The CMS ECAL Endcaps. UK Responsibilities Procurement and testing of VPTs Design and procurement of the VPT HV system Design/procurement of the mechanical structures Electronics systems integration SC and Dee assembly Test beam appraisal and analysis. EE front end readout. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/1.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
The CMS ECAL Endcaps
UK Responsibilities
• Procurement and testing of VPTs
• Design and procurement of the VPT HV system
• Design/procurement of the mechanical structures
• Electronics systems integration
• SC and Dee assembly
• Test beam appraisal and analysis
![Page 2: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/2.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
VPTs SC HV cardsUmbilical cablesEE Motherboards All delivered EE VFE cards EE FE cards Polyethylene moderator
EE front end readout
![Page 3: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/3.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Naked SC assembly rates
Naked SC assembly rate, per week
‘Naked’ SC assembly
All 14648 VPTs and crystals glued
All SCs completed(Monday of this week!)
16/wk
Nov OsC
![Page 4: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/4.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
SC assembly
Plot:Crystal deliveryNaked SC assemblyHV tested SCs
- All SCs HV tested and ready or mounted on Dees
Nov OsC
![Page 5: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/5.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Dee assembly – SC mounting
SC mounting
Dees 1-3 SC mounting completed
Dee4 completed by today, 23.5.081 Quad
1 Dee
Nov OsC
23 May 08
![Page 6: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/6.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Power cooling
Power cooling
2 of the 8 versions of ‘super cooling units’ needed per Dee
Each is a fully welded and tested system
The last 2 (of 32) have been completed this week and are undergoing pressure/leak tests A fully welded column of 2
cooling blocks
Super unit to be welded together
Transferframe
![Page 7: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/7.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Dee4
Dee4
As of Thursday, 9 left to mount
Expect mounting to be completed by Fri 23.5.08.
![Page 8: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/8.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Dee3
Dee3
HV looming completed
Moderator mounted
Stability fibres and LV mounted
Trigger mapping into readout motherboardscompleted (this photo)
![Page 9: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/9.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Dee2
Dee2 with its complete set of SCs Dee2All super cooling units mountedInstallation of VFE and FE cards underway
OPAL transfer frame to point
5
![Page 10: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/10.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Dee1
Dee1Fibre optic readout support panels in place, ready for final fibre optic routing
Dee1All electronics in placeAll towers tested and working
![Page 11: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/11.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
EE Assembly and Integration Status
Dee Assembly and Integration Status, 22.5.2008
Dees 1–3 All 10986 channels checked and OK for signal continuity
Dee1 Single tower readout – pedestal width on all channels ~2ADC counts in line with expectations for electronics noise of 3500-4000 electrons per channel
![Page 12: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/12.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
EE Risks
Insufficient ECAL effort (ED/ID)Continually monitored
New cooling schemeAt end of production
Electronics integrationGood progress, teams in place
Cable crimpsAll replaced, checked at each levelof subsequent integration
Fibre optic routing – possible delays/misroutingDatabase ready. Routing on Dee1 commencing
![Page 13: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/13.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
EE Risks (cont’d)
Installation and commissioning at point 5
ECAL installation and commissioning led by K Bell (RAL)Brings full experience from the mounting of the36 supermodules for the barrel ECAL
Point 5 installation and commissioning team establishedTeam involves CERN CMS (point 5) and CERN ECAL engineers and techniciansand a dedicated ECAL DAQ team
Weekly meetingsDetailed installation sequence in place, from surface of point 5 to mounting on HE
Commissioning will be carried out in sectors with close feedback from the DAQ/DQM teams
![Page 14: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/14.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Planning for EE
Dee1 and Dee2 at point 5, r.f.i. by 16 June 2008Dee3 and Dee4 at point 5, r.f.i. by 21 July 2008
![Page 15: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/15.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Conclusions
SC assembly and mounting on Dees (nearly) completed
Good progress with the installation of electronics and services on Dees 1-3
Dee1 and Dee2 to point 5 by 16 June
Dee3 and Dee4 to point 5 by 21 July
![Page 16: The CMS ECAL Endcaps](https://reader036.vdocument.in/reader036/viewer/2022062315/56815ae8550346895dc8ac15/html5/thumbnails/16.jpg)
UK CMS Oversight Committee Mtg 23.5.2008
STFCRAL
D Cockerill
Other info