third party evaluation of the pilot dewats projects in dprk...third party evaluation of the pilot...
TRANSCRIPT
Third party evaluation of the pilot DEWATS
projects in DPRK
Paradigm Environmental Strategies Pvt. Ltd., G1, Lumbini Apartments,
#32, Venkatapura Main Road,
Koramangala Ist Block, Bangalore 560 034
Karnataka, India
Tel +91-80-2563 3390
Submitted to: UNICEF DPRK Office Pyongyang
28 Munsudong
PO Box 90
Democratic People’s Republic of Korea
Submitted on: 08 October, 2010
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK i
Paradigm Environmental Strategies (P) Ltd.,
Pp 2
Document No: R-ADEPT-2010-10.1/ V1
Date of submission: 071012
Submitted: Pravinjith K.P
Client: UNICEF DPRK Office Pyongyang
Internal Document Control
Sl. No. Document Number & Date Prp Chk App Remarks
1. R-ADEPT-2010-10.1/ V1 081010 PKP PKP PKP Sent to UNICEF for comments
2. R-ADEPT-2010-10.1/ V1 101110 PB PKP PKP Draft final for approval
External Document Control
Sl.
No.
Document Number & Date Submitted on No & type of
copies
Distribution
list
Purpose
1. R-ADEPT-2010-10.1/ V1 08 Oct 2010 1 - soft UNICEF Draft
2. R-ADEPT-2010-11.1/ V2 10 Nov 2010 1 - soft UNICEF Draft Final
3. R-ADEPT-2010-12.1/ V3 07Dec2010 1 - soft UNICEF Final
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK ii
Paradigm Environmental Strategies (P) Ltd.,
Pp 3
Contents
1 Background....................................................................................................................... 4
2 Terms of Reference .......................................................................................................... 4
3 Evaluation......................................................................................................................... 4
3.1 Design .......................................................................................................................... 5
3.2 Construction ................................................................................................................. 7
3.3 Commissioning........................................................................................................... 12
3.4 Operation and Maintenance ....................................................................................... 13
3.5 Performance ............................................................................................................... 15
3.6 Capacity Building....................................................................................................... 17
4 Lessons learnt ................................................................................................................. 18
5 Recommendations .......................................................................................................... 19
6 Conclusions .................................................................................................................... 22
7 References ...................................................................................................................... 23
List of Tables: Table 1 Wastewater stream characteristics adopted in design....................................................... 5
Table 2 Design DEWATS capacity and corresponding person equivalent ................................... 5
Table 3 DEWATS effluent quality at outlet of AF and equivalent treatment efficiency ............ 15
List of Photos: Photo 1 Skewed inlet pipe in BGS and larger spacing of reinforcement in ABR and AF ............ 7
Photo 2 Soil cover of 600mm for frost protection........................................................................ 8
Photo 3 Variation in pipe spacing and alignment in anaerobic tanks............................................ 9
Photo 4 Variation in pipe levels in DEWATS............................................................................... 9
Photo 5 Two chamber ABR and four chambers AF in DEWATS in 25 cum plant ........................ 10
Photo 6 Lateral entry of inlet pipe in Settlers .............................................................................. 10
Photo 7 Soil cover of 250mm for frost protection in DEWATS #26 .......................................... 11
Photo 8 Missing tee pipes in outlet chamber ............................................................................... 11
Photo 9 Irregular spacing in perforated slab for AF .................................................................... 12
Photo 10 Biogas dome constructed with a sealed cap. ................................................................ 13
Photo 11 Caked up scum in DEWATS #10................................................................................. 14
Photo 12 HGF in DEWATS #26 before and after site comments ............................................... 14
Photo 13 Attempts to measure sludge in DEWATS.................................................................... 16
Photo 14 Usage of Biogas in Community Kitchen...................................................................... 16
Photo 15 Ingenious sludge gauge fabricated with fluorescent tube............................................ 17
List of acronyms:
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK iii
Paradigm Environmental Strategies (P) Ltd.,
Pp 4
Sl.No. Acronym Expansion
1. BOD Biological Oxygen Demand
2. COD Chemical Oxygen Demand
3. DEWATS Decentralized wastewater Treatment Systems
4. ABR Anaerobic Baffle Reactor
5. AF Anaerobic Filter
6. HRT Hydraulic Retention Time
7. Cum/d Cubic meters per Day
8. M Meters
9. mg/l Milligram per litre
10. HGF Horizontal Planted Gravel Filter
11. Q Discharge Quantity
12. Sq.m Square Meters
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 4
Paradigm Environmental Strategies (P) Ltd.,
5
1 Background
UNICEF, MoCM and the Yontan County authorities have installed the
pilot DEWATS for managing wastewater generated from the
households. M/s BORDA, Germany have provided the technical type
designs of the plant. A German consultant Mr.Bernd Ebeling helped the
MoCM in the design of the horizontal filter/wetland in June 2009 and
also trained the MoCM engineers. Ms. Ina Jurga, who was retained by
UNICEF to work on rural sanitation and DEWATS and provided
construction supervision support for the wetland and Greenhouses. The
first project was commissioned in September and today Yontan county
has installed 31 DEWATS. The officials from the Academy of Sciences
have started monitoring the performance of the plant since 2008.
As part of the review, UNICEF and MoCM have decided to evaluate
the pilot DEWATS project and accordingly engaged Mr. Pravinjith
Kunhipurayil, Managing Director, Paradigm Environmental Strategies (P)
Ltd., Bangalore, India to carry out the third party evaluation. The
contract was from 27th September to 11th October 2010.
2 Terms of Reference
The terms of reference for the third party evaluation has been
described below
1. Conduct desk review of technical design documents,
development of evaluation plans, including one field visit
2. Field observation and inspection of DEWATS facilities, including
the analysis of lab test of the effluent
3. In consultation with MoCM, County authorities and other
agencies develop draft evaluation report
4. Final report writing
The methodology for the evaluation involved discussion with the
Stakeholders- UNICEF, MoCM and the Yontan County Authorities, Study
of the technical design documents, Site inspections and review of
records.
3 Evaluation
The evaluation of the DEWATS project has been carried out under the
following heads
1. Design
2. Construction
3. Commissioning
4. Operation and Maintenance
5. Performance
6. Capacity building
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 5
Paradigm Environmental Strategies (P) Ltd.,
6
3.1 Design
The review of the design has been based primarily on the “Feasibility
study DEWATS for Yontan” prepared by BORDA, the construction
drawings submitted by BORDA Germany and discussion with UNICEF,
MoCM officials and Yontan Authorities.
The BORDA team has carried out an exhaustive study of the project site
and prepared the conceptual designs of the DEWATS plants. They
have recommended DEWATS treatment capacities of 10, 25, 50 and
100 cum/day and related clustering of houses appropriate to the
chosen capacity. Accordingly, the construction drawings have been
furnished. The concept shows that mixed wastewater is allowed into a
DEWATS comprising of a Settler / biogas settler, followed by anaerobic
Baffle reactor and anaerobic filter before being discharged to the
tertiary treatment or municipal sewer as appropriate.
The Design team of MoCM received training in May 2009 in Beijing
supported by UNICEF for customizing and adapting the solutions for
their own local needs.
The waste water characteristics adopted for the design is given in Table
2 of the review report. The key input (design) values are summarised
below.
Table 1 Wastewater stream characteristics adopted in design
Sl No Parameters Input values
1 Temperature 10 deg C
2 BOD 190 mg/l
3 COD 380 mg/l
4 TSS 180 mg/l
5 Wastewater generation 130 lpcd
Accordingly, the DEWATS capacity and their design person equivalent
based on the wastewater generation of 130 lpcd are derived and
tabulated below
Table 2 Design DEWATS capacity and corresponding person equivalent
Sl No DEWATS capacity Person Equivalent (pe)
1 10 cum/day ~76
2 25 cum/day ~190
3 50 cum/day ~380
4 100 cum/day ~760
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 6
Paradigm Environmental Strategies (P) Ltd.,
7
The DEWATS have been designed for an outlet effluent value of 60 mg/l
at the end of the Planted gravel filter. The desludging period adopted
for the design based on the input characteristics is
1. Settler – 18 months routine and 24 month compulsory
2. Anaerobic baffle Reactor – 36-60 months or when sludge level is
1.0 m whichever is earlier
3. Anaerobic Filter – 24- 36 months
Observations
Design calculations for the DEWATS finally adopted for construction
(namely 10, 25 cum/day) were not available for the review. A
comparison has been made with the design person equivalent based
on 130 lpcd and the actual connected load. The same has been
tabulated below:
Sl
N
o
DEWATS
capacity and
Numbers
Design
Person
equivalent
Reported
Actual
Person
equivalent
Actual/design
1 10 Cum/ day
17 Numbers
~76 pe 193-215 pe 2.5-2.8
2 25 Cum/ day
14 numbers
~190 pe 410-536 pe 2.1-2.8
• It should be recognised that DEWATS are designed for both
hydraulic loading and also organic loading. Although, the
average hydraulic loading (as per the data submitted) has not
been exceeded in the three projects which are monitored
(DEWATS #3, #7 and #8), it remains to be seen whether it is true
for other DEWATS. However, MoCM have stated that the
wastewater generation is an average of 51 lpcd.
• It is clarified that the school is not connected to DEWATS #9 and
also that the hospital is not connected to the DEWATS #11 due to
topographical constraints.
• The table also shows that the computed organic pollution loads
are likely to be exceeded from those that of the designs. The
variation is between 2.1 to 2.8 times the design values. Although
the DEWATS has the advantage of higher treatment efficiency
with increase in concentration, it still has a bearing on the
expected effluent quality of the DEWATS (which is likely to be
higher than the design value of 60 mg/l) and also the desludging
periods which is likely to be lower than the designed period given
earlier.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 7
Paradigm Environmental Strategies (P) Ltd.,
8
3.2 Construction
The construction of the 31 DEWATS structure has been completed at
various times starting from the year 2008. Many of the plants are
already nearing two years of operation. MoCM indicated that all the
construction specification have been followed as given in the BORDA
Germany drawings and the specifications. No construction monitoring
or quality checklists exist and hence it is difficult to verify the same.
Some photos during the construction stage were made available for
the study.
Observations
Discussions with the MoCM and the Yontan County officials revealed
that they had not adopted the requirement of Styrofoam insulating
media as suggested in the BORDA drawings. This was a local decision
and they have not made any appropriate modifications. They have
also not provided the essential vent pipes for the Settler, BR and the AF
as shown in the drawings.
Photo 1 Skewed inlet pipe in BGS and larger spacing of reinforcement
in ABR and AF
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 8
Paradigm Environmental Strategies (P) Ltd.,
9
It is also understood that a baffle wall has been added within the 25
cum/day biogas dome to enhance the efficiency. This is not recorded
in the construction drawing. The reinforcement spacing appears to be
larger than the specified 120mm. (ref. D-YCNK-ST-25-BR-01). The grade
of steel used is Fe240 and not Fe415, while the concrete is M25 or lower
(likely M15) instead of M30.
In the DEWATS #3 (25 cum/day), the soil cover for frost protection was
approximately 600mm.
Photo 2 Soil cover of 600mm for frost protection
The spacing between baffle pipes was varying (between 250 and
450mm) and was also different from the specifications in drawing
(335mm). In general the level of the baffle pipes, spacing and
alignment were different from specifications.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 9
Paradigm Environmental Strategies (P) Ltd.,
10
Photo 3 Variation in pipe spacing and alignment in anaerobic tanks
Photo 4 Variation in pipe levels in DEWATS
The drawings D-YCNK-CT 25 BR-01 has indicated 4 chambers while the
ABR module actually constructed had only two baffle chambers. This is
major deviation as they seem to have used the drawing for
homogenisation and inoculation unit instead of ABR drawing as shown
in the concept drawing D-YCNK-CT-25 CON-01.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 10
Paradigm Environmental Strategies (P) Ltd.,
11
Photo 5 Two chamber ABR and four chambers AF in DEWATS in 25 cum
plant
The inlet pipe to the settler in the 10 cum/day DEWATS #26 and those
for the Biogas settler of DEWATS #3, #6 and #7 have been placed
perpendicular to the direction of flow, leading to a possible short circuit
of wastewater flow and causing reduction in treatment efficiency. This
is a strong non conformity from the BORDA drawing where the inlet of
Biogas Settler is located diametrically opposite to the extension
chamber.
Photo 6 Lateral entry of inlet pipe in Settlers
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 11
Paradigm Environmental Strategies (P) Ltd.,
12
The settler of DEWATS #26, doesn’t have the protective soil covering
specified for frost protection, only 250mm of soil covering was above
the ABR and AF.
Photo 7 Soil cover of 250mm for frost protection in DEWATS #26
Inspection of the outlet chambers of the structures revealed that the
outlet pipes are not constructed on the same levels. The Tee pipes
were also missing in the settler. This was also pointed out to the
accompanying MoCM team.
Photo 8 Missing tee pipes in outlet chamber
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 12
Paradigm Environmental Strategies (P) Ltd.,
13
The perforated slabs for anaerobic filter were also not as per drawings.
The photo is shown below.
Photo 9 Irregular spacing in perforated slab for AF
3.3 Commissioning
MoCM does not have records of the pre commissioning checks.
Hence, no comments could be made. On enquiry, it was learnt that no
inoculation have been carried out in the DEWATS plants. It is not clear
whether it has been approved by the Consultants.
Observation
In general the variation in spacing, level and alignment of baffle pipes,
missing Tee pipes, fixed dome cover etc could have been avoided
had a pre commissioning check was instituted prior to the
commissioning.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 13
Paradigm Environmental Strategies (P) Ltd.,
14
Photo 10 Biogas dome constructed with a sealed cap.
3.4 Operation and Maintenance
The MoCM and the Yontan County officials did not make available the
Operation and Maintenance manual (O & M), hence no comments
could be made. They have not carried out any O & M activities till
date.
Observations
The pipe level controller at the outlet of the Horizontal Gravel Filter of
510 cum/day capacity was almost parallel to the ground, indicating
that the water level in the HGF was not maintained adequately. It was
pointed out to MoCM that the treatment efficiency is affected
adversely.
Opening the Inlet register of Biogas Settler DEWATS #7 revealed that
there were plastic bags in the manhole. The water was generally
flowing in all the 5 DEWATS which were opened randomly and no
apparent blockage was noticed.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 14
Paradigm Environmental Strategies (P) Ltd.,
15
The inlet register of DEWATS #3 showed four pipes which was
apparently draining the wastewater from two apartments connected
to it. It was informed that two were blackwater pipes and two
greywater. The flow (around noon) also appeared to be clear with
hardly any contamination. Since the timing was during working hours, it
may indicate leaking taps. A request to inspect any one of the dwelling
units was not allowed as it was informed that all the occupants were
away at that time.
Photo 11 Caked up scum in DEWATS #10
The scum level in the settler of DEWATS #26 was found caked up. The
pipe level controller of the HGF in DEWATS #26 was vertical and the
water level was maintained about 250mm from the top of gravel. No
plants were noticed on the first day of the inspection. However, on the
subsequent visit, the Yontan officials had arranged to plant reeds on
the HGF.
Photo 12 HGF in DEWATS #26 before and after site comments
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 15
Paradigm Environmental Strategies (P) Ltd.,
16
3.5 Performance
The Academy of Science personnel have been monitoring the
performance of the DEWATS. In particular, they have monitored
DEWATS #3, #7 (both 25 cum/day) and #8 (10 cum/day) apart from
the Horizontal Gravel filter. It is learnt that they have monitored the
waste water flow by the bucket method on an hourly basis, in order to
estimate the per capita generation of wastewater. They have done
the study for four seasons. The parameters monitored include
temperature, flow volume, inlet of Settler/ biogas settler, outlet of
settler/ biogas settler, ABR and AF. The records span over a period of 15
November 2008 until 2 September 2010.
Observations
The wastewater flow data for the 25 cum/ day plant of DEWATS #3 and
#7 indicates an average of 22- 28 cum/day. Similarly the 10 cum
DEWATS #8 plant is subject to a flow varying between 8 -13 cum/day.
Apparently, the plants are overloaded hydraulically by a factor of 1.12-
1.30. This information should be interpreted cautiously as the flow
measurements have been taken at noon which is not the time of peak
flow.
The maximum and the minimum value of the effluents along with the
overall treatment efficiency at the end of AF is tabulated for the
DEWATS plant
Table 3 DEWATS effluent quality at outlet of AF and equivalent treatment
efficiency
Sl
No
DEWATS
ID
Max effluent
BOD mg/l and
date
Min effluent
BOD mg/l and
date
Maximum and
minimum overall
treatment
efficiency
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 16
Paradigm Environmental Strategies (P) Ltd.,
17
1 7 117
(20 Oct 2010)
40
(24 Jun 2010)
24.5% - 79.4%
2 3 122
(16 August 2009)
58
(24 Jun 2010)
33% - 70.3%
3 8 129
(20 Oct 2010)
50
(10 Sep 2010)
24.5% - 79.4%
The high effluent concentration at the Anaerobic Filter outlet may result
in non conformance to the design target value of 60mg/l at the end of
the Horizontal gravel filter.
The sludge level has not been measured till date, although the settler/
Biogas settler is past its due date for desludging, especially in DEWATS
#7. An attempt was made to measure the sludge in DEWATS #3 and
26, during this evaluation, but it was unsuccessful, due to the non
availability of stiff transparent tube.
Photo 13 Attempts to measure sludge in DEWATS
About 100-150mm of thick scum was noticed at the settler, and the
sludge level appears to be low (300-500mm). The baffle reactor did not
show a major development of sludge.
There is no meter to measure the gas flow. On discussions, it was learnt
that the gas is sufficient to meet the daily needs of two families.
Photo 14 Usage of Biogas in Community Kitchen
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 17
Paradigm Environmental Strategies (P) Ltd.,
18
3.6 Capacity Building
The MoCM, team citing the design training programme in Beijing and
the onsite training received from the International consultants, claim to
be confident of designing the DEWATS independently. It was also
mentioned that during construction, they received specific training
from Mr. Bernd Ebeling and from Ms. Ina Jurga on Wetland and
greenhouse construction for DEWATS. They perceive to be confident of
building the structures; this is somehow evidenced by their replication
efforts in the 31 DEWATS. Nevertheless there are certain shortcomings as
explained earlier and areas for improvement. There is a lack of training
support in the operation and maintenance aspects as well, especially
for troubleshooting. At this stage the Operation & Maintenance seems
to be limited to maintenance of sewer lines.
Observations
The MoCM team, Academy of Sciences and Yontan County Authorities
demonstrated keen interest in developing their individual capacities. A
striking point was that each of the members were referring to the notes
and learning’s of the Beijing training program and also tips and
suggestion given by the visiting consultants. In the present context,
when it was pointed out that the plants were missing in the PGF of
DEWATS #10, they promptly planted the reeds. This was noticed during
a surprise inspection following the remark.
Similarly, although the transparent tube was not available for the
sludge measurement, the Yontan County authorities fabricated a
make shift tube from a waste tube light. Although it did not work, it
shows the ingenuity and interest of the team.
Photo 15 Ingenious sludge gauge fabricated with fluorescent tube
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 18
Paradigm Environmental Strategies (P) Ltd.,
19
4 Lessons learnt
Decentralized wastewater Treatment Systems which does not use
electricity or chemicals and which has minimum maintenance
requirements is the appropriate system for a country like DPRK. It is very
clear from the evaluation that MoCM has rightly chosen this
technology for management of the wastewater. The efforts of UNICEF
support for the same is also commendable. The following are few other
lessons learnt from this mission:
• There is a mismatch between the computed organic pollution loads
and the actual values observed during operation. This increase in the
pollutant loads will result in the decrease of de-sludging period. The
effluent quality at outlet of wetland would also be higher than target
values.
• Some aspects provided in the drawings were not conformed during
the construction. Certain deviations from the drawing were also made.
The use of insulation to minimise the temperature effects has not been
complied with. Similarly, the 600 mm frost cover is also not maintained.
This shall affect the quality of treatment.
• The soil cover, skewed inlet pipes, reduced number of baffled
chambers, sealed biogas cover slab, etc indicate that a structured
Pre-commissioning checks were not instituted resulting in the non-
conformity has occurred. The consequence would be lower treatment
efficiency. This is an important omission which needs to be addressed
when further such systems are being commissioned.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 19
Paradigm Environmental Strategies (P) Ltd.,
20
• Lack of O&M activities is affecting the systems. Immediate steps to
undertake O&M should be undertaken.
5 Recommendations
It is understood that UNICEF and MoCM are planning to replicate the
project in other parts of the country. It is recommended that the
following areas could be improved.
Design
a) The grade of concrete which is likely to have been adopted in DPRK is
M25 (Fck- 25 N/sqmm or 25 Mpa) or lower, instead of the specified
M30. Similarly it appears from the construction photos, that the
reinforcement used is of the grade Fe240 (Fy -240 N/sqmm or 240MPa)
instead of Fe 415. The structural designs have to be adjusted
accordingly. This would realise considerable savings in costs and aid to
the safety of the structure. The designs have to be prepared by the
local engineers in accordance to the prevailing standards.
b) No detail construction information was available from MoCM sighting
that analysis of cost effectiveness of the intervention is not within the
remit of the evaluation. However when checked with UNICEF they
could provide some ballpark figure for the pilot DEWATS. The total cost
was about 650,000 USD with approximately 100,000 being used for
technical support, supervision and training abroad for MoCM
engineers. The actual cost of material support is in the range of 550,000
USD. With 10,000 population as current beneficiaries, the per capita
material cost of 55 USD is very expensive. In addition the plant
becomes even less cost effective because of apparently very little gas
production and no reuse of final effluent for irrigating crops for added
economic value to the infrastructure. The typical DEWATS for a small
town of 5,000 population costs about 140,000 USD in India (per capita
cost of ~28 USD) including all the material and manpower cost.
c) The wastewater generation from each house is nearly 2.6 times lower
than that assumed in the design. The sewer pipe diameter could
therefore be down sized appropriately, leading to substantial cost
savings.
d) There are several opportunities for the designer to optimise in cost and
enhance the technical efficiency. One situation would be to combine
the RC walls by overlapping adjacent DEWATS modules, instead of
constructing as depicted in the earlier photos.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 20
Paradigm Environmental Strategies (P) Ltd.,
21
Construction
a) The spacing between the reinforcement has to be ensured as per
design and specifications. The designer would have to certify that the
drawings have been followed for each of the project stage.
b) The interfaces between brick and RCC have to be tied properly by use
of dowels. All the corners have to be chamfered with cement mortar
to aid the bonding and ensure water tightness.
c) Any construction deviations/ modification should be authorised by the
local structural designer and the drawings modified. A typical example
is the biogas settler where the RCC structure is different from the
drawing D-YCNK-BS-ST-01.
d) The frost cover should be as specified in the design.
e) A set of “As built drawings” should be prepared for each project for
easy reference in future and better operation and maintenance.
Commissioning
a) A commissioning checklist should be prepared documenting all the
stage wise inspection, photographic evidence of conformance to all
critical stages and signed of by a designated person. Completion of
the checklist should precede the commissioning of the project.
Operation and maintenance
a) An Operation and maintenance manual should be
developed/modified detailing all the project parameters. The
frequency of monitoring, cleaning of sewer lines, manholes, desludging
etc should be spelt out in the O & M manual. Training should be
provided to the designated personnel and the records of such O & M
measures should be maintained.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 21
Paradigm Environmental Strategies (P) Ltd.,
22
Performance
The results of the ongoing performance monitoring however, gives an
ambiguous picture of the efficiency of DEWATS.
A more structured and logical monitoring programme has to be followed.
a) The BOD of the inlet wastewater is apparently weak but the
connected person equivalent reported by MoCM is nearly three
fold. This is virtually impossible. The values have to be rechecked
and substantiated. It should be verified whether all the family
members reported to have access to DEWATS are actually using
the pour flush toilets connected to the DEWATS.
b) Similarly, the claim that the daily gas production is sufficient for two
houses has to be verified using a gas meter. There was no offensive
smell when the DEWATS #26, which had no vent pipe was opened
which is surprising. The gas production in the Biogas settler is
proportional to the treatment efficiency, inlet BOD concentration
and the formation of sludge. The Academy of Science personnel
have to recognise this fact while interpreting the results.
c) The sampling should cover the time of peak flow. The wastewater
quantity should be compared to the quantity of water supplied
from all sources- Gravity fed water supply and any other sources.
d) The quality of water in the receiving body should be measured
upstream of the discharge point and also on the downstream.
Similarly, in case hand pumps are available, the ground water
quality could be measured routinely. This will help in demonstrating
the utility of the DEWATS in controlling the water pollution.
e) Simple tools like the sludge gauge, ice box for transporting BOD
bottles, Samplers etc should be provided for the monitoring
personnel.
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 22
Paradigm Environmental Strategies (P) Ltd.,
23
Capacity building
a) Some more technical training has to be carried out either by in-
house local staff or international resources in the area of design,
construction, quality control and performance monitoring. This is
particularly important to make the plant more cost effective and
operation efficient. A procedure for inducting new members into
the project should be developed and followed.
b) A strong focus should be provided for carrying out Social awareness
on the benefits of DEWATS in the community. Thrust should be given
on highlighting the fertilising effects of the treated effluent and the
sludge in irrigation, as compared to use of human excreta as
compost and also the saving in water usage, the impact of Biogas
in improving Indoor air quality as compared to the traditional
burning of coal. Sustained sensitisation would go a long way in
maximising the benefits of the Decentralised waste water
treatment.
6 Conclusions
The UNICEF –MoCM DEWATS project is a commendable effort to
protect the quality of groundwater and the river. The construction of 31
DEWATS locally is also the evidence of the great team effort. The
evaluation report highlights the observations, its impact on the success
of the DEWATS project.
However, the most important observation is on the cost optimization of
the plants, which needs attention. The Indian experiences have proved
that DEWATS can be constructed at much lower costs and thus
popularizing it. Regular structured monitoring of the project can further
bring down the costs by improvising the designs to suit the local
conditions. It would be advisable to additional hands on training for the
design of DEWATS and also in construction, operation and
maintenance of new DEWATS. This could be supported with the help of
international expertise.
The DEWATS being an engineering project, the evaluator does not find
it right to comment/ gloss over things which are done in conformance
to the designs and drawing provided by BORDA. However, it should be
R-ADEPT-2010-12.1/ V3 DEWATS EVALUATION –YONTAN, DPRK 23
Paradigm Environmental Strategies (P) Ltd.,
24
considered that if it is not particularly pointed out, then the
specifications have been generally adhered to by all the stakeholders.
Hence the focus has been primarily on deficiencies and areas of
improvement.
The non conformances which have been highlighted should be taken
in the right technical spirit and the team is advised to apply it globally
to all the new projects in order to avoid recurrence and also enhance
the utility of the DEWATS plant.
7 References
a) Technical report on Design of Decentralised Wastewater Treatment
Technologies in DPRK: Pilot Project in Yontan County Town.
b) BORDA Germany drawings for DEWATS – 10 cum/day and 25 cum/day
c) DEWATS Analysis data provided by Academy of Sciences
d) Photographs provided by MoCM
e) Discussion with UNICEF, MoCM, AoS and Yontan County Authorities