the episouth plus project - episouthnetwork.org · faculty of medicine, ... the episouth plus...
TRANSCRIPT
THE EPISOUTH PLUS PROJECT
MMiiddtteerrmm EEvvaalluuaattiioonn RReeppoorrtt Evaluation Period: 15 October 2010 – 15 September 2012
This report was prepared by a subcontractor as requested by the EpiSouth
Plus partnership and in accordance with a Terms of Reference (ToR).
Subcontractor: University of Thessaly, School of Health Sciences,
Faculty of Medicine,
Laboratory of Hygiene and Epidemiology,
Larissa, Greece
Evaluator:
Assoc. Prof. Christos Hadjichristodoulou,
SHIPSAN ACT Joint Action Coordinator
Evaluation assistant researcher:
Elina Kostara, MSc., Researcher
The EpiSouth Plus project is cofunded by the European Union DG-SANCO/EAHC and DEVCO/EuropeAid together with the participating national partner Institutions.
The financial support of the Italian Ministry of Health and ECDC is also acknowledged.
EpiSouth Plus Midterm Evaluation Page 2 of 74
Contents
Executive Summary ......................................................................................................................... 4
1 Scope and objective ................................................................................................................ 7
22 MMeetthhooddoollooggyy ............................................................................................................................ 8
2.1 Evaluation Tools .......................................................................................................................... 8
2.2 Questionnaire Dissemination ..................................................................................................... 9
2.3 Questionnaire analysis.............................................................................................................. 10
2.4 SWOT analysis ........................................................................................................................... 10
33 EEvvaalluuaattiioonn RReessuullttss ................................................................................................................. 11
3.1 Response Rate .......................................................................................................................... 11
3.2 Evaluation of respect of scheduled milestones and deliverables according to the project Work
Packages (WPs) .................................................................................................................................. 12
3.2.1 Interview results ........................................................................................................................ 15
3.3 Evaluation of achievement of project indicators, both for quantitative and qualitative aspects16
3.4 Project Management Evaluation .............................................................................................. 18
3.4.1 Evaluation questionnaire analysis ............................................................................................. 18
3.4.2 Comments by the questionnaire responders ............................................................................. 19
3.4.3 Interview results ........................................................................................................................ 20
3.5 Dissemination Activities Evaluation .......................................................................................... 21
3.5.1 Previous Evaluation of the WP2 Website and Electronic Bulletin ............................................. 22
3.5.2 Evaluation questionnaire analysis ............................................................................................. 23
3.5.3 Comments by the questionnaire responders ............................................................................. 26
3.6 Training Activities Evaluation ................................................................................................... 28
3.6.1 Previous Evaluation Activities ................................................................................................... 28
3.6.2 Evaluation questionnaire analysis ............................................................................................. 28
3.6.3 Comments by the responders for WP4 training ........................................................................ 31
3.6.4 Comments by the responders for WP5 training ........................................................................ 31
3.7 Documents and deliverables produced Evaluation .................................................................. 32
3.7.1 Evaluation questionnaire analysis ............................................................................................. 32
3.8 Meetings/Working Groups Evaluation ..................................................................................... 36
3.8.1 Previous Evaluation of the 1st WP7 Steering Team meeting .................................................... 36
3.8.2 Evaluation questionnaire analysis ............................................................................................. 36
3.8.3 Comments by the responders: ................................................................................................... 37
3.9 Network Consolidation Evaluation ........................................................................................... 38
3.9.1 Previous evaluation report ........................................................................................................ 38
3.9.2 Evaluation of the EpiSouth Network ......................................................................................... 39
*p-value: 0.1 ................................................................................................................................................. 40
3.9.3 Evaluation of the EpiSouth Platform ......................................................................................... 40
EpiSouth Plus Midterm Evaluation Page 3 of 74
3.9.4 Comments by the responders regarding different questions presented in Tables 15 and 16 ... 42
44 EEppiiSSoouutthh PPlluuss SSWWOOTT aannaallyyssiiss .............................................................................................. 44
55 SSuussttaaiinnaabbiilliittyy .......................................................................................................................... 46
66 AAddddeedd VVaalluuee ooff tthhee EEppiiSSoouutthh PPrroojjeecctt ................................................................................ 48
6.1 Added value of the collaboration between the EpiSouth Network and WHO in the framework of
the EpiSouth Plus WP7 ...................................................................................................................... 48
77 LLiimmiittaattiioonnss .............................................................................................................................. 50
88 CCoonncclluussiioonnss ............................................................................................................................. 51
Annexes ........................................................................................................................................... 54
Annex 1- Questionnaire 1 - Completed by the Advisory Board of the EpiSouth Network ............................... 54
Annex 2- Questionnaire 1 - Completed by all Focal Points of Institution partners and Countries involved in the
EpiSouth Network ............................................................................................................................................. 58
Annex 3- Questionnaire 1 – Completed by the Steering Committee of the EpiSouth Network ....................... 63
Annex 4- Questionnaire 1 - Completed by the WP4 Steering Team ................................................................ 66
Annex 5- Questionnaire 1 - Completed by the WP5 Steering Team ................................................................ 69
Annex 6- Questionnaire 1 - Completed by the WP6 Steering Team ................................................................ 71
Annex 7- Questionnaire 1 - Completed by the WP7 Steering Team ................................................................ 72
Annex 8- Questionnaire 2 - Completed by all Focal Points of Institution partners and Countries involved in the
EpiSouth Network ............................................................................................................................................. 73
Annex 9- Questionnaire 3 – Interview Checklist ............................................................................................... 73
Table Contents
Table 1: Response rate of the evaluation questionnaires ...................................................................................... 11
Table 2: Deliverables evaluation ............................................................................................................................. 13
Table 3: Milestones Evaluation ............................................................................................................................... 14
Table 4: Indicators Evaluation ................................................................................................................................. 16
Table 5: Evaluation Questionnaire 1: Management and timeframe evaluation..................................................... 19
Table 6: Website statistics ...................................................................................................................................... 21
Table 7: Number of Presentation/ Participations to conference and Meetings by Work Package ........................ 22
Table 8: Evaluation Questionnaire 1: Website evaluation ...................................................................................... 23
Table 9: Evaluation Questionnaire 1: Quarterly EpiSouth Electronic Bulletin evaluation ...................................... 25
Table 10: Evaluation Questionnaire 1: EpiSouth Weekly Epi Bulletin (e-WEB) ...................................................... 26
Table 11: Evaluation Questionnaire 1: WP4 Training Activities .............................................................................. 29
Table 12: Evaluation Questionnaire 1: WP5Training Activities ............................................................................... 30
Table 13: Evaluation Questionnaire 1: Documents and deliverables produced ..................................................... 32
Table 14: Evaluation Questionnaire 1: Meetings and Workshops .......................................................................... 36
Table 15: Evaluation Questionnaire 2: EpiSouth Network ...................................................................................... 40
Table 16: Evaluation Questionnaire 2: EpiSouth Platform ...................................................................................... 41
EpiSouth Plus Midterm Evaluation Page 4 of 74
Executive Summary
Objectives
This evaluation highlights the successful results, outcomes and critical aspects following the
implementation of the four specific objectives of the project, together with the assessment
of correct timing and adequacy of planned deliverables. The evaluation was conducted with
the participation of the Episouth Plus Network partners, the EU Institutions (EAHC, DG
SANCO, DG DEVCO, ECDC) and International Institutions such as WHO.
Methodology
The methods used regarding the evaluation of both process and outcome evaluations
included an analysis of the project’s documentation and an analysis and verification of the
project’s indicators. Moreover, a checklist for interviews and two questionnaires to collect
information on the project management, core activities and network consolidation were
prepared and disseminated to eight target groups. A descriptive analysis of the collected
questionnaires was conducted as well as a statistical analysis of the results related to the EU
and Non EU participant responses.
Results
A total of 10 out of 18 (55.5% response rate) interviews were conducted with members of
the Advisory Board and Focal Points and a total of 178 questionnaires (EU: 90/178, 51% and
Non EU: 88/178, 49%) were disseminated to 92 stakeholders. A total of 109 out of 178
(61%) questionnaires were collected. A lower response rate was recorded in Non EU
partners (36/88, 41%) in comparison with the EU countries (73/90, 81%) (p-value: <0.001). As
a result, the Non EU countries’ views and opinions are not equally represented. Seventy
three out of the 109 (68%) collected questionnaires were from EU countries, whereas 36 out
of 109 (33%) were from Non EU countries.
The evaluation of milestones and indicators has shown that minor and major delays occurred
in all work packages. The reason for the delays as identified by the responders includes,
amongst others, the political instability in certain countries and the long-term negotiations
between EpiSouth Plus and the European Commission (EAHC, DEVCO) regarding the Epidemic
Intelligent platform (WP6). The overall belief of the majority of the responders is that the
coordination structure of the project and the problem–solving process was effective in
EpiSouth Plus Midterm Evaluation Page 5 of 74
resolving the delays, however, responders from the EU and International organisations
commented that the project would have benefited from a more proactive approach
regarding coordination activities. The Website, the Quarterly Electronic Bulletin and the
Weekly Epi Bulletin were rated highly by the majority of the responders and identified their
importance in the dissemination of results and in providing necessary information to the
visitor. More than 80% of the responders identified that the project has great potential and
that it has achieved reliable and collaborative relationships among public health
professionals. It is characterised as a valuable network that has fully facilitated the exchange
of alerts and health information (>80%, EU: 18/22, Non EU: 8/10), enhancing the
coordinated response to public health events in the Mediterranean Area (60%, EU: 81.8%,
Non-EU: 80%). Responders also identified that the network is not used to its full potential
and there are opportunities for improvement, especially in the capacity of the Network to
strengthen participants’ laboratory capacity in terms of diagnoses response and in using the
participant organisation’s strengths and expertise. However, it should be noted that this
facilitation will be better demonstrated following implementation of activities in the
following year. It is worth mentioning that some partners from the Mediterranean countries
reported as a shortcoming the limited access to European data, however, this is due to EU
legislation constraints. A fear of duplication of information shared through the Epidemic
Intelligence was expressed as a threat as well as uncertainty over the quality of data shared.
The lack of long-term concrete vision for the sustainability of the project was identified by
the key stakeholders (EU and International organisations) as a limitation and a threat to the
project, while the identification and dissemination of the added value of the project was
indicated as an immediate need.
Conclusions
The majority of the partners rated both the process and the outcome of the project as
satisfactory or excellent, while the key stakeholders from the EU and International
organisations raised serious issues both on the timeliness and the quality of the deliverables.
Differences of EU and Non-EU countries in the evaluation results should be considered
together with the low participation of the Non-EU countries in the evaluation process. We
believe that the coordination of the project should take into consideration all the
recommendations made to improve the quality and the timeliness of the deliverables.
Moreover, the added value of the network and the platform should be better defined and
disseminated to the key stakeholders (EU and International organisations) and the public.
EpiSouth Plus Midterm Evaluation Page 6 of 74
Many ideas were put forward by all participants on the sustainability of the activities on
which the partnership has to elaborate further.
EpiSouth Plus Midterm Evaluation Page 7 of 74
1 Scope and objective
This report is Milestone No 4 of the Work Package 3 – Evaluation and is the internal
evaluation of the project covering a 24-month period of the project implementation (15
October 2010- 15 September 2012). The evaluation was conducted with the participation of
the Episouth Plus Network partners, the EU institutions (EAHC, DG SANCO, DG DEVCO, ECDC)
and International Institutions such as WHO.
Objectives
This evaluation highlights the successful results, outcomes and critical aspects following the
implementation of the four specific objectives of the project, together with the assessment
of correct timing and adequacy of planned deliverables. The following aspects will be
described and discussed:
� respect of scheduled milestones and deliverables according to the project Work
Packages (WPs);
� achievement of project indicators, both for quantitative and qualitative aspects;
� active participation and networking of both associated and collaborating countries in
the project activities;
� measure the benefits / added value gained on health and security cooperation among
the associated and collaborating countries;
� relevant recommendations for sustainability to support the finalization of the
sustainability plan of the project and for possible further developments (with particular
reference to the framework of the EC DEVCO Instrument for Stability (IfS)/ Centre of
Excellence (CoE) Programme.
The report consists of the following main sections: In Section 1 the scope and objective of the
evaluation are outlined. Section 2 describes the methodology followed. Section 3 presents
the evaluation results. Section 4 presents the EpiSouth Plus SWOT Analysis. Section 5
outlines the sustainability options identified by the partnership. Section 6 presents the added
value of the EpiSouth project, Section 7 outlines the limitations of the study and Section 8
outlines the conclusions of the midterm evaluation.
EpiSouth Plus Midterm Evaluation Page 8 of 74
22 MMeetthhooddoollooggyy To implement the evaluation strategy including all actions as described in the Terms of
Reference (ToR), evaluation tools were designed. The evaluation, both process and outcome
evaluation includes the following activities:
� Analysis of the project’s documentation
� Analysis and verification of the project’s indicators
� Preparation of tools (questionnaires and interview’s check list) for collecting
information form the institution partners of the Project and Focal Points of the
Countries involved in the EpiSouth Network aimed at evaluating project management
and core activities and network consolidation
� Collection of information from the institution partners of the Project and Points of the
countries involved in the EpiSouth Network
� Communications to be conducted through telephone calls and if there is a need, site
visits to be conducted to key stakeholders (EAHC, DG SANCO, ECDC etc). This will be
optional and only with the agreement of the project leader.
� Preparation of an evaluation report in draft
� Finalisation of the Mid-Term evaluation report
The evaluation process assessed the relativeness, effectiveness, efficiency, sustainability
utility, coherence, completeness, complementarily, coordination and additionally the
processes and outcomes.
2.1 Evaluation Tools
The tools used for the evaluation included the project’s available resources listed below and
the following:
� an evaluation questionnaire (1) for collecting information form the institution
partners of the Project and Focal Points of the Countries involved in the EpiSouth
Network aimed at evaluating project management and core activities (Annex 1, Annex
2, Annex 3, Annex 4, Annex 5, Annex 6, Annex 7)
� an evaluation questionnaire (2) to assess network consolidation (Annex 8)
� a checklist for interviews (Annex 9),
EpiSouth Plus Midterm Evaluation Page 9 of 74
The available resources used were those specified in the ToR including :
i) Documents produced by the Project (Reports, Meeting Minutes, Presentations
and abstracts, Bulletins, Draft of Sustainability Plan etc.)
ii) Information on the use of the Members area of EpiSouth web site (content,
frequency of use, frequency of downloads, etc).
iii) The monitoring sheets filled every six months by each WP leader which were
integral part of the bi-annual reports to DG DEVCO and interim report to DG
SANCO (Four rounds WPs monitoring sheets are available)
iv) The report from October 2011 where the EpiSouth Project was evaluated by DG
DEVCO with a Result Oriented Monitoring (ROM) Mission
v) The report from April 2012 where the EpiSouth Project was evaluated by DG
DEVCO with an evaluation mission for the Instrument for Stability Programme
vi) Preparation of tools (questionnaires and interview’s check list) for collecting
information form the institution partners of the Project and Focal Points of the
Countries involved in the EpiSouth Network aimed at evaluating project
management and core activities
2.2 Questionnaire Dissemination
Questionnaire 1 was divided to eight different questionnaires in accordance to the target
group that was going to be disseminated. Hence each group was able to evaluate documents
and activities that were relevant to the group they belong to. The questionnaires were
disseminated to the following target groups:
� Advisory Board (18 members)
� Focal Points (75 members)
� Steering Committee (20 members)
� WP4 Steering Team (20 members)
� WP5 Steering Team (22 members)
� WP6 Steering Team (32 members)
� WP7 Steering Team (27 members)
EpiSouth Plus Midterm Evaluation Page 10 of 74
� Head of Laboratories members of the Mediterranean Regional Laboratory Network
(MRLN) (23 members)
During the collection period, it was communicated by certain Focal Points that they would
respond collectively by sending one questionnaire. Hence the original list of the members of
the target groups was reviewed accordingly.
2.3 Questionnaire analysis
The questionnaires were entered into an Excel spread sheet and analysed using Epi Info
software. A descriptive analysis of the collected questionnaires is presented in the sections
below. The common variables of the 7 questionnaires were analysed together and
consolidated to produce one common result. Statistical analysis of the results was conducted
exploring differences on the response rate among the EU and Non EU participants using the
fisher exact or chi-square test.
2.4 SWOT analysis
The evaluation strategy used to implement all actions specified in the ToR was based on a
SWOT analysis. SWOT analysis is a strategic planning method used to evaluate the Strengths,
Weaknesses/Limitations, Opportunities, and Threats involved in a project. It involves
specifying the objectives of the project and identifying the internal and external factors that
are favourable and unfavourable to achieve the objectives. The SWOT analysis brings a
clearer common purpose and understanding of factors for success and provides linearity to
the decision making process allowing complex ideas to be presented systematically. The
SWOT analysis not only provides the basis for completing the evaluation tasks and to assess
core capacities and competencies but to also lead to an action plan that will identify the most
distinctive actions that must be addressed immediately, actions that need to be researched
further and actions to be planned for the future.
EpiSouth Plus Midterm Evaluation Page 11 of 74
33 EEvvaalluuaattiioonn RReessuullttss In the following sections the results of the evaluation questionnaires are presented as well as
the results from the evaluation of all available resources provided by the project leadership
(documents, previous evaluations etc) as these are specified in the Methodology section.
3.1 Response Rate
A total of 18 key stakeholders (Advisory Board and Focal Points) were invited to give an
interview on the EpiSouth management and timeframe, the strengths/
weaknesses/opportunities/threats and on the sustainability of the project. A total of 10
interviews were conducted.
A total of 178 questionnaires (EU: 90/178, 51% and Non EU: 88/178, 49%) were
disseminated to 92 stakeholders. The questionnaire collection period was from 5/11/12 until
15/12/12. A total of 109 out of 178 (61%) questionnaires were collected (EU: 73/90, 81%
and Non EU: 36/88, 41%) (p-value: <0.001). Seventy four out of the 109 (68%)
questionnaires collected were from EU countries whereas 36 out of 109 (33%) were from
Non EU countries. In Table 1, the number of questionnaires disseminated (total, EU and Non
EU) as well as the number of questionnaires collected and the response rate by target group
are presented.
Table 1: Response rate of the evaluation questionnaires
TOTAL EU countries Non EU countries
Target
Group Disseminated Collected
Response
Rate Disseminated Collected
Response
Rate Disseminated Collected
Response
Rate
Advisory
Board 17 8 47% 12 71% 5 42% 5 29% 3 60%
Focal
Points -
Quest. 1 47 28 60% 22 47% 18 82% 25 53% 10 40%
Focal
Points -
Quest. 2 50 32 64% 24 48% 22 92% 26 52% 10 38%
Steering
Committee 8 7 88% 5 63% 6 120% 3 38% 1 33%
WP4 ST 24 19 79% 11 46% 9 82% 13 54% 10 77%
WP5 ST 5 3 60% 4 80% 3 75% 1 20% 0 0%
WP6 ST 15 6 40% 5 33% 5 100% 10 67% 1 10%
WP7 ST 12 6 50% 7 58% 5 71% 5 42% 1 20%
Total 178 109 61% 90 51% 73 81%* 88 49% 36 41%*
*p-value: <0.001
EpiSouth Plus Midterm Evaluation Page 12 of 74
3.2 Evaluation of respect of scheduled milestones and deliverables according
to the project Work Packages (WPs)
The EpiSouth Plus partnership, in accordance with the Technical Annex and the annual work
plans, had to produce a total of 10 Deliverables (D) out of which five have been delivered, the
other four are currently in the process of being prepared and one has not started. Table 2
presents the list of deliverables and their status and Table 3 presents the evaluation of the
timely achievement of milestones.
Delays were noted in all WPs. Internal as well as external reasons such as the political
instability in certain countries of the partnership influenced the implementation of the
project. In WP1 the deliverables were produced within an acceptable timeframe but delays
were noted in the organisation of the 1st
Project Meeting that was postponed to a later date
due to the freezing of WP6. Regarding the activities of WP2 no major delays were noted
except in the finalisation of the website. The activities of the WP3 (Evaluation) and especially
the Midterm evaluation was also delayed since it was going to be presented in the 1st
Project
meeting and that meeting was postponed to M26. The Evaluation Plan although it was timely
delivered, in terms of its completeness is should be noted that it was mainly devoted in
listing the time schedule. The delays noted in WP4 were minor and mainly due to the political
instability causing a low response from the partners and due to legal constrains that had to
be taken into consideration regarding the training in the Institute Pasteur in France.
However, the training in the Institute of Pasteur was conducted with only one month of
delay. Activities of WP5 were also delayed but again this was due to the low participation by
members of the steering team due to the geopolitical situation and to the freezing of the
collaboration agreement with the work package co-leader. The decision to freeze WP6
activities that were related to the Epis based secured platform from July 2011 to January
2012 has influenced the timely preparation of milestones and deliverables. Regarding WP7,
the political instability has also delayed the implementation of activities. Moreover, regarding
WP7 activities it should be noted that the methodology and strategy for WP7 has been
revised. This has been done with a stepwise approach started with request of agreement to
the Advisory Board during the Meeting in Brussels in May 2012, sharing of needs at the
WHO-Lyon Meeting in July 2012 and consolidated in the 1st Project Meeting in Rome with
the WP7 steering team. A detailed explanation of the reasons for the delays is outlined in the
Interim Technical report (D1). It should be noted that the project leadership has requested an
EpiSouth Plus Midterm Evaluation Page 13 of 74
amendment in order to reschedule certain activities and to extend at no extra cost the
contract for another 8 months.
Table 2: Deliverables evaluation
Deliverable
Number
Deliverable Title Description As
planned
Status
Until Month (M) 24
1. Interim and final technical
implementation reports,
including financial reports
(WP1)
The Inception (M3) Interim (M17) and
final(M33) technical and financial reports
will be prepared in accordance with the
grant's requirements
M3 –
Inception
M17 –
Interim
Delivered M4
Delivered M17
2. Reports of the Project
Meetings (WP1)
Reports will be done for the AB, SC and
Project Meetings (M4, M17, M30)
M4, M17,
M30
Delivered M5
3. EpiSouth quarterly
electronic Bulletin (WP2)
A quarterly bulletin will be produced and
disseminated with project's news and
focus topics
Quarterly 1st Issue delivered in
M 9 (June 2011)
6 Issues prepared until
September 2012
4. Final Evaluation Report
(WP3)
The final evaluation will rely on indicators
verification, on-line questionnaires and
interviews. The results will be reported in
the final report.
M33 Not started
5. Laboratory Training
packages and
Recommendation for
training and capacity
building program (WP4)
Training packages will be developed on
the basis of the lab needs assessment
(M20) and Recommendation for training
and capacity building program will be
developed on the basis of all the inputs
and lessons learned coming from the
implementation (M29)
M20
M29
In progress
1 training package
completed on Dengue
and Biosafety in the
Laboratory
6. Directory of Regional
Laboratories involved in
surveillance/early
warning system in South
Europe and
Mediterranean area
(WP4)
A Directory of Mediterranean
laboratories will be created in
accordance with needs of geographic and
pathogen coverage
M29 M24
7. Preparedness plans & Risk
management capacity
building materials for
Workshops and Sessions
and Simulation Exercise.
(WP5)
Packages will be developed for all the
capacity building activities planned (M9,
M12, M21, M24, M28)
M9, M12,
M21,
M24, M28
In progress :
One Workshop and
training package
completed on cluster
analysis
Simulation exercise in
progress
8. Strategic document on
Capacity building
development regarding
Preparedness plans & Risk
management procedures
(WP5)
A detailed report will be prepared
describing the strategic approaches to be
utilized (needs assessment, multi-country
workshops and cross border exercises
and related teaching materials)
M29 In progress
9. EPIS based secured
platform interop. with EU
& other EWSs(subject to
ECDC delivery & countries
agreement)& Epi Bulletins
(WP6)
Epi Weekly Bulletin (e-WEB) since the
project's starting (M1) and launching of
the EPIS based secured platform interop.
with EU & other EWSs (subject to ECDC
delivery & countries agreement)
M1 Delivered M1- A total
of 101 E-web bulletins
published from
October 2010-
September 2012.
Delays in launching of
EPIS platform due to
freezing
10. Strategic document on
national/international
issues which may
interact/ interfere with
IHR implementation
(WP7)
Strategic document including guidelines
will be written on the basis of the project
surveys and assessments results.
M29 In progress
EpiSouth Plus Midterm Evaluation Page 14 of 74
Table 3: Milestones Evaluation
Work
Package
Milestones Month Actual Comments
WP1 1st Steering Committee in Luxembourg M3 M4
Sustainability plan M 4 M6
Annual Project Work Plans M4 & M16 M4 & M 16 M5 & M19
2nd Steering Committee & 1st Project Meeting in
Paris
M 16 M24
2nd Project Meeting (with SC) & Final Conference in
Rome
M 29 N/A
WP2 Dissemination plan M 4 M4
Promotional leaflet and outline M 4 M4
EpiSouth-plus website updating M 6 - Continuous – Delays were noted
on the delivering the final
version of the website
Presentations at conferences M 12 M12 A total of 27 presentations See
Section 3.5 - Table 7 for a
detailed list
WP3 Evaluation plan M 4 M4
WPs activities evaluation questionnaires M 14 M24 See Annex 1-7
Networking Evaluation Questionnaires M 15 M24 See Annex 8
Mid-term Evaluation Report M 18 M26 Delays due to delays of 1st
Project Meeting
Presentation of the Mid-term Evaluation results to
the Review Meeting with EC Experts Committees
M 19 M26 Delay in organizing the Project
Meeting
WP4 Meeting of expert committee to set minimum
requirements needed
M 7 M15
Mapping of existing biological expertise M 8 M13-M14
Meeting with heads of Laboratories interested in the
approach and corresponding to the minimum
requirements
M 13 M17
Identification of needs of laboratories for diagnoses
for priority diseases in the region: human, technical
and organizational
M 15 M21
Delays in collecting the
questionnaire due to political
instability
One-week Lab training at IP Paris M 21 M22 A total of 17 out of the 21
selected laboratories
participated
WP5 Report on in-depth core-capacity needs assessment M 8 M21
Workshop 1 and Capacity building Session 1 in
Madrid for 30 people
M 12 M16
Workshop 2 and Capacity building Session 2 in
Madrid for 30 people
M 24 N/A
2 one week training in Algeria (M9 and M22) M 22 Not
completed
Due to internal country level
obstacles both NFP dismissed.
Updated of the Directory of Training and Fellowships M 30 N/A
WP6 Management of the Mediterranean Cross-border
secured platform
M 1 M13-M18
Delays due to WP freezing
Review of functional specification for EPIS M 6 M13-M24
2 One-week stage at InVS of non-EU participant
(M10 - M 22)
M 22 Not
completed
Testing phase for EW Platform in EPIS and
assessment process (M11-M16)
M 16 M13-M24
Launching of EpiSouth/EPIS (if consensus met) after
1st Project Meeting
M 20 N/A
WP7 On-line questionnaire for data collection on
countries needs and constraints in enhancing their
surveillance systems
M 10 N/A New approach (See Interim
Report for further information)
Results of on-line questionnaire and preliminary
report
M 15 M20
On-line questionnaire on national procedural and
legislative aspects relevant to IHR implementation
M 16 N/A New approach (See Interim
Report for further information)
Results of on-line questionnaire and preliminary
report
M 21 N/A New approach (See Interim
Report for further information)
Preliminary strategic document report M 27 N/A
EpiSouth Plus Midterm Evaluation Page 15 of 74
3.2.1 Interview results
In the question if there were there any delays in the project plan of the EpiSouth Plus
project the interviewees responded the following:
� Five interviewees responded that the general meeting should have been organised much
earlier and closer to the middle of the project.
� Four interviewees identified the freezing of WP6 as the most important delay in the
project.
� Three interviewees identified that delays occurred in WP7 and commended that now the
scope has changed.
� Two interviewees identified that WP5 delayed due to lack of agreement with the co-
leader.
� Two interviewees responded that there were no major delays.
� One interviewee responded that the training activities were delayed for 3-6 months
� One interviewee responded that the delays are not the trend in EpiSouth Plus project
though could happen sometimes and basically the cause is dispute on financial affairs.
� Due to limited communication only through the website one responder was uncertain
what delays occurred and for what reason.
In the question on what are the reasons that resulted in delays in the project’s work plan
the interviewees responded the following:
� Financial funding.
� Arab Spring.
� Delays in epidemic intelligence work occurred because of as fear of duplication with ECDC
and the Electronic alert bulletin stopped issuing for three or six months and the different
views and vision between DG SANCO and EPISOUTH. Certain important aspects leading to
duplications were not identified at the beginning of the project.
� The delay in the training activities occurred because of the subject chosen, West Nile
Virus. The training was going to take place in France. However, due to national legislation
issues they could not conduct the training hence it will now be completed in Italy.
� Lack of discussion between the teams sometimes.
EpiSouth Plus Midterm Evaluation Page 16 of 74
� Lack of flexibility.
In the question on whether according to their opinion the issues were resolved within an
acceptable timeframe the interviewees responded the following:
� Five interviewees believed that the delays were not resolved within an acceptable
timeframe
� Not an acceptable timeframe but it was due to the decision of DG SANCO and ECDC (2
interviewees).
� The partnership had a lot of adjustments to make and there are still delays due to the
freezing of WP6 (2 interviewees).
3.3 Evaluation of achievement of project indicators, both for quantitative
and qualitative aspects
In order to achieve the projects objectives a set of process, output and outcome indicators
have been established to measure the level and quality of the achievement.
The indicators were revised by the subcontractor in collaboration with WP1 and WP3 Work
Package Leaders. The revised indicators were included in the amendment requested by the
project leadership and are summarised in Table 4.
Table 4: Indicators Evaluation
INDICATORS Level of Achievement
Specific Objective 1: Establishment of a Mediterranean Regional Laboratories
network (WP4)
Process indicators
Number of participants attending the Meeting organised by the Pasteur Institute for
Laboratories Representatives out of the total number of those selected
Completed - 12 participants out of
18 MRLN analysis team
The list of the laboratories from the EUROMED region eligible to participate in the
network is developed
Completed
Capacities assessment of the laboratories participating in the network is completed Completed
Training material is developed on time Completed (M22)
Output indicators
Number of trainees attending the training courses (>=60%) and the number of
participants attending the meetings organised by the Pasteur Institute (>=60%)
Nineteen laboratories (over the 21
of the MRLN) have proposed a
candidate for this training, but only
17 could participate (7 EU and 10
non-EU) = 80.95%
12 participants out of 18 MRLN
analysis team (66.6%)
>80% satisfied trainees from the training courses
Trainees were very satisfied of the
training and 94% have declared that
the training met their expectations
(16/17)
Number of Laboratories which accept to participate in the Network out of the total
number of those whose standards were adequate to the project’s objectives (50%)
30 laboratories from 21 countries
responded out of 27. A total number
of 26 Human labs and 3 Veterinary
Labs identified. 20 human labs and 3
EpiSouth Plus Midterm Evaluation Page 17 of 74
Veterinary Labs identified fulfilled
the selection criteria (76.6%).
Outcome indicators
Reference procedures available in the recommendation for training and capacity
building program and considered by each country for the collaboration between PH
Institutions and laboratories of the EpiSouth Network
N/A – to be evaluated in the final
evaluation of the project
Laboratory needs in the Mediterranean Area identified and shared with stakeholders
and European and international Institutions
Completed
Number of laboratory exchange of information carried out between the network of
laboratories from EU MS and Non EU countries and include the number of laboratory
generated EWRS/IHR notifications of cross border events
N/A – to be evaluated in the final
evaluation of the project
Specific Objective 2: Promotion of common procedures in interoperable Generic
Preparedness and Risk management among the countries involved in the Network
(WP5)
Process indicators
In-depth capacity needs assessment carried out, based on information collected from
a sample of participating countries
Completed.
21 out of 27 (77.7%) countries
participated in the assessment.
Two Workshops carried out One workshop (Month 16)
2nd
scheduled for M24
Training material and simulation exercise is prepared Training material is prepared
Simulation exercise in progress
Training courses are organised One training course completed
Output indicators
At least 70% of EpiSouth countries participate in the simulation exercise N/A – to be evaluated in the final
evaluation of the project
At least 70% satisfied participants in the simulation exercise N/A – to be evaluated in the final
evaluation of the project
At least 70% of EpiSouth countries attending each Workshop out of the 27 countries
in the Network
47 participants
22 out of 27 ( 81.5%) countries -
institutions
At least 70% satisfied participants from the workshop 7/9 (77.8%) responders rated the
course content as excellent
Outcome indicators
At least 50% of EpiSouth countries consider the usage of the Strategic document on
Capacity building development regarding Preparedness plans & Risk management
procedures
N/A – to be evaluated in the final
evaluation of the project
Increase of collaboration between partners from EU and Non EU countries for the
detection of threats and risk management during the last 6 months of the project
N/A – to be evaluated in the final
evaluation of the project
Specific Objective 3: Enhance Mediterranean Early Warning Systems (EWS) allowing
alerts and Epidemic intelligence information sharing among EpiSouth countries and
developing interoperability with other European Early Warning platforms (WP6)
Process indicators
Epis based cross-border secured platform developed Completed
Reference procedures available and endorsed by countries for information sharing
within EpiSouth secured platform and among it and other EW systems
Completed (October 2011)
Development of eweb bulletins (EpiSouth Weekly Epidemic Intelligence) Completed
Output indicators
>70% satisfied with the platform’s functionality (accessibility, user-friendly,
timeliness)
11/23 (47.8%) responders rated the
functionality of the platform as
Excellent whereas 11/23 (47.8%)
rated it as satisfactorily (See Section
3.9)
Number of eweb bulletins (EpiSouth Weekly Epidemic Intelligence) 101 E-web bulletins published from
October 2010-September 2012
Number of registration in the e-web bulletin mailing list 486 members are registered in the e-
web list (until 28th
November 2012) Outcome indicators
Increase the number of alerts published and their distribution among the Partners
during the last 6 months of the project
N/A – to be evaluated in the final
evaluation of the project
Increase the number of episodes of collaboration within the network between EU and
non-EU countries and between the Network and other EW platforms during the last 6
months of the project
N/A – to be evaluated in the final
evaluation of the project
Willingness of countries to continue the usage of the platform and appreciation of the
platform’s usefulness and need measured through core packages evaluation
N/A – to be evaluated in the final
evaluation of the project
EpiSouth Plus Midterm Evaluation Page 18 of 74
questionnaires
Specific Objective 4: Production of a strategic document, with guidelines based on
assessments and surveys, aimed at facilitating IHR implementation (WP7)
Process indicators
Workshop conducted Completed - 2 workshops in Rome
and Lyon
Literature review report on IHR implementation on the EpiSouth Region is prepared
and areas of priority are identified
Completed
A plan/protocol for the pilot implementation of the guidelines on coordination of
surveillance and response between points of entry and national surveillance systems
is developed
N/A – to be evaluated in the final
evaluation of the project
Output indicators
Number of participants in the workshop Meeting in Lyon: 13/14 participants
Meeting in Rome: 18/18 participants
>70% satisfied with the pilot implementation of the guidelines
N/A – to be evaluated in the final
evaluation of the project
Final report of in depth analysis of priority area (literature review and analysis of
existing monitoring frameworks)
Completed
>70% satisfied with the pilot implementation report N/A – to be evaluated in the final
evaluation of the project
Outcome indicators
Number of countries that consider to adapt the WHO Guidance in their countries on
the basis of the pilot results >=50% measured through core packages evaluation
questionnaires
N/A – to be evaluated in the final
evaluation of the project
Number of EpiSouth countries which have been helped by the EpiSouth WP7
documentation in the identification of priority areas and the IHR implementation (
>=50% measured through core packages evaluation questionnaires)
In the Midterm Evaluation
Questionnaire the “Usefulness” of
the literature review was rated as
Excellent by 7 out of 14 participants
(50%) and 6 out of 14 (42.9%) rated
its usefulness as satisfactory.
3.4 Project Management Evaluation
3.4.1 Evaluation questionnaire analysis
As shown in Table 5, the majority of the responders (>79%) rated as fully effective the project
management and the steering committee as for achieving the project objectives. About 63%
(24/38) believed that the Steering Teams fully assisted in the achievement of objectives and
facilitate the collaboration whereas 37% (14/38) believed that this was only partially
achieved. Almost 68% (26/38) rated as fully effective the communication means and
frequency whereas almost 32% (12/38) rated as partially effective the communication means
and frequency. More than 55% of the responders rated as fully effective the problem –
solving process and the monitoring and evaluation of activities in achieving the projects
objectives and in keeping on track in terms of quality and timeliness.
There were no significant differences between the responses from the EU and Non EU
countries except for the effectiveness of the problem solving process. The Non EU partners
that rated the problem solving process as partially effective were 10 out of 14 (71.4%)
EpiSouth Plus Midterm Evaluation Page 19 of 74
whereas a significant lower percentage of the EU responders (6/24, 25%) rated as partially
effective the problem-solving process (p-value: 0.028).
Table 5: Evaluation Questionnaire 1: Management and timeframe evaluation
Fully Partially Not at all
1. Do you think that the management
(planning and organising) of the project is
transparent and effective for achieving the
project objectives?
31/39 (79.5%) EU: 21/25 (84%)
Non-EU: 10/14 (28.6%)
8/39 (20.5%) EU: 4/25 (16%)
Non-EU:4/14 (28.6%) 0/39 (0%)
2. Do you think that the Steering Committee
is effective for achieving the projects
objectives?
27/34 (79.4%) EU: 18/22 (81.8%)
Non-EU: 9/12 (75%)
7/34 (20.6%) EU: 4/22 (18.2%)
Non-EU: 3/12 (25%) 0/34 (0%)
3. Do you think that the Steering Teams
established for each work package (WP)
are effective in achieving the specific
objective of the WP and in facilitating
collaboration?
24/38 (63.2%) EU: 16/25 (64%)
Non-EU: 8/13 (61.5%)
14/38 (36.8%) EU: 9/25 (36%)
Non-EU: 5/13 (38.5%) 0/38 (0%)
4. Do you think the communication means
and frequency is an effective process?
26/38 (68.4%) EU: 17/25 (68%)
Non-EU: 9/13 (69.2%)
12/38 (31.6%) EU: 8/25 (32%)
Non-EU: 4/13 (30.8%) 0/38 (0%)
5. Do you think that the problem – solving
process was effective for achieving the
project objectives?
21/38 (55.3%) EU: 17/24 (70.8%) *
Non-EU: 4/14 (28.6%) *
16/38 (42.1%) EU: 6/24 (25%)
Non-EU: 10/14 (71.4%)
1/38 (2.6%) EU: 1/24 (4.2%)
Non-EU: 0/14
(0%)
6. Do you think that the monitoring and
evaluation of activities are adequate and
assist in keeping on track in terms of
quality and timeliness?
24/39 (61.5%) EU: 15/25 (60%)
Non-EU: 9/14 (64.3%)
14/39 (35.9%) EU: 9/25 (36%)
Non-EU: 5/14 (35.7%)
1/39 (2.6%) EU: 1/25 (4%)
Non-EU: 0/14
(0%)
* p-value: 0.028
3.4.2 Comments by the questionnaire responders
� The partner web tool is not effective for project management, because there is open
sharing of information and documents, as there is too much segmentation in the
individual WP steering teams and only final documents are posted for the knowledge of
all partners. The WP leader’s coordination can be improved, allowing more sharing and
consultation. The monitoring and evaluation has presented major delays, and so far no
assessment of the quality of the outputs is verifiable, only timeliness.
� We need to have more interactive problem solving process especially with funding
organisations.
� EpiSouth is a complex and ambitious network that has proven its usefulness, its
pertinence and that actually contribute to reinforce the health security in the area. Its
composition (1/3 EU countries 2/3 non-EU countries and the sources of funding i.e.
mainly EU commission) has generated difficulties that has been difficult to overcome.
EpiSouth is to often consider by donors as purely EU network, though it is not the case.
It is the mixing of EU and Non EU countries that does make the rational for such a
network and this should be acknowledged and implemented in the request from
EpiSouth Plus Midterm Evaluation Page 20 of 74
donors. The lack of long term perspective (i.e. sustainability) is also an obstacle to
adequate problem solving in this domain. Nevertheless, despite difficulties EpiSouth is a
very successful network that have been able to cope with very complex issues including
(political instability eg Arab Spring)
� Communication means and frequency - there is a need for frequent update of provided
information regarding the list of participating countries and directories
� Major problems for project and activities management aroused following the Arab
Spring that affected several EpiSouth countries
� The announcement of the coming meetings is too short. As government employee, we
are required to ask for attendance permission via a special committee 3m prior to the
meeting
3.4.3 Interview results
In the question regarding their opinion regarding the management of the EpiSouth Plus the
interviewees responded the following:
� Five interviewees identified that it is a large network difficult to manage it with many
different countries from different political, geographical and cultural background having
different needs.
� The negative points identified in the management are that it is too bureaucratic in terms of
financial allocations. Difficulties were identified in the collaboration between EPISOUTH
and DG SANCO. EPISOUTH and DG SANCO did not have the same view and this caused
many delays especially for WP1 and WP6 (3 interviewees).
� There is enough coordination, stakeholders talk together and management is doing their
best (2 interviewee).
� Two interviewees commended that the management is weak, they should have a stronger
role and are not fully committed and dedicated and that a full time person should have
been employed to overlook activities.
� The management framework of the EpiSouth Plus project was rated by four interviewees as
satisfactory and identified as positive points in this management style the coordination and
efficiency of communications.
EpiSouth Plus Midterm Evaluation Page 21 of 74
� One interviewee identified that the management are facing problems but are dealing with
them well. It might take time but they succeed to manage all issues.
� One interviewee responded that the management is committed and motivated but they do
not have a clear vision in where the project should focus. The management is not reactive
enough but expects others to react. There seems to be confusion between the objectives
and the methods. The network is the objective and is very important but need to build at
this network and to identify the means of its mobilisation (1 interviewee).
� One interviewee commended that they have a clear vision but they do not know how to
achieve it
� One interviewee expressed that the management should complete all deliverables and the
no-cost extension will help this.
� One interviewee commended that the management are not knowledgeable about Middle
East and international work and this affects the efficiency of the management.
� One interviewee commended that the quality of the reports are poor as they are very
descriptive.
3.5 Dissemination Activities Evaluation
The dissemination activities evaluated in this section are the website, the Quarterly EpiSouth
Electronic Bulletin, the EpiSouth Weekly Epi Bulletin (e-WEB) and other dissemination
activities (e.g. presentations and posters presented to conferences and workshops). The
timeliness and level of achievement of milestones of the dissemination activities have been
evaluated in the previous sections.
As shown in Table 6, a total of 7,792 number of visits were recorded from the period of May
2011- June2012. In the same table, the detailed number of visits per six months is presented.
From the results presented, almost a 25% decrease of the number of visits was recorded
from May 2011 to June 2012. However, the geographical coverage has increased from 83
countries in the first six months of the website’s operation to 93 in the last six months.
Table 6: Website statistics
Period Number of Visits
May-September 2011 2,283 visits came from 83 countries/territories
October – December 2011 1,993 visits came from 89 countries/territories
January 2012 – March 2012 1,783 visits came from 104 countries/territories
April 2012 - June 2012 1,733 visits came from 93 countries/territories
Total 7792 total visits
EpiSouth Plus Midterm Evaluation Page 22 of 74
The EpiSouth Plus partnership has achieved a good level of representation in international
conferences promoting the awareness level of the project’s objectives and activities. The
partnership has presented and participated in a total of 27 conferences/meetings. Table 7
presents in detail the number of presentations/ participations per work package.
Table 7: Number of Presentation/ Participations to conference and Meetings by Work Package
WP No Number of Presentations/ Participations to Conferences/ Meetings
WP1/WP2
Coordination
/ Networking
1. Speech at the Cypriot Presidency Conference on Cross Border Health Threats in the EU and
Neighbouring Countries, Nicosia, Cyprus 5 July 2012 (with mention to EpiSouth)
2. Presentation at the Cypriot Presidency Conference on Cross Border Health Threats in the EU and
Neighbouring Countries, Nicosia, Cyprus 5 July 2012 (with mention to EpiSouth)
3. Poster presented at the High Level Conference "EU Health Programmes: results and perspectives",
Brussels, Belgium 3 May 2012
4. Presentation at Inter-Agency Meeting on environmental health in Southern and Eastern
Mediterranean , Marseille, France 14 March 2012
5. Poster presented at the 14th European Health Forum - Workshop on Health Security, Gastein,
Austria 5 October 2011
6. Presentation at the Union for the Mediterranean-Health Forum, Brussels, Belgium, 30 June 2011
7. Presentation at the 4th Eurasia Congress of Infectious Diseases, Sarajevo, Bosnia & Herzegovina, 1-
5 June 2011
8. Presentation at the Forum Mediterraneo in Sanità 2011, Palermo, Italy 24-26 May 2011
9. Presentation at the Subregional Meeting on Shared Solutions to Common Threats - Vaccination
and Vulnerable Populations in South East Europe, Tirana, Albania 28-29 April 2011
10. Presentation at the International Meeting on Emerging Diseases and Surveillance - IMED 2011,
Vienna, Austria 4-7 February 2011
11. Presentation at Mecids Executive Boarding Meeting, Jerusalem, Israel 26-27 November 2010
12. Presentation at the annual meeting of Arbo-zoonet, Rabat, Morroco 22-24 November 2010
13. Presentation to Delegation of Egyptian Ministry of Health , Rome, Italy 19 October 2010
WP4 14. Poster presented at the 15th Annual Conference of the European BioSafety Association (EBSA),
Manchester, UK 11-13 June 2012
15. Poster presented at the 4th Eurasia Congress of Infectious Diseases, Sarajevo, Bosnia &
Herzegovina 1-5 June 2011
16. Presentation at the ENVID Meeting, Antalya, Turkey 12-14 May 2011
17. Presentation at the Final Meeting of the EU Project EQADeBa, Brussels, Belgium 11-12 April 2011
WP6 18. First poster presented at the 15th International Congress on Infectious Diseases, Bangkok, Thailand
13-16 June 2012
19. Second poster presented at the 15th International Congress on Infectious Diseases, Bangkok,
Thailand 13-16 June 2012
20. Presentation at EWRS Meeting, Luxembourg, 24 January 2012
21. Presentation at the 4th Eurasia Congress of Infectious Diseases, Sarajevo, Bosnia & Herzegovina 1-
5 June 2011
22. Presentation at the Advanced Research Workshop on Internet-based Intelligence for Public Health
Emergencies and Disease Outbreak, Haifa, Israel 13-15 March 2011
23. Presentation at the International Meeting on Emerging Diseases and Surveillance - IMED 2011,
Vienna, Austria 4-7 February 2011
24. Presentation at EWRS Meeting, Luxembourg 1-2 December 2010
25. Presentation at the annual meeting of Arbo-zoonet, Rabat, Morroco 22-24 November 2010
WP7 26. Presentation at the Intercountry Meeting on Strengthening of Surveillance and Response
Capacities under IHR 2005, Beirut, Lebanon 26-28 March 2012
27. Presentation at XXIV Meeting of the South-eastern Europe Health Network, Tirana, Albania 10-11
November 2010
3.5.1 Previous Evaluation of the WP2 Website and Electronic Bulletin
An evaluation of the website and quarterly electronic bulletin was conducted by the WP2
Work Package leader. An online questionnaire was created to evaluate the public and
members area of the website. However, a small response rate was achieved with a total of
EpiSouth Plus Midterm Evaluation Page 23 of 74
22 (25.6%) countries’ focal points responding to the questionnaire. Results indicate a good
level of satisfaction and utilization for the project’s website and quarterly electronic bulletin
among the countries’ focal points who participated to the survey. The results of this
evaluation identified certain improvements and issues needed to be resolved especially in
relation to the Network Working Area (NWA). The geographical distribution of the
responding focal points over-represents the European countries included in the network and
under-represents countries of north-Africa, south-east Europe and middle-east (see report
titled “Evaluation of the Network website and quarterly electronic bulletin”, Annex XIII in the
Interim Technical Implementation report).
3.5.2 Evaluation questionnaire analysis
In Table 8 the details of the analysis of the evaluation questionnaires in relation to the
website are presented. The majority of the responders seem to be using the NWA and more
than 80% believe that the website fully contributes to the dissemination of results and
provides the necessary information to the visitor. Almost 78% (28/36) of the responders
rated that the website fully provides the visitor with all the necessary information concerning
the project while 22% rated it as partially. It should be noted that a higher percentage of the
Non EU responders (5/12, 42%) rated that the website partially provides the necessary
information in comparison to EU countries (3/24, 12.5%) (p-value:0.08). The public area of
the website is visited often only by the 36.8% (14/38) of the responders. From the different
sections of the website more than 60% of the responders rated as satisfactory the sections
of the Events, Meeting and Events in the NWA, and the News section whereas more than
50% rated as satisfactory the Network and Bulletin sections. A significant percentage (9 out
of 38, 23.7%) commended that they have faced problems while visiting the website.
Regarding the NWAs the majority of the responders commended they the use them but the
statement that one fourth of the responders faced problems while visiting the site should be
further investigated and resolved by the coordination of the project.
Table 8: Evaluation Questionnaire 1: Website evaluation
Website Fully Partially Not at all
7. Do you think that the website contributes to
the dissemination of the project results?
31/38 (81.6%) EU: 20/25 (80%)
Non-EU: 11/13 (84.6%)
7/38 (18.4%) EU: 5/25 (20%)
Non-EU: 2/13 (15.4%)
0/38 (0%)
8. Do you think that the website provides the
visitor with all the necessary information
concerning the project?
28/36 (77.8%) EU: 21/24 (87.5%)
Non-EU: 7/12 (58.3%)
8/36 (22.2%) EU: 3/24 (12.5%)*
Non-EU: 5/12 (41.7%)*
0/36 (0%)
Often Sometimes Seldom
9. How often do you visit the public area of the
website?
14/38 (36.8%) EU: 9/25 (36%)
Non-EU: 5/13 (38.5%)
18/38 (47.4%) EU: 10/25 (40%)
Non-EU: 8/13 (61.5%)
6/38 (15.8%) EU: 6/25 (24%)
Non-EU: 0/13 (0%)
EpiSouth Plus Midterm Evaluation Page 24 of 74
10. How often do you visit the Network Working
Area (NWA) of the website?
10/35 (28.6%) EU: 6/22 (27.3%)
Non-EU: 4/13 (30.8%)
21/35 (60%) EU: 12/22 (54.5%)
Non-EU: 9/13 (69.2%)
4/35 (11.4%) EU: 4/22 (18.2%)
Non-EU: 0/13 (0%)
Excellent Satisfactory Relatively
Satisfactory
Requires
Improvement
11. How do you rate the
Meeting and Events Area in
the NWA?
10/37 (27%) EU: 7/25 (28%)
Non-EU:3/12
(25%)
24/37 (64.9%) EU: 15/25 (60%)
Non-EU: 9/12 (75%)
2/37 (5.4%) EU: 2/25 (8%)
Non-EU: 0/12 (0%)
1/37 (2.7%) EU: 1/25 (4%)
Non-EU: 0/12 (0%)
12. How do you rate the
Document Area in the
NWA?
17/38 (44.7%) EU: 12/25 (48%)
Non-EU: 5/13
(38.5%)
17/38 (44.7%) EU: 10/25 (40%)
Non-EU: 7/13 (53.8%)
3/38 (7.9%) EU: 2/25 (8%)
Non-EU: 1/13 (7.7%)
1/38 (2.6%) EU: 1/25 (4%)
Non-EU: 0/13 (0%)
13. How do you rate the
Discussion Forum in the
NWA?
3/35 (8.6%) EU: 3/22 (13.6%)
19/35 (54.3%) EU: 10/22 (45.5%)
Non-EU: 9/13 (69.2%)
7/35 (20%) EU: 5/22 (22.7%)
Non-EU: 2/13 (15.4%)
6/35 (17.1%) EU: 4/22 (18.2%)
Non-EU: 2/13
(15.4%)
14. How do you rate the
Activities of the Network
sections in the public area
of the website?
9/37 (24.3%) EU: 7/24 (29.2%)
Non-EU: 2/13
(15.4%)
20/37 (54.1%) EU: 12/24 (50%)
Non-EU: 8/13 (61.5%)
7/37 (18.9%) EU: 4/24 (16.7%)
Non-EU: 3/13 (23.1%)
1/37 (2.7%) EU: 1/24 (4.2%)
Non-EU: 0/13 (0%)
15. How do you rate the Events
section in the public area of
the website?
10/38 (26.3%) EU: 6/25 (24%)
Non-EU: 4/13
(30.8%)
24/38 (63.2%) EU: 16/25 (64%)
Non-EU: 8/13 (61.5%)
4/38 (10.5%) EU: 3/25 (12%)
Non-EU: 1/13 (7.7%)
0/38 (0%)
16. How do you rate the
Bulletin section in the
public area of the website?
17/38 (44.7%) EU: 11/25 (44%)
Non-EU:6/13
(46.2%)
21/38 (55.3%) EU: 14/25 (56%)
Non-EU: 7/13 (53.8%)
0/38 (0%)
0/38 (0%)
17. How do you rate the
Directories section in the
public area of the website?
7/37 (18.9%) EU: 5/24 (20.8%)
Non-EU: 2/13
(15.4%)
23/37 (62.2%) EU: 14/24 (58.3%)
Non-EU: 9/13 (69.2%)
6/37(16.2%) EU: 5/24 (20.8%)
Non-EU: 1/13 (7.7%)
1/37 (2.7 %) EU: 0/24 (0%)
Non-EU: 1/13
(7.7%)
18. How do you rate the News
section in the public area of
the website?
11/38 (28.9%) EU: 8/25 (32%)
Non-EU: 3/13
(23.1%)
24/38 (63.2%) EU: 14/25 (56%)
Non-EU: 10/13 (76.9%)
3/38 (7.9%) EU: 3/25 (12%)
Non-EU: 0/13 (0%)
0/38 (0%)
Yes No
19. Have you faced any
problems while visiting the
website?
9/38 (23.7%) EU: 6/25 (24%)
Non-EU: 3/13 (23.1%)
29/38 (76.3%) EU: 19/25 (76%)
Non-EU: 10/13 (76.9%)
20. Did you use the WP4 NWA?
7/8 (87.5%) EU: 4/4 (100%)
Non-EU: 3/4 (75%)
1/8 (12.5%) Non-EU: 1/4(25%)
21. Did you use the WP5 NWA? 1/2 (50%)
EU: 1/2 (50%)
1/2 (50%) EU: 1/2 (50%)
22. Did you use the WP6 NWA?
3/5 (60%) EU: 3/4 (75%)
2/5 (40%) EU: 1/4 (25%)
Non-EU: 1/1 (100%)
23. Did you use the WP7 NWA?
5/5 (100%) EU: 4/4 (100%)
Non-EU: 1/1 (100%) 0/5 (0%)
* p-value: 0.08
In Table 9, the details of the analysis of the evaluation questionnaires in relation to the
EpiSouth Electronic Bulletin are presented. More than 67% believe that the EpiSouth
Electronic Bulletin fully contributes to the dissemination of results and provides the
necessary information to the visitor. Twelve out of 37 responders (all EU) believe that the
electronic bulletin partially contributes to the dissemination of the project results in
comparison with zero from Non-EU countries (p-value: 0.003). The layout was rated as
EpiSouth Plus Midterm Evaluation Page 25 of 74
excellent and satisfactory by all responders. About 71% (27 out of 38) of the responders
rated the range of content as satisfactory whereas 26.3% (10 out of 38) as excellent. It
should be noted that a higher percentage of the Non EU responders rated the range of
content as satisfactory (12/13, 92.3%) in comparison to EU responders (15/25, 60%) (p-
value: 0.1). Around 26% rated as excellent the range of content. A significant higher
percentage (9/25, 36%) of EU responders rated as excellent the range of content in
comparison with the Non-EU (1/13, 7.7%) (p-value: 0.1). The entire Bulletin is read by 34.2%
(13/38) of the responders (EU: 10/25, 40%, Non-EU: 3/13, 23.1%), 44.7% (17/38) read most
of it (EU: 9/25, 44.7%, Non-EU: 8/13, 61.5%), whereas 18.6% (7/38) read almost half.
Table 9: Evaluation Questionnaire 1: Quarterly EpiSouth Electronic Bulletin evaluation
Quarterly EpiSouth Electronic Bulletin Fully Partially Not at all
24. Do you think that the Quarterly EpiSouth
Electronic Bulletin contributes to the
dissemination of the project results?
25/37 (67.6%) EU: 13/25 (52%)
Non-EU: 12/12 (100%)
12/37 (32.4%) EU: 12/25 (48%)
Non-EU: 0/12 (0%)
0/37 (0%)
25. Do you think that the Quarterly EpiSouth
Electronic Bulletin provides the reader with all
the necessary information concerning the
project?
25/37 (67.6%) EU: 15/24 (62.5%)
Non-EU: 10/13 (76.9%)
12/37 (32.4%) EU: 9/24 (37.5%) *
Non-EU: 3/13 (23.1%)* 0/37 (0%)
Always Often Sometimes Seldom
26. How often do you
read the Quarterly
EpiSouth Electronic
Bulletin?
17/38(44.7%) EU: 11/25 (44%)
Non-EU: 6/13 (46.2%)
13/38(34.2%) EU: 7/25 (28%)
Non-EU: 6/13 (46.2%)
8/38 (21.1%) EU: 7/25 (28%)
Non-EU: 1/13 (7.7%)
0/38 (0%)
All Most Almost half Little
27. How much of the
Quarterly EpiSouth
Electronic Bulletin
do you read?
13/38(34.2%) EU: 10/25 (40%)
Non-EU: 3/13 (23.1%)
17/38(44.7%) EU: 9/25 (36%)
Non-EU: 8/13 (61.5%)
7/38 (18.4%) EU: 5/25 (20%)
Non-EU: 2/13 (15.4%)
1/38 (2.6%) EU: 1/25 (4%)
Non-EU: 0/13
(0%)
Excellent Satisfactory
Relatively
Satisfactory
Requires
Improvement
28. How do you like the
layout and
presentation of the
Quarterly EpiSouth
Electronic Bulletin?
16/38 (42.1%) EU: 13/25 (52%)
Non-EU: 3/13 (23.1%)
21/38 (55.3%) EU: 12/25 (48%)
Non-EU: 9/13 (69.2%)
1/38(2.6%) EU: 0/25 (0%)
Non-EU: 1/13 (7.7%)
0/38 (0%)
29. What do you think
of the range of
content?
10/38 (26.3%) EU: 9/25 (36%)**
Non-EU: 1/13 (7.7%)**
27/38 (71.1%) EU: 15/25 (60%)**
Non-EU: 12/13 (92.3%)**
1/38 (2.6%) EU: 1/25 (4%)
Non-EU: 0/13 (0%)
0/38 (0%)
* p-value: 0.003 ** p-value:0.1
In Table 10, the details of the analysis of the evaluation questionnaires in relation to the
EpiSouth Weekly EPI Bulletin are presented. Almost 79% (30/38) believe that the EpiSouth
Weekly EPI Bulletin fully contributes to the dissemination of new health events occurring in
both Non-EpiSouth and EpiSouth countries. The EpiSouth Weekly EPI Bulletin is always read
by almost 58% (22/38) of the responders whereas 34.2% (13/38) often read it. Around 51.4%
(19/37) of the responders believe that all the information of the e-web bulleting is useful to
EpiSouth Plus Midterm Evaluation Page 26 of 74
their job whereas 43.2% (16/37) believe that most of the information is useful. The layout
and range of content was rated by the majority of the responders as excellent and
satisfactory (>97%).
Table 10: Evaluation Questionnaire 1: EpiSouth Weekly Epi Bulletin (e-WEB)
EpiSouth Weekly Epi Bulletin (e-WEB) Fully Partially Not at all
30. Do you think that the EpiSouth Weekly Epi
Bulletin (e-WEB) contributes to the dissemination
of the new health events occurring in both non-
EpiSouth and EpiSouth countries
30/38 (78.9%) EU: 19/25 (76%)
Non-EU: 11/13 (84.6%)
8/38 (21.1%) EU: 6/25 (24%)
Non-EU: 2/13 (15.4%)
0/38 (0%)
Always Often Sometimes Seldom
31. How often do you read
the EpiSouth Weekly Epi
Bulletin (e-WEB)?
22/38 (57.9%) EU: 12/25 (48%)
Non-EU: 10/13 (76.9%)
13/38 (34.2%) EU: 10/25 (40%)
Non-EU: 3/13 (23.1%)
3/38 (7.9%) EU: 3/25 (12%)
Non-EU: 0/13 (0%)
0/38 (0%)
All Most Almost half Little
32. Do you find the info of
the e-web bulletin useful
for your institute/MoH?
19/37 (51.4%) EU: 10/24 (41.7%)
Non-EU: 9/13 (69.2%)
16/37 (43.2%) EU: 12/24 (50%)
Non-EU: 4/13 (30.8%)
1/37 (2.7%) EU: 1/24 (4.2%)
Non-EU: 0/13 (0%)
1/37(2.7%) EU: 1/24 (4.2%)
Excellent Satisfactory
Relatively
Satisfactory
Requires
Improvement
33. How do you like the
layout and presentation
of the EpiSouth Weekly
Epi Bulletin (e-WEB)?
21/38(55.3%) EU: 14/25 (56%)
Non-EU: 7/13 (53.8%)
17/38 (44.7%) EU: 11/25 (44%)
Non-EU: 6/13 (46.2%) 0/38 (0%) 0/38 (0%)
34. What do you think of the
range of content?
19/38 (50%) EU: 13/25 (52%)
Non-EU: 6/13 (46.2%)
18/38 (47.4%) EU: 11/25 (44%)
Non-EU: 7/13 (53.8%)
1/38 (2.6%) EU: 1/25 (4%)
Non-EU: 0/13 (0%)
0/38 (0%)
3.5.3 Comments by the questionnaire responders
Ideas that could improve the website:
� Many times access to the network area is difficult because of the need of change
constantly the password. In addition, when there is a need of downloading a
document, it is not clear where they are and many clicks are needed to have access to
it. Simplify the route or give some shortcut. It would be useful to simplify the
platform the site for communication purposes and specific training sessions should be
run. For instance, the forum is a vital function in EpiSouth but the utilization is less
than needed or expected in such a network. A specific area for joint preparation of
documents (wiki) would be useful
� We need to activate the forum as for many times no topics are implanted or
discussed losing its weight.
� To have a section on news, frequent updates, partners’ news and activities, links with
other initiatives, etc.
EpiSouth Plus Midterm Evaluation Page 27 of 74
� Sometimes the entry in the platform takes time, maybe a technical problem or errors
of connection
� The publication only in English language. Consider multi-language interface.
� It is not so clear and requires a bit of time to understand the organisation/structure of
the website
� The box "Activities of the Network" very often does not allow to correctly read the
contents of the sections in the Public Area of the website. We do not know whether
this is a problem linked to our information system
� Not able to find easily some information
� It takes sometime each time to understand the system
� Too fragmented. Location of information difficult to identify. Password procedure
should be revised.
Ideas that could improve the Quarterly EpiSouth Electronic Bulletin:
� Do not write dark bold text on dark background.
� I am a passive recipient of the project information and so far the information
available was not useful for my day-to-day work.
� It must be kept short and informative as it is
� Not all information can be included otherwise it will discourage readers
Ideas that could improve the EpiSouth Weekly Epi Bulletin:
� In case of alerts it is warranted to present basic global guidelines on the alert
(disease) management
� E-Web is almost always read in the email version sent by the WP Leader
� I can confirm that info of the e-web bulletin are indeed considered very useful by
both my institute and The MoH - I would expect the same type and quality of
information from other network and to the best of my knowledge very few
international networks produce weekly bulletin with such frequency (weekly) and
adapted to my needs
EpiSouth Plus Midterm Evaluation Page 28 of 74
Further comments
� The WP6 SOP’s have been modified to comply with the numerous EC requests (EAHC,
SANCO..) and therefore does not correspond by what it was intended to be at the
beginning and therefore this should be considered while analysing the results of this
current survey. I can confirm that info of the e-web bulletin is indeed considered very
useful by both my institute and the MoH.
� Used NWA mainly to look up for updated documents - The rest is managed by my
team
� Take into consideration the fact that due to problems of cash flow part of activities
were on in the case were lagging behind.
� In the Public Health Institution List - No Data for R. Macedonia, WP8-Directory of
Human Public Health and Veterinary Public Health Officials for Zoonoses - some data
are not correct with actual situation in the country and need to be updated
� Not applicable the discussion forum is not really used not because it is not well done
but because focal point prefer other mode of communication
3.6 Training Activities Evaluation
3.6.1 Previous Evaluation Activities
An evaluation of the training course conducted under WP4 on “Dengue and biosafety in the
laboratory” which was held in the Institute Pasteur, France from the 2nd
to 6th
of July 2012
was conducted at the end of the training course. In the evaluation both theoretical and
practical parts were evaluated as well as the trainee’s expectations for the second training.
According to this evaluation the trainees were very satisfied with the training and 94%
(16/17) of the trainees declared that the training met their expectations. However, trainees
expressed a request for more practical exercises and laboratory training. The trainees
identified topics to be addressed in the second training including complementary topics to
those addressed during the first training and training on viral culture in BSL3 conditions.
3.6.2 Evaluation questionnaire analysis
In Table 11 the results of the evaluation for the WP4 training activities are presented in
detail. More than 60% of the responders rated all aspects of the training course as Excellent.
Almost 67% of the responders rated as excellent the administrative support, comfort to
EpiSouth Plus Midterm Evaluation Page 29 of 74
meeting venue description of objectives, trainers performance, teaching methods, length of
course and relevance to job. More than 80% rated the information regarding the
participation and the details on the venue as excellent. No major differences were noted
between the responders from the EU and Non EU countries.
Table 11: Evaluation Questionnaire 1: WP4 Training Activities
Poor Average Good Excellent
Coordination and administration
35. Contact with
EPISOUTH prior to the
training courses
1/16(6.3%) Non-EU:
1/8 (12.5%)
1/16 (6.3%) EU: 1/8 (12.5%)
Non-EU: 0/8 (0%)
4/16 (25%) EU: 3/8 (37.5%)
Non-EU:
1/8 (12.5%)
10/16 (62.5%) EU: 4/8 (50%)
Non-EU: 6/8 (75%)
36. Information regarding
your participation
0/16 (0%)
2/16(12.5%) EU: 1/8 (12.5%)
Non-EU: 1/8 (12.5%)
1/16 (6.3%) EU: 1/8 (12.5%)
Non-EU: 0/8 (0%)
13/16 (81.3%) EU: 6/8 (75%)
Non-EU: 7/8 (87.5%)
37. Details on the venue 0/15(0%)
0/15 (0%)
3/15 (20%) EU: 3/8 (37.5%)
Non-EU: 0/7 (0%)
12/15 (80%) EU: 5/8 (62.5%)
Non-EU: 7/7 (100%)
38. Instructions for the
course
0/15 (0%)
1/15 (6.7%) EU: 1/8 (12.5%)
Non-EU: 0/7 (0%)
5/15 (33.3%) EU: 3/8 (37.5%)
Non-EU: 2/7 (28.6%)
9/15 (60%) EU: 4/8 (50%)
Non-EU:5/7 (71.4%)
39. Administrative support 0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 2/8 (25%)
Non-EU: 3/7 (42.9%)
10/15 (66.7%) EU: 6/8 (75%)
Non-EU:4/7 (57.1%)
40. Comfort of meeting
venue
0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 2/8 (25%)
Non-EU: 3/7 (42.9%)
10/15 (66.7%) EU: 6/8 (75%)
Non-EU: 4/7 (57.1%)
41. Trainee’s selection
requirements
0/15 (0%)
0/15 (0%)
7/15 (46.7%) EU: 4/8 (50%)
Non-EU: 3/7 (42.9%)
8/15 (53.3%) EU: 4/8 (50%)
Non-EU: 4/7 (57.1%)
42. Publicity of the course
to target audience
0/15 (0%)
0/15 (0%)
6/15 (40%) EU: 3/8 (37.5%)
Non-EU: 3/7 (42.9%)
9/15 (60%) EU: 5/8 (62.5%)
Non-EU: 4/7 (57.1%)
WORK PACKAGE4: TRAINING COURSE ON DENGUE AND BIOSAFETY IN THE LABORATORY
43. Description of the
objectives
0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 3/8 (37.5%)
Non-EU: 2/7 (28.6%)
10/15 (66.7%) EU: 5/8 (62.5%)
Non-EU: 5/7 (71.4%)
44. Course content 0/15 (0%)
1/15 (0%) EU: 1/8 (12.5%)
Non-EU: 0/7 (0%)
4/15 (26.7%) EU: 3/8 (37.5%)
Non-EU: 1/7 (14.3%)
10/15 (66.7%) EU: 4/8 (50%)
Non-EU: 6/7 (85.7%)
45. Course materials 0/15 (0%)
0/15 (0%)
4/15 (26.7%) EU: 3/8 (37.5%)
Non-EU: 1/7 (14.3%)
11/15 (73.3%) EU: 5/8 (62.5%)
Non-EU: 6/7 (85.7%)
46. Participants (number
and adequacy)
0/15 (0%)
1/15 (6.7%) EU: 1/8 (12.5%)
Non-EU: 0/7(0%)
5/15 (33.3%) EU: 3/8 (37.5%)
Non-EU: 2/7 (28.6%)
9/15 (60%) EU: 4/8 (50%)
Non-EU: 5/7(71.4%)
47. Trainers performance 0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 4/8 (50%)
Non-EU: 1/7 (14.3%)
10/15 (66.7%) EU: 4/8 (50%)
Non-EU: 6/7 (85.7%)
48. Teaching methods 0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 2/8 (25%)
Non-EU: 3/7 (42.9%)
10/15 (66.7%) EU: 6/8 (75%)
Non-EU: 4/7 (57.1%)
49. Length of course 0/15 (0%)
1/15 (6.7%) EU: 1/8 (12.5%)
Non-EU: 0/7 (0%)
4/15 (26.7%) EU: 2/8 (25%)
Non-EU: 2/7 (28.6%)
10/15 (66.7%) EU: 5/8 (62.5%)
Non-EU: 5/7 (71.4%)
50. Time keeping 0/15 (0%)
0/15 (0%)
6/15 (40%) EU: 3/8 (37.5%)
Non-EU: 3/7 (42.9%)
9/15 (60%) EU: 5/8 (62.5%)
Non-EU: 4/7 (57.1%)
51. Opportunity for
networking
0/15 (0%)
0/15 (0%)
6/15 (40%) EU: 4/8 (50%)
Non-EU: 2/7 (28.6%)
9/15 (60%) EU: 4/8 (50%)
Non-EU: 5/7 (71.4%)
52. Relevance to job 0/15 (0%)
0/15 (0%)
5/15 (33.3%) EU: 3/8 (37.5%)
Non-EU: 2/7 (28.6%)
10/15 (66.7%) EU: 5/8 (62.5%)
Non-EU: 5/7 (71.4%)
EpiSouth Plus Midterm Evaluation Page 30 of 74
53. Enjoyment 0/15 (0%)
0/15 (0%)
4/15 (26.7%) EU: 2/8 (25%)
Non-EU: 2/7 (28.6%)
11/15 (73.3%) EU: 6/8 (75%)
Non-EU: 5/7 (71.4%)
54. Work environment 0/15 (0%)
0/15 (0%)
4/15 (26.7%) EU: 3/8 (37.5%)
Non-EU: 1/7 (14.3%)
11/15 (73.3%) EU: 5/8 (62.5%)
Non-EU: 6/7 (85.7%)
Another training course was organised under WP5 activities on cluster analysis. In Table 12
the results of the evaluation of this course are presented. All of the responders rated as
excellent or good the coordination and administration of the course. The course material and
administrative support were rated as excellent by more than 90% of the responders. The
course content, the trainees’ selection requirements and instructions for the course were
rated as excellent by more than 80% of the responders. More than 70% of the responders
rated as excellent the following aspects: details of the venue, comfort of meeting venue,
publicity of the course to target group, description of the objectives, participants, trainers’
performance, teaching methods, enjoyment. Five out of 11 (45.5%) rated the relevance to
job as good and another 45.5% as excellent.
Table 12: Evaluation Questionnaire 1: WP5Training Activities
Poor Average Good Excellent
Coordination and administration
55. Contact with EPISOUTH prior to
the training courses 0/11 (0%)
1/11 (9.1%) EU: 0/6 (0%)
Non-EU:
1/5 (20%)
4/11 (36.4%) EU: 4/6 (66.7%)
Non-EU: 0/5 (0%)
6/11 (54.5%) EU: 2/6 (33.3%)
Non-EU: 4/5 (80%)
56. Information regarding your
participation 0/11 (0%) 0/11 (0%) 5/11 (45.5%) EU: 3/6 (66.7%)
Non-EU: 2/5 (40%)
6/11 (54.5%) EU: 3/6 (33.3%)
Non-EU: 3/5 (60%)
57. Details on the venue 0/11 (0%) 0/11 (0%)
3/11 (27.3%) EU: 1/6 (16.7%)
Non-EU: 2/5 (40%)
8/11 (72.7%) EU: 5/6 (83.3%)
Non-EU: 3/5 (60%)
58. Instructions for the course 0/11 (0%)
1/11 (9.1%) EU: 0/6 (0%)
Non-EU: 1/5 (20%)
1/11 (9.1%) EU: 1/6 (16.7%)
Non-EU: 0/5 (0%)
9/11 (81.8%) EU: 5/6 (83.3%)
Non-EU: 4/5 (80%)
59. Administrative support 0/11 (0%) 0/11 (0%)
1/11 (9.1%) EU: 0/6 (0%)
Non-EU: 1/5 (20%)
10/11 (90.9%) EU: 6/6 (100%)
Non-EU: 4/5 (80%)
60. Comfort of meeting venue 0/10 (0%) 0/10 (0%)
3/10 (30%) EU: 2/5 (40%)
Non-EU: 1/5 (20%)
7/10 (70%) EU: 3/5 (60%)
Non-EU: 4/5 (80%)
61. Trainee’s selection requirements 0/11 (0%) 0/11 (0%)
2/11 (18.2%) EU: 1/6 (16.7%)
Non-EU: 1/5 (20%)
9/11 (81.8%) EU: 5/6 (83.3%)
Non-EU: 4/5 (80%)
62. Publicity of the course to target
audience 0/10 (0%) 1/10 (10%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
2/10 (20%) EU: 1/5 (20%)
Non-EU: 1/5 (20%)
7/10 (70%) EU: 4/5 (80%)
Non-EU: 3/5 (60%)
WORK PACKAGE 5: TRAINING COURSE ON CLUSTER ANALYSIS
63. Description of the objectives 0/10 (0%) 0/10 (0%)
3/10 (30%) EU: 1/5 (20%)
Non-EU: 2/5 (40%)
7/10 (70%) EU: 4/5 (80%)
Non-EU: 3/5 (60%)
64. Course content 0/10 (0%)
1/10 (10%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
1/10 (10%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
8/10 (80%) EU: 5/5 (100%)
Non-EU: 3/5 (60%)
EpiSouth Plus Midterm Evaluation Page 31 of 74
65. Course materials 0/10 (0%) 0/10 (0%)
1/10 (10%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
9/10 (90%) EU: 5/5 (100%)
Non-EU: 4/5 (80%)
66. Participants (number and
adequacy) 0/10 (0%) 1/10 (10%) EU: 0/5 (0%)
Non-EU:
1/5 (20%)
2/10 (20%) EU: 1/5 (20%)
Non-EU:
1/5 (20%)
7/10 (70%) EU: 4/5 (80%)
Non-EU:
3/5 (60%)
67. Trainers performance
0/10 (0%) 1/10 (10%) EU: 0/5 (0%)
Non-EU:
1/5 (20%)
2/10 (20%) EU: 1/5 (20%)
Non-EU: 1/5 (20%)
7/10 (70%) EU: 4/5 (80%)
Non-EU: 3/5 (60%)
68. Teaching methods 0/10 (0%)
1/10 (10%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
2/10 (20%) EU: 0/5 (0%)
Non-EU: 2/5 (40%)
7/10 (70%) EU: 5/5 (100%)
Non-EU: 2/5 (40%)
69. Length of course 0/10 (0%)
2/10 (20%) EU: 1/5 (20%)
Non-EU: 1/5 (20%)
2/10 (20%) EU: 1/5 (20%)
Non-EU: 1/5 (20%)
6/10 (60%) EU: 3/5 (60%)
Non-EU: 3/5 (60%)
70. Time keeping 0/11 (0%)
1/11 (9.1%) EU: 0/6 (0%)
Non-EU: 1/5 (20%)
4/11 (36.4%) EU: 2/6 (33.3%)
Non-EU: 2/5 (40%)
6/11 (54.5%) EU: 4/6 (66.7%)
Non-EU: 2/5 (40%)
71. Opportunity for networking 0/11 (0%)
2/11 (18.2%) EU: 0/6 (0%)
Non-EU: 2/5 (40%)
2/11 (18.2%) EU: 1/6 (16.7%)
Non-EU: 1/5 (20%)
7/11 (63.6%) EU: 5/6 (83.3%)
Non-EU: 2/5 (40%)
72. Relevance to job
0/11 (0%) 1/11 (9.1%) EU: 0/6 (0%)
Non-EU:
1/5 (20%)
5/11 (45.5%) EU: 3/6 (50%)
Non-EU: 2/5 (40%)
5/11 (45.5%) EU: 3/6 (50%)
Non-EU: 2/5 (40%)
73. Enjoyment 0/11 (0%)
1/11 (9.1%) EU: 0/5 (0%)
Non-EU: 1/5 (20%)
2/11 (18.2%) EU: 0/6 (0%)
Non-EU: 2/5 (40%)
9/11 (72.7%) EU: 6/6 (100%)
Non-EU: 2/5 (40%)
74. Work environment 0/11 (0%) 0/11 (0%)
2/11 (18.2%) EU: 0/6 (0%)
Non-EU: 2/5 (40%)
9/11 (81.8%) EU: 6/6 (100%)
Non-EU: 3/5 (60%)
3.6.3 Comments by the responders for WP4 training
� Besides only Dengue and West Nile virus are a priority for the WP4 activities, we
suggest including other emerging infectious diseases like the novel corona virus. The
network could take advantage of this situation because the participation of countries
from the Middle East where the new virus was emerged and go ahead , helping this
countries to improve the EPI and lab surveillance, acting as a bridge between Europe
and this countries to share knowledge and methodology.
3.6.4 Comments by the responders for WP5 training
� The stay would be more supported by the Project organisation even after the period
after the course/training. It would be better to give a bit more information during the
transfers (arrival/departure) at the meeting.
EpiSouth Plus Midterm Evaluation Page 32 of 74
3.7 Documents and deliverables produced Evaluation
3.7.1 Evaluation questionnaire analysis
Table 13 present the evaluation of the deliverables and documents produced by the partnership. The majority of the responders rated the documents as excellent and satisfactory.
Table 13: Evaluation Questionnaire 1: Documents and deliverables produced
Deliverables /
Documents
Methodology
Used
How do you rate the
deliverable
/document?
Performance criteria
Clarity* Consistency** Usefulness/ Effectiveness Conformity to Objectives Completeness***
E* S* RS* RI* E S RS RI E S RS RI E S RS RI E S RS RI E S RS RI E S R RI
75. WP1:
1st
Steering
Committee and
2nd
SC/AB
Meeting reports
2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-
EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-
EU:
1/1
(100%)
0 0 3/6
(50%)
EU:
3/5
(60%)
3/6
(50%)
EU:
2/5
(40%)
Non-EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-
EU:
1/1
(100%)
0 0 3/6
(50%)
EU:
3/5
(60%)
3/6
(50%)
EU:
2/5
(40%)
Non-
EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-EU:
1/1
(100%)
0 0
76. WP1:
Project Work
Plan 1st and 2nd
11/21
(52.4%)
EU:
10/15
(66.7%)
Non-
EU:
1/6
(16.7%)
10/21
(47.6%)
EU:
5/15
(33.3%)
Non-
EU:
5/6
(83.3%)
0 0 11/20
(55%)
EU:
9/14
(64.3%)
Non-
EU:
2/6
(33.3%)
9/20
(45%)
EU:
5/14
(35.7%)
Non-EU:
4/6
(66.7%)
0 0 12/19
(63.2%)
EU:
11/13
(84.6%)
Non-
EU:
1/6
(16.7%)
7/19
(36.8%)
EU:
2/13
(15.4%)
Non-
EU:
5/6
(83.3%)
0 0 9/18
(50%)
EU:
8/12
(66.7%)
Non-
EU:
1/6
(16.7%)
9/18
(50%)
EU:
4/12
(33.3%)
Non-EU:
5/6
(83.3%)
0 0 13/19
(68.4%)
EU:
11/13
(84.6%)
Non-
EU:
2/6
(33.3%)
6/19
(31.6%)
EU:
2/13
(15.4%)
Non-
EU:
4/6
(66.7%)
0 0 10/17
(58.8%)
EU:
9/12
(75%)
Non-EU:
1/5
(20%)
7/17
(41.2%)
EU:
3/12
(25%)
Non-
EU:
4/5
(80%)
0 0 10/16
(62.5%)
EU:
9/11
(81.8%)
Non-EU: 1/5 (20%)
5/16
(31.3%)
EU:
2/11
(18.2)
Non-EU: 3/5
(60%)
1/16
(6.3%)
Non-
EU: 1/5
(20%)
0
77. WP1:
Sustainability
Plan
8/17
(47.1%)
EU:
7/11
(63.6%)
Non-
EU:
1/6
(16.7%)
8/17
(47.1%)
EU:
3/11
(27.3%)
Non-
EU:
5/6
(83.3%)
1/17
(5.9%)
EU:
1/11
(9.1%)
0 8/15
(53.3%)
EU:
6/9
(66.7%)
Non-
EU:
2/6
(33.3%)
5/15
(33.3%)
EU:
2/9
(22.2%)
Non-EU:
3/6
(50%)
2/15
(13.3%)
EU:
1/9
(11.1%)
Non-
EU:
1/6
(16.7%)
0 7/15
(46.7%)
EU:
6/9
(66.7%)
Non-
EU:
1/6
(16.7%)
7/15
(46.7%)
EU:
2/9
(22.2%)
Non-
EU:
5/6
(83.3%)
1/15
(6.7%)
EU:
1/9
(11.1%)
0 6/15
(40%)
EU:
5/9
(55.6%)
Non-
EU:
1/6
(16.7%)
7/15
(46.7%)
EU:
3/9
(33.3%)
Non-EU:
4/6
(66.7%)
2/15
(13.3%)
EU:
1/9
(11.1%)
Non-
EU:
1/6
(16.7%)
0 7/15
(46.7%)
EU:
5/9
(55.6%)
Non-
EU:
2/6
(33.3%)
7/15
(46.7%)
EU:
3/9
(33.3%)
Non-
EU:
4/6
(66.7%)
1/15
(6.7%)
EU:
1/9
(11.1%)
0 6/14
(42.9%)
EU:
5/9
(55.6%)
Non-EU: 1/5 (20%)
7/14
(50%)
EU:
3/9
(33.3%)
Non-
EU:
4/5
(80%)
1/14
(7.1%)
EU:
1/9
(11.1%)
0 6/12
(50%)
EU:
5/8
(62.5%)
Non-EU:
1/4(25%)
6/12
(50%)
EU:
3/8
(37.5%)
Non-EU:
3/4
(75%)
0 0
78. WP1:
D1: Interim
technical
Implementation
report
9/18
(50%)
EU:
8/13
(61.5%)
Non-
EU:
1/5
(20%)
9/18
(50%)
EU:
5/13
(38.5%)
Non-
EU:
4/5
(80%)
0 0 9/16
(56.3%)
EU:
7/11
(63.6%)
Non-
EU:
2/5
(40%)
7/16
(43.8%)
EU:
4/11
(36.4)
Non-EU:
3/5
(60%)
0 0 8/16
(50%)
EU:
6/11
(54.5%)
Non-
EU:
2/5
(40%)
8/16
(50%)
EU:
5/11
(45.5%)
Non-
EU:
3/5
(60%)
0 0 6/16
(37.5%)
EU:
5/11
(45.5%)
Non-
EU:
1/5
(20%)
10/16
(62.5%)
EU:
6/11
(54.5%)
Non-EU: 4/5 (80%)
0 0 9/16
(56.3%)
EU:
7/11
(63.6%)
Non-
EU:
2/5
(40%)
7/16
(43.8%)
EU:
4/11
(36.4%)
Non-
EU:
3/5
(60%)
0 0 6/14
(42.9%)
EU:
5/10
(50%)
Non-EU: 1/4 (25%)
8/14
(57.1%)
EU:
5/10
(50%)
Non-
EU:
3/4
(75%)
0 0 8/14
(57.1%)
EU:
7/10
(70%)
Non-EU: 1/4 (25%)
6/14
(42.9%)
EU:
3/10
(30%)
Non-EU:
3/4
(75%)
0 0
79. WP1:
DEVCO 1st 2nd
and 3rd
Technical
Biannual Reports
11/17
(64.7%)
EU:
9/13
(69.2%)
Non-
EU:
2/4
(50%)
6/17
(35.3%)
EU:
4/13
(30.8%)
Non-
EU:
2/4
(50%)
0 0 9/16
(56.3%)
EU:
7/12
(58.3%)
Non-
EU:
2/4
(50%)
7/16
(43.8 %)
EU:
5/12
(41.7%)
Non-EU:
2/4
(50%)
0 0 8/15
(53.3%)
EU:
6/11
(54.5%)
Non-
EU:
2/4
(50%)
7/15
(46.7%)
EU:
5/11
(45.5%)
Non-
EU:
2/4
(50%)
0 0 6/15
(40%)
EU:
5/11
(45.5%)
Non-
EU: 1/4
(25%)
9/15
(60%)
EU:
6/11
(54.5%)
Non-EU:
3/4
(75%)
0 0 9/15
(60%)
EU:
7/11
(63.6%)
Non-
EU:
2/4
(50%)
6/15
(40%)
EU:
4/11
(36.4%)
Non-
EU:
2/4
(50%)
0 0 7/14
(50%)
EU:
6/11
(54.5%)
Non-EU:
1/3
(33.3%)
7/14
(50%)
EU:
5/11
(45.5%)
Non-
EU:
2/3
(66.7%)
0 0 8/13
(61.5 %)
EU:
7/10
(70%)
Non-EU:
1/3
(33.3%)
5/13
(38.5 %)
EU:
3/10
(30%)
Non-EU:
2/3
(66.7%)
0 0
80. WP2:
Dissemination
plan
10/19
(52.6%)
EU:
9/13
(69.2%)
Non-
EU:
1/6
9/19
(47.4%)
EU:
4/13
(30.8%)
Non-
EU:
5/6
0 0 9/17
(52.9%)
EU:
8/11
(72.7%)
Non-
EU:
1/6
8/17
(47.1 %)
EU:
3/11
(27.3%)
Non-EU:
5/6
(83.3%)
0 0 7/16
(43.8%)
EU:
6/10
(60%)
Non-
EU:
1/6
9/16
(56.3%)
EU:
4/10
(40%)
Non-
EU:
5/6
0 0 9/17
(52.9%)
EU:
8/11
(72.7%)
Non-
EU:
1/6
8/17
(47.1 %)
EU:
3/11
(27.3%)
Non-EU:
5/6
(83.3%)
0 0 10/17
(58.8%)
EU:
8/11
(72.7%)
Non-
EU:
2/6
7/17
(41.2%)
EU:
3/11
(27.3%)
Non-
EU:
4/6
0 0 7/15
(46.7%)
EU:
6/10
(60%)
Non-EU:
1/5
(20%)
8/15
(53.3%)
EU:
4/10
(40%)
Non-
EU:
4/5
0 0 8/13
(61.5%)
EU:
7/8
(87.5%)
Non-EU:
1/5
(20%)
5/13
(38.5%)
EU:
1/8
(12.5%)
Non-EU:
4/5
(80%)
0 0
EpiSouth Plus Midterm Evaluation Page 33 of 74
Deliverables /
Documents
Methodology
Used
How do you rate the
deliverable
/document?
Performance criteria
Clarity* Consistency** Usefulness/ Effectiveness Conformity to Objectives Completeness***
E* S* RS* RI* E S RS RI E S RS RI E S RS RI E S RS RI E S RS RI E S R RI
(16.7%) (83.3%) (16.7%) (16.7%)
(83.3%) (16.7%) (33.3%) (66.7%) (80%)
81. WP2:
Evaluation
survey of
website
9/19
(47.4%)
EU:
7/13
(53.8%)
Non-
EU:
2/6
(33.3%)
10/19
(52.6%)
EU:
6/13
(46.2%)
Non-
EU:
4/6
(66.7%)
0 0 9/18
(50%)
EU:
7/12
(58.3%)
Non-
EU:
2/6
(33.3%)
8/18
(44.4%)
EU:
4/12
(33.3%)
Non-EU:
4/6
(66.7%)
1/18
(5.6%)
EU:
1/12
(8.3%)
0 7/17
(41.2%)
EU:
6/11
(54.5%)
Non-
EU:
1/5
(20%)
10/17
(58.8%)
EU:
5/11
(45.5%)
Non-
EU:
5/6
(83.3%)
0 0 8/17
(47.1%)
EU:
6/11
(54.5%)
Non-
EU:
2/6
(33.3%)
8/17
(47.1%)
EU:
4/11
(36.4%)
Non-EU:
4/6
(66.7%)
1/17
(5.9%)
EU:
1/11
(9.1%)
0 7/17
(41.2%)
EU:
5/11
(45.5%)
Non-
EU:
2/6
(33.3%)
10/17
(58.8%)
EU:
6/11
(54.5%)
Non-
EU:
4/6
(66.7%)
0 0 6/15
(40 %)
EU:
5/10
(50%)
Non-EU: 1/5 (20%)
9/15
(60%)
EU:
5/10
(50%)
Non-
EU:
4/5
(80%)
0 0 6/14
(42.9 %)
EU:
5/9
(55.6%)
Non-EU: 1/5 (20%)
8/14
(57.1%)
EU:
4/9
(44.4%)
Non-EU: 4/5
(80%)
0 0
82. WP2:
Project Outline
10/19
(52.6%)
EU:
9/13
(69.2%)
Non-
EU:
1/6
(16.7%)
9/19
(47.4%)
EU:
4/13
(30.8%)
Non-
EU:
5/6
(83.3%)
0 0 9/18
(50%)
EU:
8/12
(66.7%)
Non-
EU:
1/6
(16.7%)
9/18
(50%)
EU:
4/12
(33.3%)
Non-EU:
5/6
(83.3%)
0 0 8/17
(47.1 %)
EU:
7/11
(63.6%)
Non-
EU:
1/6
(16.7%)
9/17
(52.9%)
EU:
4/11
(36.4%)
Non-
EU:
5/6
(83.3%)
0 0 8/17
(47.1
%) EU:
7/11
(63.6%)
Non-
EU:
1/6
(16.7%)
9/17
(52.9%)
EU:
4/11
(36.4%)
Non-EU:
5/6
(83.3%)
0 0 9/17
(52.9%)
EU:
7/11
(63.6%)
Non-
EU:
2/6
(33.3%)
8/17
(47.1 %)
EU:
4/11
(36.4%)
Non-
EU:
4/6
(66.7%)
0 0 8/15
(53.3%)
EU:
7/10
(63.6%)
Non-EU:
1/5 (20%)
7/15
(46.7%)
EU:
3/10
(30%)
Non-
EU: 4/5
(80%)
0 0 7/14
(50%)
EU:
6/9
(66.7%)
Non-EU:
1/5 (20%)
7/14
(50%)
EU:
3/9
(33.3%)
Non-EU:
4/5
(80%)
0 0
83. WP3:
Evaluation Plan
10/16
(62.5%)
EU:
8/11
(72.7%)
Non-
EU:
2/5
(40%)
4/16
(25%)
EU:
1/11
(9.1%)
Non-
EU:
3/6
(50%)
2/16
(12.5%)
EU:
2/11
(18.2%)
0 8/16
(50%)
EU:
6/10
(60%)
Non-
EU:
2/6
(33.3%)
6/16
(37.5%)
EU:
2/10
(20%)
Non-EU:
4/6
(66.7%)
2/16
(12.5%)
EU:
2/10
(20%)
0 6/15
(40%)
EU:
5/9
(55.6%)
Non-
EU:
1/6
(16.7%)
8/15
(53.3%)
EU:
3/9
(33.3%)
Non-
EU:
5/6
(83.3%)
1/15
(6.7%)
EU:
1/9
(11.1%)
0 7/15
(46.7%)
EU:
5/9
(55.6%)
Non-
EU:
2/6
(33.3%)
7/15
(46.7%)
EU:
3/9
(33.3%)
Non-EU:
4/6
(66.7%)
1/15
(6.7%)
EU:
1/9
(11.1%)
0 6/15
(40%)
EU:
5/9
(55.6%)
Non-
EU:
1/6
(16.7%)
7/15
(46.6%)
EU:
2/9
(22.2%)
Non-
EU:
5/6
(83.3%)
2/15
(13.3%)
EU:
2/9
(22.2%)
0 5/13
(38.5%)
EU:
4/8
(50%)
Non-EU:
1/5
(20%)
6/13
(46.2%)
EU:
2/8
(25%)
Non-
EU:
4/5
(80%)
2/13
(15.4%)
EU:
2/8
(25%)
0 6/11
(54.5%)
EU:
5/6
(83.3%)
Non-EU:
1/5
(20%)
5/11
(45.5 %)
EU:
1/6
(16.7%)
Non-EU:
4/5
(80%)
0 0
84. WP4:
Report of Lab
Experts Meeting
16/28
(57.1 %)
EU:
11/19
(57.9%)
Non-
EU:
5/9
(55.6%)
12/28
(42.9 %)
EU:
8/19
(42.1%)
Non-
EU:
4/9
(44.4%)
0 0 16/27
(59.3 %)
EU:
12/19
(63.2%)
Non-
EU:
4/8
(50%)
11/27
(40.7 %)
EU:
7/19
(36.8%)
Non-EU:
4/8
(50%)
0 15/27
(55.6 %)
EU:
10/18
(55.6%)
Non-
EU:
5/9
(55.6%)
12/27
(44.4%)
EU:
8/18
(44.4%)
Non-
EU:
4/9
(44.4%)
0 0 14/27
(51.9%)
EU:
9/18
(50%)
Non-
EU:
5/9
(55.6%)
12/27
(44.4%)
EU:
8/18
(44.4%)
Non-EU:
4/9
(44.4%)
1/27
(3.7%)
EU:
1/18
(5.6%)
0 12/27
(44.4 %)
EU:
7/18
(38.9%)
Non-EU
EU:
5/9
(55.6%)
14/27
(51.9%)
EU:
10/18
(55.6%)
Non-
EU:
4/9
(44.4%)
1/27
(3.7 %)
EU:
1/18
(5.6%)
0 12/26
(46.2%)
EU:
8/17
(47.1%)
Non-EU:
4/9
(44.4%)
13/26
(50%)
EU:
8/17
(47.1%)
Non-
EU:
5/9
(55.6%)
1/26
(3.8%)
EU:
1/17
(5.9%)
0 14/25
(56%)
EU:
9/16
(56.3%)
Non-EU:
5/9
(55.6%)
11/25
(44%)
EU:
7/16
(43.8%)
Non-EU:
4/9
(44.4%)
0 0
85. WP4:
Report of Heads
of Lab Meeting
18/31
(58.1%)
EU:
8/18
(44.4%)
Non-
EU:
10/13
(76.9%)
13/31
(41.9%)
EU:
10/18
(55.6%)
Non-
EU:
3/13
(23.1%)
0 0 19/30
(63.3%)
EU:
9/18
(50%)
Non-
EU:
10/12
(83.3%)
11/30
(36.7%)
EU:
9/18
(50%)
Non-EU:
2/12
(16.7%)
0 0 17/30
(56.7%)
EU:
9/17
(52.9%)
Non-
EU:
8/13
(61.5%)
12/30
(40 %)
EU:
7/17
(41.2%)
Non-
EU:
5/13
(38.5%)
1/30
(3.3%)
EU:
1/17
(5.9%)
0 13/29
(44.8%)
EU:
6/16
(37.5%)
Non-
EU:
7/13
(53.8%)
14/29
(48.3%)
EU:
8/16
(50%)
Non-EU:
6/13
(46.2%)
2/29
(6.9%)
EU:
2/16
(12.5%)
0 15/29
(51.7%)
EU:
5/16
(31.3%)
Non-
EU:
10/13
(76.9%)
14/29
(48.3%)
EU:
11/16
(68.8%)
Non-EU
3/13
(23.1%)
0 0 15/28
(53.6%)
EU:
7/16
(43.8%)
Non-EU:
8/12
(66.7%)
12/28
(42.9%)
EU:
8/16
(50%)
Non-
EU:
4/12
(33.3%)
1/28
(3.6%)
EU:
1/16
(6.3%)
0 15/27
(55.6%)
EU:
7/15
(46.7%)
Non-EU:
8/12
(66.7%)
11/27
(40.7%)
EU:
7/15
(46.7%)
Non-EU:
4/12
(33.3%)
1/27
(3.7%)
EU:
1/15
(6.7%)
0
86. WP5:
Questionnaire –
in depth core
capacities
assessment
(Note: to be
officially shared
in the 1st Project
Meeting, but
annexed to the
SANCO interim
Report and in
12/20
(60%)
EU:
10/16
(62.5%)
Non-
EU:
2/4
(50%)
6/20
(30%)
EU:
4/16
(25%)
Non-
EU:
2/4
(50%)
2/20
(10%)
EU:
2/16
(12.5%)
0 11/18
(61.1%)
EU:
9/14
(64.3%)
Non-
EU:
2/4
(50%)
6/18
(33.3%)
EU:
4/14
(28.6%)
Non-EU:
2/4
(50%)
1/18
(5.6%)
EU:
1/14
(7.1%)
0 9/18
(50%
EU:
8/14
(57.1%)
Non-
EU:
1/4
(25%)
8/18
(44.4%)
EU:
5/14
(35.7%)
Non-
EU:
3/4
(75%)
1/18
(5.6%)
EU:
1/14
(7.1%)
0 9/18
(50%)
EU:
7/14
(50%)
Non-
EU:
2/4
(50%)
7/18
(38.9%)
EU:
5/14
(35.7%)
Non-EU:
2/4
(50%)
2/18
(11.1%)
EU:
2/14
(14.3%)
0 9/17
(52.9%)
EU:
8/14
(57.1%)
Non-
EU:
1/3
(33.3%)
5/17
(29.4%)
EU:
3/14
(21.4%)
Non-
EU:
2/3
(66.7%)
3/17
(17.6%)
EU:
3/14
(21.4%)
0 8/17
(47.1%)
EU:
7/14
(50%)
Non-EU:
1/3
(33.3%)
8/17
(47.1%)
EU:
6/14
(42.9%)
Non-
EU:
2/3
(66.7%)
1/17
(5.9%)
EU:
1/14
(7.1%)
0 11/16
(68.8%)
EU:
10/13
(76.9%)
Non-EU:
1/3
(33.3%)
4/16
(25%)
EU:
2/13
(15.4%)
Non-EU:
2/3
(66.7%)
1/16
(6.3%)
EU:
1/13
(7.7%)
0
EpiSouth Plus Midterm Evaluation Page 34 of 74
Deliverables /
Documents
Methodology
Used
How do you rate the
deliverable
/document?
Performance criteria
Clarity* Consistency** Usefulness/ Effectiveness Conformity to Objectives Completeness***
E* S* RS* RI* E S RS RI E S RS RI E S RS RI E S RS RI E S RS RI E S R RI
WP5ENWA)
87. WP5:
Workshop and
capacity building
session 1
Training Material
13/22
(59.1%)
EU:
11/18
(61.1%)
Non-
EU:
2/4
(50%)
7/22
(31.8%)
EU:
6/18
(33.3%)
Non-
EU:
1/4
(25%)
2/22
(9.1%)
EU:
1/18
(5.6%)
Non-
EU:
1/4
(25%)
0 12/20
(60%)
EU:
10/16
(62.5%)
Non-
EU:
2/4
(50%)
5/20
(25%)
EU:
4/16
(25%)
Non-EU: 1/4 (25%)
3/20
(15%)
EU:
2/16
(12.5%)
Non-
EU:
1/4
(25%)
0 10/20
(50%)
EU:
8/16
(50%)
Non-
EU:
2/4
(50%)
8/20
(40%)
EU:
7/16
(43.8%)
Non-
EU:
1/4
(25%)
2/20
(10%)
EU:
1/16
(6.3%)
Non-
EU:
1/4
(25%)
0 9/19
(47.4%)
EU:
8/15
(53.3%)
Non-
EU:
1/4
(25%)
8/19
(42.1%)
EU:
6/15
(40%)
Non-EU:
2/4
(50%)
2/19
(10.5%)
EU:
1/15
(6.7%)
Non-
EU:
1/4
(25%)
0 10/20
(50%)
EU:
8/16
(50%)
Non-
EU:
2/4
(50%)
7/20
(35%)
EU:
6/16
(37.5%)
Non-
EU:
1/4
(25%)
2/20
(10%)
EU:
1/16
(6.3%)
Non-
EU:
1/4
(25%)
1/20
(5%)
EU:
1/6
(6.3%)
10/18
(55.6 %)
EU:
9/15
(60%)
Non-EU:
1/3
(33.3%)
6/18
(33.3%)
EU:
5/15
(33.3%)
Non-
EU:
1/3
(33.3%)
2/18
(11.1 %)
EU:
1/15
(6.7%)
Non-
EU:
1/3
(33.3%)
0 9/17
(52.9%)
EU:
5/14
(57.1%)
Non-EU:
1/3
(33.3%)
6/17
(35.3%)
EU:
5/14
(35.7%)
Non-EU:
1/3
(33.3%)
1/17
(5.9%)
Non-
EU:
1/3
(33.3%)
1/17
(5.9%)
EU:
1/14
(7.1%)
88. WP6:
Plan of Actions
Note: Internal:
Road Map with
ECDC – annexed
to the interim
Report
4/10
(40%)
EU:
4/9
(44.4%)
6/10
(60%)
EU:
5/9
(55.6%)
Non-
EU:
1/1
(100%)
0 0 3/9
(33.3%)
EU:
3/8
(37.5%)
4/9
(44.4%)
EU:
4/8
(50%)
Non-EU:
1/1
(100%)
2/9
(11.1%)
EU:
1/8
(12.5%)
0 3/9
(33.3%)
EU:
3/8
(37.5%)
4/9
(44.4%)
EU:
3/8
(37.5%)
Non-
EU:
1/1
(100%)
2/9
(22.2%)
EU:
2/8
(25%)
0 3/9
(33.3%)
EU:
3/8
(37.5%)
5/9
(55.6%)
EU:
4/8
(50%)
Non-EU:
1/1
(100%)
1/9
(11.1%)
EU:
1/8
(12.5%)
0 3/9
(33.3%)
EU:
3/8
(37.5%)
5/9
(55.6%)
EU:
4/8
(50%)
Non-
EU:
1/1
(100%)
1/9
(11.1%)
EU:
1/8
(12.5%)
0 4/9
(44.4%)
EU:
4/8
(50%)
5/9
(55.6%)
EU:
4/8
(50%)
Non-
EU:
1/1
(100%)
0 0 3/8
(37.5%)
EU:
3/7
(42.9%)
5/8
(62.5%)
EU:
4/7
(57.1%)
Non-EU:
1/1
(100%)
0 0
89. WP6:
SOP’s (Note: to
be officially
shared in the 1st
Project Meeting,
but annexed to
the SANCO
interim Report
and in
WP6ENWA)
9/18
(50%)
EU:
8/13
(61.5%)
Non-
EU:
1/5
(20%)
8/18
(44.4%)
EU:
4/13
(30.8%)
Non-
EU:
4/5
(80%)
1/18
(5.6%)
EU:
1/13
(7.7%)
0 8/17
(47.1%)
EU:
7/12
(58.3%)
Non-
EU:
1/5
(20%)
8/17
(47.1%)
EU:
4/12
(33.3%)
Non-EU:
4/5
(80%)
1/17
(5.9%)
EU:
1/12
(8.3%)
0 8/16
(50%)
EU:
7/11
(63.6%)
Non-
EU:
1/5
(20%)
8/16
(50%)
EU:
4/11
(36.4%)
Non-
EU:
4/5
(80%)
0 0 7/16
(43.8%)
EU:
6/11
(54.5%)
Non-
EU:
1/5
(20%)
9/16
(56.3%)
EU:
5/11
(45.5%)
Non-EU:
4/5
(80%)
0 0 8/16
(50%)
EU:
7/11
(63.6%)
Non-
EU:
1/5
(20%)
6/16
(37.5%)
EU:
2/11
(18.2%)
Non-
EU:
4/5
(80%)
1/16
(6.3%)
EU:
1/11
(9.1%)
1/16
(6.3%)
EU:
1/11
(9.1%)
6/15
(40%)
EU:
5/10
(50%)
Non-EU:
1/5
(20%)
7/15
(46.7%)
EU:
3/10
(30%)
Non-
EU:
4/5
(80%)
2/15
(13.3%)
EU:
2/10
(20%)
0 7/14
(50%)
EU:
6/9
(66.7%)
Non-EU:
1/5
(20%)
6/14
(42.9%)
EU:
2/9
(22.2%)
Non-EU:
4/5
(80%)
1/14
(7.1%)
EU:
1/9
(11.1%)
0
90. WP6:
Evaluation of
secure platform
13/18
(72.2%)
EU:
11/14
(78.6%)
Non-
EU:
2/5
(50%)
4/18
(22.2%)
EU:
2/14
(14.3%)
Non-
EU:
2/5
(50%)
1/18
(5.6%)
EU:
1/14
(7.1%)
0 10/16
(62.5%)
EU:
9/12
(75%)
Non-
EU: 1/4
(25%)
5/16
(31.3%)
EU:
2/12
(16.7%)
Non-EU:
3/4
(75%)
1/16
(6.3%)
EU:
1/12
(8.3%)
0 12/16
(75%)
EU:
10/12
(83.3%)
Non-
EU:
2/4
(50%)
3/16
(18.8%)
EU:
1/12
(8.3%)
Non-
EU:
2/4
(50%)
1/16
(6.3%)
EU:
1/12
(8.3%)
0 10/16
(62.5%)
EU:
9/12
(75%)
Non-
EU: 1/4
(25%)
5/16
(31.3%)
EU:
2/12
(16.7%)
Non-EU:
3/4
(75%)
1/16
(6.3%)
EU:
1/12
(8.3%)
0 12/16
(75%)
EU:
10/12
(83.3%)
Non-
EU:
2/4
(50%)
3/16
(18.8%)
EU:
1/12
(8.3%)
Non-
EU:
2/4
(50%)
1/16
(6.3%)
EU:
1/12
(8.3%)
0 10/15
(66.7%)
EU:
8/11
(72.7%)
Non-EU:
2/4
(50%)
4/15
(26.7%)
EU:
2/11
(18.2%)
Non-
EU:
2/4
(50%)
1/15
(6.7%)
EU:
1/11
(9.1%)
0 10/14
(71.4%)
EU:
8/10
(80%)
Non-EU:
2/4
(50%)
4/14
(28.6%)
EU:
2/10
(20%)
Non-EU:
2/4
(50%)
0 0
91. WP7:
Final report of
1st investigation
Note: Shared
only with the
WP7ST members
- annexed to the
interim Report
4/12
(33.3%)
EU:
4/11
(36.4%)
7/12
(58.3%)
EU:
6/11
(54.5%)
Non-
EU:
1/1
(100%)
1/12
(8.3%)
EU:
1/11
(9.1%)
0 4/11
(36.4%)
EU:
4/10
(40%)
6/11
(54.5%)
EU:
5/10
(50%)
Non-EU:
1/1
(100%)
1/11
(9.1%)
EU:
1/10
(10%)
0 3/11
(27.3%)
EU:
2/10
(20%)
Non-
EU:
1/1
(100%)
7/11
(63.6%)
EU:
7/10
(70%)
1/11
(9.1%)
EU:
1/10
(10%)
0 3/11
(27.3%)
EU:
3/10
(30%)
7/11
(63.6%)
EU:
6/10
(60%)
Non-EU:
1/1
(100%)
1/11
(9.1%)
EU:
1/10
(10%)
0 4/11
(36.4%)
EU:
4/10
(40%)
6/11
(54.5%)
EU:
5/10
(50%)
Non-
EU:
1/1
(100%)
1/11
(9.1%)
EU:
1/10
(10%)
0 4/11
(36.4%)
EU:
4/10
(40%)
5/11
(45.5%)
EU:
4/10
(40%)
Non-
EU:
1/1
(100%)
2/11
(18.2%)
EU:
2/10
(20%)
0 5/10
(50%)
EU:
4/9
(44.4%)
Non-EU:
1/1
(100%)
5/10
(50%)
EU:
5/9
(55.6%)
0 0
92. WP7:
Report from
meeting in
Rome, July 2011
2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-
EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-EU:
1/1
(100%)
0 0 3/6
(50%)
EU:
2/5
(40%)
Non-
EU:
1/1
(100%)
2/6
(33.3%)
EU:
2/5
(40%)
1/6
(16.7%)
EU:
1/5
(20%)
0 2/6
(33.3%)
EU:
2/5
(40%)
2/6
(33.3%)
EU:
2/5
(40%)
2/6
(33.3%)
EU:
1/5
(20%)
Non-
EU:
1/1
(100%)
0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-
EU:
1/1
(100%)
0 0 2/6
(33.3%)
EU:
2/5
(40%)
3/6
(50%)
EU:
3/5
(60%)
1/6
(16.7%)
Non-
EU:
1/1
(100%)
0 2/6
(33.3%)
EU:
2/5
(40%)
4/6
(66.7%)
EU:
3/5
(60%)
Non-EU:
1/1
(100%)
0 0
93. WP7:
Final report of in
10/20
(50%)
9/20
(45%)
1/20
(5%)
0 9/19
(47.4%)
9/19
(47.4%)
1/19
(5.3%)
0 7/17
(41.2%)
10/17
(58.8%)
0 0 7/17
(41.2%)
10/17
(58.8%)
0 0 9/18
(50%)
8/18
(44.4%)
1/18
(5.6%)
0 6/17
(35.3%)
10/17
(58.8%)
1/17
(5.9%)
0 9/16
(56.3%)
7/16
(43.8%)
0 0
EpiSouth Plus Midterm Evaluation Page 35 of 74
Deliverables /
Documents
Methodology
Used
How do you rate the
deliverable
/document?
Performance criteria
Clarity* Consistency** Usefulness/ Effectiveness Conformity to Objectives Completeness***
E* S* RS* RI* E S RS RI E S RS RI E S RS RI E S RS RI E S RS RI E S R RI
depth analysis of
priority area
(literature
review and
analysis of
existing
monitoring
frameworks)
(NOTE: Shared
only with the
WP7ST members
- annexed to the
interim Report &
website)
EU:
9/16
(56.3%)
Non-
EU: 1/4
(25%)
EU:
6/16
(37.5%)
Non-
EU:
3/4
(75%)
EU:
1/16
(6.3%)
EU:
8/15
(53.3%)
Non-
EU: 1/4
(25%)
EU:
6/15
(40%)
Non-EU:
3/4
(75%)
EU:
1/15
(6.7%)
EU:
6/13
(46.2%)
Non-
EU: 1/4
(25%)
EU:
7/13
(53.8%)
Non-
EU:
3/4
(75%)
EU:
6/13
(46.2%)
Non-
EU: 1/4
(25%)
EU:
7/13
(53.8%)
Non-EU:
3/4
(75%)
EU:
8/14
(57.1%)
Non-
EU: 1/4
(25%)
EU:
5/14
(35.7%)
Non-
EU:
3/4
(75%)
EU:
1/14
(7.1%)
EU:
5/13
(38.5%)
Non-EU:
1/4 (25%)
EU:
7/13
(53.8%)
Non-
EU:
3/4
(75%)
EU:
1/13
(7.7%)
EU:
8/13
(61.5%)
Non-EU:
1/3
(33.3%)
EU:
5/13
(38.5%)
Non-EU:
2/3
(66.7%)
* Clarity: free from obscurity and easy to understand **Consistency: logical coherence and accordance with the facts ***Completeness: complete and entire; having everything that is needed
*E: Excellent S: Satisfactory RS: Relatively Satisfactory RI: Requires Improvement
EpiSouth Plus Midterm Evaluation Page 36 of 74
3.8 Meetings/Working Groups Evaluation
3.8.1 Previous Evaluation of the 1st WP7 Steering Team meeting
An evaluation of the 1st
Work Package 7 Steering Team Meeting was conducted. 14 out of the 17 participants completed the questionnaire. The meeting was rated as successful by 85% of the participants. 83% thought enough
information was available to identify the capacities to address as priority. A total of 77% agreed that the method adopted favoured the development of a wide sense of ownership of the results obtained; no participant felt this sense of
ownership was not reached altogether.
3.8.2 Evaluation questionnaire analysis
In Table 14 the results of the evaluation of the EpiSouth Plus Meetings conducted from the period of October 2010 to September 2012 are presented.
Table 14: Evaluation Questionnaire 1: Meetings and Workshops
The meeting’s usefulness and effectiveness
for the development of the project’s
processes
Material for discussion disseminated
contributed to the achievement of the
project objectives
Quality of the material
disseminated for discussion
How do you rate the coordination of
discussion?
How do you rate the quality of the
meetings report (did it include all
issues raised during the meeting)?
E* S* RS* RI* E S RS RI E S RS RI E S RS RI E S RS RI
94. 1st
Steering Committee
(WP1)
4/7 (57.1%) EU: 3/6 (50%)
Non-EU: 1/1 (100%)
2/7 (28.6%) EU: 2/6 (33.3%)
1/7 (14.3%) EU: 1/6 (16.7%)
0
3/7 (42.9%) EU: 2/6 (33.3%)
Non-EU:
1/1 (100%)
4/7 (57.1%) EU: 4/6(66.7%)
0 0
6/7 (85.7%) EU: 5/6 (83.3%)
Non-EU:
1/1 (100%)
1/7 (14.3%) EU: 1/6 (16.7%)
0 0
4/7 (57.1%) EU: 3/6 (50%)
Non-EU:
1/1 (100%)
3/7 (42.9%) EU: 3/6 (50%)
0 0
6/7 (85.7%) EU: 5/6 (83.3%)
Non-EU:
1/1 (100%)
1/7 (14.3%) EU: 1/6 (16.7%)
0 0
95. 2nd
Steering Committee
/Advisory Board
Meeting (WP1) **
3/5 (60%)
2/5 (40%)
0 0
2/5 (40%)
3/5 (60%)
0 0
4/5 (80%)
1/5 (20%)
0 0
2/5 (40%)
3/5 (60%)
0 0
3/5 (60%)
2/5 (40%)
0 0
96. WP4
Meeting of expert
committee - January
2012
4/7 (57.1%) EU: 3/5 (60%)
Non-EU:
1/2 (50%)
3/7 (42.9%) EU: 2/5 (40%)
Non-EU:
1/2 (50%)
0 0
4/7 (57.1%) EU: 3/5 (60%)
Non-EU:
1/2 (50%)
3/7 (42.9%) EU: 2/5 (40%)
Non-EU:
1/2 (50%)
0 0
3/6 (50%) EU: 2/4 (50%)
Non-EU:
1/2 (50%)
3/6(50%) EU: 2/4 (50%)
Non-EU:
1/2 (50%)
0 0
4/7 (57.1%) EU: 3/5 (60%)
Non-EU:
1/2 (50%)
2/7 (28.6%) EU: 1/5 (20%)
Non-EU:
1/2 (50%)
1/7 (14.3%) EU: 1/5 (20%)
0
5/7 (71.4%) EU: 4/5 (80%)
Non-EU:
1/2 (50%)
2/7 (28.6%) EU: 1/5 (20%)
Non-EU:
1/2 (50%)
0 0
97. WP4
Meeting with heads
of laboratories -
March 2012
11/15 (73.3%) EU: 3/7 (42.9%)
Non-EU: 8/8
(100%)
3/15 (20%) EU: 3/7 (42.9%)
1/15 (6.7%) EU: 1/7 (14.3%)
0
9/15 (60%) EU: 2/7 (28.6%)
Non-EU:
7/8 (87.5%)
5/15 (33.3%) EU: 4/7 (57.1%)
Non-EU:
1/8 (12.5%)
1/15 (6.7%) EU: 1/7 (14.3%)
0
9/14(64.3%) EU: 2/6 (33.3%)
Non-EU:
7/8 (87.5%)
5/14(35.7%) EU: 4/6 (66.7%)
Non-EU:
1/8 (12.5%)
0 0
9/14
(64.3%) EU: 3/7
(42.9%)
Non-EU: 6/7
(85.7%)
3/14 (21.4%) EU: 2/7
(28.6%)
Non-EU:
1/7 (14.3%)
2/14
(14.3%) EU: 2/7
(28.6%)
0
11/15 (73.3%) EU: 3/7 (42.9%)
Non-EU:
8/8 (100%)
4/15(26.7%) EU: 4/7(57.1%)
0 0
98. WP5:
Workshop and
capacity building
session 1 **
1/1 (100%)
0 0 0
1/1 (100%)
0/1 (0%)
0 0
1/1 (100%)
0/1(0%)
0 0
1/1 (100%)
0 0 0
1/1 (100%)
0 0 0
99. WP6 ST
Meeting in
Montenegro (2011)
**
2/3 (66.7%)
1/3 (33.3%)
0 0
3/3 (100%)
0/3 (0%) 0 0
1/2 (50%)
1/2(50%)
0 0
1/2 (50%)
1/2 (50%)
0 0
1/2 (50%)
0 0
1/2 (50%)
100. WP6 ST
Meeting in Turkey
(2011)
3/4 (75%) EU: 2/3 (66.7%)
Non-EU:
1/1 (100%)
0
1/4 (25%) EU: 1/3 (33.3%
0
3/4 (75%) EU:2/3 (66.7%)
Non –EU:
1/1 (100%)
1/4 (25%) EU: 1/3 (33.3%)
0 0
2/3 (66.7%) EU: 1 /2 (50%)
Non-EU:
1/1 (100%)
1/3(33.3%) EU: 1/2 (50%)
0 0
3/3
(100%) EU: 2/2
(100%)
Non-EU:
1/1 (100%)
0 0 0
2/3 (66.7%) EU: 1/2(50%)
Non-EU:
1/1 (100%)
0 0
1/3
(33.3%) EU: 1/2
(50%)
101. WP7:
Meeting in Rome,
July 2011
2/5 (40%) EU: 2/4 (50%)
3/5 (60%) EU: 2/4 (50%)
Non-EU:
1/1 (100%)
0 0
2/5 (40%) EU: 2/24 (50%)
3/5 (60%)
EU: 2/4 (50%) Non-EU: 1/1
(100%)
0 0
2/5 (40%)
EU: 2/4 (50%)
3/5(60%)
EU: 2/4 (50%) Non-EU: 1/1
(100%)
0 0
3/5
(60%)
EU: 2/4
(50%) Non-EU: 1/1
(100%)
2/5 (40%)
EU: 2/4
(50%)
0 0
3/5 (60%) EU:3 /4 (75%)
2/5 (40%) EU: 1/4 (25%)
Non-EU: 1/1
(100%)
0 0
EpiSouth Plus Midterm Evaluation Page 37 of 74
102. WP7:
Meeting in Lyon, July
2012
4/5 (80%) EU: 3/ 4 (75%)
Non-EU: 1/1
(100%)
1/5 (20%) EU: 1/4 (25%)
0 0
2/5 (40%) EU: 1/4 (25%)
Non-EU: 1/1
(100%)
3/5 (60%) EU: 3/4 (75%)
0 0
3/5(60%) EU: 2/4 (50%)
Non-EU:
1/1 (100%)
2/5 (40%) EU: 2/4 (50%)
0 0
4/5
(60%) EU: 3/4 (75%)
Non-EU:
1/1 (100%)
1/5 (40%) EU: 1/4 (25%)
0 0
2/5 (80%) EU: 2/4 (50%)
3/5 (20%) EU: 2/4 (50%)
Non-EU:
1/1 (100%)
0 0
*E: Excellent S: Satisfactory RS: Relatively Satisfactory RI: Requires Improvement
** Only EU responders
3.8.3 Comments by the responders:
���� The meeting was very useful provided very important feedback from countries and provides NFP a real opportunity to express their needs expectation and concerns
���� Too much time spent on discussing issues that were not directly related o the implementation of the activities and the EpiSouth itself .The 1st SC meeting was especially difficult do to the time spent on re-discussing issues that were
supposed to be agreed when grant was signed, lot of discussion between the different representative of the EU institutions to the detriment of the project
3.9 Network Consolidation Evaluation
3.9.1 Previous evaluation report
An evaluation of the WP6 – Cross border epidemic intelligence was conducted. Twenty two
persons out of 54 potential have answered the questionnaire (40% response rate). Seven of
the 22 responders (32%) were from Non –EU countries.
Main findings:
� 95% of the respondents consider that the access to the secure platform is easy
(password)
� 65% of the respondents think it is easy enough to sort, search an alert, and 27% think
it is very easy
� 73% think there are enough alerts/posting on the platform
� 54.5% think that the information of the posted alerts is relevant
� 50% think that the content/data provided in the alert are of good quality, 45.5% think
it is of excellent quality
� 68% think that the quality of the analysis of the information is good, 23% think it is
excellent.
� 54% think that the information is usually provided at the same time as other similar
sources of information
� 41% think the timeliness is very good, the information is usually provided in advance
compared to other similar sources of information
� 5% think timeliness is not good, the information is provided with too much delay
� 64% of the respondents usually transfer the information to key stakeholders
� 82% think that, on average, the posted alerts were useful for their institution or
country
� 41% always consult the alert, 23% do it frequently, and 32% consult sometimes the
alerts
� For 77% of the respondents, they usually use only the email to consult the alert (due
to problems of connection to the secure area, or because it is easier and/or faster),
EpiSouth Plus Midterm Evaluation Page 39 of 74
and for 23%, they use both the email and the secured area (one mentioned that the
summary in the email was not readable enough)
� 45% have never posted an alert
� 36% think it is easy enough to post an alert, and 12% think it is very easy
� 46% of the respondents have a direct access to their national alerts and are able to
post them while 27% have not. The remaining respondents (27%) had no opinion on
the question. Most of the respondents who answered no to the question specified
that they do have access but are not (always) allowed posting alerts.
� 45% said they would need an EpiSouth criteria procedure or a formal EpiSouth
manual to help in posting alerts, against 32% who would not need
� 82% of the respondents think that the layout of the platform is very good and that
there is no need to change anything and 68% think the same thing regarding the
colour of the platform.
3.9.2 Evaluation of the EpiSouth Network
In Table 15 the evaluation of the Episouth Network by the partnership is presented. Around
80% (26/32) of the responders believes that the EPISOUTH Network is fully facilitating the
exchange of alerts and health information. Eighteen out of 30 (60%) responders believe that
the EPISOUTH Network has fully enhanced the coordinated response to public health events
in the Mediterranean area whereas 40% (12/30) believe that this is partially achieved. About
56% (18/32) believe that the EPISOUTH Network is fully contributing in the strengthening of
Mediterranean countries capacities building whereas about 40% (13/32) responded that this
is only partially achieved. Almost 80% (26/32) of the responders believe that the EPISOUTH
Network fully works towards building reliable and collaborative relationships among public
health professionals. Eighteen out of 30 (60%) of the responders believe that the EPISOUTH
Network has only partially contributed to the development of interoperability with other
early warning systems and about 62% (18/29) that only partially has enhanced their capacity
to better respond to alerts. It should be noted that a higher percentage of EU responders
rated that the EpiSouth Network has partially enhanced their capacity to better respond to
alerts (14/19, 73.7%) in comparison to Non-EU responders (4/10, 40%).
EpiSouth Plus Midterm Evaluation Page 40 of 74
The enhancement of their capacity for communicable disease surveillance and response has
only been achieved fully according to 48.4% (15/31) of the responders whereas the same
percentage of 48.4% (15/31) believes it was achieved partially. Responders feel the same for
the capacity of the Network to strengthen their laboratory capacity in terms of diagnoses
procedure (50% fully and 45.8% partially). It should be noted that a higher percentage of Non
EU countries (7/10, 70%) believe that the network will partially strengthen their capacity of
the Mediterranean region in terms of diagnoses procedure in comparison to the EU countries
(8/21, 38.1%) (p-value: 0.10). About 53% (17/32) of the responders believed that the
network has fully used their organisations strengths and expertise in implementing its
activities and almost 44% (14/32) that it was used only partially.
Table 15: Evaluation Questionnaire 2: EpiSouth Network
Fully Partially Not at all
103. Do you think that the EPISOUTH Network is
facilitating the exchange of alerts and health
information?
26/32 (81.3%) EU: 18/22 (81.8%)
Non-EU: 8/10 (80%)
6/32 (18.8%) EU: 4/22 (18.2%)
Non-EU: 2/10 (20%) 0/32 (0%)
104. Do you think that the EPISOUTH Network
has enhanced the coordinated response to public
health events in the Mediterranean Area?
18/30 (60%) EU: 11/20 (55%)
Non-EU: 7/10 (70%)
12/30 (40%) EU: 9/20(45%)
Non-EU: 3/10 (30%) 0/30 (0%)
105. Do you think that that the EPISOUTH
Network is contributing in the strengthening of
Mediterranean countries capacities building?
18/32 (56.3%) EU: 13/22 (59.1%)
Non-EU: 5/10 (50%)
13/32 (40.6%) EU: 8/22 (36.4%)
Non-EU: 5/10 (50%)
1/32 (3.1%) EU: 1/22 (4.5%)
106. Do you think that the EPISOUTH Network
work towards building reliable and collaborative
relationships among public health professionals?
26/32 (81.3%) EU: 19/22 (86.4%)
Non-EU: 7/10 (70%)
6/32 (18.8%) EU: 3/22 (13.6%)
Non-EU: 3/10 (30%)
0/32 (0%)
107. Do you think that the EPISOUTH Network
has contributed to the development of
interoperability with other early warning systems?
11/30 (36.7%) EU: 8/20 (40%)
Non-EU: 3/10 (30%)
18/30 (60%) EU: 11/20 (55%)
Non-EU: 7/10 (70%)
1/30 (3.3%) EU: 1/20 (5%)
Non-EU: 0/10 (0%)
108. Do you think that the EPISOUTH Network
has enhanced your capacity to better respond to
alerts?
11/29 (37.9%) EU: 5/19 (26.3%)
Non-EU: 6/10 (60%)
18/29 (62.1%) EU: 14/19 (73.7%)
Non-EU: 4/10 (40%)
0/29 (0%)
109. Do you think that the EPISOUTH Network
has enhanced your capacity for communicable
disease surveillance and response?
12/29 (41.4%) EU: 7/19 (36.8%)
Non-EU: 5/10 (50%)
16/29 (55.2%) EU: 12/19 (63.2%)
Non-EU: 4/10(40%)
1/29 (3.4%) EU: 0/19 (0%)
Non-EU: 1/10
(10%)
110. Do you think that the EPISOUTH Network
will strengthen the laboratory capacities of the
Mediterranean region in terms of diagnosis and
procedures?
15/31 (48.4%) EU: 12/21 (57.1%)
Non-EU:3/10 (30%)
15/31 (48.4%) EU: 8/21 (38.1%)*
Non-EU: 7/10 (70%)*
1/31 (3.2%) EU: 1/21(4.8%)
Non-EU: 0/10 (0%)
111. Do you think that the EPISOUTH Network
has used your organisation’s strengths and expertise
in implementing its activities?
17/32 (53.1%) EU: 13/22 (59.1%)
Non-EU:4/10 (40%)
14/32 (43.8%) EU: 9/22 (40.9%)
Non-EU:5/10 (50%)
1/32 (3.1%) EU: 0/22 (0%)
Non-EU: 1/10
(10%)
*p-value: 0.1
3.9.3 Evaluation of the EpiSouth Platform
In Table 16 the evaluation of the Episouth platform by the partnership is presented. The
functionality of the platform was rated as excellent by almost 44% (13/30) of the responders
whereas 50% (15/30) rated it as satisfactory. The usefulness and effectiveness of the
platform was rated as excellent by almost 54% (16/30) and as satisfactory by 40% (33.3). The
accessibility was rated as excellent by almost 50% (15/30) and as satisfactory by 10% (10/30)
EpiSouth Plus Midterm Evaluation Page 41 of 74
whereas 13.3% (4/30) rated it as relatively satisfactorily. One out of 30 (3.3%) commended
that it requires improvement. Regarding time response, 43.3% (13/30) rated it as excellent
and almost 47% (14/30) as satisfactory. The user friendliness of the platform was rated as
excellent by 40% (12/30) and as satisfactory by 50% (15/30). More than 43% (13/30)
believed that the navigation mechanism was excellent whereas 30% (9/30) thought that it
was satisfactory and another 20% (6/30) that it was relatively satisfactory. The quality of the
content of the alerts was rated as excellent by >53% (16/30) from the responders and as
satisfactory by 40% (12/30). Finally regarding the quality of the analysis of the information
50% (15/30) of the responders believe that is excellent and almost 37% (11/30) rated it as
satisfactory. From the results in Table 16 is shown that EU responders rated with a higher
percentage the functionality, usefulness, accessibility, time response, user friendliness and
quality of the analysis of the information in contrast with the Non EU that rated these as
satisfactory.
Table 16: Evaluation Questionnaire 2: EpiSouth Platform
System/ Platform Excellent Satisfactory Relatively
Satisfactory
Requires
Improvement
112. Functionality 13/30 (43.3%)
EU: 11/21 (52.4%)
Non-EU:
2/9 (22.2%)
15/30 (50%)
EU: 8/21 (38.1%)
Non-EU:
7/9 (77.8%)
2/30 (6.7%)
EU: 2/21 (9.5%)
Non-EU: 0/9 (%)
0/30 (0%)
113. Usefulness/Effectiveness
16/30 (53.3%)
EU: 12/21(57.1%)
Non-EU:
4/9 (44.4%)
12/30 (40%)
EU: 7/21 (33.3%)
Non-EU:
5/9 (55.6%)
1/30 (3.3%)
EU: 1/21 (4.8%)
Non-EU: 0/9 (%)
1/30 (3.3%)
EU: 1/21 (4.8%)
Non-EU: 0/9
(%)
114. Accessibility 15/30 (50%)
EU: 11/21 (52.4%)
Non-EU:
4/9 (44.4%)
10/30 (33.3%)
EU: 6/21 (28.6%)
Non-EU:
4/9 (44.4%)
4/30 (13.3%)
EU: 3/21 (14.3%)
Non-EU:
1/9 (11.1%)
1/30 (3.3%)
EU: 1/21 (4.8%)
Non-EU: 0/9
(%)
115. Time response 13/30 (43.3%)
EU: 10/21 (47.6%)
Non-EU:3/9 (33.3%)
14/30 (46.7%)
EU: 8/21 (38.1%)
Non-EU:
6/9 (66.7%)
3/30 (10%)
EU: 3/21 (14.3%)
Non-EU: 0/9 (%)
0/30 (0%)
116. User friendly
12/30 (40%)
EU: 10/21 (47.6%)
Non-EU: 2/9 (22.2%)
15/30 (50%)
EU: 8/21 (38.1%)
Non-EU:
7/9 (77.8%)
2/30 (6.7%)
EU: 2/21 (9.5%
Non-EU: 0/9 (%))
1/30 (3.3%)
EU: 1/21 (4.8%)
Non-EU: 0/9
(%)
117. Easy navigation
mechanism 13/30 (43.3%)
EU: 9/21 (42.9%)
Non-EU:
4/9 (44.4%)
9/30 (30%)
EU: 6/21 (28.6%)
Non-EU:
3/9 (33.3%)
6/30 (20%)
EU: 4/21 (19%)
Non-EU:
2/9 (22.2%)
2/30 (6.7%)
EU: 2/21 (9.5%)
Non-EU: 0/9
(%)
118. Quality of the content of
the Alerts 16/30 (53.3%)
EU: 10/21 (47.6%)
Non-EU: 6/9 (66.7%)
12/30 (40%)
EU: 10/21 (47.6%)
Non-EU:
2/9 (22.2%)
2/30 (6.7%)
EU: 1/21 (4.8%)
Non-EU:
1/9 (11.1%)
0/30 (0%)
119. Quality of the analysis of
the information 15/30 (50%)
EU: 11/21 (52.4%)
Non-EU: 4/9 (44.4%)
11/30 (36.7%)
EU: 7/21 (33.3%)
Non-EU:
4/9 (44.4%)
4/30 (13.3%)
EU: 3/21 (14.3%)
Non-EU: 1/9
(11.1%)
0/30(0%)
EpiSouth Plus Midterm Evaluation Page 42 of 74
3.9.4 Comments by the responders regarding different questions presented in Tables 15
and 16
� Question 103: This is a unique network that needs to be maintained. It has became a
very important source of information for potential health threat in the area
� Question 104: This WAS NOT the objective of EpiSouth.
� Question 105: It did contribute to capacity building through meetings training and
exchanges. Nevertheless, resources (financial and human resources) were far too
limited to allow considering a major and sustainable impact.
� Question 107: It must be continued with Non EU networks and WHO
� Question 110: It is really too early to ask the question whether the network has
strengthen the laboratory capacities of the Mediterranean region in terms of
diagnosis and procedures although lab activities implemented were highly valued
� EpiSouth is a complex and ambitious network that has proven its usefulness, its
pertinence and that actually contribute to reinforce the health security in the area. Its
composition (1/3 EU countries 2/3 non-EU countries and the sources of funding i.e.
mainly EU commission) is its main strength. The lack of long term perspective (i.e.
sustainability) is an obstacle to adequate problem solving elaboration of adequate
governance and further development. Nevertheless, despite all these difficulties
EpiSouth is a very successful network that have been able to cope with very complex
issues including (political instability (eg Arab Spring) that has been able to build trust
among participating countries (and the EpiSouth Teams). Throughout the year a
genuine EpiSouth identity has emerged. Countries are more and more participating
(at least in the health information exchanges) and these achievements must be
secured for the long term.
� Information provided by countries has so far always been very useful and appropriate
� As Focal point for EpiSouth, EWRS, and IHR I do find the platform simple easy to use.
Also as Focal point for EpiSouth, EWRS, and IHR I am fully entitled o “judge” the
pertinence and usefulness of the alerts shared by the other countries and indeed this
information is very useful for my department in our activity (not EpiSouth related) but
EpiSouth Plus Midterm Evaluation Page 43 of 74
more widely for my institute and the MoH of my country and other public health
agency in my countries (just to mention one as an example: blood transfusion agency)
� It would need more time to put into place capacity building adapted to the different
level of countries system of response and it would be more important to have time to
work together for building up relevant common procedures
� We have not used it, so we cannot answer
� Constant difficulties for accessing to the NWA and constant ask for change the
password must be solved
� Find documents require much time than expected. In countries where the connection
is worst this could be a real threat
� Putting a short summary would improve notably
� It is not yet clear to me how to enter data on e/g/ number of cases of WNV, how
often (weekly, periodically), how do I guarantee that no other will use this data
without …my permission?, who is the person to contact for such entries?…Can you
resend the user name for this?
EpiSouth Plus Midterm Evaluation Page 44 of 74
44 EEppiiSSoouutthh PPlluuss SSWWOOTT aannaallyyssiiss In the following section the results of the SWOT analysis are presented as these were
identified by all responders of the questionnaires and interviews.
Strengths
� The partnership:
o Arabic and Mediterranean
Countries that would not have any
other opportunity to meet
o Bringing the cross border
dimension between EU and Non
EU countries
o Countries sharing the same
environment but do not belong in
the same WHO region and do not
have the opportunity to work
together.
� Valuable Network -
o All work packages have their
expertise
� Good opportunities to share
information/problems between
countries - Countries have the
opportunity to learn from each other.
� Trustworthiness within the network
o Good spirit.
o A network of friends and not only
of professionals.
o Scientists and Epidemiologists
sharing the same vision/ goals.
� The commitments.
� The vision of the project and the
unique objectives.
o New subjects and issues addressed
that are very important for the
countries (IHR, coordination of
information etc).
� The absence of political differences.
� Good coordination.
� User-friendly website- member’s area
� The WP4 activities-development of
laboratory network
� The WP5 activities
� The WP6 activities – Epidemic
Intelligence - The timely reliable alerts.
� Non EU countries are very committed
� Voluntary participation
Weaknesses/Limitations
� Sharing of information between North
and South. Southern countries send
information but they do not receive
information from Northern countries
due to EU legislation constrains.
� It is financially dependant.
� Many members which raises many and
different obligations.
� Difficult to agree between so many
countries.
� Duplication - The information shared is
data that already circulate through other
networks.
� The reporting must meet the project
objectives together with the objectives of
the funding organisations which is not
always the case.
� A weak link is the EU MS – the directors
– the fact that collaboration only is at
central/ high level at the laboratory
network.
� No real specific and measurable
objectives. Confusion between methods
and objectives.
� Added value of the network has not been
clearly identified and especially for EU
countries.
� The participation is difficult sometimes
due to problems like the Arab Spring.
� Unequal resources
� Need to have more meetings and eye to
eye discussion
� Voluntary participation
� Topic is very broad
� Language issue
� Weak on the surveillance – the platform
is not used – low information on it
� Not enough information sharing
� NFP not authorised to share information
� EpiSouth does not have the expertise to
work on IHR issues and especially on
Points of Entry.
EpiSouth Plus Midterm Evaluation Page 45 of 74
Opportunities
� Enhance Information Sharing:
o Facilitate information between North and
South
o Facilitate the experience to share
information between the laboratories.
o Improve direct collaboration between
laboratories.
o Enhance the exchange of information
through the platform (WP6) which is very
well developed. Not yet fully used.
� Find advocates for the network and make the
network known.
� More active participation from the side of the
members as the project output is for their
protection. Active participation through
immediate notification of any threat
encountered and not to be influenced by
political critic or internal blames.
� Bring the project closer to the countries – have
meeting in their locations and facilitate the
attendance of a larger number of that and
neighbouring countries.
� Self funding is an important step for progress.
� Identify the added value of the network.
� Look at the gaps identified by the countries
and see how the network can be mobilised.
� Expand to other southern countries (Sudan
etc).
� EpiSouth currently has a bottom up approach
on technical issues. However the opposite, a
top to bottom approach should also exist.
� Link with existing international organisations.
� Use what it was achieved in the past and
prepare new projects - A network of more
specific networks - Create smaller project
teams, not all countries need to be involved in
all WPs - Should be a FLEXIBLE – INFORMAL
network.
� Partner more with bigger institutions -
enhance further WHO collaboration.
� Find the network’s part in the world of
preparedness and response.
� Improve coordination.
� Sticking to the timetable.
� Deliver what was agreed.
� Other issues to address are immigration and
zoonoses.
Threats
� Major threat is the
sustainability of funding
� Dispute with other bodies
like IHR and ECDC and WHO
should be resolved.
� The burden of the countries
in North Africa and Middle
East with volatile situations
which is beyond control of
the project.
� Exchange data and provide
further authorisation for
data sharing.
� Countries are not willing to
share – political instabilities
delaying the exchange of
experience.
� The lack of motivation.
� Avoid duplication.
� Financial constrains.
� Time consuming.
� Low participation.
� The partnership should note
that they might find
competitors that might have
economic goals.
� Completeness.
� Not clear that the
deliverables will be used by
all countries
EpiSouth Plus Midterm Evaluation Page 46 of 74
55 SSuussttaaiinnaabbiilliittyy In the question regarding which activities implemented so far did they believe should be
sustainable, the interviewees answered the following:
� WP6- The epidemic intelligence system (8 interviewees) followed by printable guide
to manage such alerts (1 interviewee)
� The regional laboratory networking (4 interviewees)
� The training activities (3 interviewees)
� The WP7 Points of Entry (3 interviewees): The promotion of the implementation of
the PoE guidelines: A possibility to be used by MS to improve the ability of PoE to
respond is something that all countries are interested in. Regarding the PoE countries
will collaborate easier because they are all very interested in this issue. These
activities will contribute to future activities of WHO
� The Network of Epidemiologists (2 interviewee)
� The coordination and active communications with similar projects (1 interviewee)
� EpiSouth should build on bridges between health and agriculture (1 interviewee)
� Sharing of information
� Translate key documents in key languages
In the question regarding what are the means that the partnership should use in order to
become sustainable, the interviewees responded the following:
• Sustainability should come through the countries (4 interviewees).
• Financial support from international organisations or the EC or from Arab
countries league or EUROMED collaboration (2 interviewees).
• Avoid duplications (2 interviewees).
• WHO and ECDC should be on board. Southern countries will not act if not in
agreement with WHO (2 interviewees).
• G7 and Mexico Network was also approached and they showed an interest in
EPISOUTH.
• Advocacy.
EpiSouth Plus Midterm Evaluation Page 47 of 74
• Define the objectives and the vision.
• Define surveillance at PoE, identify action and countries that have the expertise to
assist.
• The network is a tool but need to define its activities.
• Different structure of the project in order to become sustainable, create more
concrete projects The network should be a political network - Enhance the
segmentation that currently exists and become a Network of Networks (3
interviewees)
• The project should have a political role and work to create a network structure
like EUROMED has.
• Motivate countries to use the platform
• Create a small project and network
• Key is to know how to prepare a successful proposal and to build on existing
achievements.
• WP5 training activities should become sustainable ECDC and DENCO aim to use
the work of EpiSouth.
• Funding should not be an issue because there are technical available tools to be
used
• To be voluntary and to engage more the Member States
• Find the best way to enhance the border surveillance
• Establish technical assistance in relation to IHR
• EpiSouth should partner with other networks
• There is no need for WP7 since this is work covered by WHO
• WP6 and the Epidemic Intelligence system should go under ECDC
• The only viable is WP4 : they should define the pathogens (since ECDC already
covers some)
• Could become eventually a laboratory network coordinated by ECDC
EpiSouth Plus Midterm Evaluation Page 48 of 74
66 AAddddeedd VVaalluuee ooff tthhee EEppiiSSoouutthh PPrroojjeecctt In the following section the added value of the WP7 activities are presented as these were
identified by the WP 7 Leader. It is highly recommended to all Work Package Leaders and Co-
leaders to prepare a summary like the one presented below of the added value of the
activities of their WPs. The main objective is to promote the dissemination of the added
value documentation to the stakeholders including EU and international organisations in
order to increase the visibility and recognition of the project.
6.1 Added value of the collaboration between the EpiSouth Network and
WHO in the framework of the EpiSouth Plus WP7
Action undertaken Output Added value Level of
implementation
Analysis of WHO
data for the
EpiSouth Region
(disaggregation
not available
before)
Report on the
level of
implementati
on of IHR in
the EpiSouth
Region
Knowledge sharing
This data was not available
before, need for it was
expressed by countries and
the collaboration between
WHO and the EpiSouth
network made the
knowledge sharing possible
Completed
Prioritization of
capacity
development
needs in the
Mediterranean
Two ST
meetings
Mutual learning
Countries presented level of
implementation of IHR in
their national settings and
contributed in the definition
of the need for and contents
of the WHO guidance on the
priority area selected through
an enlarged consensus
process.
Completed
Situational analysis
on coordination of
surveillance
between Points of
Entry (PoE) and
National
Surveillance
Systems in key
EpiSouth countries
Study report Fostering best practice
exchange
The methodology chosen is
aimed at providing best
practices developed in
Countries that are
representative of the
geopolitical diversity of the
EpiSouth Region
Ongoing
EpiSouth Plus Midterm Evaluation Page 49 of 74
Feasibility study of
the applicability of
WHO guidance on
coordination of
surveillance
between PoE and
National
Surveillance
Systems
Study Report Unlocking the potential of
innovation in health.
The contribution of the
EpiSouth network is in
analysing the possible impact
of the WHO guidance and the
opportunity of suggesting
nationally identified
strengths/constraints/propos
als. This is an opportunity for
the Countries to participate
in the formulation of the
guidance and in its national
application
Planned
WP7 Strategic
Document
Strategic
document
Identify, disseminate and
promote the up-take of
validated best practices
enriched by the revision of
experts in the network’s
advisory board, the strategic
document will build on the
activities performed to
provide a regional policy
paper on IHR implementation
in the region, the priority
need for coordination of
surveillance and solutions
adopted in key EpiSouth
Countries.
Planned
Additional aspects to consider:
- No Country could have achieved this alone
- No network could have achieved this in absence of a close and productive
collaboration with WHO
- Participants are part of a strategically relevant region comprising 27 countries of
which only 9 EU Member States, and stretching across three WHO Regions.
- Duplication was avoided (no additional data was collected for the initial assessment
and for the mapping phase of the in depth study).
- Notwithstanding the complexity of the topic identified by participants as priority,
coordination with WHO subject matter experts and with the network Focal Points
that work in this specific domain, were valued and their expert opinion was requested
in the definition of methods, tools and in the validation of results.
EpiSouth Plus Midterm Evaluation Page 50 of 74
77 LLiimmiittaattiioonnss A total of seven questionnaires with common questions/variables were disseminated to eight
different target groups. The fact that the questionnaires were disseminated according to the
target group meant that partners participating in more than one target group were obliged
to answer the same questions more than once. The common variables answered more than
once from the same responder were excluded from the analysis. As explained above, since
certain Focal Points responded collectively, ten questionnaires were identified as Not
Applicable and were excluded from the original list in order to calculate the response rate.
Moreover, four questionnaires were further excluded because the partner had not
participated in activities or was not the focal point anymore or was a work package leader
and feared would be biased if had responded to the questionnaires.
A total of 90 out of 178 (51%) questionnaires were disseminated to partners from the EU
countries and a total of 88 out of 178 (49%) were disseminated to Non EU Countries.
Lower response rate was recorded in Non EU partners (36 out of 88, 41%) in comparison
with EU countries (73 out of 90, 81%) (p-value: <0.001). As a result the Non EU countries’
views and opinions are not equally represented. This finding should be investigated further to
identify reasons and consequences. One possible explanation could be the political instability
in the Non-EU countries.
Taking into consideration that statistical significant differences were identified between the
EU and Non EU responses with the EU rating higher the activities in comparison to the Non-
EU, the overall evaluation results could potentially be different if a higher response rate was
achieved for Non-EU countries. This finding should be further investigated and addressed by
the coordination of the project.
Another limitation was the limited time available to conduct the evaluation. The period of
two months was given to revise the indicators, review all documents and activities and
prepare the evaluation tools. The collection period of the questionnaire was only two weeks
and limited time was also provided to assess the evaluation results and prepare the report.
EpiSouth Plus Midterm Evaluation Page 51 of 74
88 CCoonncclluussiioonnss The midterm evaluation covering 24 months of the implementation of the EpiSouth Plus
project has led to the following concluding remarks reflecting the views of the partnership as
expressed by the target groups (Focal Points, Advisory Board, Steering Committee, Steering
Teams) through the questionnaires and interviews.
The evaluation of milestones and indicators has shown that minor and major delays occurred
in all work packages. The reason for the delays as identified by the responders includes,
amongst others, the political instability in certain countries and the long-term negotiations
between EpiSouth Plus and the European Commission (EAHC, DEVCO) regarding the Epidemic
Intelligent platform (WP6) which were also characterised by a lack of flexibility. During the 1st
Project Meeting in Rome, the Work Package Co-leaders presented the revised methodologies
and timeframe to successfully achieve the objectives.
It was noted by all target groups that EpiSouth Plus is a large and complex project to manage
with partners that have geopolitical and cultural differences. The overall belief of the
majority of the responders is that the coordination structure of the project and the problem–
solving process were effective in resolving the delays, however, responders from the EU and
International organisations commented that the project would have benefited from a more
proactive approach in coordination activities. More than 80% of the responders identified
that the project has great potential and that it has achieved reliable and collaborative
relationships among public health professionals. It is characterised as a valuable network that
has fully facilitated the exchange of alerts and health information, enhancing the coordinated
response to public health events in the Mediterranean Area. The website, the Quarterly
EpiSouth Electronic Bulletin and especially the Weekly Epi Bulletin are valued by the partners
and they identify that the information shared is useful and needed. The training activities of
both the WP4 and WP5 were highly rated by the responders. Responders also identified that
the network is not used to its full potential and opportunities for further improvement exist,
especially in the capacity of the Network to strengthen participants’ laboratory capacity in
terms of diagnoses response and in using the participant organisation’s strengths and
expertise. It should be noted that some partners from the Mediterranean countries
mentioned as a shortcoming the limited access to European data, however, this is due to EU
legislation constraints. A fear of duplication of information shared through the Epidemic
Intelligence was expressed as a threat as well as uncertainty over the quality of data shared.
The lack of long-term concrete vision for the sustainability of the project was identified by
EpiSouth Plus Midterm Evaluation Page 52 of 74
the key stakeholders (EU and International organisations) as a limitation and a threat to the
project, and the identification and dissemination of the added value of the project an
immediate need.
It is highly recommended that all Work Package Leaders and Co-leaders should prepare a
summary of the added value of the activities of their WPs similar to what was prepared for
WP7 (see Section 6).
Through this midterm evaluation, recommendations and opportunities for improvement
have been identified. One of the strengths of EpiSouth is the double co-financing received by
DG SANCO and DG DEVCO which has allowed the concomitant involvement of EU and non-EU
partners. However, this has created additional managerial efforts since the coordinators had
to respect double regulations, requirements and expectations. This is still considered by the
partnership as an opportunity to be exploited for EpiSouth as well as other similar
projects/programmes. The coordinating structure of the project should consider enhancing
their ability to overlook the activities of the project and the extra managerial effort required
due to double co-financing by employing a full time scientist. This will allow the coordinating
structures to dedicate their time to the sustainability of the project and the quality of the
work completed.
We would highly recommend that the coordination should take into consideration the
differences of EU and Non-EU countries in the evaluation results and explore the reasons for
the low participation of the Non-EU countries in the evaluation process.
It was evident from the results of the EU and International organisations that different
opinions were expressed by the partners. The evaluators highly recommend enhancing the
communication channels with the EU and international organisations to promote all the
positive results of the project. Moreover, the added value of the network and the platform
should be better defined and disseminated to the stakeholders including EU and
International organisations.
The political instability has certainly not made easy the communication and participation of
Non EU countries in the project leading to low participation in the project’s activities, and
might possibly be the explanation for the low response rate observed to the evaluation
questionnaires by the Non EU countries. More active participation from the partners is
required in order for the network to achieve sustainability.
EpiSouth Plus Midterm Evaluation Page 53 of 74
One important recommendation identified by the responders is that facilitation of
information sharing between the laboratories should be enhanced and direct collaboration
between the laboratories should be improved. However, it should be noted that this
facilitation will be better demonstrated following implementation of the activities in the
following year.
The EpiSouth Plus partnership should review the gaps identified by the countries and identify
the methodology by which the network can be mobilised and used to its full potential. The
partnership could explore within the sustainability plan the future of EpiSouth Plus to
consider possible re-structuring where they will alter their role to more of a political public
health network/association overlooking other smaller networks that will possibly be
operated under International and European organisations.
Taking into consideration that the work completed in the 24-month period evaluated is
smaller than that scheduled in the technical annex, the partnership will have to work hard in
the next months and during the no cost extension in order to complete all scheduled tasks as
these are described in the amended technical annex and to identify the means for
sustainability.
EpiSouth Plus Midterm Evaluation Page 54 of 74
Annexes
Annex 1- Questionnaire 1 - Completed by the Advisory Board of the EpiSouth
Network
EpiSouth Plus Midterm Evaluation Page 58 of 74
Annex 2- Questionnaire 1 - Completed by all Focal Points of
Institution partners and Countries involved in the EpiSouth Network
EpiSouth Plus Midterm Evaluation Page 63 of 74
Annex 3- Questionnaire 1 – Completed by the Steering Committee of
the EpiSouth Network
EpiSouth Plus Midterm Evaluation Page 66 of 74
Annex 4- Questionnaire 1 - Completed by the WP4 Steering Team
EpiSouth Plus Midterm Evaluation Page 69 of 74
Annex 5- Questionnaire 1 - Completed by the WP5 Steering Team
EpiSouth Plus Midterm Evaluation Page 71 of 74
Annex 6- Questionnaire 1 - Completed by the WP6 Steering Team
EpiSouth Plus Midterm Evaluation Page 72 of 74
Annex 7- Questionnaire 1 - Completed by the WP7 Steering Team
EpiSouth Plus Midterm Evaluation Page 73 of 74
Annex 8- Questionnaire 2 - Completed by all Focal Points of
Institution partners and Countries involved in the EpiSouth Network
Annex 9- Questionnaire 3 – Interview Checklist