the nirspec critical design review oct 8th 2008 - dec 11th 2008 t. beck (& m. stiavelli)
TRANSCRIPT
The NIRSpec CDR
• Quick NIRSpec instrument overview
• Brief Overview of ESA’s CDR process and goals
• NIRSpec CDR Results
• Next Steps & Schedules
• Some Operational “Issues” of interest
NIRSpec Instrument Overview
JWST Focal Plane, NIRSpec tilted by 41.5o
“The most complicated instrument ever to fly in space”
• Multi-Object Spectrograph Mode (MOS) with an MSA
• Integral Field Unit (IFU)
• 4 Fixed Slits + 1 Broad Aperture
R~100, 1000 and 3000 spectroscopy over 3 Bands:I = 0.7 - 1.8mmII = 1.7 - 3.0mmIII = 2.9 - 5.0mm
NIRSpec Instrument Overview
Reflective Surfaces -
FOR Filter RMA (MSA/IFU/FS) COLL Grating CAM Detector(FWA) (GWA)
CAA
NIRSpec Instrument Overview MSA Focal Plane
• 4 MSA Quadrants
• IFU Entrance Aperture
• Fixed Slits
• New, 1.”6x1.”6 sq aperture
• (IFU “Virtual Slit” Positions)
ESA’s CDR Goals• Verify that the instrument system performance will meet both the scientific
and functional requirements
• Verify that the instrument detailed design is robust, shows adequate margins, and is compliant with product assurance reqs
• External and internal interfaces are defined/documented in the relevant ICDs
• Instrument verification/test plans are realistic and adequate
• The instrument level qualification plan is complete, satisfactory and complies with the subsystem qualification plans.
• The instrument schedule is realistic with adequate margin
• The identified risks are thoroughly assessed with clearly defined mitigation plans
• PA practices are fully implemented
• Ops concept is defined and is consistent with Flight SW architecture
• Commanding and control of the instrument is properly defined in FSW
• Critical technologies have been identified and performance demonstrated.
ESA’s CDR Process• CDR Board + 5 “Panels”
• Document Delivery to Panel and Board members (late September 2008)
• CDR “Kickoff” Meeting = 1 day of instrument presentations, 1 day of face-to-face meeting with the panels (Oct. 8-9, 2008)
• Panel members are tasked with identifying “Review Item Discrepancies” (RIDs) = discrepancies/inconsistencies/errors in documentation, design or instrument performance vs. requirements
• One month of document reading with weekly telecons between panel members - RIDs continuously input into online tracking system.
• Colocation Meeting - All RIDs from all panels discussed among the large group and actions determined
• Board Meeting - Final presentations on findings, issues from RIDs flagged with actions noted. (Dec. 11th 2008).
• Final Board Report released to team (yesterday!)
ESA’s CDR Process and Goals
• ESA led review, co-chaired by NASA Independent Review Office• 18 Board members from ESA , NASA and STScI
• 60 Panel members from ESA , NASA, IST, and STScI
Board
System Design
Overall Science & Func Perfo
Calibration
Operations
FDIR
Budgets
Schedule
Overall AIV
Panel # 1SYSTEM PANEL (SP)
R. MeynartG. Bagnasco
Structure Design
Mechanicms Design
Thermal Design
Relevant Perfo
MGSE
Relevant AIV
PANEL # 2MECH-THERMAL PANEL( MP)
R. BureoJ.C. Salvignol
Optical Design
Relevant Perfo
OGSE
Relevant AIV
PANEL # 3OPTICAL PANEL (OP)
B. HarnishM. Te Plate
Electrical Design
Harness Design
SW Design
Relevant Perfo
EGSE
Relevant AIV
PANEL # 4ELEC-SW PANEL (EP)
F. MarlianiP. Rumler/P. Strada
Quality Assurance
Product Assurance
Cleanliness & Contamination
Risk Management
Safety
PANEL # 5PA PANEL (PP)
M.v. EesbeekM. Falcolini
(M. Stiavelli)(T. Beck)
NIRSpec CDR Results• During the Reviews, Panels came up with a total of:
– 192 RIDS• 70 RIDS Classified as “Major”
• 92 RIDS Classified as “Minor”
• ALL RIDS have either been Closed or accepted with a well defined action
• NO Items were elevated to the Board for Resolution
• (At the time of the NIRSpec Instrument CDR, the MSS subsystem had not had it’s CDR - this is taking place TODAY & TOMORROW at GSFC)
NIRSpec CDR Results• Issues Highlighted by the CDR Board:
– Grating Wheel Assembly (GWA) Wavefront Error is significantly out of spec - continued troubleshooting, updates in budgets
– Refocus Mechanism Assembly (RMA) deforms at cryogenic temperatures causing WFE (coated on back, have SiC backups)
– Board requests a report by February 2009 on the recent failure of the RMA gearbox lifetime testing
– HAWAII 2RG performance - Detector Noise and sensitivity degradation due to radiation damage still not established
– MSS CDR delayed until January - after NIRSpec CDR, which resulted in a lack of proper documentation on the MSS. Board requests a report by Feb. 2009 on conclusions from the MSS CDR - incl. clear analysis of MSS problems and qualification plans/status.
– Schedule delays in some elements (e.g., GWA) will impact flight model tests - now planned to perform FM cryo tests in two phases.
NIRSpec CDR Results• Issues Highlighted by the CDR Board:
– Stray light reduction mask - out of field stray light may be blocked by a static, oversized pupil mask positioned in front of the FWA, board endorsed feasibility study for implementing such a mask.
– Concern regarding software validation flow from ICE/MSS/DS through to ISIM level, recommends that the project define and describe in detail an appropriate NIRSpec FSW validation process based on top-level requirements.
– Performance Budgets are not yet consolidated and verified with measurement values - requests that budgets are maintained and updated systematically as new data become available. (incl. GWA WFE, FOR WFE, Detector noise/sensitivity/dark current).
– Total of 70 actions assigned to Astrium, ESA and NASA on “Major” RID items - (many = updates to qual plans and verification matrix for consistency with test plans)
NIRSpec CDR Results• Total of 70 actions assigned to Astrium, ESA and NASA
on “Major” RID items, including:– many = updates to qual plans and verification matrix for
consistency with test plans, error budgets– Report from NASA on Prasedymium-Iron-Boron for use in the
MSS magnet arm, risk due to corrosion, brittleness, contamination and loss of magnetic strength
– Confirmation that acrylic adhesive Y966 can be used at cryo-temperature (reports of risk due to lack of adhesion)
NIRSpec CDR Results• CDR Board Conclusions:
– The NIRSpec CDR will be satisfactorily concluded when the recommendations highlighted (previously) and actions from the CDR panel teams have been addressed and concluded.
– The board requests a report on the status of the identified major issues and RID actions by May 2009.
NIRSpec - The Future• DM (Demonstration Model) ambient tests ongoing, cryotests in
Spring 2009 (Focal plane detector at MSA plane)
• FM (Flight Model) plan with schedule mitigation has been developed – Main deliveries: grating wheel assembly, filter wheel assembly, micro-
shutter subsystem, detector subsystem– Plan for dual cryogenic test with intermediate refurbishing – Likely to be implemented for grating wheel
Old Baseline (1 Cryo test)
New Baseline 2 Cryo Tests
Old Baseline (1 Cryo test)
New Baseline 2 Cryo Tests
• The PLAN:
• NIRSpec DM (ETU) Delivery in July 2009 (26d contingency)
• NIRSpec FM mid 2010 delivery to GSFC (40d contingency)
NIRSpec -Operational “Issues” of Interest
• MSA = A complicated component! – Stuck open/closed shutters
From T. Boker’s presentation at CDR Kickoff
NIRSpec -Operational “Issues” of Interest
• “Plugging” moves quadrants into useable space - (NOTE: most of the MSA quads considered for flight aren’t quite as bad as the ENG-grade images presented in images here)
NIRSpec -Operational “Issues” of Interest
• MSA Quad lifetime tests show that shutters can become stuck open/closed during operations, after many moves of the MSA magnet arm– MSA open/closed shutters may change over time!– MSA Quadrant heating (heat to ~270K) unsticks the
shutters and returns the MSA to it’s nominal performance– MSA Quadrant heating may need to take place after
every ~2000 moves (TBD/TBR!)– NIRSpec will be unusable during the heating process
(nominal duration TBR!, but on order of ~15hrs).– We may need an updatable map of stuck open/closed
shutters that can be updated in the APT MSA planning tool