Third Street Corridor RehabilitationCommunity Meeting # 2 | March 15, 2018
Third Street Corridor RehabilitationCommunity Meeting # 2 | March 15, 2018
City of San Rafael BKF with WRT + Parisi
![Page 2: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/2.jpg)
Third Street - Agenda
1.Welcome and Introductions
2. Project Presentation
3.Discussion
4.Wrap-Up/Next Steps
5. Adjourn 1.
Welcome and Introductions1:00
Introduction of Committee members, staff, and consultant teamwith each member outlining their interests in the process
2. Project Presentation1:15
What the project is and isn’t, timelines, work program
![Page 3: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/3.jpg)
IMPROVEMENTS
• Pavement repair and drainage
• Signal upgrades
• Sidewalk and crosswalk enhancement
• Street trees
Baseline Project Features
$12.5 MILLON AVAILABLE
FUNDING FOR MEASURE A
GOALS
• Traffic flow improvements for cars, transit,
and emergency response
• Safety for all users
• Multi-modal access
![Page 4: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/4.jpg)
Available BudgetB
ase
lin
e I
mp
rove
me
nts
$3.5 M
$9M
Bio-retention facilities
Additional cost for 12’ Multiuse Path
Road repair between Grand & Hetherton
4th Street Intersection
Improvements at
key intersections
Tota
l b
ud
get
= $
12
.5 M
illi
on
A
dd
itio
na
l
![Page 5: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/5.jpg)
Project Area
![Page 6: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/6.jpg)
Draft Final
ReportReview and
Create Preferred
Alternatives
• Existing Conditions
• Opportunities &
Constraints
• Technical and
Community Working
Group Meetings
Community
Meeting #1
Summer 2017 November 2017 Winter 2017-2018 Spring 2018
We
Are
here
Final Report to
City Council
Project Design
and Construction
Late Spring 2018 2018-2021
Project Development Schedule
![Page 7: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/7.jpg)
3rd Street Now
![Page 8: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/8.jpg)
Major East West Connector
![Page 9: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/9.jpg)
Other Projects in Pipeline
Public Projects• Grand Avenue Pedestrian Bridge over the canal
• Bettini Transit Center relocation
• SMART track extension
• Cijos St- Currently under construction.
• Intersection improvements at A Street
• Heatherton Intersection at 101
• Parking and Way finding Study
• Traffic Signal Timing Study
Private Projects • BioMarin/Senior Housing at old (Between Lindaro &
Brooks)
• Shell Station at 4th &2nd/3rd
![Page 10: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/10.jpg)
Overview
Congestion Pedestrian Safety
Accessibility Comfort
![Page 11: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/11.jpg)
Source: Marin County, February 2015
Vehicle CongestionWeekday Westbound
6 8 10 12 PM 2 4 6 8 10 PM12 AM 42
15
MIN
10
5
P
L
A
N
N
I
N
G
T
I
M
E
ADT:
19,200 TO 24,700
![Page 12: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/12.jpg)
Vehicle Speeds During Peak Hours
Source: Marin County, February 2015
![Page 13: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/13.jpg)
Collision Types
Source: Marin County, February 2015
![Page 14: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/14.jpg)
Injury Rate
Source: Marin County, February 2015
![Page 15: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/15.jpg)
Bike and Pedestrian Involved
Source: Marin County, February 2015
![Page 16: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/16.jpg)
Existing Bicycle, Pedestrian & Transit
![Page 17: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/17.jpg)
Pavement Conditions
![Page 18: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/18.jpg)
Sidewalk Width
Source: Marin County, February 2015
![Page 19: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/19.jpg)
On Street Parking
![Page 20: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/20.jpg)
What we heard from the
Community, TWG and
CWG
![Page 21: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/21.jpg)
Community Meeting- Nov 13, 2017
![Page 22: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/22.jpg)
� Pedestrian and bike safety
� Vehicular congestion and speed
� Need for tree canopy and level of comfort
� Need to improve accessibility and sidewalks
� Congestion east of 101 highway
� Maintain parking in residential zones
� Improve wayfinding
� Improve community character + identity
� Improve bike and pedestrian crossing at the 4th street
at 2nd/3rd
� Accidents at Shaver St. intersection
� Safe access to schools
Improve Bicycle Access And Safety.
What we heard
![Page 23: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/23.jpg)
Previous Community Prioritization
1. Street Trees
2. Widened Sidewalk
3. Curb Extension
4. Street Lights
5. Gateway/Civic Identity
Signalized Intersection
Vegetative Buffer
6. Sidewalk Paving
7. Painted Crosswalk
8. Wayfinding + Signage
9. Sidewalk Seating
10. On Street Parking
Improve Bicycle Access And Safety.
![Page 24: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/24.jpg)
Concept Design
![Page 25: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/25.jpg)
Corridor-wide Improvements
Conduits for Future Adaptive Signals
Bulb-outs Traffic Signal Upgrades
High Visibility Crosswalks
![Page 26: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/26.jpg)
Corridor wide Improvements
Key School Routes/Sidewalks Pavement Rehabilitation
Street Trees ADA/ Curb Ramps
![Page 27: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/27.jpg)
Zones
![Page 28: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/28.jpg)
Commercial/ Downtown
![Page 29: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/29.jpg)
Commercial/ Downtown
Issues:
• Traffic Congestion results in sudden speeding
• Long distance between cross walks
• Tree canopy
• Pedestrian visibility at intersections
• On Street parking V/S off street parking
![Page 30: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/30.jpg)
Commercial/ Downtown
![Page 31: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/31.jpg)
Existing: Brook St
![Page 32: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/32.jpg)
Proposed: Brook St
![Page 33: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/33.jpg)
Existing: A St & B St
![Page 34: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/34.jpg)
Proposed: A St & B St
![Page 35: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/35.jpg)
Existing: A St Intersection
![Page 36: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/36.jpg)
Proposed: A St Intersection
![Page 37: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/37.jpg)
Existing: E St
![Page 38: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/38.jpg)
Proposed: E St
![Page 39: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/39.jpg)
Residential
![Page 40: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/40.jpg)
Zone: Residential
Issues:
• Speed issues
• Pedestrian Crossing along 3rd St
• Vertical curves and visibility issues
• Narrow sidewalk at the G St. intersection, along
the hill
• 4th Street Intersection
![Page 41: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/41.jpg)
Zones- Residential
![Page 42: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/42.jpg)
Existing: Hayes St to Shaver St
![Page 43: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/43.jpg)
Proposed: Hayes St to Shaver St
![Page 44: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/44.jpg)
Proposed: Hayes St to Shaver St
![Page 45: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/45.jpg)
Existing: G St
![Page 46: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/46.jpg)
Proposed: G St
![Page 47: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/47.jpg)
G Street Cross Section
Existing
Interim
![Page 48: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/48.jpg)
Existing: G St Safe Route to School
![Page 49: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/49.jpg)
Proposed: G St Safe Route to School
![Page 50: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/50.jpg)
Existing: 4th St to Ida St
![Page 51: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/51.jpg)
Proposed: 4th St to Ida St
![Page 52: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/52.jpg)
Available BudgetB
ase
lin
e I
mp
rove
me
nts
$3.5 M
$9M
Bio-retention facilities
Additional cost for 12’ Multiuse Path
Road repair between Grand & Hetherton
4th Street Intersection
Improvements at
key intersections
Tota
l b
ud
get
= $
12
.5 M
illi
on
A
dd
itio
na
l
![Page 53: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/53.jpg)
Draft Final
ReportReview and
Create Preferred
Alternatives
• Existing Conditions
• Opportunities &
Constraints
• Technical and
Community Working
Group Meetings
Community
Meeting #1
Summer 2017 November 2017 Winter 2017-2018 Spring 2018
We
Are
here
Final Report to
City Council
Project Design
and Construction
Late Spring 2018 2018-2021
Project Development Schedule
![Page 54: Third Street Corridor Rehabilitation · 2018. 3. 15. · ProjectPresentation 1:15 Whattheprojectisandisn’t,timelines,workprogram. IMPROVEMENTS • Pavement repair and drainage •](https://reader036.vdocument.in/reader036/viewer/2022071217/604c72977856453d466c66d8/html5/thumbnails/54.jpg)
QuestionsQuestions