Field Observation Report #27 Date: Sept 25 th / Oct 2 nd , 2014 Project: Burleigh County Shop Time: 2:00 pm Project No: 12-04 Weather: Variable Location: Bismarck, ND Temperature: 60 degrees % Complete: 99% Visible Trades: Finishes Crew Size: 5-7 The following information is a documentation of observations and findings as a result of a visit to the construction site. Items and decisions made within this reports are considered a part of the contract documents. Photo 1: View from southwest side of the parking lot. 1. Landscaping work has begun, concrete floor sealing & hardening is underway, hardware is being installed, as well as plumbing fixtures. Project is wrapping up. 210 S 12 th Street Bismarck, North Dakota 58504 701-751-4555 www.ubldesign.com

Upload: others

Post on 01-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: th Field Observation Report #27 - Burleigh Countyburleighco.com/uploads/resources/993/field-report-27.pdfField Observation Report #27 Date: Sept 25th / Oct 2nd, 2014 Project: Burleigh

Field Observation Report #27

Date: Sept 25th / Oct 2nd, 2014 Project: Burleigh County Shop

Time: 2:00 pm Project No: 12-04

Weather: Variable Location: Bismarck, ND

Temperature: 60 degrees

% Complete: 99% Visible

Trades: Finishes

Crew Size: 5-7

The following information is a documentation of observations and findings as a result of a visit to the

construction site. Items and decisions made within this reports are considered a part of the contract

documents.

Photo 1: View from southwest side of the parking lot.

1. Landscaping work has begun, concrete floor sealing & hardening is underway, hardware

is being installed, as well as plumbing fixtures. Project is wrapping up.

210 S 12th Street

Bismarck, North Dakota 58504

701-751-4555

www.ubldesign.com

Page 2: th Field Observation Report #27 - Burleigh Countyburleighco.com/uploads/resources/993/field-report-27.pdfField Observation Report #27 Date: Sept 25th / Oct 2nd, 2014 Project: Burleigh

Photo 2: Exterior Signage has been installed.

Photo 3: Landscaping is underway.

Page 3: th Field Observation Report #27 - Burleigh Countyburleighco.com/uploads/resources/993/field-report-27.pdfField Observation Report #27 Date: Sept 25th / Oct 2nd, 2014 Project: Burleigh

Photo 4: A view of the Automatic Truck Wash

2. The punch list is still planned for October 16th, 2014. However, some Proposal Request are still

outstanding. Capital City Construction plans to have all outstanding pricing information to the

architect early next week.

3. Electrical work has been prioritized to get HVAC up and running. At the last meeting, Bergstrom

Electric indicated that the work required for a HVAC system start-up has been completed. The

electrical contractor plans to pour the light pole foundations next.

4. Electrical underground running to the lift station will need to be lowered. The ower is doing

work on the west side of the building; they plan to uncover the lines and Bergstrom will need to

re-trench to get the lines to an adequate depth.

5. All contractors are reminded that any un-used equipment, supplies, tools and garbage needs to

be removed from the project site.

Page 4: th Field Observation Report #27 - Burleigh Countyburleighco.com/uploads/resources/993/field-report-27.pdfField Observation Report #27 Date: Sept 25th / Oct 2nd, 2014 Project: Burleigh

Photo 5: A view of the maintenance bay area with the bridge crane above and hose reels in the background.

This concludes Field Observation Report #27. Please report any discrepancies to our office

within 5 days.

Thank you,

Jennifer Jackson