title in aces division 01 robins afb general...

164
UHHZ160050 INDEX OF SPECIFICATIONS INDEX OF SPECIFICATIONS Page 1 of 4 DATE: 19 January 2017 Title in ACES NUMBER TITLE PAGES Division 01 ROBINS AFB General Requirements 01005 Statement of Work 01005-1 thru 01005-11 01020 (Design-build) Construction Design Performance 01020-1 thru 01020-23 Requirements Appendix A - Fire Protection and Life Safety Analysis No. of pages = 3 01030 (Design-build) Design after Award 01030-1 thru 01030-15 01040 Site Requirements 01040-1 thru 01040-13 01300 Submittals and Contractor-Furnished Items 01300-1 thru 01300-9 01310 CADD As-Built Drawings 01310-1 thru 01310-5 01501 Temporary Services - Contractor 01501-1 thru 01501-5 01502 Temporary Utilities and Services for Continued Occupancy 01501-1 thru 01501-5 01540 Green Procurement 01540-1 thru 01540-12 Attachment 3 No. of pages = 3 01560 Environmental Requirements 01560-1 thru 01560-32 01572 Construction & Demolition Waste Management 01572-1 thru 01572-6 01580 Safety Requirements 01580-1 thru 01580-6 01600 Product Requirements 01600-1 thru 01600-3 01700 Execution Requirements 01700-1 thru 01700-6 01730 Operations and Maintenance Data 01730-1 thru 01730-6 Edit Div. 02 46 specifications from UFGS to encompass work scope required for this project. Utilize the latest release of the applicable sections required. Below are the minimum specifications required add other UFGS specifications as required. See also requirements of Procedural Guide for Designers. Division 02 Existing Conditions 02 41 00 Demolition X-X thru X-X Division 03 - Concrete 03 11 13.00 10 Structural Cast-in-Place Concrete Forming X-X thru X-X 03 20 00.00 10 Concrete Forming X-X thru X-X 03 33 00.00 10 Cast-in-Place Concrete X-X thru X-X Division 04 04 20 00 Unit Masonry X-X thru X-X

Upload: lydien

Post on 31-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

UHHZ160050 INDEX OF SPECIFICATIONS

INDEX OF SPECIFICATIONS

Page 1 of 4

DATE: 19 January 2017

Title in ACES

NUMBER TITLE PAGES

Division 01 – ROBINS AFB – General Requirements

01005 Statement of Work 01005-1 thru 01005-11

01020 (Design-build) Construction Design Performance 01020-1 thru 01020-23Requirements

Appendix A - Fire Protection and Life Safety Analysis No. of pages = 3

01030 (Design-build) Design after Award 01030-1 thru 01030-15

01040 Site Requirements 01040-1 thru 01040-13

01300 Submittals and Contractor-Furnished Items 01300-1 thru 01300-9

01310 CADD As-Built Drawings 01310-1 thru 01310-5

01501 Temporary Services - Contractor 01501-1 thru 01501-5

01502 Temporary Utilities and Services for Continued Occupancy 01501-1 thru 01501-5

01540 Green Procurement 01540-1 thru 01540-12

Attachment 3 No. of pages = 3

01560 Environmental Requirements 01560-1 thru 01560-32

01572 Construction & Demolition Waste Management 01572-1 thru 01572-6

01580 Safety Requirements 01580-1 thru 01580-6

01600 Product Requirements 01600-1 thru 01600-3

01700 Execution Requirements 01700-1 thru 01700-6

01730 Operations and Maintenance Data 01730-1 thru 01730-6

Edit Div. 02 – 46 specifications from UFGS to encompass work scope required for this project. Utilize

the latest release of the applicable sections required. Below are the minimum specifications required –

add other UFGS specifications as required. See also requirements of Procedural Guide for Designers.

Division 02 – Existing Conditions

02 41 00 Demolition X-X thru X-X

Division 03 - Concrete

03 11 13.00 10 Structural Cast-in-Place Concrete Forming X-X thru X-X

03 20 00.00 10 Concrete Forming X-X thru X-X

03 33 00.00 10 Cast-in-Place Concrete X-X thru X-X

Division 04

04 20 00 Unit Masonry X-X thru X-X

UHHZ160050 INDEX OF SPECIFICATIONS

INDEX OF SPECIFICATIONS

Page 2 of 4

Division 05 - Metals

05 50 13 Miscellaneous Metal Fabrications X-X thru X-X

05 52 00 Metal Railings X-X thru X-X

05 12 00 Structural Steel X-X thru X-X

05 40 00 Cold Formed Metal Framing X-X thru X-X

Division 06 – Wood, Plastics and Composites

06 10 00 Rough Carpentry X-X thru X-X

Division 07 - Thermal and Moisture Protection

07 61 14.00 20 Steel Standing Seam Roofing X-X thru X-X

07 42 13 Metal Wall Panels X-X thru X-X

07 21 16 Mineral Fiber Blanket Insulation X-X thru X-X

07 92 00 Joint Sealants X-X thru X-X

Division 08 - Openings

08 11 13 Steel Doors and Frames X-X thru X-X

08 33 23 Overhead Coiling Doors X-X thru X-X

08 71 00 Door Hardware X-X thru X-X

08 81 00 Glazing X-X thru X-X

08 91 00 Metal Wall Louvers X-X thru X-X

Division 09 - Finishes

09 51 00 Acoustical Ceilings X-X thru X-X

09 90 00 Paints and Coatings X-X thru X-X

Division 10 - Specialties

10 44 16 Fire Extinguishers X-X thru X-X

10 14 00.20 Interior Signage X-X thru X-X

Division 11 - 14

UHHZ160050 INDEX OF SPECIFICATIONS

INDEX OF SPECIFICATIONS

Page 3 of 4

Division 21 – Fire Suppression

21 13 13.00.10 Wet Pipe Sprinkler System, Fire Protection X-X thru X-X

Division 22 – Plumbing

22 00 00 Plumbing, General Purpose X-X thru X-X

Division 23 – Heating, Ventilation and Air Conditioning

23 00 00 Air Supply, Distribution, Ventilation and Exhaust Systems X-X thru X-X

23 03 00.00 20 Basic Mechanical Materials and Methods X-X thru X-X

23 05 93 Testing, Adjusting, and Balancing for HVAC X-X thru X-X

23 82 00.00 20 Terminal Heating and Cooling Units X-X thru X-X

Division 25

Division 26 – Electrical

26 20 00 Interior Distribution System X-X thru X-X

26 28 01.00 10 Coordinated Power System Protection X-X thru X-X

26 41 00 Lightning Protection System X-X thru X-X

26 51 00 Interior Lighting X-X thru X-X

26 56 00 Exterior Lighting X-X thru X-X

Division 27 – Communications

Division 28 – Electronic Safety and Security

28 31 64.00 10 Fire Detection and Alarm System, Addressable X-X thru X-X

Division 31 – Earthwork

31 00 00 Earthwork X-X thru X-X

31 31 16 Soil Treatment for Subterranean Termite Control X-X thru X-X

31 32 11 Soil Surface Erosion Control X-X thru X-X

Division 32 – Exterior Improvements

32 11 23 Aggregate and/or Graded Aggregate Base Course X-X thru X-X

UHHZ160050 INDEX OF SPECIFICATIONS

INDEX OF SPECIFICATIONS

Page 4 of 4

32 12 16 Hot Mix Asphalt for Roads X-X thru X-X

Division 33 – Utilities

33 30 00 Sanitary Sewers X-X thru X-X

Division 34 – 48

TOTAL NUMBER OF PAGES (Including Index) = 164

<<<<< END OF INDEX >>>>>

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 1 of 11

PART 1 – GENERAL

1.01 STATEMENT OF WORK: This is a general overview of the Design-Build project. Also see

Section 01020, Construction Design and Performance Requirements, and 01030, Design after Award.

A. Location: Accomplish work at Robins AFB, Georgia

B. Price: The original contracted price shall include special work times for utility outages and

repair of damages.

C. Contract Documents: Follow details shown by the specifications and drawings, current

version of the Robins AFB Facility Standards, UFCs, ETLs, applicable UFGS sections and

building code requirements.

D. Liquidated Damages will be applicable for this task order. If the contractor fails to complete

the work within the time specified in the contract, the Contractor shall pay Liquidated Damages

to the Government in the amount of $332.99 for the first day of delay, and $269.02 per day for

each subsequent calendar day of delay until the work is completed or accepted.

E. Design Phase Requirement: North wing of building will be vacated during construction, but

south wing shall be in full operation. Contractor shall identify all hazards during the design

phase that may have an adverse effect on building occupants, equipment, building systems, etc.

in the south wing during the construction phase. (For example: Project that includes working on

roof over occupied space: cutting insulation, replacement of existing screws can cause dust

particulates and other airborne particles that may be a hazard for personnel and/or equipment

below.) Contractor shall provide design to contain all hazards to building occupants, equipment,

building systems, etc. for contractor to utilize during the construction phase.

F. Project Scope, Objectives and Criteria: This is a Design-Build contract for both Design and

Construction. The general scope of the work includes the following:

1. Scope:

a. General Scope: Renovate north section of Bldg. 673 to accommodate C5

noseplug workload. Roof and wall panel work shall be limited to the north

section with transitions as required to tie into the south section. Lightning

protection work shall be for the entire building. Work requiring utility outages

shall be confined to non-standard working times (nights and/or weekends) to

prevent disruptions to flash jet operations. Provide all additional work as required

for a functional usable facility.

b. Existing Conditions: Bldg. 673 consists of two wings. The north wing is

currently used as a warehouse and is the area for renovation. The south wing is

currently used as a production area for flash-jet operations. Roof insulation at the

north wing has sustained water damage primarily at the eaves and needs to be

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 2 of 11

removed. Roof panels on the north wing have probably also been damaged

(hidden) as a result.

c. Abatement of Hazardous Materials: No hazardous materials have been

identified within the scope of this work.

d. Demolition:

1) Remove existing handicap ramp within the building.

2) Remove existing metal roof, roof accessories, roof insulation and lightning

protection for the north wing. Check existing lightning system on the

south wing and the entire lightning ground system for compliance,

removing any items that require reworking/replacement.

3) Remove north building exterior wall panels, exhaust fan, personnel door

and one overhead door. Remove north endwall structure and foundation

as required to restructure for new overhead door and personnel door.

4) Remove wall insulation and wall panels for remaining walls on the

renovation area (north section of building).

5) Remove existing lighting. Remove existing conductors from air switch to

transformer. Remove existing conductors/conduit/switchgear/transformer

as required for new service. Remove any conduit/conductors/devices

which are not required to remain in place (do not abandon in-place).

6) Remove existing eyewash fountain/shower.

7) Remove sufficient existing floor slab and exterior pavements as required

for the installation of new plumbing and sanitary sewer.

8) Remove existing sanitary sewer as required for the ramps.

9) Clean existing structural components in Production Area (base bid).

Protect all existing work to remain from damage.

10) Remove existing pavement on the east side as required to install new

Mechanical Room landing and steps. Removal shall include pavements

requiring re-sloping to prevent ponding adjacent to new ramps and steps.

11) Remove existing pavement on the west side of the building sufficient for

installation of the new handicap ramp, canopy and north vehicle ramp.

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 3 of 11

12) Clean and remove paint at existing metal railings at vehicle ramps and all

existing bollards adjacent to renovated area (interior and exterior).

Provide smooth surface properly prepared for repainting.

13) Provide all additional work required for demolition of miscellaneous items

as shown on the drawings and in conjunction with the overall work scope.

Also note items required for Alternates 1 and 2 as appropriate.

e. New Work:

1) Construct new vehicle ramp on north end of building.

2) Install new concrete handicap ramp with railings and awning on west side.

3) Install new concrete landing, steps and railings on east side of building at

Mechanical Room.

4) Construct new PPE and Personal Locker rooms within the building. New

rooms will include heat, cooling, lighting, electrical, plumbing

(w/fixtures), fire alarm (incl. strobes/horns) and fire suppression. Rooms

will have lay-in ceiling with cleanable fiberglass panels. Roof of rooms

shall be metal purlins with prefinished PBR metal roof panels and trim

(provide flashing for weathertight system). Fire alarm and suppression

shall be connected to existing system (requires NICET IV professional for

design). Construction shall be properly sealed to allow for required

positive and/or negative pressures (see also Section 01020).

5) Install new overhead and underground plumbing as required to service

new plumbing fixtures. Patch concrete slab and pavements as required to

match existing.

6) Install new metal roof (approx. 6,000 sf), substructure (to match existing

south roof slope), roof accessories and insulation. All roof insulation shall

have exposed white PSKP scrim. Substructure shall be painted to match

existing structural steel.

7) Install new wall panels and insulation on renovated north section of

building. All wall insulation shall have exposed white PSKP scrim.

8) Install lightning protection system for the north wing and install

new/replacement components on the south wing roof and grounding

system for a complete fully compliant system. Install additional

grounding components as needed for full code compliance. Installation

shall have 3rd party certification.

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 4 of 11

9) Install new north building exterior endwall and footings to accommodate

OH and personnel doors.

10) Install new overhead coiling door and personnel door on north end of

building.

11) Install new electrical service (conductors/conduit/transformer/etc.), power

and lighting.

12) Relocate existing sanitary sewer as required for ramps.

13) Install new emergency eyewash/shower. Unit shall be CSA certified to

meet ANSI Z358.1 with water and drain connections.

14) Patch and repair all damage to existing pavements, including any re-

sloping necessary to prevent ponding adjacent to new ramps and steps

(replace with like material).

15) Provide all additional work required for a complete renovation as shown

on the drawings and in conjunction with the overall work scope. Also

note items required for Alternates 1 and 2.

G. Bid Schedule and Alternates:

1. General: The alternates below will be applied to the Base Bid and are shown on the

Bid Form. Alternates 1 and 2 are mutually exclusive – only one of the two will be

executed (at least one of these is required for a complete project). These alternates apply

only to the HVAC for the main Production Area. HVAC requirements for the PPE and

Locker Rooms are included in the Base Bid (units shall be sized to accomplish air

pressure requirements of 01020, 9.3.5). Alternates for this project are listed below.

2. Alternate 1- Ventilation and Heat Only: Remove all existing intake louvers, exhaust

fan and heaters. Install new exhaust fans with louvers, guards and exterior rain shrouds.

Install new motorized intake louvers interlocked with exhaust fan for ventilation.

Interlock ventilation system with fire alarm system. Ventilation requirements shall be

calculated for the new area use requirements (increased capacity, both size and number of

units, may be required). Install new radiant heaters.

3. Alternate 2 – Heating and Cooling: Remove all existing intake louvers, exhaust fan

and heaters. Install new DX split unit heat pump system with emergency heat strips and

associated ductwork/dampers for even distribution. Close openings left from the removal

of louvers and exhaust fan with metal wall panels, framing and insulation (provide all

required flashings).

H. Project Requirements:

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 5 of 11

1. The contractor shall provide the technical knowledge and skill necessary to perform

services to meet standards set forth in this Statement of Work for base facilities, equipment and

systems and at a minimum meet manufacturer’s requirements.

2. All stored equipment shall be stored and protected in accordance with manufacturer’s

printed instructions.

3. This project will require daily reports to be filled out daily and submitted to the

project manager on a weekly basis. Daily reports at a minimum shall contain the following

information,

Amount and type of work accomplished

Materials delivered to the site

Weather conditions and impact to work and schedule

Labor workforces on site

Construction equipment on site

Safety inspection performed and violations noted

Any outstanding issues, i.e. delays, RFIs, etc.

4. All items shall be installed in accordance with the manufacturer’s printed installation

instructions unless the Base Facility Standards, specifications, drawings, contract clauses,

schedule, attachments, manufacturer’s requirements, and other contract documents are more

stringent. The most stringent requirement shall be met at no additional cost to the Government.

If meeting the more stringent requirement will void the manufacturer’s warranty the contractor

shall notify the Contracting Officer and the inspector prior to voiding the warranty.

5. Coordination shall be required between different disciplines.

I. Evacuation: Before fencing off the construction area, notify the Contracting Officer

in writing 30 days before ready to start so that Contracting Officer’s Representative and Project

Manager can notify appropriate personnel.

J. Physical Security:

1. The contractor shall be responsible for safeguarding all government personnel and

property being modified or adjacent to the new work. The contractor shall identify any existing

problems in writing prior to start work.

2. At the close of each work day, all government facilities, equipment, and materials

shall be secured and back in operation unless agreed on prior to the work starting. The

contractor shall be responsible for controlling access into an area that has been turn over to them

for construction.

K. Contractor Operations: Comply with Occupational Safety and Health Administration

(OSHA), Corps of Engineers Safety Manual (EM 385-1-1), the contract safety provisions will be

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 6 of 11

listed in the Appendix ‘C’, Air Force Occupational Safety and Health (AFOSH) Standards, and

National Fire Protection Association (NFPA) standards.

1. Contractor Employees:

a. Compliance with OSHA and other applicable laws and regulations for the

protection of contractor employees is the obligation of the contractor.

b. The contractor shall furnish to each of his/her employees a place of

employment that is free from recognized hazards.

c. The contractor shall brief his/her employees on the safety requirements of this

contract and on hazards associated with prescribed tasks.

d. This contract shall in no way require persons to work in surroundings or under

working conditions that are unsafe or dangerous to their health.

e. The contractor must coordinate and perform work so as not to impact the

safety of government employees or cause damage to government property.

f. This requires providing personnel with protective equipment and associated

safety equipment as may be necessary.

g. The contractor must also protect government personnel from hazards

generated by the work.

2. Contractor Badges: All employees to enter Robins AFB shall have government

provided badges. Contact the Project Manager/Badging Agent for the current badge application

form. Badge request shall be submitted a minimum of 10 days prior to the employee’s arrival.

All badges shall be returned to the Project Manager/Badging Agent at the end of the contract or

pay a $50.00 fine.

3. Fire Reporting:

a. Brief all workers and subcontractors as to the location of telephone and fire

alarm pull stations.

b. Report all fires as soon as discovered. The fire reporting number for on Base

phones is 911. The fire reporting number for off Base phones is 478-222-2900. The caller

should give his or her name and location of what is on fire. Also, give any other information that

may be requested by the Fire Department dispatcher. Stay on the telephone until the dispatcher

has obtained all necessary information.

4. Work shall be performed to, but not be limited to, the requirements set forth by the

following:

a. Robins AFB – Base Facility Standards (last edition)

b. Occupational Safety and Health Administration (OSHA)

c. All other applicable federal, state and local codes to ensure the system(s) are

installed in accordance with manufacturer’s specifications.

d. Air Force Occupational Safety and Health (AFOSH)

e. National Fire Protection Association

f. UFC 3-600-01 – Fire Protection Engineering for Facilities

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 7 of 11

g. The contractor shall perform all work to conform to the standards of the

government listed in paragraph above and per manufacturer specifications/ requirements.

h. Equipment and materials provided by the contractor shall match/meet or

exceed the specified equipment and material.

i. The contractor shall correct work not meeting these specifications at no

additional expense to the government.

j. The contractor shall coordinate work between the different disciplines.

5. Permits & Utility Outages:

a. It shall be the contractor’s responsibility to attend permit and outage request

meetings.

b. Before any “hot work” is performed on the job, an AF Form 592, USAF

Welding, Cutting, or Brazing Permit, must be obtained and displayed at the work site for the

duration of the permit.

c. Permits can be obtained by contacting the Civil Engineer Construction

Inspector/Army Corp Project Engineer assigned to the job. The Fire Alarm Dispatch Center can

be reached at 478-926-3487 or 478-926-3488.

d. Permits will be returned to the fire department, Bldg. 377 Fire Station Number

1, on the day they expire.

e. Adequate number and type of portable fire extinguishers, supplied by the

contractor, will be as close to the work as possible. At least a 10 lb ABC type fire extinguisher

shall be located at close proximity to the work being performed. In certain circumstances, one or

two 20 lb ABC type fire extinguishers will be required for hazardous locations. The fire

inspector issuing the welding/burning permit will determine the required level of protection at

the time of permit issuance.

f. A digging permit will be required before any digging, driving of stakes or post

starts.

g. Digging Permits are obtained on Monday at 0800 hours of each week at

building 1555 break area. If Monday falls on a holiday, the permits will be issued on Tuesday

following that Monday.

h. Utility Outages will be signed off on during the weekly outage meeting held

on Wednesdays at 1000 hours in building 1555. Request utility outages in writing to the Base

Civil Engineer, with a copy to the Contracting Officer a minimum of 21 days before the

proposed outage.

i. Outages shall be scheduled at the Government’s convenience and may be at

times other than normal working hours. For example, the times may be on weekends or during

the second and third shifts (including holidays, holiday weekends, and work curtailment days).

These are at no additional cost to the Government.

j. These hours are subject to change.

6. Superintendent: A full time Superintendent is required for this delivery order.

a. The Superintendent shall be a non-working superintendent. The

superintendent shall be on site at all times when any contractor or subcontractor personnel are on

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 8 of 11

site. The superintendent must be on site at all times and available to the Government and be

totally aware all aspects of the project.

b. The contractor shall provide the Contracting Officer a letter designating a

competent person as site superintendent. The letter shall state that the superintendent has full

authority to act for the Contractor and will be the primary Point of Contact for the Government.

The Government reserves the right to disapprove the proposed superintendent.

c. The Government through the Contracting Officer or Technical Representative

of the Contracting Officer (CEA Project Manager) reserves the right to shut down all Contractor

site activities if the superintendent is not on site at such times. Site work shall not resume until

the superintendent has returned to the site. Several violations of this requirement are cause for

termination for default.

7. Site, Maintenance, Clean-up and Restoration:

a. Maintain the work site in a neat, orderly and safe manner.

b. Remove scrap, waste and excess materials promptly. Provide signs,

barricades and lights as required to protect base personnel.

c. Do not allow trash and debris to accumulate and become unsightly. Sweep up

and collect in contractor-maintained disposal containers daily. Dispose of collected debris

weekly as a minimum.

d. Restore the project site to its final condition as required by the contract as

soon as possible.

e. After Beneficial Occupancy acceptance, cut all grassed areas a minimum of

(1) one time.

8. Rejected Work: If work performed by the contractor or a subcontractor does not meet

the plans, specifications, national standards, Base Standards, applicable codes, industry

standards, or acceptable workmanship the contractor shall accomplish the rework at no

additional cost to the government. Rework will be rescheduled for the next normal workday.

9. Equipment Damaged by Contractor: The contractor shall take before and after

photographs of the work site. If project site is located on the Airfield, the Contractor must obtain

from the Project Manager an Airfield Photo Authorization Letter. Prior to starting work the

contractor shall photograph, annotate, and bring to the attention of the inspector any noticeable

damage to equipment, ceilings, walls, doors and frames, furniture, floors etc. The location of the

annotated and photographs shall be well defined. If the damage is not documented then the

contractor shall be responsible for the repairs. The contractor shall jointly verify the status of the

fire alarm panel with the inspector prior to work starting. The contractor shall be responsible for

the repair of any of the above damaged in the process of performing their work. The repairs

shall utilize original manufacturer’s approved parts and comply with manufacturer’s printed

instructions/specifications. When the contractor finishes the repair, the equipment shall function

within acceptable manufacturer’s printed instructions/specifications. This shall be accomplished

at no cost to the Government.

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 9 of 11

10. Contract Qualifications: The contractor shall ensure that all employees performing

work under this contract have all applicable licenses and certification to work on the item(s) in

question. At a minimum, the contractor shall hold all applicable license(s) required by the state

for the type of work being accomplished. Supporting documentations shall be provided if

requested. At any time, work performed by a non-qualified person(s) may be rejected as

noncompliance and may not be acceptable.

1.02 CONTINUED OCCUPANCY:

A. Access: Building 673, north wing is vacated. However, the south wing (flash-jet shop) is

occupied and shall remain in full operation during the entire duration of the project. The contractor will

be given full access to the project area (north wing).

B. The work area is not in a restricted area.

C. Beneficial Occupancy: The Government reserves the right to take beneficial occupancy of

parts of the project area before the total project completion date. This is not final acceptance, and

identified deficiencies must still be corrected.

1.03 HOURS OF OPERATION:

A. Standard Work Hours: The contractor shall perform the services required under this contract

during the following hours: MON – FRI, 0730 –1600, except federal holidays and as noted herein. The

contractor may be allowed to work, with prior approval of the contracting officer representative,

extended hours to ensure timely completion of work at no additional cost to the government. Permission

to work extended/alternate hours shall be requested in writing a minimum of 5 days prior to when the

alternate work hours are desired. The Government reserves the right to deny the contractor’s request.

B. Holidays: The contractor is not required to work on the following days without written

approval: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence

Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. If the holiday

falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.

Permission to work on holidays shall be requested in writing a minimum of 5 days prior to when the

alternate work hours are desired. The Government reserves the right to deny the contractor’s request.

C. All references to days mean consecutive calendar days unless otherwise noted.

1.04 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s data in

lieu of the required certificate of compliance if he desires. The government requires manufacturer’s data

if an “X” appears under the “Mfg. Data Required” column.

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 10 of 11

B. All materials required for this delivery order shall be submitted as required per Section

01300. Form 66, in coordination with the final approved specifications, shall be completed by the

Design/Build A-E and included with the Final Design.

1.05 GOVERNMENT FURNISHED PROPERTY: Will not be provided in this project.

1.06 GOVERNMENT REPRESENTATIVES:

A. The contractor shall not make any changes to or deviate from the requirements listed in the

SOW unless approved in writing by the Contracting Officer.

B. The government project manager (PM) for the contract is David Trescott, 78 CEG/CENMP,

478-926-8838. The government construction inspector for the contract is Don Green, 78 CEG/CENME,

478-926-6960.

PART 2 - PRODUCTS

A. Sole Source Products - No sole source products are required.

B. Design Basis

1. Roof System: MBCI, Double Lok (3” trapezoidal standing seam (mechanically field

seamed), double lock).

2. Overhead Coiling (rolling steel service) Door: Overhead Door Co., Model 625.

3. Emergency eyewash/shower: Haws Drench Shower with Face/Eyewash.

4. CMU insulation: Core-Fill 500.

PART 3 – EXECUTION

3.01 COMMENCEMENT OF WORK

A. Construction Prohibition: Do not order any materials or start any construction until the

Contracting Officer has approved all related submittals.

B. Noncompliance Impacts: Any contractor costs resulting from noncompliance with these

requirements are the sole expense of the contractor. Noncompliance shall not be cause for contract

extensions or other considerations, but they may be cause for the Government to charge the contractor

for liquidated damages for all negative impacts upon the Government.

3.02 COORDINATION: The superintendent (or contractor on-site project manager) shall coordinate

work between different disciplines.

UHHZ160050 ___ STATEMENT OF WORK - 01005

Statement of Work

Page 11 of 11

A. Avoid conflicts between new mechanical, electrical, architectural, and civil systems. Also,

avoid conflicts between new work and existing structural or physical aspects or features of the facility.

Request guidance from the Contracting Officer, and then perform such work at no additional cost to the

Government.

B. Locations shown are approximate and may be moved if approved in writing by the

Contracting Officer. Show such variations on as-built drawings and do them at no

additional cost to the Government.

C. Manufacturers' recommendations and/or requirements, if more stringent than the

specifications and drawings, shall be followed at no additional cost to the Government.

3.03 AS-BUILTS: Also see Section 01300 (01310) for submittal items such as As-Builts that apply

to all projects.

<<<<< END OF SECTION >>>>>

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 1 of 23

INDEX 1. GENERAL 2. PROJECT DESCRIPTION 3. DESIGN REQUIREMENTS 4. SPACE REQUIREMENTS 5. CIVIL DESIGN 6. GEOTECHNICAL DESIGN 7. ARCHITECTURAL DESIGN 8. STRUCTURAL DESIGN 9. MECHANICAL DESIGN 10. ELECTRICAL DESIGN 1. GENERAL 1.1 Commencement of Work Immediately after notification of contract award, contact the Contracting Officer to set up the Pre-performance (Kickoff) Meeting at Robins AFB. The Contracting Officer or Project Manager normally will schedule to meet within 14 days after contract award. The usual attendees are the same as would be invited to a Pre-construction conference for a design-bid-build contract. See Section 01030. 1.2. Regulatory, Reference Requirements, Technical Criteria and Standards: See Robins Air Force Base Facility Standards, latest version. Use latest versions of all referenced UFC’s, UFGS specification sections, codes and other applicable criteria. 2. PROJECT DESCRIPTION 2.1. See Section 01005, Paragraph 1.01. 2.2. If additional land survey data is required beyond what the Government has provided, it will be the responsibility of the Contractor to obtain that survey data. 3. DESIGN REQUIREMENTS Design submittals will be as indicated in SECTION 01030, DESIGN SUBMITTAL REQUIREMENTS. Initial submittals establish the design and construction schedule. The contractor shall prepare complete construction documents for all work to be constructed in conformance with these drawings and specifications. Materials and equipment shall be limited to those specified except that where no specific material and equipment is specified or no basis of design is identified, the Contractor shall use materials and equipment in accordance with Robins Air Force Base Facility Standards (BFS), Unified Facilities Criteria (UFC), Air Force Instructions (AFI) and those identified in the standard unedited Unified Facilities Guide Specifications (UFGS). If specific materials are not identified in any of the above criteria, then the Contractor will use materials accepted within the construction industry and in compliance with these drawings and specifications.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 2 of 23

Materials selected shall be of high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy, and coordination of all designs, drawings, specifications, and other documents or publications upon which the designs and construction are based. All Design Drawings, specifications and calculations shall be prepared and stamped by a registered Architect/professional engineer in the State of GA. Existing drawings will be provided for the existing building. Contractor shall be responsible for verifying all existing conditions and dimensions, and for providing all elements required for a complete project. 4. SPACE REQUIREMENTS 4.1. General Industrial type personnel will occupy the facility. The intent of the design is to provide an industrial area required to support the C5 nose plug maintenance activities. These activities include general maintenance space, sanding booth and personal protective equipment (PPE) area. Support services (i.e. breakroom, restrooms, etc.) are located within the southern section of the facility and are considered as sufficient without modification. The contractor’s A-E (designer of record) is responsible for conducting a complete analysis of the design using all applicable life safety and building codes, UFCs and other applicable requirements referenced in this RFP in order to provide a fully code and regulation compliant final design. All additional elements for compliance with the applicable codes (i.e. egress requirements, fire rated walls, etc.) shall be considered as included within this contract. The A-E shall be solely responsible for interpreting the applicable requirements and providing a code compliant final design. 4.2. Approximately 5 personnel will occupy this section of the facility. Total occupancy is 8 personnel for the facility. 5. CIVIL DESIGN 5.1. Technical Criteria and Standards 5.1.1. All referenced material under this title in Paragraph 1. 5.2. Site Development 5.2.1. Site Survey Due to the limited sitework scope of this project, no site surveys have been performed beyond the information provided on the as-built drawings and Geobase drawings provided with this RFP. The contractor will review these documents and visually inspect the site to determine the existing conditions affecting this project. The proposal shall include all work necessary to perform the work outlined herein accommodating the existing conditions.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 3 of 23

During the design phase, contractor shall perform, at a minimum, the site surveys listed below: Subsurface Utility Exploration: Subsurface exploration shall involve, at a minimum, electromagnetic

detection, ground penetrating radar (GPR) and potholing to determine both vertical elevation and horizontal location of utilities. Locations shall correspond with the geospatial requirements of the Robins GeoBase office.

Geotechnical soil borings to determine structural soil capacity and presence of soil contaminates. Confirmation of all existing conditions and dimensions, and incorporating adjustments as necessary

into the design.

5.2.2. Demolition 5.2.2.1. Demolish and remove from site existing building elements as required to achieve design intent. 5.2.3. Erosion Control The design shall include an Erosion Control Plan in accordance with the State of Georgia "Manual for Erosion and Sediment Control", latest revision at time of contract award. Prior to construction, the Contractor shall provide an Erosion Control Package, which meets all state and local requirements. In addition, all necessary permits shall be obtained by the Contractor and complied with throughout all phases of construction. Any violation to such permits will result in the immediate shutdown of work until corrective measures have been taken at the Contractor's expense. 5.2.4. Curb and Gutters - Omitted 5.3. Pavement Design Concrete and bituminous pavement design will be as required for the installation of the new ramps and repair of existing bituminous pavement affected by the work. Existing paved roads and parking areas will be utilized for this project and will be repaired and/or replaced as required if damaged during construction. 5.4. Removal and Disposal There are no approved waste areas within the limits of Robins Air Force Base. All waste, except for scrap metal, shall be disposed of off-base at the Contractor’s expense. 5.4.1. Disposal Sites Off-base disposal of dry debris (nonhazardous waste) may be at any approved local site. Hazardous waste must be disposed of at sites that meet EPA landfill requirements, and are approved by the Contracting Officer. 5.4.2. Scrap Metal

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 4 of 23

All scrap metal shall be recycled thru the base recycling center. Contact John Carter (475-283-6542) for more information and to arrange for pick-up/drop-off /roll-offs. 5.5. Borrow Area Borrow material shall be obtained from off-base sources and non-Government controlled areas. Approved materials shall be those classified in ASTM D 2487 as GC, GM, SW, SP, SM, SC, ML, and CL and shall be free of trash, debris, roots or other organic matter or stones larger than 3" in any dimension. These requirements shall be addressed in the specifications developed by the Contractor. 5.6. Contractor's Storage Yard If approved by the Contracting Officer, the Contractor will be allowed limited space to put an office and/or storage trailer for this contract. The location will be as identified by the Technical Representative within 5 miles of project site. Items for this contract stored for the project on Base are the responsibility of the Contractor. Replace all such items stolen, vandalized, damaged, or otherwise unusable at no additional cost to the Government. Site shall be kept clean and orderly. 5.7. Haul Route See Drawings. 5.8. Grading A digging permit from the Base is required prior to any excavation operations. Re-grading is required to the extent necessary to prevent ponding of water due to the installation of the ramps and equipment pad. Any survey, testing or mapping required for the design or construction of the project shall be the responsibility of the Contractor. 5.9. Storm Runoff and Drainage System Reference Section 01560 and the Base Facility Standards for design and permitting requirements. 5.10. Utilities Show all existing utilities (size and approximate location) on the submittal drawings. Surveying required for this project is the responsibility of the Contractor. The Contractor shall obtain a digging permit, including utility verification, from the Base Civil Engineer’s office. The locations of the existing underground utilities as shown on the base utility map are not accurate, so if the project involves any exterior work on utilities or structures, include the following requirement on the design/shop drawings:

“ The contractor’s project designers/engineers shall schedule and meet with the Civil Engineering utility shop personnel at the project site and locate their underground utility lines and buried structures that might be affected by any digging/excavation on the site plans during the design phase”.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 5 of 23

5.10.1. Water Distribution System – Omitted. Water supply/plumbing for new fixtures will be connected to the existing domestic water system within the building. 5.10.2. Sanitary Sewer System The existing sanitary system currently extends to a manhole in the area to receive the new ramp. Relocate the existing sewer line with new manhole(s) and cleanout(s) as required to bypass the area under the existing and new ramps. Remove/fill/permanently seal sanitary sewer section as required to install the new ramp. The Contractor shall provide new building sewer connection to a manhole in such a manner that all sewer lines can be maintained easily without major disruption to building occupants. The Contractor shall mark all sewer lines with a copper tracer wire directly above all nonmetallic piping with plastic marking tape to provide means of determining alignment of pipe by metal detecting equipment. Plastic pipe and hub-less pipe are not allowed under concrete floor slabs. The minimum size sanitary sewer outside the building 5 feet line is 6 inches and the minimum size sanitary between manholes is 8 inches. The maximum length of building sewer without a manhole is 100 feet. 5.10.2.1. Temporary Sewer System Temporary pipeline by-pass and pump station(s) may be required to keep adjacent facilities in service while work is progressing on this contract. Temporary pumps shall be rated sufficiently to provide a working system. 5.10.2.2. Sewer Line Sizes and Velocities Sewer building service lines shall have a minimum diameter of 6 inches and lateral and mains shall be a minimum diameter of 8 inches. Lines shall be designed for a minimum velocity of 2 ft/sec for the average daily flow rate and 2.5 ft/sec for the peak flow rate. Lines shall not exceed a maximum velocity of 10 ft/sec. Pipe, 8" in diameter, shall have a minimum slope of 0.4 percent. 5.10.2.3. Ground Cover and Cleanouts Sanitary sewer lines shall have a minimum of 2 feet of cover to provide frost protection. Cleanouts shall be provided at each facility 5-foot line. The cleanouts shall be of the two-way type, which allows cleaning in either direction. 5.10.2.4. Manholes Manholes shall be provided where sewer lines exceed 100 feet in length from the facility to the sewer main line. Manhole shall be provided where there is a change in direction of sewer on lateral and main. Manholes shall also be provided on main lines at 300 feet spacing. A fixed siderail ladder shall be provided for manhole depths greater than 12 feet. The word "Sanitary Sewer" shall be cast in manhole covers. Vehicle loading is H-20.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 6 of 23

5.10.2.5. Materials Concrete pipe is not a viable option due to the corrosive nature of the soil. 5.10.2.6. Manning’s Formula For gravity flow line, Manning's formula shall be used: V = (1.486/n) R 2/3 S 1/2 where, 'n' values smaller than 0.013 shall not be permitted despite manufacturers' reports of 'n' values between 0.009 and 0.011. 5.10.2.7. Utility Trenching and Location All utilities shall be installed in accordance with the ROBINS AFB FACILITY STANDARD. Water and sanitary sewer lines shall not be installed in the same trench. Minimizing utility locations under the street is preferable. A digging permit from the Base is required prior to beginning any excavation. 5.11. Fencing 5.11.1. Contractor Yard, Omitted 5.12. Landscaping General landscaping will be designed in accordance with Base Facility Standard. Also after construction, all disturbed areas shall be seeded with either Centipede or Bermuda grass if planted between April and August. Use Penntine or Falcon fescue if planted between September and March. Areas surrounding the perimeter of the new facility shall be sodded. 5.13. Calculations Provide design calculations for the following: 5.13.1. Water System, Omitted 5.13.2. Storm Drainage, Omitted 5.13.3. Sanitary Sewer

a. Sanitary Sewer (average and peak flows demands and velocities) b. Profiles

6. GEOTECHNICAL DESIGN Geotechnical Soil Borings: Provide a minimum of 1 soil boring to determine the existing soil structural characteristics for the ramp addition (north side of building). Structural characteristics shall include structural testing and recommended design criteria. Provide soil borings by a geotechnical engineer registered in the State of Georgia.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 7 of 23

7. ARCHITECTURAL DESIGN

7.1. Scope and Objectives

Renovate north section of Bldg. 673 (approx. 6,000 square feet) for use as maintenance area for C5 noseplug operations. Major architectural components for this project are shown on the attached drawings, included within Section 01005 and as stated below.

Exterior metal building roof and wall replacement outlined below shall be designed by an engineer registered in the state of Georgia. Design shall be in accordance with the American Institute of Steel Construction, IBC 2015, ASCE 7-10 and MBMA requirements. Ultimate wind speed shall be set as Category IV (per UFC 3-301-01, minimum 120 mph) and Exposure C (ASCE 7-10) . Manufacturer shall have IAS AC472 accreditation through MBMA. All components for wall and roof shall be provided by a single source (one manufacturer) and shall be in accordance with warranty requirements.

7.2. Exterior Construction

7.2.1. Exterior Walls

Existing exterior wall consists of metal building wall panels over girts and insulation. Remove existing metal wall panels, personnel door, northwest overhead door and exhaust fan on the north endwall of the building. Restructure existing endwall to meet new opening configuration (structural steel and foundations). Install new prefinished metal wall panels, trim, flashings, etc. to match existing. Wall panels shall be PBR with major ribs at 12” o.c., minimum 1 ¼” high. Finish on exposed wall panels and trim shall be Kynar 500 or Hylar 5000 polyvinylidene fluoride (PVDF) factory finish with a 20 year NDL material warranty. Provide new wall insulation, R=19 with white scrim, type PSKP, basis of design – Lamtec WMP50. All seams shall be taped (stapling not allowed). All components shall be provided by same manufacturer as roof.

On remainder of exterior building walls within the production area, remove existing wall panels and insulation. Install new metal PBR wall panels. Install new wall insulation as required for a total R = 19. Scrim on new insulation facing the interior shall be type PSKP, basis of design - Lamtec WMP50. Scrim shall be completely sealed on all edges and around all penetrations for a continuous vapor barrier. All seams shall be taped (stapling not allowed).

On exterior walls, existing structural framing members are required to be cleaned to remove existing dirt and mildew. Cleaning/pressure washing shall be performed as to not damage existing paint coatings or equipment to remain.

7.2.2. Windows, Omitted

7.2.3. Roof

Remove existing standing seam metal roof and insulation over the 6,000 sf renovated area, and any associated flashing. Protect all existing components scheduled to remain (i.e. electrical equipment, fire

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 8 of 23

alarm, etc.) from damage. Install new sub-structural as required to match the roof slope of the south building section. Install new insulation, minimum R=30, with PSKP scrim, basis of design – Lamtec WMP50. All seams shall be taped (stapling not allowed). Install insulation such that a maximum of 6” (or less per roof manufacturer’s recommendations) is compressed between the roofing panels and substructure. Provide roof expansion/transition joint between new and existing roof to remain. Roof finish and color shall be in accordance with the ROBINS AFB BASE FACILITY STANDARD. Roof system shall be minimum 24 gauge industrial metal roof with 3” minimum height trapezoidal mechanically seamed standing seam roof panels, 360° mechanical seam shall be seamed onsite (90°/180°/270° seams not allowed) with maximum panel width of 24 inches. Install system with thermal insulation blocks. Panels shall have intermediate low profile ribs, flat pans not allowed. New roof shall have a Kynar 500 or Hylar 5000 polyvinylidene fluoride (PVDF) factory finish. New metal roofing shall be designed and installed in a manner that requires no field fabrication of panels in direction of installation (i.e. panels shall be installed on correct module and rake trim fasteners in flat of roof panels shall not be acceptable). Fabrication length shall be as required to extend over new wall panels. All roof components (including flashing, trim, penetrations and insulation) shall be provided by the roof manufacturer in accordance with the warranty requirements.

New roof system shall be provided in accordance with the provisions of UFGS 07 61 14.00 20 Steel Standing Seam Roofing, UFC 3-110-03 (special emphasis on Appendix D for inspections) and the BFS.

All required warranties shall be single source from the roof manufacturer. Roof system warranty shall be a true 20 year single source NDL (no dollar limit) covering materials and labor (limit to original purchase price will not be allowed). Warranty shall cover weather-tightness, design wind speeds, and finish of the roofing and flashing components. Sample of warranty, along with manufacturer's certification for the installer, will be submitted with the material submittal for approval. A certified roof installer (certified by the manufacturer of the roof system) shall be on-site at all times while roof system is being installed. Prior to acceptance, the manufacturer shall perform the necessary roof inspections (minimum 1 within 3 days of starting roof construction, 1 intermediate and 1 after completion) as required to determine that installation is per the manufacturer’s instructions (written reports are required) and issue a letter (with final inspection report) to that effect. COR must be present during final inspection (provide minimum 3 working day notification). Roof shall not be accepted without this letter. Warranty will not include the following exclusions:

a. Wind uplift different from the design (per IBC 2015/ASCE 7- 10).b. Workmanship or exclusion of manufacturer during the installer’s warranty.c. Manufacturers’ warranties that require periodic inspections or repairs at the Government’s

expense to maintain the warranty are not permitted..d. Exclusions will not conflict with the warranty requirements listed in UFC 3-110-03, Appendix

D.

Repairs that become necessary because of defective materials and workmanship while roofing is under warranty shall be performed within 7 days after notification, unless additional time is approved by the Contracting Officer. Failure to perform repairs within the specified period of time will constitute grounds for having the repairs performed by others and the cost billed to the manufacturer.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 9 of 23

Existing structural roof framing members are required to be cleaned to remove existing dirt and mildew. Protect all existing components scheduled to remain (i.e. electrical equipment, fire alarm, etc.) from damage during cleaning operations. Cleaning/pressure washing shall be performed as to not damage existing paint coatings or equipment. 7.2.4. Gutters and Downspouts Gutters and downspouts will not be required due to the large number of trees on the east side. Provide all eave flashings and trim as required for a weathertight enclosure. 7.2.5. Exterior Doors 7.2.5.1 Personnel Doors Provide new insulated galvanized exterior hollow metal door and frame in the north endwall. Provide door hardware including panic device w/cylinder, closer, butts, threshold and weatherstripping. Door shall have vertical vision lite. Door, frame and hardware shall meet the requirements of the appropriate UFGS sections and the Robins BFS. 7.2.5.2 Overhead Coiling Door Provide new insulated overhead coiling door, size as shown on drawing. Door will be heavy duty service door with an electric operator with push button controls (requires continuous pressure for operation), door shroud and required safety devices. Any wireless electronic control components shall be fully disabled or removed. Provide manual chain operation for operation during power outages. Door shall meet the requirements of the UFGS specification section and the Robins BFS. 7.2.6. Louvers Provide louvers as required for the operation of the HVAC system and to prevent entry of water into the building. Provide rain hoods for new louvers. Louvers and hoods shall be finished with paint finish to meet ROBINS AFB BASE FACILITY STANDARD. 7.2.7. Expansion and Control Joints Provide new expansion and control joints as required. 7.2.8. Termiticide Provide termiticide treatment at new construction in contact with grade. 7.2.9. Miscellaneous Metals 7.2.9.1 General: Miscellaneous metals shall consist of steel pipe railings, angles, plates, anchors, etc. required for a complete facility.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 10 of 23

7.2.9.2 Steel Pipe Railings: Railings shall be fabricated from galvanized steel pipe meeting the requirements of IBC 2015, NFPA 101, DoD ABA and UFGS. Railings shall be painted.

7.2.10. Wood

Pressure/fire treated wood shall be used for miscellaneous nailers, blocking etc. Maximum moisture content when delivered and when installed is 19%. Wood nailers shall not be used in metal roof construction.

7.2.11. Painting and Coatings

a. Existing prefinished metal building wall panels and trim do not require repainting.

b. Railings and miscellaneous metals: Paint shall be alkyd industrial enamel, eggshell finish, 3coat system (primer/intermediate/top). Clean existing railings and metals to remain asrequired for proper adhesion per manufacturer's instructions.

7.3. Interior Construction

In general, items called out below do not list colors, textures, and architectural form aspects. The contractor's designer shall provide a Structural Interior Design (SID) submittal per Section 01030 to show the coordinated design of these aspects into an architecturally pleasing whole. The Government reserves the right to redirect the designer on these design elements after the first submittal.

7.3.1. Interior, Non-Relocatable Partitions

New interior partitions for PPE area and Personal Locker room shall be painted 8" CMU (enclose all 4 sides). Height shall be sufficient for 9 ft. ceiling heights. CMU shall have 2 component foam block insulation, Class A fire rated meeting ASTM E-84, basis of design – Core-fill 500.

7.3.2. Interior Surface of Exterior Wall

The interior surface of exterior walls shall be exposed PSKP white scrim with exposed structural.

7.3.3. Toilets, Omitted

7.3.4. Fireproofing and Firestopping

New construction shall be fireproofed and firestopped as required to be in conformance with code requirements.

7.3.5. Interior Doors and Frames

Interior doors and frames will be galvanized hollow metal. Provide door hardware including privacy set lever hardware, closers, butts, and silencers. Doors shall have vertical vision lite. Doors, frames and hardware shall meet the requirements of the appropriate UFGS sections and the Robins BFS

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 11 of 23

7.3.6. Fire Extinguishers and Cabinets Provide new fire extinguishers as required by code. Extinguishers shall be on brackets. 7.3.7. Sealants Provide sealants and caulking per manufacturer’s recommendations. 7.3.8. Ceilings PPE and Personal Locker Rooms shall be constructed with cold formed metal framing ceiling structure with metal PBR roof panels, minimum 20 psf live load. Although not exposed to weather, treat roof as weathertight system (use EPDM washers on fasteners), minimum slope ½” per ft.. Install R19 batt insulation in the ceiling/roof supported independently from the suspended ceiling. Provide trim and flashings as required to conceal edges of roof panels and framing. Provide new 2’ x 2’ cleanable moisture/mold resistant fiberglass ceiling tiles within the PPE and Personal Locker Rooms (provide with hold-down clips). Seal ceiling assembly as required for positive and negative pressures required under HVAC systems. Main production area ceilings shall be exposed white PSKP insulation scrim. 7.3.9. Corner Guards, Omitted 7.4. Interior Finishes. 7.4.1. Carpet, Omitted. 7.4.2. Painting and Coatings

a. PPE Area and Personal Locker Room walls: Paint all exposed CMU walls inside and outside. Paint shall be 3 coat (primer/intermediate/top) high performance acrylic over block filler.

b. PPE Area and Personal Locker Room floors: 2 part epoxy floor finish. Prepare concrete in accordance with manufacturer's requirements.

c. Railings, new structural members (endwall components) and miscellaneous metals: Paint shall be alkyd industrial enamel, eggshell finish, 3 coat system (primer/intermediate/top). Clean existing railings and metals to remain as required for proper adhesion per manufacturer's instructions.

8. STRUCTURAL DESIGN 8.1. General

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 12 of 23

The structural criteria established herein shall be used for structural loading, design, and installation of all structural systems and foundations, including manufacturing, erection, supervision, testing, and quality assurance of the complete installation. All structural calculations and drawings shall be checked and stamped by a registered Professional Civil Engineer, registered in the state of the project location. The structural work generally consists of design, using the DESIGN LOADS AND DESIGN CRITERIA below, and of construction of, but not limited to:

a. Foundations. b. Load Bearing and Non-loadbearing Walls. c. Vertical Framing Members. d. Horizontal Framing Members, including roof decks and diaphragms, roof beams and joists,

floor beams and slabs. e. Interconnection Details, including all fastening requirements. f. Special Conditions, such as expansion, construction, and control joints, and changes in floor

levels. g. Attachment provisions for architectural, mechanical, and electrical elements.

8.2. References Current editions of the codes and specifications listed in the ROBINS AFB, Base Facility Standards. 8.3. Design Criteria Design shall meet the following criteria and the minimum load standards presented herein. 8.4. Design Loads 8.4.1. Dead Loads The structural system shall be designed and constructed to safely support all dead loads, permanent or temporary, including but not limited to self-weight, partitions, insulation, ceiling, floor covering, and all equipment that is fixed in position. 8.4.2. Vertical Live Loads 8.4.2.1. Roofs shall be designed to support live load, snow loads, including drifting snow, sliding snow, and rain or snow, and support wind loads including components and cladding in accordance with the ROBINS AFB, Base Facility Standards. Snow loads full or unbalanced shall govern where such loadings will result in larger members at connections. 8.4.2.2. If the design roof snow loading is less than 20 psf, a minimum roof live loading for construction and maintenance of 20 psf shall be used for design of the structure. This roof live loading is in lieu of and not in addition to the snow loading. However, unbalanced snow loads, sliding and drifting snow (in particular areas), or wind loads may be the controlling load case for particular elements. 8.5. Seismic Design

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 13 of 23

Design for seismic shall be in accordance with the ROBINS AFB, Base Facility Standards. 8.6. Wind Design Design for wind shall be in accordance with the ROBINS AFB, Base Facility Standards, with a minimum Basic Design Wind Speed, V (mph) of 120, corresponding to a 3-second peak gust wind speed at 33' above ground. 8.7. Construction Tolerances Allowable variations from level, or specified slopes, shall be as follows:

a. For overall length, or surface of 10 feet or less: plus or minus 1/8 inch. b. Up to 25 feet: plus or minus 1/4 inch. c. Up to 50 feet: plus or minus 3/8 inch.

8.8. Embedded Steel Nonstructural steel (handrails, etc.) embedded in concrete shall be galvanized steel, with the embedded area coated with two thick coats of coal-tar epoxy to just above grade before placing them. All damaged galvanized areas shall be repaired prior to embedment. 8.9. Structural System

a. All structural mill sections or welded built-up plate sections shall be designed in accordance with the the ROBINS AFB, Base Facility Standards. The overall structural system shall be selected based on durability, maintainability, and cost-effectiveness

b. All cold-formed steel structural members shall be designed in accordance with the AISC “Specification for the Design of Cold-Formed Steel Structural Members, Latest Edition.

c. Structural Framing Systems shall be in accordance with the American Institute of Steel Construction (AISC) and applicable commercial standards for pre-engineered metal buildings.

8.10. Foundation System The foundation system shall be determined from the following system types:

a. Continuous spread footings and stem walls with concrete slab-on-grade floor slabs.

b. Spread footings and grade beams with concrete slab-on-grade floor slabs.

c. Foundations for interior and exterior columns shall be isolated spread footings. 8.11. Design Criteria

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 14 of 23

8.11.1. Serviceability 8.11.1.1. Foundation Settlement Strength An adequate level of protection against structural failure due to uniform and/or differential foundation settlement or general shear shall be provided. 8.11.1.2. Vertical Deflection of Suspended Horizontal Framing Members Building serviceability shall not be impaired by vertical deflections. The sum of the instantaneous vertical deflections due to live load plus long-term sustained load deflections shall not exceed the span divided by:

a. 240 at roofs b. 360 at floors c. 600 at masonry lintels for masonry walls

8.11.1.3. Horizontal deflection shall not exceed standard limits when the structure is subjected to the required seismic or wind loads. 8.11.1.4. Ultimate Strength of Structural Elements An adequate level of protection against structural failure under extreme loads shall be provided. The Contractor shall check the usual loading conditions for normal factors of safety and the extreme loading conditions, if present, for appropriate (unusual) factors of safety to provide levels of protection appropriate for the conditions. 8.11.2. Durability/Time Reliability 8.11.2.1. Structural components shall be protected from condensed moisture that could impair their structural adequacy through deterioration. 8.11.2.2. Special attention shall be given to protection against corrosion or oxidation of metals, decay of wood and wood base materials, spilling of concrete, leaching of mortar, and deterioration of adhesives. Prevention of these hazards shall be especially important. 8.11.2.3. The materials used in structural elements, components, and assemblies shall be resistant to or protected from damage by exposure to normal climatic conditions. 8.12. General Design Criteria 8.12.1. The design drawings shall contain in the General Notes a list of the design loading criteria, a list of the strengths of the engineering materials used, the design soil values, and any other data that would be pertinent to remodeling and/or future additions. 8.12.2. Walls mostly below grade that are supported laterally by diaphragms at or near the top and bottom, shall be designed using loadings based on at rest soil pressures.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 15 of 23

8.12.3. Diaphragms shall have continuous chord members on all edges and shall have direct positive connection for transferring load to all members of the main lateral force resisting system. 8.12.4. Metal deck shall be of the gauge and configuration to meet the loading and wind uplift requirements specified. 8.13. Concrete Design 8.13.1. General All walls, columns, beams, and slabs shall be constructed of reinforced cast-in-place concrete with a minimum compressive strength of 4000 PSI at 28 days. Footings shall be constructed of reinforced cast-in-place concrete with a minimum compressive strength of 3000 PSI at 28 days. 8.13.2. Testing of concrete work shall be done at the Contractor's expense by an independent testing laboratory at least once a day during concrete placement. Tests shall include air, slump, and strength. 8.13.3. Forms Provide plywood, metal, metal-framed, aluminum, reinforced fiberglass, or plywood-faced forms, to provide continuous, straight, smooth, exposed surfaces. 8.13.4. Reinforcing Materials Reinforcing Bars: ASTM A 615, Grade 60. 8.13.5. Concrete Materials

a. Cement: ASTM C 150, Type I-II Portland cement. b. Fine Aggregate: ASTM C 33. c. Coarse Aggregate: ASTM C 33. d. Air-Entraining Admixture: ASTM C 260. e. Flowing Concrete Admixture: ASTM C 1017, Type 1 or 2. f. Calcium Chloride shall not be permitted. g. Fly Ash: ASTM C 618, Class "F". Fly ash is required per GPP requirements unless determined as detrimental to concrete strength (certification by structural engineer will be required). However, fly ash content shall not exceed 20 percent of cement content or 200 lbs. of fly ash per cubic yard of concrete.

8.13.6. Vapor Barrier Provide vapor barrier under all slab-on-grade floors. Vapor barrier shall be polyethylene sheet not less than 10mil thick. Provide a 4" thick capillary water barrier under the vapor barrier (modify only if directed otherwise by the soils report). 8.13.7. Curing Compound

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 16 of 23

Liquid type membrane-forming curing compound complying with ASTM C 309, Type I, Class A or B. Compound shall be compatible with flooring adhesives to be used. 8.13.8. Ready-Mix Concrete ASTM C 94. 8.13.9. Slabs 8.13.9.1. Slabs supported on ground shall have a minimum 4000-PSI concrete, 28-day compressive strength, and shall be reinforced. 8.13.9.2. Slabs will be placed in lane fashion. Areas of sections bounded by crack control joints will not exceed 225 sq. ft., and distance between crack control joints shall not exceed 15 feet. 8.13.9.2.1. Provide contraction joints, either formed or saw cut or cut with a jointing tool, to a depth of 1/4 of the slab thickness. Sawed joints shall be completed within 4 to 12 hours after concrete placement. Reinforcement will be interrupted 2 inches (clear each side) at sawed or impressed crack control joints. Bars shall be mid-depth and starting 2 inches from edge of slab. The ends of crack control and corners of isolation joints will meet at a common point so far as practical. Provide crack control re-entrant bars at all slab inside corners, including at doorways interrupted by masonry. Floor slab isolation joint shall be 30-pound felt. 8.13.9.2.2. Provide construction joints only at approved locations. Continue reinforcement across joints, unless otherwise indicated. 8.13.9.3. Expansion Joints Stop reinforcing at joint and provide smooth slip dowels across the joint. Dowels shall be ASTM A 36 material. Provide a bond breaker isolation joint where all concrete slabs abut a vertical surface (foundation walls). 8.13.9.4. When thickened slabs are employed under column bases or partitions, crack control joints shall be offset from the thickened areas. Re-entrant corners in slabs will be reinforced with a minimum of one No. 4 diagonal bar. 8.13.9.5. Slabs supported on ground shall conform to the minimum requirements for slab-on-grade: 8.13.9.5.1. Slabs-on-Grade Slabs shall be a minimum of 4 inches thick with 0.18 percent reinforcement. 8.13.9.5.2. Horizontal runs of conduits and pipes shall not be embedded in slabs supported by ground. Vertical penetrations shall conform to ACI 318-11. Aluminum conduit and pipes shall not be embedded in any concrete structure. 8.14 Concrete Finishing

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 17 of 23

8.14.1 Slabs: Provide troweled finish for all interior slabs, broom finish for exterior walks. 8.14.2 Exposed Concrete: Provide smooth parge coating on all exposed vertical concrete surfaces. 8.15. Masonry Design 8.15.1. Joints shall be 3/8 inch, tooled concave, Type "N" mortar. 8.15.2. Concrete masonry units shall have a minimum compressive strength (f'm) of 1500 PSI. 8.16. Structural Steel Design 8.16.1. The detailing of structural steel framing, if any, including connections, shall be complete. All weld types, weld locations, bolting layouts, bolt sizes, connection plates, member sizes and locations, and stiffener plate sizes and locations shall be shown. 8.16.2. All members, elements, and connections that are a part of the main vertical and/or lateral force resisting system must be completely detailed. 8.17. Slab-on-grade: Finished floor elevation shall be minimum 6 inches above adjacent grade level. 9. MECHANICAL DESIGN 9.1. General The heating, ventilation, and air conditioning (HVAC), plumbing systems, and fire suppression system shall be as described herein and/or as mentioned in the description of work. Reference Section 01005 for description for HVAC alternates for heat/ventilation only and heat/AC/ventilation. Design methods for the various mechanical, plumbing, and fire suppression materials and methods shall be in accordance with the current editions of the codes and specifications listed below: 9.2. Criteria References UFC 1-200-01 General Building Requirements UFC 3-400-10N Design: Mechanical Engineering UFC 3-410-1 Heating, Ventilating, and Air Conditioning UFC 3-420-01 Design Plumbing UFC 3-600-01 Fire Protection IBC International Building Code IMC International Mechanical Code IPC International Plumbing Code IFGC International Fuel Gas Code UFC 4-010-01 DOD Antiterrorism Standards for Buildings NFPA National Fire Protection Association ASHRAE Standards ACGIH Industrial Ventilation Manual Recommended Practice

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 18 of 23

Robins AFB Base Facility Standards 9.3. HVAC Design Criteria Design heating, ventilation, and air conditioning in accordance with ASHRAE design standards. Provide all heat load and cooling load calculations based on ASHRAE fundamental handbook and determined the proper HVAC systems with the highest efficiency rating and best performance value based on DOE recommendations and standards. 8” Natural Gas line is available within 300 feet of the building. 9.3.1 When providing thermostat(s). Thermostat shall have a programmable automatic changeover for temperature set points during fall to winter and winter to spring seasons.

9.3.2 When providing a heat pump in the central Georgia area, heat pump shall be design with supplemental electric heat strip for winter heating.

9.3.3 Provide additional 5% safety factor for HVAC load calculations. 9.3.4 Indoor thermostat set points shall be as follows: Administrative/Clean room/Decontaminated room: Summer: 78 degree DB and dehumidification is not required. Winter: 70 degree DB and humidification is not required. Bay Area: Summer: 81 degree DB and dehumidification is not required. Winter: 65 degree DB and humidification is not required. 9.3.5 Indoor space air pressurization shall be as follows:

a. Decontaminated room: slightly negative pressure. b. Clean room: normal atmospheric pressure c. Bay area: normal atmospheric pressure

9.4 Plumbing Design Criteria Design plumbing systems in accordance with IPC and Base Facility Standards. 9.5 Fire Suppression Design Criteria Design fire suppression in accordance with UFC 3-600-01 and Based Facility Standards. 10. ELECTRICAL DESIGN 10.1. Codes and Standards

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 19 of 23

The design and construction of the electrical systems shall be in compliance with: (1) NFPA Codes, (2) the rules and recommendations of ANSI C2, (3) as required herein, and (4) ROBINS AFB BASE FACILITY STANDARD. 10.2. Specific Instructions 10.2.1. The work included in this section shall consist of furnishing all labor, materials, equipment, supervision, and services necessary to complete all electrical work as indicated on the drawings and described herein. The work includes the following principal items:

a. Power Distribution system. b. Lighting system. c. Fire Alarm and Detection system d. Grounding system. e. Lightning protection system d. Voice/Data systems. f. CATV system. – N/A g. PA system.- N/A

10.2.2. Design shall include development of construction drawings clearly indicating all devices, wiring and functional requirements necessary to provide systems which comply with user needs as determined in correspondence and meetings with the users during the design phase. The D-B drawing package indicates quantities of outlets, fixtures, and devices to be as expected. Exact requirements regarding quantities, types and locations shall be determined during the final design phase. 10.3. Electrical Design Criteria The intent of this project is to provide power, lighting, and miscellaneous systems for an open shop type construction. All such conduits and cables shall be installed in the ceilings to provide maximum flexibility as possible. Provide flexible whips 4 feet in length. The design contractor shall finalize design drawings and add all necessary details to result in a complete and usable system. 10.3.1. Electrical Work for HVAC Systems 10.3.1.1. General Provide all materials, labor, and supervision for power requirements to run installed mechanical equipment. 10.3.2. Site Electrical The point of connection to the Robins AFB primary electrical and communication systems will be as shown in concept on the renovation floor plan, Sheet A-102. This site plan does not relieve the Design/Builder of the requirement to visit the site and coordinate work with the Base. 10.3.3. Electrical Service

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 20 of 23

10.3.3.1 Pad Mounted Transformer A new concrete pad and pad mounted transformer will be required for this project. A-E shall perform load calculations of existing and new electrical usage requirements and size transformer per the ROBINS AFB FACILITY STANDARD. 10.3.3.2 – Service Entrance Existing air switch is 12,470/7,200 V, grounded Wye. Replace existing conductors from the air switch to the transformer. Conductors shall be #2 AWG with neutral. Reference ROBINS AFB FACILITY STANDARD for additional information. Install underground service consisting of new conductors and conduit from transformer to building as required for new service. 10.3.4. Lighting Assume 100 percent demand for all lighting loads. 10.3.4.1. Illumination Levels Calculate lighting levels based upon IES (Illuminating Engineering Society) and UFC 03-530-01 for average and maintained levels. Average and maintained level is defined as a calculated foot-candle level taking into consideration all depreciation light loss factors (LLF). 10.3.4.2. Fixtures Fixtures shall comply with Robins AFB Base Facility Standard. Parabolic fixtures are not allowed. Layout of lighting fixtures in open shop areas shall be spaced to provide uniform distribution of light. For LED lighting application, perform Building Life Cycle Cost (BLCC) analysis (10 year payback) and meeting LED lighting requirements as per the ETL 12-15. 10.3.4.3. Switching Occupancy Sensors for lighting the large open shop areas shall be located in such location as to providing the most on-time lighting much as possible during production or occupancy and shall be arranged in logical groupings or zones. Panelboard circuit breakers shall not be used for switching. 10.3.4.4. Emergency Lighting Illuminated exit signs and emergency lighting shall be provided for all emergency exits and passageways as required by the NFPA Life Safety Code No. 101. In areas with fluorescent or LED lighting, use fixtures with emergency ballasts and battery packs per the ROBINS AFB FACILITY STANDARD.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 21 of 23

10.3.5. Power 10.3.5.1. Switchboard/Panelboards Switchboard/Panelboards (480/277V) shall have a separately mounted main circuit breaker. Provide spare capacity of 25 percent in the service and distribution equipment and wiring; provide 30 percent spare pole spaces in distribution, lighting, and appliance panelboards. Branch circuit panelboards shall have 200% rated neutrals. Service and distribution equipment and branch circuit panelboards shall be of the circuit breaker type. Panelboards will be surface. 10.3.6. System Characteristics System characteristics shall be 480/277 volt, 3 phase, 4-wire, with solidly grounded wye. Dry type transformers shall be provided for 208/120-volt loads. Transformers shall be K-rated per the Electrical Section of the Robins AFB Base Facility Standard. 10.3.7. Transient Voltage Surge Suppression (TVSS) Transient Voltage Surge Suppression (TVSS) shall be provided at the main service equipment and at each panelboard. TVSS shall conform to the ROBINS AFB FACILITY STANDARD. 10.3.8. Electrical Disconnects 10.3.8.1. Electrical disconnects shall be installed adjacent to equipment and accessible to equipment operators for the following equipment: Motors and equipment as required by the NEC and OSHA requirements. 10.3.9. Wiring Devices 10.3.9.2. Mounting and Location 10.3.9.2.1. Devices located in the same approximate position on one section of wall, floor, column, etc. shall be grouped to create a functional and pleasing appearance. Similar outlet groups throughout the job shall be similarly grouped. Unless necessary otherwise, groups shall be developed as follows where applicable:

a. Devices at different levels shall be aligned vertically. b. Devices at the same level shall, where possible, be grouped using sectional gang boxes, except that individual dimmer switches shall be installed in an individual 2-gang box. Devices or device groups occurring in architectural features, i.e., wall sections, etc. shall be accurately centered in the feature(s), unless functionally required otherwise. Wall switches shall be located on the strike side of a door, 6 inches from the door opening, unless otherwise functionally required.

10.3.9.3. Toggle Switches

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 22 of 23

Refer to requirements in the ROBINS AFB FACILITY STANDARD. 10.3.9.4. Standard Receptacles Refer to requirements in the ROBINS AFB FACILITY STANDARD. 10.3.9.5. Weatherproof Receptacles Provide these on the exterior walls, two on each wall of production area, spaced symmetrically (6 receptacles total). 10.3.9.6. Ground Fault Circuit Interrupter (GFCI) Outlets

a. GFCI outlets are to be used for 20-amp convenience type outlets in the following areas: Outdoors, wet locations, bathrooms, and other locations as required by the National Electric Code or OSHA. b. Ground Fault Circuit Interrupted (GFCI) receptacles shall be UL listed as providing protection for personnel against line-to-ground shock hazard. The GFCI device shall continuously monitor current in the two-phase conductors and shall interrupt the circuit for a current differential of more than a predetermined value to the outlet(s). The device shall be solid state with test button and indicator, a reset button, all properly labeled and with printed instructions. The GFCI receptacle shall be the end-of-line or feed-thru type as appropriate to the installation.

10.4. Outlet requirements General-purpose receptacles shall be provided as follows:

a. One duplex receptacle at each column. Existing outlets may be used but must be circuited for a maximum of 2 outlets per 20A circuit. b. One duplex receptacle at midpoint between each pair of columns. c. Two duplex receptacles in each of the PPE and Personal Locker Rooms (total 4 outlets). d. Four duplex receptacles on the production side of the PPE/Personal Locker Room walls. f. All receptacles shall be circuited for 2 receptacles maximum on 20A circuit.

10.5. Special Power Requirements. N/A 10.6. Fire Alarm and Detection 10.6.1. This facility has an existing fire alarm system and must be protected from damage due to the work, moisture or water during the roof/wall replacement and structural frame cleaning processes. Functional testing will be required in conjunction with the CE alarm shop prior to start of the work. 10.7. System Grounding

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS - 01020

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS 01020 - 23 of 23

10.7.1. Provide grounding per the ROBINS AFB FACILITY STANDARD. Note the additional measures required due to high soil resistivity. 10.7.2. Provide special grounding for these systems: (describe as needed for SIPRNET and NIPRNET systems, lightning protection, electronic and computer areas, electrostatic discharge workstations, etc., if they need more than the basic level of grounding, especially with regard to maximum ohm levels.) 10.8. Lightning Protection Provide a lightning protection system per the ROBINS AFB FACILITY STANDARD. Perform visual examination and functional testing of the existing system during the design phase to identify any existing deficiencies. Notify the contracting officer of the deficiencies in writing, separating those areas that are and are not directly affected by the work (i.e. disturbed or replaced by the work scope). Deficiencies not directly affected by the work will be negotiated accordingly. Prior to acceptance of the work, the entire building lightning protection system shall be certified by a 3rd party in accordance with UFC 3-575-01 requirements and ROBINS AFB FACILITY STANDARD. 10.9. Voice/Data System Work 10.9.1. The Contractor shall provide 4 – 1” conduits and outlet boxes to extend to the common wall of the north and south building wings and penetrate the wall above the admin. area for data. Locations for outlet boxes shall be determined during the final design (proposal to assume location anywhere within the renovated area). Work shall comply with the ROBINS AFB FACILITY STANDARD. 10.10. CATV System and T-Net System – N/A. 10.11. PA System – N/A

<<<<< END OF SECTION >>>>>

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE

REQUIREMENTS – APP A

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS – APP A

01020 APP A - 1 of 3

FIRE PROTECTION/LIFE SAFETY CODE ANALYSIS

(THIS IS A SAMPLE ONLY)

THIS SAMPLE CONTAINS REFERENCES TO OLDER CODES – EDIT AS REQUIRED FOR

THIS PROJECT AND CURRENT APPLICABLE CODES)

ALL CODES SHALL BE LATEST EDITION

EXCEPT USE IBC EDITION AS PER CURRENT UFC 1-200-01

NOTE TO CONTRACTOR’S DESIGNER: A preliminary Fire Protection/Life Safety code analysis has

not been performed as a part of this RFP. It shall be the contractor’s responsibility during bidding,

based on information included within the RFP, to include all components required to satisfy these

requirements (contractor should consult with their intended A-E as needed). This shall constitute as

normal cost of business required for bidding and shall not obligate the Govt. RFIs may be submitted

requesting information on existing conditions and intended usage. Bid shall include all cost necessary to

comply with these requirements.

REFERENCES:

Unified Facilities Code (UFC) 3-600-01 on Fire Protection

Engineering Circular EC 1110-1-92, Classification of Type of Construction, 21 June 2000

International Building Code (IBC) 2003

NFPA 101, Life Safety Code, 2000

NFPA 10, Standard for Portable Fire Extinguishers, 1998

BUILDING DESCRIPTION:

One Story Building, Approximately 41,000 Square Feet

AUTOMATIC SPRINKLER SYSTEM (UFC 3-600-01): Required

UBC OCCUPANCY:

Warehouse, Records: S-1 Moderate Hazard Storage

DCO, Cable Vault: F-1 Moderate Hazard Industrial

Battery Room: H-3 Hazardous (high physical hazard)

All Other Spaces: B Business

NFPA 101 OCCUPANCY:

Warehouse, Records: Storage (Chapter 42)

DCO, Cable Vault: Special Purpose Industrial (Para 40.1.4.1(b))

All Other Spaces: Business (Chapter 38)

CONSTRUCTION TYPE (UBC Table 5-B): Type V-N

Construction may be of any materials allowed by UBC, nonrated.

References: 505.2 Unlimited area increase – 60’ yards all sides

504.3 exc 2 H Occupancy less than 10% of building area

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE

REQUIREMENTS – APP A

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS – APP A

01020 APP A - 2 of 3

EXTERIOR WALL AND OPENING PROTECTION (UBC Table 5-A):

No requirements based on location on property.

FIRE RATED SEPARATIONS:

Battery Room: One Hour (UBC Table 3-B)

Shaft enclosures: One Hour (UBC Table 6-A)

Vertical openings: One Hour (NFPA 101 8.2.5.2).

Mechanical, Generator rooms: One Hour (NFPA 101 8.4.1.1).

Records, Warehouse: One Hour (UFC 3-600-01)

ATTIC DRAFT STOPS (UFC 3-600-01):

Unsprinklered attic spaces at combustible roof construction: Draft stops of gypsum board on wood or

metal framing required to divide space into areas not exceeding 3,000 square feet.

OCCUPANT LOAD (NFPA 101, Table 7.1.3.2):

Occupancy Area Occupant Load

Storage 3070 6

Industrial 5700 4

Business 32,230 323

TOTAL 41,000 333

EGRESS REQUIREMENTS (NFPA 101)

CAPACITY (Table 7.3.3.1): Level Components and Ramps: 333(0.2)=67 inches

MINIMUM CORRIDOR WIDTH (38.2.3.2): 44 inches

NUMBER OF EXITS (7.4.1, 40.2.4.1 exc, 42.2.4.1 exc 2):

Two required at Business

One permitted at Storage if reached in Common Path distance

One permitted at Industrial if reached in Common Path distance

MAXIMUM DEAD END (38.2.5.2, 40.2.5.2, 42.2.5.3 exc):

50 feet at Business, Industrial

100 feet at Storage

MAXIMUM COMMON PATH OF TRAVEL (38.2.5.3, 40.2.5.3, 42.2.5.4 exc): 100 feet

MAXIMUM TRAVEL DISTANCE (38.2.6, 40.2.6.1 exc 1, 42.2.6.2):

300 feet at Business

250 feet at Industrial

400 feet at Storage

INTERIOR FINISHES:

WALL AND CEILING FINISHES (UFC 3-600-01):

Class A in Exits and Exit Passageways.

Class A, B or C all other areas.

Class A materials shall not exceed FS 25 and SD 50.

Class B materials shall not exceed FS 75 and SD 100.

Class C materials shall not exceed FS 200 and SD 200.

UHHZ160050 (DESIGN-BUILD) CONSTRUCTION PERFORMANCE

REQUIREMENTS – APP A

(DESIGN-BUILD) CONSTRUCTION PERFORMANCE REQUIREMENTS – APP A

01020 APP A - 3 of 3

Cellular Plastics not permitted.

FLOOR FINISHES (NFPA 101 38.3.3.3, 10.2.8.2):

No requirements.

PORTABLE FIRE EXTINGUISHERS (NFPA 10):

Maximum travel to fire extinguisher: 75 feet

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 1 of 15

REVISED 10-May-2013

1. GENERAL 2. SCOPE OF SERVICES 3. ADMINISTRATIVE INFORMATION 4. DESIGN RESPONSIBILITIES AND DOCUMENTATION 5. AREAS COVERED IN THE PROCEDURAL GUIDE FOR AE’S 6. ORDER OF PRECEDENCE FOR DESIGN CRITERIA 7. MEETINGS AND DESIGN SUBMITTALS 1. GENERAL 1.1 End Product: The requirements within this section establish the design efforts of the successful Contractor, following Design Notice to Proceed. The design shall provide a final useable product that conforms to the descriptions in Sections 01005 and 01020. 1.2. Delays caused by the Contractor in completion of the design phases are not a valid cause for extending the completion date for the entire project. 2. SCOPE OF SERVICES 2.1. General: The Architect-Engineer (AE) employed by the Contractor shall perform all the services and furnish all materials required for the production and subsequent delivery to the Contracting Officer of field investigations, surveys, design calculations, drawings, specifications, cost estimates, and electronic files as stated in these Specifications. AE shall also verify all existing conditions, including existing field measurements for incorporation within the design package. 2.2. Design Objectives 2.2.1. In general, the requirements presented are design objectives. The Architect-Engineer is encouraged to suggest changes where they would not seriously deviate from the overall requirements and would result in (1) improved performance or (2) greater environmental sustainability in arriving at the results. Read and follow Air Force standards such as Engineering Technical Letters, applicable chapters of Unified Facilities Criteria (UFC) 1-200-01 on General Building Requirements, UFC 1-200-02 on High Performance and Sustainable building Requirements, UFC 3-600-1 on Fire Protection Engineering, , UFC 4-010-01 on Antiterrorism Standards, and applicable sections of the RAFB Base Facility Standards.

2.2.2. Project Specifications: A. Preparation of Specifications:

1. The designer shall use Robins AFB Division 1 and UFGS specs to develop the specs included in this package, in accordance with the outline in the contract and Robins Air Force Base Facility Standards. Contact the Contracting Officer or Base Project Manager after Notice to Proceed (NTP) to obtain a CD or e-mail containing all of the Robins AFB Division 1 and Robins Air Force Base Facility Standards. 2. The Government has provided with the contract package an index of specifications for Divs. 02-46 for this contract. Provided are all of the sections anticipated for the design.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 2 of 15

REVISED 10-May-2013

3. Division 1: The Government has edited certain Division 1 sections, and they are included in the contract.

a. To edit one of the Division 1 Sections already in the contract, such as Environmental Section, 01560, submit the request in a separate letter/e-mail directly to the Base Project Manager. Either spell out the requested change, or provide a complete edited Section that shows tracked changes. The Base Project Manager will then reply to the Contractor with approval/disapproval details on the proposed edits. Include the revised Section in the Specifications package. Also, include the Base Project Manager's reply in the Design Analysis. b. Include other available Division 1 Sections when practical, edited as needed. Ensure that they do not conflict with the Sections already in the contract, since the contract Sections take precedence.

4. Divisions 02-46:

a. The contractor must provide properly edited versions for the required sections in Divisions 02 through 46. The specs either are as provided or shall be taken from the Unified Facilities Guide Specifications (UFGS) package. If a suitable UFGS or Govt. spec. is not available for the required material/system, a suitable specification consistent with industry standards may be used but will be subject to approval by the Project Manager. b. Editing of Divisions 02 through 46 shall remove references to materials/systems that are not a part of the scope of the project. Leaving these within the spec. will cause confusion as to the materials/systems intended. Example: If a project contains metal studs only, Section 06 10 00 Rough Carpentry should not have references to wood studs. c. Add or delete RAFB Division 1 Sections from Divs 02-46 as needed for the design effort. All such additions and/or deletions shall be documented in the Design Analysis and are subject to approval/disapproval by 78 CEG/CENMP Project Manager.

B. Material Submittals:

1. The specification sections listed in the outline contain lists of material submittals. The contractor shall provide all applicable material submittals as listed. 2. It is best to provide the material submittals with the design packages to avoid delays in the Government granting approval for the contractor to start site work. Where material submittals are provided with design packages, each material submittal shall have its own AF Form 3000 and will require additional time beyond the design submittal review. Material submittals made at other times must use AF Form 3000 and may have a 4-week turnaround.

2.2.3. Pointers on Design Negotiation A. Formal Conferences: We expect the design firm to send only one to two persons to each formal review meeting on Preliminary and Final Designs.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 3 of 15

REVISED 10-May-2013

B. Direct design fees shall not exceed 6.0% of construction cost, since we have provided the design concept in Sections 01005 and 01020. C. Visits and involvement by design firm personnel after the approval and base signing of Corrected Final documents are to be covered out of design firm overhead, at design firm expense, as is customary in the industry. D. The Government will not pay for the design firm pre-construction work. This is also to be covered out of the design firm's overhead.

3. ADMINISTRATIVE INFORMATION 3.1. Contract Administration Authority 3.1.1. Authority: The Contracting Officer in Base Operational Contracting, AFSC/PZIOC, is responsible for the administration of this contract. The Contracting Officer has designated the Office of the Civil Engineer as the design and technical surveillance representative for this contract. 3.1.2. Design Guidance: Only the Contracting Officer can make changes in the description of the scope and provisions of this contract. No other verbal or written instructions by Government personnel carry any such authority. On many design-build projects, the user personnel may attempt to provide additional guidance and/or requests to the design firm during the design stages, especially when design firm personnel visit the work site. Further, the design firm personnel often request clarifications directly to the user personnel. Neither of these are acceptable actions. Only the Office of the Civil Engineer is authorized to provide design guidance, not the user personnel, and only in those cases where the directions do not constitute a "change" to the contract. 3.1.3. Changes without Proper Authority: The contractor must direct all concerns about contract changes to the Contracting Officer in writing, especially if they appear to involve an increase or decrease in scope that may require a formal contract change and adjustments in contract cost. If the contractor does not follow these requirements before acting on any such directions or instructions by other than the Contracting Officer, then the contractor takes such actions at its own expense. 3.2. Design Fee Payments 3.2.1. When to Bill: Do not bill for any design work until the action (such as a review conference) has been completed or held for that phase. 3.2.2. Decision: The Base Project Manager will decide whether each stage has been accomplished satisfactorily. 3.2.3. Fee payment guidelines: These are for the design portion of the contract without phasing:

Prefinal/Preliminary Conference Met 60% of design cost First Final Conference Met 80% of design cost Final CADD, Word Proc Disks verified by Base as correct 100% of design cost

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 4 of 15

REVISED 10-May-2013

(After Corrected Final signed by Design Flight Chief and others on base) 3.3. Channels for Obtaining Information 3.3.1. Point of Contact: The Office of the Civil Engineer will appoint a Base Project Manager for this work. The Base Project Manager will provide technical support to the Contracting Officer and serves as the primary point of contact for the AE on all technical matters, and all work performed by the AE on base will be coordinated with the Base Project Manager. 3.3.2. Coordination of Work: Except as specified herein, all requests for information necessary to do this work shall be made to the Contracting Office and Base Project Manager or his supervisor. The AE shall maintain at all times close liaison with that office by appropriate means to assure maximum coordination of the work. 3.3.3. User Personnel Contact: At no time are user personnel authorized to provide design or construction criteria or information directly to the contractor's design firm and construction crew. 3.4. Government Furnished Information: The Office of the Civil Engineer will furnish applicable data, drawings, and information as available for the described work. 4. DESIGN RESPONSIBILITIES AND DOCUMENTATION 4.1. General Regardless of any review, acceptance, or approval by the Government, the AE is responsible for the professional and technical quality of all designs, drawings, specifications, and other material produced under this contract. The design shall comply with good engineering practice as determined by the Office of the Civil Engineer. The AE is also responsible for the professional quality and adequacy of the service and materials furnished and for compliance with design criteria specified by the Government for use under this contract. 4.2. Conferences and Meetings 4.2.1. Periodic Design Progress Meetings: During the design phase of the contract, the contractor's representative and the lead designer shall meet as specified with the PZIOC representative, the CENMP project manager, and the CENME construction manager to discuss progress in accordance with the approved schedule. These meetings may be combined with the design review meetings if the contractor makes the request to the Contracting Officer at least one week ahead of the date for the design review meeting. 4.2.2. Meeting Records: The Contractor (or AE) shall provide to the Contracting Officer and 78 CEG/CENMP a written record of all conferences and meetings held between the Government and the contractor's design firm during which the technical design of the project is discussed. The primary items to note are decisions made and action items with responsible person noted and date due. These written records of conferences and meetings held between the Government and the AE shall not constitute a "Notification of Change" as described by the changes clause of the contract. Provide as and when noted in Section 01300. For additional record purposes, either the Contractor or the Government may elect to audiotape the meeting.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 5 of 15

REVISED 10-May-2013

4.3. Personnel Safety The design shall meet all applicable safety requirements of the US Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1) and the Occupational Safety and Health Act (OSHA). The construction specifications and drawings provided shall specify the OSHA standards in detail or by explicit reference; e.g., (1) Handrails and guardrails will be provided as required by OSHA standards 1910.23 or (2) Ladders will be constructed in accordance with OSHA standard 1910.27. 4.4. Life Safety Analysis As applicable, the design for new or renovated facilities shall include a life safety analysis. See sample in 01020 Appendix A. 4.5. ATFP Analysis As applicable, the design for new or renovated facilities shall include an ATFP analysis. Within renovation work, analysis will only denote compliance with ATFP requirements. No ATFP deficiencies will be included as these could be constituted as classified information. See sample in 01020 Appendix B. 4.6. Asbestos or Lead Paint The Government is not aware of any materials containing asbestos or lead paint in the existing building. However, the potential for encountering these materials remains. The AE shall notify the Contracting Officer immediately upon discovery of any suspect material. The Government will sample the material and take corrective action as required. Any further action by the AE will be covered by the Changes clause of the contract. 5. AREAS COVERED IN THE PROCEDURAL GUIDE FOR AE'S 5.1. Site Investigations 5.1.1 Follow the details noted in the Procedural Guide for AE’s for site investigations by visiting the project site prior to commencing design and performing all fieldwork necessary to determine the existing conditions at the site of the work. 5.1.2. Take load readings on electrical or mechanical equipment to verify existing load conditions. The AE shall furnish temporary metering as necessary for this purpose. 5.1.3. The AE shall take digital photos as necessary to assist in determining existing conditions and scope of demolition. Use digital cameras, and provide electronic copies of all photos to the Base Project Manager. If the AE desires to take photos in or enter a controlled area, a 48-hour notice is required to allow the Government to arrange escorts for taking photos or gaining access to the controlled area. 5.2. Design Analysis Provide a comprehensive design analysis as detailed in the Procedural Guide for AE’s.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 6 of 15

REVISED 10-May-2013

5.3 Interior Design 5.3.1. Structural Interior Design 5.3.2. Comprehensive Interior Design 5.4 Documentation Requirements Follow the Procedural Guide for AE’s sections for letters and forms, specifications, and drawings. 6. ORDER OF PRECEDENCE FOR DESIGN CRITERIA The Drawings included with the contract specifications for this project are intended to show the initial concept as conceived by Government personnel. They are provided to help clarify design objectives and are intended to be used as complementary with the documents below. Where there appear to be conflicts between various standards, follow this order of precedence: 6.1. First: Section 01020, Construction Design Performance Requirements, is intended to identify specific project requirements. In cases of criteria conflict, Section 01020 holds precedence over all other criteria mentioned or referenced. Project specifications define minimum material quality requirements for material and installation. The contract drawings furnished by the Government are complementary to the Specifications. 6.2. Second: Follow any edited specifications included with the contract documents. 6.3. Third: Follow the Procedural Guide for Architect-Engineer Firms (Procedural Guide for AE’s). This covers site investigations, design analyses, interior design, and documentation requirements for specifications and drawings. 6.4. Fourth: Follow the Robins AFB Facility Standard and Architectural Compatibility Standard. These define technical requirements for all construction at Robin AFB. In many cases, they also specify criteria for project drawings and specifications. They also reference the federal and national standards for compliance. 6.5. Fifth: Use the latest versions of Unified Facility Guide Specifications (UFGS) to edit for project. 6.6. Sixth: Areas not covered by the above shall be governed by the most severe DOD, Air Force, federal, or other national standard. 6.7. The Base Project Manager may grant waivers to these criteria. Request the waivers in writing for a decision, and then document them in the design analysis. Waivers are not valid until documented in an approved design analysis. 7. MEETINGS AND DESIGN SUBMITTALS 7.1. Project Pre-performance (Kickoff) Meeting

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 7 of 15

REVISED 10-May-2013

7.1.1. Immediately after notification of contract award, contact the Contracting Officer to set up the Pre-performance (Kickoff) Meeting at Robins AFB. The Contracting Officer or Project Manager normally will schedule to meet within 14 days after contract award. The usual attendees are the same as would be invited to a Pre-construction conference for a design-bid-build contract.

7.1.2. Checklist: Use the attached Kickoff Meeting Checklist to help prepare the items to bring to the meeting.

7.1.3. Items for Contractor to address at the Kickoff Meeting will include as a minimum the following:

A. Present a copy of the Kickoff Meeting Checklist to the Base Project Manager. B. Discuss the submittal, for approval, of the contractor's records on negotiations between the Government and Contractor before award. C. Provide a project timeline schedule at the Kickoff meeting for CO or COR review and/or approval.

D. Set up a time/day each month for the design progress meeting, per paragraph 4.2.1. E. Discuss the format for the meeting records per paragraph 4.2.2. F. Make request for any additional documents needed by the Contractor at this time. J. Discuss at Contractor request any clarifications and fine-tuning of the details of the contract requirements.

7.1.4. Negotiations: Provide a submittal, for approval, of the contractor's records on negotiations between the Government and Contractor before award, if such negotiations took place. If no such records are submitted and approved, then all future conflicts over the negotiation results shall be decided by most stringent project requirements. 7.1.5. Schedule: Submit for approval a comprehensive project timeline schedule. The Bidder/Contractor and AE shall determine and submit the written schedule of plans with numbers of days for each step in the process for the design submittals and subsequent construction to ensure they meet the time schedule for the entire project.

A. Notice to Proceed: The Government will not give the contractor notice to proceed (NTP) until the Contracting Officer approves the schedule at or after this post-award meeting on Pre-performance. B. Material/Design: The Contractor shall have approved submittals before ordering any equipment under this contract. If equipment is ordered prior to receiving approval, it will be solely at the Contractor’s risk. C. Base Design Approval: The following individuals or their alternates are responsible for signing the drawings for base approval of the design drawings.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 8 of 15

REVISED 10-May-2013

Title Office Person Engineering Section Official 78 CEG/CENMP Stefanie Dawson Design Project Manager 78 CEG/CENMP David Trescott Constructability Official 78 CEG/CENME Don Green Fire Department Official 78 CES/CEXFP (Fire Dept.) Lupe Diaz D. Typical Schedule Dates: The Government's estimated time schedule is attached as an Appendix to Section 01300. The total time of the contract is as set forth in the Appendix, unless the Contracting Officer chooses to alter the contract times through issuing amendments after inputs from bidders at least 10 days before bid opening.

7.1.6. Preaward Submittals: In addition to bringing the approved schedule to the Kickoff meeting, also bring copies of the approved design firm submittal and subcontractor submittal. 7.1.7. Promised Documents: At least three workdays before the meeting, advise the Project Manager of any additional items needed for the design effort. 7.1.8. Clarifications and Fine Tuning: Use the meeting to ask any questions needed to begin the design effort in earnest. Make site visits or contacts with base personnel as may be helpful. 7.2. Preparations before Submitting a Design Package 7.2.1. Contact the Project Manager to obtain a time and date for the review conference. 7.2.2. After scheduling the review conference, deliver hardcopies and a CD to the contracting officer, notifying both the contracting officer and the Base Project Manager of the delivery by e-mail. Provide submittal with an AF Form 3000 listing the deliverables. Specific requirements for deliverables are listed below for each package. 7.2.3. Except for First Final Design packages, allow 14 calendar days after the date each package is delivered to the Base Project Manager for adequate design review by Base personnel. Written review comments will be e-mailed or placed into the off-base postal system by the end of the 14 days. Time does not include additional time needed for material submittals submitted with a design package. 7.2.4. For First Final Design packages, allow 21 days for the same actions described above. 7.3. Delivering Packages Provide the items in ( ) if changes were made because of review comments or designer revisions. Ask for and follow the Base Project Manager’s directions when unsure whether to send a particular revision. 7.4. Prefinal/Preliminary Design 7.4.1. Consider the design provided by the Government as already completed to 35% design. 7.4.2. Prepare a preliminary design featuring the items listed below. This should correspond to the AE taking the design from the percentage already completed by the Government to being about 60 – 70% complete on drawings and specifications, and 90 – 100% complete on the design analysis. Drawing and

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 9 of 15

REVISED 10-May-2013

specification completeness shall be interpreted as including all major components to convey a full understanding of the design intent and shall include all major building components. 7.4.3. Prior to this submission, the AE shall have held an internal design review to confirm all inter-discipline design assumptions made during the course of the design (e.g. has the Mechanical Engineer properly determined wall construction in heating/cooling calculations?). Include this internal review in the design analysis. 7.4.4. Contact the Project Manager to obtain a time and date for the review conference. 7.4.5. After that, send a notification of shipment by e-mail to the Base Project Manager and Contracting Officer. Send deliverables as noted below. 7.4.6. Allow 14 calendar days after the date each package is delivered to the Base Project Manager for adequate design review by Base personnel. Written review comments will be e-mailed or placed into the off-base postal system by the end of the 14 days.

NOTE: If the Government decides that the design submittal was inadequate, then the Contracting Officer/Design Flight Chief reserves the right to direct the contractor to resubmit an adequate design package.

7.4.7. Send the entire package as listed below to the Contracting Officer (do not send directly to the Project Manager). The Contracting Officer will log the AF3000 with the design package in and transfer to the Project Manager. Deliverables are as follows: Qty Description 1 set 11”x17” Drawings, hardcopy, bound. 1 set 11”x17” Drawings, hardcopy, unbound (clipped together). 1 set 22”x34” Full size drawings, hardcopy, bound 1 set Specifications, hardcopy, bound 1 set Specifications, hardcopy, unbound (clipped together) 1 Preliminary DA, hardcopy, bound. 1 Preliminary DA, hardcopy, unbound (clipped together). 1 CD with electronic files of items above, all documents in pdf format NOTE: The Base Project Manager will advise the other designers in his/her office of the review conference via e-mail. 7.5. First Final Design 7.5.1. Obtain written approval from the CENMP Chief before proceeding with this next design package. 7.5.2. After approval to proceed, prepare a final design based upon the review comments. This work shall be in a form considered to be 100% complete. 7.5.3. Prior to this submission, the AE shall have held an internal design review to confirm all inter-discipline design assumptions made during the course of the design (e.g., has the Mechanical Engineer properly determined wall construction in heating/cooling calculations?). Include this internal review in the design analysis.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 10 of 15

REVISED 10-May-2013

7.5.4. Contact the Project Manager to obtain a time and date for the review conference. 7.5.5. After that, send a notification of shipment by e-mail to the Base Project Manager and Contracting Officer. Send deliverables as noted below. 7.5.6. Allow 21 calendar days after the date each package is delivered to the Base Project Manager for adequate design review by Base personnel. Written review comments will be e-mailed or placed into the off-base postal system by the end of the 21 days.

NOTE: If the Government decides that the design submittal was inadequate, then the design chief of CENMP reserves the right to direct the contractor to resubmit an adequate design package. This may be due to the lack of annotated review comments, an incomplete submittal, or non-incorporation of review comments.

7.5.7. Send the entire package as listed below to the Contracting Officer (do not send directly to the Project Manager). The Contracting Officer will log the AF3000 with the design package in and transfer to the Project Manager. Deliverables are as follows: Qty Description 1 set 11”x17” Drawings, hardcopy, bound. 1 set 11”x17” Drawings, hardcopy, unbound (clipped together). 1 set 22”x34” Full size drawings, hardcopy, bound 1 set Specifications, hardcopy, bound 1 set Specifications, hardcopy, unbound (clipped together) 1 Preliminary DA, hardcopy, bound. 1 Preliminary DA, hardcopy, unbound (clipped together). 1 CD with electronic files of items above, all documents in pdf format NOTE: The Base Project Manager will advise the other designers in his/her office of the review conference via e-mail. 7.6. Corrected Final Design 7.6.1. Obtain written approval from the CENMP Project Manager before proceeding with this next design package. 7.6.2. After approval to proceed, prepare and submit the corrected final design package. 7.6.3. Prior to this submission, the AE shall have held an internal design review to confirm all inter-discipline design assumptions made during the course of the design (e.g. has the Mechanical Engineer properly determined wall construction in heating/cooling calculations?). Include this internal review in the design analysis. 7.6.4. The above submittal will be reviewed without a formal conference at the Office of the Civil Engineer. Written review comments are not anticipated, but if they are, they will be provided at or within three workdays after the submittal is received.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 11 of 15

REVISED 10-May-2013

NOTE: If the Government decides that the design submittal was inadequate, then the design chief of CENMP OR CENME reserves the right to direct the contractor to resubmit an adequate design package. This may be due to the lack of annotated review comments, an incomplete submittal, or non-incorporation of review comments.

7.6.5 Send the entire package as listed below to the Contracting Officer (do not send directly to the Project Manager). All drawing sheets shall be stamped and signed by a registered architect (RA, architectural drawings) or a registered professional engineer (PE, all other drawings). The Contracting Officer will log the AF3000 with the design package in and transfer to the Project Manager. Deliverables are as follows: Qty Description 1 set 11”x17” Drawings, hardcopy, bound. 1 set 11”x17” Drawings, hardcopy, unbound (clipped together). 1 set 22”x34” Full size drawings, hardcopy, bound 1 set Specifications, hardcopy, bound 1 set Specifications, hardcopy, unbound (clipped together) 1 Preliminary DA, hardcopy, bound. 1 Preliminary DA, hardcopy, unbound (clipped together). 1 set Miscellaneous forms, filled/signed, hardcopy, unbound (clipped together) 2 CD with electronic files of items above, all documents in pdf format. Also provide

drawings in dwg (CAD) format and specifications in docx (MS Word) format. 7.7. Formal Approval of Design Documents 7.7.1. After the CENMP Project Manager has accepted the corrected final design package with the PE/RA stamped and signed drawings, the Base Project Manager must obtain a set of approval signatures on a project approval sheet. All final design and as-built drawings and package shall be stamped and signed by a registered architect/ registered professional engineer who is specialized in the field of his professional practice. Provide electronic copy of specifications, drawings, etc. as required. Electronic drawings shall be in AutoCad 2013 version file. 7.7.2. Allow the Government 14 days for processing the signatures.

NOTE: The CENMP Project Manager reserves the right to direct the contractor to make further corrections due to non-incorporation of review comments or just-discovered design errors and omissions.

7.7.3. After the base personnel have placed their approval signatures on the project approval sheet, the Base Project Manager will inform the Contracting Officer and retain that sheet and the PE/RA stamped and signed drawings set in the CENMP official project folder (case file). 7.7.4. The Contracting Officer will then give the Contractor formal Notice to Proceed (NTP) for construction. The contractor shall then proceed with construction in accordance with the approved design package. 7.8. Abbreviations

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 12 of 15

REVISED 10-May-2013

The above listings of submittal attachments use the following abbreviations: Letters/Memos: AF3000 Form AF3000 listing all deliverables for submittal (i.e. CD, Specs – HC bound, DD –

11”x17” binder clipped, etc.) Narratives/Packages: KO Forms Kick-Off Meeting Forms (after contract award)

Contractor’s Kick-off Meeting Checklist Project Timeline AF3064

DR Forms Design Review Forms

Contractor’s Design Submittal Checklist DA Design Analysis

Includes following bookmarks: Project scope, Discipline narratives, Discipline calculations, LEED narrative, LEED Scoring Sheet, Comprehensive interior design objectives (if CID is provided), Meeting minutes and Annotated comments (include all previous minutes and comments) Hardcopy format – 8 ½ x 11, tabbed, bound (binder clipped and punched where

noted) Electronic formats – single PDF (w/bookmarks) and MS Word (2010)

Specs Specifications

Includes all divisions (with Div.1 base specs including SOW sections) Hardcopy format (HC)– 8 ½ x 11, tabbed, bound (binder clipped and punched

where noted) Electronic formats (CD)– single PDF file (w/bookmarks) individual MS Word files (2010)

Specs(Draft) Specs in original form with deletions crossed out and inserts indicated or attached. This aids the base reviewers in tracking what is to be deleted as well as added. Recommend using “Track Changes” in MS Word.

SID Structural Interior Design package. Scan or photograph (without flash) color board for

electronic version. CID Comprehensive Interior Design package (if required by SOW). Scan or photograph

(without flash) color samples for electronic version. DD Design Drawings

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 13 of 15

REVISED 10-May-2013

Civil, architectural, life safety, mechanical, plumbing, electrical, fire protection, fire alarm, communications and all other applicable design drawings. Hardcopy format (HC) – Full sized, ANSI D, 22”x34” Half sized (50% reduction), 11”x17” (binder clipped and

punched where noted) Electronic formats (CD) – single PDF (w/bookmarks) Autocad 2013 format (dwg)

DFL Design Furniture Layout – Floor plan with desk/furniture layout marked up by user (if applicable)

RD Base record drawings/as-builts (include all drawings in DD incorporating changes) CF Forms Corrected Final Forms

AF 2519 Welding and Safety Checklist, ODS Ozone Depleting Substance Certification

<<<<< END OF NARRATIVE SECTION >>>>> Kickoff Meeting and Design Submittal Checklists follow.

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 14 of 15

REVISED 10-May-2013

CONTRACTOR’S KICKOFF MEETING CHECKLIST Project: Enter check mark or date below. In general, these items must be accomplished or prepared before the meeting.

Check/Date No. Item

1 Contact the Contracting Officer immediately after award to set up this meeting.

2 Prepare (if applicable) a record of last-minute negotiations for presentation

and approval.

3 Bring a project timeline schedule at the Kickoff meeting for CO or COR review and/or approval.

4 Bring the 2 Forms 3064 as directed in Section 01300.

5 Request from the Base Project Manager of any additional documents needed,

such as: drawings title block, signature block, master specs, drawings standards, record drawings, and transmittal letter masters.

6 Prepare to discuss needed clarifications and ask questions to proceed with

the project.

7 Prepare to record major discussion points and decisions made at the meeting in order to provide a written copy of meeting minutes with 3 days.

8 All design packages are to be delivered to the Contracting Officer with AF

Form 3000, in accordance with approved project schedule.

9 Set up the dates and times for the monthly progress meetings.

10 Other:

UHHZ160050 (DESIGN-BUILD) DESIGN AFTER AWARD - 01030

(DESIGN-BUILD) DESIGN AFTER AWARD 01030 - 15 of 15

REVISED 10-May-2013

CONTRACTOR’S DESIGN SUBMITTAL CHECKLIST Project: Submittal Stage (Check One): Preliminary First Final Corrected Final Enter check mark or date below. If not applicable, put "N/A."

Check/Date No. Item

1 Prepared this design submittal per the specs, drawings, and Procedural Guide for AE firms (includes descriptions of what should be in the Preliminary and Final Designs.)

2 Included all the attachments listed in spec section 01030.

3 Included a Design Analysis with outline per the Procedural Guide for AE

firms.

4 Included copies of all meeting records in the Design Analysis.

5 Addressed all review comments from past submittals along with placing annotated comments in the Design Analysis.

6 Used Robins AFB Division 1 and UFGS specs to develop the specs included

in this package, in accordance with the outline in the contract and Robins Air Force Base Facility Standards.

7 Set up the time and date of the review conference with the Contracting

Officer or Project Manager before sending the design package.

Date:

9 Completed internal design review of this package on date shown.

10 Applicable material submittals are included with this package.

11 A revised schedule is included.

12 Understand the contractor cannot start field/site work until notified that all

applicable base personnel have signed the corrected final drawings and Notice To Proceed has been issued for construction.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 1 of 13

PART 1 - GENERAL

1.01 SPECIAL REQUIREMENTS:

A. Controlled Areas (General): Omitted, project is not in a controlled area.

B. Airfield Zone Waivers: Omitted, project is not within the airfield zone.

C. Airfield Zone Site Requirements: Omitted, project is not within the airfield zone.

D. MFH projects: Omitted, project is not an MFH project.

E. AMC/Joint STARS Area: Omitted, project is not in this area.

F. Electronic Warfare Complex (Bldg 229): Omitted, project is not in this area.

G. Avionics Complex: Omitted, project is not in this area.

1.02 UTILITY REQUIREMENTS

A. Outages: Request utility outages in writing to the Base Civil Engineer, with a copy to the

Contracting Officer, a minimum of 21 days before the proposed outage. These will be scheduled

at Government convenience and may be at times other than normal working hours. For example,

the times may be on weekends or during the second and third shifts (including holidays, holiday

weekends, and work curtailment days). These are at no additional cost to the Government.

B. Metering.

1. Credit Unions, banks, public schools and other non-Federal organizations at their expense

furnish, install, operate and maintain all facilities required to obtain service, including suitable metering

and regulating equipment and service connections to the government’s utility system.

2. For DoD agencies, including MWR activities and Air National Guard Units; Defense Base

Operating Fund activities; non-DoD Federal agencies, including post office facilities; occupants of

privately owned mobile homes located on Air Force installations; government civilian employee renting

quarters owned or controlled by the Air Force; and occupants of military housing projects insured by the

government under Title 12 U.S.C., Sections 1701 and 810, install meters on all:

a. New facilities or renovated facilities, using applicable constructions funds.

b. Existing facilities at government expense when the total cost to install the meter does

not exceed the estimated gross revenue for 1 year. For energy management purposes, install permanent

or temporary meters at government expenses, regardless of gross revenue for 1 year, on new or existing

individual buildings, structures, appliances, or equipment. For installing meters on existing facilities,

the Base Civil Engineer budgets for and prioritizes installing meters using fund sources that include

Operations and Maintenance; Research, Development, Test and Evaluation; Military Family Housing

(P713 or P722); Medical Support Facilities; and, DBOF facilities.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 2 of 13

3. Meter family house using a master metering system according to DoD Instruction 4165.37.

4. Provide service entrance metering on the facility for electrical, natural gas, and steam utilities,

as applicable. Due to small demand based on new fixtures (2 sinks), water meter will not be

required.

1.03 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items.

B. Material Submittals: None required under this section.

C. Other Submittals: Provide the following submittals as required by the contract or as directed

by the Contracting Officer.

Inspector

Para # Description Date Required Checklist

1.01.B.1 Airfield Construction Waiver - Not Applicable

1.01.B.2 Airfield Crane Request – Not Applicable

1.01.C.2 Airfield Schedule – Not Applicable

1.01.C.3 Airfield Storage Request – Not Applicable

1.01.C.4 Airfield Haul Route Request – Not Applicable

1.01.C.6 Return AF Forms 483 – Not Applicable

1.01.D MFH Courtesy Slip – Not Applicable

1.01.E AMC/Joint STARS Information – Not Applicable

1.01.G.1 Avionics Complex Information – Not Applicable

1.02 Utility Outage Requests 21 days prior to outage ______

1.04 Safeguarding LAN Com Lines 21 days prior to work ______

3.01.E Road/Parking Closure Request 21 days prior to work ______

3.02.A Govt Property Damage Notice Within 3 days of event ______

3.03.C Warning Tape 14 days after NTP ______

3.03.D Tracer Wire 14 days after NTP ______

3.04 Bldg Number on Corners – Not Applicable

3.05 Before - Site Photos Before Construction ______

3.05 After - Site Photos Before Final Inspection ______

3.08 Storage and Trailer Request 14 days after NTP ______

Form 1 Fire Alarm Request 7 days before work ______

Form 2 Fire Alarm Inspection Before Work 3 days before work ______

Form 3 Fire Alarm Inspection After Work Before pre-final ______

1.04 SAFEGUARDING COMMUNICATION FACILITIES: For work that will interfere with Local

Area Network (LAN) cable, aerial cable, house cable, underground cable, or other communication

facilities, notify the Contracting Officer in writing 21 days before the scheduled construction. Do no

work until receiving written approval.

PART 2 - PRODUCTS - OMITTED

PART 3 - EXECUTION

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 3 of 13

3.01 DIGGING/EXCAVATION REQUIREMENTS: The Drawings show underground utilities and

structures as presently shown on the best available record drawings of the site, and these may have some

inaccuracies. The information is provided for general bidding purposes only. Actual locations and

quantities must be determined at the site while obtaining the form below.

A. Digging/Excavation Permit (Obtained on Base): Digging permits are obtained at 0800

Monday mornings, only, in Building 1555. The Contractor, along with the technical

representative, shall meet with Civil Engineering utility personnel at this time to make all

necessary arrangements for the excavation permit before any digging. The Contractor will be

given instructions on how to prepare and properly complete Digging/Excavation Permit. This

includes coordination before beginning any work involving digging/excavation and location of

buried structures and utility lines. Before getting signatures, provide a drawing indicating the

full extent of digging/excavation (width/depth/length of trench or hole). Civil Engineering utility

personnel will meet with the Contractor at the site and locate their underground utility lines and

buried structures that might be affected by any digging/excavation. Do not do any digging until

all parties have approved the permit (three day maximum). The digging/excavation permit shall

be effective only for the time period indicated by the final signature authority.

B. Re-coordination of the Digging/Excavation Permit with all organizations and the technical

representative shall be required for any additional time required after expiration of the original

time period. No digging/excavation shall be done after l600 hours on weekdays or anytime on

weekends unless prior approval is obtained.

C. Location of Buried Structures and Utility Lines: Accurately locate and stake buried

structures and utility lines indicated.

D. Excavation, trenching, and backfilling: Excavate to the required depth by hand digging

within three (3) feet either side of the buried structures or utility line. Do not use motorized

equipment within these parameters. Only open those trenches for which material is ready for

replacement. As soon as approved by the technical representative, backfill trenches as required

by the drawings or specifications. As a minimum, replace topsoil and grass the disturbed area by

seeding and watering.

E. Damage: The contractor is responsible for any damage to underground structures and utility

lines identified on the drawings and any identified and marked in the field as a result of obtaining

the digging/excavation permit. If any underground utility is damaged, notify the technical

representative immediately.

F. Cutting of Roads, Streets, and Paved Parking Areas:

1. Mark, barricade, and illuminate construction work on or near roads or streets

which may present a traffic hazard in accordance with the Manual on Uniform Traffic Control

Devices (MUTCD) 2000. Closures of streets, parking lots, and other traffic areas will not be

permitted unless approved by the Contracting Officer after written request 30 days before the

scheduled closure.

2. Road cuts shall be backfilled immediately after completion of associated utility

work. When the road is reopened, the cut shall be filled with temporary or permanent materials

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 4 of 13

to a smooth condition, or metal plates or other approved methods shall be employed to prevent

discomfort or damage to vehicular traffic. Road cuts shall be permanently closed within 5

working days unless approved otherwise by the Contracting Officer. Provide advance signage

warning motorists of the condition in accordance with the MUTCD. Repair streets as shown on

the drawings.

3.02 REPAIR OF WORK AND MATERIAL: Carefully lay out cutting, channeling, chasing, or drilling

of finish or structure or other surfaces for the installation of equipment or material to avoid damaging

Government property or adjacent materials not involved in the project. If Contractor personnel or

equipment inadvertently damage such items, then follow the procedures below. Failure to follow the

notification procedures below shall be considered a serious violation of the contract.

A. Notify the Contracting Officer by telephone immediately and confirm within 3 days with a

typed letter if damage to Government property occurs. The Government reserves the right to

require the Contractor to work overtime and purchase material for repair before the end of the

workday at no additional cost to the Government.

B. Repair damage to building or equipment to match existing as directed by the Contracting

Officer with skilled workmen of the trades involved at no additional cost to the Government.

C. Repair Fire Resistant Assemblies that have been violated before the end of the day. In the

event the work is incomplete, provide fire-rated gypsum board to cover holes 2-inch and greater

in any dimension.

D. Reconnect Disconnected Equipment before the end of the day and insure that it is operating.

E. Existing Equipment and Material to remain or to be relocated is the property of the

Government. However, the Contractor is responsible for items to remain.

F. Labels on equipment plates with information shall be properly protected before any operation

that could damage or cover the label.

G. Fire Alarm: This contract involves work requiring existing fire alarm equipment either to

remain or to be removed and reinstalled. The Contractor shall comply with the requirements of

the inspection forms in the Appendix at the end of this section. One form is to notify the

appropriate personnel that work is being accomplished on fire alarm systems. The other forms

are used to establish the conditions of the system components prior to and following the

contractor’s work.

3.03 IDENTIFYING UNDERGROUND LINES AND STRUCTURES:

A. Regardless of statements in other Spec sections, provide tracer wires and warning tapes over

buried underground utilities and structures. Follow these requirements if the other Spec sections are less

detailed and stringent.

B. These include all underground items such as utility lines, oil/water separators, fuel and water

storage tanks, and utility pits and manholes with tops below grade.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 5 of 13

C. Provide a warning tape of standard industrial width and thickness with imprinted words

identifying the type of utility line or structure below it. Place along the length (and width if

not a utility line) of the protected item at one-foot depth below grade.

D. For buried non-metallic lines and structures also provide a tracer wire placed just above them, so

conventional locating equipment may be used to locate the lines or structures. These items may be made

of plastic, fiberglass, or similar non-metallic material. Design basis of the tracer wire is BMS Heavy

Tracer Wire by Utilitronics, PO Box 480, Stoughton, MA 02072 - phone 1-800-245-8850. Use no less

than #12 AWG copper solid wire, 5/64” HMWPE insulation, with white color.

3.04 BUILDING NUMBER: Omitted.

3.05 SITE PHOTOGRAPHS:

A. General: Take "before" and "after" color photographs of the work site on a digital camera

with a resolution for each picture of at least 60 KB compressed image. Provide for approval on a

CD-RW/DVD disk at least 24 views chosen by the Technical Representative of the Contracting

Officer (TRCO) before construction. Provide additional views as directed to show the full extent

of the work. Provide for approval an identical set of "after" views.

B. Underground Utilities: For projects where there is trenching for any underground utilities,

even if just laterals from outside equipment into mech-elec rooms, take an additional set of as-

built photos after construction for approval before final inspection. These must cover the entire

length of the trenching with a view to showing nearby landmarks to enable a person to locate the

line in the field in the future by using the photos after the disturbed soil is no longer visible.

3.06 SITE MAINTENANCE, CLEAN UP, AND RESTORATION:

A. Maintain the work site in a neat, orderly, and safe manner. Cut grass regularly to maintain

site to base standards.

B. Remove scrap, waste, and excess materials promptly. Provide signs, barricades, and lights as

required to protect base personnel.

C. Do not allow trash and debris to accumulate and become unsightly. Sweep up and collect in

contractor-maintained disposal containers daily. Dispose of collected debris weekly as a

minimum.

D. Store materials on site in a neat and orderly manner.

E. Restore the project site to its final condition as required by the contract as soon as possible.

F. Do not open trenches or excavations until material is on-hand or scheduled to arrive within

three days. Close excavations or ditches as soon as the work has been placed, inspected, and

accepted by the Government.

3.07 CRANES, BOOM-TRUCKS, ETC.: Any tall equipment, such as a crane or boom-truck, must be

lowered when not in use, especially at the end of each work day. If used at night, then operate the

appropriate lighting at the peak element.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 6 of 13

3.08 STORAGE AND OFFICE AREA: Submit a request for approval if the Contractor desires a

storage area or storage/office trailer(s) on Base. If approved, the Contractor will be allowed limited land

area to put an office and/or storage trailer and storage area, but only for this contract. The location will

be as identified by the Technical Representative within the Base perimeter.

A. Trailers: All contractor trailers must be identified with a professionally lettered and neat sign

giving the name and phone number of both the trailer rental company and the contractor.

Trailers must be in good repair and give a presentable appearance. Trailers used as Field Offices

shall be anchored with rods and cable or by steel straps to ground anchors. The anchor system

shall be designed to withstand high winds and must meet applicable state or local standards for

anchoring mobile homes. Minimum 1 each corner.

B. Items stored for the project on Base are the responsibility of the Contractor. Replace all such

items acquired for this contract that are stolen, vandalized, damaged, or otherwise unusable - at

no additional cost to the Government. The Contractor may install a temporary fence in the

manner and of the type that is acceptable to the Contracting Officer.

C. This site shall be kept clean and orderly, or the Contracting Officer may require the

Contractor to evacuate the site before the end of the contract.

3.09 PROJECT CONSTRUCTION SIGNAGE: See Robins AFB Facility Standards, Part 4B.

3.10 ROOF WARRANTY BUILDING SIGNAGE: Submit a copy for approval of the Contractor’s

proposed roof warranty building signage in accordance with example below to be mounted on corner of

building. If approved, the Contractor will install roof warranty signage at location as identified by the

Contracting Officer’s Technical Representative.

ROOF WARRANTY SIGN EXAMPLE

SIZE TO BE 8 ½” HIGH X 11” WIDE. SIGN TO BE ¼” REYNOBOND MATERIAL WITH VINYL

BACKGROUND (FEDERAL STANDARD (FED-STD) 595B COLOR, STANDARD BROWN –

10100) AND VINYL LETTERING (FED-STD 595A COLOR, WHITE - #17875). LETTERING TO

BE BLOCK STYLE, WITH ARIAL FONT.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 7 of 13

<<<<< END OF SECTION >>>>>

Appendix follows:

Form 1 – Fill out and submit to get approval to work on a fire alarm system.

Form 2 – Fill out and submit to document existing conditions of a fire alarm system to be worked on.

Form 3 – Fill out and submit to document conditions of a fire alarm system after contractor work is

completed.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 8 of 13

FIRE ALARM SYSTEM INSPECTION

COMPONENTS EXISTING TO REMAIN OR TO BE REMOVED AND REINSTALLED

PART 1. Prior to construction start DONE (Contractor to Initial/Date)

A. Schedule testing of all fire alarm components not scheduled for demolition (at Government's

convenience-minimum 72-hours notice required)

Person Notified (at CENME)

B. List all persons attending test:

* Fire Alarm Shop (CEOFA)

* Contractor Superintendent

Construction Management (CENME)

** Sub-Contractor Foreman

* Required Personnel

** This shall be the person(s) directly overseeing any removal and re-installation of fire alarm

equipment.

C. Inspection (CENME Inspector to check one of the following)

(All parties to initial below):

All existing components in the project area have been tested and are working properly

All components have been tested and the following are not working properly. (Specify

equipment, quantity, and location; e.g., 2 smoke detectors in northwest quadrant of Room 102.):

Acknowledgments:

CEOFA ______________ CENME _____________ Contractor ______________

Sub-Contractor ________________ Others: _________________

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 9 of 13

Page 1 of 2

FIRE ALARM SYSTEM INSPECTION

(COMPONENTS EXISTING TO REMAIN OR TO BE REMOVED AND REINSTALLED)

PART 2. At completion of work: DONE (Contractor to Initial/Date)

(before Prefinal inspection)

A. Schedule testing of all fire alarm components not scheduled for demolition (at Government's

convenience-minimum 72-hours notice required)

Person Notified (at CENME)

B. List all persons attending test:

* Fire Alarm Shop (CEOFA)

* Contractor Superintendent

Construction Management (CENME)

** Sub-Contractor Foreman

* Fire Department (CEXFP)

* Required Personnel

**This shall be the person(s) directly overseeing any removal and re-installation of fire alarm

equipment.

C. Inspection Results (to check by CENME Inspector all parties to initial below):

_______Passed: All components have been tested and the system has been returned to its

original condition.

NOTE: Minor failures referenced below are defined as only one or two components having been

improperly reconnected or damaged and which can be readily repaired. Any damage to wiring, conduit

or alarm panels, or more than one or two components, is a major failure on the part of the Contractor.

Failed (Minor): All components have been tested and the system has not been returned to

its original condition. The following items must be repaired, replaced, or reconnected as necessary to

restore their operation, at no additional cost to the Government, and those items retested.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 10 of 13

Page 2 of 2

Failed (Major): All components have been tested and the system has not been returned to

its original condition. The following items must be repaired, replaced, or reconnected as necessary to

restore their operation, at no additional cost the Government, and those items retested.

Acknowledgments:

CEOFA ______________ CENME _____________ Contractor ______________

Sub-Contractor ________________ Others: _________________

NOTE: The contractor shall reimburse the Government for any failed (major) test at the current shop

rate (between $30.00 and $50.00) per person hour, including one (1) hour per person travel and

preparation time. This does not include the CENME Inspector. We estimate between 2 and 4 people

will be required.

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 11 of 13

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 12 of 13

UHHZ160050 SITE REQUIREMENTS - 01040

REVISION DATE 31 JULY 2014

SITE REQUIREMENTS

01040 - 13 of 13

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 1 of 9

PART 1 - GENERAL

1.01 GENERAL:

A. BASIC:

1. Provide items requiring drawings, diagrams, certifications, manufacturers’ literature, data

brochures, technical data, sample requests, forms, and other data as noted under the submittals

section of each specification section. All submittals and operations and maintenance data shall

be submitted in a 3-ring binder or comb binder.

2. This section does not describe design submittals required under design-build contracts.

B. CONSTRUCTION SUBMITTALS:

Inspector

Para No. Description Date Required Checkmark

1.01.C1 Time Schedule by Preperf/Precon Mtg _____

1.01.C1 Meeting Records As Noted or Monthly _____

1.03.D Progress Report Monthly _____

1.03.E List of Values with First Progress Report _____

1.03.F Daily Reports Weekly _____

1.10 Closeout Report before Final Inspection _____

C. PRECONSTRUCTION SUBMITTALS:

1. In accordance with this Section, the following documents are required and must be

submitted within 14 days after Construction NTP is issued:

List of proposed subcontractors

List of proposed products

Construction Progress Time Schedule (AF Form 3064)

1 Set of Bid Documents (Drawings & Specs)

Submittal register

Meeting Records

Health and safety plan

Work and Demolition plan

Quality control (QC) plan

(Environmental protection plan)

(Storm Water Pollution Prevention Plan)

(Storm Water Notice of Intent)

(Existing Conditions – Photographs and Field Verification Sign-off)

D. CONTRACTOR RESPONSIBILITY:

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 2 of 9

1. Review, Corrections, or Comments made on the Submittals do not relieve the contractor from

compliance with the requirements of the Drawings, Specifications, Addendums, and Contract

Documents. By entering into this contract, the contractor agrees that the purpose of submittals

is to demonstrate to the contracting officer that the contractor understands the design concept

and that he demonstrates his understanding by indicating which equipment and material he

intends to furnish, install, and use. Review of shop drawing will be general only for basic

conformance with the design concept. The Government’s review of such drawings, schedules,

or cuts shall not relieve the contractor from the responsibility for correcting all errors of any

sort contained in the submittals.

2. The contractor is responsible for confirming and correlating all quantities and dimensions;

selecting proper fabrication processes, construction methods and installation techniques;

coordinating this work with that of all other trades; and performing all work in a safe,

workmanlike and satisfactory manner.

3. The Government has not stipulated dates for turning in material submittals, unless noted

elsewhere in the specifications. The contractor must manage his/her material and equipment

lead times for obtaining approval in sufficient time to complete work on schedule.

1.02 SUBMITTALS: Provide the following submittals as required by the contract or as directed

by the Contracting Officer.

Inspector

Para # Description Date Required Check Mark

1.05 A Superintendent Data As Directed ___

1.08 Equipment List 30 Days before Prefinal ___

1.03 SUBMITTAL INSTRUCTIONS: Each Specification Section lists the submittal requirements unique

to it. The following apply to all sections.

A. SUBMITTAL FORMS: Material submittals shall be made using AF Form 3000. For design-

build (DB) projects, all design submittals only require a transmittal letter. Material submittals

included with DB design packages do not require the use of the AF Form 3000, but they are

considered part of the design package.

B. MATERIAL SUBMITTALS:

1. COMPLETE SUBMISSIONS: All items requiring submittals for each section shall be

provided at one time. Partial submittals will be returned without approval. No time extensions

will be granted for failure to comply. In some instances the specifications may require certain

items from one or more specifications sections to be submitted at one time. For example,

condensing units and air handler submittals may be required to be provided together.

2. SUBMITTAL CHECKLIST: The contractor shall complete a copy of the checklist

provided in the submittals paragraph of each specification section. This checklist shall be

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 3 of 9

provided with each submittal. Submittal information shall be arranged in order to correspond

with each checklist.

3. TIME: The Contractor shall have approved submittals before ordering any equipment

under this contract. If equipment is ordered prior to receiving approval, it will be solely at the

Contractor’s risk. Under no circumstances will material be installed prior to approval of

submittals. There will be no time schedule for providing material submittals unless noted

elsewhere in the specifications. The Contractor will be required to manage his

materials/equipment lead times and obtain approval in sufficient time to complete the work on

schedule. Disapproval of incomplete or unsatisfactory submittals shall not be grounds for

contract extensions. Other submittals such as as-builts, test reports, etc., shall be provided as

indicated.

4. MANUFACTURER’S DATA: When the specifications contain an “X” under the

“Manufacturer’s Data Required” field of the submittals paragraph checklist, then the

submission of manufacturer’s data is required. If an “X” is in the “Certificate of Compliance”

field, then it becomes the Contractor’s option to submit manufacturer’s data or a Certificate of

Compliance as detailed below.

5. EXCEPTIONS: If any material proposed for use on this contract deviates from the

specifications, the Contractor shall submit those proposed deviations for approval along with

detailed justification. All exceptions and deviations shall be described in detail with each

product submittal. Cost will not be considered a justification for taking exceptions unless a

credit is offered to the Government.

6. SUBSTITUTIONS: Products provided by manufacturers other than those specified as the

“design basis” shall be considered substitutions.

a. All features of items submitted as substitutions are implied to be in full compliance

with Specifications and Drawings if not specifically noted as "Exceptions."

b. Where a design basis is referenced in Specifications and Drawings, substitutions must

meet or exceed the salient features of the design basis as determined by the Technical

Representative of the Contracting Officer. Exceptions to design basis characteristics

must be clearly noted as "Exceptions." Note: The Federal Acquisition Regulations

place the burden of proving the substitute as equal or better on the contractor.

c. Changes required to accommodate approved substitution shall be made at no

additional cost to the Government. For example, an approved motor substitution may

require upsized electrical cable and conduit.

7. Certificate of Compliance: The Contractor may, at his option, submit a “Certificate of

Compliance” (COC) in lieu of providing manufacturer’s catalog cuts/data. Only one

COC will be required per specification section. Submit three copies of each COC

package. The COC must be signed by the contractor and either the supplier or the

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 4 of 9

manufacturer. The COC letter is attached at the end of this specification section. The

letter must be completed in full.

C. OTHER SUBMITTALS: Other submittals such as samples, test results, spare parts, etc.,

shall be provided as required by each specification section. Provide 4 copies of each unless

directed otherwise. Upon request contractor shall provide any other submittals as required by the

COR.

D. CONSTRUCTION REPORTS

1. PROJECT TIME SCHEDULE

a. Submit a schedule for the entire contract at the Kickoff (Preperformance or

Preconstruction) Meeting, or before that meeting if so directed elsewhere in these

specifications.

(1). The schedule for the entire contract may be submitted in Microsoft

Project format if the contractor so chooses. The Government will also accept

similar sequence patterns shown in Word or Excel if they are properly developed

and displayed.

(2). If there are several projects in one contract, submit a separate

schedule for each project at the same time.

b. Include timelines for design (as applicable), mobilization, start site work,

separate timelines for each discipline and subcontractor, prefinal and final inspection

times, punchlist completion, and demobilization.

c. The contracted total allotted time and the Government's estimate for each

part of the schedule are included in the attachment to this specification.

(1). The attached schedule includes days after award for holding the Pre-

performance or Preconstruction Meeting and for one resubmittal of documents

provided by the Contractor at the meeting.

(2). No (design or) construction work may begin until the Contracting

Officer has approved the schedule.

(3). Resubmit if and as directed by the Contracting Officer. (Also, see

section 01030 if this is a design-build project.)

(4). If the approval process takes longer than the amount of days allotted,

that will not result in a time extension for the entire contract.

2. PROJECT PAY SCHEDULE

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 5 of 9

a. Also submit at the Kickoff (Pre-performance or Pre-construction) Meeting

time schedule(s) on AF Form 3064 that show(s) the percentage completion timeline.

This establishes the pay schedule.

(1). Ensure the Form 3064 matches up with the Project Time Schedule

described above, even if that requires two or more pages of the Form 3064.

(2). Also ensure the price percentages match up with the approved price

proposal at each step on the timeline.

(3). For design-build projects, submit two separate 3064’s for design and

construction. Follow the Schedule described above for dates, and use the price

proposal to get your percentages. Invoices during construction shall show 100%

design that was paid, and the current percent complete on the construction part.

Show that the sum of design and construction subtotals adds up to the grand total

for each design-build project.

3. MEETING RECORDS:

a. Whenever the contractor meets with Government representatives to discuss

outstanding issues or details, the contractor shall prepare a written meeting record of

major decisions made and of action items, noting person responsible and date due for

each item. These will stand as accepted by the Government unless contradicted by

Government personnel who attended the meeting.

b. No decisions made constitute a contract change - the Contracting Officer

handles these in separate contract modification packages.

c. Meeting records are due by e-mail or fax to all offices represented at the

meeting by no later than two workdays after the meeting.

d. The Contracting Officer considers any resolved issues, decisions, or

identified action items to the benefit of the Contractor without these written records to

have never happened, since they were not documented and accepted by the

Government.

e. For additional record purposes, either the Contractor or the Government

may elect to audiotape the meeting.

4. PROGRESS REPORTS:

a. Prepare and submit a monthly progress report (AF Form 3065) for each

project and the entire contract on a monthly basis.

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 6 of 9

b. Obtain coordination signature on the monthly progress reports from the

Technical Representative of the Contracting Officer (CENME Inspector) before

submitting to the Contracting Officer.

E. LIST OF VALUES: Include for approval with the first monthly progress report a breakout of

net costs for each item of work for the project. These are costs that include materials, labor,

equipment, overhead and profit, etc. to be prorated against each item. These numbers are for

use by the base to improve future estimates.

F. LOG BOOKS:

1. Keep daily logs of the activities of the prime contractor and subcontractor

employees. The logs shall include the following:

a. Date

b. Number of people on the job site and skills for each

c. List of construction equipment on the job site

d. Types of work accomplished and how much

e. Materials delivered to the job site

f. Problems and their impacts that arose with the site, the Inspector, facility

users, subcontractors, and the weather.

2. Provide a copy of this daily log (or the original) to the Technical Representative

of the Contracting Officer (CENME Inspector) weekly.

1.04 RETURN AND DISAPPROVAL OF SUBMITTALS: This is a routine project. The Contracting

Officer will return submittals made with AF Form 3000 to the Contractor within 14 days after receipt,

using the AF Form 3000 to show approval or disapproval. Resubmit revisions of disapproved submittals

within 14 days after receipt of disapproval, again using AF Form 3000. Disapproval shall not be cause

for time extension.

1.05 SUPERINTENDENT:

A. When requested, provide name and qualifications for review. Designate a competent person

who shall have full authority to act for the Contractor and who shall be the primary contact

with the Government until project acceptance. The superintendent is a non-working site

supervisor/manager who shall be on site at all times when any Contractor personnel are on

site. The “site” is defined as the location where construction work is being done. The

Government through the Contracting Officer or Technical Representative of the Contracting

Officer (CENME Inspector) reserves the right to shut down all Contractor site activities if the

superintendent is not on site at such times. Site work shall not resume until the superintendent

has returned to the site. Several violations of this requirement are cause for termination for

default.

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 7 of 9

B. If the FAR clause requiring the formal Superintendent is not included in the contract, then the

Contractor shall have a designated work leader or foreman on site during all occasions when there are

two or more personnel on site. There shall always be “someone in charge” who has authority to act for

the Contractor at all such times, even if the person is just the most senior of the laborers on site.

1.06 TURN-IN OF IDENTIFIED EQUIPMENT, SPARE PARTS, TOOLS, AND OTHER

MATERIALS: Items in the Submittals section of each Specification Section (or elsewhere) that are

indicated for turn-in to the Government shall be delivered as directed, or at least before prefinal

inspection. Obtain receipts from Government employees receiving the materials and deliver them to the

Contracting Officer before prefinal inspection.

1.07 AS-BUILT DRAWINGS: Submit CADD as-built project drawings for approval, as detailed in

Section 01310. The Government will not make Final Payment to the Contractor until these are fully

accepted and approved.

1.08 PROVIDE EQUIPMENT LIST to Contracting Officer.

A. Indicate the make, model number, and warranty expiration date of equipment installed by

Contractor. The Technical Representative will inform the Contractor which equipment should be on list.

After the Government approves the list, complete the GSA Forms 274 obtained from Technical

Representative, and then place these labels on the equipment in the list before prefinal inspection.

B. If any of the equipment needs repair during the warranty period, prior to the expiration date,

the Contractor Officer will notify the contractor of the problem. Also, the Contracting Officer’s Technical

Representative will be notified to accompany the Contractor to the equipment. The contractor shall

provide a service ticket to the Contracting Officer and Technical Representative to indicate the corrective

action taken to remediate the problem with the equipment.

1.09 FINAL INSPECTION ONLY: If the Contracting Officer elects to have only a final inspection, turn

in prefinal inspection submittals before the final inspection.

1.10 CLOSEOUT REPORT

A. Record: Keep a record of all new equipment, facility square footage, utility runs, and items

that may be considered “real property” which are purchased and installed under the contract,

separated by project for multiple project contracts. Upon request, the Technical Representative

of the Contracting Officer (CEG Inspector) may be willing to provide any engineering records

available to assist in this effort.

B. New Items: Include the following information in this record:

1. Equipment type and description

2. Sizes and parameters (i.e. tonnage, KW, dimensions, etc.)

3. Quantities

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 8 of 9

4. Model and Serial numbers

C. Demolished Items: Also include similar information for equipment removed, relocated to

another facility, or disposed of at Government request. Do not include like-for-like

replacements.

D. Submit for approval before Final Inspection.

<<<<< END OF SECTION >>>>>

Certificate Follows.

UHHZ160050 SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS – 01300

Revision date 10 May 2013

SUBMITTALS AND CONTRACTOR-FURNISHED ITEMS

01300 - 9 of 9

MATERIALS CERTIFICATE OF COMPLIANCE

Project(s) UHHZ ___________, (Title)___________________________________________

Contract Number: ___________________

Specification Section (or Drawing) Number: __________________

Prime Contractor: __________

Sub Contractor: __________

Material Supplier: __________

Contractor Certification: I hereby certify that I and/or personnel under my direct supervision and/or

control have reviewed all proposed materials for the above contract. I further certify that the submittal

has been reviewed for completeness and accuracy and that all materials submitted will comply with the

drawings and specifications in every respect unless specifically noted as an “exception taken” on the

attached submittal checklist.

Signature: _______________________

Title: _______________________

Company:_______________________

Date: _______________________

Attachment:

Submittal Checklist for Spec or Drawing Listed Above

UHHZ160050 CADD AS-BUILT DRAWINGS - 01310

Revision date 18 February 2014

CADD AS-BUILT DRAWINGS

01310 - 1 of 5

PART 1 - GENERAL

1.01 GENERAL:

1. Basic: Submit as-built project drawings for approval at 50% construction completion stage

(hard copy), 75% construction completion stage (hard copy), and final (hard copy and electronic) as

noted below.

2. As noted in Section 01300, the Government will not make 50% construction completion

payment, 75% construction completion payment, and Pre-Final Payment to the Contractor until these

are fully accepted and approved.

1.02 SUBMITTALS: Provide the following submittals as required by the contract or as directed by the

Contracting Officer.

Inspector

Para # Description Date Required Check Mark

3.02.2. As-Built Redlines 50% completion ___

3.02.2. As-Built Redlines 75% completion ___

3.02.5.a As-Builts Redlines, Soft Copies 100% completion,

Prior to Pre-Final ___

3.02.5.7 As-Built Resubmittals As Directed ___

3.07 GIS for Facs. and Utils. By Pre-Final ___

PART 2 - PRODUCTS - OMITTED

PART 3 - EXECUTION

3.01 Contractor Receiving CADD Files:

1. CADD Files will be provided after contract award and at Contractor request to the

Contracting Officer Representative (COR), normally after the mid-point of construction to ensure any

contract modifications are shown on the final design drawings.

2. The Government will provide an electronic copy of the final design drawings and associated

files to the Contractor at that point. The electronic copies will consist of the CADD files on CD

standard format. The CADD files will be in the AutoCAD 2013 version.

3.02 Submittals:

1. Acceptance and Quality Review by Government: The Government places a high value on the

accuracy and detail provided in these as-builts. The contract shall not be considered complete until the

as-built information is approved and accepted in its entirety.

2. 50% and 75% completion Submittal (Hardcopy Only): Submit for approval at 50% and 75%

completion (with AF Form 3000) a full set of hardcopy contract drawings with “redline” changes

indicated on the drawings. The as-built hard copy shall show all red lines in red color.

a. Mark all drawings as “50% AS-BUILT” or “75% AS-BUILT” as applicable in the

revisions block of the title block area.

UHHZ160050 CADD AS-BUILT DRAWINGS - 01310

Revision date 18 February 2014

CADD AS-BUILT DRAWINGS

01310 - 2 of 5

b. If no changes to the drawings are required, submit the hardcopy drawings with "no

changes, xx% submittal" printed in large red letters on the title sheet (replace "XX" with the

percentage of the submittal).

c. Do not submit drawings with stray markings or sketches made in the field which are

not red and are not intended to convey as-built information. Do not create new drawings to

convey as-built conditions. Submit all redline information on an otherwise clean sheet of "hard

copy" contractor drawings. Reproduction of a clean set is the responsibility of the contractor.

3. The Inspector will evaluate the submittal for correctness and completeness and either approve

or disapprove them via notation on the AF Form 3000. If the submittal is disapproved, it will be

returned to the contractor, along with directions for corrections. Incorporate these corrections into the

drawings and resubmit with AF Form 3000 for approval.

4. After receipt of the Inspector’s approval and prior to updating the drawings electronically,

contact the Inspector and make contact with the As-built Coordinator for the originating design office to

discuss technical issues associated with preparing the final as-built drawings.

5. Final Inspection Set

a. Submit (with AF Form 3000) prior to Pre-Final Inspection a 11” x 17” redline as-built

drawings for approval, along with a full set of electronic drawing files (sheet files and model

files) provided by the Government per para. 3.01.2 above, modified electronically to reflect the

reflect the redline changes made on the hardcopy drawings. Accomplish all changes to the

electronic drawing files according to industry standard CADD drawing practices acceptable to

the Government. . The as-built hard copy shall show all red lines in red color.

b. Maintain the file names and naming pattern of the files as provided by the

Government.

c. Label the drawings as “Final As-built” in the revision block area of the electronic

drawings.

d. Retain the existing georeferenced model file and sheet file structure originally used to

produce the drawings to create the final drawings. Maintain the links of the reference (model)

files. For example, if the floor plan was a model file, any changes to the floor plan shall be

accomplished on the model file. If utility lines were a part of the sheet file, the changes shall be

made to the sheet file.

e. Also submit PDF format files of all drawings readable with Adobe Acrobat Reader.

Format files are to be printed at a 1:1 scale on the original size sheet (no enlargement or

reduction will be allowed for accurate plotting to the original size sheet).

6. The Inspector and As-built Coordinator will reevaluate for correctness and completeness and

then provide either approval or further directions for corrections to the Contractor.

7. Resubmit (with AF Form 3000) complete submittals as directed until the Government

provides full approval.

UHHZ160050 CADD AS-BUILT DRAWINGS - 01310

Revision date 18 February 2014

CADD AS-BUILT DRAWINGS

01310 - 3 of 5

3.03 Format:

1. Provide electronic copies of the design drawings and as-built drawings in AutoCAD 2013

version.

2. Drawing elements shall be retained in original format. Raster elements may remain raster,

and vector elements shall remain vector.

3. Make all changes in the colors and levels that match those in the original drawings that were

provided by the Government.

4. Notes shall be legible and changes shall be shown clearly indicating differences, however

minor, between actual construction and project drawings. Include corrections to underground utilities

and unforeseen site conditions discovered during performance of contract.

5. Update the indexes of the electronic files to reflect any changes.

3.04 Utility Data: Provide the following exterior utility information as “smart lines” when already on

the original drawing files. If smart lines were not used, then provide a separate file in Microsoft Word

or Excel format with the following data, as a minimum, for each segment of utility lines:

Size

Material

Depth

Date Installed (Normally to coincide with warranty date)

3.05 Accuracy of Dimensions for Site Drawings: Locate all significant exterior features and utility

lines within a one (1) foot accuracy for purposes of as-built submission, even if not changed during

construction.

1. The locating may be accomplished by traditional survey methods or by global positioning

system (GPS) satellite equipment supplemented by traditional methods where required.

2. Locations may be from existing buildings or from base monument system. Any existing

structures used as a survey reference must be checked for conformity to NAD 83 surveying coordinates.

3. Recognize that the base maps which are often the basis for the contract site plans have been

prepared from aerial photographs and as such show the roofline instead of the building structure line.

3.06 Qualified Firms for CADD and GPS Support: The Contractor may use any commercial firm or in-

house resources to accomplish the requirements. In some cases we used an Architect-Engineer (A-E)

firm to design the project, and in those cases they are noted on the Drawings and may be used if desired.

If requested, the Inspector will also provide names of other firms the Government believes should be

capable of providing the services required, based upon base personnel experience with them.

3.07 GIS Submittals for Facilities and Utilities: This project also requires data and CADD drawing info

for updating the Robins AFB GIS/Geobase data system.

UHHZ160050 CADD AS-BUILT DRAWINGS - 01310

Revision date 18 February 2014

CADD AS-BUILT DRAWINGS

01310 - 4 of 5

1. GIS Software: The Robins AFB GIS utilizes the ESRI Suite of GIS products. Deliverables to

RAFB must be compatible with ArcGIS 10.0 or newer.

2. IGDS File Format - IGDS Graphic File Format: All graphic files are to be supplied in

Autocad 2013.dwg file format. The symbology of graphic features must comply to Tri-Service Spatial

Data Specifications (TSDDS) Version 2.40.

3. Spatial Data Specification (*)

a. Coordinate System/Projection:

State Plane, Georgia West

Mapping units resolution of 1,000 UOR’s per foot

Storage Minimum Point X,Y = 0,0

b. Geodetic Vertical Datum

System: State Plane Coordinate System

Geodetic Datum: North American Datum 1983 (NAD83)

Ellipsoid: “GRS80”

c. Note that a contractor should contact 78 CEG/CENME (Joshua Winters) POC for a

copy of the 78 CEG/CENME GIS project design file that contains all the required NAD83

projection specifications.

4. Object ID Values for Attribute Tables: Contractor needs to contact the 78 CEG/CENME GIS

Coordinator to ensure that Object ID values for attribute tables do not already exist in the 78

CEG/CENME GIS.

5. Delivery Media

a. The delivery media will be on CD-ROM. The volume name on the delivery media

should match the data set name documented in the Delivery Media Metadata. The abstract

should point to the Delivery Media Metadata file.

b. The delivery media must be labeled with the following:

Volume name

Date - Record for the creation of the Data Set Contract Number and Work Order

Number

Project Name

Name of Contractor preparing the data set

c. NOTE: The TSSDS standard may be obtained by calling Bobby Carpenter at

(601)634-4572 or sending e-mail at [email protected]. The Tri-Service Commission

operates an internet web page at http://mr2wes.army.mil. For further information on 78

CEG/CENME’s implementation of the TSSDS, please contact the 78 CEG/CENME GIS

Coordinator, Joshua Winters.

UHHZ160050 CADD AS-BUILT DRAWINGS - 01310

Revision date 18 February 2014

CADD AS-BUILT DRAWINGS

01310 - 5 of 5

3.08 GIS Submittals for Environmental Systems: Omitted.

<<<<< END OF SECTION >>>>>

UHHZ160050 TEMPORARY SERVICES - CONTRACTOR - 01501

TEMPORARY SERVICES - CONTRACTOR

01501 - 1 OF 5

PART 1 - GENERAL

1.01 GENERAL: Electricity required for contractor convenience will be provided at no charge. Other

utilities will be provided as available, also at no charge. Telephone hookups are contractor responsibility.

A. These requirements are general in nature and are not intended to override safety requirements.

B. Provide all equipment required for temporary utilities (such as transformers, poles,

disconnects, etc.) hookup to base system and after final inspection remove equipment before final

acceptance.

1.02 OMITTED:

1.03 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s

data in lieu of the required certificate of compliance if he desires. The Government requires

manufacturer data if an “X” appears under the “Mfg. Data Required” column.

B. Material Submittals: Omitted.

C. Other Submittals: Provide the following submittals as required by the contract or as directed

by the Contracting Officer.

Inspector

Para# Description Date Required

Checklist

1.04 A Temp HVAC Shop Drwgs 14 days prior ___

1.04 B.1 Temp Elect Shop Drwgs 14 days prior ___

1.04 B.2 Notification of Need before start of work ___

1.04 B.3 Notification of Installation 15 days prior ___

1.04 B.4 Notification of Removal 15 days prior ___

1.04 REQUIRED INFORMAITON:

A. Heating and Ventilating: The contractor shall submit shop drawings for approval indicating

the methods and equipment to be used to maintain the space temperature.

B. Electrical:

1. Shop Drawing of Temporary Service Entrance: The routing, point of connection, size

of pipe(s), and method of support for the temporary service mast shall be submitted for

approval before installation.

2. Notification of Need: Contractor shall submit typed letter to indicate the need for

Government furnished electrical hook-up to his service before work begins.

UHHZ160050 TEMPORARY SERVICES - CONTRACTOR - 01501

TEMPORARY SERVICES - CONTRACTOR

01501 - 2 OF 5

3. Notification of Installation: Contractor shall notify the Contracting Officer fifteen (15)

days before electrical hook-up of Service. The pole shall be set before notification.

4. Notification of Removal: Contractor shall notify the Contracting Officer fifteen (15)

days before electrical disconnection of Service. The Service shall be removed before final

inspection.

PART 2 - PRODUCTS - Omitted

PART 3 - EXECUTION

3.01 DOMESTIC WATER:

A. General: Where required for the convenience of the contractor or as required to maintain

continued occupancy of the work area, the contractor shall provide temporary water service of

adequate capacity. At all points of tie-in to existing lines, the contractor shall provide a cut-off

valve to isolate temporary lines from existing.

B. Insulation: Where temporary water service lines are exposed to the weather, they shall be

insulated to prevent freezing from 1 November through 31 March.

C. Disinfection: Where temporary lines will be used for drinking water, they shall be flushed and

disinfected before being placed into service.

D. Removal: All temporary water lines shall be removed before final inspection. The shut-off

valve at the point of tie-in to the existing line shall remain unless indicated otherwise. Provide a

six (6) inch section of pipe on the downstream side of valve and cap.

E. Temporary Restrooms: Where construction work renders existing restrooms unusable and

alternate facilities are not within a reasonable distance as determined by the Contracting Officer,

the Contractor shall provide a minimum of one portable toilet for each 15 people of each sex. As

a minimum, one toilet shall be provided for each sex. Temporary facilities shall be maintained by

the Contractor and located where directed by the Contracting Officer.

3.02 HEATING AND VENTILATING:

A. General: Where temperature control is necessary for the contractor's comfort, the contractor

may provide temporary heating and/or air conditioning

B. Utilities: All utilities available on the site such as chilled water, steam, and electricity may be

used by the contractor in conjunction with temporary heating and/or air conditioning equipment.

C. Removal of Temporary Equipment: Before final acceptance, the contractor shall remove all

equipment used to provide temporary heating and/or air conditioning.

3.03 ELECTRICAL SERVICE:

UHHZ160050 TEMPORARY SERVICES - CONTRACTOR - 01501

TEMPORARY SERVICES - CONTRACTOR

01501 - 3 OF 5

A. Pole: Contractor shall set a pole with rigid steel mast feeding a panelboard with a NEMA 3R

or 4X enclosure. The pole and mast shall be set in accordance with Article 230 of National

Electrical Code(NEC).

B. Locks: The Service panelboard provided by the contractor shall be locked at all times when

work is not being accomplished at job site. In all cases when the service is locked, the main

breaker shall be turned off.

C. Shut-off: The existing panelboard which is used to feed the temporary circuits may require

installation of necessary breakers at no additional cost to the Government. The contractor shall

turn off each breaker feeding a temporary circuit connected when he is not at the work site.

1. Label: A piece of red tape shall be placed on each of the contractor's circuits when

they are turned off. A notice shall be mounted within one (1) foot of panelboard stating

correct operating procedure (turn breakers off when not in use) and warnings

(Government personnel should not turn on breaker no.'s with red tape on them.)

D. Clearance: All temporary branch circuits not in conduit shall be mounted at least 10' AFF.

E. Remote disconnects: In each room with some type of divider between the temporary service

and location of outlets, provide a separate disconnect. This disconnect shall be visible and

mounted approximately 4' AFF. Disconnect shall be of the safety switch type. Disconnects shall

be lockable in the off position.

1. Shut-off: The remote disconnect shall be turned to "off" position when circuits are not

in use.

2. Label: The disconnect shall be painted in stripes 1-1/2" wide running diagonally at a

30-degree angle from left lower corner to right upper corner. Stripes shall be alternate

colors of red, yellow, and black.

F. Feeders shall be protected by approved overcurrent devices (fuses or circuit breakers) and

originate from approved distribution centers. Overcurrent protection devices and connection shall

be enclosed in approved cabinets or boxes. Provide a readily accessible, manually operated switch

for each incoming supply circuit.

3.04 WIRING:

A. Rules: Wiring shall conform to NEC Article 305, and the following:

1. Wiring passing through work areas shall be covered or elevated to protect it from

damage which would create a hazard to employees. Worn or frayed electric cables shall

not be used. Wiring shall be fastened at ceiling height or 8-feet, whichever is higher, every

10 ft. No conductor shall be laid on the floor.

B. Branch circuits shall originate in a standard power outlet, disconnect, or panelboard.

Conductors shall be permitted within multiconductor cord and cable assemblies (no open

conductors may be used). All conductors shall be protected by overcurrent devices at their

ampacity per NEC 310-16.

UHHZ160050 TEMPORARY SERVICES - CONTRACTOR - 01501

TEMPORARY SERVICES - CONTRACTOR

01501 - 4 OF 5

C. Extension Cords: The use of a number of short extension cords to reach the power source is

not acceptable. A single extension cord should be used in all cases. Flexible extension cords shall

be of the hard usage (SF, SJO, SJT, and SJTO) or extra-hard usage (S, SO, SJ and STO) types

and listed by Underwriters Laboratories. The size shall not be less than #14 AWG, and length

shall be 50 ft or less. Protect them against accidental damage caused by traffic, sharp corners,

projections, and pinching in doors or elsewhere. They shall not be fastened with staples, hung

from nails, or suspended by wire.

D. Splices do not have to be in a junction box. Splice using wire caps. The wire caps shall be

offset from one another, and cables assembled compressed with a layer of plastic tape applied

continuously with 30% overlap from one end of spliced area to the other.

3.05 OUTLETS:

A. 15- and 20-ampere attachment plugs and connectors shall be constructed so that there are no

current-carrying parts except the prongs, blades, or pins. The cover for wire terminations shall be

mechanically secured or an integral part of the attachment plug or connector. Plugs and

receptacles shall have the proper NEMA configuration (such as 5-15R) for the voltage, phase,

and amperage ratings for which they will be used. Receptacles should be marked to show

operating voltage. Plugs and receptacles shall not be interchangeable between circuits with

different voltage and current ratings. No dual voltage receptacles or attachment plugs shall be

used. All receptacles shall be of an approved grounding type, grounded by connection to a

separate grounding conductor.

B. Attachment plugs for use in work areas shall be so constructed that they will endure rough use

and be equipped with a suitable cord grip to prevent strain on the terminal screws. Attachment

plugs or other connectors supplying equipment at more than 300 volts shall be of the skirted type

or otherwise so designed to confine the arcs.

3.06 LIGHTING:

A. Temporary lights shall be equipped with heavy-duty electric cords with connections and

insulation maintained in safe condition. Temporary lights shall not be suspended by their electric

cords unless cords and lights are so designed. Temporary festoon lighting strings shall be made

with cords having lamp sockets and connections protected by insulating coverings. Handlamps of

the portable type shall be of the molded composition or other type approved for the purpose.

Brass-shell paper-lined lampholders shall not be used. Temporary lighting shall be connected to a

ground fault interrrupter outlet. A ground wire shall be provided for all temporary lighting

circuits unless there are no exposed metal parts of the lighting fixture.

B. Special: Lighting on barricades, fences, or sidewalk coverings shall be encased in metal

raceway.

C. Guards: Temporary lights shall be equipped with guards to prevent accidental contact with

the bulb. Guards are not required when the reflector construction has a deeply recessed bulb.

Handlamps shall be equipped with a handle and a substantial guard over the bulb attached to the

handholder or the handle. Do not use exposed empty light sockets and broken bulbs.

UHHZ160050 TEMPORARY SERVICES - CONTRACTOR - 01501

TEMPORARY SERVICES - CONTRACTOR

01501 - 5 OF 5

D. Lighting Levels: Temporary lighting systems which are installed to provide illumination

during construction work shall furnish sufficient illumination for safe working conditions. Special

attention should be given to illumination at stairways, ladders, floor openings, basements and

other hazardous locations.

<<<<<END OF SECTION>>>>>

UHHZ160050 TEMPORARY UTILITIES AND SERVICES

FOR CONTINUED OCCUPANCY – 01502

TEMPORARY UTILITIES AND SERVICES FOR CONTINUED OCCUPANCY

01502 - 1 of 2

PART 1 - GENERAL

1.01 GENERAL

A. The contractor shall provide temporary utilities and services, as required, to maintain

continued occupancy in the building during construction at no additional cost to the Government.

B. Temporary utilities shall include lighting, heating, air conditioning, electrical power, domestic

water, waste, and any other service normally available in the occupied area(s) that will be

disconnected to allow the contractor's work to proceed.

C. Temporary utilities shall not be required where the interruptions to normal service are limited

to times the building will be unoccupied.

D. Utilities: All utilities available at the site such as steam, electricity, and chilled water may be

used by the contractor in conjunction with his temporary services.

PART 2 PRODUCTS - OMITTED

PART 3 EXECUTION

3.01 DOMESTIC WATER:

A. Required when service will be interrupted for over 4 hours in more than (25%) of the building.

3.02 HEATING/AIR CONDITIONING:

A. General: Temporary heating shall be provided from 1 October to 31 March. Temporary air

conditioning shall be provided from 1 April to 30 September.

B. Heating shall be provided to maintain 65 degrees F in administrative areas and 55 degrees F in

shop areas.

C. Air conditioning is required only within administrative areas. Temperature shall not exceed 85

degrees F in any location.

D. Shop Drawings: The contractor shall submit shop drawings for approval indicating the

methods and equipment to be used to maintain the space temperature within limits, points of

connection, size of pipe(s) and method of support.

E. Removal of temporary equipment: At the completion of the contract or when permanent

equipment is made functional the contractor shall remove all temporary equipment. Pipe

connections shall be terminated as close to tie-in as practical with a valve, six (6) inch section of

pipe and cap. Show on as-builts.

3.03 ELECTRICAL SERVICES

UHHZ160050 TEMPORARY UTILITIES AND SERVICES

FOR CONTINUED OCCUPANCY – 01502

TEMPORARY UTILITIES AND SERVICES FOR CONTINUED OCCUPANCY

01502 - 2 of 2

A. Temporary service shall be required prior to the disconnection of existing service to any area

occupied by Government personnel.

<<<<<END OF SECTION>>>>>

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 1 of 12

PART 1 GENERAL

1.1 GREEN PROCUREMENT & POLLUTION PREVENTION

Green Procurement is a mandatory component of the Air Force pollution prevention program. The

AF Installation Pollution Prevention Program Guide includes this goal for Green Procurement: "100%

of all products purchased each year in each of U.S. EPA's 'Guideline Item' categories shall contain

recycled materials meeting U.S. EPA's Guideline Criteria." Currently, reporting of green procurement

purchases is limited to contracts having a total value greater than $100,000 which include the

purchase of any amount of U.S. EPA-designated items. This document contains guidelines for

implementing the RCRA, EO, DOD, and Air Force requirements.

1.2 AUTHORITY AND REFERENCES

A. The Resource Conservation and Recovery Act (RCRA), Section 6002 (42 U.S.C. 6962)

B. The Farm Security and Rural Investment Act (FSRIA), Section 9002 (7 U.S.C. 8102)

C. Executive Order (EO) 13423, Strengthening Federal Environmental, Energy, and

Transportation Management.

D. Title 40, Code of Federal Regulations (CFR), Part 247, Comprehensive Procurement

Guideline for Products containing Recovered Material.

E. Title 7, Code of Federal Regulations (CFR), Part 2902, Guidelines for Designating

Biobased Products for Federal Procurement.

F. Federal Acquisition Regulations (FAR)

1.3 SUBMITTALS

Government approval is required for submittals with a "GA" designation. Submittals having an "FIO"

designation are For Information Only. The following shall be submitted in accordance with Section

01300 SUBMITTAL PROCEDURES:

SD-01 Data

Product Data; GA|CD

The Contractor shall submit manufacturer's material specifications, installation instructions, physical

characteristics, etc, to show that the product meets project and specification requirements.

SD-13 Certificates

Product Certificates; GA|CD

The Contractor shall submit documentation certifying that products meet or exceed the specified

requirements.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 2 of 12

SD-14 Samples

Product Samples; GA|CD

The Contractor shall submit samples of the product intended for use for project record.

1.4 DEFINITIONS

A. GREEN PROCUREMENT: The purchase of environmentally preferable products

manufactured from recycled, reclaimed, and/or biobased materials.

B. ACQUISITION: The acquiring by contract with appropriated funds for supplies or services

(including construction) by and for the use of the Federal Government through purchase or

lease, whether the supplies or services are already in existence or must be created,

developed, demonstrated, and evaluated. Acquisition begins at the point when agency needs

are established and includes the description of requirements to satisfy agency needs,

solicitation and selection of sources, award of contracts, contract financing, contract

performance, contract administration, and those technical and management functions

directly related to the process of fulfilling agency needs by contract.

C. Biobased Products: As defined by FSRIA, "biobased products" are products determined by

the U.S. Secretary of Agriculture to be commercial or industrial goods (other than food or

feed) composed in whole or in significant part of biological products, forestry materials, or

renewable domestic agricultural materials, including plant, animal, or marine materials.

Made from renewable plant and animal sources, biobased products are generally safer for

the environment than their petroleum-based counterparts. They are usually biodegradable or

recyclable.

D. CONTRACTOR: The prime contractor, subcontractors, material suppliers, and equipment

suppliers who provide the products that will be used in the construction of this project.

E. ENVIRONMENTALLY PREFERABLE: Products or services having a lesser or reduced

effect on human health and the environment when compared to competing products or

services, serving the same purpose. This comparison may consider raw materials

acquisition, production, manufacturing, packing, distribution, reuse, operation,

maintenance, or product or service disposal. (Section 201, EO 12873)

F. EPA DESIGNATED ITEM: An item that is or can be made with recovered material; that is

listed by the Environmental Protection Agency (EPA) in a procurement guideline (40CFR,

part 427); and for which EPA has advised purchasing recommendations in a related

Recovered materials Advisory Notice (RMAN). (FAR 23.402)

G. EXECUTIVE AGENCT OR AGENCY: An executive agency as defined in 5 U.S.C. 105.

For the purpose of this order, military departments, as defined in 5 U.S.C. 102 are covered

under the auspices of the Department of Defense.

H. FORM: The Green Procurement Reporting Form found at the end of this section.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 3 of 12

I. POLLUTION PREVENTION: Source reduction as defined in the Pollution Prevention Act of

1990 (42 U.S.C. 13102), and other practices that reduce or eliminate the creation of

pollutants through (a) increased efficiency in the use of raw materials, energy, water, or

other resources; or (b) protection of natural resources by conservation.

J. POSTCONSUMER MATERIAL: A material or finished product that has served its intended

use and has been discarded for disposal or recovery, having completed its life as a

consumer item. "Post-consumer material" is a part of the broader category of "recovered

material".

K. PROCUREMENT: The purchase and providing of products to be used in the construction of

this project.

L. PRODUCT: Materials and equipment that will be used in the construction of this project.

M. RECOVERED MATERIALS: Waste materials and by-products which have been recovered

or diverted from solid waste, but such term does not include those materials and by-

products generated from, and commonly reused within, an original manufacturing process.

(Section 205, EO 12873 and FAR 23.402)

N. RECYCLABILITY: The ability of a product or material to be recovered from or otherwise

diverted from the solid waste stream for the purpose of recycling. (Section 206, EO 12873)

O. RECYCLING: The series of activities, including collection, separation, and processing by

which products or other materials are recovered from the solid waste steam for use in form

of raw materials in the manufacture of new products other than fuel for producing heat or

power by combustion. (Section 207, EO 12873)

P. RECYCLED MATERIAL: A material utilized in place of raw or virgin material in product

manufacturing consisting of materials derived from post-consumer waste, industrial scrap,

material derived from agricultural wastes, and other items, all of which can be used in new

product manufacturer. (EPA Guidelines & OFPP Policy Letter 92-4)

Q. RECYCLED PRODUCT: A recycled product is one made completely or partially from

waste materials or by-products recovered or diverted from the solid waste stream.

R. SOLID WASTE: Garbage, refuse, sludges and other discarded materials including those

from industrial, commercial, and agricultural operations, and from community activities.

This excludes solids or dissolved materials in domestic sewage or other significant

pollutants in water resources, such as silt, dissolved or suspended solids in industrial waste

water effluents, dissolved materials in irrigation return flow, etc. (EPA Guidelines)

S. SPECIFICATION(S): A clear and accurate description of the technical requirements for

materials, products, or services including the minimum requirement for materials' quality

and construction and any equipment necessary for an acceptable product. In general,

specifications are in the form of written descriptions, drawings, prints, commercial

designations, industry standards, and other descriptive references.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 4 of 12

T. UNREASONABLE PRICE: If the cost of the recycled content product exceeds the cost of a

non-recycled item, the Air Force considers the cost to be unreasonable. (Air Force Green

Procurement Plan)

U. VERIFICATION: Procedures used by procuring agencies to confirm both vendor estimates

and certifications of the percentages of recovered materials contained in the products

supplied to them or to be used in the performance of a contract. (EPA Guidelines)

V. WASTE PREVENTION: Any change in the design, manufacturing, purchase, or use of

materials or products (including packaging) to reduce their amount or toxicity before they

are discarded. Waste prevention also refers to the reuse of products or materials.

W. WASTE REDUCTION: Preventing or decreasing the amount of waste being generated

through waste prevention, recycling, or purchasing recycled and environmentally preferable

products.

1.5 REGULATORY BACKGROUND

Section 6002 of RCRA requires federal agencies to give preference in the acquisition process to

products and practices that conserve and protect natural resources and the environment. EO 12873

requires federal agencies to expand waste prevention and recycling programs, implement green

procurement programs for the United States Environmental Protection Agency (EPA) -designated

items, and procure other environmentally preferable products and services. The stated purpose of the

Green Procurement Program is to stimulate the market for recovered materials. As a result of EO

12873, the EPA issued the Comprehensive Procurement Guidelines (CPGs) that have established the

mandatory procurement by federal agencies of 36 items produced with recovered materials. The EPA

has also issued Recovered Material Advisor Notices (RMANs) to accompany the CPGs and provide

detailed information on the designated items. Section 9002 of The Farm Security and Rural

Investment Act (FSRIA) was signed into law in 2002. A goal of that legislation is to increase the

government’s purchase and use of biobased products. In addition to lessening our national

dependence on foreign oil, use of biobased materials promotes economic development by creating

new jobs in rural communities and providing new markets for farm commodities. Please direct all

questions regarding the plan to the Contracting Officer's Representative for forwarding to the 78

CEG/CEV Environmental Division, 478-327-4173.

1.6 APPLICABILITY

These procedures apply to Contractors employed in the construction of projects at Robins AFB,

GA. For additional information on GPP, visit the following website, http://afenvsymp.ecatts.com/start.

You will have to register first using the following registration password: symposium. Please direct all

questions regarding the plan to the Contracting Officer's Representative for forwarding to the 78

CEG/CEIEC Environmental division, 478-327-4173.

1.7 DOD AND AIR FORCE REQUIREMENTS

Green Procurement programs are required of all Air Force (USAF) installations. Department of

Defense (DOD) Instruction 4715.4, Pollution Prevention, calls for program establishment in

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 5 of 12

accordance with RCRA, EO 13423, and EO 12873. Green Procurement is also addressed in Air Force

Instruction (AFI) 32-7080, Pollution Prevention Program, and the 24 July 1995 Air Force Pollution

Prevention Strategy. The Strategy sets program goals, and the AFI provides program guidance.

1.8 EXEMPTIONS

1.8.1 EPA Recommendations

The U.S. EPA recommends minimum content levels for those items listed in the attached GREEN

PROCUREMENT REPORTING FORM. These levels are mandatory for Air Force procurements

unless one of the following exemptions applies. RCRA provides the following exemptions from the

requirement to purchase EPA-designated items:

1. The product is not available from a sufficient number of sources to maintain a satisfactory

level of competition (i.e., available from two or more sources).

2. The product is not available within a reasonable period of time.

3. The product does not meet the performance standards in applicable specifications or fails to

meet reasonable performance standards of the procuring agency.

4. The product is not available at a reasonable price. For Air Force purposes, "unreasonable

price" is defined as follows: If the price of the recycled-content product exceeds the cost of

a non-recycled item, then the price is considered unreasonable.

1.8.2 Contractor Responsibility

The Contractor is responsible for completion of the Form with respect to the work and products being

provided. The Prime Contractor is responsible for insuring that all sub-contractors comply with this

order. Each contractor shall provide written documentation to support his/her decision not to acquire

items meeting the minimum content levels. This documentation shall be forwarded to the Contracting

Officer for review and approval. In the event the documentation fails to support the contractor's

findings, the Contracting Officer's Representative shall return the documentation to the Contractor

citing the reason(s) for disapproval. The Contractor shall resubmit and address the deficiencies.

1.9 U.S. EPA DESIGNATED ITEMS

The 54 U.S. EPA-designated items are listed below. Not all of these materials may be required in

the construction of this project. Please refer to the drawings and specifications. The attached

GREEN PROCUREMENT REPORTING FORM shall be used to demonstrate compliance with the

stated procurement requirements.

PAPER PRODUCTS

1. All paper and paper products, excluding building and construction paper grades.

VEHICULAR PRODUCTS

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 6 of 12

2. Lubricating oils containing re-refined oil, including engine lubricating oils, hydraulic fluids,

diesel fuel additives, and gear oils, but excluding marine and aviation oils.

3. Tires, excluding airplane tires.

4. Reclaimed engine coolants, excluding coolants used in non-vehicular applications

CONSTRUCTION PRODUCTS

5. Building insulation products.

6. Structural fiberboard products for applications other than building insulation.

7. Laminated paperboard products for applications other than building insulation.

8. Cement and concrete, including products such as pipe and block, containing fly ash.

9. Cement and concrete, including concrete products such as pipe and block, containing ground-

granulated blast furnace (GGBF) slag.

10. Carpet made of polyester fiber for use in low- and medium-wear applications.

11. Floor tiles containing recovered rubber or plastic.

12. Patio blocks containing recovered rubber or plastic.

25. Shower and restroom dividers/partitions containing recovered steel or plastic.

26. Reprocessed and consolidated latex paint for specific uses.

37. Carpet cushion.

38. Flowable fill.

39. Railroad grade crossing surfaces.

TRANSPORTATION PRODUCTS

13. Traffic barricades used in controlling or restricting vehicular traffic.

14. Traffic cones used in controlling or restricting vehicular traffic.

27. Parking stops.

28. Channelizers used as temporary traffic control devices.

29. Delineators used as temporary traffic control devices.

30. Flexible delineators used as temporary traffic control devices.

PARK AND RECREATION PRODUCTS

15. Playground surfaces containing recovered rubber or plastic.

16. Running tracks containing recovered rubber or plastic.

31. Plastic fencing.

40. Park benches and picnic tables.

41. Playground equipment.

LANDSCAPING PRODUCTS

17. Hydraulic mulch products containing recovered paper or recovered wood.

18. Compost made from yard trimmings, leaves, and/or grass clippings.

32. Garden and soaker hoses containing recovered rubber or plastic.

33. Lawn and garden edging containing recovered rubber or plastic.

42. Food waste compost.

43. Plastic lumber landscaping timbers and posts.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 7 of 12

NON-PAPER OFFICE PRODUCTS

19. Office recycling containers.

20. Office waste receptacles.

16. Plastic desktop accessories.

22. Toner cartridges.

23. Binders.

24. Plastic trash bags.

34. Printer ribbons (re-inked ribbons or re-inking equipment/service for ribbons).

35. Plastic envelopes.

44. Solid plastic binders.

45. Plastic clipboards.

46. Plastic file folders.

47. Plastic clip portfolios.

48. Plastic presentation folders.

MISCELLANEOUS PRODUCTS

36. Pallets

49. Sorbents.

50. Industrial drums.

51. Awards and plaques.

52. Mats.

53. Signage, including sign supports and posts.

54. Manual-grade strapping.

55. Water Tank Coatings.

1.10 INTENT

The intent of this section is to increase the awareness of all Contractors as to the availability of

products manufactured from, or that contain recycled and/or biobased materials, thereby increasing

the use of these products in the construction of this project.

The various sections of the specifications contain references to products to be used in the construction

of this project. The listed product may or may not be manufactured from or contain recycled or bio-

based materials. Therefore, all contractors, subcontractors, equipment suppliers, and material

suppliers are responsible for compliance with this specification; particularly the paragraph entitled

DOD AND AIR FORCE REQUIREMENTS and those items/products listed on the GREEN

PROCUREMENT REPORTING Form. Recycled and/or biobased products shall be used wherever

possible subject to the exemptions as per the paragraph entitled EXEMPTIONS. Substitution of

recycled/biobased materials or recycled/biobased products for specified products are subject to the

provisions of the paragraph entitled SUBMITTALS.

1.11 RECYCLED OR RECOVERED PRODUCTS

Those construction materials identified on the Form at the end of this section.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 8 of 12

1.12 QUALITY ASSURANCE

Companies specializing in the manufacture of products that comply with the requirements of this

section shall have a minimum of three (3) years documented experience.

PART 2 PRODUCTS

2.1 PARTIAL LIST OF PRODUCT SOURCES & INFORMATION

The following is a partial list of companies that manufacturer products using recycled/biobased

materials. This partial list is presented to establish a standard of quality and does not infer that other

manufacturers do not qualify. All products intended for use on this project, whether listed below or

not, shall be submitted to the Contracting Officer's Representative.

GENERAL DATA

1. GreenSpec Binder, Environmental Building News, www.ebuild.com

2. Certified Forest Products Council, www.cerifiedwood.org/

3. Wiley Series in Sustainable Design, www.wiley.com/

4. The Carpet and Rug Institute, www.carpet-rug.com/

5. Information, McGraw-Hill, [email protected]

6. Florida Directory of Recycled Product Vendors,

www.2.dep.state.fl.us/waste/programs/rbac/downloads/rbac_dir.pd

7. Oikos Green Building Source, News, searchable products data base, library, www.oikos.com

8. Green Design Network, News, publications, databases, www.greendesign.net

9. Green Works Recycled Content7 Product Guide, detailed vendors directory,

www.metrokc.gov/greenworks/recycontent.htm

DIVISION 3 - CONCRETE

1. GranCem, granulated blast-furnace slag, www.grancem.com/

2. Syndesis, cement-based, pre-cast product workable with wood tools, www.syndesisinc.com/

DIVISION 4 - MASONRY

1. Heble Building Systems, autoclaved aerated concrete blocks, www.heble.com/

2. Ytong Florida Ltd., autoclaved aerated concrete blocks, www.ytong-usa.com/

DIVISION 6 - CARPENTRY

1. Avonite, solid surfacing, www.avonite.com/

2. Chemical Specialties, wood treatment, www.treatedwood.com/

3. Homasote Company, structural fiberboard, www.homasote.com/

4. Isoboard, fiberboard composed of straw fibers and non-toxic resins, www.isoboard.com/

5. TrusJoist Mac Millan, engineered wood products, www.homasote.com/

DIVISION 7 - THERMAL & MOSITURE PROTECTION

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 9 of 12

1. Duro-Last Roofing, recycled PVC walkway pads, 1-800-248-0280

2. Johns Manville, Insulation products, www.jm.com/

3. Majestic Skylines, rubber-based slate-look roofing for steep roofs,

www.majesticskylines.com/

4. Owens-Corning, insulation products, www.owenscorning.com/

DIVISION 8 - DOORS & WINDOWS

1. Marvin Window & Door, windows, some meeting "Energy Star Label", www.marvin.com/

2. Pella, energy efficient windows, www/pella.com/

DIVISION 9 - FINISHES

1. Armstrong World Industries, Inc.-Flooring Systems, www.armstrong-floors.com/

2. Armstrong World Industries, Inc.-Ceiling Systems, www.ceilings.com/

3. Benjamin Moore & Co., VOC free acrylic interior latex paint, www.benjaminmoore.com/

4. CanFibre Group Ltd., all-green medium-density fiberboard, www.canfibre.com

5. Chemrex Inc., low-e interior paint, www.chemrex.com/

6. Collins & Aikman Floor coverings, carpet with 100% post-consumer backing,

www.powerbond.com/

7. DesignTex, Inc., polyester panel fabric made from 100% PET fiber, www.dtex.com/

8. Dodge-Regupol, Inc., 100% recycled rubber-flooring, www.regupol.com/

9. Eco-sensitive modular tile, vinyl tile with 100% recycled carpet-backing,

www.powerbond.com/

10. Environmental Stone Products, stone manufactured from 100% recycled glass,

www.environmentalstone.com/

11. Glidden: residential interior latex paints 100% free of VOC, www.icipaintstores.com/

12. Homasote Inc., sound barrier, www.homasote.com/

13. Isoboard Enterprises, Inc. panel made from wheat straw and non-toxic resins, 1-503-242-

7345

14. Marley-Flexco Co., flooring made form 95% recycled truck and bus tires,

www.marleyflexco.com/

15. The Mat Factory, Inc., interlocking roll-up tiles made from 100% postconsumer tire rubber

and PVC plastic from electric cable covers, 1-949-645-3122

16. Permafirm Pad Co., carpet pads made from almost 100% recycled content, 1-800-344-6977

17. Sherwin Williams, VOC compliant paints and enamels, www.sherwin.com/

18. SierraPine Limited, formaldehyde-free particleboard and medium density fiberboard

containing recycled/recovered wood fiber, www.sierrapine.com/

19. Summittville Tiles, impervious porcelain tiles using feldspar tailings,

www.summitville.com/

20. Tectum, natural-fiber acoustical ceiling and wall panels, www.tectum.com/

21. Tiles with natural fibers, tiles made of a bio-alloy material and natural fibers,

www.maderatile.com

22. USG Interiors, Inc., synthetic gypsum board, www.usg.com/

23. Decorative Architectural Tiles, floor, counter & wall tile made from 100 % postconsumer

glass, 1-808-8857812

24. Forbo, linoleum flooring utilizing renewable resources, www.forbo.com/

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 10 of 12

DIVISION 10 - SPECIALTIES

1. The Access Store, modular ramping system made from 100% recycled rubber,

www.accessstoe.com/

2. BP Solar, photovoltaic modules and systems, www.bp.com/bpsolar/index

3. Mecho Shade Systems, interior shadecloths, www.mechoshade.com/

4. R Control, structural insulated panel (SIP), www.mechoshade.com/

DIVISION 12 - FURNISHINGS

1. Guilford of Maine, fabric from 100% recycled materials, www.terratex.com/

2. Phenix Biocomposites, tabletops made from soy based products free of petrochemicals, 1-

800-324-8187

3. Safe Solutions, LLC, furniture manufactured from waste wood, 1-970-247-3333

DIVISION 14 - CONVEYING SYSTEMS

1. Montgomery KONE, AC girlies elevators, www.montgomery-kone.com/

DIVISION 16 - ELECTRICAL

1. Advance Transformer Company, linear reactor ballast, www.advancetransformer.com/

2. Artemide Inc., energy efficient cold-cathode lighting, www.artemide.com/

3. Edison Price Lighting, track mounted metal-halide PAR 30 &38 lamps, 1-212-521-6995

4. Leviton Manufacturing Corporation, Inc., occupancy sensors, www.leviton.com/

5. Phillips Lighting, energy efficient compact fluorescent lamps, www.phillips.com/lighting

6. Osram Sylvania, mercury-free lamps and energy efficient fluorescent lamps,

www.osramsylvania.com/

7. Sensor Switch, lighting control occupancy sensors, www.sensorswitch.com/

8. Venture Lighting, pulse-start high performance lamp-ballast system,

www.venturelighting.com/

PART 3 EXECUTION

3.1 INSTALLATION

All products shall be installed per manufacturer's instructions.

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 11 of 12

GREEN PROCUREMENT REPORTING FORM

(PER EXECUTIVE ORDER 13423)

PROJECT NUMBER:___________________________________

BLDG NUMBER:_______________________________________

PROJECT MANAGER___________________________________

PROJECT INSPECTOR:_________________________________

CONTRACTOR:________________________________________

This form is to be completed by the Contractor and submitted through AFSC/PZIOC to

78 CEG/CENME. It is the responsibility of the 78 CEG/Engineering Division construction inspectors to

keep this documentation in the contract file IAW E.O. 13423 Strengthening Federal Environmental,

Energy, and Transportation Management.

RECYCLED/RECOVERED/

BIO-BASED PRODUCT % REQUIRED

(MINIMUM)

%

AVAIL

(ACTUAL)

QUANTITY

USED/UI

EXEMPT

ED

1,2,3,4

-ROCK WOOL INSUL 75%

-FIBERGLASS INSUL 20-25%

-LOOSE FILL/SPRAY ON 75%

-PERLITE COMP BOARD 23%

-PLASTIC RIGID FORAM 9%

-GLASS FIBER REINF 6%

-PHENOLIC RIGID FOAM 5%

-STRUCTURAL FIBER BD 80-100%

-LAMINATED PAPER BD 100%

-CEMENT/CONCRETE

(FLYASH)

SEE SPEC

-CARPET (PET) 25-100%

-PATIO BLOCKS/RUBBER 90-100%

-PATIO BLOCKS/PLASTIC 90-100%

-FLOOR TILES/RUBBER 90-100%

-FLOOR TILES/PLASTIC 90-100%

-TRAFFIC CONES 50-100%

-TRAFFIC BARRICADES 80-100%

-PLAYGROUND SURFACES 90-100%

-RUNNING TRACKS 90-100%

-COMPOST 100%

-WOOD-BASED HYDRAULIC

MULCH

100%

-PAPER-BASED HYDRAULIC

MULCH

100%

REPROCESSED WHITE, OFF-

WHITE & PASTEL COLORS

20%

UHHZ160050 GREEN PROCUREMENT - 01540

GREEN PROCUREMENT

01540 - Page 12 of 12

REPROCESSED GREY,

BROWN, EARTHTONES &

OTHER DARK COLORS

50-99%

CONSOLIDATED LATEX

PAINT

100%

PLASTIC/RUBBER PARKING

STOPS

100%

CONCRETE CONTAINING

COAL FLY ASH PARKING

STOPS

20-40%

CONCRETE CONTAINING

GGBF

PARKING STOPS

25-70%

PLASTIC SHOWER &

RESTROOM

DIVIDERS/PARTITIONS

20-100%

MOBILE EQUIPMENT

HYDRAULIC FLUIDS

44-100%

ROOF COATINGS 20-100%

DIESEL FUEL ADDITIVES 90-100%

PENETRATING LUBRICANTS 68-100%

CERTIFICATION

I hereby certify the Statement of Work/Specifications for the requisition/procurement of all materials

listed on this form comply with EPA standards for recycled/recovered materials content.

_______________ _______________

Contractor Inspector

The following exemptions may apply to the non-procurement of recycled/recovered content materials:

1) The product does not meet appropriate performance standards

2) The product is not available within a reasonable time frame

3) The product is not available competitively (from two or more sources)

4) The product is only available at an unreasonable price (compared with a comparable non-

recycled content product.)

B-13

Recovered Materials Determination Form (RMDF) User’s Guide

1. PURPOSE OF FORM. The “Recovered Materials Determination Form” (RMDF) is used to

clearly identify items listed in the Comprehensive Procurement Guidelines (CPG) that are

included in a procurement action, require the consideration of energy efficiency and

environmentally preferable purchasing (EPP) for the procurement action, and document the use

of applicable exemptions taken for the CPG items identified.

2. OPR. All organizations procuring items through avenues other than the Government-wide

Purchase Card (GPC).

3. OCR. Contracting, CE /Operations, CE /Construction, CE /SABER, and CE /Materiel

Acquisition.

4. APPLICABILITY. The RMDF applies to all procurement actions (other than GPC

purchases) that include items that are listed in the CPG, Biobased, Energy Star®, or FEMP Low

Standby Power programs.

5. INTENT FOR USE.

a. GPC holders will not complete this form and will use the “GPC Purchasing

Considerations and Guidelines Log” instead. The RMDF is included in the Robins AFB

Environmental Protection specification. The Environmental Protection specification will be

included in all service and construction contracts as well as all work orders greater than $2,500

that will be completed in-house.

b. Contractors and CE Operations shop personnel (for in-house job and work orders

regardless of project cost) will be responsible for completing an RMDF if any of the mandatory

EPP items are required. For CPG items where exemptions are identified during project/contract

performance, an amended RMDF must be completed documenting the exemption. The OCR

organizations listed above will be responsible for verifying the completed RMDFs.

c. If the procurement action does not include any CPG, Biobased, Energy Star®, or FEMP

Low Standby Power items, complete the Green Procurement Statement instead.

6. FILING PROCEDURE. If applicable, the RMDF and any amended RMDFs will be

provided to contracting with the Purchase Request (PR) package and will be maintained in the

contract file.

B-15

RAFB GPP PLAN ATTACHMENT 3 Recovered Materials Determination Form

Instructions

This form is to be completed by the procurement originator when EPA or USDA -designated

items included in the Green Procurement Program are being procured from outside vendors.

Current information regarding whether products count as “U.S. EPA-designated” or what the

required recycled content for the item is, refer to the product descriptions on U.S. EPA’s Website

at www.epa.gov/cpg/products.htm. Information pertaining to USDA products can be found at

www.biopreferred.gov. The completed form becomes part of the contracting office contract

file.

PR No./ Project No._______________________________________________

The EPA or USDA designated items being procured are:

Construction Products

___Building insulation products ___Carpet and carpet cushion

Cement and concrete containing: ___coal fly ash ___ground granulated blast

furnace slag ___cenospheres ___silica flume

___Consolidated and reprocessed latex paint

___Floor tiles ___Flowable fill (backfill) ___Laminated paperboard ___Modular threshold ramps ___Nonpressure pipe ___Patio blocks ___Railroad grade crossing surfaces ___Roofing Materials ___Shower and restroom

dividers/partitions ___Structural fiberboard

Landscaping Products

___Compost made from yard trimmings or food waste

___Garden and soaker hoses ___Hydraulic mulch ___Lawn and garden edging ___Plastic lumber landscaping

timbers and posts

Non-Paper Office Products

___Binders, clipboards, file folders, clip portfolios, and presentation folders

___Office furniture ___Office recycling containers ___Office waste receptacles ___Plastic desktop accessories ___Plastic envelopes ___Plastic trash bags ___Printer ribbons ___Toner cartridges

Paper and Paper Products

___Commercial/industrial sanitary tissue products ___Miscellaneous papers (tray liners) ___Newsprint ___Paperboard and packaging products ___Printing and writing papers

Park and Recreation Products

___Park benches and picnic tables ___Plastic fencing ___Playground equipment ___Playground surfaces ___Running tracks

Transportation Products

___Channelizers ___Delineators and flexible delineators ___Parking stops ___Traffic barricades ___Traffic cones

Vehicular Products

___Engine Coolants ___Rebuilt vehicular parts ___Re-refined lubricating oils

___Retread tires

Miscellaneous Products

___Awards and plaques ___Bike racks ___Blasting grit ___Industrial drums ___Manual-grade strapping ___Mats ___Pallets ___Signage ___Sorbents

Bio-Based Products

___Mobile Equipment Hydraulic Fluids ___Urethane Roof Coatings ___Water Tank Coatings ___Diesel Fuel Additives ___Penetrating Lubricants ___Bedding, Linens, and Towels

B-16

RAFB GPP PLAN ATTACHMENT 3 –Cont.

Recovered Materials Procurement Determination

___ EPA recycled-content requirements have been met for this procurement action.

**** OR ****

___ The following EPA designated guideline item is included in the specifications for project

number , however, compliance with EPA standards is not attainable.

Item:

I have determined that the EPA guidelines were considered and determined inapplicable, based

on the following:

_____ Item is not available within a reasonable period of time.

Need date: _____________________ Date available: ______________________

Item fails to meet a performance standard in the specifications.

Describe the standard and why it is needed: _____

_____________________________________________________________________________

_____________________________________________________________________________

Describe how the guideline item fails to meet the standard: ________________________

______________________________________________________________________________

______________________________________________________________________________

_____ Item is not available from 2 or more sources.

Market research was performed by calling ____(insert number) vendors, but only

________________________________ (enter name) was able to supply the item.

_____ Item was only available at an unreasonable price (i.e., recycled item is more expensive).

Price of recycled item: ______________ Price of non-recycled item: _______________

This determination is made in accordance with FAR 23.405(c).

Comments_____________________________________________________________________

______________________________________________________________________________

______________________________________________________________________________

________________________________________ ____________

Technical OPR - Signature and Office Symbol Date

Title/Role ______________________________

________________________________________ ____________

Concurrence - Contracting Officer Date

UHHZ160050 ENVIRONMENTAL REQUIREMENTS - 01560

Environmental Requirements for Robins Air Force Base

01560 - Environmental Requirements Rev Date: September 2015

Page 2 of 32

Table of Contents Table of Contents ................................................................................................................................................ 2

PART 1 GENERAL .............................................................................................................................................. 5

1.1 GENERAL SCOPE ................................................................................................................................... 5

1.2 CONTRACTOR RESPONSIBILITY ............................................................................................................. 6

1.2.1 Environmental Management Systems (EMS) Awareness Training.................................................. 6

1.3 NO NOTICE INSPECTIONS ..................................................................................................................... 6

1.4 SUBMITTALS ......................................................................................................................................... 7

1.4.1 General Submittals ....................................................................................................................... 7

1.4.2 Material Submittals ...................................................................................................................... 7

1.4.3 Other Submittals........................................................................................................................... 7

PART 2 EXECUTION .......................................................................................................................................... 8

2.1 DISPOSAL OF WASTE/EXCESS MATERIAL ............................................................................................... 8

2.1.1 General ......................................................................................................................................... 8

2.1.2 Solid Waste Handling .................................................................................................................... 8

2.1.3 Solid Waste Disposal ..................................................................................................................... 9

2.1.4 Reporting of Disposal and Recycling ............................................................................................ 10

2.1.5 Submittals, Notifications, and Approvals ..................................................................................... 11

2.2 SPECIAL WASTES OR HAZARDOUS MATERIALS .................................................................................... 12

2.2.1 General ....................................................................................................................................... 12

2.2.2 Hazardous Waste ........................................................................................................................ 12

2.2.3 Asbestos Containing Materials .................................................................................................... 13

2.2.4 Lead Paint ................................................................................................................................... 14

2.2.5 Polychlorinated Biphenyls (PCB) ................................................................................................. 15

2.2.6 Ozone Depleting Substances (ODS) and Controlled Substances Restriction ................................. 16

2.2.7 Hazardous Materials (HazMat) .................................................................................................... 17

2.2.8 Submittals, Notifications, and Approvals ..................................................................................... 18

2.3 AIR QUALITY ....................................................................................................................................... 20

2.3.1 General ....................................................................................................................................... 20

2.3.2 Open Burning ............................................................................................................................. 20

2.3.3 ODS ............................................................................................................................................ 20

2.3.4 Generators ................................................................................................................................. 20

01560 - Environmental Requirements Rev Date: September 2015

Page 3 of 32

2.3.5 Submittals, Notifications, and Approvals ..................................................................................... 21

2.4 PESTICIDES (INSECTICIDES, FUNGICIDES, HERBICIDES, ETC.) ................................................................ 21

2.4.1 General ....................................................................................................................................... 21

2.4.2 Licenses ...................................................................................................................................... 21

2.4.3 Handling ..................................................................................................................................... 21

2.4.4 Submittals, Notifications, and Approvals ..................................................................................... 21

2.5 STORAGE TANKS ................................................................................................................................. 22

2.5.1 General ....................................................................................................................................... 22

2.6 THREATENED AND ENDANGERED SPECIES OF PLANTS AND WILDLIFE ................................................. 22

2.6.1 General ....................................................................................................................................... 22

2.7 WETLANDS ......................................................................................................................................... 22

2.7.1 General ....................................................................................................................................... 22

2.8 GREEN PROCUREMENT PROGRAM (GPP) ............................................................................................ 22

2.8.1 General: ...................................................................................................................................... 22

2.9 PRESERVING HISTORICAL AND ARCHAEOLOGICAL RESOURCES ........................................................... 23

2.9.1 General ....................................................................................................................................... 23

2.9.2 Archaeological Finds ................................................................................................................... 23

2.10 PROTECTION OF WATER AND LAND RESOURCES ................................................................................ 23

2.10.1 General ....................................................................................................................................... 23

2.10.2 Stormwater Management during Construction ........................................................................... 23

2.10.3 Post Construction Stormwater Management .............................................................................. 24

2.10.4 Prohibition of Illegal Discharges .................................................................................................. 24

2.10.5 Prohibition of Illicit Connections ................................................................................................. 25

2.10.6 Spills ........................................................................................................................................... 25

2.10.7 Tree Protection and New Landscaping ........................................................................................ 25

2.10.8 Restoration of Landscape Damage .............................................................................................. 26

2.10.9 Submittals, Notifications, and Approvals ..................................................................................... 26

2.11 BACKFLOW PREVENTION DEVICES (BPDs) ........................................................................................... 28

2.11.1 General ....................................................................................................................................... 28

2.11.2 Coordination ............................................................................................................................... 28

2.11.3 Installation.................................................................................................................................. 28

2.11.4 Inspection and Testing ................................................................................................................ 28

01560 - Environmental Requirements Rev Date: September 2015

Page 4 of 32

2.11.5 Submittals, Notifications, and Approvals ..................................................................................... 28

Forms

SPECIAL WASTE ACCEPTANCE APPLICATION (SWAA) .......................................................................................... 29

WASTE SHIPMENT TRACKING DOCUMENT ......................................................................................................... 30

WASTE MANAGEMENT REPORT (MONTHLY)...................................................................................................... 31

01560 - Environmental Requirements Rev Date: September 2015

Page 5 of 32

PART 1 GENERAL

1.1 GENERAL SCOPE

This Section provides the requirements necessary to ensure that all projects are in environmental compliance.

Environmental Management, 78 CEG/CEIE, is the organization responsible for management of base

environmental concerns. Contact program managers in 78 CEG/CEIE at (478) 327-8104 or (478) 926-9645 or

electronically [email protected].

1.1.1 The following programs have the potential to be impacted by contracts: solid and hazardous

wastes, toxics, water quality, air quality, natural resources, storage tanks, cultural resources,

pollution prevention, hazardous materials, and fuels.

1.1.2 All contracts performed on Robins Air Force Base (AFB) are bound by all Federal, State of Georgia,

Houston County, Department of Defense (DoD), and Air Force laws, regulations, and policies and

subject to no-notice inspections by these regulators and officials. Robins AFB operates under the

requirements of 10 regulatory permits and over 20 management plans. The following table

identifies applicable Air Force Instructions (AFI) related to this document that also requires

compliance.

Air Force Instructions

AFI 32-1053 Integrated Pest Management Program

AFI 32-1067 Water and Fuel System

AFI 32-7040 Air Quality Compliance and Resource Management

AFI 32-7042 Waste Management

AFI 32-7044 Storage Tank Environmental Compliance

AFI 32-7064 Integrated Natural Resources Management

AFI 32-7065 Cultural Resources Management

AFI 32-7086 Hazardous Materials Management

1.1.3 A digging permit obtained from the 78th Civil Engineer Group is required for all projects where

excavation or other forms of ground penetration may be required to complete the task. This permit

process is the method used by the Base to coordinate the required work with key base activities and

to identify potentially hazardous work conditions; in an attempt to protect personnel, prevent

accidental damage to Base assets, and ensure the proper restoration of the excavated site upon

completion.

01560 - Environmental Requirements Rev Date: September 2015

Page 6 of 32

1.2 CONTRACTOR RESPONSIBILITY

Comply with all applicable Federal, State of Georgia, any laws and regulations from other states where disposal

might occur, and local laws and regulations concerning environmental compliance and pollution prevention.

Ensure all products produced or generated under contract shall meet all stated performance objectives and shall

not violate in any manner the Environmental Requirements of any applicable local, state, or federal entity

including the DoD.

1.2.1 Environmental Management Systems (EMS) Awareness Training: All contractor personnel working

on Robins AFB who perform activities on the installation are required to complete Air Force-

provided initial EMS Awareness Training. It is the responsibility of the Prime Contractor to ensure

that all sub-contractors, vendors, and employees complete this training prior to beginning work on

Robins AFB. Notification of training completion shall be sent to both the Robins AFB Contracting

Officer (CO) to be maintained in the contract file and Environmental Management, 78 CEG/CEIE,

([email protected]) for tracking purposes. Failure to provide documentation of EMS

Training may result in termination of the contract.

EMS training is provided by Environmental Management at (478) 327-8104 or (478) 926-9645.

Contractors have two options to satisfy the mandatory EMS Awareness Training requirement.

Contractors that do not have a Common Access Card must exercise Option 2.

a. Option 1 (Preferred Option): The Air Force version of EMS Awareness Training is available

through the Advanced Distributed Learning Service (ADLS) website:

https://golearn.adls.af.mil/kc/rso/login/ADLS_login.asp. EMS Awareness Training is located

under the Miscellaneous tab. This option is only available to contractors who have a CAC

and takes approximately 10 minutes to complete.

b. Option 2: Contractor requests a copy of the Robins EMS Awareness Training Power Point

Presentation from Environmental Management. The request should be sent to the

Environment Management Workflow Box at the following email address,

[email protected]. Once the presentation is received, the contractor is

responsible for ensuring that all his/her employees view the training.

1.3 NO NOTICE INSPECTIONS

78 CEG/CEIE will conduct no-notice inspections to ensure compliance with all Environmental

Requirements. Written documentation of any findings from such an inspection will be forwarded to the

CO by the inspector. The CO will follow-up with the Contractor on all findings of non-compliance

reported by the inspector. A finding of non-compliance with any of the Environmental Requirements

may result in the issuance of a work stoppage by the CO until documentation of compliance is submitted

and accepted by both 78 CEG/CEIE and the CO. No-notice inspections are frequently conducted by

federal and state regulators.

01560 - Environmental Requirements Rev Date: September 2015

Page 7 of 32

1.4 SUBMITTALS

1.4.1 General Submittals: Provide the following submittals in accordance with instructions found in this

document. The contractor may submit manufacturer’s data in lieu of the required certificate of

compliance if desired. The Government requires manufacturer’s data if an “X” appears under the

“Mfg. Data Required” column.

1.4.2 Material Submittals: Not required under this section.

1.4.3 Other Submittals: Provide the following submittals as required by the contract or as directed by the

CO.

*** IMPORTANT >> Designer, edit list below to project requirements***

Inspector Para #

Description Submittal Timeframe Check Mark

1.2 Notify 78 CEG/CEIE of Digging Beginning of project, before digging

2.1.3 c Landfill License Prior to dumping ☐

2.1.3 c. i. Special Waste Acceptance Application 5 days prior to dumping ☐

2.1.3 c. ii. Waste Shipment Tracking Monthly by the 5th ☐

2.1.3 d. Commencement Notice Prior to dumping ☐

2.1.3 d. 2.1.4 2.1.5 a. vi.

Waste Management Report Landfill Receipts

Monthly by the 5th and prior to final payment

2.1.5 a. 2.1.5 a. ii.

Solid Waste Disposal Plan 10 days prior pre-con. conf.

2.2.3.b. GA EPD Asbestos Abatement or Demolition Project Notification Form

15 days prior to starting work

2.2.2 2.2.8 a. ii.

Hazardous Waste/Hazardous Material List Prior to starting work ☐

2.1.3 c. i. 2.2.1 2.2.3 a. i.

Asbestos Removal Info As required ☐

2.1.3 c. i. 2.2.4 a. i.

Lead Compliance/Training/Sampling Prior to starting work At the end of the project

2.2.8 b. i. Refrigerant Technician Certification Prior to starting work ☐

2.2.8 b. ii. Refrigerant Appliance List Within 7 days ☐

2.2.8. b. ii. Sub-bullets

Refrigerant Maintenance Repair Log Within 7 days ☐

2.2.8 b. iii. Refrigerant Equipment Certification Within 7 days ☐

2.2.8 b. iii. Refrigerant Purchase Documentation Within 7 days ☐

2.3.4 Generators Prior to order ☐

01560 - Environmental Requirements Rev Date: September 2015

Page 8 of 32

Inspector Para #

Description Submittal Timeframe Check Mark

2.3.5 Air Permit Data 6 months prior to construction start date

2.4.2 Pesticide List At end of project ☐

2.4.2 Pest Control License Prior to pest control ☐

2.5.1 Underground Storage Tank Removal 45 days after Notice to Proceed

2.10.7 d. Landscaping Plan Prior to beginning work ☐

2.7.9 a. i. Erosion, Sediment, and Pollution Control Plan

60 percent design package

2.7.9 a. Notice of Intent – NPDES Permit 14 days prior to site work ☐

2.7.9 a. ii. Permits/Fees Copies – NPDES Permit 14 days prior to site work ☐

2.7.9 a. iii. Notice of Termination – NPDES Permit After final stabilization at site

2.7.3 2.7.9 b.

Post Construction Stormwater Management Plan and Calculations

60 percent design package

2.7.3 2.7.9 c.

Post Construction Operation and Maintenance Plan

60 percent design package

2.8.5 a. Backflow Device Location Prior to installation ☐

2.8.5 b. Backflow Prevention Device Test Report After BPD installation ☐

2.8.5 c. Use of fire hydrant/penetrate water mains

Prior to start of work ☐

PART 2 EXECUTION

2.1 DISPOSAL OF WASTE/EXCESS MATERIAL

2.1.1 General: The Contractor shall take a proactive, responsible role in the management of non-hazardous solid

waste and require all subcontractors, vendors, and suppliers to participate in the effort. Non-hazardous

Solid Waste, as defined in Code of Federal Regulations (CFR) 261.2, dispositioned for disposal shall be

removed from the base in accordance with all Federal, State of Georgia, and local codes and requirements.

Every effort shall be made to segregate individual waste streams and divert waste from any landfill by

reusing or recycling materials. Direct all non-hazardous solid waste inquiries to 78 CEG/CEIEC Solid Waste

Program Manager, (478) 327-9283 or (478) 926-9645.

2.1.2 Solid Waste Handling: All persons engaged in solid waste handling, including solid waste collection and

transportation, or operations of solid waste handling facilities or disposal sites, shall have a solid waste

handling permit or permit by rule letter. The provisions of Georgia Environmental Protection Division (GA

EPD) regulations concerning proper handling of solid waste and applicable prohibitions shall govern. All

01560 - Environmental Requirements Rev Date: September 2015

Page 9 of 32

materials and equipment not turned in to the Government is considered property of the contractor and

must be properly removed by the end of the project.

2.1.3 Solid Waste Disposal: Use one or more of the following methods to divert/dispose of non-hazardous solid

waste. All materials to be disposed of in other than a sanitary landfill must be kept segregated at the project

site from those materials which are allowed only in a sanitary landfill.

a. Reuse (diversion): First consideration of waste shall be given to salvage for reuse to be used in the

original form. Sale or donation of waste suitable for reuse shall be considered. Salvaged materials

shall not be used in this project unless approved by the CO. Materials defined as “recovered

materials” are excluded from regulation as solid wastes.

b. Recycling (diversion): Waste material not suitable for reuse but having value as a recyclable

material shall be recycled whenever practical and economically feasible. Materials destined for

recycling must meet the definition of non-hazardous wastes under federal/state solid waste

regulations. Recyclable metal materials shall remain the property of the government and be

recycled through the Robins AFB Qualified Recycling Program (QRP). To coordinate

removal/collection of scrap wire and metal, please contact QRP Manager Casey Lucas at (478) 327-

9283 or Alternate QRP Manager Darryl Mercer at (478) 256-7032.

c. Sanitary Landfill (disposal): All solid waste may be disposed of in a sanitary landfill properly licensed

by the State of Georgia. Provide proof that any Georgia municipal solid waste disposal facility

receiving Robins AFB waste is operated by someone who has obtained the certification required by

the Georgia Solid Waste Management Act, O.C.G.A. 12-8-24.1. If a landfill other than Houston

County Landfill is used, provide a copy of the landfill license.

i. If the presence of lead based paint, asbestos, or other hazardous materials are suspected,

an analysis of the suspected material shall be performed by a certified lab approved by the

State. If the Toxic Characteristic Leaching Procedure (TCLP) results for lead are greater than

5 mg/L, the waste shall be disposed of as hazardous waste in a Subtitle C permitted facility--

not a Subtitle D permitted facility such as the Houston County Landfill. If the lab analysis for

asbestos is positive, the permission for landfill disposal is required and waste must be

dispositioned through the Special Waste Acceptance Application (SWAA) process. Houston

County Landfill currently does not require a SWAA if there is no presence of lead based

paint, asbestos, or other non-hazardous Special Waste or hazardous materials suspected.

ii. SWAA Process: The results of the tests/lab analysis as well as the completed top and middle

portion of the SWAA must be submitted to 78 CEG/CEIEC Solid Waste Program Manager for

approval and signature. The 78 CEG/CEIEC Solid Waste Program Manager will be the signing

authority as the generator on the SWAA form. 78 CEG/CEIEC will email the completed form

to the County’s landfill consultant for disposal acceptance/approval and for issuance of

Special Waste Profile Number. The Special Waste Profile Number must be used on the

Waste Shipment Tracking Document. The Waste Shipment Tracking Document and SWAA

are both attached at the end of the document. Allow a minimum of three working days for

78 CEG/CEIEC to process the SWAA form and to obtain the profile number. The 78

CEG/CEIEC Solid Waste Program Manager will issue the completed SWAA back to the

contractor via email. The Contractor must certify that no hazardous waste was introduced

01560 - Environmental Requirements Rev Date: September 2015

Page 10 of 32

into the waste while in his custody. The contractor must provide a Waste Shipment

Tracking Document with each disposal load when required by Houston County. These forms

must also be included in contract documents.

d. Inert Waste Landfill (disposal): Materials not likely to cause production of leachate of

environmental concern may be disposed of in an inert waste landfill. Only earth and earth-like

products, concrete, cured asphalt concrete, rock, bricks, yard trimmings, and land clearing debris

such as stumps, limbs, and leaves are acceptable for disposal in an inert waste landfill. A copy of the

written notice of commencement of operation by the landfill as given to the GA EPD and a copy of

the landfill license or permit by rule letter issued by the GA EPD must be provided to the Base

Engineering Division (78 CEG/CEN) Project Manager and maintained in the contract documents.

The weights of inert waste disposed in the landfill must be documented in the monthly waste

management report, provided to the 78 CEG/CEN Project Manager, and then forwarded to the 78

CEG/CEIEC Solid Waste Program Manager.

e. Construction/Demolition Disposal Site (disposal): Materials will be recycled where practical.

Recyclable metal materials (scrap metal, wire, motors, etc) shall remain the property of the

government and will be recycled through the Robins AFB QRP. To coordinate removal/collection of

scrap metal materials, please contact QRP Manager Casey Lucas at (478) 327-9283, Alternate QRP

Manager Darryl Mercer at (478) 256-7032, or 78 CEG/CEIE Front Office at (478) 327-8104 or (478)

926-9645. Other construction and demolition (C&D) waste, including but not limited to wood,

paper, cardboard can be recycled through the base recycling program or through another

appropriate recycling avenue. Materials that can go in an inert waste landfill may be recycled

according the rules of the State of Georgia, disposed of in an inert landfill, or lastly in the landfill. If

the wastes are being disposed of at a landfill other than the Houston County Landfill, provide the

landfill license to the 78 CEG/CEN Project Manager. Refer to Section 2.1.4 regarding proper

reporting of disposal and recycling (weights). For construction and demolition wastes, a minimum

of 60 percent by weight of the total project solid waste shall be diverted from the landfill.

f. Solid Waste Disposal Outside of Georgia: No solid waste can be disposed of outside the state of

Georgia without prior written approval of the CO. The contractor shall provide sufficient

information as determined by the CO to allow verification of compliance with the law.

2.1.4 Reporting of Disposal and Recycling: Robins AFB is required to report the amount (weight) of solid waste

and C&D debris which is dispositioned by reuse, recycle, or disposal. Each month, the Contractor shall

record the amounts of reused, recycled, and disposed materials on the Waste Management Report

(attached at the end of the document). Weights shall be cumulative from the start of each month and shall

reflect the total amount of material disposed or recycled during the month. The report should reflect the

method of disposal for the material generated from the project. Weights of material disposed of in a

sanitary or C&D landfill shall be reported based on the weight tickets. Material disposed of in other types of

landfills, which do not have weight scales, may be estimated. The weight of materials reused and or

recycled may be estimated. Use a good faith effort to obtain the most accurate estimate possible. The

Contractor shall also provide the cost to landfill or divert/recycle the C&D debris on the Waste Management

Report. A copy of the Waste Management Report shall be turned in to the 78 CEG/CEN Project Manager by

the 5th of the following month and prior to final payment. The 78 CEG/CEN Project Manager shall forward

01560 - Environmental Requirements Rev Date: September 2015

Page 11 of 32

the Waste Management Report to the 78 CEG/CEIEC Solid Waste Program Manager. If there are any

questions, the Solid Waste Program Manager contact information is:

Casey Lucas

Email: [email protected]

Phone: (478) 327-9283 or (478) 926-9645

2.1.5 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. Solid Waste Disposal Plan: The Contractor shall provide a Solid Waste Disposal Plan stating how all

materials leaving Robins AFB shall be disposed of and recycled no later than15 days after notice to

proceed and not less than 10 days before the preconstruction meeting prior to starting work. The

Solid Waste Disposal Plan shall include actions that will be taken to reduce solid waste generation,

specific approaches to be used in recycling/reuse of materials, waste management and storage

information, and anticipated net cost savings.

i. The plan shall certify that the Contractor shall manage, dispose, and recycle all materials in

compliance with all Federal, State of Georgia, and local laws. The plan shall address the disposal

of each item in Sections 2.1.1 through 2.2.8 as applicable. The plan shall designate an employee

who shall be responsible for verifying that all materials removed from Robins AFB are disposed

of in accordance with the above referenced laws. Non-hazardous solid waste shall be broken

down into individual types, i.e., asphalt, concrete, wood, brick, etc. to facilitate recycling of

recovered materials.

ii. Provide a copy of the Solid Waste Disposal Plan to the CO and to the 78 CEG/CEN Project

Manager. The 78 CEG/CEN Project Manager will forward to 78 CEG/CEIEC prior to review and

approval 10 days prior to the Pre-construction Conference or 15 calendar days prior to the start

of disposal operations if no pre-construction conference is held.

iii. Identify each landfill and recycler to be used. A copy of all landfill permits shall be provided

unless the Houston County landfill is used.

iv. Provide a copy of a Solid Waste Handling Permit or permit-by-rule letter, issued by GA EPD,

which allows the Contractor to handle solid wastes, including solid waste collection and

transportation. A copy of the EPD permit-by-rule letter is required for the inert waste landfill

being used.

v. Establish and maintain a Daily Waste Disposal and Recycling Log. Each load of materials that

leaves Robins AFB shall be accounted for in the log. The log shall list the load number, bill of

sale number/date or other record for recycling, as well as the name of the contract employee

who verified that the material was disposed of properly, along with details as to how verification

was accomplished.

vi. Keep evidence of proper disposal and recycling of construction debris as well as provide this

evidence to the 78 CEG/CEN Project Manager. Examples of evidence include dump tickets from

01560 - Environmental Requirements Rev Date: September 2015

Page 12 of 32

a licensed sanitary landfill, copies of current landfill permits from the State of Georgia (unless

Houston County landfill is used), manifest, bill of sale, or other record for recycling. The

evidence shall be obtained the workday after the load is carried off and provided by the 5th of

each month on the Waste Management Report.

vii. Prior to final payment, 78 CEG/CEIEC Solid Waste Program Manager must have received all

monthly waste tracking reports. Attach a copy or duplicate of the Waste Shipment Tracking

Document for each load transported for disposal and recycling.

b. Building Demolition: Submit copies of GA EPD demolition notification to CO and the 78 CEG/CEN

Project Manager. The 78 CEG/CEN Project Manager will forward to the 78 CEG/CEIEC Solid Waste

Program Manager 15 days prior to starting work and prior to submittal to the GA EPD for review,

and submit final copies with copy of any payment made to GA EPD.

2.2 SPECIAL WASTES OR HAZARDOUS MATERIALS

2.2.1 General: The Contractor must comply with all applicable federal, state, and local requirements concerning

use of hazardous materials and hazardous waste. If there should be a conflict between environmental

regulation/ordinances/statues and the contract’s specifications, the contractor shall, in writing, contact the

CO for a written determination. Disposal of all non-hazardous Special Wastes, such as asbestos, requires

submittal of a SWAA to obtain a Profile Number for use on the Waste Shipment Tracking Document as

described in 2.1.3.c.

2.2.2 Hazardous Waste: Hazardous Waste is defined as waste meeting the requirements of 40 CFR 261.3. 78

CEG/CEIER Hazardous Waste Program Manager makes all hazardous waste determinations for waste

generated on Robins AFB. The Contractor must provide all data necessary to determine the regulatory

status of waste to 78 CEG/CEIER. Activities requiring large quantities of disposal must be coordinated prior

to beginning work in order to ensure a sufficient number of hazardous waste containers are available. The

Contractor must ensure personnel have completed hazardous waste training prior to generating hazardous

waste. All hazardous and universal wastes generated on Robins AFB must be disposed of through 78

CEG/CEIER at building 359. Direct all inquiries to the 78 CEG/CEIER Hazardous Waste Program Manager.

a. Paints, sealants, solvents, rags, or any other hazardous material(s) destined for disposal must be

managed as a hazardous waste unless they have been determined not to be via Safety Data Sheet

(SDS) or laboratory sampling. 78 CEG/CEIER is the only organization authorized to make a hazardous

waste determination.

b. Waste generated from the project itself (e.g. lead-based paint removed from walls, contaminated

soil, sludge from tank cleaning, etc.) must be turned-in to Building 359 for disposal.

c. High-intensity discharge (HID) and fluorescent lamps and tubes or switches containing mercury must

be recycled as universal waste. Labeled containers must be requested through 78 CEG/CEIER at

building 359 prior to job start.

d. Batteries used in emergency and exit lights that contain lead must be recycled. These batteries

must be turned-in to building 359 with no cost for disposal.

e. Disposal Procedures for Hazardous and Universal Waste:

01560 - Environmental Requirements Rev Date: September 2015

Page 13 of 32

i. Payment for waste disposal will be made through the property/building organizations

Department of Defense Activity Address Code (DODAAC) account. Since all regulated

wastes must be disposed of through DLA-DS, a valid DODAAC is essential to prevent contract

operation delays. This step must be completed prior to requesting waste containers and

labels. Authorization to use the organizations DODAAC also indicates there are sufficient

funds available to pay for waste disposal generated from the project.

ii. Obtain labels and containers prior to job start from building 359 and place the labels on

containers suitable for shipping per Department of Transportation (DOT) guidelines.

Fluorescent lamps/tubes may be placed in the original boxes the tubes came in or in boxes

designed to prevent breakage. Take care not to break any universal waste lamps/tubes. If

any are broken, they must be treated as spilled hazardous waste and turned-in to building

359 immediately.

NOTE: Rolloff boxes to contain waste for large projects must be requested at least 2 weeks in advance.

iii. Accumulate hazardous waste under either the satellite accumulation rules (<55 gallons

total, no time limit, 3 day limit to turn-in full drums) or 90-day rules (no quantity limit, use

up to 90 days in the field, other 40 CFR 262.34(a)(1)(i) requirements apply). Turn-in

containers to building 359 when full or approaching time limit(s).

iv. The contractor is responsible for maintaining regulatory compliance for all regulated waste

under their control. Responsibility for site compliance does not end until the waste is

accepted by 78 CEG/CEIER for disposal.

v. Do not abandon waste at the job site.

2.2.3 Asbestos Containing Materials:

a. Asbestos Work/Removal: The Contractor shall provide 15 working day notification to the CO and 78

CEG/CEIEC Toxics Program Manager and 10 working day notification to GA EPD prior to the start of

any work involving asbestos. Copies of all notifications, GA EPD approval, and landfill disposal

receipts and waste shipment tracking forms must be provided to the CO and 78 CEG/CEIEC Toxics

Program Manager.

i. Provide a written plan to the 78 CEG/CEN Project Manager and the 78 CES/CEIER

Asbestos/Toxic Operations Manager. Provide description of work to be performed and work

procedures to comply with rules and regulations. Provide employee training program

certification that contractor personnel involved in removal and handling of asbestos has

received asbestos training, respiratory protection, and medical surveillance program

information.

b. Building Demolition: Follow guidance above regarding notification procedures. This may also apply

to the modification of a building, and is considered demolition when the removal of a load-bearing

wall occurs. For more information, visit: http://epd.georgia.gov/asbestos-notification-requirements

or coordinate with 78 CEG/CEIEC Solid Waste Program Manager or the 78 CEG/CEN Project

Manager. The GA EPD Asbestos Abatement or Demolition Project Notification Form for asbestos

renovation, encapsulation, or demolition can be at the website noted above.

01560 - Environmental Requirements Rev Date: September 2015

Page 14 of 32

c. Do not use any products containing asbestos.

d. Prior to the start of any demolition, renovation, or digging, determine if asbestos is in the area of

construction. If there is no known asbestos in the project area, proceed as normal. If the contractor

discovers any material suspected to be asbestos, bring it to the CO’s attention immediately. Stop all

work in that area until directed to proceed.

i. Known Asbestos, not written in the contract: If asbestos is in the area of construction,

describe where it is located. There should not be any work done in the area involving

asbestos if it was not written in the contract. If any asbestos is accidentally damaged, notify

78 CES/CEIER Asbestos/Toxic Operations Manager at (478) 327-8518, Bioenvironmental

Engineering, 78 AMDS/SGPB at (478) 327-7555, and 78 CEG/CEIEC Toxics Program Manager

at (478) 327-3976 immediately. After they inspect the damage, the contractor shall repair it

and remove debris in accordance with the following regulations, at no additional cost to the

Government:

29 CFR 1910.1001

40 CFR 61.145

40 CFR 61.150

AFOSH Standard 161-4

Georgia Air Quality Rules, Section 391-3-1-02(9)(b)1

2.2.4 Lead Paint:

General: The contractor shall take precautions to protect contract and government employees from

exposure to lead dust hazards during C&D projects in accordance with 29 CFR 1926.62, Occupational, Safety,

and Health Administration (OSHA) Lead in Construction Standard. All painted surfaces including painted

surfaces covered by other materials such as wall paper may contain varying levels of lead. All lead based

paint abatement work shall only be performed in the areas shown by the required specifications and shall

be in accordance with Unified Facilities Guide Specifications (UFGS).

a. For all projects (Major Abatement projects; Housing or Childcare Facilities; Maintenance, Repair, and

Minor Construction Projects): All painted surfaces, including painted surfaces covered by other

materials such as wall paper, may contain varying levels of lead. The disposal of all debris containing

lead paint shall be handled as a hazardous waste until a determination has been made otherwise

based on test results. For hazardous waste, the contractor shall provide DOT approved drums and

collect the waste in the drums. The drums shall be sealed, properly labeled, and turned in to the

government for disposal.

i. Provide a written plan as required by OSHA Standard 29 CFR 1926.62 to the 78 CEG/CEN

Project Manager and the 78 CEG Toxics Operations Manager. Provide description of work to

be performed and work procedures to comply with rules and regulations. Provide

certification that contractor personnel involved in removal and handling of lead based paint

01560 - Environmental Requirements Rev Date: September 2015

Page 15 of 32

has received training in accordance with OSHA Lead Standards and medical surveillance

program information. At the end of the project, provide results of air sample testing to

demonstrate worker safety.

2.2.5 Polychlorinated Biphenyls (PCB): Do not use equipment or components containing PCB’s. This includes

ballasts and capacitors for fluorescent and HID lighting.

a. Disposal Procedures for Fluorescent lighting ballasts and HID lighting capacitors containing PCB’s:

i. Fluorescent lighting ballasts and HID lighting capacitors must be managed and disposed of

as toxic waste unless the label states they do not contain PCB’s. Ballasts and capacitors with

no markings are assumed to contain PCB. Ballasts and capacitors marked as non-PCB are

handled as standard solid waste.

ii. Gather HID capacitors and fluorescent ballasts into separate containers and place them into

labeled, suitably sized DOT-approved containers per 49 CFR 173.202. (Typical sizes are 1, 5,

10, 30, and 55 gallons) Labels and containers may be obtained from building 359, 78

CEG/CEIER, (478) 926-1176.

iii. If any are broken, they must be treated as spilled hazardous material. Contact 78

CEG/CEIER, (478) 926-1176 for disposal instructions.

iv. Dispose of sealed non-leaking capacitors through DLA-DS, (478) 926-5162. Do not keep any

of the full or partially full containers at the construction site for more than 30 days. Provide

DD Form 1348 obtained from building 359 prior to contacting DLA-DS for disposal.

b. Disposal Procedures for all other PCB containing materials, including but not limited to: plastics

(such as plastic insulation from wire or cable; radio, television and computer casings; vehicle parts;

or furniture laminates); preformed or molded rubber parts and components; applied dried paints,

varnishes, waxes or other similar coatings or sealants; caulking; asbestos:

i. Prior to the start of any demolition, renovation, or digging, determine if PCB containing

materials are in the area of construction. If the contractor discovers any material he/she

suspects to contain PCBs, or if lab results indicate PCB-containing materials, the material

shall be managed as PCB hazardous waste.

ii. Notify 78 CEG/CEIER Hazardous Waste Support at (478) 926-1176 that a project area

contains PCB materials. Building 359 will provide the necessary containers for collection as

well as a DD Form 1348 for completion.

iii. Upon completion of DD Form 1348, the containers will be picked up directly by DLA-DS. The

DLA-DS POC is Darlene Smith, (478) 926-5162. If DLA-DS is not available to pick up PCB

containing materials, notify 78 CEG/CEIER Hazardous Waste Support at (478) 926-1176 for

alternate disposal procedures.

iv. PCB waste will always be transported using a hazardous waste manifest which must be

signed by a 78 CEG/CEIE representative. Payment for waste disposal will be made through a

01560 - Environmental Requirements Rev Date: September 2015

Page 16 of 32

valid DODAAC account. This step must be completed prior to requesting waste containers

and labels. See section 2.2.8.c, page 19 for instructions on obtaining a DODAAC.

2.2.6 Ozone Depleting Substances (ODS) and Controlled Substances Restriction:

a. Unless the requiring activity has obtained prior Senior Acquisition Official (SAO) approval,

contractors may not provide any service or product with any specification, standard, drawing, or

other document that requires the use of a Class I ODS in the test, operation, or maintenance of any

system, subsystem, item, component, or process or provide any specification, standard, drawing, or

other document that establishes a test, operation, or maintenance requirement that can only be

met by use of a Class I ODS.

[Air Force Federal Acquisition Regulation Supplement (AFFARS) Part 5352.223-9000, Elimination of Use of

Class I Ozone Depleting Substances (ODS)]

For the purposes of Air Force policy, the following products are Class I ODS:

i. Halons: 1011, 1202, 1211, 1301, and 2402;

ii. Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114,

CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the

blends R-500, R-501, R-502, and R-502; and

iii. Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide

NOTE: Materials that use one or more of these Class I ODSs as minor constituents do not meet the Air Force

definition of a Class I ODS. [AFFARS Part 5352.223-9000, Elimination of Use of Class I ODS].

b. Class II ODS usage requires prior approval through the Air Force (AF) Form 3952 Authorization

Process. [Air Force Instruction (AFI) 32-7086, Hazardous Materials Management]

i. Do not develop or modify any existing weapon or facility system scheduled to remain in the

AF inventory beyond 1 January 2020 in any manner that requires or adds requirements for

Class II ODS in their operations or maintenance.

ii. For exceptions to this Class II ODS policy, the requiring activity must receive SAO approval,

using the same process as Class I ODS Contract approvals, or, for installation Real Property

air conditioning and refrigeration equipment, the requiring activity must obtain approval

authority from the Base Civil Engineer (BCE). [AFI 32-7086, Hazardous Materials

Management]

iii. For the purposes of Air Force policy, the following products are Class II ODS:

Hydrochlorofluorocarbons (HCFCs): HCFC-21, HCFC-22, HCFC-31, HCFC-121, HCFC-122,

HCFC-123, HCFC-124, HCFC-131, HCFC-132, HCFC-133, HCFC-141b, HCFC-142b, HCFC-151,

HCFC-221, HCFC-222, HCFC-223, HCFC-224, HCFC-225ca, HCFC-225cb, HCFC-226, HCFC-231,

HCFC-232, HCFC-233, HCFC-234, HCFC-235, HCFC-241, HCFC-242, HCFC-243, HCFC-244,

HCFC-251, HCFC-252, HCFC-253, HCFC-261, HCFC-262, HCFC-271 [AFI 32-7086, Hazardous

Materials Management, Table 4.2]

01560 - Environmental Requirements Rev Date: September 2015

Page 17 of 32

c. The Contractor shall label products which contain or are manufactured with ODS in the manner and

to the extent required by 42 United States Code (U.S.C.) 7671j(b), (c), and (d) and 40 CFR Part 82,

Subpart E, as follows:

Warning

Contains (or manufactured with, if applicable) *_______, a substance(s) which harm(s) public health and

environment by destroying ozone in the upper atmosphere.

* The Contractor shall insert the name of the substance(s). [Federal Acquisition Regulation (FAR) Part

52.223-11, ODS]

d. The Contractor shall comply with the applicable requirements of Sections 608 and 609 of the Clean

Air Act (42 U.S.C. 7671g and 7671h) as each or both apply to this contract. [FAR Part 52.223-12,

Refrigeration Equipment and Air Conditioners]

2.2.7 Hazardous Materials (HazMat):

a. HazMat Definition: The term HazMat includes all items (including medical supply items, but

excluding drugs in their finished form and pharmaceuticals in individually-issued items) covered

under Emergency Planning and Community Right-to-Know Act (or other federal, state, or local)

tracking requirement, the OSHA Hazard Communication (HAZCOM) Standard, and all Class I and

Class II ODS. It does not include munitions or hazardous waste.

b. HazMat Exemptions: The OSHA HAZCOM Standard [29 CFR 1910.1200(b)(6)(ix)] excludes “Any

consumer product or hazardous substance, as those terms are defined in the Consumer Product

Safety Act (15 U.S.C. 2051 et seq.) and Federal Hazardous Substances Act (15 U.S.C. 1261 et seq.)

respectively, where the employer can show that it is used in the workplace for the purpose intended

by the chemical manufacturer or importer of the product, and the use results in a duration and

frequency of exposure which is not greater than the range of exposures that could reasonably be

experienced by consumers when used for the purpose intended.” OSHA further states in a 14 April

2005 interpretation letter that office cleaning products utilized with the same frequency and

duration as that of a normal consumer would fall under the HAZCOM Standard exemption for

consumer products in 29 CFR 1910.1200(b)(6)(ix). Based on the OSHA HAZCOM Standard

exemption, consumer products that are used at Robins AFB in such a way that the duration and

frequency of use are the same as that of a consumer are not required to be included in the

employer’s HAZCOM program. If unsure if the item meets the exemption, contact the HazMat Cell

([email protected]).

c. Lead Acid Batteries: OSHA determined that lead acid batteries are hazardous chemicals because of

their potential chemical exposure risks and physical hazards. As a result, lead acid batteries are

classified as HazMat and do not fall under the article exemption because they have the potential to

leak, spill or break during normal conditions of use.

d. Aerosol Products: All aerosol products are classified as HazMat.

01560 - Environmental Requirements Rev Date: September 2015

Page 18 of 32

e. The storage and usage of all HazMat must be tracked in the Air Force Standardized Tracking System.

If the contractor does not have access to a government-furnished computer and cannot access the

Air Force Standardized Tracking System, the contractor must report data on the HazMat stored and

used during the performance of the contract at a minimum of weekly to the HazMat Cell and in the

format specified. The Contractor should coordinate the submittal of HazMat data with the HazMat

Cell prior to the beginning of work.

f. Each HazMat container must have an Air Force-approved bar code tracking label affixed, with the

exception of kits. The tracking label shall be generated from the Air Force Standardized Tracking

System and must be for the same manufacturer, same product and same size item. Substitutions

are not allowed. HazMat that has been broken down into smaller “child” containers from the

original “parent” container must have a packaging label affixed in addition to the bar code tracking

label. If the contractor does not have access to a government-furnished computer and cannot

access the Air Force Standardized Tracking System, the contractor must coordinate with the HazMat

Cell the printing of bar code labels for all HazMat items.

g. All HazMat must be authorized prior to use. The material is authorized by stock number for the

using organization or contractor. Authorizations are good for three years. At the end of the three

year period, the user must re-new the authorization. HazMat items cannot be issued in the Air

Force Standardized Tracking System to an employee without an active, valid authorization. The

contractor must submit an Air Force Form 3952 (or the electronic equivalent through the Air Force

Standardized Tracking System) for the authorization to use the HazMat.

h. Contractors must submit a “Hazardous Material Purchase Request for Contractors” form prior to

transporting any hazardous material onto Robins AFB. Contact the HazMat Cell for the “Hazardous

Material Purchase Request for Contractors” form, [email protected]. This form must be

completed for all hazardous materials purchased by contractors for use on Robins AFB and approval

must be granted prior to transportation onto Robins AFB. The purpose of this form is to ensure

compliance with AFI 32-7086 and OSHA HAZCOM, ensuring that hazardous materials are approved

for use prior to transportation onto Robins AFB and a current SDS is available in the Air Force

Standardized Tracking System. Once approval is given, the contractor is permitted to transport

hazardous materials onto Robins AFB. The contractor must track the hazardous materials in the Air

Force Standardized Tracking System.

i. Contractors must maintain compliance with the Robins AFB Hazardous Material Management Plan

and AFI 32-7086. A copy of the plan can be obtained by contacting the HazMat Cell.

j. Contractors should contact the HazMat Cell ([email protected] ) with specific HazMat

questions.

2.2.8 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. HAZCOM Program: The Contractor must submit a written HAZCOM program to the CO when

hazardous materials or chemicals are to be used or demolished. This HAZCOM plan must include

the following information:

i. List of each work activity/process required to use/demolish hazardous materials/chemicals.

01560 - Environmental Requirements Rev Date: September 2015

Page 19 of 32

ii. List of hazardous materials/chemicals used.

iii. SDS for each hazardous material/chemical used. The SDS must be the most current SDS

available from the manufacturer. SDSs from third party SDS sites are not allowed.

iv. HazMat Listing and Air Force Form 3952 for each HazMat: Provide the CO with SDS and the

list of hazardous materials/chemicals prior to starting work. Each SDS must be accompanied

with a completed Air Force Form 3952, detailing the intended use of the hazardous material.

The same procedure should be followed for additional hazardous material brought on base

during the performance of the contract. The CO will forward the list of hazardous materials,

Air Force Form 3952s and SDSs to the HazMat Cell for review and approval. HazMats are

not permitted for transportation onto Robins AFB or use on Robins AFB until approval is

given by 78 CEG/CEIEC. A completed, signed, approved Air Force Form 3952 is required for

every hazardous material used on Robins AFB.

v. Written procedures for handling of any hazardous waste generated.

b. ODS and Controlled Substances Restriction:

i. The Contractor shall provide the name, address, telephone number, and technician

certification of each person who will service, repair, maintain and/or dispose of any

equipment containing and/or using a refrigerant (Class I ODS, Class II ODS, or non-ozone

depleting substance) to 78 CEG/CEIEC.

ii. The Contractor shall provide a list of appliances located on base that have a capacity of 50

pounds or more of a Class I or Class II refrigerant to 78 CEG/CEIEC. Include the following

information for each appliance:

◦ The type of appliance, i.e., commercial refrigeration appliance, industrial process

refrigeration appliance, comfort cooling appliance, or other type of refrigeration

appliance;

◦ The location of each appliance;

◦ The manufacturer, serial number, or other method of identification;

◦ The amount of the full charge of refrigerant, the type of refrigerant used, and the

date full charge was determined.

◦ For maintenance, service, repair, and/or disposal of base appliances containing 50

pounds or more of a Class I or Class II refrigerant, provide records, work logs, service

tickets, invoices, and supporting documentation to 78 CEG/CEIEC. The

documentation required should contain the following:

◦ The date and type of service performed, i.e., repair, maintenance and/or disposal;

◦ The date any leak was discovered;

◦ A complete, detailed description of any service performed;

01560 - Environmental Requirements Rev Date: September 2015

Page 20 of 32

◦ The amount of refrigerant added at the completion of each service performed;

◦ Dates and results of the initial and follow-up verification tests; and

◦ The name of the technician who performed the work.

iii. For any equipment used to recover or recycle refrigerants on base, provide the following

information to 78 CEG/CEIE:

◦ A copy of any invoice or other record documenting the purchase or rental of such

equipment, including the type of equipment, the manufacturer’s name, the

equipment model number, year manufactured, and any associated serial number;

and

◦ A copy of the equipment certification sent to US EPA.

iv. For any purchases or acquisitions of refrigerant used for any service on base, provide copies

of records, including, but not limited to, receipts, invoices, purchase orders, or bills of lading

to 78 CEG/CEIE. The information should include the name, address and telephone number

of each person, agent, or business entity from whom the facility purchased refrigerant.

c. DODAAC Account: After the Preconstruction Conference, the Contractor must have a valid DODAAC

or work with the CO to obtain a DODAAC account number to pay DLA-DS for disposals.

i. After contract award, work with 78 CEG/CEIER Hazardous Waste Disposal/Turn-in

personnel, (478) 926-1176, to discuss how to obtain containers and container labels. The

Contracting Official Technical Representative must apply or update a DODAAC through the

Air Force DODAAC manager at https://dodaac.wpafb.af.mil/.

ii. Wait until the DODAAC account number is validated to begin generating regulated waste

items to avoid long-term storage issues.

2.3 AIR QUALITY

2.3.1 General: The contractor will perform value engineering for each project requiring specification or

installation of equipment for control of regulated air pollutants. These analyses will ensure that the

proposed control technology meets air quality compliance requirements. New sources require utilization of

Maximum Achievable Control Technology to reduce emissions of hazardous air pollutants.

2.3.2 Open Burning: Open burning operations are prohibited on base and shall not be used. Open burning is any

outdoor fire which emits products of combustion directly into the open air without passing through a stack,

chimney, or duct.

2.3.3 ODS are restricted from use. Comply with paragraph 2.2.8.b.

2.3.4 Generators: Projects which will put generators into operation (new or replacement units) will require

certification from the manufacturer of the unit that all Federal Standards for the performance of Stationary

Compression Ignition Internal Combustion Engines are met. This certification must be submitted and

01560 - Environmental Requirements Rev Date: September 2015

Page 21 of 32

approved by the CO and 78 CEG/CEIEC Air Quality Program Manager prior to ordering and delivery of the

unit.

2.3.5 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. Air Permit – Emission Sources: According to GA EPD Rules for Air Quality Control, Chapter 391-3-1-

.03, any person prior to beginning the construction or modification of any facility which may result

in air pollution shall obtain a permit for the construction or modification of such facility. The

contractor shall submit the required data to complete the permit application form as early in the

planning process as possible, at least within six months of the start date. Since an approved permit

to construct is mandatory prior to start of construction, the contractor shall not install the

equipment until the permit has been approved and Government approval of the contractor's

submittal has been obtained. Contractor shall anticipate nine months to one year from air source

data submittal for this to occur. Direct all inquiries to the 78 CEG/CEIEC Air Program Manager.

b. Notify the 78 CEG/CEIEC Air Program Manager of any decommissioning or replacement of

sources/equipment that emit air pollution.

2.4 PESTICIDES (INSECTICIDES, FUNGICIDES, HERBICIDES, ETC.)

2.4.1 General: The Contractor shall use only United States Environmental Protection Agency (US EPA) approved

pesticides, insecticides, fungicides, herbicides, etc., and report pounds of active ingredient used for each

pesticide to the 78 CEG/CEIEC Natural Resources Program Manager at the end of the project. The

Contractor shall abide by the principles of Integrated Pest Management, implementing physical methods to

control pests as the primary strategy. Chemical methods of control should only be used as a last resort, and

the chemicals used should be the most environmentally benign available. The contractor shall contact 78

CEG/CEIEC before using pesticides, herbicides, etc., in order to ensure that the chemical they plan to use is

on the list of products that have been approved for use on Robins AFB.

2.4.2 Licenses: The Contractor must possess a pest control operator’s license and a list of all chemicals to be used.

Use only a pest control operator licensed in the State of Georgia to apply these chemicals.

2.4.3 Handling: The Contractor must ensure proper delivery, storage, handling, and disposal of all chemicals.

a. Pesticides, insecticides, fungicides, and herbicides are classified as HazMat and must be managed as

HazMat.

2.4.4 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. The Contractor must submit a list of all pesticides to be used and amount (pounds) of active

ingredients used to 78 CEG/CEIEC Natural Resources Program Manager so that coordination of all

pesticide usage can be coordinated with Base Entomology Shop, 78 CES/CEOIE.

b. Proof of License: The contractor must submit a copy of the pest control operator’s license to the CO

and 78 CEG/CEIEC.

01560 - Environmental Requirements Rev Date: September 2015

Page 22 of 32

2.5 STORAGE TANKS

2.5.1 General: Underground storage tank (UST) installation should be a last resort and require approval by 78

CEG/CEIEC Tank Program Manager; aboveground storage tanks are preferred. Contracts not associated with

direct tank removal, replacement, or addition must still identify the presence of any tanks, oil/water

separators (OWS), and associated piping in the construction area. Coordinate any actions before removal

and installation with 78 CEG/CEIEC to meet GA EPD notification requirements prior to work start. Direct all

inquiries to the 78 CEG/CEIEC Tanks Program Manager.

2.5.2 Tank Removal or Closure: The Contractor shall provide information to the CO so that 78 CEG/CEIEC can

submit notification to the GA EPD concerning the installation or removal of tanks. Allow at least 45 days

after the Notice to Proceed before starting the removal process for tanks. The removal process must be

completed within 90 days to comply with GA EPD regulations. Ensure contractor performs proper UST

closure in accordance with Georgia Rules 391-3-15-.11. Cleanup requirements in 40 CFR 280.60-67 and 391-

3-15-.09 apply. Additional information can be found at US EPA Rules:

http://www.epa.gov/OUST/ustsystm/close.htm

2.5.3 Tank Addition or Replacement: For the installation of a new tank, submit the following to the 78 CEG/CEIEC

Tanks Program Manager: manufacturer, date of manufacture, size (how many gallons), model, and serial

number for the tank. All signage and markings on the new tank need to be stenciled in accordance with AFI

23-204, Task Order 37-1-1, and Military Standard 601.

2.5.4 Septic Tanks: The installation of septic tanks or systems is not allowed on Robins AFB.

2.6 THREATENED AND ENDANGERED SPECIES OF PLANTS AND WILDLIFE

2.6.1 General: One state-protected species of plants occurs on Robins AFB, as well as eight other species

considered to be rare. The Contractor shall not clear vegetation on project sites without prior approval from

78 CEG/CEIEC. Rare wildlife species such as Bald Eagles and Wood Storks are occasionally seen on base. The

Contractor shall not harm wildlife of any kind. Most wildlife species found on base are protected by law,

including birds, bats, land turtles, non-venomous snakes, and game species such as deer. If the Contractor

encounters problems with wildlife, notify the CO. The CO shall contact the 78 CEG/CEIEC Natural Resources

Program Manager to determine the best solution for each problem. The CO will ensure that the

Contractors’ actions do not injure rare species and/or their habitats.

2.7 WETLANDS

2.7.1 General: Wetlands delineation has been completed on base and wetland boundaries are currently

identified with markers. However, markers can, in some instances, be missing or not readily visible, and

wetlands often do not contain water throughout the year, so they may not be apparent. When in doubt,

verify that the site in question is or is not a wetland by contacting 78 CEG/CEIEC. These areas shall not be

filled, dredged, or disturbed in any way. Comply with water and land protection sections outlined in this

Specification to prevent construction site sediments and runoff from entering wetlands.

2.8 GREEN PROCUREMENT PROGRAM (GPP)

2.8.1 General: GPP is a mandatory federal acquisition program that focuses on the purchase and use of

environmentally preferable and biobased products and services. Air Force GPP Policy includes the

01560 - Environmental Requirements Rev Date: September 2015

Page 23 of 32

purchasing of Energy and Water Efficient Products; Alternative Fuels and Fuel Efficiency; Biobased Products;

Non-Ozone Depleting Substances; Priority Chemicals; and Environmentally Preferable Products. GPP

requirements apply to all acquisitions including services and new requirements. Federal Acquisition

Requirement 23.404(b) applies and requires 100% of US EPA designated product purchases contain

recovered materials, unless the item cannot be acquired: competitively within a reasonable timeframe;

meeting reasonable performance standards; or at a reasonable price.

2.9 PRESERVING HISTORICAL AND ARCHAEOLOGICAL RESOURCES

2.9.1 General: When a building or archaeological site determined eligible for the National Register of Historic

Places is within a project area, the Contractor shall take adequate measures to prevent adverse impact to

the cultural resource. This may include the development of a mitigation plan, consultation with the Georgia

State Historic Preservation Office, the Advisory Council on Historic Preservation, and 12 culturally affiliated

Native American tribes.

a. Coordination: The Contractor shall provide 78 CEG/CEIE with all the project information to prevent

adverse impacts to the building or archaeological site. The Contractor shall contact 78 CEG/CEIEC

Cultural Resources Program Manager at the beginning of the project prior to beginning any work.

b. Discoveries: When cultural resources are inadvertently discovered during construction, project

personnel are directed to avoid the site of discovery and immediately contact the 78 CEG/CEIEC

Cultural Resources Program Manager. All work in the area of discovery must stop until it can be

investigated. 78 CEG/CEIE will send a qualified representative to the site and the resource will need

to be recorded and evaluated and the effects mitigated as necessary.

2.9.2 Archaeological Finds: All archaeological finds are the property of Robins AFB. Do not remove or disturb

finds without the CO's written authorization. Archaeological Finds are artifacts, ecofacts, or modifications to

the landscape that are associated with past human activity and are a minimum of 50 years old.

2.10 PROTECTION OF WATER AND LAND RESOURCES

2.10.1 General: The Contractor shall not take any action that will adversely affect the existing Water Quality

Standards classification of any streams, rivers, lakes, wetlands, or reservoirs within or adjacent to the project

site or which would otherwise contribute to the pollution of these water resources. No fuel, oils,

bituminous, calcium chloride, acids, construction waste, or otherwise harmful materials shall be permitted

to enter these water resources. Land resources shall be preserved in their present condition or restored to a

condition that appears natural and does not detract from the appearance of the surrounding area. If

restoration is to be accomplished, the Contractor shall submit an appropriate restoration plan and receive

base approval from 78 CEG/CEIE on the proposed mitigation procedures.

2.10.2 Stormwater Management during Construction: All land disturbances shall be conducted in accordance with

the Georgia Erosion and Sediment Control Act, the Rules of the State of Georgia, and if applicable, the

Georgia General Permit for Discharge of Stormwater Associated with Construction Activity. The Contractor

shall implement procedures and practices to eliminate or minimize stormwater pollution during

construction activities in accordance with the Engineering Technical Letter (ETL) 03-1: Stormwater

Construction Standards. The Contractor shall not allow any debris to get into the storm drainage system.

Chemicals, fuels, oils, lubricants, greases, or scrap metal stored on construction sites shall have containment

01560 - Environmental Requirements Rev Date: September 2015

Page 24 of 32

and/or cover to prevent stormwater contact. No materials shall be discharged into a drain, ditch, or ground

surface that could result in pollution of stormwater runoff. Minimum control measures shall be

implemented to prevent degradation of water quality downstream resulting from any construction activity.

Construction activities such as concrete truck washing, cleaning of painting equipment, equipment fueling,

and general site housekeeping will require implementation of specific best management practices (BMP) to

prevent stormwater contamination. For information on BMPs contact the 78 CEG/CEIEC Water Quality

Program Manager.

2.10.3 Post Construction Stormwater Management: The Contractor shall design and implement control measures

for stormwater runoff from new development and redevelopment projects that includes the creation or

addition of 5,000 square feet or greater of new impervious surface area, or that involves land disturbing

area activity of 5,000 square feet of land or greater in accordance with the: Stormwater Local Design

Manual for Houston County, Georgia (LDM); Georgia Stormwater Management Manual (GSMM); and

Section 438 of the 2007 Energy Independence and Security Act (EISA).

A Post Construction Stormwater Management Plan (i.e., Hydraulics and Hydrology Report, EISA 438 Design

Analysis, etc., including related narratives and calculations) shall be submitted by the Contractor to

document appropriate and effective control measures are included in the project. The Plan shall be

submitted through the established design review process.

The Contractor shall use the following guidance when developing post construction stormwater

management systems: Unified Facilities Criteria (UFC) 3-210-10, Low Impact Development Manual; US EPA

841-B-09-001: Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal

Projects under Section 438 of the Energy Independence and Security Act; LDM; GSMM; and ETL 08-6: Design

of Surface Drainage Facilities.

The Contractor shall develop a Post Operation and Maintenance (O&M) Plan for all designed post-

construction BMPs to ensure the storm water control measures will function as designed. The O&M Plan

shall be submitted through the design review process.

2.10.4 Prohibition of Illegal Discharges: The Contractor shall not discharge or cause to be discharged into the

municipal storm drain system or watercourses any materials, including but not limited to pollutants or

waters containing any pollutants that cause or contribute to a violation of applicable water quality

standards, other than stormwater.

The commencement, conduct, or continuance of any illegal discharge to the storm drain system is

prohibited except as described below:

a. The following discharges are exempt from discharge prohibitions established by this requirement:

water line flushing or other potable water sources, landscape irrigation or lawn watering, diverted

stream flows, rising groundwater, groundwater infiltration to storm drains, uncontaminated

pumped ground water, foundation or footing drains (not including active groundwater dewatering

systems), crawl space pumps, air conditioning condensation, springs, natural riparian habitat or

wetland flows, swimming pools (if dechlorinated - typically less than one part per million chlorine),

firefighting activities, and any other water source not containing pollutants.

01560 - Environmental Requirements Rev Date: September 2015

Page 25 of 32

b. Discharges specified in writing by 78 CEG/CEIEC Water Program Manager as being necessary to

protect public health and safety.

c. Dye testing is an allowable discharge, but requires a written notification to and approval from 78

CEG/ CEIEC Water Program Manager prior to the time of the test.

d. The prohibition shall not apply to any non-stormwater discharge permitted under an National

Pollution Discharge Elimination System (NPDES) permit, waiver, or waste discharge order issued to

the discharger and administered under the authority of the Federal Environmental Protection

Agency, provided that the discharger is in full compliance with all requirements of the permit,

waiver, or order and other applicable laws and regulations, and provided that written approval has

been granted for any discharge to the storm drain system.

2.10.5 Prohibition of Illicit Connections:

a. The construction, use, maintenance or continued existence of illicit connections to the storm drain

system is prohibited.

b. This prohibition expressly includes, without limitation, illicit connections made in the past,

regardless of whether the connection was permissible under law or practices applicable or

prevailing at the time of connection.

c. The Contractor is considered to be in violation of this requirement if the Contractor connects a line

conveying non-stormwater discharges to the stormwater conveyance system, or allows such a

connection to continue.

2.10.6 Spills: Prevent the spill of chemicals, fuels, oils, grease, bituminous materials, waste washings, herbicides,

cement drainage, or any other hazardous materials, including broken fluorescent or HID lamps and tubes.

Immediately report all spills to the Base Fire Department, 778 CES/CEX, and emergency number 911. Ensure

to report all emergency information, including name, telephone number, location of spill, and type and

amount of material spilled. Notify the CO of the spill immediately following initial reporting to the Fire

Department and 911. The contractor shall be responsible for containment of all spills. The contractor is

responsible for maintain spill containment and cleanup equipment and materials onsite that are appropriate

for the materials being stored and in sufficient quantities to provide containment for the volume of material

used and stored. Under no circumstances should anyone attempt to handle a spill situation for which they

have not been trained.

The Contractor is responsible for the cleanup of material(s) spilled as well as any soil, grass, etc. that has

absorbed spill materials. Ensure complete and thorough clean-up of materials spilled by testing water

and/or soil (full analytical tests are required). No spill residue shall be transported off Robins AFB without

specific approval from the CO. Spills involving large quantities and/or requiring special protective clothing

and/or breathing devices to facilitate clean up may require action by the Base Spill Response Team. When

the Base Spill Response Team is utilized, the Contractor shall provide support, as appropriate, for

containment and clean-up of spills. The contractor is responsible for all fees associated with the Base Spill

Response Team.

2.10.7 Tree Protection and New Landscaping:

01560 - Environmental Requirements Rev Date: September 2015

Page 26 of 32

a. Trees marked for removal on approved plans and drawings shall have existing identification tags

removed (if present) and forwarded to the CO. Except in areas marked on the plans to be cleared,

do not deface, injure, destroy, remove, or cut trees or shrubs without authority from the CO and 78

CEG/CEIEC Natural Resources Program Manager. In cases where construction necessitates the

removal of a large number of trees, 78 CEG/CEIEC will need to first evaluate whether or not a

logging contract is warranted (to be arranged by CEIEC), as per AFI 32-7064 it is inappropriate to give

away forest resources which have significant value.

b. In general, trees shall be protected from either excavation or filling within the root zone closer than

the normal drip line of the tree. No ropes, cables, or guys shall be fastened to, or attached to any

existing trees for anchorage unless specifically authorized by the CO. The contractor shall not allow

vehicles to be routinely parked within the drip zone of trees which are designated for protection,

nor will equipment be staged under these trees. The Contractor shall in any event be responsible

for any damage resulting from such use.

c. Where, in the opinion of the CO, trees may possibly be defaced, bruised, injured, or otherwise

damaged by the Contractor's equipment, blasting, dumping, or other operations, the CO may direct

the Contractor to adequately protect such trees by placing boards, planks, plastic fence, or poles

around them. When directed by the CO, construct barriers to protect trees from earthwork

operations. Rocks that are displaced into uncleared areas shall be removed. Monuments, markers,

and works of art shall be similarly protected before beginning operations near them.

d. The Contractor shall submit all landscaping plans to the 78 CEG/CEIEC Natural Resources Program

Manager for review and approval before implementation. Plans shall emphasize the use of native

plant and tree species whenever possible, and shall include provisions for conserving water use and

minimizing the need for pesticide and herbicide use. Brown Top Millet is not authorized for use at

Robins AFB.

2.10.8 Restoration of Landscape Damage: Surface Drainage: Surface drainage from cuts and fills within the

construction limits and from borrow and waste disposal areas, shall be held in suitable sedimentation ponds

or shall be graded to control erosion. Temporary erosion and sediment control measures such as berms,

dikes, drains, or sedimentation basins, shall be provided and maintained until permanent drainage and

erosion control measures are completed and operating. The area of bare soil exposed by construction

operations at any time shall be held to a minimum. Stream crossings by fording with equipment shall be

limited to control turbidity. Fills and waste areas shall be constructed by select placement to eliminate

adjacent streams.

Stabilization of permanent steep slopes shall be accomplished as soon as possible to establish vegetation.

Apply mulch (no more than 2-3 inches in depth) immediately after finished grading is completed, regardless

of season, and delay seeding and fertilizing until the season most favorable for germination.

2.10.9 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. Permit for Stormwater Management during Construction: If the project will disturb one (1.0) acre or

more of land surface, coverage under NPDES General Permit GAR 100001, GAR 100002, or GAR

100003 shall be obtained through the submission of a Notice of Intent (NOI) to the GA EPD district

01560 - Environmental Requirements Rev Date: September 2015

Page 27 of 32

office. Provide the following as a minimum in complying with all applicable local, state, and federal

laws:

i. The Contractor shall submit an Erosion, Sediment, and Pollution Control (ESPC) Plan signed

and stamped by a Georgia Professional Engineer with Level 2 Certification from the Georgia

Soil and Water Conservation Commission to 78 CEG/CEIE for review and approval prior to

submitting the NOI to GA EPD. The ESPC Plan shall be developed using the Robins AFB ESPC

Plan Template and meet or exceed the requirements of the respective applicable permit and

the current edition of the Manual for Erosion and Sediment Control in Georgia.

ii. The Contractor shall submit a completed NOI to be covered by a NPDES Permit for

stormwater discharge associated with construction activity to 78 CEG/CEIE for review and

approval prior to submitting the NOI to GA EPD. After 78 CEG/CEIE approval of the ESPC

Plan, the Contractor shall submit the NOI form and pay permit fees to both GA EPD and

Houston County Public Works Department, at least 14 days prior to any site work.

iii. The Contractor is responsible for compliance with the NPDES Permit and shall perform all

permit-required tasks, including inspections, monitoring, and recordkeeping until such time

the site achieves final stabilization. Final payment shall not be performed until the site

achieves final stabilization as defined by the NPDES Permit. Special attention must be

provided to consider the timing of project completion to ensure permanent vegetation is

established (i.e., projects may require over-wintering with temporary grass until the spring

growing season, when permanent grass (Bermuda/Centipede) shall be applied to the site

after raking and fertilization. The Contractor shall submit a 78 CEG/CEIE reviewed and

approved Notice of Termination (NOT) to the GA EPD after final stabilization is achieved and

there is no discharge associated with construction activities. All records shall be maintained

for a period of three years from the date the NOT is submitted. All NPDES Permit-required

records shall be provided to 78 CEG/CEIEC Water Quality Program Manager.

b. Post Construction Stormwater Management Plan: The Contractor shall submit a Post Construction

Stormwater Management Plan including narrative and calculations for sizing of all post construction

BMPs. The Plan shall be submitted for all new development or redevelopment greater than 5,000

square feet (of impervious area or land disturbance). This Plan typically includes a Hydraulic and

Hydrology Report, Design Analysis, and EISA Compliance requirements, and related narrative,

figures, and drawings. The design shall meet the minimum stormwater management standards of

the GSMM and Section 438 of EISA. The Plan shall be submitted as part of the project design

documents for the 60 percent design (i.e., intermediate design) submittal.

c. Post Construction Operation and Maintenance Plan: The Contractor shall submit an Operation and

Maintenance Plan for all designed permanent BMPs. The Plan shall include at minimum a

description and drawing of the BMP, a schedule of recommended inspection and maintenance

activities, and any other required information to ensure proper and effective operation of the BMP

through its designed operational period.

01560 - Environmental Requirements Rev Date: September 2015

Page 28 of 32

2.11 BACKFLOW PREVENTION DEVICES (BPDS)

2.11.1 General: All BPDs must be installed in accordance with current Uniform Plumbing Code (Section 603.3.4)

and AFI 32-1067. BPDs must be selected to address the level of hazard and installed in locations that are

readily accessible for inspection and maintenance. All BPDs must be installed by Georgia-certified BPD

technicians. Direct all inquiries to Bioenvironmental Engineering, 78 AMDS/SGPB, (478) 327-7555.

2.11.2 Coordination: The Contractor shall coordinate with Government Project Manager to ensure

Bioenvironmental Engineering has assigned the level of hazard and identified the appropriate BPD for the

application prior to purchase of BPDs.

2.11.3 Installation: The Contractor shall coordinate the BPD installation location with the Government Project

Manager to ensure the installation location is accessible and meets space requirements for inspection and

maintenance.

2.11.4 Inspection and Testing: The Contractor shall provide an inspection/testing of the BPD(s) in accordance with

the manufacturer’s instructions for the particular device or using procedures recognized by the tester’s

certifying agency. At a minimum, all devices shall be tested after installation, cleaning, repair, or relocation.

2.11.5 Submittals, Notifications, and Approvals: The following submittals, notifications, and approvals are required

to maintain compliance:

a. The Contractor must coordinate location of BPDs with the Backflow Prevention Program Manager

prior to installation.

b. The Contractor must submit a copy of BPD Test Report to the Backflow Prevention Program

Manager.

c. The Contractor must obtain approval to use fire hydrants or to penetrate water mains from 78

AMDS/SGPB, Bioenvironmental Engineering at (478) 327-7555 and Civil Engineering Plumbing Shop

(478) 468-2399 or (478) 327-8969. Use only lead free materials with the drinking water system, for

solder no more than 0.2 percent and for pipes/fittings no more than 8 percent per 40 CFR 141.43.

---- END OF NARRATIVE SECTION ----

NOTE: Copies of the SWAA form, its tracking document, and monthly waste management report form follow.

01560 - Environmental Requirements Rev Date: September 2015

Page 29 of 32

Houston County MSW Landfill Profile No:

2018 Kings Chapel Road (Assigned by Houston County) Perry, Georgia 31069

Telephone: (478) 987-0089 Fax: (478) 987-0102

SPECIAL WASTE ACCEPTANCE APPLICATION (SWAA)

Generator Name: Contact:

Address: Telephone: Fax:

Description of Waste:

Source / Location of Waste:

Waste Quantity: Cubic Yards ☐ Tons ☐

Frequency of Disposal: Daily ☐ Weekly ☐ Monthly ☐ One Time ☐ Other

LABORATORY DATA (Please attach a hard copy of laboratory test data)

Physical Properties: Physical State: Solid ☐ Semisolid ☐ Liquid ☐ Color:

Halogenated Organics: mg/kg Flash Point: ☐F Odor: Yes ☐ No ☐

Water Content: % by Weight Paint Filter Test Passed ☐ Failed ☐

Reactive: No ☐ Yes ☐ With H2S mg/kg HCN mg/kg Others mg/kg

pH Value: (S.U.) Infectious: Yes ☐ No: ☐

Chemical Properties (TCLP): (Concentrations in mg/l)

Arsenic m-Cresol Hexachlorobenzene Pyridine

Barium p-Cresol Hexacholorobutadiene Selenium

Benzene Total Cresol Hexachloroethane Silver

Cadmium 2,4-D Lead Tetrachloroethene

Carbon Tetrachloride 1,4 Dichlorobenzene Lindane Toxaphene

Chlordane 1,2 Dichloroethane Mercury Trichloroethene

Chlorobenzene 1,1 Dichloroethylene Methoxychlor 2,4,5 Trichlorophenol

Chloroform 2,4 Dinitrotoluene Methyl Ethyl Ketone 2,4,6 Trichlorophenol

Chromium Endrin Nitrobenzene 2,4,5TP (Silvex)

o-Cresol Heptachlor (a hydroxide) Pentachlorophenol Vinyl Chloride

None of the above constituents exceed TCLP disposal limits Others (List)

Other Information: Delivery method: Bulk ☐ Other

Regulatory Agency Approval Received: Yes ☐ No ☐ Permit Number

Material Safety Data Sheet Provided: Yes ☐ No ☐

Generator's Certification Statement

"I certify under penalty of law that this document and all attachments were prepared under my direction and supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information

submitted. To the best of my knowledge, the material described above is not classified as hazardous waste under current

regulations, and I agree to notify Houston County MSW Landfill if such classification changes. The attached information provided is true and accurate to the best of my knowledge."

Signature of Authorizing Agent Date

Name of Agent (Typed or Printed) Title

01560 - Environmental Requirements Rev Date: September 2015

Page 30 of 32

Houston County MSW Landfill Profile No:

2018 Kings Chapel Road (Assigned to SWAA) Perry, Georgia 31069

Telephone: (478) 987-0089

WASTE SHIPMENT TRACKING DOCUMENT

Generator Name: Contact:

Address:

Telephone: Fax:

Description of Waste:

Location of Waste:

Date Shipped: Quantity Shipped:

Certification: I certify the waste described above is the waste represented by the Special Waste Acceptance Application

(SWAA) of the same Profile Number and no regulated hazardous waste has been introduced into the waste.

Generator's Signature: Date:

Transporter: Contact:

Address:

Telephone:

Certification: I certify no regulated hazardous waste was introduced into the waste while in my custody:

Hauler's Signature: Date:

Waste Disposal Site: Houston County MSW Landfill

Quantity Received:

Certification: I certify receipt and proper disposal of the Special Waste Profiled materials covered by this manifest.

Operator’s Printed Name:

Operator’s Signature: Date:

01560 - Environmental Requirements Rev Date: September 2015

Page 31 of 32

WASTE MANAGEMENT REPORT (MONTHLY)

Contract Number Government Inspector:

Contractor Project # Title:

Contractor POC: Date:

Phone No:

I. MSW Landfill Disposal II. C&D Landfill Disposal III. Inert Landfill Disposal

Quantity (tons): Quantity (tons): Quantity (tons): Landfill Site: Landfill Site: Landfill Site:

Tip fee/ton ($/ton): Tip fee/ton ($/ton): Tip fee/ton ($/ton):

*Total cost of disposal ($): *Total cost of disposal ($): *Total cost of disposal ($):

*Total cost/ton ($/ton): *Total cost/ton ($/ton): *Total cost/ton ($/ton):

IV. Alternatives to Landfilling (Recycling Strongly Encouraged)

Type of Material

Quantity

(pounds

or tons) Destination

* Handling &

Transportation

Cost ($)

*Expected

Revenue & Tip

Fee Earnings ($) * Net Cost ($)

*Cost if

Landfilled ($)

* Comparison

Cost

(+)/Savings (-)

Cardboard

Dimensional wood

Beverage containers

Land debris

Concrete

CMU

Asphalt

Metals - all types

Gypsum board

Paint

Carpet

Insulation

Glass

Cast stone

Wood materials

Electric cable

PVC piping

Rubber flooring

Raised flooring

IV. Total net cost (+) or savings (-) from all alternatives to landfilling all project waste

V. Means of keeping recyclables free of contamination

All similar materials will be grouped together based on the requirements of the recycling center.

All dissimilar materials will be kept in separate containers/bins in order to avoid contamination.

VI. Meetings to be held to address waste management

At regularly scheduled job site coordination/progress meetings and at job safety meetings, waste management requirements will be

discussed to clarify any confusion with craftspeople.

* Optional

01560 - Environmental Requirements Rev Date: September 2015

Page 32 of 32

<<<<< END OF ENVIRONMENTAL REQUIREMENTS >>>>>

Author: HEIDI L. SCHWINGLE, 78 CEG/CEIEC, 478-327-8287

Reviewer:

Approval: ________________________________________________________

Stefanie Dawson, 78 CEG/CENMP, 478-327-2948

Revision History

30 Sep 2015: Updated and re-formatted per Environmental Management, 78 CEG/CEIE

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 1of 6

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The

publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E 1609 (1994; R 2001) Development and Implementation of a

Pollution Prevention Program

U.S. GREEN BUILDING COUNCIL (USGBC)

LEED (2006; R 2007) Leadership in Energy and Environmental

Design(tm) Green Building Rating System for New

Construction (LEED-NC)

1.2 GOVERNMENT POLICY

Government policy is to apply sound environmental principles in the design, construction and use of

facilities. As part of the implementation of that policy the Contractor shall: (1) practice efficient

waste management when sizing, cutting, and installing products and materials and (2) use all

reasonable means to divert construction and demolition waste from landfills and incinerators and to

facilitate their recycling or reuse. A minimum of 75 percent by weight of total project solid waste

shall be diverted from the landfill.

1.3 MANAGEMENT

Develop and implement a waste management program in accordance with ASTM E 1609 and as

specified. Take a pro-active, responsible role in the management of construction and demolition

waste and require all subcontractors, vendors, and suppliers to participate in the effort. The

Environmental Manager, as specified in Section 01 35 40.00 20 Environmental Management, shall be

responsible for instructing workers and overseeing and documenting results of the Waste

Management Plan for the project. Construction and demolition waste includes products of demolition

or removal, excess or unusable construction materials, packaging materials for construction products,

and other materials generated during the construction process but not incorporated into the work. In

the management of waste consideration shall be given to the availability of viable markets, the

condition of the material, the ability to provide the material in suitable condition and in a quantity

acceptable to available markets, and time constraints imposed by internal project completion

mandates. The Contractor is responsible for implementation of any special programs involving

rebates or similar incentives related to recycling of waste. Revenues or other savings obtained for

salvage, or recycling accrue to the Contractor. Appropriately permit firms and facilities used for

recycling, reuse, and disposal for the intended use to the extent required by federal, state, and local

regulations. Also, provide on-site instruction of appropriate separation, handling, recycling, salvage,

reuse, and return methods to be used by all parties at the appropriate stages of the project.

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 2of 6

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G"

designation are [for Contractor Quality Control approval.][for information only. When used, a

designation following the "G" designation identifies the office that will review the submittal for the

Government.] The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals; Waste Management Plan.

SD-11 Closeout Submittals; Records

1.5 MEETINGS

Conduct Construction Waste Management meetings. After award of the Contract and prior to

commencement of work, schedule and conduct a meeting with the Contracting Officer to discuss the

proposed Waste Management Plan and to develop a mutual understanding relative to the details of

waste management. At a minimum, environmental and waste management goals and issues shall be

discussed at the following additional meetings:

a. Pre-bid meeting.

1.6 WASTE MANAGEMENT PLAN

A waste management plan shall be submitted within 15 days after notice to proceed and not less

than 10 days before the preconstruction meeting. The plan shall demonstrate how the project

waste diversion goal shall be met and shall include the following:

a. Name of individuals on the Contractor's staff responsible for waste prevention and

management.

b. Actions that will be taken to reduce solid waste generation, including coordination with

subcontractors to ensure awareness and participation.

c. Description of the regular meetings to be held to address waste management.

d. Description of the specific approaches to be used in recycling/reuse of the various materials

generated, including the areas on site and equipment to be used for processing, sorting, and

temporary storage of wastes.

e. Characterization, including estimated types and quantities, of the waste to be generated.

f. Name of landfill and/or incinerator to be used and the estimated costs for use, assuming that

there would be no salvage or recycling on the project.

g. Identification of local and regional reuse programs, including non-profit organizations such as

schools, local housing agencies, and organizations that accept used materials such as materials

exchange networks and Habitat for Humanity. Include the name, location, and phone number for

each reuse facility to be used, and provide a copy of the permit or license for each facility.

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 3of 6

h. List of specific waste materials that will be salvaged for resale, salvaged and reused on the

current project, salvaged and stored for reuse on a future project, or recycled. Recycling

facilities that will be used shall be identified by name, location, and phone number, including a

copy of the permit or license for each facility.

i. Identification of materials that cannot be recycled/reused with an explanation or justification,

to be approved by the Contracting Officer.

j. Description of the means by which any waste materials identified in item (h) above will be

protected from contamination.

k. Description of the means of transportation of the recyclable materials (whether materials will

be site-separated and self-hauled to designated centers, or whether mixed materials will be

collected by a waste hauler and removed from the site).

l. Anticipated net cost savings determined by subtracting Contractor program management costs

and the cost of disposal from the revenue generated by sale of the materials and the incineration

and/or landfill cost avoidance.

Revise and resubmit Plan as required by the Contracting Officer. Approval of Contractor's Plan will

not relieve the Contractor of responsibility for compliance with applicable environmental regulations

or meeting project cumulative waste diversion requirement. Distribute copies of the Waste

Management Plan to each subcontractor, the Quality Control Manager, and the Contracting Officer.

1.7 RECORDS

Records shall be maintained to document the quantity of waste generated; the quantity of waste

diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or

incineration. [Records shall be kept in accordance with the LEED Reference Guide and using the

LEED Letter Template.] Quantities may be measured by weight or by volume, but must be consistent

throughout. List each type of waste separately noting the disposal or diversion date. Identify the

landfill, recycling center, waste processor, or other organization used to process or receive the solid

waste. Provide explanations for any waste not recycled or reused. With each application for payment,

submit updated documentation for solid waste disposal and diversion, and submit manifests, weight

tickets, receipts, and invoices specifically identifying the project and waste material. The records

shall be made available to the Contracting Officer during construction, and a copy of the records shall

be delivered to the Contracting Officer upon completion of the construction.

1.8 REPORTS

Provide quarterly reports and a final report to the Contracting Officer. Quarterly and final reports

shall include project name, information for waste generated this quarter, and cumulative totals for the

project. Each report shall include supporting documentation to include manifests, weight tickets,

receipts, and invoices specifically identifying the project and waste material. Include timber harvest

and demolition information, if any.

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 4of 6

1.9 COLLECTION

Separate, store, protect, and handle at the site identified recyclable and salvageable waste products in

a manner that maximizes recyclability and salvagability of identified materials. Provide the necessary

containers, bins and storage areas to facilitate effective waste management and clearly and

appropriately identify them. Provide materials for barriers and enclosures around recyclable material

storage areas which are nonhazardous and recyclable or reusable. Locate out of the way of

construction traffic. Provide adequate space for pick-up and delivery and convenience to

subcontractors. Recycling and waste bin areas are to be kept neat and clean, and recyclable materials

shall be handled to prevent contamination of materials from incompatible products and materials.

Clean contaminated materials prior to placing in collection containers. Use cleaning materials that are

nonhazardous and biodegradable. Handle hazardous waste and hazardous materials in accordance

with applicable regulations and coordinate with Section 01560 ENVIRONMENTAL

REQUIREMENTS CHECKLIST and 01572 CONSTRUCTION AND DEMOLITION WASTE

MANAGEMENT. Separate materials by one of the following methods:

1.9.1 Source Separated Method.

Waste products and materials that are recyclable shall be separated from trash and sorted as described

below into appropriately marked separate containers and then transported to the respective recycling

facility for further processing. Deliver materials in accordance with recycling or reuse facility

requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances

deleterious to the recycling process). Separate materials into the following category types as

appropriate to the project waste and to the available recycling and reuse programs in the project area:

a. Land clearing debris.

b. Asphalt.

c. Concrete and masonry.

d. Metal (e.g. banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized,

stainless steel, aluminum, copper, zinc, lead brass, bronze).

(1) Ferrous.

(2) Non-ferrous.

e. Wood (nails and staples allowed).

f. Debris.

g. Glass (colored glass allowed).

h. Paper.

(1) Bond.

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 5of 6

(2) Newsprint.

(3) Cardboard and paper packaging materials.

i. Plastic.

(1) Type 1: Polyethylene Terephthalate (PET, PETE).

(2) Type 2: High Density Polyethylene (HDPE).

(3) Type 3: Vinyl (Polyvinyl Chloride or PVC).

(4) Type 4: Low Density Polyethylene (LDPE).

(5) Type 5: Polypropylene (PP).

(6) Type 6: Polystyrene (PS).

(7) Type 7: Other. Use of this code indicates that the package in question is made with a

resin other than the six listed above, or is made of more than one resin listed above, and

used in a multi-layer combination.

j. Gypsum.

k. Non-hazardous paint and paint cans.

l. Carpet.

m. Ceiling tiles.

n. Insulation.

o. Beverage containers.

1.9.2 Co-Mingled Method.

Waste products and recyclable materials shall be placed into a single container and then transported to

a recycling facility where the recyclable materials are sorted and processed.

1.9.3 Other Methods.

Other methods proposed by the Contractor may be used when approved by the Contracting Officer.

1.10 DISPOSAL

Control accumulation of waste materials and trash. Recycle or dispose of collected materials off-site

at intervals approved by the Contracting Officer and in compliance with waste management

UHHZ160050 CONST. & DEMOLITION WASTE MANAGEMENT - 01572

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT

01572 - PAGE 6of 6

procedures. Except as otherwise specified in other sections of the specifications, disposal shall be in

accordance with the following:

1.10.1 Reuse.

First consideration shall be given to salvage for reuse since little or no re-processing is necessary for

this method, and less pollution is created when items are reused in their original form. Coordinate

reuse with the Contracting Officer. Sale or donation of waste suitable for reuse shall be

considered.

1.10.2 Recycle.

Waste materials not suitable for reuse, but having value as being recyclable, shall be made available

for recycling. All fluorescent lamps, HID lamps, and mercury-containing thermostats removed from

the site shall be recycled. Arrange for timely pickups from the site or deliveries to recycling facilities

in order to prevent contamination of recyclable materials.

1.10.3 Compost

Consider composting on site if a reasonable amount of compostable material will be available.

Compostable materials include plant material, sawdust, and certain food scraps.

1.10.4 Waste.

Materials with no practical use or economic benefit shall be disposed at a landfill or incinerator.

1.10.5 Return

Set aside and protect misdelivered and substandard products and materials and return to supplier for

credit.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

<<<<<END OF SECTION>>>>>

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 1 of 6

PART 1 - GENERAL

1.01 CONTRACTOR OPERATIONS: This section establishes requirements to ensure the safety of

Government and other personnel not directly or indirectly under the employment of the Contractor.

Comply with standards maintained by Occupational Safety and Health Administration (OSHA), Corps of

Engineers Safety Manual (EM 385-1-1), Air Force Occupational Safety and Health (AFOSH) Standards,

and National Fire Protection Association (NFPA). Copies of the Corps of Engineers Safety and Health

Requirements Manual, EM 385-1-1, may be obtained from the local Corps of Engineers office,

Department of the Army, US Army Corps of Engineers, Washington, DC 20314-1000, or US

Government Printing Office, Washington, DC 20314.

A. CONTRACTOR EMPLOYEES: Compliance with OSHA and other applicable laws and

regulations for the protection of Contractor employees is the obligation of the Contractor. This

contract is not intended in any way to require persons to work in surroundings or under working

conditions that are unsafe or dangerous to their health.

B. Coordinate and perform work so as not to impact the safety of Government or non-

Contractor personnel, or cause damage to government property. This requires providing

appropriate safety devices to be utilized in and around the work areas to perform the job safely

and protect others from hazards generated by the work.

1.02 SUBMITTALS:

A. General: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items.

B. Material Submittals: None required under this section.

C. Other Submittals: Provide the following submittals as required by the contract or as directed

by the Contracting Officer.

Inspector

Para # Description Date Required Checklist

3.01.c. Fire Reporting If Fire ______

3.02 AF Form 592, Weld/Cut Permit Before Work ______

3.09 Hazard Communication Before Work ______

3.11 Injury/Mishap Reports By 1 hour after ______

1.03 OSHA INSPECTIONS: Department of Labor (DOL) OSHA inspectors may arrive at Contractor

work sites without formal notification in the event of an employee complaint or a no-notice inspection.

The DOL has the right to stop or delay work and/or issue costly fines due to noncompliance with safety

requirements. Any costs borne by such actions are the sole responsibility of the Contractor.

PART 2- PRODUCTS: Omitted

PART 3- EXECUTION

3.01 FIRE REPORTING: Report all fires as soon as discovered. The fire reporting number on or off

Base is 911. The caller should give his or her name and location of what is on fire. Also, give any other

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 2 of 6

information that may be requested by the Fire Department dispatcher. Stay on the telephone until the

dispatcher has obtained all necessary information.

3.02 OPERATIONS INVOLVING WELDING, CUTTING, BRAZING, AND OPEN FLAME are

carefully controlled at Robins AFB due to several fires caused by such operations.

A. Start no such work until the Technical Representative of the Contracting Officer has been

notified, the site has been inspected, the operation approved by the authorized Fire Inspector, and

an AF Form 592 (Welding, Cutting, and Brazing Permit) has been approved by the Fire Inspector.

Do not contact the Fire Department directly.

B. Observe caution and provide welding, cutting, brazing, and open flame equipment in

accordance with NFPA 51B, OSHA 1926.350 through 1926.354, and AFOSH Standard 91-5.

The foreman at the work area must retain the AF Form 592 for the duration of the work.

C. Perform a fire watch to inspect the work area and adjacent areas for the evidence of fire for at

least one-half hour after completion of the welding, cutting, brazing, or open flame. More than

one fire watch may be required. Fire watch personnel shall sign the AF Form 592 acknowledging

the completion of the inspection for each occurrence of welding, cutting, and brazing work. The

AF Form 592 shall be returned to the Fire Department, Bldg 377, by one hour after the fire watch

is completed. If "after inspection" is required by the Fire Department, call (478)926-2145 or 926-

3487 before leaving the site. Two "after-inspections" will be made by the Fire Department for

work involving roofs.

D. No tar pots or kettles shall be used until checked and approved by the Fire Department. After

Fire Department approval is obtained, the pots or kettles shall be under constant supervision by a

qualified operator when operated. The pots or kettles shall be positioned at least 25 feet from the

building where work is being performed. Adequate fire extinguishers shall be placed within 25

feet and accessible to each pot or kettle. Base fire department also requires a minimum of two 20

lb multi-purpose dry chemical extinguishers at each area of tar application.

E. Roofing mops have been implicated in some roofing fires. The suspected cause is spontaneous

combustion of the mop after immersing in hot asphalt/tar because of chemicals used in the

manufacture of the mop. Because of this, Contractors shall store all mops or rags soaked in

roofing materials away from the building and any other combustible materials so that no damage

may result from an incident of this type. At no time, shall mops or rags soaked with tar be left

unattended on the roof. Used mops and rags shall not be in contact with combustibles and will be

removed from the premises at the end of each daily work period.

F. Smoking shall not be permitted on the roof or within the vicinity of the tar kettle, fuel source,

or any combustible material. Refer to NFPA 1, NFPA 241, and RAFBI 32-2001 for further

instructions on tar kettle operations and torch applied roofing material operations.

3.03 FIRE HYDRANTS/HOSES

A. Fire hydrants shall not be used without prior approval of the Plumbing Shop, 926-2215. If

permission is granted for use of a fire hydrant, the Contractor must furnish a gate valve to fit the 2

1/2" outlet and a proper hydrant wrench. Each time a hydrant is to be opened or used, it must be

opened slowly to prevent a water surge, and it must be opened to the full "open" position. When

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 3 of 6

closing the hydrant, close it slowly to prevent a water surge. (The Plumbing Shop will advise the

Fire Department that the hydrant is being used).

B. The Fire Department will not loan equipment; e.g., fire hoses, nozzles, or hydrant wrenches.

C. No vehicles or equipment shall be parked or stored within 15 feet of a fire hydrant.

3.04 FIRE PROTECTION ALARM SYSTEMS

A. Extreme care must be taken when working around or near any fire protection/detection alarm

systems. Accidental contact with components of these systems or the production of steam,

smoke, vapors, or dust could cause activation, damage, or false alarm by the Fire Department.

B. At any time a fire protection/detection alarm system hampers the accomplishment of contract

work, call 926-5098 and 926-3487 for assistance.

3.05 DEBRIS

A. The accumulation of all debris inside a building shall be kept to a minimum during

construction.

B. Piles of debris awaiting removal outside any facility shall not be placed in fire lanes or within

25 feet of the facility.

C. When debris is dropped through holes, from roofs, etc., protective chutes or proper barricades

shall be used to protect personnel. Signs warning of the hazards of falling material shall be posted

at each level. Warning signs and barricades must be erected before the work requiring the

signs/barricades begins.

D. Walkways, roadways and sidewalks shall be kept clear of building material, equipment, or

other obstructions caused by the Contractor operation. Protective barriers and warning signs

shall be installed.

3.06 PORTABLE HEATERS AND LIGHTING

A. All temporary heat that is provided by portable electric heaters must be approved by Factory

Mutual (FM) or Underwriters Laboratory (UL). Heaters shall be kept away from combustible or

flammable materials.

B. All extension cords used must be of sufficient gauge to operate heaters and lighting without

heating the cord or plug.

C. All unnecessary electrical appliances shall be unplugged at the end of the workday.

D. Only explosion proof electrical fixtures and appliances shall be used in areas where flammable

vapors are present.

3.07 FLAMMABLE AND COMBUSTIBLE LIQUIDS

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 4 of 6

A. All flammable liquids shall be stored in suitable metal containers only.

B. Store other flammable materials properly.

C. Gasoline or any other low flash point flammable liquid shall not be used for cleaning purposes

or to start fires.

D. Static bonding wires shall be properly attached before combustible or flammable liquid is

transferred from one vessel to another. This includes vehicles, portable gasoline driven

equipment, etc.

E. Smoking or the use of spark or flame producing equipment in areas where flammable liquids

are being used or stored is strictly prohibited.

3.08 FIRE EXTINGUISHERS: The Contractor is responsible for providing an adequate number of fire

extinguishers. Extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained

in a fully charged and operable condition.

3.09 HAZARD COMMUNICATION: In any contract where hazardous materials are involved, the

Contractor must comply with 29CFR 1910.1200, Hazard Communication. Contractors must provide 78

AMDS/SGPB the Material Safety Data Sheets (MSDSs) for each chemical used at least 5 working days

prior to start date. This includes, but is not limited to, all solvents, paints, adhesives, sealants, coatings,

primers, mastics, etc. MSDSs must be the most current available. MSDS’s are available for hazardous

materials that Contractor personnel may come into contact with on RAFB. Contact your Contracting

Officer for assistance.

3.10 CONFINED SPACE ENTRY: In recent years, there have been increased injuries and mishaps in

confined spaces. The Contractor assumes full responsibility for performing all work in and around a

confined space in a safe manner and IAW CFR 1910.146. Protect Robins Air Force Base and other

personnel by supplying barricades, warning signs, and traffic control measures as necessary.

3.11 INJURIES/MISHAP REPORTING: The Contractor shall report mishaps or incidents exceeding

$1,000 (material + labor) and all injuries to any personnel, including Contractor employees, within one

(1) hour by phone to the Contracting Officer during normal day shift hours. This report shall contain all

available facts. Mishaps/Incidents occurring at other times of the day shall be reported as soon as

possible the next normal workday. Immediately secure the mishap scene and damaged property, then

impound pertinent maintenance and training records until released through the Contracting Officer by the

WR-ALC Safety Office, whose sole function in such cases is to ensure the safety of Government property

and non-Contractor personnel.

3.12 MOTOR VEHICLES: The Contractor shall comply with AFI 91-207 regarding the use of safety

belts and other protective devices during vehicle operations while on Base. No vehicle shall be stopped,

parked, or left standing on any road or adjacent thereto or in any area in such a manner as to endanger

the vehicle, other vehicles, equipment, or personnel using or passing that road or area. Roads shall be

swept if spillage occurs during hauling. For chemical spills, see the Environmental Requirements section

of the specifications. Ensure safe operating condition of all Contractor-owned vehicles. Unsafe and

unserviceable vehicles shall be removed from service immediately. Personnel engaged in vehicle

operations on the Flightline and industrial areas shall be trained and certified in Flightline procedures by

78 OSS/OSAB at 926-2114. Schedule this training with adequate lead-time so as not to interfere with

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 5 of 6

contract schedules. Certification shall be annotated on AF Form 483, Certificate of Competency, and

must be in the possession of the vehicle operator when operating a vehicle on the Flightline or industrial

areas. Furnish a trained and certified vehicle operator/escort for all infrequent vehicle operations such as

material deliveries. The certified escort can be a passenger or operate a lead vehicle no further than three

(3) vehicle lengths in front of the escorted vehicle. Ensure that all Subcontractors comply with these

requirements.

3.13 EXCAVATIONS: In all excavations where any personnel may be exposed to danger from moving

ground, protection shall be provided by means of a shoring system, sloping of the ground, or some other

equivalent means. All trenches over five feet deep in either hard and compact or soft and unstable soil

shall be sloped, shored, sheeted braced or otherwise supported. Trenches less than five feet in depth shall

also be effectively protected when hazardous ground movement may be expected. Additional

information/requirements may be found in 29 CFR 1926 and EM 385-1-1.

3.14 PROTECTIVE BARRIERS/WARNING SIGNS: When it is necessary to barricade an area for

excavation, open manholes, overhead work, or the protection of personnel from hazardous operations,

moving equipment or cranes, barricades are to be provided by the Contractor. Barricades must be

erected before the work begins. If the barricades are in a roadway or walkway, blinking lights must be

used during the hours of darkness. Barricades and associated equipment shall be kept neat and orderly at

all times. When the work is complete, the barricades must be removed immediately from the job site.

Kerosene lamps and open flame pots shall not be used for or with warning signs or devices. Additional

information/requirements may be found in 29 CFR 1926 and EM 385-1-1. Provide as required safety

signs at job sites, such as MEN WORKING ABOVE, DO NOT WATCH WELDER, and NO

SMOKING.

3.15 PROTECTIVE EQUIPMENT: The Contractor is responsible for the use of appropriate personal

protective equipment by his and subcontractor employees and guests. The Government recommends

voluntary use of the standards in EM 385-1-1.

3.16 TOOLS AND EQUIPMENT

A. LADDERS/SCAFFOLDS: Use standard ladders that are structurally rigid, sound, equipped

with approved safety shoes, and free of cracks. Metal ladders shall not be used near or for

electric service. All ladders shall be tied off at the top and bottom as necessary. Special purpose

job ladders may be constructed if they are properly designed and built IAW 29 CFR 1926.

Scaffolds and platforms shall have handrails and toe boards. Additional information/requirements

may be found in EM 385-1-1.

B. HAND TOOLS/ELECTRICAL TOOLS, PNEUMATIC TOOLS/COMPRESSED AIR: The

Contractor is responsible for ensuring that all hand tools used by his or subcontractor personnel

are used IAW applicable safety standards, especially 29 CFR 1910 and 1926.

C. ELECTRICAL WIRING AND EQUIPMENT: All electrical wiring and equipment shall be a

type listed by UL or another recognized listing agent. All temporary electrical wiring shall be

adequately installed and placed to avoid physical damage from other operations and comply with

29 CFR 1926.405. Temporary wiring shall be removed immediately upon completion of

construction or the purpose for which the wiring was installed. All extension cords shall be of the

three-wire type and kept in a good state of repair. Splices shall be avoided, but if they are made,

they must comply with 29 CFR 1926.405. All portable electrical appliances and equipment shall

UHHZ160050 SAFETY REQUIREMENTS - 01580

SAFETY REQUIREMENTS

01580 - 6 of 6

be unplugged at the end of each workday. Only explosion-proof electrical fixtures and appliances

shall be used in areas where explosive vapors might be present. Additional

information/requirements may be found in EM 385-1-1.

3.17 CONTROL OF HAZARDOUS ENERGY (Lockout/Tagout): Authorized personnel shall ensure

the control of all hazardous energy (active or stored) when servicing and maintaining equipment or

machines. Power shall be disconnected and all energy isolating devices will be locked out and/or tagged

out before starting work. The authorized person will verify the isolation and deenergization.

3.18 FOREIGN OBJECT DAMAGE (FOD) PREVENTION FOR FLIGHTLINE PROJECTS: Air

Force aircraft are easily damaged by loose objects on the Flightline. When working or driving through

such areas, the Contractor shall establish and maintain an effective FOD prevention program. The

program must be followed as an integral part of the overall project execution to prevent damage from

construction-generated debris to aircraft operating near or within the construction area. Prevent the

spread of debris to areas outside of the construction site as well as controlling and removing debris within

the site as required by aircraft operations. Also, all vehicles must stop at FOD checkpoints. The vehicle

operator will visually inspect all tires (check the tire threads for rocks or other debris) to ensure all

trapped items between the tire threads are removed and disposed of properly to prevent the loose objects

from being carried onto the Flightline.

<<<<< END OF SECTION >>>>>

UHHZ160050 PRODUCT REQUIREMENTS - 01600

Product Requirements 01600 - 1 of 3

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Products.

B. Product delivery requirements.

C. Product storage and handling requirements.

D. Product options.

E. Product substitution procedures.

F. Equipment electrical characteristics and components.

1.2 PRODUCTS

A. Furnish products of qualified manufacturers suitable for intended use. Furnish products of

each type by single manufacturer unless specified otherwise.

1.3 PRODUCT DELIVERY REQUIREMENTS

A. Transport and handle products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure products comply with requirements, quantities are

correct, and products are undamaged.

C. Provide equipment and personnel to handle products by methods to prevent soiling,

disfigurement, or damage.

1.4 PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. Store and protect products in accordance with manufacturers' instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive products in weather tight, climate controlled, enclosures in an

environment favorable to product.

D. For exterior storage of fabricated products, place on sloped supports above ground.

E. Provide bonded off-site storage and protection when site does not permit on-site storage

or protection.

F. Cover products subject to deterioration with impervious sheet covering. Provide

ventilation to prevent condensation and degradation of products.

UHHZ160050 PRODUCT REQUIREMENTS - 01600

Product Requirements 01600 - 2 of 3

G. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing

with foreign matter.

H. Provide equipment and personnel to store products by methods to prevent soiling,

disfigurement, or damage.

I. Arrange storage of products to permit access for inspection. Periodically inspect to verify

products are undamaged and are maintained in acceptable condition.

1.5 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any product meeting

those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of one of

manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with Provision for

Substitutions: Submit request for substitution for any manufacturer not named in

accordance with the following article.

1.6 PRODUCT SUBSTITUTION PROCEDURES

A. Instructions to Bidders specify time restrictions for submitting requests for Substitutions

during bidding period to requirements specified in this section.

B. Substitutions may be considered when a product becomes unavailable through no fault of

Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that Bidder:

1. Has investigated proposed product and determined that it meets or exceeds quality

level of specified product.

2. Will provide same warranty for Substitution as for specified product.

3. Will coordinate installation and make changes to other Work that may be required

for the Work to be complete with no additional cost to Owner.

4. Waives claims for additional costs or time extension that may subsequently

become apparent.

5. Will reimburse Government for review or redesign services associated with re-

approval by authorities having jurisdiction.

E. Substitutions will not be considered when they are indicated or implied on Shop Drawing

or Product Data submittals, without separate written request, or when acceptance will

require revision to Contract Documents.

F. Substitution Submittal Procedure:

UHHZ160050 PRODUCT REQUIREMENTS - 01600

Product Requirements 01600 - 3 of 3

1. Submit three copies of request for Substitution for consideration. Limit each

request to one proposed Substitution.

2. Submit Shop Drawings, Product Data, and certified test results attesting to

proposed product equivalence. Burden of proof is on proposer.

3. Contracting Officer will notify Contractor in writing of decision to accept or

reject request.

PART 2 PRODUCTS

2.1 EQUIPMENT ELECTRICAL CHARACTERISTICS AND COMPONENTS

A. Wiring Terminations: Furnish terminal lugs to match branch circuit conductor quantities,

sizes, and materials indicated. Include lugs for terminal box.

PART 3 EXECUTION

Not Used.

<<<<<END OF SECTION>>>>>

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 1 of 6

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Closeout procedures.

B. Final cleaning.

C. Starting of systems.

D. Demonstration and instructions.

E. Testing, adjusting and balancing.

F. Protecting installed construction.

G. Project record documents.

H. Operation and maintenance data.

I. Manual for materials and finishes.

J. Manual for equipment and systems.

K. Spare parts and maintenance products.

L. Product warranties and product bonds.

M. Maintenance service.

1.2 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been

inspected, and that Work is complete in accordance with Contract Documents and ready

for Architect/Engineer's review.

B. Provide submittals to Contracting Officer required by authorities having jurisdiction.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous

payments, and sum remaining due.

D. Owner will occupy all portions of building as specified in Section 01100.

1.3 FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 2 of 6

B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels,

stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted

and soft surfaces.

C. Clean equipment and fixtures to sanitary condition with cleaning materials appropriate to

surface and material being cleaned.

D. Replace filters of operating equipment.

E. Clean debris from roofs, gutters, downspouts, and drainage systems.

F. Clean site; sweep paved areas, rake clean landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from site.

1.4 STARTING OF SYSTEMS

A. Coordinate schedule for start-up of various equipment and systems.

B. Notify Contracting Officer seven days prior to start-up of each item.

C. Verify each piece of equipment or system has been checked for proper lubrication, drive

rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify tests, meter readings, and specified electrical characteristics agree with those

required by equipment or system manufacturer.

E. Verify wiring and support components for equipment are complete and tested.

F. Execute start-up under supervision of applicable Contractors' personnel in accordance

with manufacturers' instructions.

G. When specified in individual specification Sections, require manufacturer to provide

authorized representative to be present at site to inspect, check, and approve equipment or

system installation prior to start-up, and to supervise placing equipment or system in

operation.

H. Submit a written report in accordance with Section 01300 that equipment or system has

been properly installed and is functioning correctly.

1.5 DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate operation and maintenance of products to RAFB maintenance personnel two

weeks prior to date of final inspection.

B. For equipment or systems requiring seasonal operation, perform demonstration for other

season within six months.

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 3 of 6

C. Utilize operation and maintenance manuals as basis for instruction. Review contents of

manual with Owner's personnel in detail to explain all aspects of operation and

maintenance.

D. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing,

maintenance, and shutdown of each item of equipment at agreed time at equipment

location.

E. Prepare and insert additional data in operations and maintenance manuals when need for

additional data becomes apparent during instruction.

F. Required instruction time for each item of equipment and system is specified in

individual sections.

1.6 TESTING, ADJUSTING AND BALANCING

A. Independent firm will perform services specified in Section 15950.

B. Reports will be submitted by independent firm to Contracting Officer indicating

observations and results of tests and indicating compliance or non-compliance with

requirements of Contract Documents.

1.7 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual

specification sections.

B. Provide temporary and removable protection for installed products. Control activity in

immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or

movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity

is necessary, obtain recommendations for protection from waterproofing or roofing

material manufacturer.

F. Prohibit traffic from landscaped areas.

1.8 PROJECT RECORD DOCUMENTS

A. Maintain on site one set of the following record documents; record actual revisions to the

Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 4 of 6

5. Reviewed Shop Drawings, Product Data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Contracting

Officer’s Representative.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record at each product section description of actual

products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual

construction including:

1. Measured depths of foundations in relation to finish [first] [main] floor datum.

2. Measured horizontal and vertical locations of underground utilities and

appurtenances, referenced to permanent surface improvements.

3. Measured locations of internal utilities and appurtenances concealed in

construction, referenced to visible and accessible features of the Work.

4. Field changes of dimension and detail.

5. Details not on original Contract drawings.

G. Submit documents to Contracting Officer with claim for final Application for Payment.

1.9 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11 inch text pages, three D side ring binders with durable

plastic covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project, and subject matter of binder when multiple binders

are required.

C. Internally subdivide binder contents with permanent page dividers, logically organized as

described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger

drawings to size of text pages.

1.10 MANUAL FOR EQUIPMENT AND SYSTEMS

A. Submit two copies of preliminary draft or proposed formats and outlines of contents

before start of Work. Architect/Engineer will review draft and return one copy with

comments.

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 5 of 6

B. For equipment, or component parts of equipment put into service during construction and

operated by Owner, submit documents within ten days after acceptance.

C. Submit one copy of completed volumes 15 days prior to final inspection. Draft copy be

reviewed and returned [after final inspection], with Architect/Engineer comments. Revise

content of document sets as required prior to final submission.

D. Submit two sets of revised final volumes in final form within 10 days after final

inspection.

E. Each Item of Equipment and Each System: Include description of unit or system, and

component parts. Identify function, normal operating characteristics, and limiting

conditions. Include performance curves, with engineering data and tests, and complete

nomenclature and model number of replaceable parts.

F. Panelboard Circuit Directories: Provide electrical service characteristics, controls, and

communications; typed.

G. Include color coded wiring diagrams as installed.

H. Operating Procedures: Include start-up, break-in, and routine normal operating

instructions and sequences. Include regulation, control, stopping, shut-down, and

emergency instructions. Include summer, winter, and special operating instructions.

I. Maintenance Requirements: Include routine procedures and guide for preventative

maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and

alignment, adjusting, balancing, and checking instructions.

J. Include servicing and lubrication schedule, and list of lubricants required.

K. Include manufacturer's printed operation and maintenance instructions.

L. Include sequence of operation by controls manufacturer.

M. Include original manufacturer's parts list, illustrations, assembly drawings, and diagrams

required for maintenance.

N. Include control diagrams by controls manufacturer as installed.

O. Include Contractor's coordination drawings, with color coded piping diagrams as

installed.

P. Include charts of valve tag numbers, with location and function of each valve, keyed to

flow and control diagrams.

Q. Include list of original manufacturer's spare parts, current prices, and recommended

quantities to be maintained in storage.

R. Include test and balancing reports as specified in Section 01400.

UHHZ160050 EXECUTION REQUIREMENTS – 01700

Execution Requirements 01700 - 6 of 6

S. Additional Requirements: As specified in individual product specification sections.

T. Include listing in Table of Contents for design data, with tabbed dividers and space for

insertion of data.

1.11 SPARE PARTS AND MAINTENANCE PRODUCTS

A. Furnish spare parts, maintenance, and extra products in quantities specified in individual

specification sections.

1.12 PRODUCT WARRANTIES AND PRODUCT BONDS

A. Obtain warranties and bonds executed in duplicate by responsible subcontractors,

suppliers, and manufacturers, within ten days after completion of applicable item of

work.

B. Execute and assemble transferable warranty documents and bonds from subcontractors,

suppliers, and manufacturers.

C. Verify documents are in proper form, contain full information, and are notarized.

D. Co-execute submittals when required.

E. Include Table of Contents and assemble in three D side ring binder with durable plastic

cover.

F. Submit prior to final Application for Payment.

G. Time Of Submittals:

1. For equipment or component parts of equipment put into service during

construction with Owner's permission, submit documents within ten days after

acceptance.

2. Make other submittals within ten days after Date of Substantial Completion, prior

to final Application for Payment.

3. For items of Work for which acceptance is delayed beyond Date of Substantial

Completion, submit within ten days after acceptance, listing date of acceptance as

beginning of warranty or bond period.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

<<<<<END OF SECTION>>>>>

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 1of 6

PART 1 GENERAL

1.01 NOT USED

1.02 SUBMITTALS:

A. GENERAL: Provide the following submittals in accordance with instructions found in Section

01300, Submittals and Contractor Furnished Items. The contractor may submit manufacturer’s

data in lieu of the required certificate of compliance if he desires. Manufacturer’s data is

required by the government if an “X” appears under the “Mfg. Data Required” column.

B. MATERIAL SUBMITTALS: Not required under this section.

C. OTHER SUBMITTALS: Provide the following submittals as required by the contract or as

directed by the Contracting Officer.

Inspector’s

Para # Description Date Required Checklist

1.51 Data Package As Directed ______

1.03 SUBMISSION OF OPERATION AND MAINTENANCE DATA:

A. Submit operation and maintenance (O&M) data which is specifically applicable to this contract

and a complete and concise depiction of the provided equipment or product. Data containing

extraneous information to be sorted through to find applicable instructions will not be accepted.

Present information in sufficient detail to clearly explain user O&M requirements at the system,

equipment, component, and subassembly level. Include an index preceding each submittal.

Submit in accordance with Section 01300, "Submittals."

B. Quantity: Unless specified otherwise in the AF Form 66, submit four copies of the

manufacturers' information specified herein for the components, assemblies, subassemblies,

attachments, and accessories. The items for which O&M data is required are listed in the

technical sections which specify that particular item.

C. Package Content: For each product, system, or piece of equipment requiring submission of

O&M data, submit the package required in the individual technical section. Package content

shall be as required in the paragraph herein entitled "Schedule of Operations and Maintenance

Data Packages."

1.3.3 Delivery:

Submit O&M data to the Contracting Officer for review and acceptance; submit data specified for a

given item within 30 calendar days after the item is delivered to the contract site.

1.3.4 Changes to Submittals

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 2of 6

Manufacturer-originated changes or revisions to submitted data shall be furnished by the Contractor

if a component of an item is so affected subsequent to acceptance of the O&M data. Changes,

additions, or revisions required by the Contracting Officer for final acceptance of submitted data,

shall be submitted by the Contractor within 30 calendar days of the notification of this change

requirement.

1.4 TYPES OF INFORMATION REQUIRED IN O&M DATA PACKAGES

1.4.1 Operating Instructions

Include specific instructions, procedures, and illustrations for the following phases of operation:

1.4.1.1 Safety Precautions

List personnel hazards and equipment or product safety precautions for all operating conditions.

1.4.1.2 Operator Prestart

Include requirements to set up and prepare each system for use.

1.4.1.3 Startup, Shutdown, and Postshutdown Procedures

Include a control sequence for each of these operations.

1.4.1.4 Normal Operations

Include control diagrams with data to explain operation and control of systems and specific

equipment.

1.4.1.5 Emergency Operations

Include emergency procedures for equipment malfunctions to permit a short period of continued

operation or to shut down the equipment to prevent further damage to systems and equipment.

Include emergency shutdown instructions for fire, explosion, spills, or other foreseeable

contingencies. Provide guidance on emergency operations of all utility systems including valve

locations and portions of systems controlled.

1.4.1.6 Operator Service Requirements

Include instructions for services to be performed by the operator such as lubrication, adjustments,

and inspection.

1.4.1.7 Environmental Conditions

Include a list of environmental conditions (temperature, humidity, and other relevant data) which are

best suited for each product or piece of equipment and describe conditions under which equipment

should not be allowed to run.

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 3of 6

1.4.2 Preventive Maintenance

Include the following information for preventive and scheduled maintenance to minimize corrective

maintenance and repair.

1.4.2.1 Lubrication Data

Include lubrication data, other than instructions for lubrication in accordance with paragraph entitled

"Operator Service Requirements":

a. A table showing recommended lubricants for specific temperature ranges and applications.

b. Charts with a schematic diagram of the equipment showing lubrication points, recommended

types and grades of lubricants, and capacities.

c. A lubrication schedule showing service interval frequency.

1.4.2.2 Preventive Maintenance Plan and Schedule

Include manufacturer's schedule for routine preventive maintenance, inspections, tests and

adjustments required to ensure proper and economical operation and to minimize corrective

maintenance and repair. Provide manufacturer's projection of preventive maintenance man-hours on

a daily, weekly, monthly, and annual basis including craft requirements by type of craft.

1.4.3 Corrective Maintenance

Include manufacturer's recommendations on procedures and instructions for correcting problems and

making repairs.

1.4.3.1 Troubleshooting Guides and Diagnostic Techniques

Include step-by-step procedures to promptly isolate the cause of typical malfunctions. Describe

clearly why the checkout is performed and what conditions are to be sought. Identify tests or

inspections and test equipment required to determine whether parts and equipment may be reused or

require replacement.

1.4.3.2 Wiring Diagrams and Control Diagrams

Wiring diagrams and control diagrams shall be point-to-point drawings of wiring and control circuits

including factory-field interfaces. Provide a complete and accurate depiction of the actual job

specific wiring and control work. On diagrams number electrical and electronic wiring and

pneumatic control tubing and the terminals for each type, identically to actual installation numbering.

1.4.3.3 Maintenance and Repair Procedures

Include instructions and list tools required to restore product or equipment to proper condition or

operating standards.

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 4of 6

1.4.3.4 Removal and Replacement Instructions

Include step-by-step procedures and list required tools and supplies for removal, replacement,

disassembly, and assembly of components, assemblies, subassemblies, accessories, and attachments.

Provide tolerances, dimensions, settings and adjustments required. Instructions shall include a

combination of text and illustrations.

1.4.3.5 Spare Parts and Supply Lists

Include lists of spare parts and supplies required for maintenance and repair to ensure continued

service or operation without unreasonable delays. Special consideration is required for facilities at

remote locations. List spare parts and supplies that have a long lead time to obtain.

1.4.3.6 Corrective Maintenance Man-Hours

Include manufacturer's projection of corrective maintenance man-hours including craft requirements

by type of craft. Corrective maintenance that requires participation of the equipment manufacturer

shall be identified and tabulated separately.

1.4.4 Appendices

Provide information required below and information not specified in the preceding paragraphs but

pertinent to the maintenance or operation of the product or equipment. Include the following:

1.4.4.1 Parts Identification

Provide identification and coverage for all parts of each component, assembly, subassembly, and

accessory of the end items subject to replacement. Include special hardware requirements, such as

requirement to use high-strength bolts and nuts. Identify parts by make, model, serial number, and

source of supply to allow reordering without further identification. Provide clear and legible

illustrations, drawings, and exploded views to enable easy identification of the items. When

illustrations omit the part numbers and description, both the illustrations and separate listing shall

show the index, reference, or key number which will cross-reference the illustrated part to the listed

part. Parts shown in the listings shall be grouped by components, assemblies, and subassemblies.

a. Manufacturer's Standard Commercial Practice: The parts data may cover more than

one model or series of equipment, components, assemblies, subassemblies,

attachments, or accessories, such as a master parts catalog, in accordance with the

manufacturer's standard commercial practice.

b. Other Than Manufacturer's Standard Commercial Practice: End item manufacturer may add a

cross-reference to implement components' assemblies and parts requirements when

implementation in manual form varies significantly from the style, format, and method of

manufacturer's standard commercial practice. Use the format in the following example:

End Item Actual

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 5of 6

Manufacturer's Manufacturer's Name Actual Manufacturer

Alphanumeric Sequence and FSCM Part No.

100001 John Doe & Co. 00000 2000002

1.4.4.2 Warranty Information

List and explain the various warranties and include the servicing and technical precautions prescribed

by the manufacturers or contract documents to keep warranties in force.

1.4.4.3 Personnel Training Requirements

Provide information available from the manufacturers to use in training designated personnel to

operate and maintain the equipment and systems properly.

1.4.4.4 Testing Equipment and Special Tool Information

Include information on test equipment required to perform specified tests and on special tools

needed for the operation, maintenance, and repair of components.

1.4.4.5 Contractor Information

Provide a list that includes the name, address, and telephone number of the General Contractor and

each subcontractor installing the product or equipment. Include local representatives and service

organizations most convenient to the project site. Provide the name, address, and telephone number

of the product or equipment manufacturers.

1.5 SCHEDULE OF OPERATION AND MAINTENANCE DATA PACKAGES

Furnish the O&M data packages specified in individual technical sections. The required information

for each O&M data package is as follows:

1.5.1 Data Package

a. Safety precautions

b. Normal operations

c. Emergency operations

d. Environmental conditions

e. Lubrication data

f. Preventive maintenance plan and schedule

g. Trouble shooting guides and diagnostic techniques

UHHZ160050 OPERATIONS AND MAINTENANCE DATA - 01730

OPERATIONS AND MAINTENANCE DATA

01730 - 6of 6

h. Wiring diagrams and control diagrams

i. Maintenance and repair procedures

j. Removal and replacement instructions

k. Spare parts and supply list

l. Parts identification

m. Warranty information

n. Testing equipment and special tool information

o. Contractor information

<<<<<END OF SECTION>>>>>