the estimate at completion

Upload: spatil1472

Post on 27-Feb-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 The Estimate at Completion

    1/3

    The Estimate at Completion - A Project Management Best Practice

    Project managers are continually asked by company management and the customer

    to verify that the projecst cost and schedule goals can be met within the authorized

    budget, the Budget at Completion (BC!, and the Planned Completion "ate (PC"!#

    $he %stimated at Completion (%C! and the %stimated Completion "ate (%C"! are

    the measures used to provide the answers to this &uestion#

    $he %arned 'alue uidelines de)ne the %C as the sum of the contract*s cumulative

    to date ctual Cost of +ork Performed (C+P! plus the company project manager*s

    best estimate of the timephased resources (funds! re&uired to complete the

    remaining authorized work, the %stimate to Complete (%$C!# $his relationship is

    often e-pressed by the formula %C . C+P / %$C# $hus, the %C is a forecast of

    the project*s )nal cost# $he project manager may revise work priorities, replan

    remaining tasks on the project schedule and0or adjust the technical approach to

    complete the project*s goals within the estimated remaining resources# $he goal is

    to complete all of the contract work scope within the Contract $arget Cost (budget!

    and Contract Completion "ate (schedule!#s with all estimates, the level of uncertainty of an %C will vary with the type of

    remaining work, the available information, and the perceived remaining risks#

    Prudent management needs to know how valid an %C is, especially when the %C

    varies signi)cantly from the project*s authorized budget (BC!# $hus, the objectives

    of project management include the identi)cation of the level of uncertainty

    associated with the remaining schedule, establishing the cost estimate for the

    remaining work, and managing the impact of the uncertainty upon the project cost

    goals#

    1or these reasons, the Contract Performance 2eport (CP2! and the 3ntegrated

    Program 4anagement 2eport (3P42! re&uire three separate %Cs in an attempt tocapture information regarding the level of cost uncertainty or the magnitude of the

    known project risks# $hese reports re&uire %Cs which represent the Best Case (or

    lowest potential cost!, the +orst Case (or highest potential cost! and the 4ost 5ikely

    %C (the project manager*s best estimate! with their respective forecasted

    completion datesgenerally referred to as %stimated Completion "ates (%C"s!#

    nother important factor to consider regarding realistic %Cs and customer

    reporting is the 6arbanes07-ley ct# 8nrealistic %Cs reported in publicly owned

    companies are subject to the conse&uences of this ct# $he 6arbanes7-ley ct

    came into force in 9uly :;;: and introduced major changes to the regulation of

    corporate governance and )nancial practices# +ith regard to periodic statutory

    )nancial reports (i#e#, Company nnual 2eports! the ct re&uires that a companyinclude certi)cations that< $he )nancial statements and related information fairly

    present the )nancial condition and the results in all material respects# 1inancial

    statements published by issuers are re&uired to be accurate and presented in a

    manner that does not contain incorrect statements# =ote that the )nancial

    information on CP2s and 3P42s directly feed corporate annual reports and that

    serious overrun or underrun conditions will e>ect the pro)t statements in these

    reports# $he ct also imposes penalties and )nes and0or imprisonment for altering,

  • 7/25/2019 The Estimate at Completion

    2/3

    destroying, mutilating, concealing, falsifying records, documents or tangible objects

    with the intent to obstruct, impede, or in?uence a legal investigation#

    6ince the actual cost to date is a known value, %C uncertainty is a function of the

    %stimate to Complete# $he %$C is prepared by reestimating the resources re&uired

    to complete the remaining authorized work using the cost e-perience to date and

    then applying a number of other factors@ such as current direct and overhead rates,6chedule 2isk ssessment (62!, 4onte Carlo simulations, root cause analysis, etc#

    well conceived %$C also considers purchase order commitments, anticipated labor

    eAciency and rate, material price and usage, 7ther "irect Cost (7"C! price and

    usage performance, risk and opportunities, resources by type, and other factors

    identi)ed by higher management# dditionally, as the %$C is being developed it

    should be mapped to the current schedule consistent with the %stimated

    Completion "ate (%C"!#

    s a means to crosscheck the %C, a mathematical or independent estimate of the

    %C is typically prepared using performance indices based upon the cost and

    schedule e-perience to date# 1or e-ample, the Cost Performance 3nde- (CP3!(cumulative Budgeted Cost for +ork Performed 0 C+P! can be used to complete

    the %C by dividing the project BC by the CP3# $he resulting %C is often referred

    to as the

    %'46 %ducation Center 3ndependent %C (3%C! to distinguish it from a formal or

    grass roots %C# $he 3%C can be &uickly prepared and then used to test the

    reasonableness of the current cost estimate and to indicate when a comprehensive

    %C should be undertaken# 3t is important to note that these calculations do not

    consider any thinking about the considerations mentioned above with respect to

    anticipated labor eAciency and rate, risk and opportunities, 62, etc# 3t is often said

    that they are independent of sanity, logic and judgment but are calculated for

    comparative analysisan important purpose#

    $he capability to regularly prepare an %C along with the calculation of the Best

    Case, +orst Case, and 4ost 5ikely %Cs is becoming an industry best practice# t

    least annually, a complete bottomsup %C, called the Comprehensive %C, is

    re&uired on those projects subject to the "12 :D:#:EFG;;: %arned 'alue

    4anagement 6ystem re&uirements# comprehensive %C is also often prepared at

    the start of a major project phase@ such as the start of production or construction#

    Conse&uently, it can re?ect the reduced uncertainty resulting from a design release

    and0or a released bill of material, which enables the project manager to answer

    these &uestions