the fns “apd process”
DESCRIPTION
The Rules Your Clients Play By, and How to Help Them Win!. The FNS “APD Process”. Session Contents. The FNS “APD Process” and the role YOU play What we tell the States – your clients – about: The Power of the RFP Open Competition & Conflicts of Interest - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/1.jpg)
The Rules Your Clients Play By,
and How to Help Them Win!
![Page 2: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/2.jpg)
The FNS “APD Process” and the role YOU play
What we tell the States – your clients – about:
The Power of the RFP
Open Competition & Conflicts of Interest
Contractor Selection Criteria and Bid Scoring
FNS & Vendors – Areas of Common Interest
![Page 3: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/3.jpg)
Responsibility for oversight of State Automation and
Modernization efforts is shared - between the Regional Office
SNAP or WIC program and the State Systems Office - SSO.
![Page 4: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/4.jpg)
Advance Planning & Acquisition Documents
State Systems Office FNS Regional Office
Approval or Additional Documentation Request
![Page 5: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/5.jpg)
NERO
MARO
SERO
SWRO
WRO
MPROMWRO
![Page 6: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/6.jpg)
Gregg Saxton
![Page 7: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/7.jpg)
Karen Painter-Jaquess
![Page 8: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/8.jpg)
Kathy Tankersley
![Page 9: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/9.jpg)
Lynn Jordan
![Page 10: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/10.jpg)
Catalina Luna Jennifer Renegar
![Page 11: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/11.jpg)
States should expect a coordinated response from FNS.
SSO – Lead on APD Process, Project Management and Technical Issues
Region – Lead on Program Functionality
![Page 12: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/12.jpg)
![Page 13: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/13.jpg)
![Page 14: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/14.jpg)
![Page 15: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/15.jpg)
![Page 16: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/16.jpg)
![Page 17: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/17.jpg)
When vendors understand the process you can:
- Help states comply with it- Avoid clients being caught in the
middle- Be aware of when the products that
you create are subject to the federal process- Planning docs- Change orders that cross the threshold- Status reports and/or components of the
APDUs
![Page 18: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/18.jpg)
![Page 19: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/19.jpg)
Planning Advance Planning Document (PAPD)
Implementation Advance Planning Document (IAPD)
IAPD Update (IAPDU)IAPDU As-Needed
![Page 20: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/20.jpg)
Request For Proposal (RFP)
Contract
![Page 21: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/21.jpg)
Planning Advance Planning Document (PAPD)
Implementation Advance Planning Document (IAPD)
IAPD Update (IAPDU)IAPDU As-NeededEmergency Acquisition Request (EAR)
![Page 22: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/22.jpg)
![Page 23: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/23.jpg)
“A Planning APD is required for review and approval for all projects > $5M total project costs”
FNS Handbook 901, Section 2.2.1, Planning APD
![Page 24: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/24.jpg)
PAPD is a brief document that:Requests prior approval and Federal funds to
explore the feasibility of new system initiatives
Describes the planning activitiesEstimates the cost and timeline of planning Identifies and prepares for acquisition
activities
![Page 25: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/25.jpg)
25
60 DAYS
![Page 26: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/26.jpg)
![Page 27: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/27.jpg)
![Page 28: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/28.jpg)
![Page 29: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/29.jpg)
![Page 30: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/30.jpg)
![Page 31: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/31.jpg)
![Page 32: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/32.jpg)
50 States x 2 programs (WIC & FSP)+ states with multiple
systems + WIC ITOs & US
territoriesx ~3-6 docs/project
÷ 6 of us----------------
60 days
![Page 33: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/33.jpg)
THEN WHAT?THEN WHAT?
![Page 34: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/34.jpg)
Define the scope
Review business processes
Conduct requirements analysis
Conduct feasibility study/alternatives analysis
Prepare cost benefit analysis
Prepare IAPD
Planning Activities
![Page 35: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/35.jpg)
![Page 36: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/36.jpg)
![Page 37: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/37.jpg)
![Page 38: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/38.jpg)
![Page 39: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/39.jpg)
![Page 40: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/40.jpg)
Culmination of the planning process
Reflects the results of the analysis and feasibility of various automation alternatives
Reflects the design and description of the automation project
![Page 41: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/41.jpg)
Provides an initial management plan for acquiring, developing, testing, and implementing the selected alternative(s)
Requests prior approval and Federal funding from FNS
![Page 42: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/42.jpg)
Feasibility Study/Alternatives Analysis/Cost-Benefit Analysis
Functional RequirementsManagement PlanScheduleBudget
![Page 43: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/43.jpg)
43
60 DAYS
![Page 44: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/44.jpg)
44
![Page 45: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/45.jpg)
THEN WHAT?THEN WHAT?
![Page 46: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/46.jpg)
Convert functional requirements into the system requirements
Develop / Transfer / Integrate
Test and Pilot
Train and Implement statewide
Design, Development & Implementation Activities
![Page 47: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/47.jpg)
![Page 48: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/48.jpg)
What Makes Training Effective?Incorporates UAT resultsIs scheduled “just in time”Is “hands on”Does not end at rollout
![Page 49: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/49.jpg)
![Page 50: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/50.jpg)
What a Pilot Should Not Be:Simply the first phase of rolloutA formality to proceed
What a Pilot Should Be:The extension of system testing into
the real worldA real test of the system
![Page 51: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/51.jpg)
![Page 52: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/52.jpg)
PAPDSubmit to FNS
FNS approves
Do planning tasks
SubmitAPDUs
Closure
Submit planning phase RFP(s)
FNS approves
Release RFP & choose
contractor
Submit contract to FNS
FNS approves
![Page 53: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/53.jpg)
Project managementDevelopment contractorQA contractorIV&VCommunicationsTraining???
![Page 54: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/54.jpg)
IAPDSubmit to FNS
FNS approves
Do DDI tasks
SubmitAPDUs Closure
Submit DDI
phase RFP(s)
FNS approves
Release RFP & choose
contractor
Submit contract to FNS
FNS approves
![Page 55: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/55.jpg)
FSP > $5M total acquisition cost
WIC > $100K total acquisition cost
FSP > $1M total acquisition cost
WIC > $100K total acquisition cost
Competitive {
Non-
competitive {
![Page 56: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/56.jpg)
56
60 DAYS
![Page 57: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/57.jpg)
HHSEasier on you if we talk
and agree!
![Page 58: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/58.jpg)
![Page 59: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/59.jpg)
Stewardship
Ownership
Partnership
![Page 60: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/60.jpg)
Stewardship
![Page 61: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/61.jpg)
Partnership
![Page 62: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/62.jpg)
Ownership
![Page 63: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/63.jpg)
KnowledgeConfidenceBacking
![Page 64: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/64.jpg)
Know what they wantDescribe it accuratelyRecognize what resources they need to
hireDescribe them accuratelyHire the contractor that has the right stuffUse tools to hold contractor accountable
![Page 65: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/65.jpg)
What States want
Reasonable costLow riskReliable outcomeHappy ExecsOn timeHappy usersNo bad press
What you want
![Page 66: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/66.jpg)
Fair and competitionStewardship of Federal fundsA process that results in access &
integrity in benefit deliveryA process that holds up to legal
challengesEvidence that the State is in control of
its own destiny
HINT: HINT:
Use the RFP
Use the RFP
Checklist in
Checklist in
901!901!
![Page 67: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/67.jpg)
NEVERdefine the work and then bid on it
do the work, and then evaluate it.
OR
![Page 68: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/68.jpg)
Used to hire professional and technical skill sets to design a new system, write or adapt the software, produce documentation, and test and implement the system.
![Page 69: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/69.jpg)
Introduction & OverviewCurrent processing environmentWorkload dataNew system environment (including
projected growth)
Hint: This stuff is
in 901’s
procurement
chapter!
![Page 70: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/70.jpg)
Solicitation Instructions and Conditions“Boilerplate” language – legal and
purchasing requirementsProposal structure and contentProcurement scheduleQ&A processSubmission process
![Page 71: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/71.jpg)
Statement of Work (SOW) – the MEAT!Desired project scheduleDeliverablesInstallation, Conversion, Maintenance
requirementsPersonnel requirementsFunctional requirements
![Page 72: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/72.jpg)
![Page 73: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/73.jpg)
![Page 74: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/74.jpg)
Did th
ey
get what
they
asked fo
r?
How did they stay on
schedule?
Did they win
that lawsuit?Only 3 change orders?!
![Page 75: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/75.jpg)
Create a detailed project timelineGuide state through design or functional
verification processDocument requirements and tech specsWrite or adapt the application codeCreate user and technical documentationConduct testingConvert data from the old systemConduct or support trainingOperate or train the Help Desk
![Page 76: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/76.jpg)
![Page 77: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/77.jpg)
![Page 78: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/78.jpg)
Rely on bidders’ questionsto clarify things you didn’t explain
fully.
Bid the product they built for the last customer
GuessBid high enough to cover the
unknowns
![Page 79: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/79.jpg)
![Page 80: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/80.jpg)
“Pay me now or
Pay me later”and
![Page 81: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/81.jpg)
![Page 82: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/82.jpg)
![Page 83: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/83.jpg)
![Page 84: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/84.jpg)
![Page 85: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/85.jpg)
![Page 86: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/86.jpg)
Management PlanIdentify who the contractor will report toDescribe the project management
structureDefine the type and frequency of status
reports requiredSpecify who will review and approval of
work performedClarify roles of state staff and other
contractors
![Page 87: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/87.jpg)
Evaluation and Award Process
Identify evaluation criteriaSpecify weight or points for each one Describe the scoring processSpecify the minimum technical scoreExplain how bidders will be notified
![Page 88: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/88.jpg)
DO√ Ensure that RFPs contain enough detail to clearly define requirements.
![Page 89: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/89.jpg)
DO√ Describe requirements and timeline expectations in specific terms to provide the contractor with adequate information to develop a responsive bid.
![Page 90: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/90.jpg)
DO
√ Describe acceptable levels and measures of performance for products and/or deliverables.
![Page 91: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/91.jpg)
![Page 92: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/92.jpg)
DO√ Assign people with enough technical expertise to the evaluation panel
√ Allow them enough time to really read and score all the proposals
√ Provide them training on how the process works and what the selection criteria mean
![Page 93: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/93.jpg)
Describe the performance and other relevant requirements of the procurement.
DON’TSpecify a “brand name” product instead of allowing “an equal” product to be offered, unless you’re talking about a state technical standard.
![Page 94: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/94.jpg)
Place unreasonable requirements on firms to qualify to do business.
Keep it
![Page 95: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/95.jpg)
Specify geographical preferences.
![Page 96: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/96.jpg)
Require unnecessary experience and excessive bonding
Include unlimited liability clauses
![Page 97: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/97.jpg)
Use noncompetitive pricing practices between firms or affiliated companies
Permit organizational conflicts of interest
Allow noncompetitive awards to consultants on retainer contracts
Take any arbitrary action in the procurement process
![Page 98: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/98.jpg)
PRICE TECHNICAL
![Page 99: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/99.jpg)
WHEW!Are we done yet?
![Page 100: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/100.jpg)
(But almost…)
![Page 101: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/101.jpg)
![Page 102: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/102.jpg)
Handbook 901Chapter 6 –
Procurement
All the goodies – Contract components, terms and conditions, checklists – including FNS-required provisions
![Page 103: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/103.jpg)
States are required to provide an annual update on all approved multi-year PAPD/IAPD projects
Allows FNS to fulfill its oversight responsibility
![Page 104: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/104.jpg)
Keep a State’s PAPD/IAPD current by periodically updating FNS on project status:Progress, accomplishments, and issues Changes or adjustments in plans or
approachesChanges in budget or expenditures Changes to scheduleMechanism to request approval for
successive phases of project (if limited approvals were initially provided)
![Page 105: The FNS “APD Process”](https://reader035.vdocument.in/reader035/viewer/2022070418/56815957550346895dc693f3/html5/thumbnails/105.jpg)
A significant increase in total project costs FSP >$1m or 10% of the total project cost,
whichever is higher
A significant change/delay to major milestones in project schedule FSP >120 days