the windfloat project - offshore renewablesatlantic pre-comercial phase the windfloat project lcoe...

31
The WindFloat Project WindFloat 2 MW Floating Offshore Wind WavEC Workshop 13 th of November, 2015

Upload: others

Post on 01-Feb-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

  • The WindFloat Project

    WindFloat 2 MW Floating Offshore Wind

    WavEC Workshop

    13th of November, 2015

  • The WindFloat Project 2

    1. Why Floating Offshore Wind?

    2. WindFloat Technology

    3. The WF1 Project (Demonstration Phase)

    4. WindFloat Atlantic (Pre-Commercial Phase)

    5. Conclusions

    Agenda

  • The WindFloat Project 3

    Why Floating Offshore Wind?

    Why Offshore Wind?

    • Higher wind resource and less turbulence

    • Large ocean areas available

    • Best onshore wind locations are becoming scarce

    • Offshore wind, including deep offshore, has the capacity to deliver large amount of energy

    Why Floating Offshore Wind?

    • Limited locations with shallow waters (mostly in the North Sea)

    • Most of the offshore wind resource is in deep waters

    • Unlimited installation sites available

    • Less restrictions for offshore deployments and reduced visual impacts

    • Enormous potential around the world: PT, Spain, UK, France, Norway, Italy, the Americas, Asia …

  • EDP INOV – Technology Development 4

    Deep offshore wind potential goes in line with the quality of the resource and the availability of areas to explore

    Deep Offshore Wind: Floating or Fixed?

    0 10 5 km

    EU15 Potential • Good offshore wind resource (load factor > 3.000h)

    • Offshore wind potential is mostly in transitional and deep waters(1) (~65 %)

    • Energy Potential >700 TWh (~220 GW)

    • Ports and docks available along European coast

    Portuguese & Spanish Potential • Continental shelf ends near the coast

    • Grid connection available near the coast

    • Limited Potential for water depths < 40m

    • 250 km of PT Costal Line suitable to be explored

    • Energy Potential in PT >40 TWh (~12 GW)

    • Energy Potential in SP >290 TWh (~98 GW)

    Depth (m) 0 - 30 40 – 200 +

    Offshore

    potential EU15 77 GW >140 GW

    Mean Wind speed (50m)

    European Bathymetry

    Depth (m) 0 - 30 40 – 200 +

    Offshore

    potential

    PT 2 GW >10 GW

    SP 18 GW >80 GW

    (1)Analysis limited to 100m water depths

    Source: Univ.de Zaragoza – Evaluación Potencial Energías Renovables (2007)

    Source: Greenpeace & Garrad Hassan 2004; IEA; Global insight;

  • EDP INOV – Technology Development

    Offshore wind technology is likely to follow Oil &Gas addressing the deep offshore wind challenges

    Deep Offshore Wind: Floating or Fixed?

    Monopiles

    • Basic extension of turbine tower w/ transition piece

    • Economically feasible in shallow water depths (10-30m)

    Jackets

    • Economically feasible in transitional water depths (30-50m)

    • Several jackets successfully installed at depths of less than 50m (Beatrice in 2006 was the first project to deploy at 45m)

    Other fixed (tripods, tripiles, gravity bases ,…)

    • Very limited experience

    • Similar depth limitations as jackets

    Floating

    • Expected economical feasibility in deep waters (50-?m)

    • Still limited experience

  • 6

    WindFloat is >2 years ahead in commercial deployment vs. most competitors

    State of development of selected floating turbine concepts

    Sem

    i-su

    bm

    ers

    ible

    Sp

    ar

    TLP

    Concept development Scale testing Full scale prototype Pre-commercial/Commercial

    WindFloat (US/PT)

    Mitsui (JP)

    Ideol(FR)

    HiPR Wind (EU)

    Mitsubishi(JP)

    Diwet (FR)

    Gusto (NL)

    Hywind(NO)

    Toda(JP)

    Japan Marine (JP)

    Nautica AFT (US))

    Sea Twirl (SW))

    Sway(NO))

    Gicon (GE))

    Blue H(GE))

    Pelastar (US)

    Iberdrola Etorgai (SP)

    Mitsui (JP)

    Source: Main(e) International Consulting, LLC

  • The WindFloat Project 7

    1. Why Floating Offshore Wind?

    2. WindFloat Technology

    3. The WF1 Project (Demonstration Phase)

    4. WindFloat Atlantic (Pre-Commercial Phase)

    5. Conclusions

    Agenda

  • The WindFloat Project 8

    The main characteristics of the WindFloat leads to High Stability even in rough seas

    The WindFloat Technology

    Turbine Agnostic

    • Conventional turbine (3-blade, upwind)

    • Changes required in control system of the turbine

    High Stability Performance

    • Static Stability - Water Ballast

    • Dynamic Stability - Heave Plates and active ballast system

    - Move platform natural response above the wave excitation (entrained water)

    - Viscous damping reduces platform motions

    • Efficiency – Closed-loop Active Ballast System

    Depth Flexibility (>40m)

    Assembly & Installation

    • Port assembly – Reduced risk and cost

    • No specialized vessels required, conventional tugs

    • Industry standard mooring equipment

  • The WindFloat Project 9

    The WindFloat…

    … requires NO PILLING

    …is structurally decoupled from seadbed

    …is independent from depth

    …is assembled and commissioned quayside

    …does NOT require high lift capacity vessels

    Due to the features of the WindFloat, the risk and cost of offshore works is significantly reduced

    The WindFloat Technology

    Reduced Risk and Cost

  • The WindFloat Project 10

    1. Why Floating Offshore Wind?

    2. WindFloat Technology

    3. The WF1 Project (Demonstration Phase)

    4. WindFloat Atlantic (Pre-Commercial Phase)

    5. Conclusions

    Agenda

  • EDP Inovação

    WindFloat Technology Roadmap Bringing the Technology from Prototype to Fully Commercial Farms

    11

    WF 1

    • 2MW Conservative Design

    • Verified Numerical Models

    • Operational Learning

    Pre-Commercial

    • Design Optimization

    • ~30 MW Windfarms with >6MW

    • Different sites and Turbines:

    Commercial

    • Fully Optimized

    • World Wide designs

    • LCOE Below market

    • Project Finance

    2MW

    +8MW

  • The WindFloat Project 12

    The Project is promoted by…

    …in a joint venture…

    …and counts with the support of…

    The WindFloat project was structured as a Joint Venture, WindPlus

    The WF1 Project (Prototype)

    WindPlus

    http://www.inovcapital.pt/index.php?PHPSESSID=2c0eb933e72bc2a50d1fc88ce6aba25b

  • The WindFloat Project

    The project followed a risk mitigation approach but…

    …the challenges were enormous…

    …project being done for the first time

    …Lack of offshore know-how in Portugal

    …different cultures involved(US, Denmark, Portugal, France)

    …Collaboration between two different industries that have never worked together (Oil & Gas and Wind Industry)

    … Standards & Rules for design exist but need to adapted

    13

    The development of the WindFloat project carried enormous challenges due to the lack of know-how in Portugal

    The WindFloat Project

  • The WindFloat Project 14

    The project was implemented under a tight scheduled

    The WindFloat Project

    Task Timeline

    Project Start

    Pre-FEED

    PDR

    FEED

    Turbine Selection

    Final Investment Decision

    Project Execution

    Detail Design

    Fabrication

    Offshore Installation

    Offshore Commissioning

    Testing and Monitoring

    Sep, 09

    Jan, 10

    Sep, 10

    Sep, 11 May, 11

    Nov, 11

    Dez, 11

    Ago, 13

    Sep, 11

    Sep, 11

    Project was completed in less than 2,5 years Fabrication completed in less than 9 months

    Significant space to improve project implementation schedule!

  • The WindFloat Project 15

    Workshop Fabrication of main components

    A. Silva Matos was the responsabilbe for the

    fabrication of the WindFloat

  • The WindFloat Project 16

    Pre-assembly of the columns

    outside the Dry-dock in Setúbal

  • The WindFloat Project 17

    Columns moved to Dry-dock

  • The WindFloat Project 18

    Dry-dock assembly

  • The WindFloat Project 19

    Mooring Pre-Lay in parallel

    with the fabrication

  • The WindFloat Project 20

    Turbine Installation in the Dry Dock using the

    shipyard’s gantry crane

  • The WindFloat Project 21

    Tow from Setúbal to Aguçadoura (~400 km) using the

    same vessel that was used for the mooring installation

  • The WindFloat Project 22

    Hook-up at final location

  • The WindFloat Project 23

    Energy delivery since December 2011!

    More than 16 GWh produced up today!

  • The WindFloat Project 24

  • The WindFloat Project 25

    1. Why Floating Offshore Wind?

    2. WindFloat Technology

    3. The WF1 Project (Demonstration Phase)

    4. WindFloat Atlantic (Pre-Commercial Phase)

    5. Conclusions

    Agenda

  • The WindFloat Project 26

    • Total capacity: ~25MW capacity, (3 or 4 units equipped with 8MW or 6MW)

    • Location: 20 km off the coast of Viana do Castelo, in water depth of 85-100m

    • Interconnection: connected to the transport grid (60kV). No offshore substation

    • Construction: several shipyards options available close to final location. Turbine installation quayside

    • Floating structure certification: designed for 25 years, certified throughout design, construction and installation by ABS, an independent party

    • Strong Institutional Support:

    - EU: NER 300

    - Portugal: Feed-in Tariff, APA

    Pre-Commercial Phase – WindFloat Atlantic

  • The WindFloat Project 27

    Second Generation currently in late stages design for real projects proving considerable reduction in Cost of Energy

    Larger turbines (x3-4)

    Design life extension (x5)

    Proportionally smaller

    platform

    Structural optimizations

    Equipment improvement

    Accessibility

    Mooring improvements

    Installation improvements

    Full Class Certification

    WF1 Prototype

    WF Atlantic Pre-comercial phase

  • The WindFloat Project

    LCOE competitive with currently commercial technology such as Jackets and the most cost effective in deep waters

    126 129 132 129

    0

    20

    40

    60

    80

    100

    120

    140

    Jacket 45m WF 45m Jacket 60m WF 60m

    NREL Feb ‘14

    Source: GL / GH, December 2012 NREL, Feb 2014

    Target:

    100

    €/MWh

    28

    Levelized Cost of Energy (€/MWh)

    Water Depth

  • The WindFloat Project 29

    1. Why Floating Offshore Wind?

    2. WindFloat Technology

    3. The WF1 Project (Demonstration Phase)

    4. WindFloat Atlantic (Pre-Commercial Phase)

    5. Conclusions

    Agenda

  • The WindFloat Project

    Final Remarks

    30

    1

    2

    3

    Floating is already proven technology, and is now proving its financial and economic viability

    Reduction of Cost and Risk => Addressing the industry’s challenges while enabling it to reach its full potential

    Already several Pre-Commercial Projects ongoing worldwide, expecting to be deploying commercially in the marketplace by 2018

  • The WindFloat Project 31

    Thank you!