the critical path method

19
The Critical Path Method The Critical Path Method Presented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter June 20, 2002 San Juan, Puerto Rico

Upload: zamri-nasir

Post on 21-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

Flight Management

TRANSCRIPT

Page 1: The Critical Path Method

The Critical Path MethodThe Critical Path MethodPresented by Antonio Prensa, MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter

June 20, 2002San Juan, Puerto Rico

Page 2: The Critical Path Method

"I believe that this nation should commit itself to achieving a goal, before this decade is out, of landing a man on the moon..." - John F. Kennedy,May 27,1961

Page 3: The Critical Path Method

On July 20, 1969, just eight years after Kennedy's speech, Apollo 11 landed two men on the moon. This achievement was possible only with careful production planning that included the critical path method.

NASA used the critical path method to help determine an efficient schedule for the tasks that led to the moon landing.

Page 4: The Critical Path Method

Discussion Topics

BackgroundSome questions about the projectWhat is the Critical Path Method (CPM)?Why the CPM?How to use the CPM ?Questions and Answers

Page 5: The Critical Path Method

Background

The critical path method (CPM) was invented by project managers in the early 1950's. The US Navy adapted and improved it to manage the Polaris missile project in the late 1950's

Page 6: The Critical Path Method

Some questions about the project

How long will the entire project take to complete? Which activities determine total project time? Which activity times should be shortened, if possible, or in other words, how many resources should be allocated to each activity?

Page 7: The Critical Path Method

What is the CPMCPM?Critical Path Method (CPM), is a procedure for using network analysis to identify those tasks which are on the critical path: ie where any delay in the completion of these tasks will lengthen the project timescale, unless action is taken. For all tasks off the critical path, a degree of tolerance is possible (eg. late start, late completion, early start, etc.). Network charts and CPM analysis used to be carried out by hand. Software is now available which requires the user only to enter the tasks, duration of each task and dependencies upon other tasks; a network chart and CPM is then automatically created.

Page 8: The Critical Path Method

Why the CPM?

The CPMCPM formally identifies tasks which must be completed on time for the whole project to be completed on timeIdentifies which tasks can be delayed for a

while if resource needs to be reallocated to catch up on missed tasksIt helps you to identify the minimum length of

time needed to complete a projectThe CPM determines both the early start and

the late start date for each activity in the schedule.

Page 9: The Critical Path Method

How to use the CPM?

Project Network Diagram•• Any schematic display of the logical relationshipsAny schematic display of the logical relationships

of project activities.of project activities.

1

3

2

5 7

4 6

8

Page 10: The Critical Path Method

How to use the CPM?

List the activitiesAnd relationshipsList the activitiesAnd relationships

Create a start node

Create a start node

Draw arrows fromStart node to the

First activity’s node

Draw arrows fromStart node to the

First activity’s node

SequentiallyArrange all

Activities from“Start”

SequentiallyArrange all

Activities from“Start”

Repeat processfrom successorsfor all activities

Repeat processfrom successorsfor all activities

Double check formissed

relationships

Double check formissed

relationships

Page 11: The Critical Path Method

How to use the CPM?

EarlyStart (ES)

LateStart (LS)

Early Finish(EF)

LateFinish (LF)

Task duration

Page 12: The Critical Path Method

How to use the CPM?

Task ID Duration Dependency

A 7B 3C 6 AD 3 BE 3 D,FF 2 BG 3 CH 2 E,G

Page 13: The Critical Path Method

How to use the CPM?

FS

A

B

C G

H

D

F

E

(7) (6) (3)

(3) (3)

(2)

(3)

(2)

0

0

77 13 16

16 18

3 3 6

3 5

6 9

13

Page 14: The Critical Path Method

How to use the CPM?

FS

A

B

C G

H

D

F

E

(7) (6) (3)

(3) (3)

(2)

(3)

(2)

0

0

77 13 16

16 18

3 3 6

3 5

6 9

1816

16

16

13

13

13

13

770

13

13

10

11

107

Page 15: The Critical Path Method

How to use the CPM?

FS

A

B

C G

H

D

F

E

(7) (6) (3)

(3) (3)

(2)

(3)

(2)

0

0

77 13 16

16 18

3 3 6

3 5

6 9

1816

16

16

13

13

13

13

770

13

13

10

11

107

0

000

77

8

7

Page 16: The Critical Path Method

Summary

Critical Path Analysis is an effective and powerful method of assessing:

Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be

completed Resources needed to achieve a project The sequence of activities, scheduling, and

timings involved Task priorities

Page 17: The Critical Path Method

Do you need more information?

Project Management:A systems approach to Planning, Scheduling, and Controlling –Harold Kerzner, Six edition.Project Management: A Managerial Approach

– Jack R. Meredith, Samuel J. Mantel, Fourth Edition.Web Search Engine – key word: The Critical

Path Method or The CPM.

Page 18: The Critical Path Method

Contact me at:

Antonio Prensa� Email: [email protected] /

[email protected]� Phone: (787) 751-9800 ext. 3725

Page 19: The Critical Path Method

The Critical Path MethodThe Critical Path MethodPresented by Antonio Prensa,

MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter

June 20, 2002San Juan, Puerto Rico