the power of greater nashville - 1 - t&d planning at nashville electric service paul h. allen,...

33
The Power Of Greater Nashvi lle - 1 - T&D Planning at Nashville Electric Service Paul H. Allen, Nashville Electric Service APPA E&O Technical Conference March 9, 2004 - San Antonio, Texas

Upload: prudence-wiggins

Post on 19-Jan-2016

220 views

Category:

Documents


0 download

TRANSCRIPT

  • T&D Planning at Nashville Electric Service

    Paul H. Allen, Nashville Electric ServiceAPPA E&O Technical ConferenceMarch 9, 2004 - San Antonio, Texas

    The Power Of Greater Nashville

  • BackgroundNashville Electric Service (NES) is the operating name for The Electric Power Board of the Metropolitan Government of Nashville and Davidson CountyNES is governed by a five member board, appointed by the Mayor and confirmed by the CouncilThe Board Members serve 5 year terms, without pay, and have full responsibility for the operation of NESThe day-to-day responsibility is delegated to the President and CEO of NES

    The Power Of Greater Nashville

  • NES Statistics700 m2 Service territoryapprox. 328,000 Customers291,000 Residential 30,000 Small Commercial 6,700 Large C&I12,233,000 MWh sold in FY 200355.8% of revenue from C&I customers77.8% to purchase powerResidential - 6.545 / kWh; $6.01 customer charge

    The Power Of Greater Nashville

  • NES Statistics62 Major substations161 kV and 69kV transmission voltages23.9kV, 13.9kV and 4 kV distribution voltagesSecondary network system in downtownNo generation - 22 feed points from TVA

    Went from winter peaking to summer peaking in mid 1990sSummer peak 2,474 MW August 2000Winter peak 2,441 MW December 1989

    The Power Of Greater Nashville

  • Issues in the PastPrior to 1992, a 5 year system plan was prepared that included a one year construction planThe plan was prepared internally and the plan was reviewed by an independent engineering consultant - similar to an external financial auditThe plan was redone every five years or when annual load growth exceeded 2.5%Increasing financial pressure resulted in some maintenance activities being scaled back in the late 1980s

    The Power Of Greater Nashville

  • Timeline of Events

    The Power Of Greater Nashville

    Year

    T&D Plan

    Significant Events

    1988

    5 year Plan(internal)

    Some maintenance activities had been scaled back

    Rate Decrease

    Computer planning tool in place but not fully utilized

    1989

    Management change

    Significant public opposition to T-Line project

    Rate Increase

    1990

    Approx. 10% of workforce retires (early)

    Rate Decrease

    1991

    Construction budget scaled back

  • Timeline of Events

    The Power Of Greater Nashville

    Year

    T&D Plan

    Significant Events

    1992

    First 20 year Plan (External)

    1993

    Management change

    Joint city wide GIS effort dissolved

    1994

    Ice storm, 1/3 of customers affected, two week restoration

    Fiber optic partnering started

    1995

    GIS, OMS effort began

    Manual collection of reliability data

    Rate Increase

  • Timeline of Events

    The Power Of Greater Nashville

    Year

    T&D Plan

    Significant Events

    1996

    1997

    20 Year Plan(internal and external)

    Added contract labor resources

    Rate increase

    1998

    Delayed T-Line started with Citizens Advisory Committee for routing process

    Tornado in downtown, 1 week restoration

  • Timeline of Events

    The Power Of Greater Nashville

    Year

    T&D Plan

    Significant Events

    1999

    2000

    Management change

    Reliability Initiative

    New radio system in service

    2001

    EPRI Study - Asset Mgmt., Maintenance Mgmt.

    Rate increase

    2002

    20 Year Plan (external)

    Work Management Project started

    Budget Prioritization Project started

    2003

    Rate increase

    2004

    Management change

  • Current EnvironmentPlanning Process - OverviewA 20 year comprehensive T&D plan is prepared at least every 5 years or when system demand reaches or exceeds 105% in the base year of the last studyResult - a new plan every 3 to 5 yearsAn external consultant is used on every other planAssures that process is state of the artProvides appropriate due diligence to Board and Executive ManagementInterim studies are performed (internally) between plans to determine if plan should be accelerated or slowed

    The Power Of Greater Nashville

  • Current Tool IntegrationOMS(CADOPS)GIS(ArcInfo)SCADA(ESCA)Distribution(Feederall)Transmission(PTI PSS/E)Forecast(Foresite)Reliability(Relinet)AVLCIS(Legacy)Common Data BaseSystemForecastVarious Inputs

    The Power Of Greater Nashville

  • Current EnvironmentPlanning Process - ForecastsSystem ForecastRolling 5 year trending method based on historical data - primarily the weather adjusted peakSufficiently accurate for 5 year periodHigh, medium, and low forecastsForecast changes from plan to plan are explainedSubstation ForecastArea load growth forecasts using software toolDetermines where the load growth is likely to occur

    The Power Of Greater Nashville

  • Current EnvironmentSubstation ForecastCreation of land use models from satellite imagery, zoning data, city planning data, etc. - one acre small areasMuch of information is from GIS systemsSmall areas are assigned to distribution substationsSystem forecast is spread to substations by software tool and substations loads are grown relative to each other based on small areasUsed to identify capacity needs, inputs for transmission load flow studies, and to determine loads on distribution feeders

    The Power Of Greater Nashville

  • Land Use Model - Downtown

    The Power Of Greater Nashville

  • Southwest Area Growth - 2020

    The Power Of Greater Nashville

  • Current EnvironmentPlanning Process - Contingency AnalysisTransmissionN-1 planning criteria using software tool using inputs from forecastsIdentify multiple solutionsShort list of solutions developed (costs developed)DistributionExtract distribution model from OMS systemIdentification of loading and voltage problems and potential solutions using software toolIdentification of reliability solutions for worst circuits using software tool

    The Power Of Greater Nashville

  • Current EnvironmentPlanning Process - Project IdentificationImpact analysis - external factors that could affect the solution - property, schedules, public, etc.Selection of solution and identification of needed projects for the selected solutionPrioritization of projects for selected solution - order of constructionSchedule leveling of projects for selected solution - dollars and resources

    The Power Of Greater Nashville

  • Current EnvironmentBudget Process5 year financial model used to forecast net incomeKey financial goalsCash reserve, debt coverage, leverage goalCapital budget developed from T&D plan, forecasted new business, other infrastructure projects, and equipment/facilitiesCurrent prioritization is by senior management team and stakeholders Iterative Process - capital expenditures affect financial goals - pressure to limit expenditures

    The Power Of Greater Nashville

  • Financial Model

    The Power Of Greater Nashville

    FORECASTED FUNDS AVAILABLE FOR DEBT SERVICE AND CONSTRUCTION

    BUDGET

    Jun-04

    Jun-05

    Jun-06

    Jun-07

    Jun-08

    NET INCOME

    $14,579,407

    $8,526,784

    $10,754,427

    $5,708,525

    $1,461,450

    ADJUSTMENTS:

    DEPRECIATION

    31,500,000

    32,760,000

    34,070,400

    35,433,216

    36,850,545

    INTEREST EXPENSE

    19,939000

    25,759,423

    25,027,694

    24,363,456

    23,654,398

    EXISTING BOND PROCEEDS

    27,159,040

    0

    0

    0

    0

    NEW BONDS

    0

    35,000,000

    33,000,000

    32,000,000

    0

    TOTAL AVAILABLE FOR DEBT SERVICE,CONSTRUCTION, & WORKING CAPITAL

    $93,177,447

    $102,046,207

    $102,852,520

    $97,505,197

    $61,966,393

    REQUIREMENTS:

    DEBT SERVICE

    31,999,268

    37,997,369

    37,998,008

    37,998,119

    37,999,731

    CONSTRUCTION & REMOVAL COSTS

    52,573,207

    60,000,000

    60,000,000

    60,000,000

    60,000,000

    TOTAL REQUIREMENTS

    84,572,475

    97,997,369

    97,998,008

    97,998,119

    97,999,731

    NET CHANGE IN CASH

    $8,604,972

    $4,048,838

    $4,854,512

    ($492,922)

    ($36,033,338)

    ENDING CASH

    $49,350,888

    $53,399,726

    $58,254,239

    $57,761,317

    $21,727,979

    CASH REQUIREMENT(7% OF O & M and Taxes)

    $51,472,151

    $53,266,854

    $54,005,834

    $55,037,698

    $56,093,910

    EXCESS OR DEFICIENCY FROM CASH GOAL

    (2,121,262)

    132,872

    4,248,405

    2,723,619

    (34,365,931)

    DEBT COVERAGE RATIO

    2.70

    2.32

    2.42

    2.33

    2.26

    DEBT COVERAGE RATIO GOAL

    2.00

    2.00

    2.00

    2.00

    2.00

    PERCENT OF CONSTRUCTION(ANNUAL)

    52%

    58%

    55%

    53%

    0%

  • Current EnvironmentPlans have been and will always be at risk for delay for many reasons - financial, public pressure, major equipment failures, weather, etc.Its our experience that when plans are delayed beyond a reasonable timeframe, the cost of providing safe, reliable service dramatically increases, the solutions required to provide that service may not optimal, and there is increased risk to the reliability of the electric systemThis is a constant pressure on the planning process

    The Power Of Greater Nashville

  • Capital Expenditures

    The Power Of Greater Nashville

    ActualHistory

    11106741.316207376.0712017544.942559476.67

    11779592.495918540.9712520768.323145293.07

    11103578.496777193.79996247.235108037.87

    9501291.9119482343.9611155855.586287554.1

    7738000774100078080004546000

    6516000902600091230002241000

    69170004004000101530003727000

    475000032240008388000992000

    4931000319900086300002458000

    63150006986000131540006165000

    89420004580000138940007715000

    102940007491000168700009239000

    103730009413000210970008447000

    1131400010684000139340005144000

    15092000134970001850700010410000

    14878875208245832106462111732000

    11244000255250001865700010016000

    1127500026499000187150009104000

    12179672.5125874649.5120470803.2514935395.48

    1263664016234361184416595260547

    1316715326361988205704247940850

    1367725327307275213932328371600

    1417296025882550217408598723600

    1453789627169681218732387646100

    New Business

    System Construction

    Other Construction

    Equipment & Facilities

    Construction Program - Actual Expenditures

    ActualAdjusted

    15149984.85706148467078.7621491216392352.96640353491215.98407895

    15997612.50825338037843.8500873417004187.54375554271555.21733624

    14948973.63805199124273.7692640713458151.03259746877055.31415584

    12574050.144723425783016.900255314763706.74629798320975.85148936

    9549674.60317469553376.984126999636063.492063495610341.26984127

    7824231.6602316610838169.884169910954644.78764482690930.5019305

    8210637.404580154752839.6946564912051843.51145044424034.35114504

    5659961.685823763841624.52107289994896.551724141182038.31417625

    5638018.382352943657680.147058829867389.705882352810433.82352941

    7167755.474452567929364.9635036514930270.07299276997500

    9723643.356643364980349.6503496515108510.48951058389388.11188811

    10926395.90443697951197.9522184317906382.25255979806583.61774744

    11240428.571428610200149.82578422861209.05923349153369.33797909

    11807563.758389311150080.536912814541859.06040275368402.68456376

    15645373.3333333139918901918559010791700

    15476020.484949821660352.217391321910023.849498312202849.4983278

    11244000255250001865700010016000

    10992241.379310325834448.275862118245658.307218875686.52037618

    11619258.130705524684098.152177919528895.12514248184.0315337

    1263664016234361184416595260547

    New Business

    System Construction

    Other Construction

    Equipment & Facilities

    Construction Program2004 Dollars

    Data

    History plus ProjectionsHandy Whitman Adusted to 2001 dollars

    New BusinessSystem ConstructionOther ConstructionEquipment & FacilitiesTotalHandy WhitmanNew BusinessSystem ConstructionOther ConstructionEquipment & FacilitiesTotal

    1.FY 1985$11,106,741$6,207,376$12,017,545$2,559,477$31,891,139228$15,149,985$8,467,079$16,392,353$3,491,216$43,500,633

    2.FY 1986$11,779,592$5,918,541$12,520,768$3,145,293$33,364,195229$15,997,613$8,037,844$17,004,188$4,271,555$45,311,199

    3.FY 1987$11,103,578$6,777,194$9,996,247$5,108,038$32,985,057231$14,948,974$9,124,274$13,458,151$6,877,055$44,408,454

    4.FY 1988$9,501,292$19,482,344$11,155,856$6,287,554$46,427,046235$12,574,050$25,783,017$14,763,707$8,320,976$61,441,750

    5.FY 1989$7,738,000$7,741,000$7,808,000$4,546,000$27,833,000252$9,549,675$9,553,377$9,636,063$5,610,341$34,349,456

    6.FY 1990$6,516,000$9,026,000$9,123,000$2,241,000$26,906,000259$7,824,232$10,838,170$10,954,645$2,690,931$32,307,977

    7.FY 1991$6,917,000$4,004,000$10,153,000$3,727,000$24,801,000262$8,210,637$4,752,840$12,051,844$4,424,034$29,439,355

    8.FY 1992$4,750,000$3,224,000$8,388,000$992,000$17,354,000261$5,659,962$3,841,625$9,994,897$1,182,038$20,678,521

    9.FY 1993$4,931,000$3,199,000$8,630,000$2,458,000$19,218,000272$5,638,018$3,657,680$9,867,390$2,810,434$21,973,522

    10.FY 1994$6,315,000$6,986,000$13,154,000$6,165,000$32,620,000274$7,167,755$7,929,365$14,930,270$6,997,500$37,024,891

    11.FY 1995$8,942,000$4,580,000$13,894,000$7,715,000$35,131,000286$9,723,643$4,980,350$15,108,510$8,389,388$38,201,892

    12.FY 1996$10,294,000$7,491,000$16,870,000$9,239,000$43,894,000293$10,926,396$7,951,198$17,906,382$9,806,584$46,590,560

    13.FY 1997$10,373,000$9,413,000$21,097,000$8,447,000$49,330,000287$11,240,429$10,200,150$22,861,209$9,153,369$53,455,157

    14.FY 1998$11,314,000$10,684,000$13,934,000$5,144,000$41,076,000298$11,807,564$11,150,081$14,541,859$5,368,403$42,867,906

    15.FY 1999$15,092,000$13,497,000$18,507,000$10,410,000$57,506,000300$15,645,373$13,991,890$19,185,590$10,791,700$59,614,553

    16.FY 2000$14,878,875$20,824,583$21,064,621$11,732,000$68,500,079299$15,476,020$21,660,352$21,910,024$12,202,849$71,249,246

    17.FY 2001$11,244,000$25,525,000$18,657,000$10,016,000$65,442,000311$11,244,000$25,525,000$18,657,000$10,016,000$65,442,000

    18.FY 2002$11,275,000$26,499,000$18,715,000$9,104,000$65,593,000319$10,992,241$25,834,448$18,245,658$8,875,687$63,948,034

    19.FY 2003$12,179,673$25,874,650$20,470,803$14,935,395$73,460,521326$11,619,258$24,684,098$19,528,895$14,248,184$70,080,435

    20.FY 2004 Budg$12,636,640$16,234,361$18,441,659$5,260,547$52,573,207$12,636,640$16,234,361$18,441,659$5,260,547$52,573,207

    21.FY 2005 proj$13,167,153$26,361,988$20,570,424$7,940,850$68,040,415

    22.FY 2006 Proj$13,677,253$27,307,275$21,393,232$8,371,600$70,749,360

    23.FY 2007 Proj$14,172,960$25,882,550$21,740,859$8,723,600$70,519,969

    24.FY 2008 Proj$14,537,896$27,169,681$21,873,238$7,646,100$71,226,915

    25.

    20 yr Average$9,944,370$11,659,402$14,229,875$6,461,615$42,295,262

    10 yr Average$11,822,919$16,062,259$18,165,108$9,200,294$55,250,581

    5 yr Average$12,442,838$22,991,519$19,469,817$10,209,588$65,113,761

    FY 1985-1993$74,343,204$65,579,455$89,792,416$31,064,362$260,779,437Average$11,104,960$10,103,830$15,248,475$6,612,022$43,991,592

    FY 1994-2003$111,907,548$151,374,233$176,363,424$92,907,395$532,552,600

    FY 2002-2006$62,935,719$122,277,274$99,591,118$45,612,392$330,416,503$9,204,149

    Total$249,186,470$339,230,961$365,746,959$169,584,150$1,123,748,539

    Data

    0

    0

    0

    0

    FY 1994-2001

    PHAHandy Whitmand Index 1/1/2001 South AtlanticTotal Distribution PlantJan 1 or entire Year1973 = 100

  • Current Gaps - PrioritizationCurrent process is perceived to be unreliableIn March 2003, began implementation of the EPRI Project Prioritization toolGoals:Model All Distribution Capital and O&M ProjectsValue projects using multiple attributes and Common ScaleDetermine measurements and weightsInitial Model Spring 2004 - T&D Projects onlyEnd result -> prioritized project list by value

    The Power Of Greater Nashville

  • Project Prioritization

    The Power Of Greater Nashville

    _1137236387.doc

  • Current Gaps - Work Mgmt.Mainframe legacy system installed in 1989Purchased integrated system in 2002 (Mincom)Work Management, Finance, Supply ChainExternal consultant facilitated Best Practice process definitionsPlanned Go-Live is July 1, 2004Goals:Enable one view of all workImprove ability to prioritize and manage workImprove project management Reduce overall cycle time for work lifecycleProvide accurate tools for estimation and designEnsure that resources are at the right place at the right time

    The Power Of Greater Nashville

  • Work Management

    The Power Of Greater Nashville

  • Current Gaps - Asset Mgmt.No existing system or formal processEPRI recommendationProcess consultant recommendationNew work management system will provide necessary data and support system (Equipment Register)

    The Power Of Greater Nashville

  • Current Gaps - Asset Mgmt.Manage the AssetsMaintenancePlanningBudgetingConstructionPlanningStandardsOther WorkPlanningSystemPlanning

    The Power Of Greater Nashville

  • Current Gaps - Asset Mgmt.

    The Power Of Greater Nashville

  • Current Gaps - Asset Mgmt.

    The Power Of Greater Nashville

  • Current Gaps - Asset Mgmt.Goals:Improve information on health of assetsImprove ability to compare and prioritize capital workImprove project management Develop consistent maintenance programsImprove linkage between budgeted projects and actual work performedBenefits realizationImproving quality of asset dataCoordination of repair/replace decisionsImprove short and long term budgetingImprove standards and estimating process

    The Power Of Greater Nashville

  • The FutureWe striving for...More integration of and proficiency with tools and systemsMore public involvement in the planning processMore accurate SCADA and OMS dataMore real time integration with SCADAUse of the Equipment Register to capture costs and operating statistics by circuit and equipmentBetter communication of the benefits and risks of proper T&D planning and construction to all of our stakeholders

    The Power Of Greater Nashville

  • Future Integration PlansOMS(CADOPS)GISSCADADistributionPlanningTransmissionPlanningSubstationForecastReliabilityPlanningSystemAutomationCISCommon Data BaseSystemForecastVarious InputsMobile Data/AVLOther Operational ApplicationsEquipmentRegister

    The Power Of Greater Nashville

  • Thank You!

    The Power Of Greater Nashville