the effect of shop floor continuous improvement programs

Upload: irina-adriana-vieriu

Post on 05-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    1/13

    ORIGINAL ARTICLE

    The effect of shop floor continuous improvement programs

    on the lot sizecycle time relationship in a multi-product

    single-machine environment

    Moacir Godinho Filho & Reha Uzsoy

    Received: 27 August 2008 /Accepted: 2 June 2010# Springer-Verlag London Limited 2010

    Abstract While continuous improvement on the shop floor is

    a major component of many popular management movementssuch as lean manufacturing and Six Sigma, there are few

    quantitative studies of the cumulative effects of such

    improvement programs over time. On the other hand, lot

    sizing has long been recognized as an important problem in

    manufacturing management. In this paper, we use a system

    dynamics model based on the Factory Physics relationships

    proposed by Hopp and Spearman [1] to examine the effect of

    different continuous improvement programs on the relation-

    ship between lot sizes and cycle times. We compare two

    different types of improvement programs: large improve-

    ments in a single parameter, such as might be obtained by a

    focused project, or small improvements in many parameters

    simultaneously. Our results show that the relationship

    between lot sizes, cycle times, and shop floor parameters is

    complex and nonlinear. The cycle time benefits of improve-

    ments in shop floor parameters are significantly enhanced by

    the reduced lot sizes they enable; on the other hand, a poor

    choice of lot sizes can negate the benefits of a continuous

    improvement program. Although the largest cycle time

    reduction is achieved by a large reduction in setup time,

    small, simultaneous improvements in several parameters can

    achieve much of the same benefit. The cycle time benefits of

    multiple simultaneous improvements are mutually reinforc-ing, creating a positive feedback between shop floor

    improvements and reduced lot sizes. Our model yields

    insight into why the Toyota Production System has been

    able to obtain such excellent results over time, and suggests a

    number of interesting future directions.

    Keywords Lot size . Cycle time .

    Continuous improvement. System dynamics .

    Factory physics .

    Multi-product single-machine environment

    1 Introduction

    According to Buffa [2], manufacturing decisions, such as lot

    sizing, can have major strategic implications for the firm. An

    extensive literature on lot sizing problems exists [3, 4], most

    of which seeks to find an optimal lot size (called Economic

    Order Quantity (EOQ) or Economic Production Quantity)

    that achieves the optimal tradeoff between fixed costs of

    ordering and inventory holding costs. Reviews of the lot

    sizing literature are available in [3, 4]. Despite its benefits,

    the EOQ model has been criticized in the literature, for

    failing to consider several key issues such as uncertainty in

    demand and resources with limited capacity [5].

    According to Kuik and Tielemans [6], criticism of cost

    accounting methods for production planning led to a

    growing interest in physical measures of manufacturing

    performance. One such measure is manufacturing cycle

    time (also known as lead time or flow time), defined as the

    mean time required for a part to complete all its processing.

    Time-based competition [7], initially proposed by Stalk [8],

    focuses on cycle time reduction as a primary manufacturing

    M. Godinho Filho (*

    )Departamento de Engenharia de Produo,

    Universidade Federal de So Carlos,

    Via Washington Luiz, km 235, Caixa Postal 676, So Carlos,

    SP 13.565-905, Brazil

    e-mail: [email protected]

    R. Uzsoy

    Edward P. Fitts Department of Industrial and Systems

    Engineering, North Carolina State University,

    Campus Box 7906,

    Raleigh, NC 27695-7906, USA

    e-mail: [email protected]

    Int J Adv Manuf Technol

    DOI 10.1007/s00170-010-2770-8

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    2/13

    goal. Despite this interest in cycle time reduction, de

    Treville et al. [9] point out that the literature on cycle time

    reduction has been largely anecdotal and exploratory.

    Some exceptions are the Factory Physics work of Hopp and

    Spearman [1, 10], and the Quick Response Manufacturing

    approach of Suri [11] that use queuing theory to develop a

    set of relationships between throughput, cycle time and

    critical shop floor parameters, aiming to increase themanagers understanding of manufacturing dynamics. One

    such is the relationship between lot size and average cycle

    time, which is studied in this paper. Karmarkar et al. [12]

    first introduced the convex relationship between lot size

    and average cycle time. This relationship is derived from

    queuing theory, specifically the Kingman approximation of

    the expected cycle time in system for the G/G/1 queue [1],

    and is illustrated in Fig. 1. Lambrecht and Vandaele [13]

    describe this relationship: Large lot sizes will cause long

    cycle times (the batching effect); as the lot size gets smaller

    the cycle time will decrease but once a minimal lot size is

    reached a further reduction of the lot size will cause hightraffic intensities resulting in longer cycle times (the

    saturation effect).

    Several other papers have used queuing models and

    simulation to study the relationship between lot size

    decisions and cycle time. Karmarkar et al. [14] present

    heuristics for minimizing average queue time. Rao [15]

    discusses alternative queuing models in relation to lot sizes

    and cycle time. Lambrecht and Vandaele [12] develop

    approximations for the expectation and variance of the

    cycle time under the assumption of individual arrival and

    departure processes. Kenyon et al. [16] use simulation to

    evaluate the impact of lot sizing decisions on cycle time in

    a semiconductor company. Vaughan [17] uses queuing

    relationships to model the effects of lot size on cycle time.

    Other papers relating lot size and cycle times are [1820].

    Although these studies provide a basis for understanding

    the relationship between lot sizes and cycle times, there is

    no literature showing the impact of continuous improve-

    ment (CI) efforts on this relationship. This is despite the

    repeated observation that reduction of lot sizes and cycle

    times is a critical component of lean manufacturing and the

    Toyota Production System [21]. In this context, this paper

    compares the effect of six shop floor continuous improve-

    ment programs on the lot size-cycle time relationship in a

    multi-product, single-machine environment using a combi-

    nation of system dynamics and factory physics approaches.

    The next section gives a short review of the relevant

    literature on CI and the two modeling approaches used inthis paper (system dynamics and factory physics); Section 3

    presents the model developed and the experimental design

    and Section 4 the results of the experiments. We conclude

    the paper in Section 5 with a summary and some future

    directions.

    2 Literature review

    2.1 Continuous improvement

    Caffyn [22] defines continuous improvement as a massinvolvement in making relatively small changes which are

    directed towards organizational goals on an ongoing basis.

    Continuous improvement has been recognized for many years

    as a major source of competitive advantage, and is inherent in

    many recent management movements such as the Theory of

    Constraints [23], Six Sigma [24] and the Toyota Production

    System [21]. Inability to effectively implement continuous

    improvement programs is seen by many scholars and

    practitioners as one of the reasons why Western firms have

    not fully benefited from Japanese management concepts

    [25]. Savolainen [26] points out that CI is a complex process

    that cannot be achieved overnight, but involves considerable

    learning and fine tuning of the mechanisms used. The core

    principles of CI are, according to Imai [27]:

    1. process orientation

    2. small step improvement of work standards

    3. people orientation.

    Leede and Looise [28] suggest that the main issue

    regarding CI is the problem of combining extensive

    employee involvement with market orientation and present

    the mini-company concept, which they claim incorporates

    these elements. However, there appears to be a lack of

    quantitative studies examining how different CI approaches

    affect manufacturing performance over time.

    In this paper, we deal with CI in six different shop floor

    parameters: (1) arrival variability, (2) process variability

    (natural process time variability, repair time variability and

    set up time variability), (3) quality (mean defect rate), (4)

    mean time to failure, (5) mean repair time, and (6) mean set-up

    time. Basically, these improvements deal with improvement in

    different parameters: mean times and rates and their variabil-

    ity, measured in terms of coefficient of variation (cv).

    0

    500

    1000

    1500

    2000

    2500

    3000

    0 100 200 300 400 500 600 700

    Lot size (pieces)

    CycleTime(hours)

    Fig. 1 Relationship between lot size and cycle time

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    3/13

    Hopp and Spearman [1] indicate that increasing variability

    always degrades the performance of a production system in

    terms of cycle time, work in process inventory (WIP) level or

    throughput. So, if a company cannot reduce variability, it will

    pay in one or more of the following ways: reduced throughput,

    increased cycle times, higher inventory levels and long lead

    times [1]. Schoemig [29] presents a simulation study illustrat-

    ing the corrupting influence of variability caused by machineand tool unavailability on manufacturing performance.

    Although the negative effects of variability are well

    known, there is little research examining the dynamic

    behavior of these effects over time, especially when linked

    to other shop-floor parameters. Newman et al. [30] claim

    that reducing variability and increasing flexibility enable

    capacity, inventory and time to be reduced, increasing

    companys performance; Mapes et al. [31], by means of a

    study in 963 manufacturing plants in UK, determine that

    the high performance companies utilize processes and

    procedures that have low levels of variability and uncer-

    tainty. Despite this conclusion, these authors state that theirpaper considers the performance of the plants at a particular

    point of time, and suggest studies of the relation between

    variability reduction and performance in a dynamic envi-

    ronment in the face of ongoing reductions in variability,

    which is exactly the issue addressed in this paper.

    The literature suggests a number of methods that can help

    reduce the arrival and the process variability. For reducing

    arrival variability, Hopp and Spearman [1] suggest: (1)

    decreasing process variability at upstream stations, (2) better

    scheduling and shop floor control to smooth material flow, (3)

    eliminating batch releases, and (4) installing a pull production

    control system such as Constant Work in Process or Kanban

    [21]. For a review about kanban variations see Lage Jr and

    Godinho Filho [32]. They formalize the relationship between

    different shop floor parameters in the form of a diagnostic tree

    [33]. Process variability is routinely addressed in practice

    using techniques such as Six Sigma, operator training,

    standardized work practices and automation. Other methods

    to improve manufacturing parameters include the Single

    Minute Exchange of Die system [34] to reduce the mean set

    up time; Total Productive Maintenance [35] to achieve

    improvements in mean repair time and mean time to failure;

    and finally, quality control methods like Statistical Process

    Control, Six Sigma and Total Quality Management to reduce

    mean defect rate, Lean Manufacturing [36], Quick Response

    Manufacturing [11], among others.

    Table 1 shows examples of methodologies/tools used to

    improve the shop floor parameters studied in this paper.

    2.2 System dynamics

    System dynamics (SD) were developed by Jay Forrester in

    1956 at the Massachussets Institute of Technology [37]. In

    complex systems such as manufacturing systems objects

    interact and a change in one variable affects other variables

    dynamically, which feeds back the original variable, and so

    on [38]. An excellent introduction to system dynamics

    modeling is given by Sterman [39].

    The structure and the relationship between variables in

    an SD model are represented by means of causal loop

    diagrams or stock and flow diagrams [39]. In this paper, we

    use the causal loop diagram, which has four main elements:

    (a) Stocks that characterize the state of the system and

    generate the information upon which decisions and

    actions are based [39]. The stock level is given by thedifference between cumulative inflow and outflow.

    (b) Flows that lead to the increase or decrease of stocks.

    These represent the dynamic behavior of the system

    over time and may depend on the stock levels.

    (c) Auxiliary variables that may be functions of stocks, as

    well as constants or exogenous inputs [39].

    (d) Links that represent information exchange between

    stocks, flows and auxiliary variables.

    System dynamics models have been used to address

    problems in a wide variety of areas [40, 41]. However,

    there is a lack of SD applications to manufacturing systems,

    despite evidence that this technique is suitable for industrial

    modeling. Baines and Harrison [42] point out that the

    computer simulation of manufacturing systems is common-

    ly carried out using Discrete Event Simulation, and suggest

    that manufacturing system modeling represents a missed

    opportunity for SD. This is also the opinion of Lin et al.

    [43], who propose a framework to help industrial managers

    apply SD to manufacturing system modeling. This is one of

    our motivations for the work in this paper. Recent advances

    in interactive modeling, tools for representation of feedback

    Table 1 Examples of methodologies/tools used for shop floor

    improvement

    Shop floor variable Examples of methodologies/tools

    used to improve such variables

    (1) arrival variability (cv) decreasing process variability at

    upstream stations; using a better

    scheduling and shop floor control

    to smooth material flow; eliminatingbatch releases, and; installing a pull

    production control system

    (2) process variability (cv) Six sigma, operators training,

    standardizing work practices

    and automation

    (3) mean defect rate SPC, Six Sigma and TQM

    (4) mean time to failure TPM

    (5) mean repair time TPM

    (6) mean set up time SMED

    TQM Total Quality Management

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    4/13

    structure, and simulation software make SD models much

    more accessible to practitioners than they have been in the

    past [39].

    2.3 Factory physics

    The Factory physics approach was created by Hopp and

    Spearman [1, 10]. This approach is based on a set ofmathematical principles derived from queuing theory. It

    has, according to Hopp and Spearman [10], three proper-

    ties: it is quantitative, simple and intuitive; so it provides

    managers with valuable insights. The basic approach

    consists of a set of equations that relate the long-run steady

    state means and variances of critical performance measures

    such as cycle time and WIP levels to the mean and variance

    of system parameters such as time between failures, setup

    times and processing times.

    As noted by Standridge [44], factory physics provides a

    systematic description of the underlying behavior of a

    production system. This description can provide supportssimulation studies in the following ways:

    1. It helps in deciding what performance measures to

    collect and what alternatives to evaluate as well as in

    interpreting simulation results.

    2. It helps identify the properties of systems that may be

    important to include in models.

    3. It provides an analytic foundation that helps in under-

    standing the behavior of systems and gives insight into the

    types of issues addressed in simulation studies.

    4. Verification and validation evidence can be collected

    based on the underlying relationships.Some recent papers that use the factory physics approach

    are [4549].

    3 Modeling and analysis

    The use of the factory physics concepts in a system dynamics

    model may, at first glance, appear to be somewhat contradic-

    tory. The factory physics approach as presented in Chapters

    8 and 9 of Hopp and Spearman is based on long-run steady

    state analysis of the production system, generally derived

    using the methods of queuing analysis. System dynamics, on

    the other hand, usually emphasizes the dynamic behavior of

    complex systems that are not in steady state. However, for our

    objective in this paper, the factory physics equations provide a

    systematic mathematical model linking the mean and variance

    of key system parameters such as setup and repair times to key

    performance measure such as cycle time and utilization. In

    order to use these equations as the basis for a system dynamics

    model, we assume that the time increments that form the basis

    of the system dynamics model are quite long, corresponding

    to periods of the order of several months. This is a reasonable

    assumption in our context, since it generally takes some time

    to identify opportunities for improvements, implement the

    necessary changes and obtain the results. We thus assume that

    within each time period, the queue representing the manufac-

    turing system will be in steady state, allowing us to use the

    factory physics equations to describe the behavior of the

    system. The assumption of long time periods also allows us toneglect the transient behavior at the boundaries between time

    periods.

    Our basic approach then is to model the performance of

    the system over an extended time horizon of several years

    using time increments of the order of several months.

    Continuous improvement policies are modeled as a reduc-

    tion in the mean or variance of the parameters studied

    (arrival variability, process variability, quality, time to

    failure, repair time, and setup time) obtained in each period.

    In each period, the new parameter values are calculated

    based on the improvements implemented in the previous

    period, and the factory physics equations are used topropagate the effects of these improvements to system

    performance measures. We assume a completely determin-

    istic model of the effects of continuous improvement on

    average cycle time, following the suggestion of Sterman

    [36] that a deterministic approach is generally sufficient to

    capture the principal relationships of interest. Note that the

    effects of randomness in the operation of the system itself

    are captured by the variances used in the factory physics

    equations, and our primary performance measure is the

    expected cycle time of the system in each period.

    Surprisingly, given the extensive discussion of continuous

    improvement and cycle time reduction in the literature and

    industry, there seems to be very little industrial data available

    on the rates of improvement realized over time in different

    industries, which makes it difficult to calibrate models of this

    type. Hence, we demonstrate the behavior of our model

    through a simplified example of our own construction.

    3.1 The model

    We consider a manufacturing system modeled as a single

    server with arbitrary interarrival and processing time distribu-

    tions, which we shall represent as a G/G/1 queue. The

    notations and relations used in the model are as follows:

    t0=>mean natural processing time (the time required to

    process a job without any detractors other than the

    variability natural to the production process);

    0=>standard deviation of the natural processing time;

    te=>mean effective time to process one good part

    (which is the natural processing time modified by the

    impacts of disruptions such as setups and machine

    failures);

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    5/13

    ce=>coefficient of variation of the effective time to

    process one good part;

    L=>average lot size;

    ta=>mean interarrival time between lots;

    ca=>coefficient of variation of the mean interarrival

    time between lots;

    l=>arrival rate of lots (the inverse of time between

    arrivals, giving l=1/ta);D=>mean annual demand

    H=>total number of hours worked in a year.

    As the system must be in steady state to avoid

    unbounded accumulation of jobs in the queue, the mean

    arrival rate to the system must equal the mean demand rate,

    implying ta=LH/D.

    The mean time to process a lot of L parts is then given

    by Lte, and the mean utilization of the server by:

    uLte

    ta

    Dte

    H1

    The other primary performance measure of interest in

    this study is the mean cycle time. For the G/G/1 queue, no

    exact analytical expression exists, but the following

    approximation has been found to work well and is

    recommended by Hopp and Spearman [1]:

    CTc2a c

    2e

    2

    u

    1 u

    Lte Lte 2

    where LTe is the mean time to process one lot.

    The average work in process is given by the well known

    Littles Law [1]:

    WIP l CT L 3

    The effective time to make one piece is constructed from

    the natural processing time by adding in first the effects of

    preemptive disruptions, in our case machine failures, then

    the effects of non-preemptive outages, in our case setups;

    and finally the effect of defective items. Both the means and

    the variances of the effective processing times must be

    calculated, as reflected in the model. Thus we first calculate

    the mean and variance of the intermediate effective process-

    ing time with machine failures, which we shall denote as tfe .

    Following Hopp and Spearmans treatment, we shall assume

    that the time between failures is exponentially distributedwith mean mf, and that the time to repair has mean mr and

    variance s2r. Then the mean availability of the server is

    given by A mf= mf mr

    , yielding tfe t0=A, and

    sfe

    2

    s20

    A2

    m2r s2r

    1 A t0

    Amr4

    We now incorporate the effects of setups, assuming, as in

    Hopp and Spearman [1], that a setup is equally likely after

    any part is processed, with expected number of parts

    between setups equal to the specified lot size L. The mean

    setup time is denoted by ts, and its variance by s2

    s. We thus

    obtain the mean of the effective processing time with both

    non-preemptive and preemptive outages (denoted by teo)as

    toe tfe ts=L. Its variance is given by:

    soe

    2 sfe

    2

    s2

    s

    L

    L 1

    L2

    t2s 5

    Finally, incorporating the effect of defective items, we

    have the overall mean of the effective processing time te,

    given by te toe= 1 p , where p denotes the proportion of

    defective items. The overall variance of the effective

    processing time is given by:

    s2e

    soe

    21 p

    p toe 2

    1 p 26

    Figure 2 shows all of these relationships in a stock and

    flow diagram.

    Since our objective is to examine the effects ofcontinuous improvement in six parameters on the cycle

    time of the system over time, we need a mechanism to

    model continuous improvements. We use an exponential

    model of improvement, where the value of a parameterA at

    time t is given by:

    At A0 G et=t 7

    where, A0 denotes the initial value of the parameter, and G

    the minimum level to which it can be reduced. The

    parameter represents the average amount of time it takes

    for the improvement to be realized, representing in our case

    the difficulty of improving the parameter in question.Figure 3 shows the SD structures used to model improve-

    ment on mean setup time. This structure is linked to the

    variable setup time with improvement in Fig. 2. Similar

    structures are used to model the improvements in the other

    parameters studied (arrival variability, process variability,

    setup time variability, repair time variability, and natural

    process time variability), quality, mean time to failure, and

    repair time. These structures are linked to the following

    variables, respectively: arrival coefficient of variation with

    improvement, variance of setup time with improvement,

    variance of repair time with improvement, variance of

    natural process time with improvement, defect rate with

    improvement, mean time to failure with improvement, and

    repair time with improvement.

    3.2 Parameters of the model

    We will vary individual parameters in different experiments

    to examine their effect on the relationship between lot sizes

    and cycle times. The basic time period in the system

    dynamics model is assumed to be 3 months or 12 weeks.

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    6/13

    This is a reasonable time increment for the purposes of this

    paper, since it is likely to require several months to develop

    and implement the improvements needed to make a

    significant reduction in repair or setup times. We simulate

    the operation of the system over a period of 10 years, or 40

    quarters. Since our objective is to study the effects of

    continuous improvement in system parameters, the annual

    demand is held constant at D=11,520 parts/year. We

    assume an initial lot size of 200 parts, and that the plant

    operates a total of H=1,920 h/year. The interarrival times

    are assumed to be exponentially distributed (ca=1), as is the

    natural processing time per part, with t0=6 min and c0=1.

    At the start of the simulation, the mean time between

    failures mf=9,600 min, the mean time to repair is mr=

    480 min, and the mean setup time is ts=180 min. The

    parameter of the improvement process was chosen to

    provide a half life for the exponential decay of 1 year. The

    initial proportion of defective items p=5%.

    We vary the lot size in order to examine the effect of lot

    sizes on cycle time. This is done for all improvement

    policies tested: (1) no improvement, (2) 50% improvement

    in arrival variability, (3) 50% improvement in each of the

    parameters affecting process variability (natural process

    variability, repair time variability and setup time variabil-

    ity), (4) 50% reduction in defect rate, (5) 50% increase in

    mean time between failures, (6) 50% improvement in mean

    repair time, (7) 50% improvement on setup time, (8) 5%

    improvement in all variables, (9) 10% improvement in all

    variables, (10) 15% improvement in all variables, and (11)

    20% improvement in all variables.

    4 Results

    Figure 4 shows the effect on expected cycle time of all 50%

    improvements over the time period (cases (1) to (7)) for a

    lot size of 200 parts. Similar figures can be drawn for the

    Set up Time with

    improvement

    Improvement

    on set up time

    Error on set up time

    improvement

    GOAL REGARDING SETUP TIME

    IMPROVEMENT

    Improvement rate onset up time

    ADJUSTMENT TIME FORSET UP TIME

    IMPROVEMENT

    -

    +

    B2

    VARIANCE OF

    SET UP TIME

    Fig. 3 SD Structure of improvement in setup time

    arrival rate throughput

    Utilization

    Set up Time with

    improvement Arrival coefficient ofvariation withimprovement

    Coefficient of variation for

    effective processing time

    Lot Size

    NATURAL

    PROCESS TIME

    TIME WORKED

    DURING THE YEARANNUAL

    DEMAND

    Number of pieces on

    queue

    Queue Time

    Cycle Time

    Variance of of effective processingtime with nonpreemptive and

    preemptive outages

    Mean repair time with

    improvement

    Availability

    Mean of effective processingtime with nonpreemptive and

    preemptive outages

    Variance of set up time

    with improvement

    Variance of effective processingwith preemptive outage

    (machine failures)Variance of natural

    process time withimprovement

    Total WIP

    Variance of repair time

    with improvement

    Defect Rate withimprovement

    Mean time to failure

    with improvement

    production rate

    Overall mean ofeffective processing

    time

    Overall variance of

    effective processing time

    Fig. 2 Main body of the SD model

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    7/13

    other lot size values tested (600, 400, 170, 150, 130, 100, 80,

    70, 60, 40, 30). From these results, lot size-cycle time curves

    are drawn for each improvement policy after these curves

    become stable. The resulting lot size-cycle time curves for the

    large improvement program are discussed in Section 4.1. The

    same procedure is performed for the small improvement

    program and reported in Section 4.2.

    4.1 Effect of large improvements in just one variable on lot

    size x cycle time relationship

    Figures 5, 6, 7, 8, 9, and 10 present the effects of each of

    the six 50% improvement programs (cases (2) to (7)) on the

    lot size-cycle time relationship, while Fig. 11 presents all

    the effects in a single graph for comparison. Table 2

    presents the values used to build Figures 5, 6, 7, 8, 9, 10,

    and 11. In these figures, it can be seen that:

    50% improvement in arrival cv has only slight effect on

    cycle time reduction for given lot size. This effect is

    even shorter when lot sizes are decreased. This may be

    because of the fact we are considering a single

    workstation.

    As expected, a 50% improvement in defect rate, repair

    time, time to failure, setup time, and process variability

    shift the lot size-cycle time curve down and to the left,

    reducing the lot size required to achieve a given cycle

    time.

    The positive effect on cycle time of 50% improvement

    in setup time, process variability and defect rate

    Graph for Cycle Time600

    500

    400

    300

    2000 30 60 90 120

    Time (months)

    Improvement in Process variabilityImprovement in Arrival cv

    Improvement in Time to failureImprovement in defect rateImprovement in repair time

    No improvement

    Improvement in set up time

    Fig. 4 Cycle time performance of all 50% improvements over time for a lot size of 200 parts

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    CycleTime(hours)

    Lot Size (pieces)

    no improvement

    improvement in arrival cv

    Fig. 5 The effect of 50% improvements in arrival cv on lot size-cycle

    time curve

    0

    500

    1000

    1500

    2000

    25003000

    3500

    4000

    0 100 200 300 400 500 600 700

    Lot Size (pieces)

    CycleTime(hou

    rs)

    no improvement

    improvement in process

    variability

    Fig. 6 The effect of 50% improvements in process variability on lot

    size-cycle time curve

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    8/13

    increases as lot sizes are reduced. This suggests a

    strong interaction effect between lot sizes, cycle time,

    and improvement in system parameters. In particular,

    this indicates the presence of a virtuous cycle time:

    improvements in setup time, defect rate, and process

    variability allow the reduction of lot sizes, which

    allows reduction of cycle times beyond the level that

    would be achieved by improving the system but

    keeping lot sizes constant. Thus, the small lot sizes

    advocated by lean manufacturing are a result of

    continuous improvement efforts; reduction of lot sizes

    without any accompanying improvement in shop floor

    capabilities will merely increase cycle time, as sug-

    gested by Fig. 1. The cycle time reductions from 50%

    improvement in repair time and time to failure increase

    at extreme values of the lot sizes. This is to be

    expected; the effect of these parameters is to make

    more capacity available.

    50% improvement in setup time achieves the best cycle

    time reduction for small lot sizes. Improvement in

    setup time is the only improvement that allows

    production system to use really small lot sizes (e.g.,

    30 or 40 parts);

    On the other hand, the importance of lot sizes to

    effective manufacturing performance is also evident from

    the results. Table 2 shows that in the original system with

    no improvements, a lot size of 150 parts leads to an

    average cycle time of 530 min. Reducing the lot size to 80

    leads to significantly higher cycle time even when all

    improvements have taken place. Thus, a poor choice of lot

    sizes can completely negate the benefits of a significant CI

    program.

    4.2 Effect of small improvements in several variables on lot

    sizecycle time relationship

    Figures 12, 13, 14, and 15 present comparisons between

    50% improvement in set up time, no improvement and each

    of the small improvement programs in all parameters

    simultaneously (5%, 10%, 15%, or 20%). Figure 16

    presents a comparison between the two large improvements

    that achieves the best results in the last section (set up time

    and process variability) and the small (5%, 10%, 15% or

    20%) improvement in all parameters simultaneously. The

    numerical values corresponding to this figure are shown in

    Table 3. A 15% simultaneous improvement in all variables

    outperforms all the large individual improvements, except

    when very small lot sizes are used. Large improvements in

    setup time achieve the best result in this case.

    In Fig. 16, the curves for 50% improvement in setup

    time and process variability represent situations where a

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    Lot Size (pieces)

    CycleTime(hours)

    no improvement

    improvement in

    defect rate

    Fig. 7 The effect of 50% improvements in defect rate on lot size

    cycle time curve

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    Lot Size (pieces)

    CycleTime(hou

    rs) no improvement

    improvement in time tofailure

    Fig. 8 The effect of 50% improvements in mean time between

    failures on lot sizecycle time curve

    0

    500

    1000

    1500

    2000

    25003000

    3500

    4000

    0 100 200 300 400 500 600 700

    Lot Size (pieces)

    CycleTime(hou

    rs)

    no improvement

    improvement inset

    up time

    Fig. 10 The effect of 50% improvement in mean set up time on lot

    sizecycle time curve

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    Lot Size (pieces)

    CycleTime(hours)

    no improvement

    improvement in

    repair time

    Fig. 9 The effect of 50% improvement in mean repair time on lot

    sizecycle time curve

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    9/13

    major reduction in these parameters is obtained. An

    improvement of this magnitude would very probably

    require the adoption of new technology, or at least a

    sustained, focused engineering effort. However, the curves

    for 10% and 15% improvement in all parameters capture

    almost the entire cycle time benefit of these programs,

    except at small lot sizes. Even a 5% improvement in all

    parameters yields a 50% improvement in average cycle

    time at small lot sizes over the no improvement situation.

    As suggested by the successful approach of Toyota,

    investing in small, combined improvements in all shop

    floor parameters yields better cycle time reduction than a

    single large, high-investment improvement. Examination of

    the Kingman equation relating cycle time to manufacturing

    parameters suggests the reason for this. The benefit of

    reduction in any given parameter may not be great in itself,

    but the benefits tend to be multiplicative, and hencemutually reinforcing. In system dynamics terminology, this

    suggests positive feedback between improvements in the

    different parameters, which is good news for managers.

    However, the opposite is also trueif the values of several

    parameters begin to deteriorate simultaneously, the detri-

    mental effects will also be mutually reinforcing, leading to

    precipitate degradation in cycle time.

    5 Conclusions

    In this paper, a combination of the SD and factory physicsapproaches is used to study the effect of continuous

    improvement programs aimed at improving six key parame-

    ters (arrival variability, process variability, quality (defect

    rate), time to failure, repair time, and setup time) on lot size-

    cycle time relationship in a multi-product, single-machine

    environment. Two sets of experiments were performed: (a) a

    large (50%) improvement in each parameter separately, as

    might be obtained by a significant one-time investment; (b) a

    small improvement in all parameters simultaneously.

    There are two salient conclusions from this set of

    simulation experiments. The first of these is the strong

    interaction between improvements in different system param-

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    No

    improvement

    Improvement

    in set up

    Improvement

    in defect rate

    Improvement

    in arrival cv

    Improvement

    in repair time

    Improvement

    in time to

    failureImprovement

    in process

    variability

    Lot Size (pieces)

    Cycle

    Time(hours)

    Fig. 11 Effect of 50% improvements on the lot size-cycle time curve

    Table 2 Values of lot size-cycle time curve for all improvement programs

    Lot size Cycle time

    No improvement Improvement

    in arrival cv

    Improvement

    in process cv

    Improvement

    in defect rate

    Improvement in

    time to failure

    Improvement

    in repair time

    Improvement

    in set up time

    600 896.77 837.47 594.18 825.86 705.73 673.92 784.69

    400 696.97 653.37 459.69 639.08 559.47 535.64 574.68

    200 535.56 505.91 349.69 483.19 446.19 428.72 373.03

    170 527.18 498.9 343.29 472.19 442.64 425.39 345.68

    150 530.01 502.25 344.38 471.24 447.33 429.8 328.74

    130 545.95 518.13 353.84 479.99 462.89 444.36 313.53

    100 633.81 602.98 408.81 537.91 538.01 514.1 297.13

    80 860.67 820.17 552.77 681.52 717.56 677.58 296.24

    70 1,244.88 1,187.22 797.44 890.84 996.97 923.86 303.14

    60 3,735.17 3,564.47 2,385.17 1,660.44 2,329.88 1,979.78 321.05

    40 501.39

    30 2,205.09

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    10/13

    eters and improved cycle time. While improvements in system

    parameters provide cycle time benefits on their own, furtherbenefits can be realized by reducing lot sizes to the levels

    permitted by the improvements. Similarly, when a firm sets its

    lot size near the minimal value on the lot sizecycle time

    curve, the need for improvement in machine availability

    decreases. In other words, a good choice of lot size can offset

    the disadvantages of unreliable equipment to some degree,

    although clearly the firm should continue to improve its

    equipment reliability. Similarly, when the lot sizes are small

    and hence utilization is high, improved machine up time

    creates additional capacity, reducing utilization and allowing

    significant reduction in cycle time.

    This close interaction between lot sizes and system

    parameters has another implication. As seen in any of the

    figures above, simply reducing the lot sizes without any

    improvement in the system parameters may lead to a

    catastrophic increase in cycle time. If the lot sizes were

    extremely high to begin with, quite significant reductionsmay be possible with significant cycle time benefits,

    essentially moving to the left along the linear portion of

    the lot sizecycle time curve. Since very few manufacturing

    facilities can predict the shape of the lot sizecycle time

    curve with any degree of precision without a significant

    data collection and analysis effort, this suggests that

    management exercise considerable caution when reducing

    lot sizes. A gradual reduction over time, making sure that

    enough time has elapsed for the effects of each reduction to

    be observed and understood, is probably the best strategy. It

    is better to gradually reduce lot sizes than to reduce them to

    such a degree that setups consume an undue amount of

    capacity and compromise the performance of the system.

    Our results in Table 2 show that a poor choice of lot sizes

    can offset all the benefits of a major CI program.

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 200 400 600 800

    CycleTim

    e(hours)

    Lot Size (pieces)

    no improvement

    10% improvement in all

    variables

    50% improvement in set up

    time

    Fig. 13 Comparison between 50% improvement in set up time, 10%

    improvement in all variables and no improvement case

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    CycleTim

    e(hours)

    Lot Size (pieces)

    no improvement

    20% improvement in allvariables

    50% improvement in set up

    time

    Fig. 15 Comparison between 50% improvement in set up time, 20%

    improvement in all variables and no improvement case

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 200 400 600 800

    CycleTime(hours)

    Lot Size (pieces)

    no improvement

    15% improvement in allvariables

    50% improvement in set uptime

    Fig. 14 Comparison between 50% improvement in set up time, 15%

    improvement in all variables and no improvement case

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 200 400 600 800

    Cycle

    Time(hours)

    Lot Size (pieces)

    no improvement

    5% improvement in allvariables

    50% improvement in set up

    time

    Fig. 12 Comparison between 50% improvement in set up time, 5%

    improvement in all variables and no improvement case

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    11/13

    The conclusion, again, is inescapable: improving the

    parameters of the shop floor is beneficial in itself, but when

    combined with the right choice of lot size the benefits are

    significantly enhanced. This result supports the Quick

    Response Manufacturing theory, which claims that in an

    environment with considerable set up time, a lot size of one

    piece, contrary to what is advocated by Lean Manufactur-

    ing, actually contributes to increased cycle time. Put

    another way, the lot size of one advocated in the Lean

    Manufacturing literature requires signifciant improvements

    in the parameters of the produciton system itself if it is to be

    realized without compromising cycle time performance.

    Our second salient finding is that a significant proportionof the benefits obtained by a major improvement in one

    parameter, as might be achieve by investing in a new

    technology, say, can be obtained by pursuing small

    improvements in multiple system parameters simultaneous-

    ly over time. As expected, setup time reduction allows the

    system to operate with the smallest lot size (in our case for

    30 or 40 parts). However, such a dramatic improvement

    may be difficult to achieve without major capital expendi-

    ture and interruptions to production. Our results suggest

    that a substantial portion of the benefits of this type of

    dramatic reduction in setup time can be improved by

    relatively minor simultaneous improvements in otherparameters, which can be pursued in parallel with a longer

    term setup reduction effort. Even a 5% improvement in all

    parameters gives cycle time savings of almost 50% at low

    lot sizes.

    The results presented underscore the benefits of the

    factory physics approach to understanding and diagnosing

    manufacturing systems. As the factory physics equations

    suggest, the behavior of these systems over time is quite

    nonlinear; the effects of changes in parameters are

    multiplied to yield nonlinear improvements or degradations

    in cycle time. The presence of positive feedback between

    improvements in system parameters, lot sizes, and cycle

    time goes a long way towards explaining how Japanese

    Table 3 Values of lot size-cycle time curve used to build Fig. 12

    lot

    size

    Cycle time

    No improvement 5% Improvement

    in all variables

    10% Improvement

    in all variables

    15% Improvement

    in all variables

    20% Improvement

    in all variables

    50% Improvement

    in set up

    50% improvement

    in process cv

    600 896.77 776.4 672.05 581.27 502.12 784.69 594.18

    400 696.97 601.96 519.72 448.27 386.05 574.68 459.69

    200 535.56 457.23 390.34 332.94 283.5 373.03 349.69170 527.18 447.46 379.95 322.43 273.22 345.68 343.29

    150 530.01 446.13 377.56 318.77 268.82 328.74 344.38

    130 545.95 456.19 381.95 320 267.95 313.53 353.84

    100 633.81 513.44 418.69 342.83 281.3 297.13 408.81

    80 860.67 654.91 508.69 400.53 318.16 296.24 552.77

    70 1,244.88 863.25 629.57 473.5 363.17 303.14 797.44

    60 3,735.17 1,656.39 985.35 657.72 466.07 321.05 2,385.17

    40 501.39

    30 2,205.09

    0

    500

    1000

    1500

    2000

    2500

    3000

    3500

    4000

    0 100 200 300 400 500 600 700

    No improvement 5% improvement in allvariables

    10% improvement in all

    variables

    15% improvement in all

    variables

    20% improvement in allvariables

    50% Improvement in set up

    50% improvement inprocess variability

    Lot Size (pieces)

    CycleTime(hours)

    Fig. 16 Comparison between the large improvement in setup and

    process variabilities and simultaneous small improvements in all

    variables

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    12/13

    factories have been able to achieve the massive cycle time

    and WIP reductions that many Western experts simply

    could not believe were possible in the early 1980s.

    Finally, the SD/Factory Physics combined model pro-

    posed in this paper has been shown to be a valuable tool for

    simulating the impact of alternative continuous improve-

    ment programs on manufacturing performance measures

    over time.A number of extensions of this approach suggest

    themselves. An interesting direction is to provide insight

    into the allocation of limited continuous improvement

    resources in a complex systemshould all available

    resources be directed towards improving one specific

    resource, or should parallel efforts be maintained in several

    different areas? Another interesting question is how the

    benefits of different CI programs are affected by uncertainty

    in ability to achieve improvements. One would conjecture

    that a portfolio approach, where multiple improvements are

    pursued simultaneously, would yield better average im-

    provement over a given time interval than an effortdedicated at a single highly uncertain improvement.

    Acknowledgments The research of Reha Uzsoy was partially

    supported by the National Science Foundation under Grant No.DMI-

    0559136. Moacir Godinho Filho would like to acknowledge FAPESP

    Brazilian agency for funding this research.

    References

    1. Hopp WJ, Spearman ML (2008) Factory physics: foundation of

    manufacturing management, 3rd edn. McGrawHill, Irwin, New York

    2. Buffa ES (1984) Meeting the competitive challenge. Irwin,

    Homewood, IL

    3. Drexl A, Kimms A (1997) Lot sizing and schedulingsurvey and

    extensions. Eur J Oper Res 99:221235

    4. Karimi B et al (2003) The capacitated lot sizing problem: a review

    of models and algorithms. Omega-Int J Manag Sci 31:365378

    5. Woolsey G (1988) A requiem for the EOQ: an editorial. Prod

    Invent Manage J 29(3):6872, Third Quarter

    6. Kuik R, Tielemans TFJ (2004) Expected time in system analysis

    of a single-machine multi-item processing center. Eur J Oper Res

    156:287304

    7. Hum S, Sim H (1996) Time-based competition: literature review and

    implications for modeling. Int J Oper Prod Manage 16(1):7590

    8. Stalk G (1988) Timethe next source of competitive advantage.

    Harvard Business Review, pp 41-51, July-August

    9. Treville SD et al (2004) From supply chain to demand chain: the

    role of lead time reduction in improving demand chain perfor-

    mance. J Oper Manag 21:613627

    10. Hopp WJ, Spearman ML (1996) Factory physics: foundations of

    manufacturing management, 1st edn. Irwin, Nova York

    11. Suri R (1998) Quick response manufacturing: a companywide

    approach to reducing lead times. Productivity Press, Portland

    12. Karmarkar US et al (1985) Lot sizing and lead time performance

    in a manufacturing cell. Interfaces 15(2):19

    13. Lambrecht MR, Vandaele NJ (1996) A general approximation for

    the single product lot sizing model with queueing delays. Eur J

    Oper Res 95:7388

    14. Karmarkar US et al (1992) Multi-item batching heuristics for

    minimization of queues. Eur J Oper Res 58:99111

    15. Rao S (1992) The relationship of work-in-process inventories,

    manufacturing lead times and waiting line analysis. Int J Prod

    Econ 26:217227

    16. Kenyon G et al (2005) The impact of lot sizing on net profits and

    cycle times in the n-job, m-machine job shop with both discrete

    and batch processing. Int J Prod Econ 97:263278

    17. Vaughan TS (2006) Lot size effects on process lead time, lead

    time demand, and safety stock. Int J Prod Econ 100:1918. Kekre S (1987) Performance of a manufacturing cell with

    increased product mix. IIE Trans 19(3):329339

    19. Hafner H (1991) Lot sizing and throughput times in a job shop.

    Int J Prod Econ 23:111116

    20. Choi S, Enns ST (2004) Multi-product capacity-constrained lot

    sizing with economic objectives. Int J Prod Econ 91:4762

    21. Liker J (2004) The Toyota way: 14 management principles

    from the worlds greatest manufacturer. McGraw-Hill, New

    York

    22. Caffyn S (1999) Development of a continuous improvement self-

    assessment tool. Int J Oper Prod Manage 19(11):11381153

    23. Goldratt E, Fox RE (1986) The race. North River Press: Great

    Barrington.

    24. Pande P et al (2000) The six sigma way: how GE, Motorola and

    other top companies are honing their performance. McGraw-Hill,

    New York

    25. Berger A (1997) Continuous improvement and kaizen: standardiza-

    tion and organizational designs. Integr Manuf Syst 8(2):110117

    26. Savolainen TI (1999) Cycles of continuous improvement: realiz-

    ing competitive advantages through quality. Int J Oper Prod

    Manage 19(11):12031222

    27. Imai M (1986) Kaizenthe key to Japans competitive success.

    Random House, New York, NY

    28. Leede J, Looise JK (1999) Continuous improvement and the mini-

    company concept. Int J Oper Prod Manage 19(11):11881202

    29. Adams M, Componation P, Czarnecki H, Schroer BJ (1999)

    Simulation as a tool for continuous process improvement.

    Proceedings of the 1999 Winter Simulation Conference. Univer-

    sity of Alabama, Huntsville, Alabama, USA

    30. Schoemig AK (1999) The corrupting influence of variability in

    semiconductor manufacturing. Winter Simulation Conference

    31. Newman WR, Hanna M, Maffei MJ (1993) Dealing with the

    uncertainties of manufacturing: flexibility, buffers and integra-

    tion. International Journal of Operations and Production

    Management, 13

    32. Lage Jr M, Godinho Filho M (2010) Variations of the kanban

    system: literature review and classification. Int J Prod Econ 125

    (1):1321

    33. Mapes J et al (2000) Process variability and its effects on plant

    performance. Int J Oper Prod Manage 20(7):792808

    34. Hopp WJ, Iravani SMR, Shou B (2009) A diagnostic tree for

    improving production line performance. J Oper Manag 16

    (1):7792

    35. Shingo S (1986) A revolution in manufacturing: the SMED

    system. Productivity Press, Cambridge

    36. Nakajima S (1988) Introduction to TPM. Productivity Press,

    Portland, OR

    37. Forrester JW (1962) Industrial dynamics. MA, MIT Press,

    Cambridge

    38. Womack JP et al (2000) The machine that changed the world.

    Harper Perennial, New York

    39. Tesfamariam D, Lindberg B (2005) Aggregate analysis of

    manufacturing systems using system dynamics and ANP. Comput

    Ind Eng 19:98117

    40. Sterman JD (2000) Business dynamics: systems thinking and

    modeling for a complex world. McGraw-Hill, New York

    Int J Adv Manuf Technol

  • 7/31/2019 The Effect of Shop Floor Continuous Improvement Programs

    13/13

    41. Chen JH, Jan TS (2005) A system dynamics model of the

    semiconductor industry development in Taiwan. J Oper Res Soc

    56(10):11411150

    42. Kumar S, Yamaoka T (2007) System dynamics study of the

    Japanese automotive industry closed loop supply chain. J Manuf

    Technol Manage 18(2):115138

    43. Baines TS, Harrison DK (1999) An opportunity for system dynamics

    in manufacturing system modeling. Prod Plan Control 10:542552

    44. Lin C et al (1998) Generic methodology that aids the application

    of system dynamics to manufacturing system modeling. IEE ConfPubl 457:344349

    45. Standridge CR (2004) How factory physics helps simulation.

    Proceedings of the 2004 Winter Simulation Conference

    46. Watkins B, Kurz ME (2004) An application of factory physics

    tools in a complex manufacturing environment. In: IIE Annual

    Conference and Exhibition, mai.2004, Proceedings[S.I];: Insti-

    tute of Industrial Engineers

    47. Li et al. Applied factory physics study on semiconductor assembly

    and test manufacturing. In: IEEE International Symposium on

    Semiconductor Manufacturing Conference, 2005, Proceedings

    [S.I]: Institute of Electrical and Electronics Engineers, p 4

    48. Kline WA (2005) A course in manufacturing systems with

    simulation. In: ASEE Annual Conference and Exposition, JunE

    2005, Proceedings[S.I]: American Society for Engineering

    Education, pp 2359-236849. Zheng et al (2008) Cycle time reduction in assembly and test

    manufacturing factories: A KPI driven methodology. In: IEEE

    International Conference on Industrial Engineering and Engineer-

    ing Management, 2008, Proceedings [S.I]: Inst. of Elec. and

    Elec. Eng. Computer Society, pp 1234-1238

    Int J Adv Manuf Technol