the lcgt project...roof and wall. but this is still not perfect. we will have another roof on top of...
TRANSCRIPT
Status of the KAGRA Project
Takaaki Kajita,for the KAGRA collaboration (~230 members)
ICRR, Univ. of TokyoKajita_at_icrr.u-tokyo.ac.jp
GWPAW2015June, 2015, Osaka
Outline
• Introduction: Overview of KAGRA– Key features– Science examples
• Status of the KAGRA construction (iKAGRA)• Plan toward the cryogenic operation (bKAGRA) • Joining the Global GW network• Summary
KAGRA project 2
KAGRA project 3
Introduction: Overview of KAGRA
10 countries, ~230 members
KAGRA collaboration
KAGRA project 4
Key features of KAGRA
The detector will be constructed underground Kamioka. Reduction of seismic noise (to approximately 1/100).
Very high sensitivity.
Cryogenic mirrors will be used to reduce the thermal noise (in the 2nd phase).
We are here today.
KAGRA project 5
KAGRA surface facility
Super-Kamiokande
Present mine entrance
Toyama airport
40min.by car
LocationMozumi
New Atotsu
We are here today.
KAGRA project 6
Sources of Gravitational Waves1. Coalescence of neutron star binaries2. Coalescence of black hole binaries3. Core collapse of massive stars (Supernova)
(good location; Super-Kamiokande at the same site)4. Rotation of pulsars
Merger
Blackholequasi-normal mode
inspiral
msec
KAGRA project 7
Sensitivities GWIC report (2010)
Ad.-LIGO, Ad-Virgo, KAGRA similar design sensitivities
KAGRA
KAGRA project 8
Expected NS-NS Coalescence signal
8
BH Ringdown (2.8MSun)
Expected signal rate : ~10 / year
KAGRA project 9
Supernova
Example collapse and bounce wave form with 2 different EoSDimmelmeier et al. 2008 [PRD 78, 064056]
Various possible gravitational wave emission mechanism:• Core collapse and bounce• Rotational non-axisymmetric instabilities of proto-neutron star• Post-bounce convection• …
Neutrino (Super-K)
msec
KAGRA project 10
Status of the KAGRA construction(iKAGRA)
KAGRA project 11
Time line (Construction and Observation)
The construction/operation plan is in 2 stages: At the end of 2015, non-cryogenic operation (iKAGRA). Starting operation with cryogenic system in JFY 2017 (bKAGRA). (High sensitivity operation in ?)
2010 2011 2012 2013 2014 2015 2016 2017 2018Calendar yearProject startTunnel excavationiKAGRA
bKAGRA
operation
operationAdv. Optics system and tests
Cryogenic system
Today
KAGRA project 12
iKAGRA and bKAGRAiKAGRA ( ~ 2015) bKAGRA
◆Simple Michelson interferometer with:room temperature operation and2W class laser.
However, full end-to-end (relatively short) observation, in order to experience the operation and to understand the potential problems as soon as possible.
◆ Full bKAGRA with;power and signal recycling, cryogenic sapphire mirrors, and ~180W laser.
KAGRA project 13
iKAGRA on-site schedule (2014-2015) (planed in 2014)
Calendar year 2014 2015
Electricity
Tunnelexcavation
Ventilation
Drain
Crane & Hanging anchor
Dust prevention coating
Clean booth
Network and PHS
Arm tubes
Chambers
Mirror suspension
Input optics
Optical baffles etc
Vacuum pumps
Commissioning
iKAGRAoperation
Physicist-like works
( )
( )
( )
( )
Tunnel excavation
KAGRA project 14
End of April, 2012
Mid June, 2012
New Atotsu entrance
KAGRA project 15
Excavation completed at the end of March 2014
Y-arm
X-arm
Excavation completion ceremony on July 4, 2014.
KAGRA project 16
Status Connection and the
leak tests of 3km X 3km beam tubes have been finished.
Y arm tunnel and vacuum tubes
X arm tunnel and vacuum tubes
KAGRA project 17
Status
All the vacuum tanks located (slightly old photo).
Clean booth construction (planed for JFY2014) finished.
Laser
Y-arm
X-arm
entrance
KAGRA project 18
Underground water and KAGRA tunnel
EXCBS
EYC
X-arm
Y-arm
ITMXITMY
O
EXAhorizontal plane at Y end
horizontal plane at center room
horizontal plane at X end
Y-arm
optical plane of interferometer
X-arm
O (BS)
to lower levelto outsideWater
WaterCenter room
KAGRA project 19
Status (some delay…) • The underground water has
been (much) more than expected, in particular during spring (due to melting snow).
• It has been impossible to install the in-vacuum devises.
• Additional civil-engineering work to minimize the effect of the water during this winter-spring.
• Rescheduling of the installation and commissioning works…
Water proof of the experimental rooms
KAGRA project 20
Walls and the floor of the Center and X and Y end rooms have been coated by plastic. But that was not good enough.
Therefore, plastic sheets were used to cover the roof and wall.
But this is still not perfect. We will have another roof on top of the clean booths soon.
Installation of in-vacuum equipment resumed
21KAGRA project 21
Laser
Y-arm
X-arm
Vacuum tank for Input Mode Cleaner (June 2015)
Testing seismic attenuation system at TAMA
22KAGRA project 22
Seismic Attenuation System(for BS ad SR systems)
Installation of the SAS system into the TAMA vacuum tank (May 2015).
Dummy mirror (Al) in the TAMA tank suspended by the SAS.
KAGRA project 23
iKAGRA Laser system Preparation of the iKAGRA laser (since Nov.
2014). (ISO class 1 achieved and has been kept).
iKAGRA will use low power laser (2W). (180W class laser in bKAGRA) Laser
Y-arm
X-arm
KAGRA project 24
iKAGRA digital system
Computer room at front area in the mine: end of December of 2014
Movement of racks, computers, DC powers: Jan 2015
Network connection: in Feb. Construction of electric panel:
Feb-March
Network for controls and DAQGPS antenna
MozumiEntrance
Entrance to the KAGRA facility
Timing: Synchronization for all RT PC and ADC/DAC
GW buildings at Kamioka
RFM RT control signal: very low latencyDAQ GW data: huge amount, low latency
TCP/IP: EPICS, NFS, network boot
Remote control
Data storage
KAGRA project 25
ICRR @Kashiwa (3PB/5years)
Main Data storage
Low latency analysis Osaka city U., Osaka U. (150TiB/5 years)
Office building
KAGRA project 26
KAGRA office (from Hida-city, since 2012, 140m2)
New office building to be built in 2013. (340m2).
Control room (@office building)
KAGRA project 27
KAGRA project 28
Updated iKAGRA on-site schedule (2015)
Simplified version of the updated schedule by Uchiyama-san will be shown here.
Month in 2015 Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec.
Preparation for site worksInput optics commissioningRemaining clean boothsMode cleaner installation and lockVibration isolation installation and commissioningAuxiliary optics (optical lever etc)Commissioning…iKAGRA run
Rescheduled taking the water problem into account…
Still hoping to have the iKAGRA operation in Dec. 2015…
KAGRA project 29
Plan toward the cryogenic operation(bKAGRA)
Cryogenic mirrors and cryostat
KAGRA project 30
4 cryogenic mirrors
Cryo shield
Cryo-cooler
Cryo-payload
Cryo-mirrorCryo-shield tubeRock
2nd floor
~14m
Vibration isolation system (@room temp.)
1st floor
KAGRA project 31
Status of construction: Cryogenic systemFeb. 2013 Cryostat testing at Toshiba Co.
Aug. 2014
2015
All cryostats and the relevant components installed in the KAGRA tunnel.
Status of preparation: Sapphire mirror • 4 Sapphire crystals (C-axis,
22cmφ, 15cm t) have been delivered. (4 more to come).
KAGRA project 32
Surface roughness (test polishing with 200mmφ)
0.24nm r.m.s. over 140mmφ0.48nm r.m.s. over 180mmφ (OK!)
E.Hirose et al., PRD 89, 062003 (2014)
And much more going on…
KAGRA project 33
210 W
Data analysis activities
KAGRA project 34
Compact Binary Coalescence (CBC)• Pipeline development for frequency domain matched filtering (MF)• Low latency analysis (time domain MF) (Osaka CU) : components
preparation.• Bayesian parameter estimation : Basic study with KOREAN group• Alert sending system to EM partners (multi-messenger astronomy)
Burst• Development of single detector search pipeline.• Data Retrieving, Data Conditioning, Event Selection : implemented.• Parameter Estimation : In progress.
Continuous Wave(CW)• Developing codes using the resampling technique.
KAGALI DevelopmentKAGRA data analysis group is developing KAGRA’s data analysis library called KAGra Algorithmic LIbrary or “KAGALI”.
KAGRA project 35
Joining the global GW network
Ad. Virgo
KAGRAAd. LIGO GEO-HF
◆The scientific output will be maximized by the global network.◆KAGRA has to learn various experiences / technologies from the existing interferometers.◆KAGRA will join the worldwide network of gravitational wave detection / astronomy. MOU between LSC/Virgo/KAGRA.
LIGO-India
KAGRA project 36
Importance of Global GW Network: Angular res.
Determination of source sky position: 95%CL, supernova, S/N =10 Wen and Chen, arXiv: 1003:2504
LIGO (L+H) + Virgo
LIGO (L+H) + Virgo+KAGRA
LIGO(L+H)+Virgo
Of course, the addition of LIGO-India will further improve the performance.
KAGRA project 37
Follow-ups/counterparts partners of KAGRA
Fast processing of KAGRA data
Mutually follow-ups with EM and neutrinos
Further scienceon GW data analysis
Grants-in-Aid for Scientific Research “New developments in astrophysics through multi-messenger observations of gravitational wave sources”, PI: T. Nakamura
GW data analysis
Xraymonitor
Optical, RadioNeutrino
theory
Multi-messenger astroUnderstanding GW sources
KAGRA project 38
Summary• KAGRA is a unique GW interferometer with the
underground site and the cryogenic technology.• The underground water during spring is a problem.
Due to this problem, the KAGRA detector construction has been delayed for several months. But, we would like to keep the overall schedule as we initially planed:– Initial operation (iKAGRA) in late 2015. We have to work
really hard!– We plan to start the full cryogenic operation within JFY 2017,
and to play an important role as a member of the global GW network.
• KAGRA would like to contribute to the global network of gravitational wave detection/astronomy.