the new co-simulation tool for traction power supply
TRANSCRIPT
Stephan_RTS2010_OpenPowerNet.ppt (Figure 1)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Prof. Dr.-Ing. Arnd Stephan
The new Co-simulation Tool for Traction Power Supply
AC Railway DC Railway / Trolleybus
Stephan_RTS2010_OpenPowerNet.ppt (Figure 2)
– Co-Simulation Tool for Traction Power Supply RTS 2010
• The voltage situation as well as the network structure influence the electrical load distribution (… current levels and current directions).
• There are energy consumers with time-dependent and position-dependent power demands (… picking up and recovering energy).
⇒ Thus the power supply system influences the energy consumption.
• Energy consumption analysis and prognosis• Design and rating verification of the electrical installations• EMC studies
Simulation of these dynamic processes enables:
Simulation of Traction Power Supply – what for?
Stephan_RTS2010_OpenPowerNet.ppt (Figure 3)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Power Supply Network Structure (DC 0.6 … 3.0 kV)
Power Grid Connection3 AC 10 / 20 / 30 kV
OCS
Rails
train NOT in section train in section
Substation
GO1
GR1
GO3
GR2
GO4
GR3
GO5
GR4
sw
sw
SS1
sw
sw
SS2
sw
sw
SS3
sw
sw
SS4
Earth
G’RE G’RE G’RE G’RE G’RE G’RE G’RE
sw sw sw sw
GO2
single-end double-end double-end
0.6 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 4)
– Co-Simulation Tool for Traction Power Supply RTS 2010
• currents and power losses increase with decreasing voltage,
• under low voltage conditions current or power limitations of the train propulsion control are activated ⇒ … impact on driving dynamics,
• the network voltage influences the braking energy recovering decisively (“energy absorption capability”).
The network voltage situation affects the electrical load flows and may have retroaction to the propulsion characteristics of the trains:
Special Requirements
Stephan_RTS2010_OpenPowerNet.ppt (Figure 5)
– Co-Simulation Tool for Traction Power Supply RTS 2010
• each train’s driving state and its required traction power,
• the train’s positions within the network,
• the layout and the capability of the power supply system.
Energy consumption simulation for electrical railway systems requires detailed information concerning …
• either concerning the complexity of the railway operation simulation,
• or regarding the modelling depth of the propulsion technology and the electrical network.
In the past a number of compromises were made
Initial Situation
All these information are needed exactly at the same time.
Stephan_RTS2010_OpenPowerNet.ppt (Figure 6)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Separation of Simulation Tasks
• Line routing and alignment• Track layout• Signalling system• Train data• Timetable• Connecting conditions• Operating rules
• Train propulsion data• Power grid parameter• Substation arrangement• Feeder lines and cables• Catenary system• Earthing system• Switch status
Railway Operation Load Flow and Energy
Plug-in
Stephan_RTS2010_OpenPowerNet.ppt (Figure 7)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Input Data Output DataSimulation
Rolling Stock
Infrastructure
Timetable
Interactivity
Animation
Diagrams
Timetable Graphs
Track Occupations
Statistics
Stephan_RTS2010_OpenPowerNet.ppt (Figure 8)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Geometrical Track Model
Stephan_RTS2010_OpenPowerNet.ppt (Figure 9)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Source: IFB
Stephan_RTS2010_OpenPowerNet.ppt (Figure 10)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Propulsion Technology
Railway Operation Simulation
ATMAdvanced
Train Module
“Co-Simulation”
Power Supply System
PSCPower Supply
CalculationInteraction
Stephan_RTS2010_OpenPowerNet.ppt (Figure 11)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Sequence per Time Step
Line Voltage, Requested Effort
Train Current
Train Position,Requested
EffortAchieved
Effort
OpenTrack
PSC ATM
Stephan_RTS2010_OpenPowerNet.ppt (Figure 12)
– Co-Simulation Tool for Traction Power Supply RTS 2010
AP Server
PSC ATM
network data base
propulsion data base
train_ID, engine_ID,line_ID, track_ID,train location, time,requested force,speed
1
line_ID, track_ID,train location, time, train current
2
train voltage, nominal voltage,nominal frequency
3train_ID,engine_ID, requested force,speed,
train voltage,nominal voltage,nominal frequency
4
achieved force,train current
5
achieved force
6SOAP interface
Stephan_RTS2010_OpenPowerNet.ppt (Figure 13)
– Co-Simulation Tool for Traction Power Supply RTS 2010
a) constant efficiency factors for propulsion equipment
b) driving state related efficiency factors
c) load depending efficiency factors of components
d) detailed engine models of components
+ auxiliaries and eddy current break power
+ additionally: limiting values of propulsion control (e.g. voltage related current limitation)
Modelling levels available for propulsion simulation
Stephan_RTS2010_OpenPowerNet.ppt (Figure 14)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Pel
Pmech
Propulsion Structure
Stephan_RTS2010_OpenPowerNet.ppt (Figure 15)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Wirkungsgradverläufe ICE 3 für maximale ZugkraftHerstellerangabe für Betrieb bei 15 kV 16,7 Hz
0,5
0,6
0,7
0,8
0,9
1
0 20 40 60 80 100 120 140 160 180 200
Motorfrequenz
Wirk
ungs
grad
Transformator
4-QS
Pulswechselrichter
Asynchron-Fahrmotor
Radsatzgetriebe
Gesamt
Hz
Efficiency Characteristics of ICE3 train1 AC 15 kV 16,7 Hz
Stephan_RTS2010_OpenPowerNet.ppt (Figure 16)
– Co-Simulation Tool for Traction Power Supply RTS 2010
1σL 2'σL1R sR 2'
HL1u
2'i1i
1 2'+i iΨH
1Ψ 2'Ψ
= +e le k t m e c h L ä u fe r v e r lu s teM M M23
2 22 ' '2 2
⋅= =
π πR o to r v e r lu s te
L ä u fe r v e r lu s tei RPM
n n
Propulsion Component Modelling (example for traction motor)
Stephan_RTS2010_OpenPowerNet.ppt (Figure 17)
– Co-Simulation Tool for Traction Power Supply RTS 2010
23000
23500
24000
24500
25000
25500
26000
26500
2700000
:00
00:3
0
01:0
0
01:3
0
02:0
0
02:3
0
03:0
0
03:3
0
04:0
0
04:3
0
05:0
0
05:3
0
06:0
0
06:3
0
07:0
0
07:3
0
08:0
0
08:3
0
09:0
0
Zeit in Minuten
Span
nung
in V
olt
-500,00
-400,00
-300,00
-200,00
-100,00
0,00
100,00
200,00
300,00
400,00
500,00
Spannung in Volt Strom in Ampere
Propulsion Model VerificationTrain Current and Pantograph Voltage
time h:min
volta
ge
curre
nt
AV
Train Current and Pantograph Voltage
Stephan_RTS2010_OpenPowerNet.ppt (Figure 18)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Fahrschaubild und Leistungsverlauf ICE1Betriebsfahrt Hannover - Göttingen, Meßwerte am führenden Triebkopf,
Simulation IFB: Standardparameter und Wirkungsgradmodell ICE1/2
0
20
40
60
80
100
120
140
160
180
200
220
240
260
0 10 20 30 40 50 60 70 80 90 100
Weg
v
-4
-2
0
2
4
6
8
PStr
v Meßfahrtv SimulationP MeßfahrtP Simulation
km/h
MW
km
Fehlertoleranzen: Fahrschaubild < 1 %
Energie ab Stromabnehmer < 2 %
Quelle: IFB
Train Speed and Power CharacteristicsMeasurement and Simulation Results
ICE1 Hannover – Göttingen
Stephan_RTS2010_OpenPowerNet.ppt (Figure 19)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Requirements to the Electrical Network Model
- Simulation of all common AC- and DC-railway power supply systems
- Representation of the entire electrical network structure
- Unrestricted choice of conductor configuration along the line
- Precise consideration of electromagnetic coupling effects of overhead line conductors for a.c.-systems
- Change of switching status within the power supply network
- Retroaction to the railway operation simulation (OpenTrack)
- Iterative communication with the propulsion simulation (ATM)
- Configurable data output
- Interfaces for post-processing
Stephan_RTS2010_OpenPowerNet.ppt (Figure 20)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Power Supply Network Structure (DC 0.6 … 3.0 kV)
Power Grid Connection3 AC 10 / 20 / 30 kV
OCS
Rails
train NOT in section train in section
Substation
GO1
GR1
GO3
GR2
GO4
GR3
GO5
GR4
sw
sw
SS1
sw
sw
SS2
sw
sw
SS3
sw
sw
SS4
Earth
G’RE G’RE G’RE G’RE G’RE G’RE G’RE
sw sw sw sw
GO2
single-end double-end double-end
0.6 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 21)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Power Grid Connection1 AC 110 kV 16,7 Hz
Power Supply Network Structure (1 AC 15 kV 16,7 Hz)
OCS
Rails
Substation
YO1
YR1
YO2
YR2
YO3
YR3
sw
sw
SS1
sw
sw
SS2
Earth
Y’RE Y’RE Y’RE Y’RE Y’RE Y’RE Y’RE
sw swsw
CS
sw
15 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 22)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Power Supply Network Structure (2 AC 25 kV ~ 50 / 60 Hz)
OCS
Rails
Negative Feeder
train NOT in section train in section
AutotransformerSubstation
YO1
YR1
YN1
Autotransformer Autotransformer
YO2
YR2
YN2
YO3
YR3
YN3
YO4
YR4
sw
sw
sw
SS
sw
sw
sw
AT1
sw
sw
sw
AT2
sw
sw
sw
AT3
Power Grid Connection3 AC 110 / 220 kV
Earth
Y’RE Y’RE Y’RE Y’RE Y’RE Y’RE Y’RE
25 kV
-25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 23)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Modelling of the Railway Power Supply System
- Electrical network structure (feeding sections, feeding points, switch state) in congruence to the track topology
- Electrical characteristics of the feeding power grid
- Electrical characteristics of the substations
- Electrical characteristics of the conductors (cables, Catenary wires, tracks, rails)
- Electrical characteristics rail-to-earth
- Modelling of additional power consumers (e.g. switch heatings)
- Loading capacity (conductors, converters, transformers)
- Protection settings
Stephan_RTS2010_OpenPowerNet.ppt (Figure 24)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Substation / AT Structure (2 AC 25 kV ~ 50/60 Hz)
Stephan_RTS2010_OpenPowerNet.ppt (Figure 25)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Trackside Arrangement of Conductors
Source: DB KoRiL 997
Stephan_RTS2010_OpenPowerNet.ppt (Figure 26)
– Co-Simulation Tool for Traction Power Supply RTS 2010
„Slice“
Catenary Arrangement and Conductor Model
Stephan_RTS2010_OpenPowerNet.ppt (Figure 27)
– Co-Simulation Tool for Traction Power Supply RTS 2010
y
x
(0; 0)
(x1; y1)
material, diameter
electro-magneticcoupling effects
Slice n
Catenary Arrangement and Conductor Model
Stephan_RTS2010_OpenPowerNet.ppt (Figure 28)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Sequence of Slices
Stephan_RTS2010_OpenPowerNet.ppt (Figure 29)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Electrical network calculation using the advanced method of nodes
nodes
node voltages inductive voltages currents
Voltage drops caused by self- and mutual induction
Stephan_RTS2010_OpenPowerNet.ppt (Figure 30)
– Co-Simulation Tool for Traction Power Supply RTS 2010
High Speed Railway 350 kph
966 km Double Track 2AC 25 kV 50 Hz
Stephan_RTS2010_OpenPowerNet.ppt (Figure 31)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Example: High Speed Railway 966 km, Track Alignment (Detail)
Stephan_RTS2010_OpenPowerNet.ppt (Figure 32)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Example: High Speed Railway 966 km, OCS Infeed (Detail)
Stephan_RTS2010_OpenPowerNet.ppt (Figure 33)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 34)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Detail
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 35)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 36)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Detail
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 37)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 38)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Minimum Pantograph Voltage, Wuhan-GuangzhouLine Wuh-Gua_1, Track Up, km 1265.75-1319.69
New
Xia
nnin
g [1
274.
588]
New
Chi
bi [1
317.
74]
TSS_
1291
_Qnk
[129
1.26
7]TS
S_12
91_Q
nk [1
291.
687]
SP_1
265_
Qnk
[126
5.96
]
ATS
_127
9_Q
nk [1
279.
22]
ATS
_130
4_Q
nk [1
304.
81]
SP_1
319_
Qnk
[131
9.48
]
17000
19000
21000
23000
25000
27000
29000
31000
1265 1275 1285 1295 1305 1315
Position [km]
Volta
ge [V
]
Isolator AT Infeed Tolerance U (EN 50163) U_nom min_voltage_panto
Simulation Results: High Speed Railway 2AC 25 kV
Stephan_RTS2010_OpenPowerNet.ppt (Figure 39)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Busbar Power, Wuhan-GuangzhouSubstation TSS_1444_Hua, Transformer 1444_Hua_TT-02
-20000
-10000
0
10000
20000
30000
40000
50000
60000
70000
80000
12:0
0:01
12:0
5:01
12:1
0:01
12:1
5:01
12:2
0:01
12:2
5:01
12:3
0:01
12:3
5:01
12:4
0:01
12:4
5:01
12:5
0:01
12:5
5:01
Time
App
aren
t Pow
er [k
VA
]A
ctiv
e P
ower
[kW
]
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
Rea
ctiv
e P
ower
[kva
r]
|S|‐1444_Hua_TT‐02 P‐1444_Hua_TT‐02 Q‐1444_Hua_TT‐02
Stephan_RTS2010_OpenPowerNet.ppt (Figure 40)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
57,0
49,5
62,462,1
78,5
74,077,176,8
73,973,2 72,271,8 71,671,4
81,0
71,2
85,2
79,681,881,8
91,590,992,992,9 92,592,1
107,8107,8
78,078,0
91,390,5
96,596,5
91,091,087,587,5
44,0
37,7
0,0
20,0
40,0
60,0
80,0
100,0
120,0
Elec
tric
Ene
rgy
[MW
h]
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20Substation No.
TSS Energy Delivery (1 h)WGPDL - Operation Program 2028
Energy totalEnergy by TSS
Stephan_RTS2010_OpenPowerNet.ppt (Figure 41)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
15,1%
0,5%
6,0%
0,3%0,9%
0,5% 0,3%
13,7%
7,0%
0,0%
0,6%
0,0%0,5%
0,0% 0,0%
0,9%
0,0% 0,0% 0,0%
16,6%
0,0%
2,0%
4,0%
6,0%
8,0%
10,0%
12,0%
14,0%
16,0%
18,0%
Ener
gy R
ecov
erin
g
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20Substation No.
Recovery Rates (peak operation)WGPDL - Operation Program 2028
Stephan_RTS2010_OpenPowerNet.ppt (Figure 42)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Vehicle Type EngineID Transport WorkTotal Energy
Specific Energy
Consumed Energy
Recovered Energy
Degree Of Regeneration
Available Braking Energy
Used Braking Energy
[tkm] [kWh] [Wh/tkm] [kWh] [kWh] [%] [kWh] [kWh]
CRH3 G469‐0 26001,806 1754,227 67,466 1755,741 1,513 0,1 1,942 1,596CRH3 G469‐1 26001,806 1754,227 67,466 1755,741 1,513 0,1 1,942 1,596CRH3 G371‐0 25973,739 1759,052 67,724 1759,052 0,000 0,0 0,000 0,000CRH3 G371‐1 25973,739 1759,052 67,724 1759,052 0,000 0,0 0,000 0,000CRH3 G299‐0 26002,845 1754,247 67,464 1755,755 1,508 0,1 1,936 1,591CRH3 G299‐1 26002,845 1754,247 67,464 1755,755 1,508 0,1 1,936 1,591CRH3 G355‐0 25996,262 1756,881 67,582 1758,806 1,926 0,1 3,791 2,009CRH3 G355‐1 25996,262 1756,881 67,582 1758,806 1,926 0,1 3,791 2,009CRH3 G509‐0 8741,502 588,711 67,347 588,711 0,000 0,0 0,000 0,000CRH3 G509‐1 8741,502 588,711 67,347 588,711 0,000 0,0 0,000 0,000CRH3 G600‐0 7635,276 533,004 69,808 533,004 0,000 0,0 0,000 0,000CRH3 G600‐1 7635,276 533,004 69,808 533,004 0,000 0,0 0,000 0,000CRH3 G520‐0 15460,187 1068,943 69,142 1068,943 0,000 0,0 0,000 0,000CRH3 G520‐1 15460,187 1068,943 69,142 1068,943 0,000 0,0 0,000 0,000
Vehicle Energy Consumption And Recovery Overview, Wuhan - Guangzhou
Ygm 1862-1918
Stephan_RTS2010_OpenPowerNet.ppt (Figure 43)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Energy output to catenary at substation [kWh] 72300,187 Losses in contact wire [kWh] 525,588Energy input from catenary at substation [kWh] 1154,082 Losses in messenger wire [kWh] 565,248Total energy at substation [kWh] 71146,105 Losses in negative feeder [kWh] 481,426
Losses in return conductor [kWh] 138,879Vehicles energy consumption [kWh] 78540,848 Losses in left rail [kWh] 13,174Vehicles braking energy used for auxiliaries [kWh] 639,139 Losses in right rail [kWh] 13,196Vehicles braking energy recovered by catenary [kWh] 9230,867 Losses in LEBC [kWh] 31,117Total used vehicles braking energy [kWh] 9870,007 Total losses in conductors [kWh] 1768,629Total vehicles energy [kWh] 69309,980 Losses in connectors [kWh] 1,495
Losses in autotransformers [kWh] 21,896Total energy consumption [kWh] 81016,112 Total losses in catenary system [kWh] 1792,020Energy consumption from national power grid [kWh] 71233,480
Losses in feeders [kWh] 44,072Average efficiency of traction power supply 97,6%
Losses in traction transformers [kWh] 87,375
Energy Consumption And Losses Overview, Wuhan - Guangzhou
Cha 1532-1600
Stephan_RTS2010_OpenPowerNet.ppt (Figure 44)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
44
94
67
88
70
95
69
93
66
93 94
69
93
82
103
115
93 94
89
83
93 93 93 9492 92
95 9490
92
70
92 91
70
91
69
92
6973
00
20
40
60
80
100
120
App
aren
t Pow
er [M
VA]
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20Substation No.
Maximum Substation PowerWGPDL - Operation Program 2028
WU dir.GUA dir.
Stephan_RTS2010_OpenPowerNet.ppt (Figure 45)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
0
200
400
600
800
1000
1200
Max
. Cur
rent
[A]
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20Section No.
Maximum Return Cable CurrentWGPDL - Operation Program 2028
SP WU dir.ATS WU dir.ATS GUA dir.SP GUA dir.
Stephan_RTS2010_OpenPowerNet.ppt (Figure 46)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Short Circuit Current, Wuhan-GuangzhouLine Wuh-Gua_2, Track Up, km 1961.2-2015.12
New
Sha
ogua
n [1
987.
638]
TSS_
1986
_Sha
[198
6.37
]TS
S_19
86_S
ha [1
986.
79]
SP_1
961_
Sha
[196
1.41
]
ATS
_197
4_Sh
a [1
974.
539]
ATS
_199
7_Sh
a [1
997.
4]
SP_2
015_
Sha
[201
4.91
]
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
1961 1971 1981 1991 2001 2011
Short Circuit Position [km]
Cur
rent
[A]
Isolator AT Infeed short_circuit_current
Stephan_RTS2010_OpenPowerNet.ppt (Figure 47)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
Maximum Rail-Earth Potential, Wuhan-GuangzhouLine Wuh-Gua_2, Track Up, km 1961.2-2015.12
New
Sha
ogua
n [1
987.
638]
TSS_
1986
_Sha
[198
6.37
]TS
S_19
86_S
ha [1
986.
79]
SP_1
961_
Sha
[196
1.41
]
ATS
_197
4_Sh
a [1
974.
539]
ATS
_199
7_Sh
a [1
997.
4]
SP_2
015_
Sha
[201
4.91
]
0
20
40
60
80
100
120
140
160
180
1961 1971 1981 1991 2001 2011
Position [km]
Vol
tage
[V]
Isolator AT Infeed URE_max LR_U_LEBC_Up LR_U_LEBC_Up‐2 LR_U_LEBC_Up‐3 RR_U_LEBC_Up RR_U_LEBC_Up‐2 RR_U_LEBC_Up‐3
78 V78 V
Stephan_RTS2010_OpenPowerNet.ppt (Figure 48)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
ATS
km 1997,4
TSS SHA
km 1986,8
SP
km 2015,1
1987,000EMC 1 / EMC 2
1997,000EMC 3
1998,000EMC 4
10,9 MW
10,9 MWOCS
Rails
NF
RC
LEBC
880 A 880 A2x CRH 3
1988,000 2014,300
2x CRH 3
512 A
303 A
24 A
363 A
136 A
74 A
148 A
163 A
60 A
103A
7 A
13 A
387 A1150 A 280 A 493 A
603 A 603 A 387 A 387 A
Stephan_RTS2010_OpenPowerNet.ppt (Figure 49)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Simulation Results: High Speed Railway 2AC 25 kV
tunnel subgrade
Stephan_RTS2010_OpenPowerNet.ppt (Figure 50)
– Co-Simulation Tool for Traction Power Supply RTS 2010
City Light Rail Network300 km TRAM
220 km TrolleybusDC 600 V
Stephan_RTS2010_OpenPowerNet.ppt (Figure 51)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Graphical time table
Line A
Stephan_RTS2010_OpenPowerNet.ppt (Figure 52)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Stephan_RTS2010_OpenPowerNet.ppt (Figure 53)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Minimum voltage: catenary and pantographNormal operation
STR
Vt [5
.804
]
HEG
A [5
.398
]
IHA
G [5
.017
]
FRIE
[4.6
81]
FRIB
[4.3
04]
HO
EF [3
.748
]
GO
LPt [
3.46
9]
ZWIN
[3.1
75]
KA
LKt [
2.76
2]
KER
N [2
.493
]
HEL
Vt [2
.311
]
MIL
A [1
.913
]
RO
EN [1
.581
]
LIM
Mt [
1.28
8]
Heu
ri-Fr
iese
n
Heu
ri-H
öfliw
e
Bad
en-K
alkb
reB
aden
-Lan
gstr
Alb
is-S
chw
eig
Lette
-Lim
mat
p
0
100
200
300
400
500
600
700
800
900
1 1,5 2 2,5 3 3,5 4 4,5 5 5,5 6
Weg [km]
Span
nung
[V]
Trenner Toleranz U (EN 50163) U_nenn U_min_abs U_min_Tfz
Stephan_RTS2010_OpenPowerNet.ppt (Figure 54)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Rail-to-earth potential Normal operation
FRA
N [6
.915
]
WIN
Z [6
.494
]
WA
RT
[6.0
51]
ZWIE
[5.6
91]
MEI
E [5
.374
]
SCH
T [4
.998
]
ATR
O [4
.602
]
EGU
T [4
.234
]
WA
IF [3
.754
]
WIP
K [3
.297
]
EWYS
[3.0
63]
DA
MM
[2.6
89]
QU
EL [2
.416
]
LIM
M [2
.092
]LI
MM
p [2
.003
]
MU
FG [1
.732
]
SIH
L [1
.391
]
Fran
k-ä.
Lim
ma
Tobe
l-m_L
imm
a
Lette
-i.Li
mm
a
Lette
-Wip
king
Lette
-o.L
imm
a
0
10
20
30
40
50
60
70
80
1 2 3 4 5 6 7
Weg [km]
Span
nung
[V]
Stephan_RTS2010_OpenPowerNet.ppt (Figure 55)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Converter current and bus-bar-voltage Depot gateway 4:50 - 7:05 h
400
450
500
550
600
650
700
750
0 450 900 1350 1800 2250 2700 3150 3600 4050 4500 4950 5400 5850 6300 6750 7200 7650 8100
Zeit [s]
Span
nung
[V]
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Stro
m [A
]
U-Sammelschiene I-Sammelschiene
Stephan_RTS2010_OpenPowerNet.ppt (Figure 56)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Load and loading capacity Substation DC ConverterNormal operation, blackout in neighbouring subst.
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
1 10 100 1000 10000
Zeit [s]
Effe
ktiv
stro
m [A
]
SammelschieneSK i.LimmatstSK i.HardturmSK RosengarteSK HardbrückeSK ZWestRK HardturmstRK RosengarteBK V, 2381 ABK VI, 2381 A
Stephan_RTS2010_OpenPowerNet.ppt (Figure 57)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Load values Substation Feeders, Normal operation without blackouts
Station Sektor Imax Ieff Pmax Eab Eauf Everl IEinst IKmin IKmin/IEinst Imax/IEinst
[A] [A] [kW] [kWh] [kWh] [kWh] [kA] [kA]1 s 7200 s soll > 110% soll < 90%
2 h
SK -o.Rämistraße 1915 588 1221 520 -10 4 3,5 14,0 400% 54,7%SK -Seilergraben 1686 404 1072 264 0 2 3,0 11,7 390% 56,2%SK -Hottingerstraße 1961 475 1252 417 0 3 3,0 10,4 347% 65,4%SK -Klosbachstraße 1665 332 1048 257 0 4 3,5 10,4 297% 47,6%SK -Kreuzbühlstraße 3710 1018 2312 1000 -33 36 4,2 12,7 302% 88,3%SK -Heimplatz 1128 310 720 290 0 1 3,0 34,0 1133% 37,6%SK -u.Rämistraße 40 172 50 111 36 0 0 3,0 23,0 767% 5,7%SK -u.Rämistraße 129 1145 316 738 220 0 1 3,0 38,2%SK -Bellevueplatz 2824 1075 1770 1226 -6 18 3,5 16,6 474% 80,7%SK -Zeltweg TB 912 279 582 153 -28 1 2,5 2,7 108% 36,5%RK -Heimplatz 2 Kabel -1242 513 -749 0 -627 3RK -Kreuzbühlstraße -2164 678 -1324 2 -789 8RK -o.Rämistraße -649 238 -393 0 -281 2RK -Heimplatz -3425 1375 -2065 0 -1683 8RK -Bellevueplatz -1742 657 -1050 0 -804 7RK -Zeltweg TB -912 279 -582 28 -153 1gesamt 8773 3527 5289 4305 0 97
SK: SpeisekabelRK: Rückleiterkabel
Prom
enad
e
SK: Feeder cableRK: Return current cable
Stephan_RTS2010_OpenPowerNet.ppt (Figure 58)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Load and loading capacity Catenary wire at feeding pointNormal operation, blackout in neighbouring subst.
0
200
400
600
800
1000
1200
1400
1 10 100 1000 10000
Zeit
Stro
mst
ärke
Belastbarkeit Ri107 Abnutzung 0 %
Belastbarkeit Ri107 Abnutzung 20 %
Ieff je VL Abnutzung 0 %
Ieff je FD Abnutzung 20 %
s
A
Stephan_RTS2010_OpenPowerNet.ppt (Figure 59)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Energy balance
Case 1 Case 2 Case 3 Case 4
Recovered energy
Delivered energy of all substations
Stephan_RTS2010_OpenPowerNet.ppt (Figure 60)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Power losses balance
Case 1 Case 2 Case 3 Case 4
Stephan_RTS2010_OpenPowerNet.ppt (Figure 61)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Recovering balance
Case 1 Case 2 Case 3 Case 4
Stephan_RTS2010_OpenPowerNet.ppt (Figure 62)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Conclusions
- OpenPowerNet is able to simulate all common a.c. and d.c. railway power supply systems.
- OpenPowerNet works as a co-simulation with the commercial OpenTrack railway operation simulator.
- The Co-simulation principle is profitably for modelling, data handling and independent software further development.
- The accuracy of the electrical network simulation was verified by field measurements.
- Simulation service can be provided including or excluding the operation modelling (… already existing models can be used easily).
- OpenPowerNet was officially put into the market in 2009.
Stephan_RTS2010_OpenPowerNet.ppt (Figure 63)
– Co-Simulation Tool for Traction Power Supply RTS 2010
Eine Expertenrunde für das Gesamtsystem Bahn
The Expert Team for the Complete Railway System
IFB Dresden Branch, Wiener Str. 114-116, 01219 Dresden, GermanyPhone: +49 351 87759-0, E-Mail: [email protected], Web: www.bahntechnik.de