theme-9: field demonstration india update · 2020-07-20 · presenter: suresh srivastava, iit...

26
1 UI-ASSIST: VIRTUAL WORKSHOP Presenter: Suresh Srivastava, IIT Kanpur JULY 21-24, 2020 THEME-9: FIELD DEMONSTRATION INDIA UPDATE

Upload: others

Post on 29-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

1

UI-ASSIST: VIRTUAL WORKSHOP

Presenter: Suresh Srivastava, IIT Kanpur

JULY 21-24, 2020

THEME-9: FIELD DEMONSTRATION

INDIA UPDATE

2

Theme-9: Co-leads and Members from India

Organization First Name Last Name RoleIIT Kanpur Saikat Chakrabarti Co-LeadIIT Kanpur Suresh Srivastava Co-LeadIIT Kanpur Ankush Sharma Co-Lead

NETRA Subrata Sarkar Co-Lead

TERI Alekhya Datta Co-LeadIIT Kanpur Santanu Mishra MemberIIT Kanpur Vinay Tiwari Member

TERI Shashank Vyas MemberNETRA Subrata Sarkar MemberNETRA Shish Pal Singh MemberPGCIL Rajesh Kumar MemberPGCIL Manish Kumar Tiwari MemberBRPL Abhishek Ranjan MemberUPPCL Chief Engineer

Distribution

DVNNL Kanpur Zone

(Rajendra Prasad)

Member

3

Theme 9: Objectives

Theme 9

Field

Demonstration

0101Rural Pilot by IIT Kanpur and

DVVNL/UPPCL

Semi-Urban Pilot by IIT Kanpur

inside IITK Campus

Urban Pilot by IIT Kanpur

inside IITK Campus

02

03

04Rural Pilot by NETRA

05Urban Pilot (Feeder,

Residential and Institutional

level) By TERI and BRPL

Rural Distribution Pilot

at NRECA

02Semi-Urban Distribution

Pilot 1 at WSU

03Semi-Urban Distribution

Pilot 2 at TAMU

04Urban Distribution

Pilot 1 at Spokane, WA

05Urban Distribution

Pilot 2 at Philadelphia, PA

4

INPUTS FROM OTHER THEMES: EXAMPLE

Theme-3

Storage and Sizing

Charge/discharge

Control

Theme-4

Primary and Secondary

controlsProtection

Theme-5

Communication options

Cyber measures

Theme-6

DSO functions (SE, Volt/Var, Opt.

operation, Forecasting,

etc.)

Theme-7

DSO regulation

aspect

Theme-10

Social and load survey (baseline)

Site and technology selection

Basic engineering and tendering

Detailed engineering (drawing, documents,

and operating philosophy

Installation, testing and commissioning

Field Demonstration Pilots

5

Field Demonstration Pilots by IITK, DVVNL/UPPCL

AC Microgid Rural pilot by IIT Kanpur and UPPCL covers two village hamlets (of

about 85+75 houses) in Kanpur (100 kWp SPV, 100kW, 200 kWh Li-Ion Battery

Storage and Biomass-appx. 30 kW, six solar pumps )

The Semi-urban Pilot by IIT Kanpur inside campus covers 30 single storey houses

in two lanes (30x 5kWp roof top SPV, 70 kW 140kWh Li-Ion and 50kW, 100kWh

Redox Flow Battery Storage#) and two EV Charging stations (each having single

phase Bharat chargers, 3-phase Slow AC charger and Fast DC charger, fed from 25

kWp SPV & Grid, 40 kWh Li-ion battery to emulate EV#).

Urban pilot inside IITK campus covers two housing towers (2x25 kWp SPV,

2x50kWh Li-ion Battery Storage) and an academic building with Thermal Energy

Storage (TES) system.

DSO-ADMS functions to be integrated at IITK SCADA Control Center.

# Alternate Technology/EVs being considered due to excessive cost quoted.

6

Contracts for Field Demonstration Pilots by IITK

I. Thermal Energy Storage (TES) System 545 TRHR (Urban Pilot):

Awarded to M/s Kehems Engineering Pvt. Ltd, Indore, MP in April 2019.

After review of engineering documents, installation work completed in first week of March 2020.

Commissioning held up due to COVID 19 lockdown (delayed and likely in July 2020).

II. ADMS Development and Implementation of DSO Functions: (Common to all pilots)

Awarded to M/s Synergy Systems & Solutions, Faridabad, Haryana in Aug. 2019 (also industry

partner).

Functional Design Specifications (FDS) finalized in April 2020. Two of the ADMS functions developed

by consortia partners being coded by M/s Synergy for implementation.

III. Rural, Semi-urban and Urban Smart Grid Pilots (complete work except above two):

Awarded to Siemens Ltd., Gurugram, Haryana on 31 December 2020.

Jointly finalized the distribution, protection, communication and operating philosophy etc.

Majority of the electrical, civil, microgrid controls design and drawing documents reviewed.

Site mobilization took place in Mid March 2020, work could not start due to COVID 19 lockdown.

Scheduled completion 30 June 2020, but delay of about 4-5 months expected.

7

Few More Highlights of the Rural Microgrid Pilot

Social survey was conducted in the beginning. Apart from electricity,

villagers urgently need irrigation pumping system. The distribution system

is part of contribution of DVVNL/UPPCL to this project.

DVNNL completed electrification work under ‘Saubhagya Yojana’ of the

GoI and DVVNL has installed transformers in both the hamlets.

There were objections in the allocation of land given by Gram Panchayat.

Now with their concurrence, the allocated land is converted into free land

and officially given for the pilot set up.

A local society named “Chhaba Niwada-Bargadiyapurwa village

Renewable Energy Promotion Society” approved by relevant authority.

DVVNL in principle agreed for net metering billing at one point

(transformer LV point) to the village society, that will manage the

microgrid.

Data from smart meters, placed in the transformer feeders, are being

recorded at IITK SCADA control center. Base case profiling being done.

8

9

20.01 kW

0

5

10

15

20

25

Loa

d (

kW

)

Time 0-24 hrs

Load Profile: Bargadiya Purwa Village

Hamlet

on 27 May 2020

LOAD PROFILE OF BARGADIYA PURWA VILLAGE HAMLET

1510

1272

1094

1469

2098

353

524553

800

11011158

2010

2207

2513

0

500

1000

1500

2000

2500

3000

Co

nsu

mp

tio

n (

kW

h)

Month - Year

Monthly Consumption of Village Hamlet Bargadiya Purwa

In 2019, Peak load for short period on 2nd

June was 12.18 kW. Smart meter in

other Chhabba Niwada hamlet not

connected due to problem in CT.

10

GROUND BREAKING CEREMONY ON 17 JUNE 2020 TO START FIELD WORK AT

CHHABBA NIWADA & BARGADIYA PURWA

Chief Engineer DVVNL/UPPCL

Lady Gram Pradhan and her Husband

Siemens Site Engineers

Recent Activities in Harnoo Village Kanpur Rural Pilot

11

SOLAR WATER PUMP INSTALLATION & BOUNDARY FOUNDATION WORK-

CHHABBA NIWADA – END JUNE 2020*

*Latest Update:•3 solar water pumps already installed & tested. •Civil work for biomass being started in BargadiyaPurwa.

12

Semi-Urban Field Pilot inside IIT Kanpur

• Two lanes inside campus (lanes 32 and 33) having single

storey houses were identified for Semi-Urban pilot.

• Sites for rooftop PV (30 x 5 kWp) , centralized storage at

two places (140 kWh Li-ion and 100 kWh Flow* BESS) in

the lanes, and EV charging stations (each with 25 kWp PV

and 40 kWh Li-ion BESS*) were planned.

* dropped from tender due to very high cost. Request sent

for alternate technology and EVs.

• Data from smart meters already placed in the two

feeders is being used for load profiling at SCADA

control center.

• Operation of the microgrid through Microgrid Controller

Being provided by M/s Siemens.

13

Semi-Urban Field Pilot inside IIT Kanpur

RTU

11kV/415V

To main substation

415 V Power Line

H.No. 15 KW

Communication channel

Auxilary SWNO

70kW, 140 kWhHybrid Inverter with

battery storage

Main SW NC

.

.

.

.

50kW, 100 kWhHybrid Inverter with

battery storage

H.No. 175 KW

H.No. 195 KW

H.No. 35 KW

H.No. 25 KW

H.No. 185 KW

H.No. 205 KW

H.No. 45 KW

H.No. 15 KW

H.No. 35 KW

H.No. 75 KW

H.No. 95 KW

H.No. 105 KW

H.No. 85 KW

H.No. 45 KW

H.No. 25 KW

FP-25

FP-28

connected to nearest feeder pillar using

customized AC-DB panel with communicable

MCCBs

connected to nearest feeder pillar using

customized AC-DB panel with communicable

MCCBs

ACB-2 630A

CT CORE-2, 600/5ACL 5P20, 10VA

ACB-3 630A

ACB-1 630A

CT CORE-1, 600/5A

CL 0.5S, 10VA

ACB-B NC 800A

ACB-4630A

CT CORE-1, 300/5ACL 5P20, 10VA

CT CORE-1, 300/5ACL 5P20, 10VA

CT CORE-2, 300/5A

CL 0.5S, 10VA

CT CORE-2, 300/5A

CL 0.5S, 10VA

50/51 + 50N/51NRelay

SMART METER

SMART METER

50/51 + 50N/51NRelay

OUTGOING-1LANE-32

OUTGOING-2LANE-33

67+67N 50/51+50N/51N

Relay

SMART METER

ACB-A1600A

11kV/415V1000kVA

Transformer

No voltage sensing & input to hybrid inverter

Outdoor free standing type degree of

protection: IP55

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

----No voltage sensing

CT CORE-1, 300/5ACL 5P20, 10VA

CT CORE-2, 300/5A

CL 0.5S, 10VA

SMART METER

50/51 + 50N/51NRelay

-----No voltage sensing

415V BUS

From 11kV Switch gear

- - - - -- - - -

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - -

3½ core x 240sq.mm AYFY CABLE

Existing ( Spare to be used )

Existing 415V Switch gear in

Sub Station No. 3

415V ACB Panel (New) In Sub Station No. 3

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

415V, 630A Bus Bar

Spare

----No voltage sensing

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

IIT Kanpur Sub Station No. 3Modifications in feeders to

lanes 32 & 33

EV charging stations (2 Nos) inside IITK

Petrol pump complex and near taxi stand.

14

52.8041 kW

0

10

20

30

40

50

60

00

:00

:00

00

:25

:30

00

:51

:00

01

:16

:30

01

:42

:00

02

:07

:30

02

:33

:00

02

:58

:30

03

:24

:00

03

:49

:30

04

:15

:00

04

:40

:30

05

:06

:00

05

:31

:30

05

:57

:00

06

:22

:30

06

:48

:00

07

:13

:30

07

:39

:00

08

:04

:30

08

:30

:00

08

:55

:30

09

:21

:00

09

:46

:30

10

:12

:00

10

:37

:30

11

:03

:00

11

:28

:30

11

:54

:00

12

:19

:30

12

:45

:00

13

:10

:30

13

:36

:00

14

:01

:30

14

:27

:00

14

:52

:30

15

:18

:00

15

:43

:30

16

:09

:00

16

:34

:30

17

:00

:00

17

:25

:30

17

:51

:00

18

:16

:30

18

:42

:00

19

:07

:30

19

:33

:00

19

:58

:30

20

:24

:00

20

:49

:30

21

:15

:00

21

:40

:30

22

:06

:00

22

:31

:30

22

:58

:00

23

:23

:30

23

:49

:00

Load

(k

W)

Time

Load Profile FP-25 (Lane-32) on 5 September 2019

72.4078 kW

0

10

20

30

40

50

60

70

80

00

:00

:00

00

:26

:00

00

:52

:00

01

:18

:00

01

:44

:00

02

:10

:00

02

:36

:00

03

:02

:00

03

:28

:00

03

:54

:00

04

:20

:00

04

:46

:00

05

:12

:00

05

:38

:00

06

:04

:00

06

:30

:00

06

:56

:00

07

:22

:00

07

:48

:00

08

:14

:00

08

:40

:00

09

:06

:00

09

:32

:00

09

:58

:00

10

:24

:00

10

:50

:00

11

:16

:00

11

:42

:00

12

:08

:00

12

:34

:00

13

:00

:00

13

:26

:00

13

:52

:00

14

:18

:00

14

:44

:00

15

:10

:00

15

:36

:00

16

:02

:00

16

:28

:00

16

:54

:00

17

:20

:00

17

:46

:00

18

:12

:00

18

:38

:00

19

:04

:00

19

:30

:00

19

:56

:00

20

:22

:00

20

:48

:00

21

:14

:00

21

:40

:00

22

:06

:00

22

:32

:00

22

:58

:00

23

:24

:00

23

:50

:00

Load

(k

W)

Time

Load Profile FP-28 (Lane-33) on 9 September 2019

15

Urban Field Pilot inside IIT Kanpur

It covers two faculty housing towers C&D (each to be provided with 25 kWp roof top SPV and 50

kWh Li-ion BESS), and Thermal Energy Storage (TES) system for Centre for Environmental

Science & Engineering (CESE) building.

Three-phase smart meters are installed in two residential apartments and the CESE Building. Data

collected are being used for preparing the load profiles for the buildings.

The 545 TRHR TES system will be integrated with the existing 230 TRHR system (made functional).

In case of power failure and non-availability of Solar PV output, BESS will feed only common area

lighting and list loads.

16

Glycol solution with phase-change material

is being used for the TES (achieves -4 deg C

in about 10 hours).

During night hours, building AC load shall

be met from Institute central AC plant, and

during peak load time (11:00 to 17:00 hrs)

by the TES system.

Peak load management by TES system

through SCADA system as part of ADMS.

Installation work completed in March 2020,

Commissioning delayed due to COVID 19,

likely in July 2020

Thermal Energy Storage (TES) System-CESE Building,

IIT Kanpur Urban Pilot

CESE Building

IIT Kanpur

17

46.08 kW

0

10

20

30

40

50

00

:04

:20

00

:34

:20

01

:04

:22

01

:34

:20

02

:04

:19

02

:34

:19

03

:04

:18

03

:34

:20

04

:04

:18

04

:44

:18

05

:14

:17

05

:44

:18

06

:14

:19

06

:44

:18

07

:14

:20

07

:44

:29

08

:14

:21

08

:44

:18

09

:14

:19

09

:44

:18

10

:14

:20

10

:44

:20

11

:14

:18

11

:44

:20

12

:14

:18

12

:44

:21

13

:34

:18

14

:14

:19

14

:44

:18

15

:14

:19

15

:44

:19

16

:14

:19

16

:44

:17

17

:24

:18

17

:54

:18

18

:24

:18

18

:54

:19

19

:24

:19

19

:54

:36

20

:34

:21

21

:14

:23

21

:44

:17

22

:14

:21

22

:44

:28

23

:24

:16

23

:54

:17

Load

(k

W)

Time

Load Profile Faculty Building – C Block on 4 July 2019

58.4 kW

0

10

20

30

40

50

60

70

00

:06

:34

00

:36

:35

01

:06

:34

01

:36

:36

02

:06

:34

02

:36

:34

03

:06

:35

03

:36

:34

04

:06

:35

04

:36

:34

05

:06

:35

05

:36

:33

06

:06

:34

06

:46

:34

07

:16

:34

07

:46

:35

08

:16

:34

08

:46

:35

09

:26

:34

09

:56

:35

10

:36

:35

11

:16

:37

11

:46

:36

12

:16

:35

12

:56

:34

13

:26

:34

13

:56

:35

14

:36

:33

15

:06

:34

15

:46

:34

16

:16

:35

16

:46

:40

17

:16

:37

17

:46

:34

18

:16

:33

18

:46

:34

19

:16

:39

19

:56

:35

20

:26

:34

20

:56

:36

21

:26

:33

21

:56

:34

22

:26

:34

22

:56

:33

23

:26

:33

23

:56

:32L

oa

d (

kW

)

Time

Load Profile Faculty Building – D Block on 3 June 2019

18

73.75 kW

0

10

20

30

40

50

60

70

8000

:15

:46

00

:45

:47

01

:15

:46

01

:45

:46

02

:15

:46

02

:45

:46

03

:15

:46

03

:45

:46

04

:15

:48

04

:45

:45

05

:15

:46

05

:45

:47

06

:25

:46

07

:05

:46

07

:35

:48

08

:05

:47

08

:35

:47

09

:15

:46

09

:45

:46

10

:15

:47

10

:45

:47

11

:15

:47

11

:46

:01

12

:25

:46

12

:55

:46

13

:25

:46

13

:55

:46

14

:25

:47

14

:55

:46

15

:25

:47

16

:05

:47

16

:45

:46

17

:15

:47

17

:45

:45

18

:35

:45

19

:05

:45

19

:35

:46

20

:05

:46

20

:35

:46

21

:05

:46

21

:35

:49

22

:05

:46

22

:45

:47

23

:15

:45

23

:45

:46

Load

(k

W)

Time

Load Profile of Centre for Environmental Science & Engineering Building on 11 September, 2019

Building AC load during peak hours : Appx. 120 TR

Building AC load during night hours : Appx. 72 TR

19

Smart Grid Control Room and SCADA/AMI System, IIT Kanpur

Built under ‘Smart

City’ pilot project

funded by MoP/

NSGM & IIT

Kanpur

Being used as

platform for

ADMS integration

under UI-ASSIST.

Monitoring and

Control functions

of DSO will be

performed

integrating the

three field pilots.

20

Applications of BESS at Distribution Downstream

Distribution Transformer

Level

Group Housing Society

Institutional Campus

Field Demonstration Urban Pilots by TERI/BRPL

Shortlisted few DTs (8 Nos.) to carry out study, in association with BRPL

Collected AMR meter data for three years (2015-18) for all DTs

Data correction & gap filling and load pattern analysis

Identified a particular overloaded DT for further study

Conducted field survey to analyze consumer behavior towards BESS adoption

Evaluated load pattern for year 2022 and calculated required battery size to manage overload

Carried out simulation study for DT overload management in MATLAB

Shortlisted few Gated communities (7 Nos.) to carry out the study

Conducted field survey to identify appropriate applications of BESS

Analyzed the power outage frequency and common /critical loads

Identified a SPD* society having RTPV and DG as back-up source

Calculated the benefit to consumers if DG operation is optimized

ToD is applicable for selected consumer (TERI SAS)

RTPV installed and DG used as back-up source

Energy Time shift (Energy Arbitrage) identified as appropriate application

Defined BESS operation to maximize the benefit to the institute

*SPD – Single Point Delivery

21

TERI’s Urban Pilot Locations within BRPL Licensee Area

Pilot LocationsPower

Converter rating

BESS Design Capacity as per

BHEL QuoteType Application

Inter-connection

Point for BESS Integration

Category A(New Friends Colony, Taimur

Nagar)140 kVA 368.64 kWh

Li-ion (NMC/LFP*) or Adv. Lead Acid

Overload management of

DTR

At Low Tension terminal of 990

kVA DT

Category B(Ispatika Society, Dwarka,

Sector-4)270 kVA 201.6 kWh Li-ion (NCM/ LFP*)

Back-up power & demand response

At DG Output terminal wherein

Grid reference signal is received

Category C (TERI School of Advanced Studies, Vasant Kunj)

56 kVA 96 kWhLi-ion

(NCM/ LFP*)Energy time shift

At Low tension terminal of 1600

kVA DT

* Suitable battery technology identified during the tender evaluation process

22

Pilot Implementation – Case study for Category-A(Taimoor Nagar, New Friends Colony, ND)

Location for BESS Installation

Case study for Category-A(Taimoor Nagar, New Friends Colony, ND)

Case study for Category-B(Ispatika Society, Sector-4, Dwarka)

Case study for Category-C (TERI-SAS)

23

Future Task-TERI/BRPL Pilots

Testing & validation of control algorithm in laboratory and in real-time

test bed system with the help of IIT K prior to field deployment.

Network is being modelled in RTDS at IIT Kanpur laboratory

Issuance of Purchase Order to BHEL (Given on 29 June 2020)

Delivery of materials (battery, PCS, HAVC etc.): 3-4 months

Installation & commissioning of pilots as per allocated time schedule (3-4

months).

24

Field Demo Pilot in a Village near Rihand by NETRA

Project:

• Implementation of Micro-Grid and the Impact

Analysis and Policy Recommendation

Benefit:

• Reliable power supply to School, Hospital, Girls Hostel etc

• Improvement of socio-economic condition of people

• Cater different loads i.e. Lighting, Motors, irrigation etc.

• DC system-improved system efficiencySalient Features:

• PV Plant with optimum size battery storage in

Banvasi Sewa Ashram (BSA) near NTPC Rihand

• Optimum DC Voltage levels for DC power

transmission, household/road

lighting/School/hospital loads

• Monitoring and control of complete system through

centralized control station

Status:

• Survey of Load/Energy requirement according to type of

loads : Completed

• System architecture along with storage & exact location

w.r.t. Load Centre and finalization of Tender- joint study

planned with IIT Kanpur.

25

Major Outcomes Expected from Field Demo Pilots

• Providing a role model for microgrid, RES (PV and Biomass) and storage integrated future distribution systems in India under typical rural, semi-urban and urban settings.

• Demonstrating a new community based rural microgrid management model.

• Addressing electricity access and reliability issues and ensuring 24x7 supply.

• Demonstrating ADMS/DSO model to manage future smart distribution systems.

• Creating/enhancing local job opportunities and cottage industries along with rural pilots.

• Demonstrating overload relief to distribution transformers in urban and semi-urban areas and capital investment deferral due to storage deployment and optimal control.

• Demonstrating socio technical impact and bringing out policy recommendations to regulators and government to facilitate promotion of such systems.

26

Thank youAcknowledgement:

“The work reported in this presentation is supported by the Department of Energy

under Award Number DE-IA0000025 and the Indo-US Science and Technology

Forum in partnership with Department of Science and Technology, Government of

India, under grant no. IUSSTF/JCERDC-Smart Grids and Energy Storage/2017.

The views and opinions expressed herein do not necessarily state or reflect those of

the India/US Government or any agency thereof.”