the capital budgeting process workshop training materials
TRANSCRIPT
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
1/395
AFRITAC East Regional Workshop
The Capital Budgeting Process
September 1 5, 2014, Entebbe/Uganda
Concept Note
The overarching aim of this workshop is to discuss all the major factors that need to be
taken into account to ensure that capital spending leads to the creation of productive
assets (tangible and intangible).Its central focus will be on how to increase the efficiency
and effectiveness of public investment spending. Public investment is generally regarded as
having a positive relationship with growth and therefore desirable in itself. However, the
literature has also emphasized the need to focus not just on quantitybut also on the qualityof
the capital spending (as for any other spending for that matter). For example, S. Gupta et al
point out that in countries with weak public investment management processes, public
investment expenditure is unlikely to translate fully into productive capital assets.1
Some of the seven AFRITAC East (AFE) member countries are currently allocating
significant amounts to capital spending.Capital expenditure in Rwanda, for example,
accounts for 12 percent of GDP, the highest among East African Community Partner states.
Similarly, Uganda is implementing an ambitious program of infrastructure development
which includes the construction of power plants, transmission lines and distribution network
together with roads and railway and an oil refinery, in anticipation of a significant increase in
revenue due to oil exports. In light of this and against the broad purpose mentioned above,
the workshop will set out to provide participants with a better understanding of the following
issues:
basic requirements for successful capital budgeting including appropriate institutional
arrangements
S. Gupta et al, Efficiency-Adjusted Public Capital and Growth, World Development 2014, Vol. 57, p. 164 1
78.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
2/395
2
key features of good practices of public investment management systems for efficient
and effective capital spending insights into the systems of at least two internationally recognized good practice
countries pros and cons of alternative financing and implementation modalities
macro-fiscal, project and other risks associated with capital spending and ways ofminimizing and/or managing them
improving the linkages between strategic planning and capital budgeting.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
3/395
3
Recent development in PFM has had a positive impact on the quality of public
investment spending.Three practices in particular have been so identified, namely, medium
term budgeting framework (MTBF), performance budgeting and accrual accounting .2
MTBFs facilitate the integration of investment spending within a more comprehensive
resource use framework. In its absence, planning documents tend not to be rooted in any
macro-fiscal framework. Performance budgeting (PB), in emphasizing results rather than the
nature of the spending (notably whether it is recurrent or capital), facilitates expenditure
prioritization and provides the basis to enforce accountability, helping to improve budget
outcome. PB can contribute to determine whether capital spending has been effective or not.
Accrual accounting provides a more comprehensive picture of a governments capital assets
than cash accounting.
The kind of MTBFs practiced by some countries, however, might not always bring
about the benefits expected.If forward estimates are merely indicative (meaning there are
large variations with the actual the following year), rather than binding, this will not result inthe necessary funding predictability required for successful capital budgeting. Even where
the forward projections are robust, as in advanced countries, the challenge has been to
reconcile the three or five year estimates with the far longer term horizon of some of the big
infrastructure projects. This has led some countries such as Ireland and UK to introduce
longer term commitment in particular sectors like transport, rather than specific projects. The
workshop will examine the fundamental issue of medium term budgeting as a key
requirement for productive capital spending.
An effective project cycle is also critical for successful public investment management.
The main stages are: Identification; Appraisal; Approval; Implementation; and Evaluation.
Some countries use fairly sophisticated techniques to carry out efficiently those stages. The
UKs Gateway model among advanced countries and Chiles National Investment Systems
among emerging economies are two such examples, both considered successful in their own
right. Both models will be presented during the workshop and participants will explore their
relevance and applicability to their respective countries. Each country delegation will be
required to present its capital budgeting system pointing out the respective strengths and
weaknesses and comparing against such best practices.
Israel Fainboim, Duncan Last, Eivind Tandberg, Managing Public Investment, in IMF, Public Financial2
Management and Its Emerging Architecture, p.313- 314
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
4/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
5/395
5
There are several risks to the workshop not reaching its principal objectives.First, the
choice of participants attending might not be the most appropriate. Despite AFEs insistence
to member countries to avoid doing so, workshops are often seen by them as a sinecure to
reward not always meritorious staff rather than a learning exercise for those involved in the
relevant areas of work and in need of capacity building. Attempts are usually made to
minimize the risk by closely scrutinizing participants but they are not always successful.
Also, at times it is a delicate matter to refuse a participant who has been nominated by his/her
member country. The next risk relates to the tradeoff between the intensity of the workshop
and the responsibility to cover as much ground as possible to warrant the significant costs
involved in the preparation of such a workshop. Workshop organizers typically try to reach a
compromise between the need to cover key elements of the subject while seeking to avoid
making it too intensive. It has been the case with this workshop. Participants evaluation
forms will tell whether the risk was mitigated. The workshop is prioritizing a practical
approach to the topic. There are risks that it might not have succeeded and the workshop is
perceived as being too theoretical.
The workshop will revolve around five thematic areas.They are as follows:
1. The basics in regard to the capital budgeting process.It has been pointed out in the
literature that getting the basics of the budget process right is fundamental. What is less clear
is what exactly basics are and what are not. The sessions here will propose two elements as
forming form part of the basics: (i) an MTFF/MTBF; and (ii) the integration of recurrent and
capital budgets (a related issue being what is the most appropriate institutional setup for
successful capital budgeting). As pointed out above (and in the reference article in thefootnote), putting the budget in a robust medium term framework helps to contain public
investment within a fiscally constrained environment (which could be based on explicit fiscal
rules). Previously (but still prevalent in some countries), Ministries of Planning prepared
ambitious public investment programs (PIPs) in disregard to any medium term fiscal
framework.
The integration of the current and development budgets - a major reform aimed at improving
budgetary management- has proved a challenge. The sessions would provide an opportunity
for participants to discuss why separate current and capital budgets have evolved over time
and what are the challenges posed by that. Participants would be exposed to the basic
principles of a unified budgeting system and identify the potential areas of improvements that
would underpin a sustained transition to it.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
6/395
6
2. Increasing the efficiency and effectiveness of Public Investment. Public investments are
increasingly viewed as unaffordable, insufficient and sometime unsustainable posing a
challenge to prudent fiscal management. The sessions would examine the current practices
that undermine the efficiency and effectiveness of capital budgeting. The overall objective
would be to identify the best practices within the region and global context that promote: (i)
systematic cost benefit or cost effectiveness analysis of investment proposals; (ii) adoption of
a clear and transparent criteria to guide project selection, as well as (ii) institutional
arrangements for monitoring the implementation of the investment Projects.
The sessions will also explore ways of ensuring best practices at each of the following stages
of Public Investment management: Identification; Appraisal; Independent Review; Approval;
Implementation; Evaluation.
3. Financing of Public Investment.There are different ways of financing public investment,
each with their own risks and benefits. Domestic revenue, donor financing, borrowing on
concessional and non concessional terms and PPPs are the different ways to do so. The
sessions will discuss them but PPP will feature most prominently for the reasons explained
above. Participants will also learn about best practices from countries that are experienced in
this area. It is expected that case studies will be presented.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
7/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
8/395
AGENDA(FINAL)
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
9/395
2
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
10/395
3
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
11/395
4
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
12/395
5
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
13/395
6
GROUPPHOTOGRAPHOFPARTICIPANTS
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
14/395
7
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
15/395
8
LISTOFPARTICIPANTS
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
16/395
9
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
17/395
The Capital Budgeting Process
Program Presentation
Tawfik Ramtoolah
AFRITAC East PFM Adviser
Monday September 1, 2014
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
18/395
Welcome to all ParticipantsWorkshop Objectives
Overarching aim: discuss the major factors that need to be taken into account to ensurethat capital spendingleads to the creation of productive assets. Specifically, theworkshop aims at providing participants with a better understanding of the following :
basic requirements for successful capital budgeting including appropriateinstitutional arrangements
key features of good practices of public investment management systems forefficientand effectivecapital spending
insights into the systems of at least two internationally recognized good
practice countries
pros and cons of alternative financing and implementation modalities
risks associated with capital spending and ways of managing them
improving the linkages between strategic planning and capital budgeting
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
19/395
Five thematic areas to be covered
1. Getting the Basics Right2. Increasing the efficiency and effectiveness of Capital spending
3. Financing Public Investment
4. Public Investment practices in AFE member countries and elsewhere
5. Institutional and Capacity building priorities and Technical Assistance
It is expected that through the coverage of those five themes, participants arebeing provided with the skills and knowledge required to improve capital
budgeting in their countries
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
20/395
Requirement for the workshop to be successful
Good time management arrive on time and start on time Participation is important interaction between delegates and resource person
encouraged
Fairly intensive program still try to have a balance b/n intensity and relaxing
Overlapping nature of some of the themes/topics
Program prepared on basis that topics relevant, relates to the work ofparticipants but may be not always so
Flash drive with all the PPT and reading list (no hard copy) Workshop evaluation important
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
21/395
The Capital Budgeting Process
Theme 1: Capital Budgeting Getting the Basics Right
Session 1.1: What are the Basics?
Tawfik Ramtoolah
AFRITAC East PFM AdviserMonday September 1, 2014
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
22/395
What are the Basics?
Outline
PIP (or Capital budget) v/s Acquisition of Non Financial Assets(ANFA)
ANFA v/s growth
Current v/s Capital spending
National Planning Strategy, MTFF and MTBF(needs v/s funding
availability)
The appropriate institutional setting (one unified central financeagency v/s two)
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
23/395
PIP (or Development or Capital Budget) v/s Acquisition ofNonfinancial Assets Issue No. 1
Government seeks to build assets through spending in the budget. It takes theform of PIP or Capital budget.
Question: are all the spending in the Capital Budget or all the projects in thePIP really about building assets or some merely recurrent in nature?
If a large part consists of salaries, they cannot be included as Acquisition offixed assets
..\ICD & Others - Courses\GFS 2014 - Clasification of Expense.pdf
..\ICD & Others - Courses\GFS 2014 - NonFinancial asets (detail).pdf
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
24/395
Acquisition of non-financial assets and growth - Issue No.2
Do all ANFA contribute to growth? Is the impact on growth the same from one asset to another?
The construction of a market can be expected to increase value added
How about the construction of a bridge leading to nowhere (while elephant)
What should be done to strengthen the link between capital spending,acquisition of non-financial assets and growth?
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
25/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
26/395
Current and Capital expenditure: Is the distinction alwaysuseful? - Issue No. 3
If capital spending has to be efficient and effective, how about currentspending?
All spending must be useful whether current or capital
A fertilizer/farm input subsidy program, if well designed and targeted couldhave greater impact on growth that a capital project
Is fixing leakages in a water network better that building a new dam?
Policy issues can be tackled using either current or capital expenditure e.g.
lower female enrolment The distinction between current and capital is sometimes useful sometimes
counterproductive the quality of the spending is more important than thedistinction b/n the two types
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
27/395
National Planning strategy and MTFF/MTBF: Needs v/sFunding availability Issue No 4
Importance of medium term fiscal framework in constraining investmentspending
Importance of medium term budget framework in providing for fundingpredictability (locks in the funding)
An example is provided
..\Eritrea\MTFF South Africa 2011 -15.pdf
..\Eritrea\MTBF South Africa 2011 -15.pdf
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
28/395
Macro-FiscalApprovedBudget 2012/13
BudgetEstimates2013/14 2014/15 2015/16 2016/17 2017/18
Nominal GDP 55,574.03 62,322.97 69,631.08 77,818.64 87,488.28 98,250
DomesticResources 7,467.60 8,843.40 9,993.90 11,719.90 13,682.00 15,980
Nominal GDP (%growth) 12.14% 11.73% 11.76% 12.43% 12.30
DomesticResources (%
growth) 18.42% 13.01% 17.27% 16.74% 16.80
Tax Revenue (%
growth) 15.07% 17.49% 17.42% 16.86% 16.8
Budget support (%growth) -93.38% -16.94% 2.91% 3.07% 2.9
Project support (%growth) 17.05% -28.18% -20.50% 3.00% 3.0
DomesticFinancing (%
growth) -21.12% -33.09% -8.03% -62.78% 101.28
Comprehensiveness of the expenditure ceiling the case of Uganda
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
29/395
Uganda - The resource envelope
ApprovedBudget2012/13
BudgetEstimates2013/14 2014/15 2015/16 2016/17 2017/18
Domestic Resources 7,467.60 8,843.40 9,993.90 11,719.90 13,682.00 15,
URA Revenue 7,284.70 8,382.20 9,848.30 11,564.30 13,514.40 15,
Non-tax revenue 171.1 461.2 145.6 155.6 167.6
Loan repayments 11.8 0 0 0 0
Budget support 749.5 49.6 41.2 42.4 43.7
Grants 480.7 49.6 41.2 42.4 43.7
Loans 268.8 0 0 0 0
Project Support 1,992.80 2,332.60 1,675.30 1,331.90 1,371.80 1,
Grants 762.1 805.5 722.6 622.3 641
Loans 1,230.70 1,527.10 952.7 709.6 730.8
Domestic Financing 988.6 779.8 521.8 479.9 178.6
Resource envelope (inc.projects) 11,198.50 12,005.40 12,232.20 13,574.10 15,276.10 17,
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
30/395
Uganda - From resource envelope to expenditure ceiling
ApprovedBudget2012/13
BudgetEstimates2013/14 2014/15 2015/16 2016/17 2017
Resource envelope (exc. Projects) 9,205.70 9,672.80 10,556.90 12,242.20 13,904.30 1
External debt repayments -250.4 -300 -303.2 -301.7 -326.2
Amortization -217.2 -272.5 -288.5 -295.7 -322.8
Exceptional Financing -9.4 -13.2 -14.7 -6 -3.4
Arrears -23.8 -14.3 0 0 0
Domestic debt repayments -9.7 -9.7 -9.7 -9.7 -9.7
Resource envelope (excl. debt repayment) 8,945.60 9,363.10 10,243.90 11,930.70 13,568.40 1
Domestic arrears 35 0 50 50 50
Resource envelope (excl. debt repaymentand Domestic arrears) 8,910.60 9,363.10 10,193.90 11,880.70 13,518.40 1
Interest payments 839.2 908.5 729.5 719.2 674.2
o/w domestic 712.8 785.1 615.9 603.6 566.7
o/w external 126.4 123.4 113.6 115.6 107.5
Resource envelope (net of interest, debt andarrears) Expenditure ceiling 8,071.40 8,454.60 9,464.40 11,161.50 12,844.20 1
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
31/395
Uganda - From resource envelope to expenditure ceiling
ApprovedBudget2012/13
BudgetEstimates2013/14 2014/15 2015/16 2016/17 2017
Resource envelope (exc. Projects) 9,205.70 9,672.80 10,556.90 12,242.20 13,904.30 1
External debt repayments -250.4 -300 -303.2 -301.7 -326.2
Amortization -217.2 -272.5 -288.5 -295.7 -322.8
Exceptional Financing -9.4 -13.2 -14.7 -6 -3.4
Arrears -23.8 -14.3 0 0 0
Domestic debt repayments -9.7 -9.7 -9.7 -9.7 -9.7
Resource envelope (excl. debt repayment) 8,945.60 9,363.10 10,243.90 11,930.70 13,568.40 1
Domestic arrears 35 0 50 50 50
Resource envelope (excl. debt repaymentand Domestic arrears) 8,910.60 9,363.10 10,193.90 11,880.70 13,518.40 1
Interest payments 839.2 908.5 729.5 719.2 674.2
o/w domestic 712.8 785.1 615.9 603.6 566.7
o/w external 126.4 123.4 113.6 115.6 107.5
Resource envelope (net of interest, debt andarrears) Expenditure ceiling 8,071.40 8,454.60 9,464.40 11,161.50 12,844.20 1
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
32/395
The appropriate institutional settingfor best practice Capital budgeting Issue No. 5
Issue: Is it better to have one unified central agency (e.g. Ministry ofFinance, Planning and Econ Dev) or two (Finance; Planning or NatPlanning Commission) or more (an Independent agency)?
Compare the case of South Africa and Tanzania
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
33/395
The need to prepare the Current and Capital budgets together:Issue No. 6
Importance of preparing the 2 budgets together to ensure that recurrent costsof capital spending are included in the budget
Avoid building schools and not having teachers to teach or electricity or water
The issue is closely linked to the institutional fragmentation of the budgetprocess having different agencies involved could complicate it (becomesmore difficult to budget for recurrent costs)
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
34/395
To summarize
Ensure PIP or Capital spending translate into productive assets Productive assets should have as large an impact on value added as possible
All spending should be useful whether current or capital the distinction b/nthe two is useful at times but could be counterproductive in other times
MTFF/MTBF are critical instruments to constrain capital spending andprovides an anchor to otherwise overambitious planning documents
Institutional set-up is important one agency might be better than two or
more (except for an independent one) Preparing current and capital together is better
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
35/395
CAPITAL BUDGETINGWORKSHOP, ENTEBBEIndependent and Quasi-Independent
InstitutionsSimon Groom
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
36/395
Reasons for establishingindependent or quasi-independent
institutions Objectivity/impartiality
Promoting good practices
Compensating for skill shortages byconcentrating capacities
Strategic guidance on capital investment
priorities
2
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
37/395
Overview
S. Korea: PIMAC
UK: Major Projects Authority
South Africa: Planning Commission
Ireland: CEEU
European regional organisations
3
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
38/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
39/395
Status of PIMAC
PIMA merged with Private InfrastructureInvestment Centre in 2005 - consistent withintroduction of unified framework for PPPproject appraisal
PIMAC is a statutory organisation under thePPP Act (as amended 2005)
PIMAC is an affiliated body of the KoreanDevelopment Institute, an independent think-tank under the tutelage of the MOSF.
Korean Development Institute comes under
Government Funded Research Institute Act
5
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
40/395
A Unified Framework for PPP Project Appraisal
6
Project Initiation(Solicited / Non-Solicited)
FeasibleProject?(PFS)
VFM Test
Formulation of PPP Alternative
STOPGO thru PPP
N
Y
NY
Phase 1
Phase 2
Phases 3
GO thru Government Project
6
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
41/395
Organization Chart for PIMAC
85 staff in 3 divisions
7
Policy ResearchUnit
Public InstitutionEvaluation Unit
ProgramEvaluation Unit
Executive Director
PFS Unit 1 RSF Unit PPP Policy UnitPPP ProjectUnit
Finance & IntlCooperation U
Policy and Research Division(21)
Public Investment Evaluation Division(32)
Public-Private Partnerships Divisio(30)
Conduct and manage PFS andRSF and RDF
Policy research on PIM
Research on Methodology ofProject Evaluation
Program Evaluation andPerformance Management ofPublic Investment Projects
Appraisal for SOE Projects
Formulate PPP Annual Plan anddevelop PPP guidelines
Conduct Evaluation of PPP Projec Researches on PPP Financing and refinancing PPP Capacity building training Infrastructure DB management
PFS Unit 2
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
42/395
Role of PIMAC
Researcher Theoretical and policy studies on infrastructure
development and management
Research on evaluation methodology
Formulation of the Annual PPI Plan
Project Appraiser/Evaluator
PFS on large-scale government projects/programs PFS on large SOE projects
RSF (re-assessment study of feasibility) onongoing projects
VfM tests on PPP projects
EBP (in-depth evaluation of budgetary program)
8
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
43/395
Impact of PIM System ReformsImplemented by PIMAC
Preliminary Feasibility Studies PFS performed for 528 projects 1999-2011, of
which 61.6% found to be feasible
Total Project Cost Management Average cost increase requested fell from 26.4% in
1996-99 to 4.4% in 2000-03
Agreed cost increases fell from 11.1% in 1996-99to 1.0% in 2000-03
Re-assessment Study of Feasibility 24 out of 140 projects subject to RSF were stopped
2006-2010
Total project cost savings of 18% made (compared
9
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
44/395
Why is PIMAC Interesting?
Demonstrates potentially significant impactthat impartial, non-conflicted institutions canhave on improving value for money
Illustrates proportionality in appraisal effort
Shows how a unified approach to PPP can bestrengthened through organisationalarrangements
10
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
45/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
46/395
Origins of MPA
Origins lie in a critical report by the NationalAudit Office, Assurance for High RiskProjects, instigated because of some highprofile project failures:
Defines assurance as independent assessment ofwhether required elements to deliver projects
successfully - good project management practicesand appropriate funding and skills - are in placeand operating effectively
Found that:
High-risk projects often large-scale, innovative andreliant on complex relationships between stakeholders
12
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
47/395
Main Activities of MPA
Develop and maintain the first (!) system formonitoring Government Major ProjectPortfolio (GMPP):
Annual Report on progress around 200 projects
Traffic-light warning system for deliveryconfidence
Instigate mandatory Starting Gate Reviewprocess decision-step before any publicannouncement
Introduce system of Integrated Assurance andApproval Plans schedule of assurance
13
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
48/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
49/395
Delivery Confidence Ratings for Major Projects
15
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
50/395
Completeness of Submissions from Spending Ministries
16
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
51/395
Why is MPA Interesting?
Illustrates usefulness of independent view onthe overall portfolio and systems
Identified need for MPA illustrates:
Potential loss of central oversight over capitalprojects in decentralised, performance-orientedbudgeting systems [consultants opinion!]
Recognition of high risk of many public sectorinterventions
Role of organisation highlights:
Insufficient attention to deliverability in thetraditional interplay between spending ministries
17
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
52/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
53/395
Functions of NPC
Lead the development and periodic reviewSouth Africa Vision 2030 and long-termnational strategic plan
Lead investigations into critical long-termtrends
Advise on key economic and social issues
Assist with mobilising society around thenational vision
Contribute to reviews of implementation orprogress in achieving the objectives of thenational plan
19
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
54/395
Activities of NPC
Prepared diagnostic Overview (June 2011)setting out key challenges in combattingpoverty and inequality and led consultations
Draft National Development Plan Vision for2030 (November 2011)
Undertook national dialogue on draft nationalplan, including sub-national governments andcivil society
Prepared revised National Development Plan(September 2012)
Currently advising government on
20
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
55/395
NDP and Capital Budgeting
Diagnostic Overview includes MaterialConditions Diagnostic, which in turn coverssocial and economic infrastructure, identifyingcurrent provision, demand growth and gaps
Chapter 4 of NDP deals with economicinfrastructure, identifying key policy issues
and priorities in each sector -
21
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
56/395
Why is the NDP Interesting?
Provides an example of an independent think-tank developing the kind of strategic guidancenecessary for identifying and prioritisingpublic capital investment
No role in budgeting, so no risk of dualbudgeting problems
Other AFE countries have planningcommissions, but sometimes more directlyinvolved in capital budgeting, potentiallyundermining the advantages of integratedbudgeting:
22
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
57/395
Ireland: Central ExpenditureEvaluation Unit
Began in 1996 as Central Evaluation Unit(CEU) with finance ministry, but has alwaysoperated more or less independently
As late as 1990, Ireland had no systematicprocess for public investment management
Driver was the need to set up good systems forplanning capital investment projects fundedthrough EU Structural Funds and then theextension of these systems to domesticallyfunded projects.
23
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
58/395
Functions of the Central Evaluation Unit
The functions of the original CEU were definedas: Assist ministries with developing (outcome-
oriented) performance indicators by which they areassessed;
Undertake interim evaluations of ministry plans,
including investment plans; Offer advice on and set standards for cost-benefitanalysis; and
Offer advice on wider evaluation issues, e.g., expost evaluations.
The Unit led the process of developing the
24
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
59/395
Functions of the CentralExpenditure Evaluation Unit
The CEEU was created in 2006 with a widerremit than the CEU:
Verification of the application of the 2005 CapitalAppraisal Guidelines;
Co-ordination of overall implementation of thecomprehensive program of value for money and
policy reviews agreed by the Government in 2006;
Preparation and rollout of program evaluationsunder the National Development Plan 2007-2013;and
General remit to promote value for money acrossthe system including through the provision, as
25
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
60/395
Why is the CEEU Interesting?
Example of a quasi-independent organisationoperating under the finance ministry (and from2011 the ministry for public expenditure andreform)
Demonstrates that a small, focused unit with agood deal of independence can be very
influential: original CEEU had staff of 10,including 6 specialist evaluators
Decentralised approach to improving capitalbudgeting: CEEU promotes good practice
26
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
61/395
Regional Institutions to Fill Capacity Constraints:Joint Assistance to Support Projects in European Regions
(JASPERS)
Managed by European Investment Bank andco-sponsored by EC, EBRD and KfW
Provides advice to 13 New Member States aswell as candidate countries
Provides technical support to prepare majorinfrastructure schemes financed by EUStructural and Cohesion Funds
Improves to improve the quantity and qualityof requests for funding
27
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
62/395
Regional Institutions to Fill Capacity Constraints:Western Balkans Investment Framework (WBIF)
Joint initiative of the EU, internationalfinancial institutions (EIB, EBRD & WB),bilateral donors (KfW) and governments of theWestern Balkans
Provision of small grants which are used to
attract larger amounts of loan finance(leverage)
Grants largely used for technical assistance inpreparing bankable projects for investors tomake their investment decision. TA provided
by contracted teams of consulting experts
28
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
63/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
64/395
Edgardo S. Mimica ([email protected])1
Through time the NIS has achieved a high level of legitimacy in its:
TECHNICAL- ECONOMICAL DIMENSION due to its success in filtering the
bad and finding the best projects among 0.5 million alternatives that arerevolving in the data base. This gain in efficiency has helped to solve more
social demands with the limited, available public funds
ETHIC DIMENSION for the increasing transparency and availability of
contemporary information regarding the public investment process. Any proje
in the Integrated Bank of Projects has been made public through the Internet
See: www.bip.mideplan.cl/bip-consultas/inicio_ie.htm
DEMOCRATIC DIMENSION for the increasing participation of civil society in
discussion of investment decisions process. Private and non-governmental
organizations may also propose and formulate investment projects, but they
must coordinate through the Provincial or Local governments in order for them
to apply indirectly for public funding
POLITICAL DIMENSION for the coordination of government policies and
strategies
LEGITIMACY OF THE NATIONAL INVESTMENT
SYSTEM
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
65/395
Edgardo S. Mimica ([email protected])2
The National Investment System (NIS
strategic planning and budgeting for
public investment
Content of this PresentatioContent of this Presentatio
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
66/395
Edgardo S. Mimica ([email protected])3
In Chile (since 1973):
State Enterprises
Ministries
Organisms depending
from Ministries
Local governments
Majors Municipalities
Provincial Governments
Governors Formulate & appraisprojects, but.. accordi
to Ministry of Planni
regulations
To verify if Investment Initiatives are attractive, means:
Performing an Economic or SOCIAL Project Appraisal
(i.e Evaluation from the point of view of the entire Nation)
MINISTRY of PLANNINGdoes not formulate projects, they only REVIEW and MONITOR the
appraisal of projects
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
67/395
Edgardo S. Mimica ([email protected])4
National Investment System (NIS)
legal framework (summary)
Laws: Financial Administration of the Nation
Laws: Planning Ministry
Laws: Budget of Public Sector
Laws: Provincial Governments
Regulations: Office of the Budget
NOTE: A National Investment System must be overwhelmingly rooted in the National Legal
System of a country. Hopefully, requiring Constitutional amendment
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
68/395
Edgardo S. Mimica ([email protected])5
PURPOSE OF THE NATIONAL INVESTMENT SYSTEM
Contribute to increase the general welfare of the communi
To provide the public authorities with a plentiful portfolio of good investme
projects, so that they can choose those suited as more convenient for society as
whole
Investment projects must comply with quality standards in terms of elaboratio
evaluation and analysis, they are controlled and monitored according to uniform a
transparent rules and with an adequate democratic participation of both the pub
institutions and the organized community or civil society (interest groups, ngo
private sponsors, etc)
Purpose: To increase the quality of National Public Investment
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
69/395
Edgardo S. Mimica ([email protected])6
PROJECTS HAVE TO FOLLOW THE NATURAL DEVELOPMENT
CYCLE TO BE APPROVED
The N.I.S has been designed toimpose projects to go through th
Project Life Cycle, starting from the identification of a proje
idea/concept to the final operation and ex-post evaluation stage
The project development cycle is a continuous and dynamic proces
with a great deal of overlap, interaction and feedback among th
various phases. Many of the activities are inter-related and cannot b
confined to one particular phase (*)
This interrelationship is particularly strong among the phase
preceding the implementation. There is a considerable interactiobetween the implementation phase and the evaluation phase as th
lessons ofex-post evaluationare constantly used to suitably mod
the operations of the project
* Note: From Glenn P. Jenkins Project Appraisal Manual
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
70/395
Edgardo S. Mimica ([email protected])7
Identification of an unresolved problem, possible benefits, geographic localiza
and objectives
Collect additional data and check previous information. Examine technical
institutional alternatives, establish first cost assessments for investm
operation, project life and other requirements. Do a preliminary evaluation
Get all the detailed information needed. Eliminate certain unviable alternati
and evaluate the rest. Pre-arrange for financing. Study all modules: market
demand, technical, environmental, human resources, institutional. Do financ
economic and distributional appraisals. Do also sensitivity and risk analy
Find the best alternative
Detailed engineering design, blue prints and specifications, define all
logistics, do final adjustments previous to execution stage, draft bidding propo
Develop the chosen alternative and reduce the uncertainties to acceptable limdefine its parameters. Arrange final financing scheme. Go deeper into study
modules with the highest risks, check all the assumptions you made
Idea
Profile
Pre
Feasibility
Feasibility
Design
Components of NIS Project Cycle: Pre-Investment Stag
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
71/395
Edgardo S. Mimica ([email protected])8
Flux Diagram of a Project Life CycleIdea
Profile
Pre-Feasibility
Feasibility
Detailed design & Execution-Construction $$$.$$$.$$$
Operation $.$$$.$$$
Wait Reject
RejectWait
Reject
Reject
Wait
WaitExecution
Execution
Go deeper $$$
Go deeper $$.$$$
Go deeper $.$$$.$$$
Ministry of Finance
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
72/395
Edgardo S. Mimica ([email protected])9
Processes for appraising investment
projects ex-ante
Content of this PresentatioContent of this Presentatio
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
73/395
Edgardo S. Mimica ([email protected])10
1st) SYSTEMATICALLY KILL BAD PROJECTS AND
TO DO IT AS SOON & EARLY AS POSSIBLE,
DURING THE PRE-INVESTMENT STAGES
Politics & civil society enter the investment decision
discussion or start lobbying only after the NIS pre-investment process is terminated.
This is, public discussion is only on the portfolio of projects th
approved the NIS process
TWO GENERAL PURPOSES OF THE NATIONAL INVESTMENT SYSTEM (NIS
If this is successfully done, then
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
74/395
Edgardo S. Mimica ([email protected])11
2nd) TO SLOW DOWN THE INVESTMENT DECISIO
PROCESS BY INTRODUCING GRADUALISM
THROUGH A MANDATORY PROJECT LIFE CYCLE
TWO GENERAL PURPOSES OF THE NATIONAL INVESTMENT SYSTEM (NIS
If this is successfully done, then
The NIS becomes the anchor ofthe financial system; it provides
stability, forcing to approach the
desired end by gradual stages
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
75/395
CAPITALBUDGETINGWORKSHOP,
ENTEBBETheme 1: Getting the Basics Right
Recap of the Days Presentation
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
76/395
What are the basics?
Ensure PIP or Capital spending translate intoproductive assets
Productive assets should have as large an impact onvalue added as possible
All spending should be useful whether current orcapital the distinction b/n the two is useful attimes but could be counterproductive in other times
MTFF/MTBF are critical instruments to constraincapital spending and provides an anchor tootherwise overambitious planning documents
Institutional set-up is important one agency might
be better than two or more exce t for an
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
77/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
78/395
Case for Independent Institutions:
Is there a place for an independent pre-appraisalprocess like S. Koreas? Do AFE countries have thesame sort of problems that S. Korea was trying toovercome? What would be the constraints in termsof human resource capacities and financing?
Are there advantages from the planning commission
model in terms of developing realistic plans anational consensus about the future direction ofinvestment? What are the potential disadvantages interms of mission creep and embedding the capital-current budgeting dichotomy?
Is the small, independent evaluation unit a possible
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
79/395
Chiles National InvestmentSystem
NIS applies to all levels of government and hasstrong legal basis
MOP does not prepare capital budget: it maintainsand polices the NIS and is the ultimate arbiter indeciding which projects go forward during pre-investment stage
Clear allocation of roles and responsibilitiesbetween MOP , MOF and other actors
Rigorous, sector-specific methodologies economic analysis techniques, supported bypublished parameter values
NIS is iant filter screenin out ro ects at idea
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
80/395
CAPITALBUDGETINGWORKSHOP,
ENTEBBEInvestment Project Cycle Ensuring good practice
& country examples
Simon Groom
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
81/395
Introduction
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
82/395
What is a Project?
UK definitionAproject has definite start and finish dates, a clearlydefined output, a well defined development path, anda defined set of financial and other resourcesallocated to it; benefits are achieved after the projecthas finished, and the project plans should include
activities to plan, measure and assess the benefitsachieved by the project.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
83/395
Project Cycle
Formalised sequence of activities and decision-making with feed-back loop
Moving from one stage to the next should notbe automatic and projects can be stopped atany time
Where necessary, Departments and public bodies should be prepared at any stage,despite costs having been incurred in appraising, planning and developing aproject, to abandon it if, on balance, continuation would not represent value formoney. (Irish Public Spending Code)
Number of stages not as important as thediscipline a formal project cycle structurebrings to the public investment management
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
84/395
Indicative Project Cycle
Preparation
Appraisal
IdentificationEvaluation &Audit
FundingApproval
Implementation& Monitoring
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
85/395
Project Cycle: Linksto Budgeting and
Strategic Planning
Preparation
Appraisal
IdentificationEvaluation &
Audit
FundingApproval
Implementation& Monitoring
StrategicPlanning
StrategicPlanning
Budgeting
Budgeting
Budgeting
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
86/395
UK Project Cycle
Stage 1 Scoping the proposal andpreparing the Strategic Outline Case (SOC) Making the case for change
Exploring the preferred way forward
Stage 2 Planning the scheme andpreparing the Outline Business Case (OBC) Determining value for money
Preparing the potential deal
Ascertaining affordability and funding requirement
Planning for successful delivery
Stage 3 Procuring the solution and
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
87/395
Ireland: Decisions and Approvals Linked to ProjectStages
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
88/395
No Inventory No strategicfilters; weak
projectscreening
Low allocation; Newfavored overcompletion
Consistentunder
execution;incomplete
projects
Sporadic audit,evaluation
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
89/395
Project Identification
(& Strategic Guidance)
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
90/395
Identification: Key Elements
Authoritative and operational strategicguidance to guide identification
Credible = realistic
Operational = not so vague that it is subject tointerpretation
Authoritative = supported at the highest politicallevel
Formal projection initiation process, involving:
Preparation of project profile/concept note
Preliminary screening
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
91/395
Where Do Project Concepts Come From?
Sector strategies
Problem and stakeholder analysis (framed by sector strategies)
Identification of appropriate project ideas to address anidentified problem (including non-engineering solutions)
Asset management systems
Spontaneously from politicians through consultation withconstituents origin of some good ideas, but also of many
potential white elephants NEED TO FOLLOW SAMEPROJECT CYCLE AS ALL OTHER PROJECTS
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
92/395
Strategic Guidance
Starting point for identifying project concepts Basis for prioritisation
Investment strategies better when costed,framed by realistic resource constraints andspecific (not visions)
No blueprint for strategic planning:
National development strategies/plans withinvestment/infrastructure components
National investment/infrastructure strategies
Sector investment strategies - better if part of
13
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
93/395
Ireland
Economic and Social Infrastructure OperationalProgramme of 7-year National Development Plan2000-06 (linked to EU funding cycle)
Sector investment strategies, e.g., Transport 212006-2015 (within NDP 2007-13)
United Kingdom National Infrastructure Plan 2013 a new
instrument for UK
Previously, ministry investment strategies
Netherlands
Examples of Advanced CountryStrategic Guidance
14
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
94/395
Focus on the role of the publicsector in a mixed marketeconomy
Based on realistic estimates ofresource availability, includingEU Structural Funds
Integrated planning
Factors in the Success of IrelandsNDP 2000-2006
15
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
95/395
Ireland: Process for Identifying NationalInvestment Priorities
16
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
96/395
Structure of UK National InfrastructureStrategy 2013
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
97/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
98/395
Ireland Preliminary appraisal for projects >!5 million to
assess case for in-depth appraisal of fully preparedproject:
Sets out project objectives; assesses needs; and identifiesoptions for in-depth analysis
United Kingdom
Strategic Outline Case for projects prepared withan emphasis on the Strategic Case:
Examines strategic priority; identifies project options forin-depth analysis; and assesses affordability.
Examples of Formal Project Initiation Processes
19
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
99/395
Each of 5 thematic cases is given more or lessemphasis at different stages of projectdevelopment:
1. Strategic Case: sets out rationale forproposed investment, making the case at the
strategic level2. Economic Case: assesses economic costs
and benefits of the proposal to society as awhole, and spans the full life cycle of theproject
20
UK: 5 Thematic Cases to Be Developed andMonitored at Each Stage of the Project Cycle
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
100/395
Strategic Outline Case Outline Business Case Full Business Case
Strategic Case Completed in full but maybe revised later
Revisited. Revisited and revised if required.
Economic Case Completed as far as reviewof a long-list of options,recommended way forwardand an initial short-list forOBC stage
Completed according tomethodological guidance onappraisal and evaluation incentral government (theGreen Book).
Findings of procurementincluded in the economicanalysis and recorded.Economic case re-assessed.
Commercial Case Addresses the fundamentalsof any potentialprocurement or deal, e.g.,initial identification ofpotential PPP options.
Outlines envisaged dealstructure/s and any contractualclauses and paymentmechanisms.
Recommended deal writtenup.
Financial Case Discusses likely affordabilityof the proposed project
Detailed analysis ofaffordability and any fundinggaps.
Affordability and fundingissues resolved.
Management Case Outlines how the project willbe set up and managed
Develops in more detail howthe project will be deliveredwith an outline of theproposed project managementplan.
Detailed plans for deliveryand arrangements forrealization of benefits, themanagement of risk and expost evaluation are recorded
21
UK: Strategic Outline Case
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
101/395
1. Business case basics
a. Aims & objectivesb. Options is there a proposed option and will it
achieve the aim/s?
c. What are the fallbacks/other options?
d. What must be taken into account and/or cannotbe ignored?
2. Timeline
3. Team capability
4. Finances estimated cost and availablebudget
5. Risks
22
UK: Starting Gate Reviews for Major Projects
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
102/395
Examples of Formats for Project Profiles
South Africa:
The problem that has given rise to the need forthe project
The statistical data, baseline information andservice-delivery indicators pointing to the needat this time
The extent and urgency of the need
The consequences if the need is not met
The proportion of the need a given request isintended to meet
How the project fits into the ministrys long-
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
103/395
Logical Framework Approach
Sets out hierarchy of project objectives based oncause and effect (internal project logic):
Overall Goal
Project purpose
Outputs
Activities
Identifies measurable indicators of achievement andmeans of verification
Identifies assumptions and risks (external projectlogic)
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
104/395
Preparation & Appraisal
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
105/395
Preparation & Appraisal: KeyElements
Regulated process with main steps, decisionsand allocation of roles and responsibilitiesclearly defined and understood by participants
Rigorous methodologies, applied consistently,but proportionately
Independent review or assessment
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
106/395
Project Preparation
Project concept developed sufficiently to verifygood use of public money
More than an engineering analysis; less than adetailed design (at least for appraisal decision)
Crucial to identify and analyse project
alternatives Involves:
Technical design and costing
Feasibility studies economic/financial &technical/engineering
Pre-feasibility studies for major/complex projects
27
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
107/395
Ireland
Project preparation process regulated by Part B Appraisal & Planning - of the Public SpendingCode setting out appraisal steps, approvalsrequired and roles and responsibilities -http://publicspendingcode.per.gov.ie/appraisal-and-planning/
The Central Expenditure Evaluation Unit of theDepartment (Ministry) for Public Expenditure andReform is responsible for system design andpromoting use of good practice
Spot checks required to ensure good process has
been followed
Examples Regulated Project Preparation Processes
28
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
108/395
Strategic Outline Case Outline Business Case Full Business Case
Strategic Case Completed in full but may berevised later
Revisited. Revisited and revised ifrequired.
Economic Case Completed as far as review ofa long-list of options,recommended way forwardand an initial short-list forOBC stage
Completed according tomethodological guidance onappraisal and evaluation incentral government (theGreen Book).
Findings of procurementincluded in the economicanalysis and recorded.Economic case re-assessed.
Commercial Case Addresses the fundamentals ofany potential procurement ordeal, e.g., initialidentification of potential PPPoptions.
Outlines envisaged dealstructure/s and anycontractual clauses andpayment mechanisms.
Recommended deal writtenup.
Financial Case Discusses likely affordabilityof the proposed project
Detailed analysis ofaffordability and anyfunding gaps.
Affordability and fundingissues resolved.
Management Case Outlines how the project willbe set up and managed
Develops in more detail howthe project will be deliveredwith an outline of theproposed projectmanagement plan.
Detailed plans for delivery anarrangements for realization obenefits, the management ofrisk and ex post evaluation arerecorded
29
UK: Outline Business Case
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
109/395
Ireland
Part D Standard Analytical Techniques- of thePublic Spending Code gives guidance on appraisalmethods and techniques, including financialanalysis and economic cost-benefit analysis -http://publicspendingcode.per.gov.ie/d-standard-analytical-techniques/
Sector specific guidance developed for keyinfrastructure, e.g., National Road Authoritys2011 Project Appraisal Guidelines -http://www.nra.ie/policy-publications/project-appraisal-guideli/ - and supporting parametervalues
Methodological Guidance
30
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
110/395
1. Introduction and background2. Overview of appraisal and [ ex post]
evaluation
3. Justifying action [including reasons forgovernment intervention]
4. Setting objectives: objectives,
outcomes and outputs5. Appraising the options
a. Creating options
b. Valuing the costs and benefits of options
c. Adjustment to values of costs and benefits
d. Discounting [including specification of
discount rate
31
UK Green Book: Appraisal and Evaluationin Central Government
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
111/395
Ireland
Strong proportionality in the use of assessmenttools [see next slide]:
The complexity of the appraisal or evaluation of aproject or programme and the methods used willdepend on the size and nature of the project orprogramme and should be proportionate to itsscale. The resources to be spent on appraisal orevaluation should be commensurate with the likelyrange of cost, the nature of the project orprogramme and with the degree of complexity ofthe issues involved.
United Kingdom
Proportionality in the Application of Assessment Tools
32
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
112/395
Ireland: Proportionality in Use of Assessment Tools
Project Value (Minimum) Type of Assessment
< !0.5 million Simple assessment for minorprojects, such as those involvingminor refurbishment works, fit-outs, etc.
> !0.5 million < !5.0 million Single appraisal (combiningelements of Preliminary Appraisaland Detailed Appraisal)
> !5.0 million < !20.0 million Multi-criteria analysis of options
> !20.0 million Cost-benefit analysis or cost-effectiveness analysis (dependingon the extent to which benefits canbe readily monetised)
33
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
113/395
Basic Appraisal Criteria
! Is it clear why the government needs to act?
! Does the proposal meet with thegovernments published policies and priorities,and with sector strategies?
! Is it clear what actual needs (rather thandesires) the project is designed to meet, and
how the projects outputs can be expected todo this?
! Have the objectives and expected results ofthe proposed project been expressed clearly ina manner that is measureable and time-bound?
! Are the claimed benefits realistic?
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
114/395
Appraisal Summary Table Dateproduced:
Contact:
Name of scheme: Name
Description of scheme: Organisation
Role Promoter/Official
Impacts Summary of key impacts Assessment
Quantitative Qualitative
Monetary
Distributional
(NPV) 7-pt scale/vulnerabl
e grp
Economy
Business users & transport providers Value of journey timechanges()
Net journey time changes ()
0 to2min
2 to5min
> 5min
Reliability impact on Business users
Regeneration
Wider Impacts
Environment
al
Noise
Air Quality
Greenhouse gases Change in non-traded carbonover 60y (CO2e)
Change in traded carbon over60y (CO2e)
Landscape
Townscape
Historic Environment
Biodiversity
Water Environment
Social Commuting and Other users Value of journey timechanges()
Net journey time changes ()
0 to 2 to
35
UK: Appraisal Summary Table for Transport Projects
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
115/395
Optimism Bias
Optimism bias is a systematic tendency forproject costs to be under-estimated and forproject benefits to be over-estimated.
Research found significant cost over-runs andtraffic shortfalls in a large (200+) sample of
major transportation projects, irrespective ofcountry, continent or transport mode, and withno tendency to diminish.
9/10 projects had cost over-runs: average(real) cost over-run was 45% for rail, 34% for
bridges and tunnels and 20% for roads.
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
116/395
UK: Adjustment Factors for OptimismBias
Project Type Historical Average % Increase at OutlineBusiness Case
Capital Expenditure Works Duration
Standard buildings 24% 4%
Non-standardbuildings
51% 39%
Standard civilengineering works
44% 20%
Non-standard civilengineering works
66% 25%
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
117/395
Ireland
If the value of the capital project exceeds !20mthen the CBA (or CEA) is submitted to the CentralExpenditure Evaluation Unit (CEEU) for theirviews prior to approval in principle by theauthority responsible for approving the project.
The CEEU gives its views to the agency
sponsoring the project and may publish theirreview of the CBA (or CEA) on their website.
United Kingdom
Business cases for projects above delegated limitsmust be reviewed and approved by the economic
and finance ministry at key decision points.
Examples of Independent Review
38
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
118/395
UK: Gateway Review Process
Peer review of a project carried out byindependent experts who are external to theproject and the implementing agency
Initiated as part of 2007 procurement strategy,Transforming Government Procurement
5 stage review: Business Justification (SOBC)
Delivery Strategy (OBC)
Investment Decision (FBC)
Readiness for Service
39
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
119/395
Independent Assessment: S. KoreasPreliminary Feasibility Study (PFS)
Short and brief evaluation of a project to produce information for budgetary
decision
Owned by the Ministry of Planning and Budget (MPB) and managed byPIMAC
While (detailed) feasibility study analyzes technical aspects of a project indetail, PFS emphasizes broader analysis of a project from a national socio-economic viewpoint.
Meaning of PRELIMINARY is two-folded:
Provisional, or short and brief; and
PFS costs about 80~100 million Won, and takes about 6 months; DetailedFS costs about 300 million to 2 billion Won.
Preceding a (detailed) feasibility study
The National Finance Act of 2006 provides the legal basis of PFS.
40
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
120/395
41
Coverage of PFS
All new large-scale projects with total costs amounting to 50 billion Won
(about USD 50 million) or more are subject to PFS.
Local government and PPP (Public-Private Partnership) projects are alsosubject to PFS if central government subsidy exceeds 30 bill Won.
Initially focused on economic infrastructure, PFS has expanded to socialinfrastructure and non-infrastructure (e.g. R&D, welfare) programs.
Projects with little benefit of PFS are exempted
Typical building projects: government offices and correctionalinstitutions
Legally required facilities: sewage and waste treatment facility
Rehabilitating projects and restoration from natural disaster
Military facilities and projects related with national security
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
121/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
122/395
Flowchart of PFS Analyses
Project proposal
Review of statement of purpose Collect socio-economic, geographic, and
technical data Brainstorming (Other Alternatives) Issues to be addressed
Background study
Consistency with higher-level plan
and policy directions Project risk (financing and
environmental impacts) Project-specific evaluation item
Policy analysis
Demand analysis Cost estimation
Benefit estimation Cost-benefit analysis Sensitivity analysis Financial analysis
Economic analysis
Overall feasibility Recommendations
Analytic Hierarchy Process
Regional backwardness indexanalysis
Regional economic impactanalysis (IRIO Model)
Balanced regional developmentanalysis
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
123/395
Review of Appraisal Decision
Ireland Approval to Proceed to Tender by Sanctioning
Authority after verification that project asdesigned is consistent with Approval inPrinciple
Check on continued validity of appraisaldecision based on tender prices
United Kingdom
Full Business Case prepared after tenderdecision and before contract signature
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
124/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
125/395
Screening vs Selection
Screening is a quality control process -identification & appraisal - that precedesbudgeting
Selection is done through a funding decisionmade through the budget/MTBF process
(depending on preparedness of project): Involves transparent prioritisation (usually within
sectors/sub-sectors)
Screening results taken into account, but fundingapproval should also be a portfolio decision drivenby practical and political factors
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
126/395
47
Integrating Project Screening and ProjectSelection
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
127/395
Advantages of MTBF for PIM
Predictability of MTBF gives a framework fordeveloping a project pipeline andprogramming implementation
Projects that pass preliminary screening can beprogrammed for outer years of MTBF
Preparation can be programmed Prepared projects with positive appraisal can
be programmed for implementation in budgetyear or later depending on fiscal space
48
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
128/395
Annual Roll-Over of MTBF
Previously identified project concepts movecloser to implementation
Preparation of screened concepts isprogrammed to precede opening up of fiscalspace for implementation
Projects ready for implementation (i.e., priorityprojects with positive appraisals and necessaryplanning approvals and documentation)proposed for funding in forthcoming budgetyear
Other new concepts enter the outer year of the 49
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
129/395
Advantages of PIM for MTBF
Good PIM can strengthen the MTBF MTBF ceilings cannot be set independently of
commitments to ongoing projects or of theproject pipeline
Sector ministries need to prepare baseline
capital expenditure programmes as an input toceiling setting
Importance of good financial monitoring andaccurate forecasting of project completionrates
50
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
130/395
Project Selection Criteria
Alignment of the project with Governmentsexpressed national spending priorities and withsector investment plans.
Priority Government attaches to improvingservices to the target beneficiaries of the
project. Consistency of the proposed spending with the
balance of spending between different sub-sectors within its sector.
Indications that the project will deliver better
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
131/395
Capital Budgeting in Ireland
Performance-oriented budgeting andmanagement are intended to provideappropriate incentives and accountability sothat projects are selected in line with nationaland sector policy priorities.
Similarly, accountability arrangements fordelivering public sector outputs discouragebudgeting of new projects at the expense ofongoing projects.
Prioritisation criteria established in medium- to
long-term strategic planning documents,
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
132/395
Gate-keeping and Project Selection in Chile
Legal provisions prevent unscreened projectsfrom entering the budget
Projects must have come through the NationalInvestment System and
Have a positive assessment from the Ministry ofPlanning
Congress cannot add projects to the budget
Spending agencies have portfolios of positivelyappraised projects greater than their fundingallocations
53
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
133/395
Capital Budgeting in Botswana and South Africa
Ministries budget within capital ceilings Structured negotiation process for finalising
ceilings
Distinction between budget for ongoingprojects - capital baseline - and new projects
Finance ministries challenge line ministryprioritisation decisions
In Botswana projects must be in NDP;Parliament approves total estimated cost ofproject not annual allocation - and annual
ceiling for ministry capital spending, allowing
54
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
134/395
Project Implementation
& Monitoring
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
135/395
Implementation & Monitoring
Tendering and contracting Agreed resources used to carry out project
activities and deliver outputs
Financial reporting
Periodic checks to assess progress and enable
adjustments Capital programme monitoring and updating
Systematic and regular information flows fromproject implementers to management anddecision makers
Simon Groom 56
N.B. Without good projectimplementation plans monitoring
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
136/395
Ireland: Project Management Structure
Sanctioning Authority: on basis of monitoringreports must satisfy itself that project is beingdelivered within specified costs, to specifiedstandards and on time
Sponsoring Agency: overall responsibility forproper management of project; makes legalcommitment with contractor
Steering Group: oversees the execution of theproject; usually chaired by Sponsoring Agency
Project Coordinator: person responsible forensuring project is executed on time, to the
Simon Groom 57
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
137/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
138/395
UK: Assurance Process
Independent view of how a project isprogressing.
Involves checking that: The project remains viable in terms of costs and benefits
(business assurance)
Users requirements are being met (user assurance)
The project is delivering a suitable solution (technicalassurance).
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
139/395
Project Monitoring, Re-assessment andAdjustment in S. Korea
Total Project Cost Management System(TPCM)
Used to monitor closely the total cost of majormulti-year projects and to prevent significantcost escalation
Strict principles limiting the justifications forcost increases and the authority to agree tosuch increases.
Re-assessment of Demand Forecast (RDF)
Demand forecasts for major projects are re-
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
140/395
Evaluation & Audit
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
141/395
Evaluation & Audit
Completes the project cycle Project results assessed compared to what was
planned as with monitoring, if projectplanning is weak evaluation becomes difficult
Ex post studies to assess economy, efficiency,
effectiveness and sustainability compared to exanteassessments
Lesson learning for design and implementationof similar projects
Procedures need to be in place to apply lessons
Internal evaluations su lemented b selective
62
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
142/395
Ireland: Post-Project Reviews
All projects >!20 million; at least 5% sampleof the rest
Carried out by project Sponsoring Agency
Those conducting reviews and evaluationsshould not be the same people as conducted
the appraisal or managed the implementation To determine whether:
The basis on which a project was undertakenproved correct;
The expected benefits and outcomes materialised;
63
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
143/395
UK National Audit Office
Independent body reporting to Parliament
Reports used by Public Accounts Committeewhich holds hearings and then reports toParliament
NAO has no judicial or administrativeauthority
Central government spending only
Legally empowered to carry out performanceaudits; does this on a (small) sample basis witha focus on problem or innovative projects
64
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
144/395
NAO Performance Audit of FiReControl Project
Project to replace 46 local control centres with9 regional centres and improve the efficiencyand resilience of fire and rescue services
Project stopped before completion at a cost of469 million: nothing to show but 8 desertedbuildings with limited alternative uses
Findings Lack of consultation at project concept and design
stage stakeholders didnt want the project!
Project launched too quickly without adequatepreparation - unrealistic forecast costs andsavings, nave over-optimism on the deliverability
65
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
145/395
FiReControl Project: Recommendations
Follow proper business case approvalprocedures and ensure that an appropriate levelof challenge is applied to the approval process
Follow proper project and programmemanagement procedures and ensure staff hasright skills
All its future contracts contain terms andconditions which clearly define responsibilitiesand outputs
Clearly identify roles and responsibilities and
66
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
146/395
NAO Guidance
Delivering successful IT-enabled businesschange: Case studies of 9 successful projects,including: Modernisation of welfare payments system,
London congestion charging
e-procurement system
Guide to initiating successful projects,including 5 examples of good project planning,including: 2012 Olympic Games
Building programme academies - for new type of
school
67
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
147/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
148/395
!"#!$
!"#$%&%#!%
'() +,-./01 $203)4,25 6772,0/( 8,2 9() :);.- #" 6/4#"!#"&58 &-5#'&564 "87!#/787,&5565-987, #" 5*8 26A8N 4#/9656#/: O-" !&"8/57 !"#%"&''89 -7 5# "87!845 #-" 8298"71 ()*+)#, &'3*$"&3+ ,*)0 $"#3 0&$"0) # 4#)+0 &3$0+)#$0/ 2)*905$ *) # '0$ :*) 2*)$1*4&*; *1 2)*905$'< P*8!"#%"&' '&/&%8" *&7 #8 &4*68M !"#? (*'$ ("#'0()0@&360'$,03$ ("#'0
Y/9 #3
8? (*'$ ("#'0
A0'&+3
("#'0
Z"#%"&'
984676#/
=360'$,03$ ()*905$'
B*60)3,03$#4 ()*+)#,'
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
150/395
!"#!$
!"#$"%%&$"# ()*%"#$%&'%( ()$*&
+,-.*'(/#01223 +45 ",)#/6789*':$;
+%,- .,/%0> ?$@/'%(#,% A+B C"7B D/9 E9%#$(,%B F'G99H9*. 8,*%'%( ()$*&@ I9*9 &'@#*'J)#9& $K,%( #/9
:,**'&,*@B L%:9 $ @9*(9$%# $@G9&M ?/. $*9 I9
K9$H'%( ,%9 ()$*& '% N*,%# ,N #/'@ :K,@9& &,,*O D/9
&,,* ,-9%9& '%#, $ @8$KK @#,*$(9 *,,8B P, ,%9
G%9I $% $%@I9*B D/9 ,%K. *9@-,%@9 I$@M ?9
$KI$.@ /$H9B
D/9 -9*@'@#9%# @9*(9$%# G9-# *9@9$*:/'%(B 7N#9* $
:,)-K9 ,N 8,%#/@ #/9 N'%$K :,%:K)@',% I$@ #/'@M !"
$%&$ '()*"+ ,-. /0).1" 21) 1 +.".)13 (4.' ,-1,
055*6. ,0 7..8 *980),1", :1) '06(9.",4 1"' 147.'
1 +(1)' ,0 ;. 3.5, *" 5)0", 05 ,-1, '00)B
D/$# I$@
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
151/395
!"#!$
!"#$"%&' ) *+, #- "+.%,+/ 0"#1+2,*
!" $%&'()* *"$(
!"#$%&' )$#'*+*",'-#.
//
0&'-#*121-$#1"3 45
6*$13$7' /8
9"&1: 2&""* ;85
/
?'$@ >4
AAB ;;C!*"-=*'D'3# 5E>
H
I"#$& ;J8/8 +*",'-#.()*+,-./01"!!2 (34 5)60/#789,-:; 2
!""! $%&'()&
!"#$"%&' 3#24%. !"#1+2, 54,6#7,48-"%*,"72,7"+
()*+,-./01"!!2 (34 5)60/#789,-:;# '&&3
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
153/395
!"#!$
!"#$%&' )*+ ,&-#-*$
!"#$%&%'%() +,- &"."'%/"& 01 2343 5) ,
6%1-7'#01( 809: 8%9 ;?
@,#"9 ,&%/#"& 5) ABC 01 0#- CDEE ."-/01&"-*$"-&$- ,&%2-3$ ,/)*4*5
F799"1#') 7-"& 5)G
H01,160,' 01-#0#7#0%1- I>?JK =?JK LJM
>1#"91,#0%1,' D9(,10N,#0%1- I;ODM
=("160"- I;?K =7-=>?K F>?=K ODP=?MF%71#90"- IF$0'"K F%'%:50,K !"Q06%K R79%/",1 ;10%1M
)*+,-./012"!!3 )45 6*710#89:-.;
#$% &'()*+,-$%*(%
$+)./%'.+,, ,0%
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
156/395
!"#!$
!"#$%&'() !+,-./)&0 123%&4/%(
!" $%& '% (%) *+,-.+$ /',()/"$ )0, 1.%2+,3 )% 2, 4%+5,' -(' )0, 6%-+4to be achieved, you'll be immersed in a sea of immobility for long)/3,7777
!!! #$%&'( )*+, -./ 0'$$ 1'2 3$'+4'2 56%&6 5+- 7 ./860 0. 8. 9:.1 6':'; "1 8.%,8 0. ?!) @+%= #$%&'! )7, 06%4 &+4'2 %0 =.'4 ,.0 1+00': 56%&6 5+- -./ 8.2)4+%= 06' *+0! *+::.$ A'5%4
829,*)/5,4 -(' 6%-+4
!"#$ &' $"( )*+&,#- ./#0(1*/2 3#$/&45
!"# %& ' &()'(*+%, -.'//%/+ (00. 10) -)0+)'2& '/3-)04*,(&
!"# &()*/+(5*/& (5* -)*-')'(%0/ '/3%2-.*2*/('(%0/ 01 -)0+)'2& '/3 -)04*,(&6
!"# &722')%8*& (5* 2'%/ )*&7.(& 01 (5* -)*-')'(%0/01 (5* -)0+)'2 0) -)04*,(6
!"# -)09%3*& ' :'&%& 10) &,5*37.%/+ 01%2-.*2*/('(%0/ -5'&*
!"# 1',%.%('(*& 20/%(0)%/+; ,0/()0. '/3 *
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
157/395
!"#!$
!"#$ $"& '()*+#, -.#/&0(.1 2#$.*3 *4 7
!"# %& '()*+ ,-.*+/, ,0*12*/%3+ 34 5637,8/& 3656396*:& :,/;3
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
158/395
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
159/395
!"#!$
!"#$%&' ) !"#*"+, !-".#/%
!"#$%&'()*+,,- !/0 1"2)(3456%&78+9
01%"+22
03$%&'41%/
!"#$%&'
!-".#/%
5#,.#6%6'/
0-'.-'/
7&'414'4%/
89+' :# ;#- 9#.% '# +&,.24/9 )( 78%6D %67%68)&"? 8?=
65")&"?8> ;2##"%) &? )(6 6>=6%>$
?2%;&?' ("56;
M>=6%>$ #%";)%8)6 8?= ;65&3
#%";)%8)6 L(" %676&E6= ("2;&?'D
@""=D #%&58%$ (68>)( 78%6D
%67%68)&"? 8?= 65")&"?8> ;2##"%)
&? )(6 6>=6%>$ ?2%;&?' ("56;
16?&"%; %676&E&?' 568>;D
%67%68)&"? 8?= #%&58%$ (68>)(
78%6 &? K#6? !6?)6%;
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
160/395
!"#!$
!"#$%&&
!()#*+,"#-
.$/)#*+
.0$1/-#
2/31/4#4+-
!0+10+-
5*+,",+,#-
!()#*+,"#-6 5*+,",+,#-
!"#$%&'()*+,,- !/0 1"2)(3456%&78
7/8 %$# +9# */31/4#4+-
:/,4: +/ (# 1$/;0*#;1@ 1A=)
)*&56,7 >4,'$%3%-"$%&'
!"#$%&'( %*# +,-./#01 -' %*# 2$2/(3#" 1&%42%&-$
5-641 %*# 2$2/(1&1 -$ %*# 02&$ &114#
5-,04/2%# %*# +,-./#0 21 2 $#72%&8# 1%2%#0#$%
9- $-% 6-$'41# %*# +,-./#0 :&%* 2 /26; -' 1-/4%&-$
)*+,-./012"!!3 )45 6*710#89:-.;< ="
>7:&*$"'$ /#%4,6%',0B
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
164/395
!"#!$
!" $%&'' ()(*$!'(
!!!"#$%&'() !+,-./)&0 123%&4/
+,-./0,1/2,34 56578,-5
#$%&'()*+,-../ #01 2$3+*4567'(89 !:
5"6 )" 7&89/:&;3 8944388 &) (/8 H34"23 /
2&DD:3 &04"23 4"90)%$> )(/0E8 )" #3"#:3 :&E3 $"9F G"9% 4"90)%$ &8
"03 "= )(3 I363:8 "= 1=%&4/F
J%&)3 D"60 )(3 D384%)&"0 "= $"9% 4"90)%$ &0 )(/) =9)9%3K 5"6 D"
$"9 833 &)< 5"6 /%3 )(3 4&)&38> )(3 =/2&:&38> )(3 03&'(H"%(""D8> )(3%"/D8> )(3 &0=%/8)%94)9%3> )(3 84("":8> ("8#&)/:8> 3)4F
2&DDA3 &04"23 4"B0)%$ E&)( )(3 F"AA"E&0' F3/)B%39G
?"4&/AA$> 34"0"2&4/AA$ /0D #"A&)&4/AA$ 32#"E3%3D E"230 4"0)%&@B)&0' )"
0/)&"0/A D3C3A"#230) &0 C/%&"B9 F"%29
HB0'3% &9 3%/D&4/)3D
.399 )(/0 =I "F #3"#A3 933J&0' K"@9 E"BAD @3 E&)("B) E"%J
LC3% M
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
166/395
!"#!$
!"##$%&$' )*%+$,%
!"$%&'()*+, $-./01,)2 345()61
7' 89!:; 5 ,+5 ?%@@%A)2* ?51,B(5=C
32 )2D5&52D52, 12D 1665==)E@5 FBD)6)1(' 52F%')2* ,+5 6%2?)D5265 %? ,+5
&5%&@5
3 ='=,54 %? &%@),)61@ *%>5(21265 A+5(5 *%>5(2452,= 1(5 >%,5D )2 12D
%B, %? &%A5( &5165?B@@'; 12D A+5(5 6),)G52= 612 +%@D *%>5(2452,= ,%
166%B2, ?%( 5??)6)52, 12D 5??56,)>5 D5@)>5(' %? &BE@)6 =5(>)65=
3 4%D5(2 12D A5@@ D5>5@%&5D )2?(1=,(B6,B(5 A),+ (5@)1E@5 525(*' =B&&@)5=
H%(@D 1,5 =56,%(/@5D *(%A,+; 6(51,)2* >1@B5/1DD5D &(%DB6,=; 12D &(%>)D)2*
F%E= ?%( %B( &5%&@532 5??56,)>5 52>)(%2452,1@ 4121*5452, ='=,54 )2 &@165 ,+1, &(%,56,=
%B( E)%D)>5(=),' 12D )= 61&1E@5 %? &(5/54&,)2* 52>)(%2452,1@ D)=1=,5(=
I% E5 1 4%D5@ )2 (5=&%2=)E@5 12D 5??)6)52, 21,B(1@ (5=%B(65 5J&@%),1,)%2
-*#.*$$,.*# /01$N(56)=5 )2?%(41,)%2 >=O -5@5>12, )2?%(41,)%2-22.3.$*34 5%6 -22.3734
()*+,-./01"!!2 (34 5)60/#789,-:;
-
8/11/2019 The Capital Budgeting Process Workshop Training Materials
167/395
!"#!$
!"#$%&'() !+,-./)&0 123%&4/ ($
!"#$% '() *(+ '()+
%,$- #../$.,($ 0
1)/2.,($23
4($.#5. 6/.#,72
8+(*9 :-;#+-( ,5#5/467)/8 83 ,0'30&3%9/ $ !&304&/:
;0&?@3A
1
-
8/11/2019 The Capital Budgeting Process Wo