CALTRANS BAY AREA TOLL AUTHORITY CALIFORNIA TRANSPORTATION COMMISSION

TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEEAMEETING M TERIALS

November 4, 2014

Page 2: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

   Letter of Transmittal

       

  

TO:  Toll Bridge Program Oversight Committee (TBPOC) 

DATE: October 28, 2014 

FR:  Program Management Team (PMT)   

RE:  TBPOC Meeting Materials Packet – November 4, 2014 

   Herewith is the TBPOC Meeting Materials Packet for the November 4th meeting.  The packet 

includes  memoranda  and  reports  that  will  be  presented  at  the  meeting.      A  Table  of 

Contents is provided following the Agenda to help locate specific topics.   

 

   

   

            

Page 3: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Final Agenda

TBPOC REGULAR MEETING November 4, 2014

Executive Session: 1:00pm – 2:00pm Regular Session: 2:00pm – 4:00pm

1120 N Street, Conference Room 2116, Sacramento, CA Item Number/ Topic

Presenter Time Desired

Outcome

1. EXECUTIVE SESSION a. Self-Anchored Suspension (SAS) Span Contract

Change Order (CCO) 150-S2 Final (Install BASE cameras on Piers W2 and E2, on tower base (T1), and at bike path belvedere at Panel Point 117)

b. 504/ 288 Addendum Follow-Up

2. CHAIR’S REPORT

S. Heminger, BATA Information

3. CONSENT CALENDAR a. TBPOC Regular/ Urgent Meeting Minutes

1. TBPOC September 30, 2014 Minutes* 2. TBPOC October 15, 2014 Minutes*

A. Fremier, BATA

Approval

4. PROGRESS REPORTS a. Capital Outlay Support (COS) Third Quarter 2014

Update*

b. Risk Management Third Quarter 2014 Update*

c. 2014 Third Quarter Project Progress and Financial Update**

A. Banani, CT

R. Foley, CT

A. Fremier, BATA

20 min

20 min

10 min

Information

Information

Approval

5. SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. SAS Update

1. SFOBB Self-Anchored Suspension Bridge Evaluation of the ASTM 354 Grade BD Rods Report**

2. Tower Base Update**

b. Bridge Information Model (BrIM) Update*

S. Heminger, BATA

B. Casey, CT B. Maroney, CT

B. Maroney, CT

M. Whiteside, CT K. Brown, CT

30 min

15 min

15 min

Approval

Information

Approval

6. OTHER BUSINESS a. Report on matters discussed and actions taken at

Urgent Meeting

NA

NA

NA

Page 4: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Item Number/ Topic

Presenter Time Desired Outcome

b. Report on matters discussed and actions taken during Executive Session

S. Heminger, BATA

5 min

Information

7. GENERAL PUBLIC COMMENT

Next TBPOC Regular Meeting: December 3, 2014, 10:00am – 1:00pm, Oakland, CA

* Attachments **Attachments to be sent under separate cover

Accessibility and Title VI: TBPOC provides services/accommodations upon request to persons with disabilities and individuals who are limited-English proficient who wish to address Committee matters. For accommodations or translations assistance, please call the Metropolitan Transportation Commission (MTC) at 510.817.5757 or 510.817.5769 for TDD/TTY. We require three working days' notice to accommodate your request.

Acceso y el Titulo VI: El TBPOC puede proveer asistencia/facilitar la comunicacion a las personas discapacitadas y los individuos con conocimiento limitado del ingles quienes quieran dirigirse a la Comité. Para solicitar asistencia, por favor llame a la Comisiớn Metropolitano de Transporte (MTC) al numero 510.817.5757 o al 510.817.5769 para TDD/TTY. Requerimos que solicite asistencia con tres dias habiles de anticipacion para poderle proveer asistencia. Meeting Conduct: In the event that any public meeting conducted by TBPOC is willfully interrupted or disrupted by a person or by a group or groups of persons so as to render the orderly conduct of the meeting unfeasible, the Chair may order the removal of those individuals who are willfully disrupting the meeting. Such individuals may be subject to arrest. If order cannot be restored by such removal, the members of the committee may direct that the meeting room be cleared (except for representatives of the press or other news media not participating in the disturbance), and the session may continue on matters appearing on the agenda.

Page 5: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Table of Contents

TBPOC MEETING November 4, 2014

INDEX TAB

AGENDA ITEM

DESCRIPTION

1 1 EXECUTIVE SESSION a. Self-Anchored Suspension (SAS) Span Contract Change

Order (CCO) 150-S2 Final (Install BASE cameras on Piers W2 and E2, on tower base (T1), and at bike path belvedere at Panel Point 117)

b. 504/288 Addendum Follow-Up

2 2 CHAIR’S REPORT

3 3 CONSENT CALENDAR a. TBPOC Regular/Urgent Meeting Minutes

1. TBPOC September 30, 2014 Minutes* 2. TBPOC October 15, 2014 Minutes

4 4 PROGRESS REPORTS

a. Capital Outlay Support (COS) Third Quarter 2014 Update*

b. Risk Management Third Quarter 2014 Update *

c. 2014 Third Quarter Project Progress and Financial Update**

5 5 SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES

a. SAS Update 1. SFOBB Self-Anchored Suspension Bridge Evaluation

of the ASTM 354 Grade BD Rods Report** 2. Tower Base Update**

b. Bridge Information Model (BrIM) Update *

6 6 OTHER BUSINESS

a. Report on matters discussed and actions taken at Urgent Meeting

b. Report on matters discussed and actions taken during Executive Session

7 7 GENERAL PUBLIC COMMENT

* Attachments ** Attachments to be sent out under separate cover

Page 6: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 1: EXECUTIVE SESSION

a. Self-Anchored Suspension Span (SAS) Contract Change Order (CCO) 150-S2 Final (Install BASE cameras on Piers W2 and E2, on tower base (T1), and at bike path belvedere at Panel Point 117)

b. 504/288 Addendum Follow-Up

Page 7: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 2:  CHAIR’S REPORT   

Page 8: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

   Memorandum

1 of 1   Item3a1_TBPOC_093014_MtgMin_memo_04Nov14 

TO:  Toll Bridge Program Oversight Committee (TBPOC) 

DATE:  October 28, 2014 

FR:  Andrew Fremier, Deputy Executive Director, Operations, MTC/ BATA 

RE:  Agenda No. ‐  3a1  

Item‐ Consent Calendar TBPOC Regular/Urgent Meeting Minutes TBPOC September 30, 2014 Minutes 

 Recommendation:    APPROVAL  Cost:     NA         Schedule Impacts:     NA   Discussion: The Program Management Team has reviewed and requests TBPOC approval of the September 30, 2014 Regular Meeting Minutes.   Attachment(s):  September 30, 2014 Regular Meeting Minutes 

Page 9: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Attend

Convene

1.

2.

3.

ees: TBPO Andre PMT

ParticDiFraMcElDean

Lori FJV); FAlan

ed: 11:10 AM EXECUTa. Public

b. SFOBB

Contra

CHAIR’S• NA

CONSENa. TBPO

Minut1. TB2. TB

b. 2015 T

TBPS

OC Membere Boutros Members: cipants: Adancia, Rich hinney, Le

nna VilcheckFogarty (OMFastener, MPense, Her M Items

TIVE SESS Information

B 504’ and 2act Addendu

S REPORT

NT CALENC Regular/

tes BPOC SepteBPOC Augu

TBPOC Mee

POC REGUeptember 3

325 Bu

rs: Steve H

Tony Anzide Akinsany Foley, Ted eah Robinsok MCA); John

Materials & rbert E. Tow

SION n Program

288’ Spans Dum Items

T

NDAR /Urgent Me

ember 15, 20st 28, 2014

eting Calen

ULAR MEE30, 2014, 11rma Road,

1 of 5

eminger (C

iano, Andreya, Ali Bana Hall, Beatron-Leach, B

n W. FisherCorrosion S

wnsend, Lou

Dismantling

eeting

014 Minute4 Minutes

ndar

ETING M1:00am – 1: Oakland CA

Item

Chair), Malc

ew Fremierani, Karin Briz Lacson, Bijan Sartip

r (TBSSRP)Specialty Cuis Raymon

• Theadd288an milcap

es

• TheCon

INUTES :00pm A

m3a1_TBPOC_

colm Dough

r, Stephen MBetts, Bill C Peter Lee, pi, Trish Sto

); Marwan NConsultants:nd, Douglas

Acti

e TBPOC Adendum to 8’ Spans Dismamount nollion for prepital outlay

e TBPOC Ansent Calen

093014_MtgM

herty,

Maller Casey, MichBrian Maro

oops, Ken T

Nader (TY L: Jeffrey Gos Williams

ion

APPROVED the SFOBBmantling Cot to exceed esented item support co

APPROVEDndar, as pre

Min_04Nov14

hele oney, Dan Terpstra,

Lin/MN orman,

D an B 504’ and ontract in $3 ms, plus st.

D the esented.

Page 10: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

(Continued)

2 of 5

Item3a1_TBPOC_093014_MtgMin_04Nov14

Items Action 4. PROGRAM ISSUES

a. Bay Bridge Salvage Agreement • A. Fremier, Deputy Executive Director,

BATA, provided a brief update on the TBPOC direction to develop an agreement with the Oakland Museum of California (OMCA), and requested TBPOC approval to allocate $4.3 million for the Bay Bridge Steel Creative Reuse Program, to cover the capital and capital outlay support costs to salvage 600 tons of bridge steel, as well as OMCA administration.

o L. Fogarty, Executive Director of the OMCA, summarized the selection process as open, rigorous and detailed, would avail of outside expertise, would focus on public projects in California, be administered in two phases within a two-year timeframe. She noted that OMCA would work closely with the Department and ensure that the visual characteristics of the bridge are retained, per the MOA.

o Discussion items included: cost estimate; timeframe alignment with demolition project schedule; steel storage and transport; working with a reduced budget for a lesser amount of steel.

b. TBSRP Capital Outlay Support (COS) Update

• A. Banani presented a Capital Outlay Support (COS) Update covering FY 14/15 Budget vs. Expenditure and FY 14/15 Unbudgeted Additional Work.

• Discussion items included: requested quarterly COS updates; reformatting presentations to reflect year-to-date amounts; minimizing cost of delays and unbudgeted work.

• The TBPOC APPROVED a

budget in an amount not to exceed $2.2 million for the Bay Bridge Steel Creative Reuse Program.

• A. Banani to give a 3rd Quarter COS

update at the TBPOC November 4, 2014 meeting. Delays and unbudgeted work presented to be accompanied by a PMT-developed plan on how to mitigate increasing costs.

5. SAN FRANCISCO-OAKLAND BAY BRIDGE UPDATES a. SAS Update

Page 11: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

(Continued)

3 of 5

Item3a1_TBPOC_093014_MtgMin_04Nov14

Items Action 1. A354 Grade BD High Strength Steel

Rods Testing Update • B. Maroney, Deputy Program

Manager, Caltrans, reported that a final report, “San Francisco-Oakland Bay Bridge, Self-Anchored Suspension Bridge, Evaluation of the ASTM A354 Grade BD Rods”, has been provided to the TBPOC and public covering the results of the testing program effort which was carried out with the help of the best and brightest experts, some of whom are present today.

The Chair and Caltrans Director M. Dougherty indicated that the report is now open to public review.

A. Fremier noted that Toll Bridge Seismic Safety Peer Review Panel (TBSSPRP) opinion on the report is requested prior to the TBPOC November 4, 2014 meeting.

• A. Pense of the Team of Fastener, Materials & Corrosion Specialty Consultants—with assistance from colleagues H. E. Townsend/J. Gorman, and Designer of Record, M. Nader—presented on the A354BD Rods Testing Program Conclusions and Recommendations.

o Discussion items included: phase two of Gorman Test, the only test still in progress (scheduled to complete March 2015); working with the ASTM to modify A354BD specification on toughness.

• B. Casey gave a slide presentation on the water recently observed at the base of tower shaft near a number of A354BD anchor rods.

Not a stress corrosion cracking issue; may lead to long-term corrosion if water is allowed to

• Staff to post the report “San Francisco-Oakland Bay Bridge, Self-Anchored Suspension Bridge, Evaluation of the ASTM A354 Grade BD Rods” to the project website today.

• TBPOC to provide an update of

their 2013 report at their November 4, 2014 meeting, and take action on accepting the final report presented today.

Page 12: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

(Continued)

4 of 5

Item3a1_TBPOC_093014_MtgMin_04Nov14

Items Action stand—a maintenance issue; in process of removing water and dehumidifying.

Source and level of water being investigated.

• The Chair thanked the team members for their work and public spiritedness, and extended the Committee’s appreciation for their efforts to extend the life of our bridge.

6.

OTHER BUSINESS a. Report on matters discussed and actions

taken at Urgent Meeting • NA

b. Report on matters discussed and actions

taken during Executive Session • The Chair reported that the TBPOC

approved Item 1b above at the Executive Session.

Next TBPOC Meeting • The next TBPOC regular meeting is on

November 4, 2014, 1:00pm – 4:00pm, in Sacramento.

7. GENERAL PUBLIC COMMENT • D. R. Darr of Analatom, Inc. gave a brief

introduction to Analatom’s Structural Health Monitoring technology related to detection, monitoring, and recording environmental conditions known to cause stress corrosion cracking.

• D. Grieshaber of the Bay Bridge House Project inquired as to when they might receive a response to their organization’s formal request for Bay Bridge steel and concrete for their proposed project.

• G. DeMar inquired as to when a report

• Staff via OMCA to provide a response to Bay Bridge House and other interested parties as part of the agreement and process approved today.

• Staff to obtain from the TBSSPRP

Page 13: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

(Continued)

5 of 5

Item3a1_TBPOC_093014_MtgMin_04Nov14

Items Action on the solution to the misaligned main cable rod problem (clearances of anchor rods) would be forthcoming.

a written letter on the 2-mm clearance requirement for anchor rods by the TBPOC November 4, 2014 meeting.

Adjourned: 1:24 PM

TBPOC REGULAR MEETING MINUTES September 30, 2014, 11:00am – 1:00pm

APPROVED BY: ______________________________________ ______________ STEVE HEMINGER, TBPOC Chair Date Executive Director, Bay Area Toll Authority ______________________________________ ______________ ANDRE BOUTROS Date Executive Director, California Transportation Commission ______________________________________ ______________ MALCOLM DOUGHERTY Date Director, California Department of Transportation

Page 14: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

   Memorandum

1 of 1   Item3a2_TBPOC_101514_CCMin_memo_04Nov14 

TO:  Toll Bridge Program Oversight Committee (TBPOC) 

DATE:  October 28, 2014 

FR:  Andrew Fremier, Deputy Executive Director, Operations, MTC/ BATA 

RE:  Agenda No. ‐  3a2  

Item‐ Consent Calendar TBPOC Regular/Urgent Meeting Minutes TBPOC October 15, 2014 Minutes 

 Recommendation:    APPROVAL  Cost:     NA         Schedule Impacts:     NA   Discussion: The Program Management Team has reviewed and requests TBPOC approval of the October 15, 2014 Urgent Meeting Minutes.   Attachment(s):  October 15, 2014 Urgent Meeting Minutes 

Page 15: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Attend

Convene

1.

2.

3.

6.

Adjourn

ees: TBPO Andre PMT

ParticMaro

ed: 4:53 PM

EXECUTa. Tower

b. SFOB

(SAS) 354 G

CHAIR’S• NA

OTHER a. Repor

taken • NA

b. Repor

taken • The Ch

above taken.

Next TBP• The ne

NovemSacram

GENERA• No pu

ed: 4:54 PM

TBP

OC Membere Boutros Members: cipants: Bi

oney, Bijan M Items

TIVE SESSr Rod Inspe

B Self-Anch Bridge Evarade BD Ro

S REPORT

BUSINESrt on matter at Urgent M

rt on matter during Exehair report were discu.

POC Meetinext TBPOC mber 4, 201mento.

AL PUBLIublic comme

M

POC URGOctober 15

rs: Steve H

Tony Anzill Casey, JoSartipi

SION ection Upda

hored Suspaluation of tods

T

SS rs discussedMeeting

rs discussedecutive Sessed that Item

ussed but no

ng regular me

14, 1:00pm

IC COMMEents receive

GENT MEE5, 2014, 4:4

1 of 2

eminger (C

iano, Andreohn Goodm

ate

ension the ASTM

d and action

d and actionsion ms 1a and 1o action wa

eeting is on – 4:00pm,

ENT ed.

ETING MI45pm – 5:0

Ite

Chair), Malc

ew Fremierman, Beatriz

ns

ns

1b as

n ,

INUTES 0pm

em3a2_TBPOC

colm Dough

r z Lacson, Pe

Acti

C_101514_CCM

herty,

eter Lee, Br

ion

Min_04Nov14

rian

Page 16: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

(Continued)

2 of 2

Item3a2_TBPOC_101514_CCMin_04Nov14

TBPOC URGENT MEETING MINUTES October 15, 2014, 4:45pm – 5:00pm

APPROVED BY: ______________________________________ ______________ STEVE HEMINGER, TBPOC Chair Date Executive Director, Bay Area Toll Authority ______________________________________ ______________ ANDRE BOUTROS Date Executive Director, California Transportation Commission ______________________________________ ______________ MALCOLM DOUGHERTY Date Director, California Department of Transportation

Page 17: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

   Memorandum

1 of 1       Item4a_COS Update_04Nov14 

TO:  Toll Bridge Program Oversight Committee (TBPOC) 

DATE:  October 28, 2014 

FR:  Ali Banani, COS Project Controls Manager, Caltrans 

RE:  Agenda No. ‐  4a  

Item‐ Progress Reports Capital Outlay Support (COS) Third Quarter 2014 Update, 

 Recommendation:   For Information Only  Cost:   NA     Schedule Impacts:   NA   Discussion:  A  capital outlay  support  (COS) update will be provided  at  the TBPOC November  4, 2014 meeting.    Attached  is  a  copy  of  the  presentation  “Capital  Outlay  Support  (COS)  Update, November 2014”.    Attachment(s): Capital Outlay Support (COS) Update, November 2014           

Page 18: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Toll Bridge Seismic Retrofit Program

Capital Outlay Support (COS) UpdateNovember 2014

Page 19: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

0

15

30

45

60

75

90

July Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

FY 14/15 Forecast

FY Budget Expenditures Thru Sept/2014

FY Forecast Budget Variance

SFOBB $ 38.4 M $14.0 M $ 49.0 M $10.6 MDumbarton

Public Access Road0 $ 0.4 M $ 0.8 M $ 0.8 M

Total $ 38.4 M $ 14.4 M $ 49.8 M $11.4 M

$M

Forecast: $49.8 MBudget: $38.4 M

Page 20: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

FY 14/15 Expenditure Analysis

Category BudgetFY Expenditures*

Thru Sept 2014FY Forecast Budget Variance

State Staff $18.8 M $6.2 M $ 24.5 M $ 5.7 M**

TY Lin/MN Str. Design $4.2 M $2.4 M $ 6.0 M $ 1.8 M

TY Lin Dismantling $2.5 M $0.7M $ 2.5 M 0

METS (Alta Vista) $5.0 M $2.0 M $5.0 M 0

A/E Others $7.9 M $3.1 M $11.8 M $ 3.9 M

Total $ 38.4 M $ 14.4 M $ 49.8 M $ 11.4 M

Expenditure Composition

State Staff, 43%

TY Lin/MN Str. Design, 

17%Ty Lin Dismantling, 

5%

METS (AltaVista), 

16%

A/E Others, 22%

* Expenditures are an estimate based on A/Einvoices and late time sheets for services performed thru Sept 2014.

** Reduction of 26 PYs by January 1, 2015 is requiredto address the state staff overrun cost.

Page 21: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

• Salary raises, Indirect cost rate increase and other adjustments … $1.70

• CM/GC Contract (executed in August) ……………………………… $0.95

• Dumbarton Public Access Road …………………………………….. $0.80

• Four months delay in contract completion for SAS ………………… $3.50

• Three Months delay in contract completion for OTD2 ……………… $1.00

• New Geotechnical Engineering Contract …………………………… $0.60

• Six months delay in the start of 504/288 dismantling ……………… - $4.00

• TY Lin Added Work ………………………………………………….. $1.80- Review Submittal for tower base- Maintenance Manual for YBI & OTD- Corrosion Specialist effort

Total …………… $ 6.35

FY 14/15 Unbudgeted Additional Work (in Millions)

Page 22: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

East Span Construction Schedule

2011 2012 2013 2014 2015 2016 2017 2018 2019

SAS

YBITS #2

YBI Landscape

OTD #2 Eastbound

504/288 Superstructure Dismantling

Marine Foundation Removal

RiskSeismic Safety Opening

8/28/2013

September 2014April 2014

Page 23: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

6

East Span CO & COS Cash Flow

Page 24: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

   Memorandum

1 of 1       Item4b_TBPOC Briefing_3Qtr14 RM_memo_04Nov14 

TO:  Toll Bridge Program Oversight Committee (TBPOC) 

DATE:  October 28, 2014 

FR:  Rich Foley, Risk Manager, Caltrans 

RE:  Agenda No. ‐  4b  

Item‐ Progress Reports Risk Management Third Quarter 2014 Update 

 Recommendation:   For Information Only  Cost:   NA     Schedule Impacts:   NA   Discussion:  A Risk Management third quarter 2014 update will be presented at the TBPOC November 4 meeting.  Attached is a copy of the presentation, “TBPOC Briefing, Risk Management Results Third Quarter 2014”.      Attachment(s): TBPOC Briefing, Risk Management Results Third Quarter 2014           

Page 25: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

TBPOC BriefingRisk Management Results

Third Quarter 2014

Page 26: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Summary Of Q3 Changes

$10 Million Increase in Total Draw this Quarter*

• $17 million Increase in Capital Outlay Forecast1. $13.1M increase in SAS Contract2. $7.3M Right of Way3. Misc. Increase/Decrease to other Contracts

• $6.5M Decrease in Capitol Outlay Risk*1. $8.3M Decrease in SAS Risk2. $16M Increase – 504/288 Delays to Bid Opening/Schedule and Foundations

• $19.6 million Increase in Capital Outlay Support Forecast*1. $17.7m – Antioch & Dumbarton Reserves moved to Program Contingency

• $45.7 million transferred to Program Contingency1. Antioch & Dumbarton Project Reserves – $25.3M2. Antioch & Dumbarton Capitol Outlay Support (COS) Reserves - $17.7M

* COS NUMBERS SUBJECT TO CHANGE OVER NEXT FEW WEEKS

Page 27: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Q3 RMC Results

Q3 2014 Q2 2014 Change % ChangeMarine Structures Dismantling 26,526,000 26,526,000 0 0504' & 288' Steel Structures Dismantling 70,197,000 55,122,000 15,075,000 27Cantilever Dismantling 6,557,000 13,750,000 (7,193,000) (52)OTD2 Eastbound 2,922,000 3,487,000 (565,000) (16)OTD Detour 75,000 75,000 0 0Self‐Anchor Suspension 19,072,000 27,431,000 (8,359,000) (30)YBI#1 Mainline Structures 1,167,000 1,167,000 0 0YBI#2 Post Traffic Switch 39,104,000 42,302,000 (3,198,000) (8)Total East Span 165,620,000 169,860,000 (4,240,000) (2)Program‐level risks (not in a contract) 9,392,000 11,659,000 (2,267,000) (19)Total Capital Outlay Risk 175,012,000 181,519,000 (6,507,000) (4)COS Risks 39,900,000 20,300,000 19,600,000 97Total Risk 214,912,000 201,819,000 13,093,000 6Draw on Program Contingency 170,912,000 115,519,000 55,393,000 48

Contract Contingency 44,000,000 86,300,000 (42,300,000)Program Contingency Balance 135,210,000 89,510,000 45,700,000Total Contingency 179,210,000 175,810,000 3,400,000

50% Probable Risk Management Cost

COS NUMBERS SUBJECT TO CHANGE OVER THE NEXT FEW WEEKS

Page 28: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

COS Changes

Q3 2014 Q2 2014 ChangeSAS 14.2 11.9 2.3YBI Detour 0.0 0.0 0.0YBITS #1 0.0 0.0 0.0YBITS #2 7.3 8.8 (1.5)OTD #2 5.7 4.0 1.7OTD Detour 0.3 0.2 0.1Program‐level 7.6 8.5 (0.9)Demolition 4.5 4.3 0.2Total East Span 39.6 37.7 1.9West Approach 0.3 0.3 0.0Antioch (7.2) 7.2Dumbarton (10.5) 10.5Total COS Risk 39.9 20.3 19.6

* COS Cost Differential is measured from the current COS Budget

Contract50% Probable COS Differential ($M)

COS NUMBERS SUBJECT TO CHANGE OVER THE NEXT FEW WEEKS

Page 29: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Q3 Draw

POTENTIAL DRAW SUBJECTTO CHANGE AS A RESULT OF EXPECTED COS CHANGES

Page 30: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

50% Probable Risk vs. Remaining Contingency

50% Probable 

Risk

Remaining Contract 

Contingency

Draw on Program 

ContingencyOTD1 Westbound 0E2/T1 0SSD 0Stormwater 0 1.0 ‐1.0West Approach 0 12.6 ‐12.6Submarine Cable 0 0.0Antioch 0 0.0Dumbarton 0 0.0

Completed Projects 0 13.6 ‐13.6OTD2 Eastbound 2.9 0.1 2.8OTD Detour 0.1 0.7 ‐0.6Self‐Anchor Suspension 19.0 5.6 13.4YBI#1 Mainline Structures 1.2 3.9 ‐2.7YBI#2 Post Traffic Switch 39.1 7.2 31.9YBI#3 0.0 1.2 ‐1.2

East Span Total 62.3 18.7 43.6Program‐level  risks  (not in a contract) 9.4 0.0 9.4COS Risks 39.9 0.0 39.9Right‐of‐way and Mitigation 3.4 ‐3.4

Program‐wide 49.3 3.4 45.9Marine Structures  Dismantling 26.5 ‐0.1 26.6504' & 288' Steel  Structures  Dismantl ing 70.2 ‐0.1 70.3Cantilever Dismantling 6.6 8.5 ‐1.9

Demolition Total 103.3 8.3 95.0

Totals 214.9 44.0 170.9

135.2Program Contingency Balance

DRAW ON PROGRAM SUBJECT TO CHANGE AS A RESULT OF EXPECTED COS CHANGES

Page 31: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Challenge Going Forward

• Project close-out - YBITS1 & OTD2 (Near Term) & SAS• Environmental Risks Continue to Increase Based on Communication

with National and State Agencies• Some opportunities for cost mitigation include:

1. Eliminate the risk related to cost estimate uncertainty of 504/288 and Marine Foundations contracts if bids come in under the estimates.

2. Obtain Concurrence to Leave Foundations – E2 & E19-E22

Page 32: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Project Risk Management

Page 33: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 4: PROGRESS REPORTS c. 2014 Third Quarter Project Progress and

Financial Update

(memo forthcoming)

Page 34: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 5: SFOBB UPDATES a. SAS Update

1. SFOBB Self-Anchored Suspension Bridge Evaluation of the ASTM 354 Grade BD Rods Report

2. Tower Base Update

(memos forthcoming)

Page 35: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

Memorandum

TO: Toll Bridge Program Oversight Committee (TBPOC)

DATE: October 28, 2014

FR: Brian Maroney, Deputy Program Manager, Caltrans Mike Whiteside, Structure Specifications Manager, Caltrans Ken Brown, Chief Structures Maintenance – Toll Bridges, Caltrans

RE: Agenda No. - 5b Item- San Francisco-Oakland Bay Bridge (SFOBB) Updates

Bridge Information Model (BrIM) DB Pilot Program Update

Recommendation: APPROVAL Staff is requesting that the TBPOC approve/ endorse the attached BRIM Pilot Program proposal for submittal to the BATA/ Caltrans Rehab Program for potential funding and implementation. Cost Impact: N/A Schedule Impact: N/A Discussion: At the March 13, 2014 TBPOC meeting, Brian Maroney and Mike Whiteside presented a proposal for the development of a pilot project for BrIM Database for the SFOBB Corridor. The TBPOC expressed interest in the proposal and requested additional clarification regarding potential cost advantages of using a BrIM database on bridge lifecycle maintenance and rehabilitation costs. An estimate has been developed for the purposes of this proposal to evaluate costs for future maintenance and rehabilitation of the New East Spans for its 150 year design life with and without a BrIM database. The use of a BrIM database for the lifecycle maintenance and rehabilitation of the New East Spans will result in a net cost advantage of $300M - $350M in 2014 dollars. It is strongly recommended that a pilot project for a BrIM Database for the SFOBB New East Spans be implemented on an immediate basis. Time is of the essence. A delay in the development of BrIM Database for this lifeline bridge would only increase

1 of 2 Item5b_BrIM Update_04Nov14_R4.docx

Page 36: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

the risk of loss of valuable design and construction information that may have to be regenerated in the future at significant additional costs, if even possible. Immediate implementation of the pilot project will allow for the consolidation and preservation of design and construction information for the SFOBB New East Spans that history has shown to be vulnerable to loss.

It is further recommended that a special purpose 3D BrIM database (BrIM Database) be developed as the pilot project for the SFOBB New East Spans. The BrIM model for this database will capture the entire New East Spans in complete as-built geometry with block level detail for all concrete and steel components. All structural elements of the New East Spans that are designed to take damage and are expected to require repairs after a design level earthquake will be modeled in complete as-built detail. A database for design drawings, structural & strength properties, and as-built shop drawings for the aforementioned elements of the New East Spans will be integrated into the BrIM model.

The schedule for completion of this effort is 24 months. A funding of $10M is hereby requested from the BATA Toll Bridge Rehabilitation funds for the BrIM Database pilot project for the SFOBB New East Spans with an allocation of $5M per year. An oversight group comprising of BATA and Caltrans representatives will be assigned to guide and evaluate the progress of this program every three months. As an option, this project may be extended to include the SFOBB West Spans in order to provide a comprehensive BrIM Database for the entire SFOBB Corridor. The TBPOC is hereby requested to provide its support and endorsement to the proposed BrIM Database pilot project. Attachment(s): NA

2 of 2 Item5b_BrIM Update_04Nov14_R4.docx

Page 37: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 6:  OTHER BUSINESS  

a.   Report on matters discussed and actions   taken at Urgent Meeting  

b.   Report on matters discussed and actions    taken during Executive Session 

Page 38: TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING … Pkt... · TOLL BRIDGE PROGRAM OVERSIGHT COMMITTEE MEETING M ... Toll Bridge Program Oversight Committee ... September 30, 2014

ITEM 7:  GENERAL PUBLIC COMMENT