the holford gas storage project

24
THE HOLFORD GAS STORAGE PROJECT FROM SITE EXPLORATION TO GAS OPERATION: A CASE STUDY Bruno Colcombet, Ross Fawthrop, BGS LONDON, 20/05/2015

Upload: others

Post on 15-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE HOLFORD GAS STORAGE PROJECT

THE HOLFORD GAS STORAGE PROJECT FROM SITE EXPLORATION TO GAS OPERATION: A CASE STUDY

Bruno Colcombet, Ross Fawthrop, BGS LONDON, 20/05/2015

Page 2: THE HOLFORD GAS STORAGE PROJECT

2

THE HOLFORD GAS STORAGE PROJECT

Salt Field in the UK (Beutel 2004)

Page 3: THE HOLFORD GAS STORAGE PROJECT

3

THE HOLFORD GAS STORAGE PROJECT

Project Summary

Site Location Byley, Cheshire (near Northwich)

Construction 2006-2013

Number of Caverns: 8

Average volume: 370,000 m3 (total 2,9 Mm3)

Depth 570 – 700 m bGL

Operating Pressures between 40 and 100 bar

Working Gas Volume 160 Mscm

Gas Operating Rate 22 Mscm/d

Compression Power 21 MW (3 compressors)

Water Injected 30 Mm3 from Weaver river

Salt Mass Extracted 7,68 MT

Solution Mining Duration 2,5 to 3 years per cavern group

Leaching facilities 28,000 to 35,000 m3/day (to Soda Ash Plant)

Saturation of the brine Holford Brinefield

Page 4: THE HOLFORD GAS STORAGE PROJECT

THE HOLFORD GAS STORAGE PROJECT

Project Timeline

1999 2013 1999 2001 2003 2005 2007 2009 2011 2013

Project Start (ICI and Scottish Power)

Planning Permission Approved

Project Acquisition by E.On UK Full Facility Gas Operation

Conceptual Design

Planning Application and Appeals

2D Seismic

Exploration Well

Wells Drilling Campaign

Caverns Solution Mining

Cavern Test, Completion, First Gas Fill, Snubbing (3 caverns)

Cavern Test, Completion, First Gas Fill, Snubbing (3 caverns)

Cavern Test, Completion, First Gas Fill, Snubbing (2 caverns)

Brine and Water Infrastructure Design and Construction

Gas Pipelines Design and Construction

Gas Plant Design and Construction

Page 5: THE HOLFORD GAS STORAGE PROJECT

5

THE HOLFORD GAS STORAGE PROJECT

Subsurface investigations

Site Detection Evaporite near surface, brine springs (Roman Times)

Salt extraction since 1680's (salt mine)

Wild brine pumping in the 19th century

Controlled Solution Mining since 1920's

Site Exploration and Existing ICI surveys, Byley well (ICI 1950),

Qualification RM wells (Middlewich Mine)

2D Seismic 20km - 4 lines (SP 2001)

Drakelow 2A well (SP 2003)

225 m of cores,

Sonic, Neutron-Density, Spectral Gamma Ray,

Borehore Scanner, VSP, Formation permeability testing

Construction Cavern Wells H401 – H408 (E.on 2006-2007)

Cores,

GR, Neutron-Density, Sonic, Spectral Gamma Ray

Nitrogen tightness tests (pre and post leaching)

Page 6: THE HOLFORD GAS STORAGE PROJECT

6

THE HOLFORD GAS STORAGE PROJECT

Comparison Salt Mining vs Gas Caverns

SALT MINING GAS STORAGE

Rock

Mechanics

Long term stability of the cavern

field under constant brine

pressure

Long term stability of cavern field under

fast pressure cycling

Thermo-mechanical modelling

Gas

Tightness

Enough for air blanket control

during construction

Investigation of salt and marl tightness

Gas tight casings, two cemented

casings in the salt layer

Downhole gas completion with safety

valves

Brine

Quality

Fully saturated, no impurities, no

dissolved gas No requirements

Schedule Uninterruptible brine supply,

flowrate depending on customers Usually as fast as possible

Cavern

shape Limited controls

Regular shapes, strict control of roof

and cavern neck

Process

Controls

Long term, low frequency, low

flow, numerous caverns online

Short term, high frequency monitoring,

high flow

Corrosion Long term acceptable, air blanket Unacceptable on casings, nitrogen

blanket

Costs As low as possible As low as possible

Page 7: THE HOLFORD GAS STORAGE PROJECT

7

THE HOLFORD GAS STORAGE PROJECT

Comparison design Salt Mining vs Gas Caverns

Typical Salt Mining:

Distance between caverns: 200 m

Cavern Diameter: 140 m

Pillar to Diameter ratio: 0.4

Cavern Volume: 600 000 m3+

Distance to rock head: 15 m

Cavern creation: 20 years+

Gas Storage Caverns:

Distance between caverns: 300 m

Cavern Diameter: 100 m

Pillar to Diameter ratio: 2

Cavern Volume: 350 000 m3+

Distance to rock head: 145 m

Cavern creation: 2.5 years+

200 m

140 m 60 m220 m

10 m

100 m 200 m 120 m

300 m

145 m

Page 8: THE HOLFORD GAS STORAGE PROJECT

8

THE HOLFORD GAS STORAGE PROJECT

Project Map

Gas Plant Leaching Station and Gas Manifold

Gas Cavern Field

Page 9: THE HOLFORD GAS STORAGE PROJECT

9

THE HOLFORD GAS STORAGE PROJECT

Core Analysis and Testing

Page 10: THE HOLFORD GAS STORAGE PROJECT

10

THE HOLFORD GAS STORAGE PROJECT

Core Analysis and Testing

Page 11: THE HOLFORD GAS STORAGE PROJECT

11

THE HOLFORD GAS STORAGE PROJECT

Site E-W Cross section

Page 12: THE HOLFORD GAS STORAGE PROJECT

12

THE HOLFORD GAS STORAGE PROJECT

Salt Mass Model

Page 13: THE HOLFORD GAS STORAGE PROJECT

13

THE HOLFORD GAS STORAGE PROJECT

Lithology and well architecture

Page 14: THE HOLFORD GAS STORAGE PROJECT

14

THE HOLFORD GAS STORAGE PROJECT

Cavern Development

Page 15: THE HOLFORD GAS STORAGE PROJECT

15

THE HOLFORD GAS STORAGE PROJECT

Cavern field horizontal view

Page 16: THE HOLFORD GAS STORAGE PROJECT

16

THE HOLFORD GAS STORAGE PROJECT

Cavern field vertical view (E-W)

Page 17: THE HOLFORD GAS STORAGE PROJECT

17

THE HOLFORD GAS STORAGE PROJECT

Cavern field vertical view (N-S)

Page 18: THE HOLFORD GAS STORAGE PROJECT

18

THE HOLFORD GAS STORAGE PROJECT

Cavern geomechanical model

Page 19: THE HOLFORD GAS STORAGE PROJECT

| 00/00/2014 | Titre la présentation 19

THE HOLFORD GAS STORAGE PROJECT

2D Seismic survey and drilling rig

Page 20: THE HOLFORD GAS STORAGE PROJECT

| 00/00/2014 | Titre la présentation 20

THE HOLFORD GAS STORAGE PROJECT

Weak brine pumps and leaching wellhead

Page 21: THE HOLFORD GAS STORAGE PROJECT

21

THE HOLFORD GAS STORAGE PROJECT

Brine Tanks and Nitrogen Facility

Page 22: THE HOLFORD GAS STORAGE PROJECT

22

THE HOLFORD GAS STORAGE PROJECT

Gas Wellhead and Completion Packer latch

Page 23: THE HOLFORD GAS STORAGE PROJECT

23

THE HOLFORD GAS STORAGE PROJECT

Debrining Wellhead and Snubbing

Page 24: THE HOLFORD GAS STORAGE PROJECT

24

THE HOLFORD GAS STORAGE PROJECT

Gas Plant and Temporary Construction Offices