THE CONCEPT OF THE AIR INTERCHANGE STATION FOR SAVING ENERGY IN THE HSUEHSHAN TUNNEL
Dr Horng-Cheh LeeChinese Taipei
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
Nankang Interchange
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
Shihting ViaductShihting Viaduct
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
Wutu Viaduct
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
Pinglin Viaduct
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007http://home.no.net/lotsberg/
data/tun10.html
Chinese Taipei
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
29.55m 29.55m
R=5.1m
R=2.105m
Main tunnel
Main tunnel
Pedestrian Cross Connection
Exiting Stair
Pilot Tunnel
The Relationship of Hsuehshan Tunnel and Pilot Tunnel
22
Cable TrayUpper : CCTV 、 communication 、 LCS、 CSLSMiddle 、 Low : Lighting 、 Fan cable
Fire detect pipeline
Coaxial Cable
CO/NO/VIDetector
Emeg LightingExit Sign
EXIT
7070
LEDExit Sign
Cable duct
22.8KV
380V/220V
TCTC
VentilationPower:2cicuits,Gen.UPSFire fighting:
–Extinguisher,HydranantLightingCommunication
RadioBroadcastLane controlCSLSCCTV
Layout of E&M Equipments
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
HSUEHSHAN TUNNEL VENTILATION SYSTEM- INTRODUCTION -The ventilation system of the Hsuehshan Tunnel is a longitudina
l ventilation system. The system contains three air exchange stations and three air interchange stations. At each air exchange stations the polluted air in each tube is exchanged for fresh air using separate fresh and exhaust air shafts. At each air interchange station the air in one tube is diverted into the other tube. This interchange of air between the two tubes permits the heavily polluted air in one tube is replaced with lightly polluted air from the other tube while the lightly polluted air in one tube is replaced with heavily polluted air from the other tube.
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
HSUEHSHAN TUNNEL VENTILATION SYSTEM- FLOW DIAGRAM -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
HSUEHSHAN TUNNEL VENTILATION SYSTEM- LAYOUT OF VENTILATION SYSTEM -
1. AXIAL FLOW FAN
– Air Exchange Stations
Supply Air Fans: 12 sets (4 sets per each station)
Exhaust Air Fans : 12 sets (4 sets per each station)
– Air Interchange Stations
Air Interchange Fans : 12 sets (4 sets per each station)
2. JET FAN
112 sets (56 sets per each tube)
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM- WHY USE AIR INTERCHANGE STATION (1/2) -
1. Longitudinal Ventilation System Without Air Interchange Station Maximum Fan Capacity: 100%+47%=147%
2. Longitudinal Ventilation System with Air Interchange Station Maximum Fan Capacity:100%+24%=124%(The peak traffic in each tube would not happen simultaneously)
Ventilation Flow
Peak Traffic in North bound
Peak Traffic in South bound
North bound Tube (Uphill) 100% 62%
South bound Tube (Downhill) 24% 47%
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007
1. Longitudinal Ventilation System without Air Interchange Station
North bound Tube : 5 Ventilation Shafts
South bound Tube : 2 Ventilation Shafts
2. Longitudinal Ventilation System with Air Interchange Station
Northbound Tube : 3 Ventilation Shafts
Southbound Tube : 3 Ventilation Shafts
BENEFITBENEFIT : To Reduce Quantity of Ventilation Shafts
HSUEHSHAN TUNNEL VENTILATION SYSTEM- WHY USE AIR INTERCHANGE STATION (2/2) -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM
- PLAN LAYOUT OF AIR EXCHANGE STATION -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM
- SECTION OF AIR EXCHANGE STATION (SUPPLY) -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM- SECTION OF AIR EXCHANGE STATION (EXHAUST) -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM- PLAN LAYOUT OF AIR INTERCHANGE STATION -
TPT-WG29, Chinese Taipei
29th APEC Transportation Working Group Meeting, Chinese Taipei, 9-13 July 2007HSUEHSHAN TUNNEL VENTILATION SYSTEM
- SECTION OF AIR INTERCHANGE STATION -