• Sometimesaverydifficultproject,includingsignificantinvestmentandperseverance,isneededtofillacriticallinkinabroaderactivetransportationnetwork
o Federal,state,andlocalfundingofnearly$25millionoverseveralphasessince2009
• Achampionandabroadcoalitionofpartnersareessentialtomakeachallengingtrailprojecthappen
GovernorJackA.Markell
GovernorJackA.Markell
GovernorJackA.Markell
Context
Context
• Sevenmiles
• Formerfreightrailline,theNewCastleIndustrialTrack,takenoutofserviceinthe1970sandsubsequentlyabandoned
• NowownedbytheStateofDelaware
MANYMATUREURBANANDSUBURBANAREAS
SIGNIFICANTENVIRONMENTALCONSTRAINTS
Phasingandpartnering
NORTHERNGAP
SOUTHERNGAP
PHASE1
PHASE2
PHASE3
Phasingandpartnering
PROJECTPARTNERS
• StateofDelaware:Ownershipofmostofthecorridor,designandconstructionofmultiplephases,bridgemaintenance
• FederalHighwayAdministration:FundingthroughTransportationAlternativesProgram(TAP),stimulus(ARRA),andCongestionManagementandAirQuality(CMAQ)programs
• NewCastleCounty:Designandconstructionofonephase,day-to-daymaintenanceandoperations
• CityofNewCastle:Matchfordesignandconstructionofonephase
• DelawareRiverandBayAuthority:Design,construction,operation,andmaintenanceoftrailtunnelunderI-295
• RiverfrontDevelopmentCorporation:Landownership,day-to-dayoperationsofonephase,securitymonitoring
• Manyotherpartnersadvocatedfortheproject
Overallnetwork
Connectstoexistingactivetransportationnetworks
TourismpotentialforWilmingtonRiverwalk
• Redevelopedriverfrontwithshopping&restaurants
• Easyaccesstodowntown
• Transitconnections,includingAmtrak
• HighlightsWilmington’shistoricshipbuildingindustry
Overallnetwork
AVIABLECOMMUTINGCHOICE
Approximatetraveltimes
Route LengthBicyclistat
12mph
Bicyclistat
20mphMotorist
Industrial
TrackTrail
6.4
miles32min 19min N/A
SR141and
US13
6.2
miles31min* 19min* 14min**
SR9/ASt6.2
miles31min* 19min* 18min**
I-95via
SR141
7.7
milesN/A N/A 11min**
*Doesnotincludedelayattrafficsignals.
**Asestimated byGoogleMaps.Maybelongerduringpeakhours.
Wilmington
NewCastle
Implementation
PHASE1
Twomilesection
Railtrail;formerIndustrialTrackfreightline
State-ownedrightofway
AmericanRecoveryandReinvestmentAct(ARRA)funding
Extremelyfast-trackschedule
Survey,conceptandfinaldesigninfivemonths
Completedin2010
Phase1
PHASE1
Implementation
PHASE1
Implementation
PHASE1
Implementation
PHASE1
Implementation
PHASE1
Implementation
PHASE1
Implementation
PHASE1
Implementation
Implementation
PHASE2
1.5milesection
DesignedandconstructedbyNewCastleCounty
ExtendsalongtheabandonedrailrightofwaytothesouthbankoftheChristinaRiver
Completedin2013
Phase2
Implementation
FILLINGINTHEGAPS
Gap#1
Gap#1:ConnectingtoNewCastle
Implementation
FILLINGINTHEGAPS
NewCastle IndustrialTrackTrail
FILLINGINTHEGAPS
TheJackA.MarkellTrail
FILLINGINTHEGAPS
Gap#2:ConnectingtoNewCastle
Anotherunsignalized,mid-blockcrossing
Medianwasinstalleduponcompletionofthisphaseofthetrailin2014
RectangularRapidFlashingBeacon(RRFB)wasinstalledtwoweeksago
NewCastle IndustrialTrackTrail
FILLINGINTHEGAPS
NewCastle IndustrialTrackTrail
FILLINGINTHEGAPS
Implementation
FILLINGINTHEGAPS
Gap#2
Gap#2:Interstate295&US13Interchange
TheJackA.MarkellTrail
FILLINGINTHEGAPS
Gap#2:Interstate295&US13Interchange
• Trailunderpassesincorporatedintolargerconstructionprojects
• Completionanticipatedthisspring
TheJackA.MarkellTrail
FILLINGINTHEGAPS
TheJackA.MarkellTrail
FILLINGINTHEGAPS
Implementation
PHASE3
1.1milesection
Feasibilitystudyandconceptdesigncompletedin2013
Finaldesignandpermittingcompletedin2016
Challengingsegment
• ChristinaRiver
• Tidalwetlands
• In-servicerailline
Opportunityforasignaturebicycleandpedestrianbridge
Phase3
TheJackA.MarkellTrail
PHASE3
PHASE3SIGNATUREBRIDGE
TheJackA.MarkellTrail
Conceptdevelopedthroughastakeholdercharrette
PHASE3SIGNATUREBRIDGE
TheJackA.MarkellTrail
TheJackA.MarkellTrail
PHASE3
PHASE1
Implementation
TheJackA.MarkellTrail
PHASE3
TheJackA.MarkellTrail
PHASE3
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
TheJackA.MarkellTrail
CONSTRUCTIONPROGRESS
PHASE3
TheJackA.MarkellTrail
Implementation
SUMMARY
Progress:
• Completed:Phases1and2&Gap#1
• Underconstruction:Phase3&Gap#2
Theentiretrailisscheduledtoopenthissummer
Phase3
Phase2
Gap#2
Phase1
Gap#1
Lessonslearned
• Getdecision-makersatthetable,andinvesttheminthedesign
• Themorepartnerswhoareinvestedinsuccessfulimplementationofaproject,themorelikelyitwillgetdone– especiallyifthey’vecontributedresources
• Thepublicisapartner– meaningfullyinvolvethem
• Demonstratesuccessfulresultstobuildsupportandfundingforfutureprojects