this document is solely for the internal use of arcelormittal. saldanha works achieving energy...
TRANSCRIPT
This document is solely for the internal use of ArcelorMittal.
Saldanha Works Achieving Energy Savings through a holistic focused management approach A Case Study
ICUE PresentationReinet van ZylAug 2012
Framework
• AMSA Background information
• Summary Background on Saldanha Plant and Process
• Electricity Price and Cost impact
• Saldanha Approach for Sustainable Energy savings
• Implementation Time line
• Performance Review
• Project Detail as examples
• 2012 Focus and Target
• Conclusions
3
ArcelorMittal South Africa
Overview of Operations
• Flat Steel Products
• Vanderbijlpark Works – 3.2 Mtpa*
• Saldanha Works – 1.2 Mtpa*
• Long Steel Products
• Newcastle Works – 1.5 Mtpa*
• Vereeniging Works – 0.4 Mtpa*
• Iron ore supply
• 6.25 Mtpa from Sishen
• 2.5 Mtpa from Thabazimbi
• Coke & Chemicals
• Coke - 597 000 tpa*
• Tar - 133 000 tpa*
VereenigingJohannesburg
NewcastleSishen mine
Vanderbijlpark
Thabazimbi mines
DurbanSouth Africa
Saldanha
Cape Town
* Based on 2006 actual final product sales
Steel plants in close proximity of key markets
COREXDR-PlantSteel shop
Mills
RHF
Statistical information
• Electricity consumption: 160 MW
• Daily water consumption: 8 000 kilo liters (world best for an integrated steel plant)
• Manpower: 548 permanent employees
• Sales output: 1,2 million ton HRC/annum
Budget 2012 Allocation
5
• Energy related components is 46% of total cost structure.• However, in the steel industry coal and coke it is strictly speaking a raw material.• Coal and Coke is required for the Boudouard chemical reaction. (On this basis the AMSA
CO2 tax calculation was reduced to the current R125 mil).
Labour, 3%
Refractories, 2%
Alloys, 3%
Fluxes, 3%
PM Maintenance, 4%
Consumables , 5%
Overheads other, 5%
Ore, 11%
Pellets, 14%
Energy, 45.5%
Other, 45.5%
Coal : 20%
Coke : 7 %
Electricity: 14.7 %
LPG: 3.6%
Other : 0.2%
This document is solely for the internal use of ArcelorMittal.
Achieving Energy Savings
Energy Review 2011 - Saldanha
WHAT WENT WELL WHAT WENT WRONG
1. Good Progress on Strategy Implementation
2. 7.7 MW av. Electricity demand saved (from expected 145.3 MW)
• 5.3% saving on baseline
• Electricity Saving value : R28.3m
• Actual Average Demand : 137.6 MW
• (2012 demand saving YTD 4 MW)
3. LPG Saved : 5798 t (compared to 2010)
• LPG saving 26% with value R52m
• (2012 YTD saving R35m)
4. $12.8/t Savings for Dec ’11 ($21/t Saving for Jun’12)
5. Three Project Engineers appointed
6. Energy Matrix Structure in place
7. Thirteen projects completed (mostly quick wins and efficiency related with some awareness focused projects).
8. Good progress on visibility and reporting of energy related information
9. EnMS implementation – good progress
1. EnMS require more system knowledge for proper integration. Some more work required to integrate into current ISO system.
2. Capital funding was cut
7
8
Energy Management Sustainability
WCM (World Class Manufacturing)Reliability centred focus
Saldanha Approach
Management Infrastructure
Step 1 : WCM (World class Manufacturing focusing on Autonomous Maintenance (TPM)
Roll Out
9
Step 2 : Energy Management
Awareness and training
Performance Measure and Control : Improved Metering and Reporting
WCM : Autonomous Maintenance
Appoint Energy Manager
H1 2010
WCM : Professional Maintenance
Energy Strategy
Energy Audit
H2 2010 H1 2011 H2 2011 H1 2012 H2 2012 2013-2016
Energy Management SystemISO 50001
Energy Projects : prioritised implementation and tracking
WCM : People Development and other 5 pillars
WCM: Cost Deployment WCM: Cost Deployment
WCM : Focused Improvement
Appoint 3Team members
Step 3 : Management Infrastructure
10
Actions contributing to improved performanceEnergy Strategy
•An Energy Manager was appointed 1 May 2010.
•An energy audit was initiated to identify potential opportunities and expand the list of opportunities already identified.
•The team was later increased by a further 3 people focusing on project implementation to fast track potential savings.
•25% of capital allocated to Energy Projects.
WCM (World Class Manufacturing)
•The plant volunteered to be a pilot for the roll out of WCM within the AMSA group.
•The program is very much focused on equipment reliability and a “clean to inspect” approach
•Bronze status reached after 18 months (usual plan 3 years to reach)
IEE Program and Energy Management System (based on ISO 50001)
•Pilot plant for the expert training in Energy Management, Electrical Motors and Pumps.
•Ensure sustainability of any energy savings made.
•Training of personnel in other IEE programs (20 people)
Management Infrastructure (MI) – doing things more efficiently
•Implementation of a MI program in Feb 2012.
•Optimally utilizing the resources currently available within the plant.
•Improve the effectiveness of the organization and address deficiencies in current practices with standards and visual management.
Energy Projects Completed 2011
Nr Opportunity Detail kWh Saving
R 1000’s saving pa
Cost(Rm)
1 De-dusting fan2.2 MW
Switch off during standing time > 2 hr.
623,624 263 0
2 System 1 Maintain water temp @ summer Temps (28 33 degC)
1,419,500 686 0
3 Compressed Air Repair Leaks & prevent misuse 2,350,400
1,207 0
4 Ladle Heating Prevent unnecessary utilisation and LPG use
250
5 Power Optimiser
Installed in main Building :10% V drop, 7% kWh saving
55,091 120 0.5
6 Low Production Periods
Focus and awareness – switch off what is not required (Jun/Aug/Sep)
31,687,198
13,308 0
7 Load Shedding Utilising Chemical energy during Winter Peak tariff (2% moved to outside peak)
5,000(R20,000
planned 2012)
0
8 LPG Reduce LPG cons. by 30% by changing operating philosophy
50,000 0
Energy Projects Completed 2011 (cont.)
Nr Opportunity Detail kWh Saving
R 1000’s saving pa
Cost(Rm)
9 Conarc Foamy slag, Transformer operation & DRI Quality
42,180,000 17,715 0
10 Mill Ancillary Switch off
Switch off possible systems during standing
876,000 464 0
11 VSD System 11 Installed Variable Speed drive 6,464,880 3,500 3.16
EnMS helps you reach your targets and sustain performance!
Nr Awareness Projects Detail
12 Solar Street Lights
13 Solar Geysers
3b Compressed Air Fixing leaks and Awareness Training
Performance YTD
13
Performance YTD
14
1.9%
3.0%
4.2%4.5% 4.6%
4.8%
4.5%
6.0% 5.9%
4.6%4.6%
4.9%
5.7% 5.8%
5.1% 5.3%5.8%
6.8%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
Jan'
11
Fe
b'1
1
Ma
r'11
Apr
il'1
1
Ma
y'1
1
Jun'
11
Jul'1
1
Aug
'11
Sep
'11
Oct
'11
No
v'1
1
De
c'1
1
Jan'
12
Fe
b'1
2
Ma
r'12
Apr
'12
Ma
y'1
2
Jun'
12
% I
mp
rove
men
t fr
om
Bas
elin
e
Ele
ctrc
ical
Co
nsu
mp
tio
n [
MW
h p
a]
Electricity Savings Tracking
Actual MWh Saving Planned MWh saving % Improvement (Mov Av) from baseline
Project Detail : LPG Reduction
Project Statistics Actions and detailLPG Reduced Consumption
Trigger : Cost and shortage of LPG
Approach : Review operational assumptions and change operational principles and philosophy.
Implementation : Q4 of 2011
Value of Saving :
26% or R 52 million for 2011
A further 30% saving for 2012
Preparation : •Restore Corex basic conditions with Tap hole repair and WCM program. This ensures stable operations and high availability of DR gas. Change in practice :•Enrichment of DR gas •No significant detrimental impact on throughput could be observed in the Midrex. •The Midrex was one of the largest LPG consumers using LPG for cooling and increasing Carbon content •The Midrex decreased the LPG consumption considerably and countered potential negative impact on quality without significant loss in production volumes or tempo.. Results :•Midrex : LPG consumption was reduced at the from 18kg/t DRI to less than 14 kg/t DRI. •RHF consumption was reduced from 9kg/t to less than 2 kg/t hot rolled coil.
15
5.13 4.46 4.35 4.21 4.10 4.2 4.0 3.9 3.8 3.7
1.33 1.30 0.91 0.66 0.64 0.66 0.56 0.06 0.06 0.06
17.0 19.3 17.2 17.5 16.4 16.4 16
1513.5 13
3.6 3.1
2.6 3.1 3.1 3
2.82.6
3.1 3.1
27.128.2
25.1 25.424.2 24.1 23.3
22.1 21.0 20.4
0
5
10
15
20
25
30
Biogas GJ/t LS
Anthracites GJ/tLSCoke GJ/t LS
Coal GJ/t LS
LPG GJ/t LS
Energy Contribution by Source
18
2012 Targets :Electricity 1199 kWh/t or 4.2 GJ/t LPG : 0.66 GJ/tCoal & Coke : 19.4 GJ/t
Energy Focus Areas 2012
Focus 2012 Risks1. Projects – high value
• Targets : 1.1MW saving on electrical demand baseline (YTD on 4 MW in 2012)
• R28m saving through energy projects
• (YTD additional or R34m)
2. EnMS (ISO50001) full implementation and integration on SEU’s with external audit.
3. Improved reporting and visibility to operator level for SEU’s to assist with proactive energy management.
4. LPG supply contract – put system in place with minimal day-to-day interface required.
5. Customer Service to Plants
6. Awareness and Training
1. Lack of Capital
2. Technology injection required for significant further progress
3. Carbon Tax
4. Electricity price increase
5. Electricity winter pricing – not viable to produce during peak hours. Impacts on viability.
19
20
Conclusion
• Stability and reliability is a prerequisite for optimisation efforts.
• Management Commitment and Resource allocation essential.
• Energy Management System ensure sustainable energy improvements.
• Energy Management System allows a structured approach looking at all aspects (not just technical)
• Focus on Energy and Energy opportunities and savings will realise.
• Measuring and reporting important for both identifying opportunities and changing behaviour.
• The more you investigate potential opportunities the more opportunities are found.
• Awareness and education is a critical part for sustained savings.
21
Questions?
Thank You