time and cost integration and control

Upload: richard-williams

Post on 06-Apr-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/2/2019 Time and Cost Integration and Control

    1/26

    281BE Project Management

    Project Control

    Time and Cost Integration

  • 8/2/2019 Time and Cost Integration and Control

    2/26

    281BE Project Management

    Outline

    The need for project control

    Traditional project control need to

    integrate expenses and progressEarned value analysis

    EVA application to project scenarios

    Earned value reporting

  • 8/2/2019 Time and Cost Integration and Control

    3/26

    281BE Project Management

    Project Control System

    Project Objectives, Corporation Management Decisions,Operating Policies Influences

    PlanningSchedule

    CostResource

    Authorisation forImplementation

    Update the

    Plan

    Measurement

    EvaluationDecision

    Implementation/

    Execution

    External Factor Influences

    Planning

    Control

  • 8/2/2019 Time and Cost Integration and Control

    4/26

    281BE Project Management

    Why do we need project control?

    Collecting information, making decisions and

    taking (corrective) actions based on this

    information

    while there is still enough time!!

    Controlling project to discover:

    What has happened?

    What is happening? What should have happened?

    What should be happening?

  • 8/2/2019 Time and Cost Integration and Control

    5/26

    281BE Project Management

    How can we exercise project control?

  • 8/2/2019 Time and Cost Integration and Control

    6/26

    281BE Project Management

    S-Curve

    Draw S-curve based on:

    Early start for all activities

    Late start for all activities

  • 8/2/2019 Time and Cost Integration and Control

    7/26

    281BE Project Management

    S-Curve

  • 8/2/2019 Time and Cost Integration and Control

    8/26

    281BE Project Management

    S-Curve

  • 8/2/2019 Time and Cost Integration and Control

    9/26

    281BE Project Management

    Consider.

  • 8/2/2019 Time and Cost Integration and Control

    10/26

    281BE Project Management

    Traditional Project Control

    Often based on a single measure

    Rely on variance analysis (e.g. cost or

    time variance)

    The difference between planand actual

    at a particular point of time

    No information about how much workcompleted/progress

    Insufficient measure of control

  • 8/2/2019 Time and Cost Integration and Control

    11/26

    281BE Project Management

    Why integrate expenses and progress?

  • 8/2/2019 Time and Cost Integration and Control

    12/26

    281BE Project Management

    Earned Value Analysis

    Planned Value (PV)baseline

    Budgeted Cost of Work Scheduled (BCWS) to be completed on

    an activity

    What I plan to do

    Earned Value (EV)

    Budgeted Cost of Work Performed (BCWP) on the schedule

    activity

    What I did

    Actual Cost (AC)

    Actual Cost of Work Performed (ACWP) on the schedule activity

    What I paid for

  • 8/2/2019 Time and Cost Integration and Control

    13/26

    281BE Project Management

    Earned Value Graph

  • 8/2/2019 Time and Cost Integration and Control

    14/26

    281BE Project Management

    Variance

    Cost Variance (CV)

    CV = EV AC

    Cost Performance Index (CPI) = EV/AC

    Schedule Variance (SV) SV = EV PV

    Schedule Performance Index (SPI) = EV/PV

    Threshold Variance To flag problem areas

    Set as a percentage (e.g. +/- 5%)

  • 8/2/2019 Time and Cost Integration and Control

    15/26

    281BE Project Management

    Other Terminology

    Budget at Completion (BAC)

    Original estimate/ budget/ quotation

    Not including profit

    Estimate at Completion (EAC)

    Revised budget based on current productivity

    Estimate-to-Complete (ETC)

    ETC = EAC ACWP

    Compare with Cost-to-Complete

    Percentage Complete (PC)

    Measure of progress up to timenow

  • 8/2/2019 Time and Cost Integration and Control

    16/26

    281BE Project Management

    Forecasting EAC

    PC

    ACWPEAC

    BAC

    BACPC

    ACWPEAC

    therefore

    BACPCBCWPas

    BACBCWP

    ACWPEAC

  • 8/2/2019 Time and Cost Integration and Control

    17/26

    281BE Project Management

    Forecasting Estimated Time toCompletion

    Assuming unchanged productivity

    Actual Time Expended (ATE)

    Time from project start until timenow Original Duration (OD)

    SPISPI)(ATE-ODATECTimeE

  • 8/2/2019 Time and Cost Integration and Control

    18/26

    281BE Project Management

    Percentage Complete

    50 50 estimate

    50% assumed when the task starts, and remaining 50% when

    completed

    0 100 percent rule

    No credit until the task is completed

    Critical input use

    E.g. skilled labour, equipment/machine

    Proportionality rule Actual task time divided by total scheduled task time, or

    Actual cost divided by total budgeted task cost

  • 8/2/2019 Time and Cost Integration and Control

    19/26

    281BE Project Management

    Earned Value Table

    Act BAC BCWS PC BCWP ACWP SV CV EAC

    100 2000 1000 40 800 1200 -200 -400 3000

    200

    300

    Total

  • 8/2/2019 Time and Cost Integration and Control

    20/26

    281BE Project Management

    Example

    Activity BAC BCWS PC BCWP Status

    100 2000 1000 60% 1200 Ahead

    200 1000 900 80% 800 Behind

    300 1500 1000 67% 1000 On time

    Total 2900 3000

  • 8/2/2019 Time and Cost Integration and Control

    21/26

    281BE Project Management

    Extrapolation

  • 8/2/2019 Time and Cost Integration and Control

    22/26

    281BE Project Management

    Scenario: the project is running late and thecosts are over budget

  • 8/2/2019 Time and Cost Integration and Control

    23/26

    281BE Project Management

    Scenario: the progress is ahead of plannedand the costs are under budget

  • 8/2/2019 Time and Cost Integration and Control

    24/26

    281BE Project Management

    Scenario: the project is ahead, but the costsare over budget

  • 8/2/2019 Time and Cost Integration and Control

    25/26

    281BE Project Management

    Earned Value Reporting

    EV graph provides overview of status; tables providedetailed information

    Management response:

    SV(+), ahead of schedule

    SV(-), behind schedule

    CV(+), costs less than budget

    CV(-), costs greater than budget

    EVA should not be used in isolation, e.g. with float

    EV is only useful if the different between planned and

    actual is 10 to 15%

    EVA is also influenced by (overoptimistic) estimate!!

  • 8/2/2019 Time and Cost Integration and Control

    26/26

    281BE Project Management

    References

    Burke R., (2003) Project management

    planning and control techniques,4th ed. John Wiley & Sons, Chichester.

    Burke, R. (2007) Introduction to project management: one small step for the

    project manager. Burke Publishing.

    Hamilton, A. (2001) Managing projects for success: a trilogy. Thomas

    Telford Publishing, London. Lockyer, K. and Gordon, J. (2005) Project management and project network

    techniques, 7th ed. Pearson Education Ltd., Harlow, England.

    Meredith, J.R. and Mantel, S.J. (2006) Project management: a managerial

    approach, 6th ed. John Wiley & Sons, Inc., Hoboken, New Jersey.

    PMI (2004) A guide to the Project Management Body of Knowledge, 3rd ed.Project Management Institute, Pennsylvania.

    Popescu, C. and Charoenngam, C. (1995) Project planning, scheduling,

    and control in construction: an encyclopedia of terms and applications. John

    Wiley & Sons, Inc, New York.