title of presentation goes here name of presenter location/date © 2005 mpa. all rights reserved....
TRANSCRIPT
Title of presentation goes here
Name of presenterLocation/date
© 2005 MPA. All rights reserved.
Task Management in MS ProjectGenea Mallow-Jensen
President, FrontRange MPAMarch 30, 2006
© 2005 MPA. All rights reserved.
FrontRange Colorado MPA
© 2005 MPA. All rights reserved.
Purpose
– To develop a strong foundational knowledge of MS Project
– To learn how to build project schedules utilizing Project Management and MS Project best practices
• Why?– Provide better more realistic schedules– Manage projects more effectively – Provide more accurate status reporting
© 2005 MPA. All rights reserved.
MS Project Overview
– Project Management Tools
– Inside MSP» YJTJ» Data Model
» Basic Task Skills» Task Information
© 2005 MPA. All rights reserved.
Your Job – Tool’s Job (YJTJ)
Information•Task Names
•Work/Effort
•Dependencies
•Constraints
•Resource Names
•etc
Scheduling•Start/Finish Dates
•Duration
•Critical Path
•Cost
•Remaining Work
•etc
© 2005 MPA. All rights reserved.
MS Project Overview
– Project Management Tools
– Inside MSP» YJTJ
» Data Model
» Basic Task Skills» Task Information
© 2005 MPA. All rights reserved.
MS Project Data Model
MS Project
TaskInformation
ResourceInformation
© 2005 MPA. All rights reserved.
MS Project Overview
– Project Management Tools
– Inside MSP» YJTJ» Data Model
» Basic Task Skills» Task Information
© 2005 MPA. All rights reserved.
– Templates
– Initiate Schedule
– Customizing Template
Basic Task Skills
© 2005 MPA. All rights reserved.
Templates
– Provide basic project structure
– Promote standardization
– Encourage best practices
– Contain process
– Are customizable
– Save time
Project
Template
© 2005 MPA. All rights reserved.
– Set Project Start Date
– Set Project Calendar
– Show Project Summary Row
– Save
Initiate Schedule
© 2005 MPA. All rights reserved.
– Add/Delete Tasks
– Rearrange Tasks
– Edit Tasks
Customize Schedule
© 2005 MPA. All rights reserved.
MS Project Overview
– Project Management Tools
– Inside MSP» YJTJ» Data Model» Basic Task Skills
» Task Information
© 2005 MPA. All rights reserved.
Task Cost
– Sources– Variable (Labor, Equipment, Materials)
– Fixed Cost
– Estimated, Actual, and Remaining
– Roll up to summaries
© 2005 MPA. All rights reserved.
Tools Change Working Time
– Overrides Resource and Project Calendars
– Typical uses– Outside normal work hours– Must occur on a particular day of
the week or time of day
Task Calendar
© 2005 MPA. All rights reserved.
Working with Tasks in MS Project
– Defining the work to be done- WBS
– Schedule Structure
– Schedule Development- Milestones- Dependencies- Constraints
© 2005 MPA. All rights reserved.
WBS - Work Breakdown Structure
Project
Phases
Deliverables
Tasks/Activities
Methods• Top Down -
decompose• Bottom Up -
categorize
© 2005 MPA. All rights reserved.
Working with Tasks in MS Project
– Defining the work to be done- WBS
– Schedule Structure
– Schedule Development- Milestones- Dependencies- Constraints
© 2005 MPA. All rights reserved.
Working with Tasks in MS Project
– Defining the work to be done- WBS
– Schedule Structure
– Schedule Development- Types of tasks- Dependencies- Constraints
© 2005 MPA. All rights reserved.
Milestones
– Significant point in time
– Have no duration
– Are used to monitor project progress
– Represent external events
– Are part of activity sequencing
– Used to represent deadlines
© 2005 MPA. All rights reserved.
Recurring Tasks
– Typically non-deliverable
– Use project resources
– Project related cost
– Date constrained
© 2005 MPA. All rights reserved.
MSP Dependencies
– FS (Finish-to-Start): the Predecessor task must be completed in order for the Successor task to begin.
– SS (Start-to-Start): the Predecessor task must start in order for the Successor task to start.
– FF (Finish-to-Finish): the Predecessor task must finish in order for the Successor task to finish.
– SF (Start-to-Finish): the Predecessor task must start in order for the Successor task to finish.
B
A
B
A
B
A
B
A
© 2005 MPA. All rights reserved.
MSP Constraints and Deadlines
ConstraintsReasons
– Mandatory
– Discretionary
Types
– Flexible
– Inflexible
DeadlinesInternally imposed target dates