the integ-risk fp 7 project (2008-2013)€¦ · the integ-risk fp 7 project (2008-2013) short...

27
iNTeg-Risk The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013

Upload: others

Post on 22-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk

The iNTeg-Risk FP 7 project (2008-2013)

Short presentation

Version of April 8, 2013

Page 2: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Contents

• Motivation – What is it about? – Challenge and solution – iNTeg-Risk Emerging Risk Management Framework (ERMF) – A 10 steps process; process for whom? – Terminology – emerging risk

• The iNTeg-Risk project (2008-2013) – Key information – Structure – Main approach – Case studies

• Main results – Overview of available material – Tools, methods and guidelines – Pre-standardization CEN Workshop Agreement (CWA) document

2

Example

Page 3: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

What is the challenge?

Any new or changed technology leading to potentially emerging risks need to balance the management of the risks against the benefits of introducing new technology to the market, including the time this takes

3

Accelerated time-to-market of EU technology

Social accepted management of emerging risks

New/changed technologies

Page 4: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

What is the solution? What is needed?

An agreed response to emerging (new technology related) risks is needed

4

This is the main idea behind the iNTeg-Risk project

Accelerated time-to-market of EU technology

Social accepted management of emerging risks

Agreed response to

emerging (new technology

related) risks

New/changed technologies

Page 5: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Agreed response – the iNTeg-Risk ERMF

5

Accelerated time-to-market of EU technology

Social accepted management of emerging risks

1. Early warnings - notions

2. Context & concerns

3. Identification of risk scenarios

4. Pre-assessment 5. Analysis(appraisal/assessment)

6. Characterization

7. Evaluation of tolerability & acceptability

8. Management & decision(treatment)

10. Monitoring, review & continuous improvement

Emerging Risk Horizon Screening

Emer

ging

Risk

Ass

essm

ent

Emerging Risk Pre-Assessm

ent

9. Communication and consultation

Emerging Risk Continuous Activities

New technology related emerging risk

Page 6: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk ERMF – a 10 steps process

6

1. Early warnings - notions

2. Context & concerns

3. Identification of risk scenarios

4. Pre-assessment 5. Analysis(appraisal/assessment)

6. Characterization

7. Evaluation of tolerability & acceptability

8. Management & decision(treatment)

10. Monitoring, review & continuous improvement

Emerging Risk Horizon Screening

Emer

ging

Risk

Ass

essm

ent

Emerging Risk Pre-Assessm

ent

9. Communication and consultation

Emerging Risk Continuous Activities

Page 7: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

For whom is this process needed?

7

New technology related emerging risk

The process is needed at all levels of concern

Page 8: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Terminology – what is an emerging risk?

8

Old issue(not regarded

as a risk)

Old risk

i) Number of hazards leading to the risk is growing

ii) Exposure to the hazard leading to the risk is increasing

iii) Effects/impacts of the hazards are getting worse (e.g. seriousness of health effects and/or the number of people affected)

Increased exposure

Increased no. of hazards

Increased severity

New risk

New risk

(Purely) new riskNew issuea) The risk did not previously exist and is caused by new processes, new technologies, new types of workplace, or social or organizational change

b) A long-standing issue is newly considered as a risk due to a change in social or public perception

c) New scientific knowledge allows a long-standing issue to be identified as a risk

New perception

New scientificknowledge

Increased risk:

New risk:

The term "increasing" is understood as something which can represent an industry wide, regional or global challenge.

Page 9: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – key information*

9

• 7th FP – Cooperation Programme – Theme 4; NMP** • Initiated through: ETPIS*** • Total budget : 19.3 mill EUR • Duration: Dec 2008 – May 2013 • Coordinator: A. Jovanovic, EU-VRi **** • No. of partners: 87 • No. of project participants: 431 • No. of deliverables: 227

* http://www.integrisk.eu-vri.eu/ ** NMP – Nanosciences, Nanotechnologies, Materials and New Production Technologies *** ETPIS – European Technology Platform for Industrial Safety **** EU-VRi – European Virtual Institute for Integrated Risk Management

Haus der Wirtschaft, Stuttgart, Germany

Page 10: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – main partners *

10

* From start-up (some changes during the project)

EDF D’Appolonia Technologica USTUTT Demokritos ARPC

GDF MIT Gmbh GERG LEIA IVF Mavionics

Definiens DNV BT URL VSB-TUO ARMINES-CRC

MERL COWI Enagás Imperial JSI GDS

TÜV Pöyry INCDPM TU Crete HSE-HSL TUKE

Novineon MOL Plc. SWISSI CONPRICI JRC FTN

R-Tech VSH KMM-VIN SINTEF CEN EKON

Iberdrola Swiss Re INERIS DTU-MAN RIVM SP

Atos Origin NIS CEA VTT RegLomb STUVA

Eni Norge Saipem BAM BZF vfdb EU-VRi

Page 11: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – structure

11

Page 12: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – main approach

12

New/changed technologies

Concurrent Top-down & Bottom-up approach

Page 13: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – case studies/ERRAs

• Grouped in four classes: – Type A: New (production) technologies 5 – Type B: New materials and products 3 – Type C: New technologies & production networks 5 – Type D: New policies 4 ----

17

• Directly or indirectly related to EU industrial innovation 13

• Bottom-up approach starting with problems identified as relevant and representative – 17 case studies; so-called ERRAs (Emerging Risk Representative Applications)

Page 14: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – case studies/ERRAs

The relations between the ERRA types are illustrated in the figure below, and also shows the structure of the CWA document where each ERRA group is represented in an annex.

14

Page 15: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of the ERRAs (Topic A)

Page 16: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of the ERRAs (Topic B)

Page 17: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of the ERRAs (Topic C)

Page 18: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of the ERRAs (Topic D)

Page 19: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

CWA document – other cases

• In the CWA document Annex A-D, corresponding to ERRA Groups A-D, the following cases have been used as examples:

– Hydraulic fracturing

– Carbon nanotubes

– Drilling in Arctic

– Nano-regulation

• In addition, Annex H consists of a sample list of emerging risks, which overlaps with the 17 ERRAs

19

Page 20: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Results: Overview of available material

20

1. Early warnings - notions

2. Context & concerns

3. Identification of risk scenarios

4. Pre-assessment 5. Analysis(appraisal/assessment)

6. Characterization

7. Evaluation of tolerability & acceptability

8. Management & decision(treatment)

10. Monitoring, review & continuous improvement

Emerging Risk Horizon Screening

Emer

ging

Risk

Ass

essm

ent

Emerging Risk Pre-

Assessment

9. Communication and consultation

Emerging Risk Continuous Activities1 document

1 document

1 document

Provides the structure/process

1StopShop

Methods, tools & information

(Portal)

Provides the methods, tools & GLs to

be used in the various process steps

Conc

urre

nt T

op-d

own

& B

otto

m-u

p ap

proa

ch

«Hundreds» of documents

Page 21: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk 1StopShop – tools/methods/etc.

21

Survey ToolTool for broad access of information/opinions in the project

ENISFERCompetences (persons & capacities) for dealing with emerging risks

EducationEducation system for professional and academic education

MethodsMart & GlossaryGeneral; Failure Analysis; Application-oriented and Alternative Methods

KPI LibraryKPIs (Key Performance Indicators) collected and stored in the KPI Library

SafetypediaInformation about the emerging risks and background information

Background tools

1StopShop

(Portal)

Page 22: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of the main tools

22

Page 23: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of selected methods*

23

1. Early warnings - notions

2. Context & concerns

3. Identification of risk scenarios

4. Pre-assessment 5. Analysis(appraisal/assessment)

6. Characterization

7. Evaluation of tolerability & acceptability

8. Management & decision(treatment)

10. Monitoring, review & continuous improvement

Emerging Risk Horizon Screening

Emer

ging

Risk

Ass

essm

ent

Emerging Risk Pre-Assessm

ent

9. Communication and consultation

Emerging Risk Continuous Activities

Existing EU and other

regulations

Expert consultations

Information from relevant organizations

Public info(Analysis by

tools)

Horizon scanning

1StopShop

Methods, tools & information

(Portal)

RICAF – C2

REWI – C2

Assessment of drone-crash scenarios – A3HAZID brainstorming – A4MIMAH – A1/A4DyPASI – A1/A4/C4Event analysis ERMF-IRGC – C4

Early risk assessment (Risk Spark) – A2Quick Check for emerging risks – B1

PHA/Rapid Risk Ranking – B3

(RICAF – C2)

REWI – C2ORIM – C2

Incident based method – C2HSE dual assurance method – C2

KPI Library

Change assessment method – A3QRA of LNG regasification – A4

QRA in underground HUBs – A5AMERA – B3

Model for safe subcontracting – C1Bayesian networks – D1

ERRA D2 Tool – D2QRA extended to NaTech events – D3

Vulnerability models for QRA NaTech ass. – D4Integrated Risk Analysis (IRA)

Tailorized Bow-Ties – A1/A4Time-framed risk assessment of CCS – A1

LCA assessment of CCS – A1

IRGC categorization

(ALARP budget approach – C1)

* Selection mainly based on ERRA summary reports and methods relevant for any emerging risk situation.

Page 24: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of other methods

24

Survey ToolTool for broad access of information/opinions in the project

ENISFERCompetences (persons & capacities) for dealing with emerging risks

EducationEducation system for professional and academic education

MethodsMart & GlossaryGeneral; Failure Analysis; Application-oriented and Alternative Methods

KPI LibraryKPIs (Key Performance Indicators) collected and stored in the KPI Library

SafetypediaInformation about the emerging risks and background information

Background tools

1StopShop

Methods, tools & information

(Portal)

Page 25: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

Overview of guidelines etc.

Handbook issues: • Uncertainty handling • Data mining • NaTech, common and systemic

factors, including security • Human factors in its

organizational context • Environmental impact assessment

25

Guidelines: • Emerging risks pre-assessment • Emerging risks appraisal • Emerging risks management • Emerging risks related to policies

and regulatory frameworks • Environmental issues • Risk governance and culture

Complementary guidelines covering all dimensions of risk (T-C-H-R) and issues like security, environment, etc.

Page 26: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

CEN WS67 CWA document – "the quintessence"

26

Page 27: The iNTeg-Risk FP 7 project (2008-2013)€¦ · The iNTeg-Risk FP 7 project (2008-2013) Short presentation Version of April 8, 2013 . Contents • Motivation – What is it about?

iNTeg-Risk project – more information

27

Check out the project web for more information (http://www.integrisk.eu-vri.eu/) In particular the project video