the centre for medicine, university of...

24
THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER Scaling Up Passivhaus Jon Chadwick

Upload: vominh

Post on 18-Aug-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER

Scaling Up Passivhaus

Jon Chadwick

Page 2: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Predicted Performance

U-values: Walls 0.13W/m²/k

Roof 0.13W/m²/k

Floor 0.13W/m²/k

Airtightness: 1m³/m²/hr @ 50Pa

Equates to: 0.33 ac/h

Page 3: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

The Design Team

Project Managers

Architect and Lead Consultant

M+E Engineers

Passivhaus Designers

Structural and Civil Engineers

Cost Consultants

Project Managers

Cost Consultants

Technical Advisor

Main Contractor

Passivhaus Designers

Architect and Lead Consultant

Structural and Civil Engineers

Passivhaus Consultants

Pre

Co

ntr

act

Po

st C

on

tra

ct

Client

Clie

nt’s

Re

tain

ed

Co

nsu

ltan

ts

Design Advisor

Co

ntr

act

or’

s D

esi

gn

Te

am

M+E Subcontractor

Page 4: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

An Overview of the 2011 Client Brief:

• Bring together the Schools of Medicine, Health Sciences and Psychology

• Adjacent to the existing medical building

• Sensitive to context – ecology and heritage

• Contribute towards reducing the University’s carbon footprint – passive design

• Allow the existing building to be upgraded in the future

• 13,000sqm of teaching, research and support spaces for 2,400 occupants

• Range of flexible teaching spaces with potential for conference use

• Deliver the building by September 2015

Page 5: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Background Site Information – Regent College Site

Page 6: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

• Locally listed building (Regent College)

• ‘Conservation Area’ and listed ‘Fire Station Cottages’

• Protected trees on site boundary

• Protected views towards the War Memorial

• Risk of overshadowing adjacent buildings

• Loss of open space & playing fields

• Ecological impact

• Concerns over car parking provision

• Bomb shelter & potential archaeology

• Demolish bomb shelter - provide new football pitch

• Increase site biodiversity

• Respect Regent College

• Face the University and mark the start of the campus

• Provide an efficient plan form

• Maximise passive measures

Planning Issues

Design Approach

Page 7: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

1. 2. 3. 4.

Finger Blocks Rotate 45

Degrees

Aligned to South &

College

Façade Respond to Sun

• Square block responds

to site boundaries.

• Split block up allowing

views through into site.

• Narrow floor plate to

max daylight.

• Landscape planted

through building gaps.

• Stepped heights of

blocks high to Uni Rd.

• Rotate blocks to

face directly south.

• Orientation best

to control solar

gain.

• Building faces the

corner legible

entrance!

• Blocks turn back on

College grid into site

responding to context.

• Rotation provides a

pedestrian arrival

space and separate

service zone.

• Prickly façade

animates building

protection from

solar gain.

Co

nce

pt

– P

lan

Fo

rm

Page 8: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

High Level View from the Roof of MSB

Page 9: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Pro

po

sed

Site

La

you

t

Regent College

Proposed Site

Re-located

Football Pitch

Future

Extension

Lancaster Road

MSB

Page 10: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich
Page 11: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

GAHE Labyrinth (change to vent towers)

Efficient AHUs with Heat Recovery (distribution within ceiling voids of occupied floors only)

Highly insulated cavity wall to lower floors

Full curtain walling with brick slip panels (concrete backing panels for thermal mass))

Contractor’s Proposals – Environmental Proposals Plant rooms brought inside Passivhaus ‘TFA’

Changed to insulated render

Active external shading blinds (continuous blind box detail as part of curtain wall façade)

Page 12: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Changes to Façade Construction – Upper Floors

• Unitised curtain walling windows between precast brick slip clad panels

• Air seals on all four sides

• Opening vent panel behind fixed louvre

• Individual blind box for each window

• Thermal mass

Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips

• Full curtain walling façade – storey height screens

• Brick slip panels fixed to insulated metal panels

• Reduced requirements air seals

• Opening vent panel behind fixed louvre

• Continuous blind box around slab perimeter

• Thermal mass replaced by non-structural infill

Page 13: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Changes to Façade Construction – Upper Floors

• Single subcontractor responsibility

• Easier construction

• Faster programme

• Tighter tolerances

Pros:

Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips

Page 14: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Changes to Façade Construction – Upper Floors

• Planning risk

• Additional movement joints

• Risk of interstitial condensation

• Additional seals / VCLs required

• Overall façade zone increased ~150mm

• Greater coordination with PT frame

Cons:

Tender: Precast Concrete Sandwich Panel CPs: Full Curtain Walling with Brick Slips

Page 15: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

External Shading Blinds

• CTB blinds - not used before in UK

• UoL nervousness about maintenance

• Automatic operation – linked to BMS

• Automatically retract in high winds

• Tender design - small sections

• Contract - continuous ‘ribbon’

• Blind box - thermal weak link

Page 16: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Façade Construction – Lower Floors

Page 17: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Façade Mock-up Panel

Page 18: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Façade Mock-Up Panel

Page 19: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Tender:

Roof top plant rooms outside thermal envelope

Basement plant room inside the thermal envelope

Contract:

All plant rooms inside thermal envelope

Increased ‘Treated Floor Area’

Ventilation duct runs – inside thermal envelope

Simplification of scheme

Thermal Envelope

Page 20: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Cold Duct Runs

•Extensive cold duct runs within envelope

•Plant room layouts changed to minimise cold duct runs

•Suitable AHUs – not available as PH certified products

Page 21: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Thermal Bridging

• Minimising thermal bridging is crucial

• Couldn’t all be eradicated or calculated prior to contract

• Schedule of thermal bridges compiled

• WDES did thermal modelling

• Pile caps insulated on all sides, piles not insulated

• Thermal pads included on all steelwork connections

• GRC cladding changed to insulated render

Page 22: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Ground-Air Heat Exchanger

• Redesigned to ease construction

• GAHE located beneath the building

• Extensive coordination – design period increased

• Vent towers integrated into ‘dummy’ columns

• Verifying the efficiency of the system to suit PHI

• Very deep excavations

• Installation took longer than anticipated

Page 23: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

08 September 2014

Page 24: THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTERukphc.org.uk/wp-content/uploads/2016/05/UKPHC14... · THE CENTRE FOR MEDICINE, UNIVERSITY OF LEICESTER ... Precast Concrete Sandwich

Conclusions

• On track - September 2015 and Passivhaus certification

• Difficulties sourcing products to suit the aesthetic

• Lack of Passivhaus knowledge and experience amongst contractors

• PHPP proved a useful design tool

• Effective communication of key design requirements - ?

• Site supervision - ?

• Increased capital costs for Passivhaus have fallen

• Achieving DEC A will be a challenge