the power of greater nashville - 1 - t&d planning at nashville electric service paul h. allen,...
TRANSCRIPT
-
T&D Planning at Nashville Electric Service
Paul H. Allen, Nashville Electric ServiceAPPA E&O Technical ConferenceMarch 9, 2004 - San Antonio, Texas
The Power Of Greater Nashville
-
BackgroundNashville Electric Service (NES) is the operating name for The Electric Power Board of the Metropolitan Government of Nashville and Davidson CountyNES is governed by a five member board, appointed by the Mayor and confirmed by the CouncilThe Board Members serve 5 year terms, without pay, and have full responsibility for the operation of NESThe day-to-day responsibility is delegated to the President and CEO of NES
The Power Of Greater Nashville
-
NES Statistics700 m2 Service territoryapprox. 328,000 Customers291,000 Residential 30,000 Small Commercial 6,700 Large C&I12,233,000 MWh sold in FY 200355.8% of revenue from C&I customers77.8% to purchase powerResidential - 6.545 / kWh; $6.01 customer charge
The Power Of Greater Nashville
-
NES Statistics62 Major substations161 kV and 69kV transmission voltages23.9kV, 13.9kV and 4 kV distribution voltagesSecondary network system in downtownNo generation - 22 feed points from TVA
Went from winter peaking to summer peaking in mid 1990sSummer peak 2,474 MW August 2000Winter peak 2,441 MW December 1989
The Power Of Greater Nashville
-
Issues in the PastPrior to 1992, a 5 year system plan was prepared that included a one year construction planThe plan was prepared internally and the plan was reviewed by an independent engineering consultant - similar to an external financial auditThe plan was redone every five years or when annual load growth exceeded 2.5%Increasing financial pressure resulted in some maintenance activities being scaled back in the late 1980s
The Power Of Greater Nashville
-
Timeline of Events
The Power Of Greater Nashville
Year
T&D Plan
Significant Events
1988
5 year Plan(internal)
Some maintenance activities had been scaled back
Rate Decrease
Computer planning tool in place but not fully utilized
1989
Management change
Significant public opposition to T-Line project
Rate Increase
1990
Approx. 10% of workforce retires (early)
Rate Decrease
1991
Construction budget scaled back
-
Timeline of Events
The Power Of Greater Nashville
Year
T&D Plan
Significant Events
1992
First 20 year Plan (External)
1993
Management change
Joint city wide GIS effort dissolved
1994
Ice storm, 1/3 of customers affected, two week restoration
Fiber optic partnering started
1995
GIS, OMS effort began
Manual collection of reliability data
Rate Increase
-
Timeline of Events
The Power Of Greater Nashville
Year
T&D Plan
Significant Events
1996
1997
20 Year Plan(internal and external)
Added contract labor resources
Rate increase
1998
Delayed T-Line started with Citizens Advisory Committee for routing process
Tornado in downtown, 1 week restoration
-
Timeline of Events
The Power Of Greater Nashville
Year
T&D Plan
Significant Events
1999
2000
Management change
Reliability Initiative
New radio system in service
2001
EPRI Study - Asset Mgmt., Maintenance Mgmt.
Rate increase
2002
20 Year Plan (external)
Work Management Project started
Budget Prioritization Project started
2003
Rate increase
2004
Management change
-
Current EnvironmentPlanning Process - OverviewA 20 year comprehensive T&D plan is prepared at least every 5 years or when system demand reaches or exceeds 105% in the base year of the last studyResult - a new plan every 3 to 5 yearsAn external consultant is used on every other planAssures that process is state of the artProvides appropriate due diligence to Board and Executive ManagementInterim studies are performed (internally) between plans to determine if plan should be accelerated or slowed
The Power Of Greater Nashville
-
Current Tool IntegrationOMS(CADOPS)GIS(ArcInfo)SCADA(ESCA)Distribution(Feederall)Transmission(PTI PSS/E)Forecast(Foresite)Reliability(Relinet)AVLCIS(Legacy)Common Data BaseSystemForecastVarious Inputs
The Power Of Greater Nashville
-
Current EnvironmentPlanning Process - ForecastsSystem ForecastRolling 5 year trending method based on historical data - primarily the weather adjusted peakSufficiently accurate for 5 year periodHigh, medium, and low forecastsForecast changes from plan to plan are explainedSubstation ForecastArea load growth forecasts using software toolDetermines where the load growth is likely to occur
The Power Of Greater Nashville
-
Current EnvironmentSubstation ForecastCreation of land use models from satellite imagery, zoning data, city planning data, etc. - one acre small areasMuch of information is from GIS systemsSmall areas are assigned to distribution substationsSystem forecast is spread to substations by software tool and substations loads are grown relative to each other based on small areasUsed to identify capacity needs, inputs for transmission load flow studies, and to determine loads on distribution feeders
The Power Of Greater Nashville
-
Land Use Model - Downtown
The Power Of Greater Nashville
-
Southwest Area Growth - 2020
The Power Of Greater Nashville
-
Current EnvironmentPlanning Process - Contingency AnalysisTransmissionN-1 planning criteria using software tool using inputs from forecastsIdentify multiple solutionsShort list of solutions developed (costs developed)DistributionExtract distribution model from OMS systemIdentification of loading and voltage problems and potential solutions using software toolIdentification of reliability solutions for worst circuits using software tool
The Power Of Greater Nashville
-
Current EnvironmentPlanning Process - Project IdentificationImpact analysis - external factors that could affect the solution - property, schedules, public, etc.Selection of solution and identification of needed projects for the selected solutionPrioritization of projects for selected solution - order of constructionSchedule leveling of projects for selected solution - dollars and resources
The Power Of Greater Nashville
-
Current EnvironmentBudget Process5 year financial model used to forecast net incomeKey financial goalsCash reserve, debt coverage, leverage goalCapital budget developed from T&D plan, forecasted new business, other infrastructure projects, and equipment/facilitiesCurrent prioritization is by senior management team and stakeholders Iterative Process - capital expenditures affect financial goals - pressure to limit expenditures
The Power Of Greater Nashville
-
Financial Model
The Power Of Greater Nashville
FORECASTED FUNDS AVAILABLE FOR DEBT SERVICE AND CONSTRUCTION
BUDGET
Jun-04
Jun-05
Jun-06
Jun-07
Jun-08
NET INCOME
$14,579,407
$8,526,784
$10,754,427
$5,708,525
$1,461,450
ADJUSTMENTS:
DEPRECIATION
31,500,000
32,760,000
34,070,400
35,433,216
36,850,545
INTEREST EXPENSE
19,939000
25,759,423
25,027,694
24,363,456
23,654,398
EXISTING BOND PROCEEDS
27,159,040
0
0
0
0
NEW BONDS
0
35,000,000
33,000,000
32,000,000
0
TOTAL AVAILABLE FOR DEBT SERVICE,CONSTRUCTION, & WORKING CAPITAL
$93,177,447
$102,046,207
$102,852,520
$97,505,197
$61,966,393
REQUIREMENTS:
DEBT SERVICE
31,999,268
37,997,369
37,998,008
37,998,119
37,999,731
CONSTRUCTION & REMOVAL COSTS
52,573,207
60,000,000
60,000,000
60,000,000
60,000,000
TOTAL REQUIREMENTS
84,572,475
97,997,369
97,998,008
97,998,119
97,999,731
NET CHANGE IN CASH
$8,604,972
$4,048,838
$4,854,512
($492,922)
($36,033,338)
ENDING CASH
$49,350,888
$53,399,726
$58,254,239
$57,761,317
$21,727,979
CASH REQUIREMENT(7% OF O & M and Taxes)
$51,472,151
$53,266,854
$54,005,834
$55,037,698
$56,093,910
EXCESS OR DEFICIENCY FROM CASH GOAL
(2,121,262)
132,872
4,248,405
2,723,619
(34,365,931)
DEBT COVERAGE RATIO
2.70
2.32
2.42
2.33
2.26
DEBT COVERAGE RATIO GOAL
2.00
2.00
2.00
2.00
2.00
PERCENT OF CONSTRUCTION(ANNUAL)
52%
58%
55%
53%
0%
-
Current EnvironmentPlans have been and will always be at risk for delay for many reasons - financial, public pressure, major equipment failures, weather, etc.Its our experience that when plans are delayed beyond a reasonable timeframe, the cost of providing safe, reliable service dramatically increases, the solutions required to provide that service may not optimal, and there is increased risk to the reliability of the electric systemThis is a constant pressure on the planning process
The Power Of Greater Nashville
-
Capital Expenditures
The Power Of Greater Nashville
ActualHistory
11106741.316207376.0712017544.942559476.67
11779592.495918540.9712520768.323145293.07
11103578.496777193.79996247.235108037.87
9501291.9119482343.9611155855.586287554.1
7738000774100078080004546000
6516000902600091230002241000
69170004004000101530003727000
475000032240008388000992000
4931000319900086300002458000
63150006986000131540006165000
89420004580000138940007715000
102940007491000168700009239000
103730009413000210970008447000
1131400010684000139340005144000
15092000134970001850700010410000
14878875208245832106462111732000
11244000255250001865700010016000
1127500026499000187150009104000
12179672.5125874649.5120470803.2514935395.48
1263664016234361184416595260547
1316715326361988205704247940850
1367725327307275213932328371600
1417296025882550217408598723600
1453789627169681218732387646100
New Business
System Construction
Other Construction
Equipment & Facilities
Construction Program - Actual Expenditures
ActualAdjusted
15149984.85706148467078.7621491216392352.96640353491215.98407895
15997612.50825338037843.8500873417004187.54375554271555.21733624
14948973.63805199124273.7692640713458151.03259746877055.31415584
12574050.144723425783016.900255314763706.74629798320975.85148936
9549674.60317469553376.984126999636063.492063495610341.26984127
7824231.6602316610838169.884169910954644.78764482690930.5019305
8210637.404580154752839.6946564912051843.51145044424034.35114504
5659961.685823763841624.52107289994896.551724141182038.31417625
5638018.382352943657680.147058829867389.705882352810433.82352941
7167755.474452567929364.9635036514930270.07299276997500
9723643.356643364980349.6503496515108510.48951058389388.11188811
10926395.90443697951197.9522184317906382.25255979806583.61774744
11240428.571428610200149.82578422861209.05923349153369.33797909
11807563.758389311150080.536912814541859.06040275368402.68456376
15645373.3333333139918901918559010791700
15476020.484949821660352.217391321910023.849498312202849.4983278
11244000255250001865700010016000
10992241.379310325834448.275862118245658.307218875686.52037618
11619258.130705524684098.152177919528895.12514248184.0315337
1263664016234361184416595260547
New Business
System Construction
Other Construction
Equipment & Facilities
Construction Program2004 Dollars
Data
History plus ProjectionsHandy Whitman Adusted to 2001 dollars
New BusinessSystem ConstructionOther ConstructionEquipment & FacilitiesTotalHandy WhitmanNew BusinessSystem ConstructionOther ConstructionEquipment & FacilitiesTotal
1.FY 1985$11,106,741$6,207,376$12,017,545$2,559,477$31,891,139228$15,149,985$8,467,079$16,392,353$3,491,216$43,500,633
2.FY 1986$11,779,592$5,918,541$12,520,768$3,145,293$33,364,195229$15,997,613$8,037,844$17,004,188$4,271,555$45,311,199
3.FY 1987$11,103,578$6,777,194$9,996,247$5,108,038$32,985,057231$14,948,974$9,124,274$13,458,151$6,877,055$44,408,454
4.FY 1988$9,501,292$19,482,344$11,155,856$6,287,554$46,427,046235$12,574,050$25,783,017$14,763,707$8,320,976$61,441,750
5.FY 1989$7,738,000$7,741,000$7,808,000$4,546,000$27,833,000252$9,549,675$9,553,377$9,636,063$5,610,341$34,349,456
6.FY 1990$6,516,000$9,026,000$9,123,000$2,241,000$26,906,000259$7,824,232$10,838,170$10,954,645$2,690,931$32,307,977
7.FY 1991$6,917,000$4,004,000$10,153,000$3,727,000$24,801,000262$8,210,637$4,752,840$12,051,844$4,424,034$29,439,355
8.FY 1992$4,750,000$3,224,000$8,388,000$992,000$17,354,000261$5,659,962$3,841,625$9,994,897$1,182,038$20,678,521
9.FY 1993$4,931,000$3,199,000$8,630,000$2,458,000$19,218,000272$5,638,018$3,657,680$9,867,390$2,810,434$21,973,522
10.FY 1994$6,315,000$6,986,000$13,154,000$6,165,000$32,620,000274$7,167,755$7,929,365$14,930,270$6,997,500$37,024,891
11.FY 1995$8,942,000$4,580,000$13,894,000$7,715,000$35,131,000286$9,723,643$4,980,350$15,108,510$8,389,388$38,201,892
12.FY 1996$10,294,000$7,491,000$16,870,000$9,239,000$43,894,000293$10,926,396$7,951,198$17,906,382$9,806,584$46,590,560
13.FY 1997$10,373,000$9,413,000$21,097,000$8,447,000$49,330,000287$11,240,429$10,200,150$22,861,209$9,153,369$53,455,157
14.FY 1998$11,314,000$10,684,000$13,934,000$5,144,000$41,076,000298$11,807,564$11,150,081$14,541,859$5,368,403$42,867,906
15.FY 1999$15,092,000$13,497,000$18,507,000$10,410,000$57,506,000300$15,645,373$13,991,890$19,185,590$10,791,700$59,614,553
16.FY 2000$14,878,875$20,824,583$21,064,621$11,732,000$68,500,079299$15,476,020$21,660,352$21,910,024$12,202,849$71,249,246
17.FY 2001$11,244,000$25,525,000$18,657,000$10,016,000$65,442,000311$11,244,000$25,525,000$18,657,000$10,016,000$65,442,000
18.FY 2002$11,275,000$26,499,000$18,715,000$9,104,000$65,593,000319$10,992,241$25,834,448$18,245,658$8,875,687$63,948,034
19.FY 2003$12,179,673$25,874,650$20,470,803$14,935,395$73,460,521326$11,619,258$24,684,098$19,528,895$14,248,184$70,080,435
20.FY 2004 Budg$12,636,640$16,234,361$18,441,659$5,260,547$52,573,207$12,636,640$16,234,361$18,441,659$5,260,547$52,573,207
21.FY 2005 proj$13,167,153$26,361,988$20,570,424$7,940,850$68,040,415
22.FY 2006 Proj$13,677,253$27,307,275$21,393,232$8,371,600$70,749,360
23.FY 2007 Proj$14,172,960$25,882,550$21,740,859$8,723,600$70,519,969
24.FY 2008 Proj$14,537,896$27,169,681$21,873,238$7,646,100$71,226,915
25.
20 yr Average$9,944,370$11,659,402$14,229,875$6,461,615$42,295,262
10 yr Average$11,822,919$16,062,259$18,165,108$9,200,294$55,250,581
5 yr Average$12,442,838$22,991,519$19,469,817$10,209,588$65,113,761
FY 1985-1993$74,343,204$65,579,455$89,792,416$31,064,362$260,779,437Average$11,104,960$10,103,830$15,248,475$6,612,022$43,991,592
FY 1994-2003$111,907,548$151,374,233$176,363,424$92,907,395$532,552,600
FY 2002-2006$62,935,719$122,277,274$99,591,118$45,612,392$330,416,503$9,204,149
Total$249,186,470$339,230,961$365,746,959$169,584,150$1,123,748,539
Data
0
0
0
0
FY 1994-2001
PHAHandy Whitmand Index 1/1/2001 South AtlanticTotal Distribution PlantJan 1 or entire Year1973 = 100
-
Current Gaps - PrioritizationCurrent process is perceived to be unreliableIn March 2003, began implementation of the EPRI Project Prioritization toolGoals:Model All Distribution Capital and O&M ProjectsValue projects using multiple attributes and Common ScaleDetermine measurements and weightsInitial Model Spring 2004 - T&D Projects onlyEnd result -> prioritized project list by value
The Power Of Greater Nashville
-
Project Prioritization
The Power Of Greater Nashville
_1137236387.doc
-
Current Gaps - Work Mgmt.Mainframe legacy system installed in 1989Purchased integrated system in 2002 (Mincom)Work Management, Finance, Supply ChainExternal consultant facilitated Best Practice process definitionsPlanned Go-Live is July 1, 2004Goals:Enable one view of all workImprove ability to prioritize and manage workImprove project management Reduce overall cycle time for work lifecycleProvide accurate tools for estimation and designEnsure that resources are at the right place at the right time
The Power Of Greater Nashville
-
Work Management
The Power Of Greater Nashville
-
Current Gaps - Asset Mgmt.No existing system or formal processEPRI recommendationProcess consultant recommendationNew work management system will provide necessary data and support system (Equipment Register)
The Power Of Greater Nashville
-
Current Gaps - Asset Mgmt.Manage the AssetsMaintenancePlanningBudgetingConstructionPlanningStandardsOther WorkPlanningSystemPlanning
The Power Of Greater Nashville
-
Current Gaps - Asset Mgmt.
The Power Of Greater Nashville
-
Current Gaps - Asset Mgmt.
The Power Of Greater Nashville
-
Current Gaps - Asset Mgmt.Goals:Improve information on health of assetsImprove ability to compare and prioritize capital workImprove project management Develop consistent maintenance programsImprove linkage between budgeted projects and actual work performedBenefits realizationImproving quality of asset dataCoordination of repair/replace decisionsImprove short and long term budgetingImprove standards and estimating process
The Power Of Greater Nashville
-
The FutureWe striving for...More integration of and proficiency with tools and systemsMore public involvement in the planning processMore accurate SCADA and OMS dataMore real time integration with SCADAUse of the Equipment Register to capture costs and operating statistics by circuit and equipmentBetter communication of the benefits and risks of proper T&D planning and construction to all of our stakeholders
The Power Of Greater Nashville
-
Future Integration PlansOMS(CADOPS)GISSCADADistributionPlanningTransmissionPlanningSubstationForecastReliabilityPlanningSystemAutomationCISCommon Data BaseSystemForecastVarious InputsMobile Data/AVLOther Operational ApplicationsEquipmentRegister
The Power Of Greater Nashville
-
Thank You!
The Power Of Greater Nashville