the regulatory framework for the eu integration of offshore wind siobhán carty, ofgem
DESCRIPTION
The regulatory framework for the EU integration of offshore wind Siobhán Carty, Ofgem. Wednesday 16 September 2009, 11.00-12.30. Agenda. Legislative context Impact on regulatory regime for wind Great Britain’s offshore regime Challenges in developing an offshore grid - PowerPoint PPT PresentationTRANSCRIPT
The regulatory framework for the EU integration of
offshore wind
Siobhán Carty, Ofgem
Wednesday 16 September 2009, 11.00-12.30
2
Agenda
• Legislative context– Impact on regulatory regime for wind
• Great Britain’s offshore regime
• Challenges in developing an offshore grid
• What are we doing to meet the challenge?
3
Legislative context – impact on regulatory regime for wind…?
• Third package
• Green package
• 2nd Strategic Energy Review
Competitive markets
Security of Supply
Sustainability
EU energy
markets
Changes made at EU will have an important impact for the regulatory regime for wind, especially off-
shore wind.…
4
For the future – pan-European offshore wind farms…?
• North-Sea offshore grid– interconnect
national electricity grids in North-West Europe together
Such projects will play an important role. However, certain issues will need consideration by
regulators and market players for them to work.
Source: www.scotland.gov.uk
5
Great Britain’s offshore transmission regime (1)
Offshore Platform
Offshore Transmission Owner (OFTO)Onshore TO Generator
Connection to onshore network
132 kV Cable 33 kV Inter Array Cables
Onshore Substation
•Key enabler of offshore wind and 2020 targets.
•“OFTO” will be awarded licence that guarantees a 20 year revenue stream. It will design, finance, construct, own and manage offshore transmission assets.
6
Great Britain’s offshore transmission regime (2)
• Key benefits of the regime– For Generators
• Delivers cheaper and more timely offshore grid connections• Focused on generator’s requirements• Flexibility for future offshore generation needs
– For OFTOs • Encourage innovation through competition and enable new
entrants to compete in the market• Long term regulatory certainty and light-handed regulation• Low risk – OFTO protected against generator failure and
credit risk
7
Great Britain’s offshore transmission regime (3)
- Facilitates the development of offshore networks
Point-to-point connections
•Generator-specific connections
Towards an integrated network
•Scope to have more than one onshore connection point; and
•Allows for interconnection of platforms – organic development towards an
integrated offshore network.
Tender stages for enduring regime expected to commence in 2011 –
some further consultation expected.
8
Challenges in developing offshore grids (1)
• Differing support schemes for renewables; and
• Different regulatory grid treatment across Member States, for– Connection; – Charges; and – Grid reinforcement.
This may influence the incentives wind generators have on where to locate – this is especially relevant
to offshore grid projects.
9
Challenges in developing offshore grids (2)
• Current market arrangements may not best facilitate wind deployment– Long gate-closure times; and – Penalties for imbalance.
Harmonisation across the EU is not necessarily the answer – shorter gate-closure times is important for
wind.
10
Challenges in developing off-shore grids (3) - conclusions
• Different regimes is not necessarily a problem.
• However, where arrangements represent barrier, then consideration needs to be given to their effectiveness.
11
What are we doing to address the challenges?
• As Ofgem, – GB offshore transmission regime; – “Project Discovery” – review of the medium
term outlook for GB’s security of supply.
• As part of CEER/ERGEG– Development of the new European network
codes for the 3rd package; – Input into the Regional
Initiatives; and – The EU Agency.
Questions? Comments?
Siobhán Carty, Regulatory Economist, OFGEM, Tel +44 20 7901 7112
13