the centre for medicine, university of...
TRANSCRIPT
![Page 1: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/1.jpg)
THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER
Scaling Up Passivhaus
Jon Chadwick
![Page 2: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/2.jpg)
Predicted Performance
U-values: Walls 0.13W/m²/k
Roof 0.13W/m²/k
Floor 0.13W/m²/k
Airtightness: 1m³/m²/hr @ 50Pa
Equates to: 0.33 ac/h
![Page 3: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/3.jpg)
The Design Team
Project Managers
Architect and Lead Consultant
M+E Engineers
Passivhaus Designers
Structural and Civil Engineers
Cost Consultants
Project Managers
Cost Consultants
Technical Advisor
Main Contractor
Passivhaus Designers
Architect and Lead Consultant
Structural and Civil Engineers
Passivhaus Consultants
Pre
Co
ntr
act
Po
st C
on
tra
ct
Client
Clie
nt’s
Re
tain
ed
Co
nsu
ltan
ts
Design Advisor
Co
ntr
act
or’
s D
esi
gn
Te
am
M+E Subcontractor
![Page 4: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/4.jpg)
An Overview of the 2011 Client Brief:
• Bring together the Schools of Medicine, Health Sciences and Psychology
• Adjacent to the existing medical building
• Sensitive to context – ecology and heritage
• Contribute towards reducing the University’s carbon footprint – passive design
• Allow the existing building to be upgraded in the future
• 13,000sqm of teaching, research and support spaces for 2,400 occupants
• Range of flexible teaching spaces with potential for conference use
• Deliver the building by September 2015
![Page 5: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/5.jpg)
Background Site Information – Regent College Site
![Page 6: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/6.jpg)
• Locally listed building (Regent College)
• ‘Conservation Area’ and listed ‘Fire Station Cottages’
• Protected trees on site boundary
• Protected views towards the War Memorial
• Risk of overshadowing adjacent buildings
• Loss of open space & playing fields
• Ecological impact
• Concerns over car parking provision
• Bomb shelter & potential archaeology
• Demolish bomb shelter - provide new football pitch
• Increase site biodiversity
• Respect Regent College
• Face the University and mark the start of the campus
• Provide an efficient plan form
• Maximise passive measures
Planning Issues
Design Approach
![Page 7: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/7.jpg)
1. 2. 3. 4.
Finger Blocks Rotate 45
Degrees
Aligned to South &
College
Façade Respond to Sun
• Square block responds
to site boundaries.
• Split block up allowing
views through into site.
• Narrow floor plate to
max daylight.
• Landscape planted
through building gaps.
• Stepped heights of
blocks high to Uni Rd.
• Rotate blocks to
face directly south.
• Orientation best
to control solar
gain.
• Building faces the
corner legible
entrance!
• Blocks turn back on
College grid into site
responding to context.
• Rotation provides a
pedestrian arrival
space and separate
service zone.
• Prickly façade
animates building
protection from
solar gain.
Co
nce
pt
– P
lan
Fo
rm
![Page 8: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/8.jpg)
High Level View from the Roof of MSB
![Page 9: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/9.jpg)
Pro
po
sed
Site
La
you
t
Regent College
Proposed Site
Re-located
Football Pitch
Future
Extension
Lancaster Road
MSB
![Page 10: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/10.jpg)
![Page 11: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/11.jpg)
GAHE Labyrinth (change to vent towers)
Efficient AHUs with Heat Recovery (distribution within ceiling voids of occupied floors only)
Highly insulated cavity wall to lower floors
Full curtain walling with brick slip panels (concrete backing panels for thermal mass))
Contractor’s Proposals – Environmental Proposals Plant rooms brought inside Passivhaus ‘TFA’
Changed to insulated render
Active external shading blinds (continuous blind box detail as part of curtain wall façade)
![Page 12: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/12.jpg)
Changes to Façade Construction – Upper Floors
• Unitised curtain walling windows between precast brick slip clad panels
• Air seals on all four sides
• Opening vent panel behind fixed louvre
• Individual blind box for each window
• Thermal mass
Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips
• Full curtain walling façade – storey height screens
• Brick slip panels fixed to insulated metal panels
• Reduced requirements air seals
• Opening vent panel behind fixed louvre
• Continuous blind box around slab perimeter
• Thermal mass replaced by non-structural infill
![Page 13: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/13.jpg)
Changes to Façade Construction – Upper Floors
• Single subcontractor responsibility
• Easier construction
• Faster programme
• Tighter tolerances
Pros:
Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips
![Page 14: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/14.jpg)
Changes to Façade Construction – Upper Floors
• Planning risk
• Additional movement joints
• Risk of interstitial condensation
• Additional seals / VCLs required
• Overall façade zone increased ~150mm
• Greater coordination with PT frame
Cons:
Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips
![Page 15: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/15.jpg)
External Shading Blinds
• CTB blinds - not used before in UK
• UoL nervousness about maintenance
• Automatic operation – linked to BMS
• Automatically retract in high winds
• Tender design - small sections
• Contract - continuous ‘ribbon’
• Blind box - thermal weak link
![Page 16: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/16.jpg)
Façade Construction – Lower Floors
![Page 17: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/17.jpg)
Façade Mock-up Panel
![Page 18: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/18.jpg)
Façade Mock-Up Panel
![Page 19: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/19.jpg)
Tender:
Roof top plant rooms outside thermal envelope
Basement plant room inside the thermal envelope
Contract:
All plant rooms inside thermal envelope
Increased ‘Treated Floor Area’
Ventilation duct runs – inside thermal envelope
Simplification of scheme
Thermal Envelope
![Page 20: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/20.jpg)
Cold Duct Runs
•Extensive cold duct runs within envelope
•Plant room layouts changed to minimise cold duct runs
•Suitable AHUs – not available as PH certified products
![Page 21: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/21.jpg)
Thermal Bridging
• Minimising thermal bridging is crucial
• Couldn’t all be eradicated or calculated prior to contract
• Schedule of thermal bridges compiled
• WDES did thermal modelling
• Pile caps insulated on all sides, piles not insulated
• Thermal pads included on all steelwork connections
• GRC cladding changed to insulated render
![Page 22: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/22.jpg)
Ground-Air Heat Exchanger
• Redesigned to ease construction
• GAHE located beneath the building
• Extensive coordination – design period increased
• Vent towers integrated into ‘dummy’ columns
• Verifying the efficiency of the system to suit PHI
• Very deep excavations
• Installation took longer than anticipated
![Page 23: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/23.jpg)
08 September 2014
![Page 24: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich](https://reader031.vdocument.in/reader031/viewer/2022022605/5b7715d57f8b9a3b7e8cdb16/html5/thumbnails/24.jpg)
Conclusions
• On track - September 2015 and Passivhaus certification
• Difficulties sourcing products to suit the aesthetic
• Lack of Passivhaus knowledge and experience amongst contractors
• PHPP proved a useful design tool
• Effective communication of key design requirements - ?
• Site supervision - ?
• Increased capital costs for Passivhaus have fallen
• Achieving DEC A will be a challenge