the entry capacity transfer & trade methodology statement transmission workstream 02-08-07

21
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

Upload: tobias-reed

Post on 13-Jan-2016

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

The Entry Capacity Transfer & Trade Methodology Statement

Transmission Workstream

02-08-07

Page 2: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

2

Prompt Buy Back Historical Information

"The information/data set out above has been provided by National Grid on a good faith basis for information purposes only. It should not be relied on by any person for any purpose, and any person uses or relies on such information/data entirely at their own risk. National Grid accepts no liability arising from any such use or reliance.”

Page 3: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

3

Background (1)

An initial consultation on the T&T MS was conducted in May 07, this was designed to provide individual exchange rates.

The two new Mods 150/A and 163 require fixed ex-ante exchange rates for multiple trades and transfers.

The Mods also specify specific parameters to be derived from the Methodology Statement e.g.:

Zonal allocation maximum Nodal allocation maximum etc.

Therefore a major revision of the draft T&T MS has been necessary.

Page 4: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

4

Background (2)

The new T&T MS is much more complex as it needs to provide fixed ex-ante exchange rates for multiple trades and transfers. As discussed at previous meetings every trade or transfer has a knock on effect to the next transaction.

In addition the exchange rate provided must also meet the Licence Obligations, broadly speaking:

Make effective use of the NTS Be compatible with the physical capability of the NTS Avoid material increases in cost

The T&T MS needs to considered together with the proposed Mods.

Page 5: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

5

Timetable

T&T MS consultation launched on the 30 July 07 T&T MS consultation closes on 28 August 07 Section 23 on the associated Licence Obligation

closes on the 28 August 07. Section 23 needs to be consented to and directed

before the T&T MS can be approved. The associated Mods cannot be implemented

without an approved T&T MS. Based on the above there will not be a trade and

transfer process for October 07.

Page 6: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

6

Conceptual Overview – Within Zone

1. For each month a zonal allocation maximum (ZAM) is set according to the T&T MS.

2. Within zone transfers and trades (surrenders) are undertaken at a 1:1 exchange rate up to the zonal allocation maximum and the specific nodal maximum (according to the T&T MS)

Page 7: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

7

Conceptual Overview – Out of Zone

Exchange rates are calculated for related zones i.e. zones that have a physical interaction i.e. reduction in flows in one zone allow more flow out of another zone.

These exchange rates will vary according to quantity and will not be on a 1:1 basis.

Page 8: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

8

To be noted

The following slides describe the T&T MS at a simplified and abbreviated level.

For a full and accurate understanding of how the process works please refer to the T&T MS

The theoretical examples and data provided are for illustration purposes only.

Page 9: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

9

Base Data

Demand – determine range for the month being considered based on historical data

Nodal allocation maximum – where possible based on network analysis data shared with the industry on 6 July. However if other limiting factors exist, constrained to maximum historical gas flow over the last 5 years.

Entry Zones – for winter 07/08 based on current Ten Year Statement

Merit Order – Prioritises ASEPs within a zone according the likelihood of them flowing at the demands determined for the particular month.

Supply scenarios – TBE scenarios flexed to reflect historical and potential future supply patterns

Page 10: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

10

Calculation of the Zonal Allocation Maximum (ZAM) – High Level Process

January

Theoretical Example

[301 – 454 mcm/d]

Northern Triangle

Teesside

(NAM = 44.3 mcm/d)

Page 11: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

11

ZAM – Scenario Analysis (Step i & ii)

What are we are trying to achieve? To reach the maximum ZAM without

an expected material increase in costs of doing trades and transfers at 1:1 rate up to this level.

Starting point is:

ZAM = sum of baselines within zone Test scenario is set (initially TBE

base Case)

Scenario shown represents a realistic supply pattern for demand level of 365 mcm/d.

Page 12: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

12

Theoretical example continued

Reverse merit order

Page 13: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

13

Theoretical example continued

Network analysis is then performed based on the new flows and balancing the remaining volumes out of zone based on swing factors.

For simplicity the balancing in this example is all shown at Bacton.

If the network does not fail, then under this scenario the ZAM could equal the sum of the baselines.

If the network fails it would suggest that it would not be possible to do trades and transfers up to the sum of the baselines without avoiding material increases in costs.

+16.5

-0.1

-16.4

Page 14: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

14

Under the assumption that it fails….

Gradually reduce the MPFL at the other ASEPs until no material increase in costs or the flow increase from obligated level to the NAM is all met within zone.

The ZAM is then the sum of the MPFLs i.e.

0 + 0 + 118.8 + 44.3 = 163.1

If there are still material increases in costs reduce NAM at Teesside towards its obligated level.

+16.5

-0.1

-7.1

-4.1

-5.2

Page 15: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

15

Calculation of the Zonal Allocation Maximum (ZAM) – High Level Process

January

Theoretical Example

[301 – 454 mcm/d]

Northern Triangle

Teesside

(NAM = 44.3 mcm/d)

Barrow

(NAM = 42.8 mcm/d)

Page 16: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

16

Cross Zone Check & “final” ZAM

The results of steps i) to iii) will provide the potential for Recipient ASEPs to flow above obligated levels.

The interaction between these ASEPs flowing at their obligated level needs to be assessed. This would not have been covered under Step ii)

If this leads to expected material increases in costs adjustments to the relevant ZAMs need to made.

After this has been completed the “final” ZAM is calculated by summing up the MPFLs.

Page 17: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

17

Inter-zone Exchange Rates

The inter-zone exchange rates are calculated for related zones i.e. zones that have a physical interaction i.e. reduction in flows in one zone allow more flow out of another zone.

These exchange rates will vary according to quantity and will not be on a 1:1 basis.

The basic process is similar to that used in the calculation of the ZAM.

Page 18: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

18

Theoretical example

Merit order (Recipients):• Teesside• Barrow

Merit order:• Isle of Grain • Bacton

Page 19: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

19

Theoretical example continued

Set test scenario Move 10 mcm/d from Isle

of Grain to Teesside. Test network If network fails 1:1 not

possible, reduce increase at Teesside until does not fail.

This sets the exchange rate for this scenario

Test scenario+10

-10

Page 20: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

20

Inter-zone exchange rates – example output table

Available Capacity for Allocation: ACfA= ZAM – sold capacity + surrendered capacity

Example 1: With all ACfA unused in zone 1, to move 10 units to zone 1 requires 25 units from zone 2:First 10 units in zone 1 = 5 units in zone 2Second 15 units in zone 1 = 5 units in zone 2Total 25 units in zone 1 = 10 units in zone 2 (2.5:1 exchange rate)

Example 2: With 10 units of ACfA in zone 1 allocated, to move 10 units to zone 1 requires 36.67 units from zone 2:

First 20 units in zone 1 = 6.67 units in zone 2Second 16.67 units in zone 1 = 3.33 units in zone 2Total 36.67 units in zone 1 = 10 units in zone 2 (3.667:1 exchange rate)

Page 21: The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream 02-08-07

21

Discussion & Questions

Consultation closes on the 28/08/07 Please note that definitive ZAM values and inter

zone exchange rates can only be provided once all potential Recipients have been analysed.

Are there limited pieces of analysis that would be useful to have before the consultation closes, for example up to Step ii) for certain ASEPs?