the spe foundation through member donations and a ... · rig and well design considered...
TRANSCRIPT
![Page 1: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/1.jpg)
1
Primary funding is provided by
The SPE Foundation through member donations and a contribution from Offshore Europe
The Society is grateful to those companies that allow their
professionals to serve as lecturers
Additional support provided by AIME
Society of Petroleum Engineers Distinguished Lecturer Programwww.spe.org/dl
![Page 2: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/2.jpg)
Luiz Alberto S. Rocha, Ph.D.
Petrobras SA
Society of Petroleum Engineers Distinguished Lecturer Programwww.spe.org/dl
A Methodology to Design Exploratory Wells
2
![Page 3: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/3.jpg)
3
Topics• Introduction
• Well Management Process– Matrix of Criticality
– Processes• Engineering
• Operation
• Safety
• Case Study
• Conclusions
![Page 4: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/4.jpg)
4
Introduction
Depletion of old field
New opportunities
New frontiers
High cost of the drilling rigs
Expensive Wells
Loss of the well
Cost Reduction
Underestimate the well design
Reconstruct a new well
Unexpected Increase in
Cost
![Page 5: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/5.jpg)
Breve HistóricoWild Cat Wells
/ CountryYear Safety Related Problems
Well-1(Country 1)
Shallow Water
1
Actual pore pressure higher than predicted pore pressure �
kick
Rig and well design considered inappropriate
Well reach TD but time and cost much higher than forecast
Lack of methodology and “well robustness” was low
Well-2(Country 1)
Shallow Water
2
Kick. No barite during the well control operation.
Rig and well design considered inappropriate
Well did not reach TD
Lack of methodology and “well robustness” was
considered low
Well-3(Country 2)
Deepwater
2
Lithology: predicted and actual did not match. Temperature
much higher than expected. No pore pressure specialist at the
rig site. Well did not reach TD
“Well robustness” was considered low
Well-4(Country 3)
Deepwater
3
New systematic for designing wells
Great emphasis on reducing geopressure uncertainties
Three independent geopressure studies were performed
Well reached TD within the forecasted time and cost 5
![Page 6: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/6.jpg)
6
Objective
Well Management Process
(WMP)
based on
Petrobras Best Practices
The final goal of the WMP is to construct the well that safely reaches its targets within the
expected time and cost
![Page 7: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/7.jpg)
7
Well Management Process
Planning Execution
MATRIXOF
CRITICALITY
SUPPORT
WELL ENGINEERING
WELL DESIGN
WELL OPERATION
EXECUTIONLOGISTICS
SAFETY
Timeline
![Page 8: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/8.jpg)
Matrix of Criticality
8
![Page 9: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/9.jpg)
9
Matrix of Criticality
Matrix of
Criticality
Well
Complexity
Index
Well
Robustness
Extra
Casings
Mitigating
Actions
![Page 10: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/10.jpg)
10
Well Complexity
The Well Complexity Index (WCI) is usedto quantify the geological, operational andlogistics risks associated to the drilling of awell.
Well Complexity Index
1 2 3 4
![Page 11: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/11.jpg)
11
Well Complexity Index (WCI)
WCI
Logistics
Water Depth
Pore and Fracture
Pressures
Temperature
TVD
Numberof Well Drilled
in the Area
Shallow Hazards
Etc.
![Page 12: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/12.jpg)
12
Well Robustness
Well Robustness (WR) is the combinationof the number of casing strings and themitigating actions that the company mustfollow to guarantee the success of the well.
Well
Robustness
Number of
Extra Casings
A 0
B 1
C 2
D 3
More
Robust
![Page 13: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/13.jpg)
13
Well Robustness versus Extra Casings
Fracture
Gradients
PoreFracture
MarginDe
pth
De
pth
KT
Fracture
Gradients
PoreFracture
MarginDe
pth
De
pth
KT
Casing shoes based on
Company Procedures
Example
WR = C
Two Extra Casing Strings
Two Extra Casings
Due to WR = C
![Page 14: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/14.jpg)
14
Well Robustness versus
Mitigating Actions
Mitigating Actions for Different Well Robustness
Item A B C D
Seismic for
GPNo No Yes Yes
GP Models 1 1 2 3
Real Time
GP- - 24 / 7 24 / 7
Company
Man
Experience5 years 5 years 15 years 20 years
WR = CGP - Geopressure
![Page 15: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/15.jpg)
15
Well Robustness versus
Mitigating Actions
Mitigating Actions for Different Well Robustness
Item A B C D
Lost Circulation
- -
Specific
DT
prepared
Specific
DT
prepared
WR = CDT – Decision Tree
![Page 16: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/16.jpg)
16
Example of Decision Tree
PROCEDURE 2
((WELL CONTROL WITH CATASTROPHIC LOSSES AND
POSSIBLE FLOW CELL)
WITHOUT
PROCEDURE 2
((WELL CONTROL WITH CATASTROPHIC LOSSES AND POSSIBLE FLOW CELL)
1.Close middle pipe ram to prevent colapse of the riser and to reduce the volume of mud lost to
the formation;
2. Read PTT (Acoustic sensor above the middle pipe ram) to define fluid level in the riser and
the volume lost to the formation;
3. Read PTT (MUX sensor under middle pipe ram) to define: equivalent pressure in the
probable lost circulation or permeable zones; static level in the wellbore.
4. Compare BHP with Pore Pressure at the Loss Zone
5. Pump 1-5 bpm through the annulus 2.0 times the annular volume between from the top of
reservoir till the loss.
PROCEDURE 2
![Page 17: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/17.jpg)
17
Decision Tree
![Page 18: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/18.jpg)
RobustnessC
om
ple
xity Index
WD = Well Design
Drilling Allowed
Drilling with Restrictions
No Drilling
4
3
2
1
DCBA
4
3
2
1
DCBA
18
Matrix of Criticality
WD
4C
![Page 19: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/19.jpg)
Well Engineering Process
Well Design and Engineering Support
19
![Page 20: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/20.jpg)
Well Engineering Process
Detailing Phase
Conceptual Phase
Engineering Phase
Execution Phase
20
![Page 21: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/21.jpg)
21
Well Safety Process(WSP)
The main goal of the WSP is to guarantee that all Company Safety Requirements are
implemented in all phases of the project.
(from planning to execution)
![Page 22: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/22.jpg)
22
Well Safety Process
• Operator Standards and Best Practices
• Well Control Specialists
• Prevention and Response
• Well Control Emergency Response Plan
– Implemented to guarantee that the entire drilling team is well trained
![Page 23: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/23.jpg)
Well Control Emergency Response Plan(WCERP)
The Operator Must Be Prepared for Any of
These Situations ...
Small Kicks ………….…Large Kicks………………..Blowout
Complex well control situation requiring actions such as
direct intervention, relief well or capping
Simple well control
situation requiring only the use of the
Drillers Method
Level 1 ………….………. Level 2 ………………..… Level 3
![Page 24: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/24.jpg)
Well Control Emergency Response Plan(Blowout Control)
• Direct Intervention
• Relief Well
• Capping
The Operator Must Be Prepared for This ...
• Simple small water
kick
(Level 3 Situation)
![Page 25: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/25.jpg)
Relief
Well
![Page 26: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/26.jpg)
Capping
![Page 27: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/27.jpg)
Capping
![Page 28: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/28.jpg)
Capping
![Page 29: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/29.jpg)
The Black Sea ProjectThe Black Sea Project
Well
Complexity Index
Well
Complexity Index
4 C
Well
Robustness
Well
Robustness
29
![Page 30: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/30.jpg)
30
Black SeaTurkey
Petrobras HeadquartersRio de Janeiro
Brazil
The Black Sea ProjectThe Black Sea Project
![Page 31: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/31.jpg)
The Black Sea ProjectThe Black Sea Project
31
![Page 32: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/32.jpg)
32
Characteristics of Ultra Deepwater
Wells of Complexity 4
• Small operational window (pore and fracture pressures very close)
• High rate of penetration (ROP)
• Long time for tripping
• Tendency to display high non productive time (NPT)
• Generally NPT higher than 40% (GoM)
![Page 33: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/33.jpg)
33
Black Sea Challenges
• Drilling
– Expected shallow gas intervals
– Long abnormally pressurized intervals
– Low fracture pressure gradients
– Expected severe lost circulation zones
– Great potential for false kicks
– Risk of gas migration through the riser
![Page 34: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/34.jpg)
Well Engineering Process
Well Design
34
![Page 35: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/35.jpg)
35
Geopressure: The Black Sea Well Interval Velocity acquired
for Pore Pressure Purpose
Dep
th (
m)
Lateral Transfer
Fault
Under
compaction
Abnormal Pore
Pressure
Mechanisms
Abnormal
Pressure
Interval
Shallow
Gas
DT (us/ft)
![Page 36: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/36.jpg)
36
Mitigating Actions to Reduce
Geopressure Related NPT
• Shallow Intervals (above surface casing)
– Conduct Shallow Hazard Study
• Deeper Intervals (below surface casing)
– Use seismic velocity adjusted for pore pressure
purpose only
– Identify abnormal pore pressure mechanisms
– Conduct independent estimates
– Create scenarios using different interpretations
![Page 37: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/37.jpg)
37
Geopressure: Independent StudiesD
epth
Narrow Operational Window
Pore
Fracture
Overburden
Pore
Fracture
Overburden
Pore
Fracture
Overburden
Depth = D
![Page 38: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/38.jpg)
Well Design Considerations
Shallow Gas Interval
Kick Tolerance
Lithology
Loss Circulation
Differential Pressure
Targets
WCI = 4
WR = C38
![Page 39: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/39.jpg)
Well Operation Process
Logistics
39
![Page 40: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/40.jpg)
40
Well Operation: Logistics
– Plays primary role in well operation
– Frontier area with no offshore infrastructure
– Mobilization of the drilling rig to the Black Sea
• Challenge: Pass the rig below the existing bridges of
the Bosphorus Straits, Turkey
![Page 41: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/41.jpg)
Drilling Rig - Mobilization
• Rig received and
derrick disassembled
in Olen, Norway;
• Rig received and
derrick disassembled
in Olen, Norway;
Norway
Turkey
EUROPE
41
![Page 42: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/42.jpg)
Drilling Rig - Mobilization
• Rig received and
derrick disassembled
in Olen, Norway;
• Rig navigated more
than 4,000 nm to the
Black Sea;
• Rig received and
derrick disassembled
in Olen, Norway;
• Rig navigated more
than 4,000 nm to the
Black Sea;
Norway
Turkey
EUROPE
Bosphorus straits
42
![Page 43: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/43.jpg)
Drilling Rig - Mobilization
• Rig received and
derrick disassembled
in Olen, Norway;
• Rig navigated 4,130 nm
to the Black Sea;
• Rig passed underneath
the existing bridges of
the Bosphorus Straits;
• Derrick reassembled in
the Black Sea, Turkey.
• Rig Mobilization = 117
days
• Rig received and
derrick disassembled
in Olen, Norway;
• Rig navigated 4,130 nm
to the Black Sea;
• Rig passed underneath
the existing bridges of
the Bosphorus Straits;
• Derrick reassembled in
the Black Sea, Turkey.
• Rig Mobilization = 117
days
Norway
Turkey
EUROPE
Bosphorus straits
43
![Page 44: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/44.jpg)
44
Well Operation: Logistics
Drilling Rig Mobilization
Bosphorus Straits
![Page 45: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/45.jpg)
Well Operation and Engineering Processes
Execution and Engineering
Support
45
![Page 46: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/46.jpg)
46
Execution and Engineering
Support
• Mitigating Actions
– Special procedure created to drill the shallow gas
interval
– All operation planned in Advance
– Decision Trees developed to mitigate problems
for each operation
– Robust Real Time Surveillance System
implemented to increase safety and reduce NPT
![Page 47: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/47.jpg)
Decision
Legend
Robust Real Time SurveillancePore Pressure Specialists
(Aberdeen)
24 / 7
Decision Support CenterHead Quarters
(Rio de Janeiro)
Operational
Office
(Ankara)
Rig Site
(Black Sea)
24 / 7
Technical Support
Pore Pressure
Data
47
![Page 48: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/48.jpg)
Robust Real Time
Surveillance
48
![Page 49: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/49.jpg)
Results
49
![Page 50: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/50.jpg)
50
Results
Fact / Incidents Observation Lesson Learned
Shallow gas zone drilled without
incidents
Good well planning. Adequate Well
Robustness
Most of the expected problems
(kicks, losses, etc.) were
successfully controlled.
Mitigating actions, such as
the use of Decision Trees,
were effective
Adequate Well
Robustness
All planned casing were run due
to well conditions
Extra casing available as
needed
Adequate Well
Robustness
Kick occurred while drilling a fault
zone
Geological issue Improve geologic
prognosis for drilling
purpose. Improve well control response.
![Page 51: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/51.jpg)
51
DE
PT
H (
m)
∆T (us/ft) GRADIENTS (ppg)
Seismic
Trend Line
Sonic Trend
Line
Seismic
Sonic
Sonic Pore
Pressure
Fracture
Pressure
ECD
MDT
Difference between Prognosis and Actual at the Peak = 6.6 %
Results
Kick
![Page 52: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/52.jpg)
52
More Results
Project in Numbers Planned Actual
Total depth (meters)5,525 /
(18,127 ft)
5,531 /
(18147 ft)
Duration (days) 152 162
NPT (%) 40 35
Number of casing strings 8 7
PPGI = 1.066 (at the peak)
*
* Considered unplanned operations (VSP, MDT, etc.)
PPGI = Pore Pressure Gradient Index = Actual PP / Expected PP
![Page 53: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/53.jpg)
More Results
53
The Well Management Process was applied in other three wells drilled in three
different countries
All wells were drilled without major incidents, safely reaching their targets
within the expected time and cost
![Page 54: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/54.jpg)
54
Conclusions
• Petrobras Well Management Process hasproved to be effective as a managementmethodology
• Quantifying the right well complexity andwell robustness helped define the requiredresources to effectively reach the objectiveof the well (safety, time and cost)
• Mitigating actions used during the planningand the execution phases were alsovaluable
![Page 55: The SPE Foundation through member donations and a ... · Rig and well design considered inappropriate Well reach TD but time and cost much higher than forecast Lack of methodology](https://reader030.vdocument.in/reader030/viewer/2022040820/5e68434f561a6d3a51012ce9/html5/thumbnails/55.jpg)
The End
Questions?
55