the iranian nuclear program: timelines, data, and estimates v5.0

24
The Iranian Nuclear Program Timelines, Data, and Estimates Maseh Zarif Deputy Director and Iran Team Lead AEI Critical Threats Project Current as of NOV 21 2012 using data from IAEA report dated NOV 16 2012 Copyright © 2012 by the AEI Critical Threats Project Version 5.0 NOVEMBER 2012 www.criticalthreats.org

Upload: aeis-critical-threats-project

Post on 09-May-2015

15.117 views

Category:

Documents


0 download

DESCRIPTION

This assessment is the seventh version of a recurring analysis of Iran’s nuclear program. This product is an exposition of the technical data contained in numerous International Atomic Energy Agency (IAEA) reports informed by the discussions of experts in the field of nuclear proliferation. It is a work in progress in that it will be revised continuously based on new information from the IAEA reports and other sources and on feedback from readers. We welcome your informed commentary on the technical considerations presented in this document. Please send your comments, with references to source-date or documentation, to [email protected]. For more on Iran's nuclear program, visit www.irantracker.org.

TRANSCRIPT

Page 1: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

The Iranian Nuclear ProgramTimelines, Data, and Estimates

Maseh ZarifDeputy Director and Iran Team Lead

AEI Critical Threats Project

Current as of NOV 21 2012 using data from IAEA report dated NOV 16 2012

Copyright © 2012 by the AEI Critical Threats Project

Version 5.0 NOVEMBER 2012

www.criticalthreats.org

Page 2: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Page 2

November 2012 International Atomic Energy Agency (IAEA) Findings

Additional Centrifuge Installation

Iran increased its enrichment capacity by installing additional centrifuges at its declared sites between August and November 2012. The hardened Fordow facility is now at maximum capacity (2,784 centrifuges). Of the 2,784, 696 centrifuges are currently enriching at Fordow and 696 are ready to begin enriching immediately. The IAEA also noted the addition of first-generation and advanced centrifuges, the latter undergoing testing, at the Natanz facility.

Increasing Enriched Uranium Stockpiles

Iran continues to produce low- (<5%) and medium-enriched (near 20%) uranium at historically high rates. It has now allocated roughly 40% of its medium-enriched uranium for conversion to reactor fuel plates; only a small fraction of the allocated material, however, has been packaged into fuel plates and placed into a reactor core as of August 2012.

Parchin Facility Inspection

Iran continues to deny the IAEA access to the Parchin facility, where the agency believes Iran conducted experiments related to nuclear weapons development. The IAEA noted that, even if it is given access to the site, its ability to “conduct effective verification will have been seriously undermined” by physical disruption and sanitization undertaken by Iran at the facility in 2012.

Weaponization

Iran continues to stonewall the IAEA regarding its weaponization activities. The agency reiterated its assessment of Iran’s work on nuclear weapons development: “the information indicates that, prior to the end of 2003 the activities took place under a structured program; that some continued after 2003; and that some may still be ongoing.”

Arak Reactor Timeline

Iran told the IAEA that it will begin operating the Arak heavy water reactor later than previously planned. The reactor, now scheduled for an early 2014 launch, will provide Iran with a separate pathway to acquiring fissile material for nuclear weapons in the form of weapons-grade plutonium.

Page 3: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

99.5 kgStored as enriched

uranium gas(available now for WGU

production)

52 kgFed into process for conversion to U3O8

(available for WGU production after re-

conversion to gas form)*

1.1 kgEnriched down to <4%

3.4 kgConverted into U3O8 fuel plates and placed into or irradiated in reactor core

(as of August 2012)

*Methods for converting near-20% material in U3O8 form back into a gas “are standard processes in the nuclear industry and Iran uses them as part of its uranium ore processing.”1 The conversion can be done using specialized facilities and can be accomplished in “days to weeks.”2 The near-20% LEU can only be classified as unusable in a breakout once the fuel assemblies containing the U3O8 are inserted and irradiated in a reactor core. Only a small fraction of Iran’s near-20% LEU in the form of U3O8 has been manufactured into fuel assemblies and placed into or irradiated in a reactor core (3.4 kg).

1) Gregory Jones, “Fueling the Tehran Research Reactor: Technical Considerations on the Risks and Benefits,” NPEC, October 12, 2009.

2) Ibid.

Iran has enough near-20% enriched uranium with which to produce weapons-grade uranium (WGU) for one warhead. Some of this material is currently stored in oxide powder form, which can be converted back into a gas for weapons-grade enrichment.

Total near-20% enriched uranium produced: 156 kg

NEAR-20% ENRICHED URANIUM 141 kg needed to produce one warhead’s worth of WGU156 kg produced as of November 2012 IAEA report (see pie chart for breakdown)151.5 kg available in gas or oxide powder form (allocated for use in fuel plates for Tehran Research Reactor)

Page 3

Status of Near-20% Enriched Uranium

Page 4: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

IRAN’S ENRICHMENT CAPABILITIES ARE NO LONGER THE PRIMARY BOTTLENECK IN A NUCLEAR BREAKOUT SCENARIO

Iran can produce one bomb’s worth of fissile material faster than it likely can deploy a functioning nuclear device. Tracking Iran’s uranium enrichment activities now addresses only Iran’s intentions and the size of its projected arsenal.

Obtaining fissile material in the form of weapons-grade uranium or plutonium is the most technically demanding step in acquiring a nuclear weapons capability. Designing an explosive device (consisting of non-nuclear components) and a delivery system for the device are comparatively less technically challenging. Those efforts can also proceed parallel to enrichment.

Iran has the infrastructure and material to produce weapons-grade uranium. It has enough enriched uranium to produce fuel for six nuclear weapons after conversion to weapons-grade levels. Its expanding enrichment activities have significantly reduced the time required for it to produce weapons-grade uranium. The key accelerants for this shrinking timeline have been its growing stockpiles of low- and medium-enriched uranium, which is 90% of the way to weapons-grade uranium, and an increasing number of centrifuges enriching.

Key Points

Copyright © 2012 by the AEI Critical Threats Project

Page 4

Page 5: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Nuclear Program ExpansionIran will likely have enough near-20% enriched uranium to rapidly produce fissile material for 2 nuclear weapons by late 2013 or early 2014.

Iran has installed many more centrifuges at the hardened Fordow facility than are now actually spinning, providing a reserve and/or surge capacity that will be difficult for Israel to destroy.

The installation of 2,088 additional centrifuges at Fordow since summer 2012 gives Iran the ability to:

produce near-weapons grade uranium (20% enrichment level) in larger quantities faster, providing rapidly-convertible feedstock for a small arsenal of nuclear weapons;

convert near-weapons grade uranium into nuclear weapons fuel in a shorter amount of time.

Iran’s uranium enrichment is at historically high rates despite increasing sanctions and damage to the Iranian economy.

Iran told the International Atomic Energy Agency (IAEA) that it plans to begin operating the Arak heavy water reactor in early 2014 (it had previously planned commencement for mid-to-late 2013). This reactor will be capable of producing two warheads’ worth of weapons-grade plutonium per year once operational.

Page 5

Page 6: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Breakout TimelinesTime needed to produce fuel for 1 nuclear weapon:

Iran needs 3.6 months to produce 25 kg of weapons-grade uranium and 1.9 months to produce weapons-grade uranium at the buried Fordow and pilot Natanz enrichment facilities.* It can cut these times significantly using the centrifuges installed but not yet operating at the Fordow facility.

Iran needs 4-10.5 weeks to produce 25 kg of weapons-grade uranium and 1.5-5 weeks to produce 15 kg of weapons-grade uranium at the main Natanz enrichment facility.* The higher end of the range accounts for a three-step conversion process.

Estimates of the time Iran needs to build a nuclear device to use this fissile material are generally longer than the timelines above.

The existence of undeclared (covert) enrichment sites would have a significant impact on breakout estimates.

Evidence of significant Iranian enrichment beyond 20% will strongly suggest not only that the decision to weaponize has been made, but also that the Iranians believe they have (or will shortly have) a viable warhead.

*All enriched uranium figures are given in terms of solid uranium (where 1 kg uranium hexafluoride is equal to ~0.67 kg elemental uranium). Estimates assume Natanz and Fordow are used with the operational capacity reflected in the November 2012 IAEA report. Iran may need 15-25 kg of weapons-grade uranium for an implosion-type bomb design depending on its

level of technical ability (high technical ability would require less material). See pages 18, 19, and 22 for further detail. Page 6

Page 7: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Iran has outfitted the hardened Fordow enrichment facility with 2,784 IR-1 centrifuges. This expansion gives Iran the capacity to produce near-20% enriched uranium at a faster rate and the means to convert that stockpile to weapons-grade uranium (WGU) more rapidly in a deeply buried site.

Time needed to produce WGU for 1 warhead from near-20% enriched uranium at Fordow

4.7 MONTHS

2.4 MONTHS

1.2 MONTHS

Page 7

Using 696 centrifuges currently enriching

Using 1,392 centrifuges currently enriching and under

vacuum

Using all 2,784 centrifuges available

Time needed to produce near-20% enriched uranium feed

for WGU for second warhead*

14 MONTHS

8.6 MONTHS

4.7 MONTHS

*Assumes constant production of near-20% enriched uranium at smaller pilot facility at Natanz

Page 8: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

0

1000

2000

3000

4000

5000

6000

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12

Iran’s Declared 3.5% Enriched Uranium Production at Natanz

Copyright © 2012 by the AEI Critical Threats Project

Page 8

Assessment: Stuxnet derailed the 2009 Iranian effort to expand enrichment capability for roughly one year, but the enrichment expansion effort recovered in mid-2010. Neither direct actions nor sanctions have had a visible effect on the enrichment program. Even the Stuxnet success does not appear to have derailed the steady growth of the enriched uranium stockpile. Iran is running its highest number of centrifuges and production rates since the enrichment program began. It has produced enough enriched uranium since 2009 to fuel a small arsenal of nuclear weapons after conversion to weapons grade.

Stuxnet Launched

New U.S./UN/EU

sanctions

Iranian Scientist

Killed

Enrichment data source: IAEA

Centrifuges enriching

Centrifuges not enriching

3.5% LEU produced

Kilo

grams LEU#

cen

trif

uge

s

Page 9: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

0

141

282

423

564

705

May-12 Jul-12 Oct-12 Jan-13 May-13 Jul-13 Oct-13 Jan-14

Near-20% Enriched Uranium Production and Projected Growth at Fordow/Natanz

BLACK: Reported productionRED: Steady-state enrichment (a)

GREEN: Gradual enrichment expansion in available centrifuges at Fordow (b)

PURPLE: Rapid enrichment expansion at Fordow (c)

*The two lines for each colored scenario represent a range based on different calculations of demonstrated centrifuge efficiency.

(a) 1,024 centrifuges currently enriching (2 cascades with 328 total IR-1 centrifuges at PFEP and 4 cascades with 696 total IR-1 centrifuges at Fordow)(b) Same as (a) but Iran begins turning on 2 additional cascades at Fordow every three months in DEC.

(c) Iran begins enriching in the 4 additional cascades under vacuum at Fordow in DEC. It will begin enriching in the 8 remaining cascades in JAN 2013.

Copyright © 2012 by the AEI Critical Threats Project

Page 9

Kilo

gram

s 1

9.7

5%

LEU

Iran will have produced 282 kg ~20% enriched uranium by late 2013/early 2014 under steady-state conditions--enough to produce WGU for two nuclear bombs designed with a low level of technical capability.

156 kg(as of NOV 2012)

Amount needed for:

4 weapons

3 weapons

2 weapons

1 weapon

~20% enriched uranium production enough to produce WGU for three nuclear bombs by late 2013/early 2014. Iran would need to begin enriching gradually in installed Fordow cascades to meet this threshold.

Page 10: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

12/1/2012 1/1/2013 2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013 8/1/2013 9/1/2013 10/1/2013 11/1/2013 12/1/2013 1/1/2014

Key Upcoming Events

Italicized dates are estimates; bold dates are fixed Listed inspection windows are approximate. The IAEA may be conducting inspections outside of these windows.

Copyright © 2012 by the AEI Critical Threats Project

Page 10

IAEA BOG = International Atomic Energy Agency Board of Governors

3/4/2013

IAEA BOG meets

2/22/2013

IAEA Report

12/15/2013

Approx. date by which Iran—at current rates—will produce enough near-20% enriched uranium

to convert to WGU for a second warhead

5/24/2013

IAEA Report

1/22/2013 - 2/12/2013

IAEA Inspection Window

6/3/2013

IAEA BOG meets

4/23/2013 - 5/14/2013

IAEA Inspection Window

11/29/2012

IAEA BOG meets

9/9/2013

IAEA BOG meets

8/30/2013

IAEA Report

7/30/2013 - 8/20/2013

IAEA Inspection Window

Page 11: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Making an Atomic Bomb (Concept)

Copyright © 2012 by the AEI Critical Threats Project

Page 11

Centrifuge cascade

LEU gas(3.5% U-235)

High-enriched elemental uranium

solid metal (90% U-235)

Natural uranium

Centrifuge cascade

Fed

th

rou

ghp

rod

uce

s

Fed back into produces

Co

nve

rted

to

UF6 gas0.7% U-235

UF6 gas19.75% U-235

Pro

cess

ed

into

Fed

bac

k in

top

rod

uce

s

UF6 gas90% U-235

Centrifuge cascadeTwo-step

uranium enrichment

process

Acquire Weapons-grade Uranium

Acquire delivery vehicle

Mate warhead with delivery vehicle

(Process complete)

Acquire weapon design

Develop detonator technology

Build weapon

Test weapon

Designwarhead

Shahab-3missile

Parallel processes Parallel processes

then

Test design and engineering

Page 12: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Making an Atomic Bomb (Status as of NOV 2012)

Copyright © 2012 by the AEI Critical Threats Project

Page 12

Centrifuge cascade

LEU gas(3.5% U-235)

High-enriched elemental uranium

solid metal (90% U-235)

Natural uranium

Centrifuge cascade

Fed

th

rou

ghp

rod

uce

s

Fed back into produces

Co

nve

rted

to

UF6 gas0.7% U-235

UF6 gas19.75% U-235

Pro

cess

ed

into

Fed

bac

k in

top

rod

uce

s

UF6 gas90% U-235

Centrifuge cascade

Acquire Weapons-grade Uranium

Acquire delivery vehicle

Mate warhead with delivery vehicle

(Process complete)

Acquire weapon design

Develop detonator technology

Build weapon

Test weapon

Designwarhead

Shahab-3missile

Parallel processes Parallel processes

then

Test design and engineering

Done

Done

Done

DoneDone

Underway

Underway

Not reporte

d

Not reporte

d

Not reporte

d

Preparin

g

Underway

Underway

Done

Preparin

g

NB: All estimates of Iran’s nuclear status and capabilities assume that there are no clandestine facilities, and that the IAEA has full access to all declared facilities. The first assumption is impossible to verify. The second assumption is known to be false.

Page 13: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

The work and time required to enrich uranium from its natural concentration (0.7%) to 3.5% LEU is an order of magnitude greater than that required to enrich 20% LEU to weapons-grade concentrations (~90% U-235). That is because centrifuges must spin more than 14,000 kg of uranium ore to produce 1,373 kg of 3.5% LEU, but only 116 kg of 20% LEU to produce 15 kg of weapons-grade uranium.

Why Enrichment Accelerates at Higher Concentration of U-235

Copyright © 2012 by the AEI Critical Threats Project

Page 13

Centrifuge cascade

LEU gas(3.5% U-235)

High-enriched elemental uranium

solid metal (90% U-235)

Natural uranium

Centrifuge cascade

Fed

th

rou

ghp

rod

uce

sFed back into produces

Co

nve

rted

to

UF6 gas0.7% U-235

UF6 gas19.75% U-235

Pro

cess

ed

into

Fed

bac

k in

top

rod

uce

s

UF6 gas90% U-235

Centrifuge cascade

1,373 kg 116 kg

14,187 kg 15 kg

5,060 SWU331 days

559 SWU37 days

115 SWU8 days

SWU = Separative work unit, a measure of the amount of effort required to process nuclear material. The SWU requirement is used to determine the time needed to enrich uranium with a given number of centrifuges operating at a given efficiency.

Page 14: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

145 km

`

Copyright © 2012 by the AEI Critical Threats Project

Fordow Fuel Enrichment Plant (FFEP)As of NOV 10 2012:

696 IR-1 centrifuges producing near-20% LEU 696 IR-1 centrifuges under vacuum and 1392 IR-1 centrifuges not enrichingFacility producing near-20% low-enriched uranium (LEU)464.3 kg 3.5% LEU converted to 64 kg near-20% LEU225 kg 3.5% LEU remaining from Natanz stockpile sent here*

Natanz Fuel Enrichment Plant (FEP)As of NOV 2012:

9156 IR-1 centrifuges producing <5% LEU 1258 additional IR-1 centrifuges not enrichingFacility producing 3.5% enriched LEU4992 kg 3.5% LEU produced herePilot Fuel Enrichment Plant (PFEP)

As of NOV 2012:328 IR-1 centrifuges producing near-20% LEU176 IR-2m and 176 IR-4 centrifuges installed and intermittently fedFacility producing near-20% LEU788.6 kg 3.5% LEU converted to 92 kg near-20% LEUUnknown kg 3.5% LEU stored here

Notes* Calculated estimated based on amount IAEA reported has been transferred from Natanz to Fordow

Iran’s Declared Uranium Enrichment Facilities

Page 14

Page 15: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Underground halls under construction FEB 2003

Natanz Enrichment Facilities

Copyright © 2012 by the AEI Critical Threats Project

Page 15

Pilot Fuel Enrichment Plant (PFEP)As of NOV 2012:

328 IR-1 centrifuges producing near-20% LEU176 IR-2m and 176 IR-4 centrifuges installed and intermittently fedFacility producing near-20% LEU788.6 kg 3.5% LEU converted to 92 kg near-20% LEUUnknown kg 3.5% LEU stored here

Natanz Fuel Enrichment Plant (FEP)As of NOV 2012:

9156 IR-1 centrifuges producing <5% LEU 1258 additional IR-1 centrifuges not enrichingFacility producing 3.5% enriched LEU4992 kg 3.5% LEU produced here

Page 16: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Image from NOV 24 2009 (Google Earth)

Image from MAR 24 2005 (Google Earth)

Areas covered in 2005 appear as entrances to underground facilities in 2009

New above-ground facility

appears between 2005 and

2009

Ridgeline rises roughly 200 feet from entrances

to peak.

Fordow Enrichment Facility: Status and Construction

Copyright © 2012 by the AEI Critical Threats Project

Page 16

Pleiades, Apollo Mapping

Image taken SEP 14 2012

Fordow Fuel Enrichment Plant (FFEP)As of NOV 10 2012:

696 IR-1 centrifuges producing near-20% LEU 696 IR-1 centrifuges under vacuum and 1392 IR-1 centrifuges not enrichingFacility producing near-20% low-enriched uranium (LEU)464.3 kg 3.5% LEU converted to 64 kg near-20% LEU225 kg 3.5% LEU remaining from Natanz stockpile sent here*

Notes* Calculated estimated based on amount IAEA reported has been transferred from Natanz to Fordow

Page 17: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Scope, Assumptions and Technical Points

Page 17

Page 18: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

This product is an exposition of the technical data contained in numerous IAEA reports informed by the discussions of experts in the field of nuclear proliferation. It is a work-in-progress in that it will be revised continuously based on new information from the IAEA and other sources and on feedback from readers.

We welcome your informed commentary on the technical considerations presented in this document. Please send your comments, with references to source-data or documentation, to [email protected].

This product does NOT contain policy recommendations. It is intended solely to inform the policy community and the American public about the nature and progress of the Iranian nuclear program.

This product does NOT assess Iran’s intentions to weaponize or to pursue breakout scenarios. It is focused entirely on technical feasibility.

Scope

Page 18

Page 19: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Worst-caseThe worst-case scenarios assume that Iran devotes all operational centrifuges at Natanz (as of NOV 2012) to producing first additional 19.75% LEU and then 90% highly-enriched uranium (HEU), ceasing production of 3.5% LEU. Such actions would be visible to inspectors and so would most likely occur between inspections. Iranian nuclear policy and strategy does not appear to be going down this road. The scenarios assume 9,156 centrifuges spinning (the number being fed uranium as of NOV 2012) operating with an efficiency of 0.9 separative work units (SWU)/centrifuge/year (roughly the efficiency they have demonstrated). 15 kg requirement: Iran begins to race to breakout by producing 116 kg total of 19.75% LEU and then enriching that material to 90% HEU.25 kg requirement: Iran begins to race to breakout by producing 193 kg total of 19.75% LEU and then enriching that material to 90% HEU. If Iran breaks out using a three-step process, it would need to produce 240 kg total of 19.75% LEU in total, then enrich to 60% HEU and then to 90% HEU to yield 15 kg. Assuming Iran needs 25 kg 90% HEU, it would need to produce 399 kg total of 19.75% LEU before it could convert to 60% and then 90%.These calculations assume tails assays of 2.0% and 9.3% for the two steps in the first process and 2.0%, 12.0%, and 41.1% for the three steps in the second process (see page 22). These data are derived from the Natanz facility; the Fordow installations are notably more efficient with lower tails assays.

Most LikelyThe 9,156 centrifuges being fed in the main cascade hall at Natanz continue to produce 3.5% LEU and are not diverted to higher-level enrichment. Iran uses 85 kg 19.75% LEU to produce 15 kg 90% HEU or continues enriching to 19.75% until it has amassed approximately 141 kg 19.75% LEU, which can yield 25 kg 90% HEU. Enrichment to 19.75% occurs in 4 cascades totaling 696 IR-1 centrifuges at Fordow (2 sets of 2 interconnected cascades) and 2 cascades totaling 328 IR-1 centrifuges at the Natanz PFEP (all currently operational). Enrichment from 19.75% to 90% occurs in 6 cascades at Fordow in one step using a tails assay of 4.6%. The difference in the tails between the worst-case and most likely breakout scenarios reflects the fact that the cascades at Fordow, like the ones at Natanz PFEP, are interconnected in pairs.

Copyright © 2012 by the AEI Critical Threats Project

Breakout Scenarios

Page 19

Page 20: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Atomic Weapons Data

Small atomic weapons can be built from cores consisting of 10-25 kg of uranium enriched to 90% U-235 (weapons-grade HEU). We use 15 kg and 25 kg to assess breakout timelines.The explosive yield of a 15 kg core is on the close order of 15 kilotons. Uranium can be enriched to HEU in a two-step or a three-step process.Both processes begin by enriching natural uranium (0.7% U-235) to 3.5% LEU.The two-step process enriches from 3.5% LEU to 19.75% LEU, and then from 19.75% LEU directly to 90% HEU.The three-step process proceeds from 3.5% LEU to 19.75% LEU, from 19.75% LEU to 60% HEU, and then from 60% HEU to 90% HEU.The most important difference between these processes is the amount of LEU required initially—the time required to enrich from 19.75% to 90% is virtually the same for either process.The two-step process for producing 15 kg weapons-grade HEU requires 85 kg of 19.75% LEU using interconnected cascades (such as at Fordow) or 116 kg using non-interconnected cascades (such as those at Natanz). Producing 25 kg weapons-grade HEU in a two-step process requires 141 kg of 19.75% LEU using interconnected cascades or 193 kg using non-interconnected cascades. The three-step process requires significantly more in non-interconnected cascades (such as at Natanz).There is disagreement among experts about Iran’s ability to execute a two-step process with its current technology and cascade configuration. If Iran were forced to use a three-step process, the primary delay would result from the time required to produce the additional 19.75% LEU, a factor that Iran could affect either by bringing more centrifuge cascades online or by beginning to enrich with more efficient centrifuges, some of which are already installed but not yet producing enriched uranium.

Copyright © 2012 by the AEI Critical Threats Project

Page 20

Page 21: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Comparison of Estimated Breakout Times

Copyright © 2012 by the AEI Critical Threats Project

AEI Critical Threats Project

Nonproliferation Policy Education Center

Bipartisan Policy Center

Institute for Science and International Security

Wisconsin Project on Nuclear Arms Control

Page 21

RED boxes denote scenarios using all or majority of available cascadesBLUE boxes denote scenarios not using cascades in the main halls at Natanz

1/7/2013

Natanz 9,156 centrifuges 16 kg 90% HEU

11/20/2012

Start

Note that some analyst estimates are based on earlier IAEA reports and do not take account of the new information. Assumptions, including efficiency rates and fissile material quantities, vary across the estimates.

11/20/2012

Start

11/20/2012

Start

1/4/2013

2-step at Natanz FEP and clandestine facility (20 kg)

12/20/2012

2-step at Natanz (20 kg)

11/20/2012

Start 3/5/2013

3-step at Natanz (20 kg)

11/20/2012

Start

2/27/2013

At Fordow with 1392 centrifuges 16 kg 90% HEU

3/20/2013

25 kg 90% HEU

3/8/2013

25 kg 90% HEU at Fordow

+pilot Natanz

2/1/2013

3-step at Natanz (25 kg)

12/25/2012

3-step at Natanz (15 kg)

12/18/2012

2-step at Natanz (25 kg)

1/16/2013

15 kg 90% HEU At Fordow

+ pilot Natanz

2/21/2013

3-step at Natanz FEP, Fordow, and PFEP (20 kg)

1/19/2013

25 kg 90% HEU

11/30/2012

2-step at Natanz (15 kg)

Page 22: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Projections for the February 2013 IAEA Report

IR-1 centrifuges being fed at Natanz FEP: 9,156 (moderate confidence)

Total 3.5% LEU produced at Natanz FEP: 5,567 kg (moderate confidence)*

IR-1 centrifuges being fed for 19.75% enrichment at Natanz and Fordow: 1,024 (low confidence)

Total 19.75% LEU produced at Natanz PFEP and Fordow FEP: 184.8 kg (moderate confidence)*

PREVIOUS PROJECTIONS3.5% LEUWe previously estimated that Iran would produce an additional 498 kg of 3.5% enriched uranium at Natanz during the last reporting period. The IAEA reported that Iran produced about 492 kg 3.5% enriched uranium during the period.

19.75% LEUWe previously estimated that Iran would produce an additional 23 kg of 19.75% enriched uranium at Natanz and Fordow during the last reporting period. The IAEA reported that Iran produced about 29 kg 19.75% enriched uranium. The error is attributed to timing (our estimate was based on a November 4 measurement and the actual measurement took place on November 10-11) and increased production rate per centrifuge at Fordow.

Page 22*Assuming IAEA measurement on 11 FEB 2013

Page 23: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

Sources

Copyright © 2012 by the AEI Critical Threats Project

International Atomic Energy Agency (IAEA) – The IAEA publishes quarterly reports on Iran’s nuclear program and enrichment progress. Enriched uranium stockpile, centrifuge count, potential inspection windows, and other technical data provided by the IAEA are used in our analysis to determine historical rates of production and to serve as a basis for building projections. IAEA reports on Iran are available at http://www.iaea.org/newscenter/focus/iaeairan/iaea_reports.shtml.

World Information Service Project on Energy (WISE) – WISE provides a uranium enrichment calculator for calculating the separative work required to achieve specific levels of U-235 concentration. The calculator uses manual inputs of feed, product, and tails figures to calculate separative work units (SWU). The resultant SWU serves as the basis for calculating time requirements. This assessment uses the WISE calculator to determine the SWU required for enriching at various levels. The online calculator is accessible at http://www.wise-uranium.org/nfcue.html.

Gregory Jones, Nonproliferation Education Policy Center (NPEC) – Gregory Jones provided the estimated tails percentage figures for enriching to weapons-grade uranium levels for two-step and three-step batch recycling methods (starting with 3.5% LEU) at the Natanz FEP and two-step batch recycling (from 3.5%) at Natanz PFEP/Fordow FEP, where cascades are interconnected. Jones has written that the technical assumption underlying an Iranian attempt to break out using two-step batch recycling without reconfiguration (from 3.5%) may not be feasible. The alternative Iranian breakout approach he suggests, adding an intermediary step between 19.75% and 90% enrichment, is one that we have relied on in our analysis. Jones’s analyses are available at http://www.npolicy.org/.

Jones has written that the process for Iran to convert the U3O8 enriched up to 20% created for fuel plates back to 20% enriched UF6 gas for use in a breakout “involves dissolution by nitric acid, followed by purification by solvent extraction. These are standard processes in the nuclear industry and Iran uses them as part of its uranium ore processing...The time required from the removal of the fresh TRR fuel from safeguards to the time to produce 19.75% enriched uranium hexafluoride would be only ‘days to weeks.’ [citing Albert Wohlstetter et al, Swords from Plowshares, Chicago University Press, 1979]” The report is available at http://www.npolicy.org/article_file/Fueling_the_Tehran_Research_Reactor-Technical_Considerations_on_the_Risks_and_Benefits.pdf.

Further on this topic, Henry Sokolski, NPEC, has written that Iran could withdraw 19.75% enriched uranium from fuel plates in the form of UF6 gas in 1-2 weeks. See http://www.nationalreview.com/corner/188387/fueling-around-iran-and-bomb/henry-sokolski.

Institute for Science and International Security (ISIS) – ISIS has contributed to a technical debate among experts regarding the feasibility of two-step and three-step batch recycling methods. ISIS analyses are available at http://isis-online.org/.

Alexander Glaser, “Characteristics of the Gas Centrifuge for Uranium Enrichment and Their Relevance for Nuclear Weapon Proliferation,” Science and Global Security (16:1-25, 2008) – Glaser’s analysis of the P-1 centrifuge—the foundation of Iran’s IR-1 centrifuge program—is the basis for two-step batch recycling projections for enriching to weapons-grade uranium. A key aspect of Glaser’s analysis in this paper was that 90% HEU can be produced in one step from 19.7% LEU without the need to reconfigure the arrangement of cascades. In October 2011, according to Gregory Jones, Glaser said he had “been made aware of certain phenomena that are not taken into account” in his 2008 analysis and that “We now find that the most credible scenarios involve some kind of cascade reconfiguration.” See Greg Jones, “Earliest Date Possible for Iran’s First Bomb,” Nonproliferation Education Policy Center, December 6, 2011, http://npolicy.org/article.php?aid=1124&rid=4. For Glaser’s original analysis, see http://www.princeton.edu/sgs/publications/sgs/archive/16-1-Glaser.pdf.

International Commission on Nuclear Non-Proliferation and Disarmament (ICCND) – The ICCND notes that a basic implosion-type nuclear weapon design with an explosive yield of 15 kilotons would require 15 kg of weapons-grade uranium. We use this figure as the minimum 90% HEU Iran would produce to fuel one bomb. See http://icnnd.org/Reference/reports/ent/part-ii-4.html.

Thomas B. Cochran and Christopher E. Paine, “The Amount of Plutonium and Highly-Enriched Uranium Needed for Pure Fission Nuclear Weapons,” National Resources Defense Council, April 13, 1995. – Cochran and Paine assert that the “significant quantity” measurement of 25 kg weapons-grade HEU used by the IAEA greatly overestimates the amount of fissile material required to fuel a basic implosion-type nuclear explosive device. They estimate that a state with a low technical capability can produce a bomb with an explosive yield of 20 kilotons with 16 kg weapons-grade HEU. See: http://www.nrdc.org/nuclear/fissionw/fissionweapons.pdf. Page 23

Page 24: The Iranian Nuclear Program: Timelines, Data, and Estimates V5.0

For more on Iran, visitwww.irantracker.org