thereby guaranteeing disturbance free
communication. To maximize the physical protection of the fiber optic cables,
the fiber optic cables shall be run in GI Conduit pipes or other means
acceptable to the National Grid Saudi Arabia.. Furthermore for the redundant
schemes using Fiber Optic cables, routing of Fiber Optics cables shall be such
that "collapsed ring" schemes and routing of the redundant schemes in the
same routing media shall be avoided.
3.2.7 The communication buses (both station communications bus and inter-bay communications bus) shall be designed in dual redundant fault-tolerant rings
at all voltage levels. For the links between individual bay IEDs to Ethernet
switches a "star" scheme shall be used. It shall be such that failure of one set
of fibers shall not affect the normal operation of the SAS. However failure of
any fibers shall be alarmed in SAS. Additionally, fiber optics cable
connection shall provide sufficient fibers for the actual connection plus 20%
of overall fibers provided (along with the required fiber optics
termination/connectors) to support ease of replacement in event of failures of
individual working fibers.
3.2.8 To increase system performance and availability the cable routing/communication buses requirement shall be as follows:
a. The inter-bay busses shall be independent and redundant at each voltage level.
b. Inter-bay buses shall be independent of each other for each voltage level, as shown in the conceptual diagram, Substation Automation System Diagram (Conceptual), Drawing Fig 07-01. The detailed requirements related to the required common interconnections at the different levels
shall be designed by the Manufacturer/Solution provider .
3.2.9 The Station bus shall be fully redundant. At station level, the entire station
shall be controlled and supervised from the station HMI. It shall be possible
to control and monitor the bay from the bay level equipment in the event that
the communication link fails. The station wide interlocking shall also be
available when the station computer, IED(s), communications link, or other
component of the SAS fails. To support station wide interlocking upon failure
of the station computer, IED(s), communications link, or other component,
there shall be hard wired interconnection both within a bay and between the
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 15 OF 119 Date of Approval: February 26, 2013
required bays for keeping the interlocking intact. For the substation's
interlocking requirements, manufacturer/SOLUTION PROVIDER shall meet
the latest revision requirements of 32-TMSS-01 for metal clad switchgear
(11kV, 13.8kV, 33kV or 34.5kV), 32-TMSS-02 for SF6 GIS (69kV through
380kV) and 32-TMSS-03 for metal clad gas insulated medium voltage
switchgear (11kV, 13.8kV, 33kV OR 34.5kV).
3.2.10 To provide highest reliability the station HMI and the Communications
Gateways shall work completely independent, i.e. the process data can be
retrieved directly from the bay level devices. Additionally the
Communications Gateway, Station HMI, communication buses (inter-bay bus
and station bus), GPS Receiver (which are part of the Time Synchronization
System) and Front End / Station Computer Unit, Firewalls and other related
hardware shall be built and configured fully redundant to ensure full
functionality and avoid single point of failure.
3.2.11 Clear control priorities shall prevent the initiation of operation of a single
switch at the same time from more than one of the available control levels, i.e.
SCADA Master Station(s), station level, bay level or apparatus level. To
ensure that clear control priorities exist, a hierarchy scheme between the
various control levels shall exist.
3.2.12 The priority shall always be on the lowest enabled control level. The station
level contains the station-oriented functions, which cannot be realized at bay
level, e.g. alarm list or event list related to the entire substation's SAS and
Communications Gateway required for the communication with remote
control centers.
3.2.13 Dedicated master clock (GPS Receivers which are part of the Time
Synchronization System) for the synchronization of the entire system shall be
provided. This master clock should be independent of all station computer
equipment and of the Communication Gateway and should synchronize all
devices via the communication buses
3.3 Ethernet Topology
The following described criterias have to be fulfilled concerning the Ethernet switches and the topology.
3.3.1 Ethernet Switches
a. The proposed Ethernet (LAN) Switches shall be modular, industrially hardened, fully manageable and specifically designed to build Ethernet
networks for mission critical, real-time control applications in utility
substation environments.
b. These hardened requirements include. (but may not be limited to) temperature, EMC and power supply (DC from the station battery) which
are suitable to be installed in the substation operating at the voltage
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 16 OF 119 Date of Approval: February 26, 2013
levels of the substation (indicated in Section 1 of this Standard, are
included in this specification.
c. The proposed LAN switches shall be equipped with dual DC (125 VDC)
power supplies.
d. The switches shall support priority tagging and open standards for ring
management.
e. External switches are required as they have the advantage that there is no interruption or reconfiguration of the Ethernet ring if one or several bay
devices are taken out of service.
f. Ethernet switches for inter-bay buses shall have 100Base-FX technology
(fiber optic-100MBPS) for inter connection of all IEDs (control,
protection and combined protection/control IEDs) with EHV/HV and
MV inter bay buses (PRP1- Bay LAN) and have Gigabit Ethernet
1000Mbps to connect Ethernet switches inside each ring EHV/HV and
MV inter-bay buses (PRP1-Bay LANs) and each ring of station buses
(PRP1-Station LANs) provided by SOLUTION PROVIDER. There shall
be consistency throughput for all inter-bay signals being provided from
the IEDs located throughout the substation and shall be consistent with
IEC 61850 requirements.
g. Security Features:
Should provide multilevel security/user passwords to prevent
unauthorized users from altering the switch configuration.
SNMPv3 encrypted authentication and access security
Support authentication/Centralized password management
(RADIUS)
IEEE 802.1q VLANs to segregate and secure network traffic
Port based Network access control (IEEE 802.1x)
Secure Shell (SSH)/Secure Sockets Layer (SSL) encryption.
h. Management Features:
Support enhanced traffic management, monitoring, and analysis,
through Embedded Remote Monitoring (RMON) software agent
supporting at least four RMON groups (history, statistics, alarms,
and events).
Telnet, CLI, LAN Switch Vendor GUI, and Web based
management interfaces.
Support for SNMP v3 interface to deliver comprehensive in-band
management.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 17 OF 119 Date of Approval: February 26, 2013
3.3.2 System Architecture
The system architecture shall be based on completely distributed approach
also concerning the connection of any device to the system. Meaning any
device protection as well as control and station level devices shall be directly
connected to the Ethernet backbone.
3.3.3 Redundant Networks
a. To ensure maximum performance and availability the network shall
b. For the inter-bay bus level of the SAS which contains the Ethernet
Switch connections for the Control IEDs, the Protection IEDs, the
SAS Front End Computers, and Communications Gateways, as a
minimum, redundant LAN configuration shall be provided by the
SOLUTION PROVIDER at all voltage levels, with separate redundant
networks provided for the IEDs at each voltage level.
c. The separate redundant networks at all voltage levels shall be
provided where the redundant inter-bay bus is interconnected with the
redundant station bus.
d. Refer to Section 14 of this Standard for further redundancy
implementation requirements which is to be implemented by the
SOLUTION PROVIDER .
e. The Bid proposal shall fully describe the proposed networks scheme.
This shall be supported by detailed network block/schematic
diagrams.
4.0 FUNCTIONAL REQUIREMENTS
4.1 General SAS Functionality
4.1.1 Control Scheme Hierarchy
a. A scheme with a predetermined hierarchy shall be provided for the
operation of the high-voltage apparatus. As such, the high voltage
apparatus within the station shall be operated from different places
(from the lowest level to the highest level):
Bay-oriented Local Control Panel with Mimic Diagram (Mimic)
Control IED
Combined Control/Protection IED
Station HMI
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 18 OF 119 Date of Approval: February 26, 2013
Power Control Center (PCC/SCADA Master Station/LDC):
b. In the scheme shown above, operation of a specific piece of high
voltage apparatus shall be allowed to be performed by only one
operation at a time. To insure this, double operation interlocking shall
be employed. Double operation interlocking shall be employed as part
of the hard-wired interlocking scheme, as well as the
Software/GOOSE interlocking scheme resident in the Control IEDs and the combined Control/Protection IEDs.
4.1.2 Control Scheme-Select-before Operate
For safety and security reasons the command execution is always to be given
in two stages, with the first stage being the selection of the object that is to
be controlled, and the second stage being the operation (execution) of the
object being selected. This select before operate scheme shall be applicable
for the Control IED level, the combined Control/Protection IED level, and
the Station HMI level Also, depending on the SAS Equipment
Manufacturers design, and National Grid Saudi Arabia requirements/standards, either a direct select before operate scheme, a direct operate scheme, or a modified two handed select-before-operate scheme may be applicable for emergency operation through the Bay
Oriented Local Control Panels with Mimic.
4.1.3 Self Supervision
The entire SAS shall be designed with continuous self-supervision features
of the entire SAS installation, with self-diagnostic features for the SAS to
specifically pinpoint trouble/mal-operation areas of the SAS. Generally, the
self-diagnostic features will be built into the Station HMI, with displays
available for these diagnostics on the Operator's Workstation and/or
Engineering Workstation.
4.1.4 User Configuration
a. The monitoring, controlling and configuration of all input and output
logical signals and binary inputs and relay outputs for all built-in
functions and signals shall be possible both locally and remotely.
b. It shall also be possible to interconnect the built-in functions using
additional logics (AND-gates, OR-gates and timers) as well as to
configure additional functions such as over-current, over-voltage,
etc.(multi-activation of these additional functions should be possible).
4.1.5 Division of Functional Requirements
a. The functional requirements shall be divided into two areas which are
shown in the two paragraphs below.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 19 OF 119 Date of Approval: February 26, 2013
b. The Bay level functions shall comprise of operations within one bay
only, with the bay comprising of one circuit breaker, associated
disconnectors (isolation switches), earthing (grounding switches) and
associated instrument transformers (PTs and CTs).
c. System Level functions which look at the SAS and the substation as a
whole.
4.1.6 Direct Connection between PTs/CTs to SAS IEDs for Analog inputs
Analogue inputs for voltage transformers (PTs/VTs) and current
transformers (CTs) measurements shall be connected directly to the voltage
transformers (PTs/VTs) and the current transformers (CTs) without
intermediate transducers. The values of active power (W), reactive power
(VAR), frequency (Hz), and the rms values for voltage (U) and current (I)
shall be calculated on the Control IEDs, combined Control/Protection IEDs
and Protection IEDs. All readings on all SAS equipment shall be direct on all
displays, taking into account the scaling factors for each device (CTs and
PT/VTs).
4.2 Bay Level Functions
4.2.1 In a decentralized architecture the functionality shall be as close to the process as possible.
4.2.2 In this respect, the following functions shall be allocated at bay level:
a. Bay control functions including data acquisition/data collection
functionality in Bay Control IED's .and combined Control/Protection
IEDs
b. Bay protection functions including data acquisition/data collection
functionality in Bay Protection IED's. and combined
Control/Protection IEDs
c. Data collection functionality.
4.2.3 Bay control functions
a. Overview
Basic functions
Control mode selection(Local/Off/Emergency/Remote)
Select-before-execute principle
Command supervision: o Interlocking and blocking
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 20 OF 119 Date of Approval: February 26, 2013
o Double command
Autoreclosing (may be considered as either a control function or protection function, depending on National Grid Saudi
Arabia requirements)
Synchrocheck, voltage selection (may be considered as either a control function or protection function, depending on
National Grid Saudi Arabia requirements)
Interruption of drive latching in case runtime is exceeded
Monitoring pole discrepancy and trip function, if applicable
Transformer tap changer control raise/lower (for power transformer bays)
Operation counters for circuit breakers and pumps, if applicable
Hydraulic pump control and runtime supervision, if applicable
Pump start cascading, if applicable
Anti pumping of circuit breaker (open/close)
Operating pressure supervision through digital contacts only
Display of interlocking and blocking
Breaker position indication on a three phase basis with indication showing pole discrepancy conditions/alarms where
pole discrepancy between the phases is detected/indicated
Alarm annunciation
Measurement display
Local HMI (local guided, emergency mode)
Interface to the station level
Data storage for at least 200 events
Run Time Command cancellation
Extension possibilities with additional I/O's inside the unit, installation of additional units and/or via fiber optic
communication and process bus
Additional functions, if any, specified in Main PTS/SCADA & Protection Appendices.
Advanced functions
Disturbance recording with capabilities for all analogue and binary values
Extension possibilities with additional I/O's inside the unit or via fiber-optic inter-bay communications and process bus
b. Control Mode Selection
As soon as the operator receives the operation access at bay level the operation is normally performed via the local HMI.
During normal operation the local HMI is guided and allows
the safe operation of all switching devices via the bay control
IED or the combined control/protection IED.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 21 OF 119 Date of Approval: February 26, 2013
It will be ensured that Protection features for the station (through the Protection IED's or the combined
control/protection IED used for the station protection function)
shall be functioning irrespective of the Control Mode.
In the event that the bay control IED or a combined control/protection IED fails, the operator shall have access to
the essential bay switchgear via a separate bay-oriented local
control panel with mimic diagram for High Voltage
switchgear, or via the Low Voltage Compartment for Medium
Voltage switchgear. This is an emergency function.
i. OFF Mode
It is not possible to operate any object, neither locally
nor remotely.
ii EMERGENCY Mode
A. The position indication shall be directly from
the primary equipment bay switchgear being
controlled.
B. On the bay-oriented local control panel with
mimic diagram, for the two handed operate principle, the device selection push button and
either the ON or OFF push button has to be
pushed simultaneously in order to close or open
the primary equipment bay switchgear. For the
single handed operate principle, as indicated in latest revision of 32-TMSS-02 each device
will have its own OFF or ON push button to press, and the operator will not be required to
use two hands to operate a device. Control
operation from other places (e.g. from
REMOTE or LOCAL) shall not be possible in
this operating mode.
iii. LOCAL (BCU) Mode
A. On the HMI the object has first to be selected.
In case of a blocking or interlocking conditions
the selection will not be possible and an
appropriate alarm annunciation shall occur.
B. If a selection is valid the position indication will
show the possible direction and the appropriate
ON or OFF button shall be pressed in order to
close or open the corresponding object.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 22 OF 119 Date of Approval: February 26, 2013
C. Control operation from other places (e.g.
REMOTE) shall not be possible in this
operating mode.
iv. REMOTE-STATION LEVEL mode
Control authority in this mode is given to the next
highest level (the Station HMI level) and the
installation can be controlled only remotely via the
Station HMI. Control operation from lower levels shall
not be possible in this operating mode.
v. REMOTE-PCC LEVEL mode
Control authority in this mode is given to the highest
level (SCADA Master Station) via the Station HMI and
the installation can be controlled only remotely via the
PCC (SCADA Master Station/LDC). Control operation
from lower levels shall not be possible in this operating
mode. National Grid Saudi Arabia notes that control
from this mode shall also be available in the event of
failure of even the (redundant) Station HMI Front End
computers, in which PCC Control and Data Acquisition
information will be transmitted and received directly
from the Communications Gateways to the applicable
Control IEDs and combined Control/Protection IEDs through the IEC 61850 Inter-bay bus.
c. Command supervision
Bay/station interlocking and blocking
i. Interlocking facilities have to be installed in the
switchgear to prevent damages and accidents in case of
false operation.
ii. Within the bay itself, a system of hard-wired interlocks and software/GOOSE interlocking controlled only
through the Bay Control IEDs (in conjunction with the
Bay Oriented Local Control Panel with Mimic) shall be
used. However, upon failure of a bay Control IED(s)
and/or combined Control/Protection IED(s) or
communications link(s), the hard-wired interlocking
shall operate and prevail. The SOLUTION PROVIDER
's proposed solution shall describe the bay interlocking
scenario in event of switching off or failure of a bay
Control SAS component(s) (Control IED(s) or
combined Control/Protection IED(s)),or other SAS
components.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 23 OF 119 Date of Approval: February 26, 2013
iii. Station interlocking systems shall be provided via hardwired or inter-bay bus. However, upon failure of
station computer, IED(s), communications link (inter-
bay bus), or other component of the SAS, the
hardwired station interlock shall operate and prevail. It
shall be a simple layout, easy to test and simple to
handle when upgrading the station with future bays.
The SOLUTION PROVIDER's proposed solution shall
describe the station interlocking scenario in event of
switching off or failure of a bay Control SAS
component(s) (Control IED(s) or combined
Control/Protection IED(s)),or other SAS components.
iv. Software/GOOSE "interlock override" functionality
shall be available as part of the SAS. However, there
shall be methods available to disable such a
software/GOOSE bay/station "interlock override scheme and/or to allow only access to this
software/GOOSE "interlock override" scheme by
privileged users using strong passwords and other
security features.
Double operation interlocking
i. Double operation interlocking prevents the operation of
two or more switches at the same time. The double
operation interlocking is a part of the station
interlocking; it shall preferably be hard-wired, but
provisions shall also be made in the SAS design for
software (GOOSE) double operation interlocking. It
shall be included for all the switches in the station. It
should be noted that unless interlocked for some
specific purpose (other than for Double Operation
Interlocking), there is no need of preventing
simultaneous operation of switches located in different
bays.
ii. With a hard-wired solution the interlocking is independent from the control authority of the station. If
a control IED and/or a combined Control/Protection
IED fails, the double operation interlocking does not
block the operation of the station. It shall still be
controlled from all the control authorities. Refer to
above Section i (under double operation interlocking) of
this Standard for further details pertaining to the overall
requirements for Double Operation Interlocking.
iii. The proposed solution shall describe the double
operation interlocking scenario while an IED of
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 24 OF 119 Date of Approval: February 26, 2013
another bay or another component of the SAS is
switched off or fails.
Other General Interlocking requirements
i. For software/GOOSE interlocks, schemes which use
the Station HMI (or other Front End) Computer
equipment to make ANY software/GOOSE
interlocking decisions or transfer software/GOOSE
interlocking data shall NOT be used..
Software/GOOSE interlocking scheme shall ONLY
utilize the Bay Control IED equipment, the combined
Control/Protection IED equipment, and
intercommunications (through GOOSE messages)
between Control IEDs and combined
Control/Protection IEDs to support software/GOOSE
interlocking requirements.
ii. For the backup hard wired interlocking scheme/solution, Solution provider shall consult with
National Grid Saudi Arabia during the Base Design
stage of the project to determine if there is a need to
incorporate hard-wired interlock bypass/override in the related SAS design.
iii. For interlocking signals which are required between voltage levels in each substation which will be used for
software/GOOSE interlocking, these interlocking
signals described in this paragraph shall be transmitted
and received between voltage levels in hardwired form
and inputted/outputted to the other voltage levels
through GGIOs/Digital Inputs/Digital Outputs between
the related Control IEDs. This is required to guarantee
that separate dedicated IP Subnets can be allocated for
each voltage level in each substation.
iv. For the relation between software/GOOSE and backup hard wired interlocks, a series downstream principle will be used. This series downstream principle will first check the conditions of the
software/GOOSE interlocks and if the interlocking
conditions are satisfied at the software/GOOSE level at
the control or combined control/protection IED, then
the control signal will then pass to the hard wired interlocks, and if it is determined at the hard wired interlocking level that the interlocking conditions are
satisfied, the control signal will then pass to the related
switchgear device.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 25 OF 119 Date of Approval: February 26, 2013
v. Finally, the hard wired interlock scheme shall be configured in such a way that, once the National Grid
Saudi Arabia obtains enough satisfactory operating
experience with the software/GOOSE interlocking
scheme, then National Grid Saudi Arabia personnel can
later easily disable the hard wired interlock scheme and later only rely on software/GOOSE interlocking for
the bay/station interlocking functionality.
Synchronism and energizing check
i. The synchronism and energizing check functions shall
be bay-oriented and distributed to the bay control
and/or protection devices. These features are:
A. Adjustable voltage, phase angle and frequency difference.
B. Energizing for dead line-live bus, live line-dead bus or dead line-dead bus with no synchro-check
function.
C. Synchro-check between live line and live bus with synchro-check function.
D. Settings for manual close command and autoreclose command shall be adaptable and adjustable for the
operating times of the specific switchgear.
E. Determination of a live line/dead line or a live bus/dead bus shall be provided automatically at the
IED level for the particular bays where the IED's
are installed by looking at the configuration of
related circuit breakers, disconnects (isolators) and
earthing (grounding) switches.
F. Furthermore, use of "sampled value" messages from adjacent IED's to transmit analog information
from PTs (VTs) (either line or bus PTs (VTs)) shall
NOT be accepted for performing synchro-check
inside an IED.
G. Depending on National Grid Saudi Arabia requirements as stated in the related Appendix of
the main PTS, synchronism and energizing check
may be required to be performed by dedicated
Synchrocheck Relays/IEDs and NOT Control or combined Control/Protection IEDs
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 26 OF 119 Date of Approval: February 26, 2013
ii. Voltage selection
A. The voltages relevant for the synchro-check functions are dependent on the station topology, i.e.
on the positions of the circuit breakers and/or the
isolators.
B. The correct voltage for synchronizing and energizing is derived from the auxiliary switches of
the circuit breakers, the isolator, and earthing
switch and related PTs and shall be selected
automatically by the Bay Control IEDs and/or
Protection IEDs. The correct voltage selection shall
also be dependent on the bay/station one-line
scheme (e.g. double bus bar-single breaker, breaker
and one-half, double bus, etc.) for each substation
to be equipped with SAS.
C. Voltage selection (which is required for synchronism and energizing check as described
Section i under Synchronism and energizing check)
shall be an integral function of the IED or
Synchrocheck Relay, and NOT through external
means.
D. Depending on National Grid Saudi Arabia requirements as stated in related Appendix of the
main PTS, voltage selection may be required to be
performed by dedicated Synchrocheck
Relays/IEDs and NOT Control IEDS or combined Control/Protection IEDs
Auto-reclosing and related synchro-check functions
i. These functions can be considered as either control or
protection functions.
ii. Depending on the National Grid Saudi Arabia
requirements as indicated in related Appendix of the
main PTS, autoreclosing and synchro-check (related to
auto-reclosing) may be implemented in a general
Control IED or combined Control/Protection IED (used
for general substation switchgear control) or a
dedicated Autoreclosing functional unit (Control IED
or combined Control/Protection IED or
Autoreclosing/related Synchro-Check built into a
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 27 OF 119 Date of Approval: February 26, 2013
Protection IED) integrated into the Protection portion
of the SAS.
iv. The autorecloser should be settable for the following modes of operation:
A. First autoreclosure sequence:
Three-phase autoreclosure Single/three-phase autoreclosure Single-phase autoreclosure
B. Further auto-reclosure sequences:
No further auto-reclosure sequences Further auto-reclosure sequences (totally 2, 3 or
4 sequences), always three-phase sequences
iv. It shall be possible to perform all three-phase
autoreclosure sequences with or without synchro-
check.
v. If synchro-check is required for any autoreclosure
sequence, refer the sub heading Synchronism and energizing check above and its subsections for a description of the synchro-check, and voltage selection
functionality
Run Time Command cancellation
If the control action is not completed within a specified time,
the command shall get cancelled, and an alarm/event shall be
raised at the Station HMI level (which may be reported to the
PCC (SCADA Master Station level). For operation of
switchgear which involves drive latching the latching shall be
interrupted by the Control IED or combined Control/Protection
IED and the drive motor power (for the latched device) shall
be interrupted also by the Control IED or the combined
Control/Protection IED. National Grid Saudi Arabia requires
that the Run-Time Command Cancellation functionality and
the Command cancellation execution timer be embedded in the
Control IEDs and combined Control/Protection IEDs either through the use of dedicated IEC 61850 Logical Nodes, or
general timer/logic gates which are incorporated in the IED
which can be configured by the user/manufacturer (by
software) through the IED configuration process.
Pole discrepancy monitoring/relaying (if applicable)
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 28 OF 119 Date of Approval: February 26, 2013
A Pole Discrepancy monitoring function, based on the
measurement of phase over-currents and current differences
between phases as well as on breaker pole status (which is
determined by reading the auxiliary contacts on each pole of
the breaker) has to be provided. Also, depending on the SAS
Equipment manufacturer's design, additional Pole Discrepancy
Relaying may be included in the SAS as an integrated
function. If the additional Pole Discrepancy Relaying is
provided as part of the SAS, the Pole Discrepancy Relaying
feature integrated into the SAS shall support Stage I and Stage
II Pole Discrepancy Relaying functions, as well as being able
to initiate Pole Discrepancy Trip signals to remote substations
via Protection Signaling equipment (PSE), and
Communications equipment (PSE and Communications
provided by other parts of the project, as applicable). Refer to
related Appendix of the main PTS to determine additional
information on whether Pole Discrepancy monitoring/relaying
will be through separate Pole Discrepancy Relays, or
integrated into the functionality of SAS (Note: If main PTS
specifies separate dedicated external Pole Discrepancy Relays,
there will still be a requirement to monitor Stage I and Stage II
Pole Discrepancy from the external Pole Discrepancy Relay(s)
through SAS as part of the alarm function of SAS.).
Transformer tap changer control
i. Voltage regulation for single transformers or parallel
transformers with on-load tap-changer shall either be
included in the numerical control unit for the power
transformer or located in a separate tap changer control
device which is associated with the power transformer.
ii In the event that a separate tap-changer control device
is selected, this shall be an integral part of the SAS like
any bay oriented Control IED or Protection IED.
iii. OLTC scheme shall be .accomplished by the Control
IED's and/or dedicated Tap Changer IEDs (which have IEC 61850 interfaces) which will be performing
the regulation and tap changing function.
iv. National Grid Saudi Arabia notes that a built-in
numerical control unit is preferred instead of a separate
tap changer unit. Also, the Transformer tap changer
control scheme shall meet latest revision of TES-P-
119.26 for control schemes for each Substation's
Equipment.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 29 OF 119 Date of Approval: February 26, 2013
d. Interface between Control IEDs and Maintenance Laptop Computer
and also between combined Control/Protection IEDs and Maintenance
Laptop Computer:
All IEDs used for the Control functions shall be provided with a serial,
Ethernet RJ45 and/or optical front connector for connection to a
Maintenance Laptop Computer.
e. Interface between the Control IEDs, the combined Control/Protection
IEDs and the inter-bay Bus pertaining to IEC 61850 and IEC 62439-3
PRP1:
For IEDs used for dedicated control, and/or combined
control/protection, each Control IED and combined Control/Protection
IED shall have full interfacing to the inter-bay communications bus
only through IEC 61850 and IEC 62439-3 PRP 1. Use of Protocol
Converters to convert from legacy protocols (e.g. DNP 3.0,
MODBUS, IEC-103, etc.) to IEC 61850/IEC 62439-3 PRP 1 will
NOT be accepted by the National Grid Saudi Arabia. REDBOX is not
acceptable for IEDs. For other equipment it is subjected to National
Grid Saudi Arabia review and acceptance. Refer enclosed drawing Fig
07.01 which shows where REDBOX is acceptable.
4.2.4 Bay protection functions
a. General
For all voltage levels except for the Medium Voltage level, the protection functions shall be independent of the control
functions (i.e. the Protection IED will NOT be performing
Control IED functions). For the Medium Voltage level, unless
specified in the main PTS, both control functions and
protection functions for a bay can be provided in one IED
(which will be known as a combined Control/Protection IED).
Refer to the related Appendix of the main PTS involving Relay
and Protection for further details on the functionalities
involved, as well as other details.
Furthermore, at the High Voltage level, for trip applications/trip commands, where there is a dedicated
Protection IED, the Protection IED shall perform the tripping
functions ONLY, and this tripping function shall NOT be
passed on to a Control IED (either through hard-wired means
and/or through use of GOOSE messages).
The protection functions are an integral part of the Substation Automation System.
All protection functions realized in the IEDs should be based on numerical technology.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 30 OF 119 Date of Approval: February 26, 2013
All IEDs shall be serial integrated for data sharing and meet the real-time communication requirements for automatic
functions. The data presentation and the configuration of the
various IEDs shall be compatible with the overall system
communication and data exchange requirements.
All IEDs used for the protection functions (Protection IEDs and the combined Control and Protection IEDs) shall also be
provided with a serial, Ethernet RJ 45 and/or optical front
connector for connection to a Maintenance Laptop Computer.
For IEDs used for dedicated protection and/or combined control/protection, each Protection IED and combined
Control/Protection IED shall have full interfacing to the inter-
bay communications bus only through IEC 61850 and IEC
62439-3 PRP 1. Use of Protocol Converters to convert from
legacy protocols (e.g. DNP 3.0, MODBUS, IEC-103, etc.) to
IEC 61850/IEC 62439-3 PRP 1 will NOT be accepted by the
National Grid Saudi Arabia. REDBOX is not acceptable for
IEDs. For other equipment it is subjected to National Grid
Saudi Arabia review and acceptance. Refer enclosed drawing
Fig 07-01 which shows where REDBOX is acceptable.
This Standard only describes general Protection Requirements, with more specific protection requirements outlined in related
portions of the main PTS/standards. Refer to the related
Appendix of the main PTS/standards for Protection (Protective
Relaying) functions for the IEDs.
b. Self-supervision
Continuous self-supervision function with self-diagnostic possibilities
shall be included.
c. Event and disturbance recording function
Each Protection IED and combined Control/Protection IED shall contain an event recorder capable of storing at least 256
time-tagged events. A Protection IED and combined
Control/Protection IED shall also provide the user, either
locally or remotely, with complete information on the last ten
disturbances.
A disturbance recorder with a minimum of 5 seconds recording time for at least 10 disturbances shall provide the user with
time-tagged disturbance records.
At least the analogue inputs as well as 16 binary signals must be recorded.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 31 OF 119 Date of Approval: February 26, 2013
The pre-fault and fault currents and voltages shall be recorded for each disturbance and be made available for further
evaluation purposes.
d. Local HMI
The local human machine interface (HMI) shall be front-mounted and based on a user-friendly, menu-structured
program, and performed with the use of a permanently
installed human machine interface unit, type-tested together
with the protection terminal.
In addition service values of current and voltages as well as active and reactive power (if voltage measurements included)
shall be available. Also the characteristic analogue values
related to the activated functions (e.g. impedance in case of
distance protection) should be available.
4.2.5 Line protection
a. General
The Protection IED and combined Control/Protection IED devices which incorporate numerical line protection shall be
selected for the protection of lines according to specific
network configurations and conditions. The scheme must
ensure reliable isolation for all kind of faults that might occur
on the specific line as per protection requirements stipulated in
Protective Relaying Appendix to the main PTS/Protective
Relay Standard.
Depending on the voltage level and complexity, the following line protection functions may be required:
b. Distance function
Distance function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS/Protective Relay Standard.
c. Differential function
Differential function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS/Protective Relay Standard.
d. Earth fault function
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 32 OF 119 Date of Approval: February 26, 2013
Earth fault function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS/Protective Relay Standard.
e. Fault location
Fault location function requirements shall be compatible to the relay
requirements indicated in Protective Relaying Appendix to the main
PTS.
f. Transformer protection
General
i. The transformer protection shall be suitable for the
protection of two- or three-winding transformers,
auto-transformers, reactors, and generator-transformer
block units, as per protection requirements stipulated
in Protective Relaying Appendix to the main PTS or
standard.
ii. The numerical transformer terminal shall be designed
to operate correctly over a wide frequency range and to
accommodate for system frequency variations and
block generator start-ups.
Current differential function
Refer to the Protective Relaying Appendix to the main PTS or
Protective Relay Standard for further details.
Other functions
Refer to the Protective Relaying Appendix to the main PTS or
Protective Relay Standard for further details.
Breaker failure protection
i. The breaker failure protection shall comprise two time
stages. The first stage shall be bay-oriented and shall
re-trip the local circuit breaker.
ii. The second stage shall be station-oriented, requiring
information from other bays, and shall trip the circuit
breakers in adjacent bays.
iii. Refer to the Protective Relaying Appendix to the main PTS or Protective Relay Standard for further details.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 33 OF 119 Date of Approval: February 26, 2013
4.3 System/Station level functions
4.3.1 Control
a. The different high-voltage switchgear and medium voltage switchgear
within the station shall be operated from different places:
from the remote control centers (SCADA Master Station(s))
from the station level
For High Voltage switchgear from the Control IED(s) in the LCC(s) (in the bays)
For High Voltage switchgear from the Bay-Oriented Local Control Panel(s) with Mimic Diagram
For Medium Voltage switchgear from the Control IED(s)/combined Control/Protection IED(s)
For Medium Voltage switchgear from the Low Voltage Compartment(s)
b. Operation shall only possible by one operator at a time.
c. The operation shall depend on the conditions of other functions, such
as interlocking, synchrocheck, etc. (see description in chapter Bay control functions).
4.3.2 Status supervision
a. The position of each switchgear, e.g. circuit breaker, isolator, earthing
switch, transformer tap changer etc., shall be supervised permanently.
Every detected change of position shall be immediately visible in the
single-line diagram on the station HMI screen, recorded in the event
list, and a hard copy printout shall be produced. Alarms shall be
initiated in the case of spontaneous position changes.
b. The switchgear positions shall be indicated by two auxiliary switches,
normally closed (NC) and normally open (NO), which shall give
relevant signals. An alarm shall be initiated if these position
indications are inconsistent or if the time required for operating
mechanism to change position exceeds a predefined limit.
c. The SAS shall also monitor the status of substation auxiliaries (which
will include, but not be limited to auxiliary relays such as trip current
supervision, DC supervision, etc.).. The status and control of
auxiliaries shall be done through separate one or more Control IEDs
and all alarm and analogue values shall be monitored and recorded
through the respective Control IEDs. It is noted also by the National
Grid Saudi Arabia that monitoring of the status of auxiliaries shall
NOT be performed from dedicated Protection IEDs or combined Control/Protection IEDs.
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 34 OF 119 Date of Approval: February 26, 2013
4.3.3 Measurements
a. The measured values shall be displayed locally on the Local HMI
contained as part of an IED, Station HMI and in the control center
(SCADA Master Station(s)). At the Station HMI level, facilities shall
exist to discard abnormal values (through the Station HMI Filtering
functions) and when an abnormal value is reached, generate an
alarm/event indicating that an abnormal value (s) has been detected.
b. All analogue values shall be updated (both in Local HMIs (contained
as part of the IEDs), and Station HMI equipment every 2 seconds, or
faster.
c. Threshold limit values shall be selectable for alarm indications.
4.3.4 Event and alarm handling
a. Events and alarms shall be generated either by the switchgear, by the
control IEDs, by the protection IEDs, by the combined
control/protection IEDs, or by the station level unit.
b. They shall be recorded in an event list in the station HMI. Alarms
shall be recorded in a separate alarm list and appear on the screen. All,
or a freely selectable group of events and alarms shall also be printed
out on an event printer.
c. The alarms and events shall be time-tagged with a time resolution of 1
ms National Grid Saudi Arabia notes that the time tagging of the
alarms and events shall be performed at the IED itself only, and NOT
through SAS Computer equipment..
d. During the Base Design Stage, the Solution provider shall submit the
Events and Alarms List (Signals List) for National Grid Saudi Arabia
approval, and once approved the Solution provider will use this
approved list as a basis for development of his SCD files for SAS.
e. As a minimum, the Signals and Events List shall contain all applicable
points as identified in TES-P-119.27 the SOE Points List and the
approved Annunciator Alarms List for the Substation. Also, in
development of the Events and Alarms List, separate dedicated lists
shall be generated for SOE, SCADA, and the Station HMI contained
as part of the Substation Automation System for review and approval.
f. Finally as part of the events and alarms handling requirement, when
there are cases where IEC 61850 DOES NOT provide for
alarms/events as part of the logical node (LN) signals definitions
(under IEC 61850) and where these alarms/events signals are required
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 35 OF 119 Date of Approval: February 26, 2013
under latest revision of Engineering Standard TES-P-119.27 (for
SCADA) the SOE Points List, and the National Grid Saudi Arabia
approved Annunciator Alarms List for the Substation, the SOLUTION
PROVIDER shall provide suitable auxiliary binary input contacts
(and/or binary outputs) as part of each IED design to extend non IEC
61850 alarms/events by hard-wired means to other components of the
SAS (which will appear as one of the GGIOs included as part of the
SAS Data Acquisition function which will be reported to the Station
HMI, the SCADA Master Stations and other equipment).
g. In/Out facility for the protection is isolating trip out put only during
maintenance of relays. However during this condition all alarms to
remote Master stations shall be isolated in order to avoid receiving any
nuisance alarms during maintenance. Facility for isolating alarms shall
be provided as part of relays or at the Gateways.
4.3.5 Time Synchronization System
a. A dedicated clock synchronization unit shall set the time within the
SAS. Time synchronization of all SAS equipment shall be
independent of the station level equipment e.g. station computer or
Communications Gateway. Time Synchronization shall be from
redundant GPS receivers located on the property of each substation.
The time shall then be distributed to the control IEDs, combined
Control/Protection IEDs and protection IEDs and other SAS
equipment via the communication buses. An accuracy of 1ms (from
the actual time) within the substation (and for ALL SAS components
within the substation which require time signals) is required.
b. Hardware/Firmware for the GPS receivers supplied by the
SOLUTION PROVIDER shall provide for a antenna, decoder, other
hardware, interfaces with the SAS and Firmware as per the latest IRIG
B122 or other National Grid Saudi Arabia approved standard time
code format (e.g. SNTP and others).
c. Software for the GPS receivers shall include a software package to
implement GPS-based time as per at least IRIG B122 standard time
code format (Day of Year and Time update rate of once per second,
AM 1 KHz carrier, resolution of + 1 mS, expressed in hh, mm, ss,
ddd) or other National Grid Saudi Arabia approved standard time code
format and able to synchronize time and date into the SAS, with all
components of the SAS receiving consistent time and date
information.
d. Upon failure of any GPS receiver in the time synchronization system,
the GPS receiver shall transmit an alarm to both the Station HMI
equipment in the SAS, and the remote SCADA Master Station(s).
-
TRANSMISSION ENGINEERING STANDARD TES-P-107.01, Rev. 0
TESP10701R0/KSB
PAGE 36 OF 119 Date of Approval: February 26, 2013
e. In the event of failures of both GPS clock receivers which are beyond
the control of the GPS clock receivers (e.g. shutdown of the GPS
satellite network, atmospheric conditions blocking reception of GPS
signals at the GPS receivers, etc.) there shall be a means of time
synchronization by the use of either internal SAS clocking sources
(e.g. internal clocks inside the IED(s), etc). or tertiary clocking
sources from the respective SCADA Master Station(s). In this respect,
during the Base Design Stage, the SOLUTION PROVIDER shall state
the holdover clocking accuracy of the internal SAS clocking sources,
the clocking drift of these internal SAS clocking sources and the
maximum allowable time which the SOLUTION PROVIDER feels
that the infernal SAS clocking sources will provide accurate (+ 1 ms
accuracy from real time) timing. If in the event that based on the
SOLUTION PROVIDER provided information, that the internal SAS
clocks will NOT provide accurate time information in the event of
both GPS receivers failing, the National Grid Saudi Arabia during the
Base Design will instruct the SOLUTION PROVIDER to utilize the
existing SCADA Master Station(s) Clocks as a tertiary
clocking/synchronization source and incorporate this SCADA Master
Station(s) clock as a tertiary clocking/synchronization source.
4.3.6 Telecontrol
Remote access to each substation data shall be enabled via the control centers
(SCADA Master Stations) upon request. The respective owners in the utility
organization may use some or all information related to the conditions of high
voltage apparatus.
4.3.7 Station HMI-Presentation and Dialogues and Design
a. General
The operator Station HMI shall provide basic functions for supervision and control within the substation.
The Station HMI shall be fully redundant and shall provide the functions for supervision and control of the substation. Access
to the redundant Front End Computers shall be through the
Operator's Workstations and the Engineer's Workstation.
However to meet the redundancy requirements a backup
workstation (included as part of a Maintenance Laptop
Computer) shall be provided with software and firmware fully
loaded which can be used to act as either the Operator's
Workstation or Engineering Workstation in the event of failure
of either the Operator's Workstations or Engineering
Workstation contained as part of the SAS.
The operator shall give commands to the switchgear on the screen via mouse clicks.
-
TRANSMISSION ENGINEERING STANDARD T