ENERGY TRANSFORMATION FOR FUTURE
Business Structure Trading
Energy Industrial
Investment
Compressed Bio-Methane Gas
(CBG) - 11 Projects at the North
Petroleum Production Project
(PPP) – in Sukhothai
Renewable & Alternative Projects
Associated Company
Bangchak Biofuel
(BBF) (UAC : BCP = 30% : 70%)
Subsidiary Company
UAC Hydrotek ( UAC : Hydrotek )
(50.003% : 49.997%)
Water Treatment Projects
Water Supply Projects
UAC&TPT Energy (UAC = 100%)
CBG 10 projects at the North
Eastern
Listed in MAI
THE FIRST CBG IN THAILAND
Established 2010, Investment Cost 180 Million Baht (100% UAC)
Plant location Mae Tang, Chiang Mai
Capacity CBG : 6 ton per day
Fertilizer : 25 ton per day
Customers PTT (contract signed for 15 years)
Technology Biogas: Rescom Engineering GmbH
Biogas Purification: UOP
Status Start Production Since February 2013
THE FIRST CBG IN THAILAND
GRAND OPENING DAY
February 15, 2013 by Thai P.M.
Gas Purification unit
Fertilizer
Recycle Water
Sludge Separator
Mixing
Biogas
Fertilizer
1. Pig manure 700 m3/D, 1-2% solid
2. Napier Grass Silage 15TPD
Current 40 acres and increasing to 160 acres
Compositions Typical UAC
Methane 50-60% 60-72%
CO2 25-40% 25-35%
Water 0-5% 0-3%
N2 0.01-2% 0.01-0.5%
O2 0.01-0.6% 0.01-0.2%
H2 0.1% -
H2S 3000 ppm 800 ppm
No.
Requirement CBG Spec. CNG Spec.
1 Water Dew Point at 20,000 kPa - 15 C Max 9.2 C
2. Hydrocarbon Dew Point at 4500 kPa
- 65 C Max 15.5 C
3. Wobbe Index 39-41 MJ/m3 37-42 MJ/m3
4. Methane Number 101 Min. 65
5. Hydrogen Sulfide max 23 mg/m3 Max 23 mg/m3
6. Hydrogen max 0.1% vol. Max 0.1% vol.
7. Carbon Dioxide max 18% vol. Max 18% vol.
8. Oxygen max 1% vol. Max 1% vol.
9. Sulfur max 50 mg/m3 Max 50 mg/m3
LOCAL ALTERNATIVE ENERGY FROM WASTES REPLACE CNG IN REMOTE AREA SUSTAINABILITY – LONG TERM PROJECT
TOTAL WASTE MANAGEMENT SOLUTIONS
BETTER INCOME TO FARMERS WHO GROW NAPIER GRASS
UAC have decided to develop another 10 new CBG projects at the same capacity (6TPD of CBG) using Napier grass silage. New plants will be located in the northern part of Thailand. UAC have set up a JV with TPT to set up another 10 new CBG projects in
northeastern part of Thailand
New 20 CBG projects in 2013-2015
Capacity/plant CBG: 6TPD
Organic Fertilizer: 25 TPD
Raw Materials Napier Grass 100 TPD
CAPEX 100 million Baht per plant
Total 2 billion Baht
Funding EPPO Fund 10% Equity 40% Bank 50%
Project Status
Doing Engineering Design and will start the civil
construction by 3Q 2013 for the first two plants
All 20 projects will be completed by 1Q 2015
Technology Germany, USA and Thailand