1 Thomas P. Infusino, Esq. P.O. Box 792 Pine Grove, CA 95665 12/1/14 Board of Supervisors County of El Dorado 330 Fair Lane Placerville, CA 95667 RE: I strongly recommend that the Board of Supervisors complete the proper environmental review, and demonstrate that the El Dorado Hills Specific Plan conforms to the 2004 General Plan, prior to approving the proposed Town Center Apartments. Dear Supervisors, I am writing to you on behalf of a number of local residents who have already expressed concerns about the proposed Town Center Apartments project. Their homes are nearby the proposed project in Fuller Sunset Mobilehome Park, Four Seasons, Versante, Crescent Hills, Ridgeview, Mormon Island Preserve, and Green Springs Ranch. A number of objections have arisen regarding the proposed Town Center Apartments, leading to recommendations for denial from the El Dorado Hills Area Planning Advisory Committee (APAC) and the Planning Commission. These bodies gave the proposed project a great deal of focused evaluation and public review. Given the common sense nature of the objections, and the agreement of the advisory bodies to recommend project denial, nobody thought it necessary to refine these objections into legal arguments. Given the unusual decision of the Board of Supervisors on November 4 to defy the recommendations of their advisory bodies, and to direct the Planning Department to prepare for project approval, it has become necessary to explain why this project approval is not only ill advised, but also unlawful at this time. I. There are at least six reasons the Board of Supervisors should not to approve the Town Center Apartments project on December 2, 2014. First, the El Dorado Hills Specific Plan seems out of conformity with the 2004 General Plan. The documents must be brought into conformity before any further project approvals in the plan area. Second, the improper Initial Study analyses and the Subsequent Mitigated Negative Declaration are the wrong CEQA documents to support approval of the Town Center Apartments. The proper CEQA documents must be completed prior to approval of the proposed Town Center Apartments.

Upload: others

Post on 20-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

1

Thomas P. Infusino, Esq.

P.O. Box 792

Pine Grove, CA 95665

12/1/14

Board of Supervisors

County of El Dorado

330 Fair Lane

Placerville, CA 95667

RE: I strongly recommend that the Board of Supervisors complete the proper

environmental review, and demonstrate that the El Dorado Hills Specific Plan conforms to

the 2004 General Plan, prior to approving the proposed Town Center Apartments.

Dear Supervisors,

I am writing to you on behalf of a number of local residents who have already expressed

concerns about the proposed Town Center Apartments project. Their homes are nearby the

proposed project in Fuller Sunset Mobilehome Park, Four Seasons, Versante, Crescent Hills,

Ridgeview, Mormon Island Preserve, and Green Springs Ranch.

A number of objections have arisen regarding the proposed Town Center Apartments, leading to

recommendations for denial from the El Dorado Hills Area Planning Advisory Committee

(APAC) and the Planning Commission. These bodies gave the proposed project a great deal of

focused evaluation and public review. Given the common sense nature of the objections, and the

agreement of the advisory bodies to recommend project denial, nobody thought it necessary to

refine these objections into legal arguments. Given the unusual decision of the Board of

Supervisors on November 4 to defy the recommendations of their advisory bodies, and to direct

the Planning Department to prepare for project approval, it has become necessary to explain why

this project approval is not only ill advised, but also unlawful at this time.

I. There are at least six reasons the Board of Supervisors should not to approve the

Town Center Apartments project on December 2, 2014.

First, the El Dorado Hills Specific Plan seems out of conformity with the 2004 General Plan.

The documents must be brought into conformity before any further project approvals in the plan

area.

Second, the improper Initial Study analyses and the Subsequent Mitigated Negative Declaration

are the wrong CEQA documents to support approval of the Town Center Apartments. The

proper CEQA documents must be completed prior to approval of the proposed Town Center

Apartments.

Page 2: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

2

Third, the CEQA documents for the Town Center Apartments improperly rely on outdated

impact analyses completed in 1987 for the El Dorado Hills Specific Plan and for the 1995 Town

Center East project. These impact analyses need to be updated prior to any approval of the Town

Center Apartments, and any amendments to the El Dorado Hills Specific Plan.

Fourth, the project can still be improved to avoid the need for an EIR.

Fifth, the Board would be wise to direct the Planning Department to work collaboratively with

the project proponent and concerned citizens to modify the proposed Town Center Apartments

project to better address the concerns raised by the APAC, the Planning Commission, and

concerned citizens.

Sixth, the County can fix the environmental review and project approval documentation

and approve the project by the spring construction season. Approving the substandard

documentation on December 2 will suspend this and other projects in the specific plan area

while the legal challenges drag through the court system over the next three to four years.

II. The El Dorado Hills Specific Plan is not consistent with the 2004 General Plan.

The 2004 General Plan sits atop the land use hierarchy as the constitution for local land use.

Virtually all other County land use decisions must be consistent with the 2004 General Plan.

(California Native Plant Society v. City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th

603.) These decisions include, specific plan amendments, rezones, and planned development

amendments like the ones needed for the proposed project. (See for example, Government Code,

Section 65454, regarding specific plans.) Because a specific plan holds a subsidiary position

relative to a general plan, a specific plan must be reviewed and amended to make it consistent

with any changes in a county general plan. (Government Code, Section 65359.)

After approval of the 1987 El Dorado Hills Specific Plan, El Dorado County completed two

comprehensive general plan updates in 1996 and in 2004. However, there is no evidence in the

record to indicate that this specific plan was ever modified to conform to the 2004 General Plan.

Similarly, there are no findings of fact that demonstrate that the El Dorado Hills Specific Plan

conforms to the 2004 General Plan. To the contrary, the record does reflect inconsistencies

between the two plans.

For example, the road system contemplated to serve the intense development in the El Dorado

Hills Specific Plan is not the same as the road system contemplated by the 2004 General Plan.

The El Dorado Hills Specific Plan calls for a road system in 2010 that includes a divided 6-lane

portion of Green Valley Road, a divided 4 lane Bass Lake Road, and divided 6-lane White Rock

Road west of the project. (Exhibit 1: El Dorado Hills Specific Plan Final EIR, Figure 7-21, page

2-2.) The Circulation Map for the 2004 General Plan reflects less road expansion for the

specific plan area, and defers its development later in time. The 2004 General Plan, figure TC-1,

depicts no portion of Green Valley Road with 6 lanes, Bass Lake Road as undivided with 4-

lanes, and the aforementioned section of White Rock Road as 4 lanes. It is now 2014, the roads

Page 3: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

3

in the plan area have still not expanded as called for in the specific plan, and as a result cannot

provide free flowing and safe traffic for the existing level of development in the specific plan

area. Thus, this lack of consistency between the specific plan and the general plan is a source of

traffic impacts in the area. Since the traffic impacts associated with the proposed Town Center

Apartments have been repeatedly voiced as a critical concern of neighbors and advisory bodies,

there is a direct nexus between the proposed project and the lack of consistency between the

plans.

We strongly recommend that the Board of Supervisors direct the Planning Department to

compare each provision (maps and text) of the El Dorado Hills Specific Plan, its conditions

of approval, its EIR, its mitigation measures, and any associated development agreements

to the provisions of the 2004 General Plan, its EIR, and its mitigation measures. The

Planning Department analysis should identify the areas of consistency and inconsistency. Where

inconsistencies exist, the Planning Department should bring forth recommendations for resolving

these inconsistencies. This analysis should be reviewed by the Area Planning Advisory

Committee and the Planning Commission, prior to being acted on by the Board of Supervisors.

The County critically needs this analysis and action to form the lawful planning foundation

for future Board of Supervisor approvals of the Town Center Apartments and the

redevelopment of the El Dorado Hills golf course.

We are confident that the County could complete this analysis and action by this spring, thus

setting the stage for lawful project approvals in time for the construction season. However, if the

County approve the Town Center Apartments on December 2, and thereby force resolution

of this issue by the thorough yet slow-moving courts, we anticipate that this issue will cloud

future project approvals in the El Dorado Hills Specific Plan Area for the next three to four

years.

III. A Subsequent Mitigated Negative Declaration for the Town Center Apartments

cannot use the 1995 Town Center East Negative Declaration as a basis.

The Town Center Apartments seeks to comply with CEQA using a subsequent mitigated

negative declaration. The prior negative declaration was done in 1995 for the Town Center East

project. Upon receipt of the Town Center Apartments application, the Planning Department staff

followed the procedure in CEQA for determining if a modified project needed additional CEQA

review. (Public Resources Code Section 21166; CEQA Guidelines Sections 15162 & 15163.)

Planning Department staff completed an initial study and Subsequent Mitigated Negative

Declaration (SMND). Staff determined that the current project, with mitigation, has no new or

substantially more severe impacts than the 1995 Town Center East project, and therefore no EIR

is needed. (See SMND, pp. 3, 7-8; December 2 Findings, pp. 1-6.) There is one major problem

with this analysis; the Town Center Apartments Project is not a modification of the 1995

Town Center East project, it is a completely different project.

Page 4: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

4

Our regional Third District Court of appeals has ruled that a lead agency can only use the

truncated environmental review procedures when it proposed to modify an existing project.

These procedures cannot be used to evaluate an entirely new project that is unrelated to the

previous project. As a matter of law, a new project requires an independent environmental

review. (Save Our Neighborhood v. Kathi Lishman (2006) 140 Cal.App.4th

1288, 1296-1301.)

As some of you may recall, the case involved a project approval in your County seat of

Placerville.

So what makes the 2014 Town Center Apartments unrelated to the 1995 Town Center East

project?

First, the applicants are not related. The applicant for Town Center East was El Dorado Hills

Investors LTD. The applicant for Town Center Apartments is the Spanos Corporation.

Second, the land in question is not the same. The Town Center East project included the entire

130-acre Village T of the El Dorado Hills Specific Plan. The Town Center Apartments is on

one, isolated, 4.565 acre portion of Village T.

Third, land uses are not the same. The Town Center East project was a commercial and office

complex with absolutely no residential component. The Town Center Apartments is an entirely

residential project with no commercial or office component.

Fourth, the timing of the projects is not the same. Town Center East project was proposed in the

20th

Century. The Town Center Apartments are being proposed in the second decade of the 21st

century. (Exhibit 2: Compare: Britzman, Town Center East Staff Report; to Subsequent Initial

Study Checklist, Town Center Apartments.)

Fifth, the environmental setting for the projects is not the same. The Town Center East project

was approved for development in the El Dorado County of the late 1990’s. The Town Center

Apartments project will add cumulative impacts on a setting further compromised by an

additional 15 years of degradation.

Sixth, the projects differ in their degree of consistency with existing development plans for the

area. The Town Center East project was consistent with the specific plan and the zoning for the

area. The Town Center Apartment requires rezoning and amendment of the specific plan.

Thus, the Planning Department staff and its consultants failed, as a matter of law, to follow the

proper environmental review procedures for the Town Center Apartment’s project. Failure to

proceed in accord with the law in approving the project is an abuse of discretion. Thus, any

Board of Supervisors’ approval of the Town Center Apartments on December 2 will result in a

court issuing a writ of mandate directing the County to revoke the approval.

The proper procedure is to complete an independent initial study for the Town Center Project to

determine if it may have a significant impact on the human environment. (It is irrelevant

whether that impact is greater or lesser than the 1995 Town Center project.) If the Board of

Supervisors wishes to validly approve the Town Center Project in the near future, it should

Page 5: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

5

direct the Planning Department to have such an independent environmental review

prepared.

IV. The analyses in the 1987 El Dorado Hills Specific Plan EIR and the 1995 Town

Center East Negative Declaration are outdated.

Even if the court ruled that the Planning Department’s subsequent mitigated negative declaration

procedure was correct, there is a second problem with tiering down from the 1995 Negative

Declaration: it is a Negative Declaration left over from the previous century! In addition, that

1995 Negative Declaration tiered off of an even older CEQA document: the 1987 El Dorado

Hills Specific Plan EIR. New information and changed circumstances have made the impact

analyses and mitigation assumptions in those documents obsolete.

For example, not one but two comprehensive general plan updates have been completed by the

County since those CEQA documents were produced. As noted above, those general plans have

reduced the roadway improvements and lowered levels of service standards in the specific plan

area, making traffic impacts greater than anticipated in 1987 and 1995. They have also delayed

the date of construction for roadway improvements.

To exacerbate this traffic impact, the funding gap for transportation impact mitigation and

improvements improvements has grown over time. Since the 1995, new traffic analyses and fee

program reviews have painted a substantially bleaker picture of the traffic future for El Dorado

County. In 2004, the County adopted a general plan indicating that 14 road segments would be

allowed to operate at Level of Service F. In 2006, the County was unable to fully fund the road

improvements required for 20 years of growth under the 2004 General Plan. The TIM Fee

program was underfunded by $130 million. The anticipated result is that, despite spending over

$840 million on road improvements over twenty years, people in peak period traffic on 94 of the

184 road segments in the County will experience, “severe restrictions in speed and freedom to

maneuver,” “poor levels of comfort and convenience,” “frustration,” and “queued traffic

traveling in a stop-and- go fashion.” (See 2004 General Plan, p. 56, description of LOS D, E,

and F; 2006 TIM Fee Program Environmental Review.) The El Dorado County Regional

Transportation Plan 2010 – 2030 estimates that the funding shortfall for roads needed through

2030 is now at $339 million. (RTP, Chapter 13, Table 13-5, p. 15.) It is this future of congested

roadways and unfunded roadway improvements that the Town Center Apartments would be

constructed in.

For another example, the county has completed multiple housing elements over the intervening

decades, repeatedly failed to achieve the affordable housing targets, and yet no affordability

covenants are included in the proposed project. (See Housing Elements covering years 1987 –

2014.)

In addition, the recent Grand Jury Report indicated that the County has not been enforcing its

grading ordinance. Thus, the County’s promise to mitigate impacts by applying the grading

ordinance to the proposed project is highly questionable, in the absence of independent

Page 6: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

6

monitoring and enforcement. (Exhibit 3: Grand Jury Report on failure to enforce grading

ordinance.)

Thus, the outdated analyses in the 1987 El Dorado Hills Specific Plan EIR and the 1995 Town

Center East Negative Declaration cannot form the basis of the analyses in the SMND for the

Town Center Apartments.

V. Project improvements are needed to avoid the preparation of an EIR.

When a proper initial study is performed independent of the prior CEQA reviews, an EIR will be

required if a “fair argument” can be made, based upon substantial evidence in the record, that the

proposed project may have significant impacts. (California Native Plant Society v. County of El

Dorado (App. 3 Dist. 2009) 170 Cal.App.4th

1026, 1058.) On the other hand, if the project were

properly improved to avoid these impacts, the time and expense of an EIR could be avoided.

As noted in comments on the project, a fair argument can be made that the project may have

significant impacts in its current form. The County Sheriff noted that the project poses

significant impacts on law enforcement services. Neighbors have noted the significant traffic

impacts of the project, and the long lead time for the mitigation measures. Recent reports

indicate that the cumulative impacts of water supply are a problem countywide, and that various

county officials disagree over how and whether to seek additional supplies. (Exhibit 4: Article

on cumulative water shortage.)

The County and the applicant would be wise to revise the project and its conditions to fully

address these issues and avoid the need for an EIR.

VI. Listen to the advice of the APAC and Planning Commission

Given the failure of the County’s infrastructure development and mitigation plans to date for the

El Dorado Hills Specific Plan area, given the ever growing funding deficit for road

improvements, given the long delays and uncertainty regarding the construction of the necessary

infrastructure and service capacity, and given the partial reliance on environmental reviews that

are 27 and 19 years old respectively; the Area Planning Advisory Committee and the Planning

Commission were wise to recommend denial of this project at this time. The Board would be

wise to direct the Planning Department to work collaboratively with the project proponent

and concerned citizens to modify the proposed Town Center Apartments project to better

address the concerns raised by the Area Plan Advisory Committee, the Planning

Commission, and concerned citizens.

Page 7: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

7

VII. The County will find it faster and cheaper to fix the environmental review and

project approval documents than to litigate the project approval.

We are confident that the County could complete the needed project approval and approval

analyses by this spring, thus setting the stage for lawful project approvals in time for the

construction season. However, should the County approve the Town Center Apartments on

December 2, and thereby force resolution of the issues by the thorough yet slow-moving courts,

we anticipate that these issues will cloud future project approvals in the El Dorado Hills Specific

Plan Area for the next three to four years.

VIII. Provide a hearing that affords a meaningful opportunity to be heard, and the

time for thoughtful Board deliberation.

The meeting agenda for December 2 indicates that individual comments are limited to 3 minutes,

and that individuals speaking for a group are limited to 5 minutes. In addition, Board permission

is needed to speak more than once.

As should be evident from this letter, the proposed project is a matter of substantial importance

to the residents of the area. For some, their home is their largest single investment. Any

government decision that could impair the value that property should be preceded by a hearing

that provides sufficient procedural due process, including a meaningful opportunity to be heard.

The project proponent also has property interests at stake, and deserves a similar meaningful

opportunity to be heard. I respectfully request that the Board provide greater leeway in

speaking time limits for this hearing. I would also ask that the Board provide me with an

opportunity for rebuttal and sur-rebuttal following the presentations by staff and the

project proponent. If the hearing needs to be continued to another date to provide for these

extended speaking opportunities, I would appreciate such a continuance.

In addition, I recognize that it is important for the Board to deliberate thoroughly on this matter.

Whenever there is a risk of litigation, the Board is wise to take the time to get a thorough

examination of the issues from County Counsel. Rather than rushing the decision, I encourage

you to take the time to get advice from County Counsel in closed session prior to voting on this

matter. If the hearing needs to be continued to provide for such thoughtful deliberation, I

encourage you to so continue the hearing. Please keep a copy of this letter and the attached

exhibits for the administrative record. Please incorporate into the administrative record the

documents referenced in this letter that are already in the possession of the County. A list of

these documents follows.

Thank you for your time and attention to this very important matter. As expressed during the

past hearings on this project, many believe that a mixed-use project could be designed for this

site that meets the objectives of the proposed project, while also eliminating most of the valid

public concerns. I believe that if this project is instead approved with all of its current flaws, it

will easily get bogged down in time consuming and costly litigation. Your choice and your

leadership will determine the outcome.

Page 8: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

8

Sincerely,

Thomas P. Infusino

cc. County Counsel, County Planning Director

Exhibits Incorporated by Reference

We incorporate by reference, into the record of proceedings for the approval of

the proposed Town Center Apartments, those documents, in their entirety, that are

already in the possession of the County, and are relevant to the County’s

compliance (or lack of compliance) with land use and environmental law.

The General Plan(s) under which the El Dorado Hills Specific Plan and the Town

Center East project were approved.

El Dorado Hills Specific Plan and Final EIR

2006 TIM Fee Program Environmental Review

El Dorado County Regional Transportation Plan 2010 – 2030

Housing Elements covering years 1987 – 2014

2004 General Plan

2004 General Plan FEIR

2004 General Plan Findings

Superior Court Ruling Upholding the 2004 General Plan Findings

2014 TGPA/ZOU DEIR

Page 9: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

9

Additional Exhibits

Exhibit 1: El Dorado Hills Specific Plan Final EIR, Figure 7-21, page 2-2.

Page 10: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

10

Exhibit 2: Compare: Britzman, Town Center East Staff Report; to Subsequent Initial

Study Checklist, Town Center Apartments.

Page 11: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

11

Page 12: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

12

Exhibit 3: Grand Jury Report on failure to enforce grading ordinance.

EL DORADO COUNTY GRAND JURY, 2013-2014 E L D ORADO C OUNTY F AILS TO E

NFORCE I TS G RADING , E ROSION AND S EDIMENT C ONTROL O RDINANCE Case

Number GJ-13/14-18

REASON FOR REPORT

The Grand Jury received a number of complaints involving improper grading of private property.

Three specific complaints were investigated and addressed in three separate reports. One

involves grading of a rural property, another involves grading of a suburban property and the

third is grading by a commercial property owner. In each instance, persons other than the

property owner suffered damage as a result of the county’s failure to ensure compliance with its

Grading Ordinance. The investigations of those cases caused the Grand Jury to question if there

was a pattern and practice of failing to comply with the County Grading Ordinance.

The Grand Jury found that it did.

BACKGROUND

The Ordinance

The El Dorado County Grading, Erosion, and Sediment Control Ordinance (hereinafter “the

Ordinance”)

…for the purpose of regulating grading within the unincorporated area of El Dorado County to

safeguard life, limb, health, property and public welfare; to avoid pollution of watercourses; and

to ensure that the intended use of a graded site is consistent with the El Dorado County General

Plan, any Specific Plans adopted thereto, the adopted Storm Water Management Plan, California

Fire Safe Standards and applicable El Dorado County ordinances including the Zoning

Ordinance and the California Building Code. (Section 15.14.110)

“This ordinance shall be implemented and enforced by the County…” (emphasis added)

A grading permit is required for all grading activities in the unincorporated area of El Dorado

County unless a specific exemption applies. (Sections 15.14.130 and 15.14.140). An exemption

did not apply to any of the specific instances investigated by the Grand Jury.

The Ordinance requires permit applications to include specific informational items. (Section

15.14.200)

Fees collected when a permit is issued are used to fund enforcement of the Ordinance. Violation

fees of twice the regular permit fees are required whenever grading is done in violation of the

Ordinance or without an approved permit. The language of the Ordinance is not discretionary; It

mandates that this violation fee be charged. (Section 15.14.230 E)

Page 13: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

13

It prohibits grading activities that cause or have the potential to result in itemized hazards

including a threat to neighboring property or degradation of water quality. (Section 15.14.290)

The county is authorized to enter private property and conduct work necessary to abate and

repair hazards from unlawfully created conditions. The County may conduct such work either

using its own employees or through a licensed contractor. The County is required to bill the

property owner for costs incurred and is authorized to recover those costs through a lien on the

property and other legal means. (Section 15.14.410)

Enforcement of the Ordinance

Review of the permit application and subsequent inspection of the grading site only happens

after permit fees are paid. Otherwise, no action is taken. When work is initiated without a valid

permit a stop work order may be issued. If work is completed prior to issuance of a stop work

order or if work continues without a valid permit, there is no inspection of the work done. Thus,

someone who wants to perform work not authorized by county ordinances could well decide to

not seek a permit in order to get away with that unauthorized work.

County employees interviewed were aware of the legal authority to charge violation fees but not

that those fees were mandatory rather than discretionary. Further, violation fees were rarely

charged and suggested that it would discourage the public from seeking a permit and encourage

performing work without proper permits.

County employees were unaware of the County’s authority to conduct necessary remedial work

at the property owner’s expense and knew of no instance when this action was taken.

Why is the Grading Ordinance Not Enforced?

Grading in violation of the Grading Ordinance resulted in substantial harm to property owners

adjacent to or affected by improper grading in each of the cases investigated by the Grand Jury.

The Grading Ordinance gives the Department of Transportation significant authority to correct

improper grading. This authority could be a very effective tool for protecting other affected

property owners if it were used, but it is not …. Why not?

Both County staff and officials reported that they perceived it to be the will of the Board of

Supervisors that the Ordinance not be enforced. They stated that El Dorado is a property rights

county; the will of the Board of Supervisors is that property owners not be burdened by strict

compliance with requirements perceived to be onerous for some property owners. Several

witnesses reported they believed the Ordinance imposed excessive burdens on property owners

maintaining rural access roads

The public appears to understand that the Ordinance is not enforced. Neither of the contractors

who performed illegal grading in Report No. 13-15 or 13-16 felt required to obtain a permit for

the grading they performed. In Report No. 13-16 the Contractor appears to have understood that

if he failed to pay the fee for a grading permit no action would be taken to enforce the terms of

the permit.

Page 14: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

14

The Ordinance is quite specific “…to safeguard life, limb, health, property and public welfare; to

avoid pollution of watercourses…” The Grading Ordinance of the County of El Dorado is

Chapter 15.14 of the County Code; it is the law of El Dorado County. Failure to enforce the

Ordinance is failure to enforce the law; that failure benefits property owners who act unlawfully

while denying the law’s specific protections to others. It leads to a perception of corruption on

the part of County officials and general disrespect for County government.

ACTIONS

Ordinance.

by the County’s failure to enforce the Ordinance.

Jury interviewed County employees responsible for implementing and enforcing

the Ordinance.

FINDINGS

1. When grading work is done in El Dorado County and no permit is obtained and no permit fee

paid, and the county is made aware of the work being done before the work is complete, the

county will issue a stop work order.

2. When work improperly continues after issuance of a stop work order or if work is completed

before a stop work order is issued, no enforcement action is taken.

3. Only payment of a permit fee triggers inspection of grading work performed.

4. Grading work performed where no permit fee is paid is not inspected.

5. El Dorado County does not enforce its Grading, Erosion and Sediment Control Ordinance.

6. The County’s failure to enforce its Grading, Erosion and Sediment Control Ordinance

encourages illegal grading to the detriment of other property owners and residents.

RECOMMENDATIONS

1. The Board of Supervisors should review the Grading, Erosion and Sediment Control

Ordinance and determine whether the Ordinance imposes overly burdensome requirements for

rural access roads.

2. If the Board of Supervisors determines the requirements for grading of rural access roads are

overly burdensome, it should amend the Ordinance to define appropriate requirements for the

grading of those roads.

Page 15: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

15

3. Whether or not the Ordinance is amended, the Grading, Erosion and Sediment Control

Ordinance should be enforced.

RESPONSES

Responses to both findings and recommendations in this Report are required by law in

accordance with California Penal Code §933 and §933.05. Address responses to:

The Honorable Suzanne N. Kingsbury, presiding judge of the El Dorado County Superior Court,

1354 Johnson Blvd., South Lake Tahoe, CA 96150.

This Report has been provided to the El Dorado County Board of Supervisors, Development

Services Department and Department of Transportation.

The Presiding Judge of the El Dorado County Superior Court additionally requests that the

responses be sent electronically as a “Word” file or “PDF” file to facilitate the economical and

timely distribution of such responses. Please email responses to the El Dorado County Grand

Jury at: [email protected]

Page 16: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

16

Exhibit 4: Article on cumulative water shortage.

Water & Power JPA on the bubble By Dawn Hodson

Mountain Democrat, From page A1 | November 19, 2014 |

Is the El Dorado County Board of Supervisors getting cold feet about going after additional

water rights?

That was the question hanging in the air as an update on the status of an application for

additional water rights turned into an extended discussion of whether or not the county

should continue to be a part of the effort.

Currently the county, the El Dorado Water Agency and the El Dorado Irrigation District are

part of a joint powers authority known as the El Dorado Water & Power Authority. EDWPA

is in the process of pursuing an additional 40,000 acre-feet of water rights for the county.

An update on the project was requested following action by the Board of Supervisors on Oct.

14 when it directed the Community Development Agency and County Counsel to “evaluate

the county’s continuing participation as a member agency of the El Dorado Water and

Power Authority.”

As part of that motion, Supervisor Santiago suggested holding a discussion of the topic at

the next regular meeting of EDWPA, which was Nov. 12. That meeting included all members

of the Board of Supervisors as well as the entire board of EID.

EDWPA’s roots

At the meeting, staff began with a history of EDWPA, noting it was originally formed as the

county’s negotiating arm during the relicensing of SMUD’s hydroelectric operation on the

Upper American River. Once those negotiations were concluded, EDWPA turned its

attention to securing additional water rights for the county.

However, Supervisor Shiva Frentzen said while the county only has one vote, it appeared it

was paying two-thirds of the cost of the project.

Fred Schaefer, who is EDWPA’s legal counsel, responded by saying the county acts more as

a pass-through mechanism for the money going to the Water Agency.

Page 17: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

17

The Water Agency has the statutory authority to impose an ad valorem tax countywide,

Schaefer said, but essentially that was replaced with Proposition 13, Prop. 8 and other

things, so consequently the county is the assessing and taxing authority and it distributes a

share to the Water Agency of funds the agency would have received if an ad valorem tax had

been passed to support it.

Clarifying the point further, Water Agency General Manager Dave Eggerton added that the

money the Water Agency receives doesn’t come from the county General Fund but is similar

to money the county collects and then distributes to special districts.

EID Director Greg Prada said his concern was that in supporting the EDWPA project,

ratepayers were being charged for future benefits, which he said was illegal.

However, EID Director George Osborne countered his argument, saying he believes the

money EID contributes to EDWPA comes from facility connection fees and not from

ratepayers. He suggested the Water Agency’s counsel talk to EID’s counsel to clarify the

issue.

Santiago went on to ask if EDWPA were abandoned, if it would affect the SMUD agreement

and subsequently the payment the county receives from that agreement. Schaefer

responded that even if the JPA were dissolved, the SMUD agreement would remain intact.

The price of dissolution

However, less clear was the question of how the application for additional water rights

would be affected if the JPA were dissolved.

Providing more background on EDWPA’s mission, Eggerton said the first time they tried for

additional water rights was in 2008. But the EDWPA board decided to change direction

after its application ran into considerable opposition. The cost of that initial effort was $3.1

million.

In 2013, the board adopted a resolution to submit a revised application to the state water

board. Subsequently environmental work was approved and a contract awarded for the new

application.

With the project divided into three phases and phase one expected to be completed by next

year, Eggerton put the total price at between $8.1 million to $11.7 million by the time it’s

finished. He said as of now, the Water Agency has enough money to complete phase one

regardless of what the county decides to do.

Emphasizing that the county won’t have enough water at build-out if the application is not

successful, Eggerton said, “I believe this is the paradigm for agencies like ours to get

Page 18: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

18

additional water supplies. We need to pursue it because we have no groundwater supplies in

time of drought.”

According to an updated report just released by the Water Agency, El Dorado County’s

western slope is expected to be short approximately 69,000 acre-feet of water per year at

full build-out even considering state-mandated water conservation.

Eggerton added that if the JPA is dissolved and the Water Agency has to take over the

application, its budget and staff time would have to be almost entirely devoted to the

project.

Criticizing the idea, Osborne said dissolving EDWPA would eliminate open and frank

discussions among the different partners. “The real thing is what does the JPA cost?” he

asked. “Virtually nothing. Staffing is done by the Water Agency. There’s very little cost to

operating the JPA. What do you save by disbanding it and losing those other benefits?

That’s the real issue.”

The budget for EDWPA is only $15,000. In a separate category are funds for the water rights

project, which is $3.16 million this year. The budget for the Water Agency, which is separate

from EDWPA, is $4.3 million.

How soon?

However, seeming to push for an end to the JPA, Supervisor Shiva Frentzen asked what was

the earliest date it could be dissolved with both she and Santiago less than happy to hear

that the JPA would probably have to continue through the end of this year.

Supervisor Ron Mikulaco interjected he didn’t want to discuss the merits of the application

or the need for more water rights, but rather what happens if the JPA dissolves.

“The JPA spent $3.1 million on the original application with nothing to show for it,” he said,

adding that he believes the real cost of the water rights application will be closer to $11

million. “It’s a big risk and we might have nothing to show for it,” he said.

In response, Osborne said EDWPA did get something for its $3.1 million. “We learned an

expensive and valuable lesson,” he said. “With 53 percent of the Legislature coming from

below the Tehachapi, if we don’t acquire these rights, the chances of our ever being able to

do so again are probably nil … Yes, it’s expensive and there’s no guarantee, but we are

getting a positive response from the staff at the state water board.”

Schaefer added that of the $3.1 million originally spent, about $1 million was spent on the

filing fees for the application so not all of the $3.1 million was lost.

Page 19: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

19

Schaefer went on to suggest that one alternative would be to harmonize the cost sharing and

inter-county coordination agreements with the Water Agency as the applicant under a

dissolved JPA. Using this approach, if the water rights application was successful, the Water

Agency would be the designated representative with SMUD to control the water that EDC

received, with the water stored in SMUD’s reservoirs. The Water Agency would also handle

the allocations or sales of water as a wholesaler, not a purveyor of water.

However , EID Director Alan Day questioned whether it was a good idea to pursue

additional water rights at all, saying they are massively over-subscribed in the state and

EDWPA’s application would just be one more. The state water board is also pushing to

regulate a lot of these rights, he said, so we might spend a lot of money and then have the

state telling us what to do with the water anyway.

However, EID Director Dale Coco pointed out that the state water agency can’t do anything

about stored water and “that’s the beauty of the water rights application EDWPA is putting

together,” he said.

‘This is it, ladies and gentlemen’

Arguing against dissolution of the JPA, Coco went on to say doing so would preclude the

county and EID from getting together to hash things out in closed session. “Instead

decisions will be left to administrators and attorneys,” he said.

Coco maintained that about one-third of the additional water would go to EID with the rest

going to agricultural interests or to those outside the county. “Should we give up a vehicle

that allows us to do business?” he asked, saying that some of the information being

circulated was based on speculation or assumption.

“This is it, ladies and gentlemen. This is it,” said Coco. “The American River is 100 percent

allocated … (and) we don’t have enough water to complete our General Plan.”

Urging the county not to be hasty in its decision, Coco asked members of the Board of

Supervisors to wait until they have solid supply and demand data. “Let’s take our time and

look at things objectively,” he said. “We’re the stewards of this county for the next 50 years,”

adding that the wrong decision could leave the county high and dry. Coco also reminded

everyone that if the water rights application is not successful, their other option would be

expanding the reservoirs which could cost $200 million to $300 million per reservoir.

Closing out the discussion were comments from members of the public.

One of those speaking was former supervisor Jack Sweeney, who is part of a group called

Citizens for Water. Echoing comments made earlier, he said the county only supplies one-

third of the cost of the project. “If you dissolve the JPA, that money will go back to the

Page 20: Thomas P. Infusino, Esq. Pine Grove, CA 95665 Board of ... · City of Rancho Cordova (App. 3 Dist. 2009) 172 Cal.App.4th 603.) These decisions include, specific plan amendments, rezones,

20

taxpayers,” he claimed, saying it’s a tax collected by the county on behalf of the Water

Agency.

Sweeney expressed concern that the water rights project would be killed just like the SOFAR

Project and he urged the members of the JPA to think long-term, saying that if SOFAR had

gone through, the county would have about $50 million a year in profits that could have

gone towards road, parks and other uses.

Saying the benefits from the water application will show up 20 to 30 years from now, he

warned, “We can’t fail again.”