![Page 1: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/1.jpg)
THE KENYA – UGANDA OIL PIPELINE PROJECT
byBen Twodo
MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA
NOT AN OFFICIAL UNCTAD RECORD
![Page 2: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/2.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
STRUCTURE1. Project Inception2. First Feasibility Study3. Complementary Study4. Highlights of the Report5. Ownership and Management6. Implementation7. Conclusion
![Page 3: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/3.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
INCEPTION OF THE PROJECT
A Memorandum of Understanding (MOU) between Kenya and Uganda signed in May 1995
A Joint Coordination Commission (JCC) established
![Page 4: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/4.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
INCEPTION cont’d …
The TOR of the JCC initially to coordinate the feasibility study for the pipeline extension.
TOR expanded in Oct 2000 to include implementation of the entire project.
![Page 5: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/5.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 5
INCEPTION cont’d …
Agreed from start that the project be promoted and developed as a regional project.
![Page 6: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/6.jpg)
THE FIRST FEASIBILITY STUDY
The European Investment Bank (EIB) financed the first feasibility study.
![Page 7: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/7.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 7
FIRST STUDY cont’d …
An international consultancy firm contracted to undertake a feasibility study in 1997.
The consultant conducted the study in 1998 and presented its report in May 1999.
![Page 8: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/8.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 8
FIRST STUDY cont’d …
The study concluded that the project is feasible and viable.
![Page 9: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/9.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 9
THE SECOND/COMPLENTARY
STUDY
In 2001, a complementary study was commissioned to:oupdate the first study and reconfirm the pipeline as the least cost mode
oprepare documentation to invite bids from private sector investors
![Page 10: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/10.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
0
COMPLEMENTARY STUDY cont’d …
Study financed by the two Governments under the auspices of the JCC.
Study carried out by another international firm.
![Page 11: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/11.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
1
COMPLEMENTARY STUDY cont’d …
Report on Stage 1 of the study submitted in Nov 2001.
![Page 12: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/12.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
2
HIGHLIGHTS OF THE REPORT
Market demandoPresent demand is about 580,000 m3 p.a.
oDemand grows at 3.5% – 5% p.a
![Page 13: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/13.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
3
HIGHLIGHTS cont’d …
Pipeline routeoPipeline to be extended from Eldoret in Kenya, through Malaba on the border (110 km), through Jinja (130 km from Malaba) then to Kampala (80 km)
![Page 14: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/14.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
4
HIGHLIGHTS cont’d …
oKisumu – Malaba is second option
oTotal pipeline length approximately 320 km
![Page 15: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/15.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
5
HIGHLIGHTS cont’d …
Pipeline sizeoAn 8 inch diameter pipeline recommended
![Page 16: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/16.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
6
HIGHLIGHTS cont’d …
Flow rate and capacityoPumping flow rate of 168 m3 per hour
oAnnual capacity is 1,200,000 m3
![Page 17: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/17.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
7
HIGHLIGHTS cont’d …
No engineering design at this stage.
![Page 18: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/18.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
8
KAMPALA TERMINAL
A common user terminal to be located in Kampala
Terminal to be located east of the city
![Page 19: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/19.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 1
9
KAMPALA TERMINAL
Ministry prefers location west of the city to lessen truck traffic through city
![Page 20: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/20.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
0
KAMPALA TERMINAL cont’d …
Kampala terminal capacity to be 72,000 m3 comprising:
o7 productso4 interface tanks
![Page 21: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/21.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
1
KAMPALA TERMINAL cont’d …
Tanks Configuration o MPS - 2 tanks - 32,500 m3
o BIK - 2 tanks - 5,654 m3
o JET - 2 tanks - 10,544 m3
o AGO - 2 tanks - 22,570 m3
o Interface - 4 tanks 904 m3
![Page 22: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/22.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
2
CAPITAL COST ESTIMATES
Cost estimates for basic development - $96.9 million
![Page 23: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/23.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
3
CAPITAL COSTS cont’d …
oDesign, engineering, supervision - $7.2 m
oPreliminaries and general costs - $5.4 m
oPipe laying - $42.2 moEldoret terminal - $4.6 m
![Page 24: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/24.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
4
CAPITAL COSTS cont’d …
oSindendet pump station - $3.4 m
o Intermediate pump station - $3.4 m
oKampala terminal cost - $30.7 m
![Page 25: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/25.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
5
CAPITAL COSTS cont’d …Additional $12 million for:
o Improvement of pumping capacity at Burnt Forest in Kenya – $5.1 m
![Page 26: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/26.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
6
CAPITAL COSTS cont’d …oT-off to government’s storage depot in Jinja; additional facilities - $2.1 m
oRe-locating terminal west of Kampala - $4.7 m
![Page 27: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/27.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
7
ECONOMICS
Current truck transportation rates vary $40 - $42 per m3
![Page 28: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/28.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
8
ECONOMICS
Viability of the project tested for various tariffs and investment configurations.
The IRR in all cases showed the project to be viable; 18% - 25%
![Page 29: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/29.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 2
9
GOVERNMENTS POSITION
The complementary study report was accepted by JCC in 2001
The Governments accepted JCC recommendation in 2003.
![Page 30: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/30.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
0
GOVERNMENTS POSITION cont’d …
Extension to be independent of existing Mombasa – Eldoret pipeline (owned and managed by GoK through the Kenya Pipeline Company).
![Page 31: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/31.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
1
GOVERNMENTS POSITION cont’d …
The two pipelines to be unified in future and operated as a single entity; Mombasa – Kampala.
![Page 32: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/32.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
2
OWNERSHIP AND MANAGEMENT
Ownership to be joint public-private partnership
oPrivate investor51%oGovernments 49%
(24.5% each)
![Page 33: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/33.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
3
OWNERSHIP AND MANAGEMENT
Private sector partner to be selected through open competitive bidding process
The project to be implemented on BOOT terms.
![Page 34: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/34.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
4
OWNERSHIP & MANAGEMENT cont’d …
Private sector to manage and operate the pipeline
![Page 35: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/35.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
5
OWNERSHIP/MANAGEMENT cont’d …
Governments’ shares to be offloaded to private investors in future
![Page 36: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/36.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
6
LEGAL FRAMEWORK
A legal framework be developed immediately by the two governments:oBilateral/International agreements defining legal, commercial, financial arrangements.
![Page 37: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/37.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
7
LEGAL FRAMEWORK cont’d …
oHost country laws on taxation, transportation, customs, etc.
oCommercial agreements – government/company or inter company.
![Page 38: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/38.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
8
ENVIRONMENTAL IMPACT ASSESSMENT
Environment impact assessment study be carried out parallel to identification of private sector investoroTOR readyoFinancing available
![Page 39: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/39.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 3
9
PROJECT FINANCING
Project financing to be used based on future stream of revenues.
Oil marketing companies willing to sign agreements with promoters.
![Page 40: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/40.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
0
WAY FORWARD
Prepare documentation to select private partner for the project
The selection will be through competitive process
![Page 41: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/41.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
1
IMPLEMENTATION TIMETABLE
Expression of Interests - - 1½ months
Bidding - 3 monthsNegotiations & contract - 1
monthFormation of JVC - 1 month
![Page 42: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/42.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
2
IMPLEMENTATION TIMETABLE cont’d …
Legal framework - 3 months
EIA - 4 months
These to run concurrent with investor selection
![Page 43: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/43.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
3
IMPLEMENTATION TIMETABLE cont’d …
Procure, Construction and Commissioning 27 – 32 months
![Page 44: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/44.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
4
CONCLUSION
The Kenya – Uganda oil pipeline project is feasible and viable.
Ready market existsAttractive rates of return
assured.
![Page 45: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/45.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
5
CONCLUSION cont’d …
The project classified as high priority in both countries.
![Page 46: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/46.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
6
CONCLUSION cont’d …
The project to be implemented as a regional project in the spirit of East African Community (EAC), the New Partnership for Africa (NEPAD), etc
![Page 47: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/47.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
7
CONCLUSION cont’d …
Many financial institutions have indicated interest to support the projectoWorld Bank Group, EIB, AfDB, PTA Bank, EADB, etc.
oBilateral sources and finance houses, etc.
![Page 48: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/48.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
8
CONCLUSION cont’d …
A number of investors have expressed interest in the project
![Page 49: THE KENYA – UGANDA OIL PIPELINE PROJECT by Ben Twodo MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA NOT AN OFFICIAL UNCTAD RECORD](https://reader036.vdocument.in/reader036/viewer/2022062223/551be457550346be588b5f9d/html5/thumbnails/49.jpg)
Ministry of Energy and Mineral Development, UGANDA.Kenya – Uganda Oil Pipeline Project 4
9
COME, LETS DO BUSINESS TOGETHER
THANK YOU!