The OCONUS IDP Network Upgrade & Optimization Project
Presented by Scott Denton
National Weather Service2015 OCONUS Technical Interchange Meeting
May 12-15, 2015
National Oceanic and Atmospheric Administration (NOAA)
2
Communications Network Upgrades
The NWS is undertaking a major project to upgrade its networks and optimize the communications infrastructure to resolve weaknesses and gaps. The OCONUS Network Upgrade & Optimization Project: Designed to increase bandwidth to ensure the NWS’s terrestrial telecommunication infrastructure supports the delivery of critical weather data to internal and external stakeholders. A near-term network upgrade will bring increased bandwidth and “Trusted Internet Connections and Access Providers” (TICAP) compliance for NWS field sites throughout Alaska and Pacific Regions. The main focus is on fixing and maintaining NWS operational networks and delivering short-to-medium term capability and reliability upgrades and improvements. It will also address network single point of failure vulnerabilities.
National Oceanic and Atmospheric Administration (NOAA)
3
NCEP OCONUS – Alaska Region
National Oceanic and Atmospheric Administration (NOAA)
4
NCEP OCONUS: Alaska Region
• Service Providers:‒ CenturyLink ‒ ACS‒ MTA (sub to ACS)‒ Wire Comm (sub to ACS)
• Who will manage the Network:‒ NCEP Staff (College Park, ARH and PRH)‒ CenturyLink‒ ACS
• Bandwidth Limitation:‒ Dynamic to meet data needs
National Oceanic and Atmospheric Administration (NOAA)
5
NCEP OCONUS: Alaska Region (Cont.)
• Connections and Routing‒ Any to Any within State‒ QOS within State ‒ Redundant and diverse wherever possible
» Diverse fiber paths into the building» Redundant and diverse paths between offices and telco CO’s » Redundant and diverse paths between Cities» Diverse paths between Alaska and long haul to CONUS NCEP Network» Alternate technology where fiber diversity is not possible
‒ Connecting to OPSnet through NCEP‒ Internet access through TICAP via NCEP
National Oceanic and Atmospheric Administration (NOAA)
6
NCEP OCONUS: Pacific Region
National Oceanic and Atmospheric Administration (NOAA)
7
NCEP OCONUS: Pacific Region
• Service Providers:‒ CenturyLink ‒ Hawaiian Telecom‒ GTA (sub to CenturyLink)‒ ASTCA (Am. Sam. Telecom)‒ O3b Networks (Sat Comm to Am. Sam.)
• Who will manage the Network:‒ NCEP Staff (College Park, PRH and ARH)‒ CenturyLink‒ Hawaiian Telecom
• Bandwidth Limitation:‒ Dynamic to meet data needs
National Oceanic and Atmospheric Administration (NOAA)
8
NCEP OCONUS: Pacific Region (Cont.)
• Connections and Routing‒ Any to Any within Hawaii ‒ QOS within State and WFO Guam‒ Redundant and diverse wherever possible
» Diverse fiber paths into the building» Redundant and diverse paths between offices and telco CO’s » Diverse paths between Hawaii, Guam, and Am Sam; and long haul to CONUS
NCEP Network» Alternate technology where fiber diversity is not possible
‒ Connecting to OPSnet through NCEP‒ Internet access through TICAP via NOAA IRC TIC
National Oceanic and Atmospheric Administration (NOAA)
9
NCEP OCONUS Network
National Oceanic and Atmospheric Administration (NOAA)
10
OCONUS Project ScheduleTask Name Duration % Complete Start Finish
Phase 1: Installation and Test (Increased bandwidth with TICAP compliance) 128 days 83% Thu 12/18/14 Wed 6/17/15
Primary Interconnect between NCEP/NCO and OPSnet configured for non-operational traffic 65 days 100% Thu 1/15/15 Tue 4/14/15
Networx primary circuits installed by Telco 35 days 100% Sat 2/28/15 Thu 4/16/15
Non-Networx primary circuits installed by Telco 89 days 100% Thu 12/18/14 Wed 4/22/15
Hardware Installed and circuits connected 38 days 100% Wed 3/4/15 Fri 4/24/15
NTWC 38 days 100% Wed 3/4/15 Fri 4/24/15
WFO Fairbanks and NESDIS (Gilmore Creek) 35 days 100% Mon 3/9/15 Fri 4/24/15
ARH and WFO Anchorage 30 days 100% Mon 3/16/15 Fri 4/24/15
WFO Juneau 25 days 100% Mon 3/23/15 Fri 4/24/15
WSO Pago Pago 2 days 100% Fri 3/13/15 Mon 3/16/15
WFO Honolulu 2 days 100% Mon 4/20/15 Tue 4/21/15
PRH/PTWC: IRC 10 days 100% Wed 4/8/15 Tue 4/21/15
WFO Guam 5 days 100% Mon 4/13/15 Fri 4/17/15
JDSU stress testing 20 days 100% Mon 3/30/15 Fri 4/24/15 Network Test (non-OPSnet traffic + Internet traffic thru TICAP site) 48 days 20% Wed 3/18/15 Fri 5/22/15 Customer support processes developed by NCO for OCONUS locations 25 days 100% Mon 4/6/15 Fri 5/8/15
Increase non-operational bandwidth w/TICAP Compliance 20 days 10% Fri 5/1/15 Fri 5/29/15
Non-OPSnet circuits disconnected/services cancelled where possible 23 days 0% Fri 5/15/15 Wed 6/17/15
H-8 Data Flow configuration and Testing 42 days 0% Fri 5/15/15 Wed 7/15/15
IDP-to-AR/PR Network Configured for H-8 Data Flow 1 day 0% Fri 5/15/15 Fri 5/15/15
Test H8 Full-Res Imagery Ingest/Display (at WFO Test Bed?) 20 days 0% Mon 5/18/15 Mon 6/15/15
End-to-End Real-Time IDP-to-WFO/HQ Live Data Flow Test 20 days 0% Wed 6/17/15 Wed 7/15/15
National Oceanic and Atmospheric Administration (NOAA)
11
OCONUS Project Schedule – Cont.Task Name Duration % Complete Start Finish
Phase 2: Installation and Test (OPSnet data added to new network) 67 days 22% Mon 4/6/15 Thu 7/9/15
Routing changes identified for OPSnet/NECP interconnect to recognize currcent VRF in/out traffic to OCONUS sites 15 days 100% Mon 4/6/15 Fri 4/24/15
Routing changes made on OPSnet/NCEP routers to recognize currcent VRF in/out traffic to OCONUS sites 30 days 25% Mon 4/27/15 Mon 6/8/15
OPSnet data (A2 and L2 radar) redirected to new network and ready for testing 11 days 0% Tue 6/9/15 Tue 6/23/15
AR and PR staff access to remote VPN access for admin and teleworkers 25 days 0% Fri 5/1/15 Fri 6/5/15
Network Test (OPSnet traffic) 10 days 0% Wed 6/24/15 Wed 7/8/15
Backup Interconnect between NCEP/NCO and OPSnet installed/established 15 days 10% Fri 5/22/15 Fri 6/12/15
Increase Operational Bandwidth 1 day 0% Thu 7/9/15 Thu 7/9/15
Post Installation (Tear down of old network) 53 days 0% Mon 6/1/15 Thu 8/13/15
Circuits disconnected and services cancelled 52 days 0% Mon 6/1/15 Wed 8/12/15
Network hardware removed 42 days 0% Mon 6/15/15 Wed 8/12/15
Tear down completed and duplicate costs of circuits eliminated where possible 1 day 0% Thu 8/13/15 Thu 8/13/15
Redundent/Diverse Path Circuit Installs 85 days 43% Fri 5/1/15 Mon 8/31/15
Order Networx circuit upgrades for Reston and Orlando: 3G to 4G 20 days 100% Fri 5/1/15 Fri 5/29/15
Installation of diverse circuit to ARH 43 days 100% Fri 5/1/15 Wed 7/1/15
Installation of diverse circuit to NTWC 43 days 100% Fri 5/1/15 Wed 7/1/15
Installation of diverse circuit to WFO Fairbanks 42 days 100% Fri 5/1/15 Wed 7/1/15
Installation of diverse path for IRC 33 days 52% Fri 5/1/15 Wed 6/17/15
Installation of diverse path for HFO Honolulu 33 days 52% Fri 5/1/15 Wed 6/17/15
Fiber trenching and installation of diverse circuit to Guam 31 days 15% Fri 5/1/15 Mon 6/15/15
Installation of diverse circuit to Am Sam (Sat Comm) 85 days 10% Fri 5/1/15 Mon 8/31/15
Installation of diverse circuit to WFO Juneau (Microwave) 85 days 10% Fri 5/1/15 Mon 8/31/15
Fiber installation of diverse circuit to WFO Anchorage 85 days 10% Fri 5/1/15 Mon 8/31/15
National Oceanic and Atmospheric Administration (NOAA)
12
H-8 Full Resolution
National Oceanic and Atmospheric Administration (NOAA)
13
H-8 Dissemination Architecture - AR/PR
14
Progress & ScheduleTask Name
% Comp Start Finish
Resource Names
Develop & Test H8 AHIProc Software in IDP 71% 12/2/2014 6/10/2015
Develop AHIProc Software 100% 12/19/2014 4/10/2015 DG
Pre-Production Data Flow Tests to AWIPS-II Testbed 93% 12/2/2014 5/22/2015 DG, NCO Software Testing in IDP Test Environment 25% 2/24/2015 6/10/2015 NCO
Develop Operational Data Dissemination System 0% 5/5/2015 6/23/2015 Implement IDP-to-OCONUS Network 0% 5/5/2015 6/23/2015 NCO Prepare Regional Networks to Receive H8 Terrestrial Data 0% 5/5/2015 5/5/2015 NCO
Network RCs Approved 0% 6/8/2015 6/8/2015 NCO
Set Up Network Path 0% 6/9/2015 6/16/2015 NCO
Configure Networks 0% 6/17/2015 6/23/2015 NCO
Test Network Connectivity 0% 6/23/2015 6/23/2015 NCO
Networks Ready for Production Tests 0% 6/23/2015 6/23/2015 NCO
IDP Production Testing and Go Live 0% 6/10/2015 9/16/2015
Final software code drop (NCO drops AHIProc into Prod) 0% 6/10/2015 6/10/2015 NCO
Build, Install, & Test AHIProc on Prod-A and Prod-B 0% 6/11/2015 7/21/2015
Test IDP to Field Connectivity 0% 6/24/2015 6/25/2015 NCO Run test cases for functionality (AWIPS-II ingest/display) 0% 6/30/2015 7/2/2015 NCO Run test cases for functionality (stress/load testing) 0% 7/6/2015 7/21/2015 NCO Run 45-day acceptance and performance test 0% 7/22/2015 9/10/2015 NCO
ORR 0% 9/11/2015 9/14/2015 NCO
Final approval; Deploy to operations 0% 9/15/2015 9/16/2015 NCO
Go Live 0% 9/16/2015 9/16/2015 NCO
Begin Terrestrial-Only Dissemination of Himawari Data 0% 11/30/2015 11/30/2015 NWS
National Oceanic and Atmospheric Administration (NOAA)
15
Himawari Level0 16 Channels (HBI)
GRB/ Himawari DRO Sites & Data Centers A & B
Japan Met Agency (JMA) Ground Segment
LAT/ LONG
GR-East Level1B
GR-West Level1B
Spare AS GR-East Level1B
GR-West Spare AS Level1B
GR-East Level0
GR-West
Level0
10Gbps 10G w/ 10Gbps Port Speed
NGDC SPADES SEVER(S) Developmental
NESDIS NSOF (STAR)/ PDA Site A DATA CENTER Site B DATA CENTER
Ground Segment LAT/ LONG
NWS SPADES SEVER(S) Operational
NWS SPADES SEVER(S) Operational NGDC
NCWCP College Park, MD. David Skaggs Research Center (DSRC) SWPC & NGDC Boulder, CO.
LAT/ LONG LAT/ LONG
10G w/ 10Gbps Port Speed
10G w/ 2Gbps Port Speed 1G w/ 200Mbps Port Speed
NCEP MPLS NCEP MPLS NCEP MPLS
1G w/ 200Mbps Port Speed
GR-East GR-West Spare AS GR-East GR-West Spare AS GR-East GR-West Spare AS GR-West Himawari GOES-W XXX XXX XXX University of Alaska GR-West Himawari Himawari Level1B Level1B Level1B Level1B Level1B Level1B Level1B Level1B Level1B Level1B Level1B
Aviation Weather Center
Kansas City, MO.
National Hurricane Center
Miami, FL.
Storm Prediction Center
Norman, OK.
(5 Channels)
Alaska Region Sand Lake, AK.
NESDIS
Gilmore Creek, AK
(5 Channels)
Pacific Region Ford Island, HI.
(5 Channels)
Barrigada, GUAM
LAT/ LONG LAT/ LONG LAT/ LONG LAT/ LONG LAT/ LONG LAT/ LONG LAT/ LONG LAT/ LONG
Salim Leyva 2014April01 REV: 6
Inte
rnet
2
or ?
National Oceanic and Atmospheric Administration (NOAA)
16