torts sample cases in full text

Upload: pa0l0s

Post on 06-Jul-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    1/76

    Page 1 of 76

    FIRST DIVISION

    [G.R. No. 66641. March 6, 1992.]

    FILINVEST CREDIT CORPORATION, petitioner, vs.

    INTERMEDIATE APPELLATE COURT and JOVITO Z.

    MANAOG, respondents.

    Labaguis, Loyola, Angara & Associates for petitioner.

    Eduardo F. Elizalde for private respondent.

    SYLLABUS

    1. REMEDIAL LAW; CIVIL PROCEDURE; EFFECT

    OF JUDGMENT; TWO ASPECTS OF RES JUDICATA;

    CONSTRUED. — The doctrine of res judicata has two

    aspects. The first is the effect of a judgment as a bar to

    the prosecution of a second action upon the same

    claim, demand or cause of action. The second aspect is

    that it precludes relitigation of a particular fact or

    issues in another action between the same parties on a

    different claim or cause of action (Lopez v. Reyes, G.R.

    No. L-29498, March 31, 1977, 76 SCRA 179). Thus, a

    party by varying the form of action or method of case

    presentation cannot escape the effect of the principle of

    res judicata nor can a party avoid an estoppel of a

    former judgment by bringing forward in a second action

    new or additional grounds in support of his case or

    defense or new arguments to sustain it, the facts

    remaining the same at least where such additional

    matter could have been pleaded and adjudicated in the

    prior action.

    2. ID.; ID.; ID.; ALLOWING THE JUDGMENT TO

    BECOME FINAL AND EXECUTORY; A PARTY IS

    PRECLUDED FROM CLAIMING SUBSEQUENT ACTION

    FOR DAMAGES FROM AN ERRONEOUS JUDGMENT.— It is worthy to note that the complaint filed by

    petitioner Filinvest against respondent Manaog in Civil

    Case No. 242126 was for recovery of sum of money

    representing unpaid monthly installments for two

    airconditioning units bought by respondent Manaog.

    The latter filed an answer, as shown by the facts of the

    case, alleging that the airconditioning units are

    defective. Respondent Manaog did not however raise as

    defense the non-delivery of the said units. In fact,

    respondent Manaog did not present any evidence for

    defense to prove non-delivery. When the trial co

    rendered judgment in favor of petitioner Filinv

    respondent Manaog allowed the judgment to beco

    final and executory and the execution thereof be fu

    enforced before disclosing certain fats which shohave been raised and proven during the hearing of

    case. Hence, he is now precluded from claiming in

    subsequent action for damages that the judgm

    against him was erroneous because he did not rece

    the airconditioning units from petitioner.

    3. ID.; ID.; ID.; REMEDY OF PARTY WHO IS N

    SATISFIED FROM A JUDGMENT RENDERED. —

    respondent Manaog was not satisfied with the judgm

    of the trial court, he should have appealed the case

    the Court of Appeals within the reglementary period

    fifteen days after receipt of the decision before

     judgment of the trial court becomes final and executo

    However, if the judgment had become final a

    executory, there are only three ways under the law

     which said judgment may be questioned: 1) by petit

    for relief 2) by direct action to annul and enjoin

    enforcement of the judgment where the alleged defec

    not apparent on its face or from the recitals contain

    in the judgment, and 3) by direct action, as certior

    or by a collateral attack against the challen

     judgment which is void upon its face or that the nul

    of the judgment is apparent from its own recit

    (People v. Pareja, G.R. No. 59979, August 30, 1990,

    SCRA 143). Respondent Manaog's action for dama

     which was founded on the alleged wrong judgment

    the trial court in Civil Case No. 242126 does not

     within any of the ways enumerated above. Although

    action was titled as one for damages, respond

    Manaog, was in effect, alleging the nullity of

     judgment against him as being without factual ba

     which is the reason why he sought damages before

    trial court. This is a collateral attack upon a fi

     judgment which cannot be done if the said judgmen

     valid and regular upon its face, as in the case at bar.

    D E C I S I O N

    MEDIALDEA, J p:

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    2/76

    Page 2 of 76

    This is a petition for review on certiorari of the decision

    of the respondent appellate court (now Court of

    Appeals) affirming the decision of the court which

    awarded damages to private respondent arising from

    the alleged wrongful execution of a final judgment.

    Cdpr

    The antecedent facts of the case are as follows:

    On April 24, 1975, petitioner Filinvest Credit

    Corporation (Filinvest for brevity) filed a complaint with

    the Court of First Instance of Manila (now Regional Trial

    Court) against respondent Jovito Manaog and a certain

    John Doe, for replevin and/or recovery of sum of money

    representing arrearages in the payment of two

    airconditioners bought by respondent Manaog from

    Heritage Mercantile Corporation. The latter as vendorassigned the contract of "sale with reservation of title"

    to petitioner Filinvest. The contract of sale provided

    among others for a down payment in the amount of

    P2,100.00 by respondent Manaog upon execution of the

    contract and the balance in installments of P538.00

    each month; and that the failure of respondent Manaog

    to pay two installments will make the whole obligation

    due and demandable.

    Because respondent Manaog failed to pay the monthlyamortization, petitioner Filinvest sent letters of demand

    to respondent Manaog demanding payment. The latter

    did not respond however to any of the demands, thus,

    prompting petitioner Filinvest to file the aforementioned

    complaint. Respondent filed his answer and

    counterclaim to the complaint alleging that the

    airconditioners are defective (p. 39, Rollo) On October 3,

    1975, the date of the scheduled hearing, respondent

    Manaog failed to appear. Hence, petitioner was allowed

    to present its evidence ex-parte.

    On November 25, 1975, the trial court rendered a

    decision in favor of the petitioner and dismissed

    respondent Manaog's counterclaim. The trial court

    subsequently issued a writ of execution which was duly

    served upon respondent Manaog. By virtue of the said

    writ of execution, a sale by public auction was

    conducted by the sheriff on October 5, 1977 and a

    return thereof was made on October 27, 1977.

    On November 11, 1977, respondent Manaog filed

    motion to suspend execution of judgment, which w

    granted by the trial court. It appears however that

    sale at public auction had already been conducted.

    On April 28, 1978, respondent Manaog filed

    complaint before the Court of First Instance (CFI)

    Rizal (now Regional Trial Court) for damages alleg

    that the judgment which was made the basis of

    execution was wrong because the airconditioning un

    subject of the contract of sale were not in fact deliver

    and hence, respondent Manaog was not indebted

    petitioner.

     After trial, the CFI of Rizal rendered its decision,

    favor of respondent Manaog, the dispositive portion

     which states:

    "Premises considered, it is the finding of this Court t

    the defendant acted in utmost bad faith, and utilized

    means within its control to harass, humiliate a

    embarrass the plaintiff. The preponderance of evide

    supports the claim of plaintiff and the court finds

    defendant liable for having acted high handedly and

     bad faith. The Court hereby sentences the defendan

    pay the plaintiff the amount of P10,099.00 with inter

    thereon at the rate of 14% starting September 24, 19until fully paid; to pay plaintiff the amount

    P20,000.00 as exemplary damages and to pay plain

    attorney's fees in the amount of P5,000.00 as well

    costs of suit.

    "SO ORDERED." (p. 38, Rollo).

    Not satisfied with the decision of the trial cou

    petitioner Filinvest appealed to the Court of Appeals.

     January 16, 1984, the Court of Appeals rendered

    decision which affirmed in toto the ruling of the tcourt.

    Hence this petition was filed with the petitio

    assigning the following errors:

    "a. The Honorable Intermediate Appellate Co

    gravely abused its discretion in not holding priv

    respondent a joint fraudfeasor even when the fa

    clearly show him to be so;

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    3/76

    Page 3 of 76

    "b. The Honorable Intermediate Appellate Court

    erred in not holding that private respondent had no

    cause of action against petitioners;

    "c. The Honorable Intermediate Appellate Court

    erred in reopening the question of delivery as private

    respondent admitted delivery before the City Court of

    Manila; further such issue is barred by prior judgment;

    "d. The Honorable Intermediate Appellate Court

    erred in not holding that the lower court had no

    jurisdiction over the subject of the action as the

    complaint is in reality a collateral attack upon;

    1) a final judgment of a court of competent

    jurisdiction; and

    2) a writ of execution validly issued by a Court of

    competent jurisdiction;

    "e. The Honorable Intermediate Appellate Court

    erred in allowing private respondent recovery even when

    it conceded the latter's gross negligence in the

    protection of his alleged rights;

    "f. The Honorable Intermediate Appellate Court

    erred in applying the principle of abuse of right in the

    instant case;

    "g. The Honorable Intermediate Appellate Court

    erred in not holding the third-party defendant Badere

    liable to Petitioner for indemnification or reimbursement

    of what the latter was ordered to pay private

    respondent." (pp. 7-8, Rollo)

    The assigned errors boil down to the basic issue of

    whether or not the losing party may file an action for

    damages based on the same facts and issues involved in

    the first action where judgment rendered therein hadbecome final and had been fully executed. llcd

    Petitioner contends that although respondent Manaog's

    complaint is one for damages arising from the wrongful

    execution of the judgment in Civil Case No. 242126 filed

    by petitioner for recovery of sum of money, the subject

    of the action for damages is in reality, the validity of the

    judgment in the said civil case which should be

    properly attacked in a direct action to annul judgment.

    It also contends that the question of delivery, which was

    already settled in Civil Case No. 242126 cannot

    reopened by respondent Manaog in his action

    damages; that if it were true that no delivery was m

    to respondent Manaog, the latter should have disclo

    this fact when Civil Case No. 242126 for sum of mo

     was filed against him.

     We find the petition impressed with merit.

    Section 49 of Rule 39 of the Rules of Court,

    amended, provides:

    "Sec. 49. Effect of Judgment. The effect o

     judgment or final order rendered by a court or judge

    the Philippines, having jurisdiction to pronounce

     judgment or order may be as follows:

     xxx xxx xxx

    "b) In other cases the judgment or order is, w

    respect to the matter directly adjudged or as to

    other matter that could have been raised in relat

    thereto, conclusive between the parties and th

    successors in interest by title subsequent to

    commencement of the action or special proceedi

    litigating for the same thing and under the same t

    and in the same capacity;

    "c) In any other litigation between the same par

    or their successors in interest, that only is deemed

    have been adjudged in a former judgment wh

    appears upon its face to have been so adjudged,

     which was actually and necessarily included therein

    necessary thereto." (emphasis supplied)

     The aforequoted legal provision contains

    fundamental principles of res judicata, finality

     judgment and estoppel by judgment which

    interchangeable in meaning. They embody the sa

    rule that once a judgment has become final a

    executory, the issues therein should be laid at rest.

     The doctrine of res judicata has two aspects. The firs

    the effect of a judgment as a bar to the prosecution o

    second action upon the same claim, demand or caus

    action. The second aspect is that it preclu

    relitigation of a particular fact or issues in anot

    action between the same parties on a different claim

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    4/76

    Page 4 of 76

    cause of action (Lopez v. Reyes, G.R. No. L-29498,

    March 31, 1977, 76 SCRA 179). Thus, a party by

    varying the form of action or method of case

    presentation cannot escape the effect of the principle of

    res judicata nor can a party avoid an estoppel of a

    former judgment by bringing forward in a second actionnew or additional grounds in support of his case or

    defense or new arguments to sustain it, the facts

    remaining the same at least where such additional

    matter could have been pleaded and adjudicated in the

    prior action.

    It is worthy to note that the complaint filed by petitioner

    Filinvest against respondent Manaog in Civil Case No.

    242126 was for recovery of sum of money representing

    unpaid monthly installments for two airconditioning

    units bought by respondent Manaog. The latter filed an

    answer, as shown by the facts of the case, alleging that

    the airconditioning units are defective. Respondent

    Manaog did not however raise as defense the non-

    delivery of the said units. In fact, respondent Manaog

    did not present any evidence for his defense to prove

    non-delivery. When the trial court rendered judgment in

    favor of petitioner Filinvest, respondent Manaog allowed

    the judgment to become final and executory and the

    execution thereof be fully enforced before disclosing

    certain facts which should have been raised and proven

    during the hearing of the case. Hence, he is now

    precluded from claiming in a subsequent action for

    damages that the judgment against him was erroneous

    because he did not receive the airconditioning units

    from petitioner.

    If respondent Manaog was not satisfied with the

    judgment of the trial court, he should have appealed

    the case to the Court of Appeals within the

    reglementary period of fifteen days after receipt of thedecision before the judgment of the trial court becomes

    final and executory. However, if the judgment had

    become final and executory, there are only three ways

    under the law by which said judgment may be

    questioned: 1) by petition for relief 2) by direct action to

    annul and enjoin the enforcement of the judgment

    where the alleged defect is not apparent on its face or

    from the recitals contained in the judgment, and 3) by

    direct action, as certiorari, or by a collateral attack

    against the challenged judgment which is void upon

    face or that the nullity of the judgment is apparent fr

    its own recitals (People v. Pareja, G.R. No. 599

     August 30, 1990, 189 SCRA 143). Respondent Manao

    action for damages which was founded on the alle

     wrong judgment of the trial court in Civil Case 242126 does not fall within any of the ways enumera

    above. Although the action was titled as one

    damages, respondent Manaog, was in effect, alleg

    the nullity of the judgment against him as be

     without factual basis, which is the reason why

    sought damages before the trial court. This is

    collateral attack upon a final judgment which cannot

    done if the said judgment is valid and regular upon

    face, as in the case at bar. LLphil

    In view of the foregoing, We find that the respond

    appellate court committed reversible error in affirm

    the ruling of the trial court which disregarded the fi

     judgment in Civil Case No. 242126 as a bar to

    relitigation in a subsequent action of the facts a

    issues raised therein. Reasons of public policy, judi

    orderliness, economy and judicial time and interes

    litigants as well as the peace and order of society

    require that stability be accorded the solemn and fi

     judgments of the courts or tribunals of compet

     jurisdiction (Lee Bun Ting, et al. v. Aligaen, et al., G

    No. L-30523, April 22, 1977, 76 SCRA 416).

     ACCORDINGLY, the petition is GRANTED and

    assailed decision of the Court of Appeals dated Janu

    16, 1984 is REVERSED and SET ASIDE.

    SO ORDERED.

    SECOND DIVISION

    [G.R. No. 55613. December 10, 1990.]

    ERNESTO DICHOSO, petitioner, vs. T

    HONORABLE COURT OF APPEALS and TEODOL

    RAMOS, respondents.

    Pardalis Law Office for petitioner.

    Felipe, Sibulo & Associates and Marciano H. Can

    for private respondent.

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    5/76

    Page 5 of 76

    D E C I S I O N

    PARAS, J p:

    This is a petition for certiorari of the July 8, 1980

    decision ** of the Court of Appeals which affirmed the

    November 3, 1975 decision *** of the then Court ofFirst Instance of Camarines Sur, the dispositive portion

    of which reads, as follows:

    "WHEREFORE, judgment is hereby rendered declaring

    the plaintiff owner of the land described in paragraph 2

    of the complaint; and ordering the defendants, Ernesto

    Dichoso and Marcelino Enciso, to restitute the

    possession of the land to the plaintiff and to deliver to

    the plaintiff 40 cavans of palay for every year from 1964

    until the land in question is returned to the latter ortheir equivalent value of P15.00 per cavan of palay. With

    costs against the said defendants.

    SO ORDERED."

    (CA Decision, Rollo, p. 14). llcd

    The facts of the case are as follows:

    The spouses Gaspar Prila and Maria Beldad, owned a

    16.8716 hectare parcel of land at Cagmanaba, Ocampo,

    Camarines Sur, surveyed in the name of Gaspar Prila

    under Plan Psu-61453 (Exhibit "2"). Upon the death of

    Maria Beldad in 1925, the eastern half thereof was

    given to Vivencia Prila, their only daughter, and when

    Gaspar Prila died in 1943, the 1/2 portion pertaining to

    him was divided into three: one third to Vivencia Prila,

    one third to Asuncion Pacamara and the other one-

    third to Custodia Parcia, as reflected in the Extra-

    judicial Settlement of Estate executed on November 22,

    1945. Under the terms of said settlement, 4/6 of the

    entire land or 11.2477 hectares was adjudicated to

    Vivencia Prila, 1/6 or 2.8119 hectares to Asuncion

    Pacamara and another 1/6 or 2.8119 hectares to

    Custodio Parcia. This stipulation was reiterated by both

    Vivencia Prila and Asuncion Pacamara in an agreement

    dated March 29, 1947 duly registered with the Register

    of Deeds on June 22, 1947 and was furthermore

    confirmed judicially by the Court of First Instance of

    Camarines Sur, in Civil Cases Nos. 3370 and 4468.

    In 1955, Vivencia Prila sold her 4/6 portion with

    area of 11.2477 hectares to the petitioner Erne

    Dichoso who had been, ever since, in actual phys

    possession thereof, exercising various acts of owners

    thereon.

    On the other hand, in a Deed of Sale dated June

    1948, Asuncion Pacamara sold to the wife of priv

    respondent Teodolfo Ramos her 1/6 share, but the d

    mentions the area of the lot sold as 4.1250 hectar

    obviously in excess of Pacamara's 1/6 share in

    property of 2.8119 hectares. Hence, aforesaid 4.12

    hectares which Ramos claims to have possessed, is n

    the land in question.

     As described in Ramos' Deed of Sale dated June

    1948, the land bought by his wife is as follows:

    "Cogon land situated in the barrio of Cagmana

    Municipality of Pili, Province of Camarines Sur, with

    area of approximately 4 hectares, 12 ares, and

    centares, and is bounded on the North by a da

    limited by the same dam, measuring 120 meters; on

    East, Cagmanaba River, limited by the same ri

    measuring 200 meters; on the South, heirs of Gas

    Prila and Mariano Rodriguez, limited by an irrigat

    ditch, measuring 200 meters; on the West, heirsGaspar Prila and limited by a big stone, measuring 3

    meters." (Exhibit "A", Original Records)

     The said Deed of Absolute Sale was notarized a

    registered with the Register of Deeds of Camarines S

    on August 2, 1948. Realty taxes for the years 19

    1960 were paid on July 22, 1960 and for the ye

    1961-1962 on November 18, 1964 (CA Decision, Ro

    p. 15).

    Herein respondent Teodolfo Ramos took possessionthe contested riceland upon its purchase. It yielded

    average harvest of 20 sacks of palay per planting wh

     was twice a year. One-third of the harvest went

    Ramos and the remaining two-thirds was the tenan

    share (Rollo, pp. 15-16).

    On the other hand, petitioner Ernesto Dichoso clai

    that the disputed land is inside his property of 11.24

    hectares which he acquired from Vivencia Prila

    P2,000.00 and evidenced by a Deed of Absolute S

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    6/76

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    7/76

    Page 7 of 76

    Prila ceded to Asuncion Pacamara one hectare more

    located on the northern portion of the land covered by

    Original Certificate of Title No. 1176. In effect, Asuncion

    Pacamara owns at least six (6) hectares of land.

    Furthermore, the Deed of Conveyance was registered on

    August 2, 1948 and the property has been declared fortax purposes in the name of Ramos' wife. Above all

    these, the question raised by Dichoso is purely a

    question of fact. LexLib

    The records show, however, that the one hectare ceded

    by Vivencia Prila to Asuncion Pacamara on the

    northern portion of the land supposed to be covered by

    Original Certificate of Title No. 1176, is not the same

    land covered by said Original Certificate of Title

    (Original Exhibits, Exhibit "3", p. 1) Therefore, while it

    may be true that Asuncion Pacamara may have been

    adjudicated a total of six (6) hectares of land, but what

    is covered by Original Certificate of Title No. 1176

    pursuant to the Extra-Judicial Settlement Agreement

    and the agreement subsequent thereto insofar as

    Vivencia Prila's share is concerned, remains to be one-

    sixth (1/6) or 2.8119 hectares (Original Exhibits,

    Exhibit "3", p. 4).

    The striking similarities in the boundaries between the

    parcel of land in dispute and the property of Ramos'wife, particularly the boundaries on the North, which is

    the dam, and on the East, which is the Cagmanaba

    River, and the fact that the deed of sale in favor of

    Ramos' wife was executed and registered ahead of that

    of Dichoso's deed of sale, led the trial court to conclude

    that the property in dispute tallies with the land bought

    by Ramos' wife. It must be pointed out, however, that

    the deed of sale in favor of Ramos' wife explicitly

    described the property as being bounded "on the South

    (by) heirs of Gaspar Prila and Mariano Rodriguez,limited by an irrigation ditch, measuring 200 meters; on

    the West (by) heirs of Gaspar Prila, limited by a big

    stone, measuring 350 meters." The commissioner's

    report (Exhibit "11") identified the land claimed by

    Ramos and indicated in the sketch as the portion

    surrounded by a red line inside Lot-3, the portion

    pertaining to Dichoso. As indicated in the said sketch

    the land of Dichoso is labelled as Lots-1 and 3 and the

    portion labelled as Lot-2 is the land of Ramos. A further

    scrutiny of Exhibit "11" shows that the area be

    claimed by Ramos, which was enclosed by a red li

     went beyond the irrigation ditch. This is contrary to

    technical description in the deed of sale in favor

    Ramos' wife as to the boundary on the southern port

    of the property (Original Exhibits, Exhibit "11").

     While the jurisdiction of this Court in cases brou

    from the Court of Appeals is limited to the review

    errors of law, said appellate court's finding of fa

     being conclusive, there are exceptions, among wh

    are: (1) when the conclusion is a finding groun

    entirely on speculation, surmises or conjectures;

     when the inference made is manifestly absu

    mistaken, or impossible; (3) . . .; (4) when the judgm

    is premised on a misapprehension of facts; (5) . . . (R

    Cement, Co., Inc. vs. Villareal, 135 SCRA 15, Febru

    28, 1985).

     This Court has held that in cases of conflict betw

    areas and boundaries, it is the latter which sho

    prevail. What really defines a piece of ground is not

    area, calculated with more or less certainty, mention

    in its description, but the boundaries therein laid dow

    as enclosing the land and indicating its limits (Eric

    Chigas, 98 SCRA 575, July 16, 1980). In a contrac

    sale of land in a mass, it is well established that specific boundaries stated in the contract must con

    over any statement with respect to the area contain

     within its boundaries. It is not of vital consequence t

    a deed or contract of sale of land should disclose

    area with mathematical accuracy. It is sufficient if

    extent is objectively indicated with sufficient precis

    to enable one to identify it. An error as to the superfi

    area is immaterial. (Loyola v. Bartolome, 39 Phil. 5

     January 24, 1919 reiterated in Erico v. Chigas, supra

     With reference to the second error, petitioner alle

    that since respondent's share of the harvest is only o

    third (1/3), the remaining two-thirds (2/3) represent

    his tenant's share, only the one-third (1/3) of

    annual harvest must be awarded to Ramos.

    Ramos, on the other hand, argues that his tenant

     be deprived of his share if only one-third (1/3) of

    harvest will be awarded to him.

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    8/76

    Page 8 of 76

    Actual or compensatory damages cannot be presumed,

    but must be duly proved, and proved with reasonable

    degree of certainty. A court cannot rely on speculation,

    conjecture or guesswork as to the fact and amount of

    damages, but must depend upon competent proof that

    they have suffered and on evidence of the actualamount thereof (Dee Hua Liong Electrical Corporation

    v. Reyes, 145 SCRA 713, November 25, 1986). prcd

    It is undisputed that the land in question yields an

    average of twenty (20) sacks of palay per planting and

    that it is planted to palay twice a year. Ramos' share of

    the harvest is only one-third (1/3). In view of his

    dispossession from 1964 and the fact that his tenant

    has vacated the land that same year (TSN, Hearing of

    February 10, 1971, pp. 2-3), he cannot allege that his

    tenant is entitled to his two-thirds (2/3) share.

    PREMISES CONSIDERED, the decision appealed from

    is hereby SET ASIDE and the area of the land awarded

    to herein respondent Ramos is hereby LIMITED to

    2.8119 hectares in accordance with the boundaries

    indicated in the deed of sale in favor of his wife, and the

    award of actual damages is hereby REDUCED in

    proportion to the area that may be awarded to Ramos

    and to his one-third (1/3) participation in the harvests,

    from 1964 up to the time the land appurtenant theretois returned to the respondent.

    SO ORDERED.

    Melencio-Herrera, Padilla, Sarmiento and Regalado, JJ.,

    concur.

    THIRD DIVISION

    [G.R. No. L-39215. September 1, 1989.]

    PHILIPPINE NATIONAL BANK, plaintiff-appellee, vs.

    UTILITY ASSURANCE & SURETY CO., INC.,

    defendant-appellant.

    The Chief and Asst. Chief Legal Counsel for plaintiff-

    appellee.

    Ceferino M. Carpio, Jr. for defendant-appellant.

    SYLLABUS

    1. CIVIL PROCEDURE; ANSWER; DENIAL IN T

    EXECUTION OF DOCUMENT SUED UPO

    UNAVAILING WHERE DEFENDANT'S AVERMENT

    IGNORANCE IS TO THE KNOWLEDGE OF THE COU

    PALPABLY UNTRUE. — Utassco had alleged in

    answer that it had no knowledge or informatsufficient to form a belief as to the truth of

    allegations made by PNB in its complaint. Utassco

    other words, purported to deny those allegations a

    hence now contends that it had generated an issue

    fact which the trial court should have first passed up

    Utassco, however, cannot be deemed to have denied

    allegations of the amended complaint, considering t

    the truth of those allegations relating to the execut

    of the surety bond and the contents thereof w

    peculiarly within the knowledge of Utassco being issuer of the bond and Endorsement No. B-60-3 its

    In Equitable Banking Corporation v. Liwanag, it

     been held that said mode of denial is unavailing 'wh

    the fact as to which want of knowledge is asserted is

    the knowledge of the court so plainly and necessa

     within the defendant's knowledge that his avermen

    ignorance must be palpably untrue.'

    2. ID.; ID.; ANSWER FAILED TO RAISE GENUI

    ISSUES OF FACT; JUDGMENT ON THE PLEADING

    PROPER. — At the same time that Utassco pretended

    have denied the allegations of PNB's amend

    complaint, it admitted in the affirmative defense sect

    of its answer that it had indeed executed the Sur

    Bond and Endorsement No. B-60-3 in favor of PN

    Utassco must be deemed thereby to have admitted

    due execution of the Bond and the Endorsement.

    affirmative defense in fact consisted of pleading the v

    provisions of the Surety Bond upon which PNB ba

    its cause of action. Thus, the issues raised by

    amended complaint and the answer were not genu

    issues of fact on which evidence would have had to

    submitted. Those pleadings raised, rather, questi

    concerning the proper interpretation of the provision

    the Surety Bond and Endorsement No. B-60-3, Un

    these circumstances, the trial court correctly rende

     judgment on the pleadings.

    3. ID.; ID.; ID.; JUDGMENT ON THE PLEADING

    ISSUANCE NOT PREMATURE. — Utassco claims t

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    9/76

    Page 9 of 76

    the trial court should have withheld judgment on the

    pleadings until after the third party action brought by

    Utassco against the owner of Lanuza Lumber on the

    indemnity agreement executed between them, had gone

    forward to judgment. The third party complaint could,

    of course, have been prosecuted quite separately fromthe principal action between PNB and Utassco. Indeed,

    there was no reason at all why the trial court should

    have deferred rendering judgment on the pleadings in

    the principal action, considering that the PNB was not

    interested at all in the outcome of the third party

    complaint. Under Section 12, Rule 6 of the Revised

    Rules of Court, the purpose of a third party complaint

    is to enable a defending party to obtain contribution,

    indemnity, subrogation or other relief from a person not

    a party to the action. Thus, notwithstanding thejudgment on the pleadings, Utassco could still proceed

    with the prosecution of its third party complaint.

    4. OBLIGATIONS AND CONTRACTS; CONTRACT

    INTERPRETATION; PRINCIPLE OF EFFECTIVENESS. — 

    The principle of effectiveness is basic in contract

    interpretation: where two (2) interpretations of the same

    contract language are possible, one interpretation

    having the effect of rendering the contract meaningless

    (and one of the parties merely dishonest for receiving

    consideration thereunder without parting with any),

    while the other interpretation would give effect to the

    contract as a whole, the latter interpretation must be

    adopted.

    5. CREDIT TRANSACTION; SURETY'S LIABILITY

    TO INTEREST NOT IN VIOLATION OF CONTRACT OF

    SURETYSHIP. — The objections that the trial court

    should not have granted interest and attorneys' fees in

    favor of PNB, considering the clause in the indorsement

    limiting the liability of UTASSCO to P25,000.00. "Theobjection has to be overruled, because as far back as

    the year 1922 this Court held in Tagawa vs. Aldanese,

    43 Phil. 852, that creditors suing on a suretyship bond

    may recover from the surety as part of their damages,

    interest at the legal rate even if the surety would

    thereby become liable to pay more than the total

    amount stipulated in the bond. 'The theory is that

    interest is allowed only by way of damages for delay

    upon the part of the sureties in making payment after

    they should have done. "In other words the surety

    made to pay interest, not by reason of the contract,

     by reason of its failure to pay when demanded and

    having compelled the plaintiff to resort to the courts

    obtain payment.

    6. ATTORNEY'S FEES; AWARD ALLOWED UND

     THE CIVIL CODE. — The New Civil Code perm

    recovery of attorney's fees in eleven cases enumera

    in Article 2208, among them 'where the court deem

     just and equitable that attorney's fees and expenses

    litigation should be recovered' or 'when the defend

    acted in gross and evident bad faith in refusing

    satisfy the plaintiff's plainly valid, just and demanda

    claim.' This gives the courts discretion in apportion

    attorney's fees.

    R E S O L U T I O N

    FELICIANO, J p:

     The Kangyo Bank Ltd., Tokyo, Japan, issued Letter

    Credit No. 14-10272 in the amount of US$28,150.00

    favor of the Pedro Bartolome Enterprises of Manila

    cover an export shipment of logs to Japan. T

     beneficiary of the Letter of Credit assigned its rights

    Lanuza Lumber. On 29 March 1960, Procopio Cader

    doing business under the trade name "Lanuza Lumb

    obtained a loan of P25,000.00 from plaintiff-appe

    Philippine National Bank (PNB) as evidenced by

    promissory note on the security, among other things

    the proceeds of the Letter of Credit. The PNB in addit

    required Lanuza Lumber to submit a surety bo

    Defendant-Appellant Utility Assurance & Surety C

    Inc. ("Utassco"), accordingly, executed Surety Bond

    B-123 in favor of PNB. It is useful to quote the terms

    the Surety Bond in their entirety:

    "SURETY BOND

    Know All Men By These Presents:

     That we, LANUZA LUMBER of Surigao, Surigao (5

    Rosario St., Manila) as Principal, and the UTIL

     ASSURANCE & SURETY CO., INC., a corporation d

    organized and existing under and by virtue of the la

    of the Philippines, with Head Office in the City

    Manila, as Surety, are held and firmly bound u

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    10/76

    Page 10 of 76

    PHILIPPINE NATIONAL BANK in the penal sum of

    TWENTY FIVE THOUSAND ONLY — PESOS

    (P25,000.00) Philippine Currency, for the payment of

    which, well and truly to be made, we bind ourselves,

    our heirs, executors, administrators and successors

    and assigns, jointly and severally, firmly by thesepresents:

    The conditions of this obligation are as follows:

    Whereas, the Kangyo Bank, Ltd., Tokyo, Japan has

    granted a letter of credit No. 14-10272 in the amount of

    $28,150.00 in favor of Pedro Bartolome Enterprises of

    302 Salvacion Apt., 2504 Pennsylvania, Manila, to cover

    shipment of 500,000 board feet of logs to Shin

    Asshigawa Co., Ltd., Tokyo, Japan;

    Whereas, on January 21, 1960 the beneficiary, Pedro

    Bartolome Enterprises assigned the aforementioned

    letter of credit to Lanuza Lumber of Surigao per

    attached Deed of Assignment;

    Whereas, the correspondent Bank, Philippine National

    Bank requires the Lanuza Lumber to post a surety bond

    in the sum of Twenty Five Thousand (P25,000.00)

    Pesos, Philippine Currency, to guarantee full and

    faithful compliance by the beneficiary of the terms and

    conditions of the said letter of credit.

    It is a special provision of this undertaking to guarantee

    the full payment of a loan not to exceed TWENTY FIVE

    THOUSAND PESOS (P25,000.00) that may be granted

    by the Philippine National Bank to Lanuza Lumber.

    Whereas, said contract requires said Principal to give a

    good and sufficient bond in the above-stated sum to

    secure the full and faithful performance on his part of

    said contract;

    Now Therefore, if the Principal shall well and truly

    perform and fulfill all the undertakings, covenants,

    terms, conditions and agreements stipulated in said

    contract, then this obligation shall be null and void;

    otherwise to remain in full force and effect.

    The liability of the UTILITY ASSURANCE & SURETY

    CO., INC., on this bond will expire on March 17, 1961

    and said bond will be cancelled TEN DAYS after its

    expiration, unless Surety is notified of any exist

    obligations thereunder.

    In Witness Whereof, we have set our hands and sign

    our names at Manila on March 17, 1960.

    Utility Assurance & Surety Co., Inc.

    S/Dalmacio Urtula, Jr.

    DALMACIO URTULA, JR.

     AUTHORIZED SIGNATURE

    LANUZA LUMBER

    S/ Procopio O. Caderao

    General Manager

    SIGNED IN THE PRESENCE OF:

    (Sgd) ILLEGIBLE

    (Sgd) ILLEGIBLE." (Emphasis supplied)

     The surety bond was accompanied by an Endorsem

    No. B-60-3 which provided as follows:

    "In lieu of the last paragraph of this bond, it is her

    declared and agreed that the following condition

    incorporated in said bond and made an integral p

    thereof:

     That, if the above bounden principal and surety sh

    in all respects, duly and fully observe and perform

    and singular terms and conditions of

    aforementioned Letter of Credit, then this obligat

    shall be and become null and of no further force

    effect; in the contrary case, the same shall continue

    full effect and be enforceable, as a joint and seveobligation of the parties hereto in the manner provid

     by law so long as the account remains unpaid a

    outstanding in the books of the Bank either thru n

    collection, extension, renewals or plans of payment w

    or without consent of the surety.

    It is a special condition of this bond that the liability

    the surety thereon shall, at all times, be enforcea

    simultaneously with that of the principal without

    necessity of having the assets of the principal resor

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    11/76

    Page 11 of 76

    to, or exhausted by, the creditor; Provided, however, that

    the liability of the surety shall be limited to the sum of

    TWENTY-FIVE THOUSAND PESOS (P25,000),

    Philippine Currency. Nothing herein contained shall be

    held to vary, alter, waive or change any of the terms,

    limits or conditions of the bond, except as herein-aboveset forth." (Emphasis supplied)

    The promissory note executed by Lanuza Lumber

    became due and payable. Neither Lanuza Lumber nor

    Utassco paid the loan despite repeated demands by

    PNB for payment. Accordingly, PNB filed in the then

    Court of First Instance of Manila an action to recover

    the amount of the promissory note with interest as

    provided thereon plus attorney's fees. 1

    In its Answer to PNB's complaint, Utassco stated that ithad "no knowledge or information sufficient to form a

    belief as to the truth of the allegations contained in

    [paragraphs 2, 3, 4 and 5] of the amended complaint

    and perforce [denied] the same." 2 At the same time,

    however, in setting out its affirmative defense, Utassco

    admitted that it had executed the surety bond and

    simultaneously pointed to the provisions of

    Endorsement No. B-60-3. In particular, Utassco

    contended that its obligation under the Surety Bond

    was to secure the performance of all the terms andconditions of the US$28,150.00 Letter of Credit issued

    by Kangyo Bank Ltd. and had not guaranteed the

    performance of Lanuza Lumber's obligation under its

    P25,000.00 loan from PNB.

    On 14 January 1971, upon motion of PNB, the trial

    court rendered judgment on the pleadings. The

    dispositive part of the judgment reads as follows:

    "WHEREFORE, in the light of the foregoing

    considerations, judgment is hereby rendered ordering

    the defendant to pay the plaintiff the sum of

    P25,000.00 plus 6% interest per annum counted from

    May 19, 1962, the date of the filing of the original

    complaint until fully paid, plus attorney's fees

    equivalent to 10% of the principal obligation and the

    costs of the suit."

    Its Motion for Reconsideration of the trial cou

     judgment on the pleadings having been denied, Utas

    appealed that judgment to the Court of Appeals.

     The Court of Appeals, by a Resolution dated 31 J

    1974, certified the appeal to us as involving o

    questions of law.

    Both before the Court of Appeals and this Cou

    Utassco claims that the trial court fell into error:

    (1) in granting the plaintiff-appellee's (PNB

    motion for judgment on the pleadings;

    (2) assuming the trial court could render judgm

    on the pleadings, in doing so prematurely; and

    (3) in awarding interest and attorney's fees in faof plaintiff-appellee PNB.

     We turn to the first alleged error. As noted earl

    Utassco had alleged in its answer that it had

    knowledge or information sufficient to form a belief

    to the truth of the allegations made by PNB in

    complaint. Utassco, in other words, purported to d

    those allegations and hence now contends that it h

    generated an issue of fact which the trial court sho

    have first passed upon. Utassco, however, cannotdeemed to have denied the allegations of the amend

    complaint, considering that the truth of th

    allegations relating to the execution of the surety bo

    and the contents thereof was peculiarly within

    knowledge of Utassco being the issuer of the bond a

    Endorsement No. B-60-3 itself. In Equitable Bank

    Corporation v. Liwanag, 3 the Supreme Court rejec

    out of hand the same argument which Utassco n

    seeks to make:

    "This pretense is manifestly devoid of merit. Althou

    the Rules of Court permit a litigant to file an answ

    alleging lack of knowledge to form a belief as to

    truth of certain allegations in the complaint, this fo

    of denial 'must be availed of with sincerity and in g

    faith, — certainly neither for the purpose of del

    Indeed, it has been held that said mode of denia

    unavailing 'where the fact as to which want

    knowledge is asserted is to the knowledge of the co

    so plainly and necessarily within the defendan

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    12/76

    Page 12 of 76

    knowledge that his averment of ignorance must be

    palpably untrue.' Thus, under conditions almost

    identical to those obtaining in the case at bar, this

    Court, speaking through Mr. Justice Villamor, upheld a

    judgment on the pleadings in Capitol Motors vs.

    Nemesio L. Yabut (G.R. No. L-28140, March 19, 1970)from which we quote:

    "'We agree with the defendant-appellant that one of the

    modes of specific denial contemplated in Section 10,

    Rule 8, is a denial by stating that the defendant is

    without knowledge or information sufficient to form a

    belief as to the truth of a material averment in the

    complaint. The question, however, is whether paragraph

    2 of defendant-appellant's answer constitutes a specific

    denial under the said rule. We do not think so. In

    Warner Barnes & Co. Ltd. vs. Reyes, et al. G.R. No. L-

    9531, May 14, 1958 (103 Phil. 662), this Court said

    that the rule authorizing an answer to the effect that

    the defendant has no knowledge or information

    sufficient to form a belief as to the truth of an averment

    and giving such answer the effect of a denial, does not

    apply where the fact as to which want of knowledge is

    asserted, is so plainly and necessarily within the

    defendant's knowledge that his averment of ignorance

    must be palpably untrue.

    In said case the suit was one for foreclosure of

    mortgage, and a copy of the deed of mortgage was

    attached to the complaint: thus, according to this

    Court, it would have been easy for the defendants to

    specifically allege in their answer whether or not they

    had executed the alleged mortgage. The same thing can

    be said in the present case, where a copy of the

    promissory note sued upon was attached to the

    complaint. The doctrine in Warner Barnes & Co. Ltd.

    was reiterated in J.P. Juan & Sons, Inc. v. LiangaIndustries, Inc., G.R. No. L-25137, July 28, 1969 (28

    SCRA 807) . . . .'" (Emphasis supplied)

    At the same time that Utassco pretended to have denied

    the allegations of PNB's amended complaint, it admitted

    in the affirmative defense section of its answer that it

    had indeed executed the Surety Bond and Endorsement

    No. B-60-3 in favor of PNB; Utassco must be deemed

    thereby to have admitted the due execution of the Bond

    and the Endorsement. Its affirmative defense in fact

    consisted of pleading the very provisions of the Sur

    Bond upon which PNB based its cause of action. Th

    the issues raised by the amended complaint and

    answer were not genuine issues of fact on wh

    evidence would have had to be submitted. Th

    pleadings raised, rather, questions concerning proper interpretation of the provisions of the Sur

    Bond and Endorsement No. B-60-3, i.e.,

    determination of whether the surety bond and

    endorsement had, as contended by the P

    guaranteed the payment by Lanuza Lumber of

    P25,000.00 loan from PNB; or whether, as maintain

     by Utassco, the surety bond and its endorsem

    served merely to secure the performance of the ter

    and conditions of the Letter of Credit No. 14-10272.

    hold, therefore, that under these circumstances, trial court correctly rendered judgment on

    pleadings.

     We turn to the second error imputed by Utassco to

    trial court: that the judgment on the pleadings, whil

    may have been within the jurisdiction of the trial cou

     was prematurely issued. This argument appears to

    even more tenuous than the first assigned er

    Utassco claims that the trial court should h

     withheld judgment on the pleadings until after the th

    party action brought by Utassco against the owner

    Lanuza Lumber on the indemnity agreement execu

     between them, had gone forward to judgment. The th

    party complaint could, of course, have been prosecu

    quite separately from the principal action between P

    and Utassco. Indeed, there was no reason at all why

    trial court should have deferred rendering judgment

    the pleadings in the principal action, considering t

    the PNB was not interested at all in the outcome of

    third party complaint. Under Section 12, Rule 6 of

    Revised Rules of Court, the purpose of a third pa

    complaint is to enable a defending party to obt

    contribution, indemnity, subrogation or other relief fr

    a person not a party to the action. Th

    notwithstanding the judgment on the pleadin

    Utassco could still proceed with the prosecution of

    third party complaint.

    Before passing on to the third error assigned

    Utassco, it is important to note that Utassco did

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    13/76

    Page 13 of 76

    really dispute the correctness of the conclusion reached

    by the trial court in respect of the substantive issue

    raised before it: whether the bond issued by Utassco

    secured the obligations of Lanuza Lumber to repay the

    P25,000.00 loan obtained from PNB, or whether the

    bond had secured the Letter of Credit. The trial courtheld that the surety bond was intended to secure the

    repayment of Lanuza Lumber's loan from PNB. We

    believe and so hold that the trial court was correct in so

    holding. In the first place, the surety bond explicitly

    stated that the P25,000.00 loan was being secured by

    the bond: cdrep

    "It is a special provision of this undertaking to

    guarantee the full payment of a loan not to exceed

    TWENTY FIVE THOUSAND PESOS (P25,000,00) that

    may be granted by the Philippine National Bank to

    Lanuza Lumber."

    In the second place, while the bond and the

    endorsement had referred to the Letter of Credit,

    Lanuza Lumber had no obligations under the Letter of

    Credit. As noted earlier, Lanuza Lumber was

    beneficiary-assignee of the Letter of Credit. Thus,

    Utassco's view would reduce the terms and conditions

    of the Surety Bond to nonsense. Such view would also

    mean that Utassco, in its own reading of the bond, wasnever at risk since there were no obligations to secure

    and that Utassco was in fact collecting premiums for

    issuing the bond under which it had no liabilities. The

    principle of effectiveness is basic in contract

    interpretation: where two (2) interpretations of the same

    contract language are possible, one interpretation

    having the effect of rendering the contract meaningless

    (and one of the parties merely dishonest for receiving

    consideration thereunder without parting with any),

    while the other interpretation would give effect to thecontract as a whole, the latter interpretation must be

    adopted. 4

    In the instant case, the reference to the Letter of Credit

    in the surety bond and the endorsement was either

    merely inadvertent surplusage or, alternatively, merely

    indication of ineptness on the part of the draftsman of

    the bond and the endorsement. It is not disputed by

    Utassco that the endorsement was intended to replace

    the final paragraph of the original bond, which

    paragraph limited the life of the bond to one year fr

    issuance. The endorsement had the important effec

    giving the bond continuing life so long as "the accou

    remained unpaid and outstanding on the books of PN

     The term "account" here could only refer to the acco

    of the principal debtor, Lanuza Lumber, with PNB. Tendorsement also made it clear that the liability

    Lanuza Lumber and Utassco was joint and several

    nature, and that Utassco had waived any benefit

    excussion that it might otherwise have had. Finally,

    a very practical level, it is difficult to understand h

    Utassco could have reasonably supposed that its bo

    in the amount of RPP25,000.00 was intended only

    even principally) to secure performance of

    obligations of the issuer — Kangyo Bank — under

    Letter of Credit which had a face value US$28,150.00, many times the face value of the bond

     We come to the final error assigned by Utassco: that

    trial court should not have granted interest a

    attorney's fees in favor of PNB, considering the clause

    the endorsement limiting the liability of Utassco

    P25,000.00. The issue here presented is not a new o

    It was extensively discussed and Utassco's submiss

    decisively rejected by this Court in Plaridel Surety a

    Insurance Co., Inc. v. P.L. Galang Machinery Co., Inc

     There, the Court held: prcd

    "Petitioner objects to the payment of interest a

    attorney's fees because: (1) they were not mentioned

    the bond; and (2) the surety would become liable

    more than the amount stated in the contract

    suretyship.

    "In support of its objection petitioner dwells on

    proposition that a surety's liability can not be extend

     beyond the terms of his undertaking, citing artic1956 and 2208 of the New Civil Code which provide

    follows:

    'ART. 1956. No interest shall be due unless it

     been expressly stipulated in writing.'

    'ART. 2208. In the absence of stipulation, attorne

    fees and expenses of litigation, other than judicial co

    cannot be recovered, except: . . .'

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    14/76

    Page 14 of 76

    "The objection has to be overruled, because as far back

    as the year 1922 this Court held in Tagawa vs.

    Aldanese, 43 Phil. 852, that creditors suing on a

    suretyship bond may recover from the surety as part of

    their damages, interest at the legal rate even if the

    surety would thereby become liable to pay more thanthe total amount stipulated in the bond. 'The theory is

    that interest is allowed only by way of damages for delay

    upon the part of the sureties in making payment after

    they should have done. In some states, the interest has

    been charged from the date of the judgment of the

    appellate court. In this jurisdiction, we rather prefer to

    follow the general practice which is to order that

    interest begin to run from the date when the complaint

    was filed in court, . . .'

    Such theory aligned with Sec. 510 of the Code of Civil

    Procedure which was subsequently recognized in the

    Rules of Court (Rule 53, Section 6) and with Article

    1108 of the Civil Code (now Art. 2209 of the New Civil

    Code).

    "In other words the surety is made to pay interest, not

    by reason of the contract, but by reason of its failure to

    pay when demanded and for having compelled the

    plaintiff to resort to the courts to obtain payment. It

    should be observed that interest does not run from thetime the obligation became due, but from the filing of

    the complaint.

    "As to attorneys fees. Before the enactment of the New

    Civil Code, successful litigants could not recover

    attorney's fees as part of the damages they suffered by

    reason of the litigation. Even if the party paid

    thousands of pesos to his lawyers, he could not charge

    the amount to his opponent.

    "However, the New Civil Code permits recovery of

    attorney's fees in eleven cases enumerated in Article

    2208, among them 'where the court deem it just and

    equitable that attorney's fees and expenses of litigation

    should be recovered' or 'when the defendant acted in

    gross and evident bad faith in refusing to satisfy the

    plaintiff's plainly valid, just and demandable claim.'

    This gives the courts discretion in apportioning

    attorney's fees.

    "Now, considering, in this case, that the princi

    debtor had openly and expressly admitted his liabi

    under the bond, and the surety knew it (p. 123 R.

     we can not say there was abuse of lower cou

    discretion in the way of awarding fees, specially wh

    the indemnity agreement . . . afforded the suradequate protection. (100 Phil. 681-682." (Empha

    supplied)

     WHEREFORE, the Court Resolved to DISMISS

    appeal by defendant-appellant Utility Assurance

    Surety Co., Inc. for lack of merit, and to AFFIRM

     judgment of the trial court dated 14 January 1971.

    pronouncement as to costs. This Resolution

    immediately executory.

    SO ORDERED.

    Fernan, C.J., Gutierrez, Jr., Bidin and Cortes, J

    concur.

    FIRST DIVISION

    [G.R. No. 82808. July 11, 1991.]

    DENNIS L. LAO, petitioner, vs. HON. COURT

     APPEALS, JUDGE FLORENTINO FLOR, Regio

     Trial Court, Branch 89 of Morong, Rizal BENJAM

    L. ESPIRITU, MANUEL QUERUBIN and CHAN TON

    respondents.

    F. Sumulong & Associates Law Offices for petitioner.

    Manuel LL. Querubin for and in his own behalf.

    Enrique M. Basa for private respondent.

    SYLLABUS

    1. CIVIL LAW; SPECIAL CONTRACTS; AGEN

     AGENT NOT PERSONALLY LIABLE TO THE PAR

     WITH WHOM HE CONTRACTED. — Lao has a va

    defense to the action for malicious prosecution (C

    Case No. 84-M) because it was his employer, St. Jos

    Lumber, not himself, that was the complainant in

    estafa case against Espiritu. It was Chan Tong,

    owner of the St. Joseph Lumber, who, upon advice

    his counsel, filed the criminal complaint agai

    Espiritu. Lao was only a witness in the case. He had

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    15/76

    Page 15 of 76

    personal interest in the prosecution of Espiritu for he

    was not the party defrauded by Espiritu. He executed

    the affidavit which was used as basis of the criminal

    charge against Espiritu because he was the salesman

    who sold the construction materials to Espiritu. He was

    only an agent of St. Joseph Lumber, hence, notpersonally liable to the party with whom he contracted

    (Art. 1897, Civil Code; Philippine Products Co. vs.

    Primateria Societe Anonyme, 122 Phil. 698).

    2. ID.; ACTION FOR DAMAGES BASED ON

    MALICIOUS PROSECUTION; ELEMENTS. — "To

    maintain an action for damages based on malicious

    prosecution, three elements must be present: First, the

    fact of the prosecution and the further fact that the

    defendant was himself the prosecutor, and that the

    action was finally terminated with an acquittal; second,

    that in bringing the action, the prosecution acted

    without probable cause; and third, the prosecutor was

    actuated or impelled by legal malice" (Ferrer vs. Vergara,

    52 O.G. 291).

    3. ID.; ID.; ID.; NOT PRESENT IN CASE AT BAR. — 

    Lao was only a witness, not the prosecutor in the estafa

    case. The prosecutor was his employer, Chan Tong or

    the St. Joseph Lumber. There was probable cause for

    the charge of estafa against Espiritu, as found andcertified by the investigating fiscal himself. Lao was not

    motivated by malice in making the affidavit upon which

    the fiscal based the filing of the information against

    Espiritu. He executed it as an employee, a salesman of

    the St. Joseph Lumber from whom Espiritu made his

    purchases of construction materials and who, therefore,

    had personal knowledge of the transaction. Although

    the prosecution of Espiritu for estafa did not prosper,

    the unsuccessful prosecution may not be labelled as

    malicious. "Sound principles of justice and public policydictate that persons shall have free resort to the courts

    for redress of wrongs and vindication of their rights

    without later having to stand trial for instituting

    prosecutions in good faith" (Buenaventura vs. Sto.

    Domingo, 103 Phil. 239).

    4. CONSTITUTIONAL LAW; DUE PROCESS OF

    LAW; DENIED IN CASE AT BAR; EFFECT. — There is

    merit in petitioner's contention that he was deprived of

    his day in court in the damage suit filed by Espiritu,

    due to the gross ignorance, negligence, and derelict

    of duty of Attorney Manuel Querubin whom

    employer had hired to act as counsel for him and the

     Joseph Lumber. However, Attorney Querubin neglec

    to defend Lao. He concentrated on the defense of

    company and completely forgot his duty to defend as well. He never informed Lao about the pre-t

    conferences. In fact, he (Attorney Querubin) neglec

    to attend other pre-trial conferences set by the cou

     When adverse judgment was entered by the co

    against Lao and the lumber company, Attor

    Querubin did not file a motion for reconsideration of

    decision. He allowed it to become final, because anyw

    Espiritu would not be able to satisfy his judgm

    against Chan Tong who had informed his lawyer t

    the St. Joseph Lumber was insolvent, had gone ou business, and did not have any leviable assets. A

    result, Espiritu levied on the petitioner's car to sat

    the judgment in his favor since the company itself h

    no more assets that he could seize. In view of

    foregoing circumstances, the judgment against Lao w

    a nullity and should be set aside. Its execution agai

    the petitioner cannot be allowed to proceed.

    D E C I S I O N

    GRIÑO-AQUINO, J p:

    For being a witness in an unsuccessful estafa c

     which his employer filed against a debtor who h

    defaulted in paying his just obligation, the petitio

     was sued, together with his employer, for damages

    malicious prosecution. The issue in this case is whet

    the damages awarded to the defaulting debtor may

    satisfied by execution against the employee's prope

    since his employer's business has already folded up.

    Petitioner Dennis Lao was an employee of the New

     Joseph Lumber & Hardware Supply, hereinafter ca

    St. Joseph Lumber, owned by the private responde

    Chan Tong. In January 1981, St. Joseph Lumber file

    collection suit against a customer, the priv

    respondent, Benjamin Espiritu, for unpaid purchase

    construction materials from St. Joseph Lumber.

    In November 1981, upon the advice of its lawyer,

     Joseph Lumber filed a criminal complaint for est

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    16/76

    Page 16 of 76

    against Espiritu, based on the same transaction. Since

    the petitioner was the employee who transacted

    business with Espiritu, he was directed by his employer,

    the firm's owner, Chan Tong, to sign the affidavit or

    complaint prepared by the firm's lawyer, Attorney

    Manuel Querubin.

    Finding probable cause after conducting a preliminary

    investigation of the charge, the investigating fiscal filed

    an information for estafa in the Court of First Instance

    of Quezon City against Espiritu. The case was however

    later dismissed because the court believed that

    Espiritu's liability was only civil, not criminal.

    On April 12, 1984, Espiritu filed a complaint for

    malicious prosecution against the petitioner and St.

    Joseph Lumber, praying that the defendants be orderedto pay him P500,000 as moral damages, P10,000 as

    actual damages, and P100,000 as attorney's fees.

    In his answer to the complaint, the petitioner alleged

    that he acted only as agent or employee of St. Joseph

    Lumber when he executed the affidavit which his

    employer submitted to the investigating fiscal who

    conducted the preliminary investigation of his

    employer's estafa charge against Espiritu. prLL

    The pre-trial of the case was set on October 30, 1984.

    Since the defendants and their counsel failed to appear

    in court, they were declared in default.

    On November 11, 1984, the defendants filed a motion

    for reconsideration of the order of default.

    On November 13, 1984, the motion was granted, and

    the order of default was set aside.

    On January 16, 1985, the defendants, including herein

    petitioner Lao, and their counsel, again failed to attend

    the pre-trial despite due notice to the latter who,

    however, failed to notify Lao. They were once more

    declared in default. The private respondent was allowed

    to present his evidence ex parte.

    On January 22, 1985, a decision was rendered by the

    trial court in favor of Espiritu ordering the defendants

    Lao and St. Joseph Lumber to pay jointly and severally

    to Espiritu the sums of P100,000 as moral damag

    P5,000 as attorney's fees, and costs.

    Petitioner's motion for reconsideration of the decis

     was denied by the trial court.

    On February 25, 1985, Lao filed a motion for new ton the ground of accident and insufficiency of eviden

     but it was denied by the trial court.

    He appealed to the Court of Appeals (CA-G.R. CV

    06796, "Benjamin L. Espiritu, plaintiff-appellee

    Dennis Lao and New St. Joseph Lumber and Hardw

    Supply, defendants-appellant"). The appellate co

    dismissed his appeal on May 21, 1987. He filed t

    special civil action of certiorari and prohibition

    partially annul the appellate court's decision andenjoin the execution of said decision against him. T

    petitioner avers that the Court of Appeals erred:

    1. in not holding that he (petitioner Lao) has a v

    defense to the action for malicious prosecution in C

    Case No. 84-M;

    2. in not holding that he was deprived of a day

    court due to the gross ignorance, negligence a

    dereliction of duty of the lawyer whom his emplo

    hired as his and the company's counsel, but who faito protect his interest and even acted in a man

    inimical to him; and

    3. in not partially annulling the decision of the t

    court dated January 22, 1985 insofar as he

    concerned.

     The petition is meritorious.

    Lao had a valid defense to the action for malici

    prosecution (Civil Case No. 84-M) because it was employer, St. Joseph Lumber, not himself, that was

    complainant in the estafa case against Espiritu. It w

    Chan Tong, the owner of the St. Joseph Lumber, w

    upon advice of his counsel, filed the criminal compla

    against Espiritu. Lao was only a witness in the case.

    had no personal interest in the prosecution of Espir

    for he was not the party defrauded by Espiritu.

    executed the affidavit which was used as basis of

    criminal charge against Espiritu because he was

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    17/76

    Page 17 of 76

    salesman who sold the construction materials to

    Espiritu. He was only an agent of St. Joseph Lumber,

    hence, not personally liable to the party with whom he

    contracted (Art. 1897, Civil Code; Philippine Products

    Co. vs. Primateria Societe Anonyme, 122 Phil. 698).

    LexLib

    "To maintain an action for damages based on malicious

    prosecution, three elements must be present: First, the

    fact of the prosecution and the further fact that the

    defendant was himself the prosecutor, and that the

    action was finally terminated with an acquittal; second,

    that in bringing the action, the prosecutor acted

    without probable cause; and third, the prosecutor was

    actuated or impelled by legal malice" (Ferrer vs. Vergara,

    52 O.G. 291).

    Lao was only a witness, not the prosecutor in the estafa

    case. The prosecutor was his employer, Chan Tong or

    the St. Joseph Lumber.

    There was probable cause for the charge of estafa

    against Espiritu, as found and certified by the

    investigating fiscal himself.

    Lao was not motivated by malice in making the affidavit

    upon which the fiscal based the filing of the information

    against Espiritu. He executed it as an employee, a

    salesman of the St. Joseph Lumber from whom Espiritu

    made his purchases of construction materials and who,

    therefore, had personal knowledge of the transaction.

    Although the prosecution of Espiritu for estafa did not

    prosper, the unsuccessful prosecution may not be

    labelled as malicious. "Sound principles of justice and

    public policy dictate that persons shall have free resort

    to the courts for redress of wrongs and vindication of

    their rights without later having to stand trial for

    instituting prosecutions in good faith" (Buenaventura

    vs. Sto. Domingo, 103 Phil. 239).

    There is merit in petitioner's contention that he was

    deprived of his day in court in the damage suit filed by

    Espiritu, due to the gross ignorance, negligence, and

    dereliction of duty of Attorney Manuel Querubin whom

    his employer had hired to act as counsel for him and

    the St. Joseph Lumber. However, Attorney Querubin

    neglected to defend Lao. He concentrated on the defense

    of the company and completely forgot his duty to defe

    Lao as well. He never informed Lao about the pre-t

    conferences. In fact, he (Attorney Querubin) neglec

    to attend other pre-trial conferences set by the court.

     When adverse judgment was entered by the co

    against Lao and the lumber company, Attor

    Querubin did not file a motion for reconsideration of

    decision. He allowed it to become final, because anyw

    Espiritu would not be able to satisfy his judgm

    against Chan Tong who had informed his lawyer t

    the St. Joseph Lumber was insolvent, had gone ou

     business, and did not have any leviable assets. A

    result Espiritu levied on the petitioner's car to sat

    the judgment in his favor since the company itself h

    no more assets that he could seize. cdphil

    In view of the foregoing circumstances, the judgm

    against Lao was a nullity and should be set aside.

    execution against the petitioner cannot be allowed

    proceed.

     WHEREFORE, judgment is hereby rendered parti

    setting aside the decision of the Court of Appeals da

    May 21, 1987, insofar as it declared the petition

    Dennis Lao, solidarily liable with St. Joseph Lumber

    pay the damages awarded to the private respondBenjamin Espiritu. Said petitioner is hereby absol

    from any liability to the private respondent arising fr

    the unsuccessful prosecution of Criminal Case No.

    20086 for estafa against said private respondent. Co

    against the private respondent.

    SO ORDERED.

    Narvasa, Cruz and Medialdea, JJ ., concur.

    Gancayco, J ., is on leave.

    FIRST DIVISION

    [G.R. No. 101706. September 23, 1992.]

    CONSOLIDATED PLYWOOD INDUSTRIES INC. A

    HENRY LEE, petitioners, vs. THE HONORAB

    COURT OF APPEALS, WILLIE KHO AND ALFR

    C.H. KHO, respondents.

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    18/76

    Page 18 of 76

    Villaraza & Cruz Law Offices for petitioner.

    Leonido C. Delante and Peter Nugas for private

    respondents.

    SYLLABUS

    1. CIVIL LAW; DAMAGES; TEMPERATE OR

    MODERATE DAMAGES; MAY BE RECOVERED WHEN

    SOME PECUNIARY LOSS HAS BEEN SUFFERED; NOT

    WARRANTED IN CASE AT BAR. — Article 2224 of the

    Civil Code provides: "Temperate or moderate damages,

    which are more than nominal but less than

    compensatory damages, may be recovered when the

    Court finds that some pecuniary loss has been suffered

    but is amount can not, from the nature of the case, be

    proved with certainty." The grant thereof is properunder the provision of Article 2205 of the Civil Code,

    which provides that damages may be recovered. In this

    case however, there was no showing nor proof that

    petitioner was entitled to an award of this kind of

    damages in addition to the actual damages it suffered

    as a direct consequence of private respondents' act. The

    nature of the contract between the parties is such that

    damages which the innocent party may have incurred

    can be substantiated by evidence.

    2. ID.; ID.; MORAL DAMAGES; MAY BE

    RECOVERED IF A PARTY NEGLECTED TO PERFORM

    ITS OBLIGATION IN BAD FAITH; CASE AT BAR. — It

    should be stated here that the hauling agreement

    between the petitioners and the private respondent had

    no fixed date of termination. It was a verbal agreement

    where the private respondents bound themselves until

    the loan with Equitable Bank in the personal account of

    petitioners had been fully paid. There was substantial

    compliance by the private respondents of theirobligations in the contract for about a year. The record

    showed that the remaining balance owing to the bank

    was only P30,000.00 which was not due until one (1)

    year and five (5) months after the breach by the private

    respondents or on September 4, 1980. However, the

    trial court found that private respondents acted with

    bad faith when it surreptitiously pulled out their hauler

    trucks from petitioner's jobsite before the termination of

    the contract. The trial court held: "The act of

    defendants in suddenly and surreptitiously withdrawing

    its hauler trucks from the jobsite and abandoning

    obligation of hauling the logs is indubitably a wan

     violation of its obligation, under the contract, a neg

    to perform its obligation in bad faith more particula

    in its stipulation to liquidate the cash advance obtain

    from Equitable Bank, for the law would not permit sdefendants to enrich themselves at the expense of

    plaintiffs."

    D E C I S I O N

    MEDIALDEA, J p:

     This is a petition for review on certiorari of the decis

    of the Court of Appeals in CA-G.R. No. 02784 entitl

    "Consolidated Plywood Industries, Inc. and Henry W

     v. Willie Kho and Alfred C.H. Kho," which modifieddecision of the Court of First Instance (now Regio

     Trial Court) of Baganga, Davao Oriental, by deleting

    award for moral damages, attorneys fees and act

    damages in the sum of P350,000.00 for the unfulfil

    import of logs, which were granted by the trial court.

    Consolidated Plywood Industries, Inc. (Corporation) a

    Henry Wee filed an action for breach of contract a

    damages against Willie Kho and Alfred C.H. Kho w

    the Court of First Instance (now Regional Trial Court

    Baganga, Davao Oriental. The facts as summarized

    the trial court are as follows: LLjur

    "xxx xxx xxx

    "Sometime in February, 1978, the plaintiff Corporat

    of which the plaintiff Henry Wee is the President, be

    in the business of logging and manufacturing tim

    products at its logging concession at Baganga a

    Caraga, Davao Oriental, on one hand, and

    defendants, father and son, who are operating a fleehauling trucks, entered into a verbal hauling agreem

     with the following terms and conditions to wit: t

    defendants shall haul the logs of the plaintiffs from

    concession area to the logpond at Baculin, Bagan

    Davao Oriental, at a hauling fee of P1.25/cu.m./km

    all species of timber, payable on weekly liquidat

     basis of all timber hauled and scaled at the Bagan

    office of the plaintiffs.

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    19/76

    Page 19 of 76

    "It was likewise agreed between the parties as a pre-

    condition before defendants' sending of the truck

    haulers to the jobsite that the plaintiffs provide

    financial assistance to the defendants in the amount of

    P180,000.00, cash, to defray cost of needed repairs and

    re-conditioning of the trucks and other expensesnecessary for the hauling operations.

    It was understood that this financial assistance was in

    the nature of cash advance obtained by the defendants

    from the Equitable Bank in the aggregate amount of

    P180,000.00 on the guaranty of plaintiff Henry Wee,

    payable by the defendants, and that the hauling

    services shall continue unless and until this loan from

    the Equitable Bank remain unpaid.

    "After the defendants obtained the aggregate amount ofP180,000.00 from the Equitable Bank on the guaranty

    of plaintiff Henry Wee by way of cash advance as

    financial assistance, the defendants proceeded to the

    jobsite at Baculin, Baganga, Davao Oriental, to

    commence the hauling service for the plaintiffs. cdrep

    "However, after hauling logs for about a year, or so,

    specifically on April 12, 1979, the defendants, without

    giving notice and information to the plaintiffs, suddenly

    and surreptitiously at nighttime, withdrew all its truckhaulers from the jobsite and returned to its base in

    Tagum, Davao del Norte, all in violation of the terms of

    the hauling agreement, particularly, the repayment of

    the cash advance to P180,000.00 obtained from the

    Equitable Bank, and that the hauling should continue

    until the said amount is fully paid.

    "Evidence on record show that all hauling services had

    been paid by the plaintiffs. In fact, it appears that from

    cash vales in the course of the hauling operation; the

    defendants have incurred an overdraft of P10,726.53

    still unliquidated.

    "Due to the sudden and surreptitious abandonment by

    the defendants of its hauling obligation in bad faith

    several logs have been left unhauled from the area

    which spawned serious and varied consequences to the

    great damage and prejudice of the plaintiffs.

    "The Aquarius Trading, a Taiwan log importer of

    plaintiffs, have charged the plaintiffs of P56,000

    reimbursements representing cancellation fee of

    chartered vessel, LC extension fee and other char

    due to plaintiffs' unfulfilled commitment of 1,500 cu.

    of logs because of the failure of hauling by defendants on the due date to the logpond. T

    plaintiffs, as a result, failed to realize a profit

    P150,000.00.

    "During the interim period between the sudd

    abandonment by the defendants in April, 1979 to M

    1979 when the plaintiffs have no immed

    replacement haulers, the plaintiffs could have produ

    5,000 cu. m. of logs, to fill other commitments, or a l

    of P350,000.00, was suffered by plaintiffs.

    "The defendants' violation of its undertaking a

    resulted in exposing the plaintiff Henry Wee to liabi

    to the Equitable Bank for the loans he guaranteed

    favor of the defendants in the total amount

    P180,000.00 which have become due, and demands

    payment resulted in unduly annoying and vexing s

    plaintiff which entitles him to moral damages in

    amount of P200,000.00." (pp. 302-305, Rollo)

     The evidence of the plaintiffs showed that they sent(2) letters to the defendants demanding the return

    the area of the six (6) hauler trucks to be used

    hauling the logs (pp. 103-104, Rollo) but the defenda

    did not heed the demand.

     The defendants waived their right to present eviden

    Hence, on January 3, 1983, a decision was rendered

    the basis of plaintiffs' evidence, the dispositive port

    of which reads: prLL

    "WHEREFORE, judgment is hereby rendered in favothe plaintiffs and against the defendants ordering

    defendants, jointly and severally to:

    (1) pay the plaintiffs the sum of P10,726.53, unp

    overdraft cash vales;

    (2) pay the plaintiffs the sum of P56,000

    reimbursement of charges of Aquarius Trading paid

    the plaintiffs;

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    20/76

    Page 20 of 76

    (3) pay the plaintiffs the sum of P150,000.00

    unrealized profit in the Aquarius Trading transaction

    unfulfilled;

    (4) pay the plaintiffs the sum of P350,000.00

    unfulfilled import of logs after the sudden withdrawal of

    defendants' trucks;

    (5) pay the plaintiffs P200,000.00 moral damages

    caused by the anxiety and annoyance as a consequence

    of the demands of the Equitable Bank on the

    defendants' unpaid cash advance of P180,000.00;

    (6) pay the plaintiffs attorneys' fees of P20,000.00;

    (7) to pay the plaintiffs litigation expenses of

    P40,000.00; and

    (8) pay the costs.

    "SO ORDERED." (pp. 306-307, Rollo)

    From the decision of the trial court, the defendants

    appealed to the Court of Appeals questioning the

    amount of damages awarded to the plaintiffs on the

    ground that the awards were not supported by

    sufficient evidence. The other grounds assigned by the

    defendants as errors were improper venue and lack of

    cause of action, in the latter case, because there was

    allegedly no contract to be enforced. LexLib

    On August 30, 1991, as already mentioned, the Court

    of Appeals rendered a decision modifying the trial

    court's decision. While the awards for the unpaid

    overdraft cash vales of P10,726.53; the sum of

    P56,000.00 as reimbursement of charges by Aquarius

    Trading paid by the plaintiff and the sum of

    P150,000.00 for unrealized profit in the Aquarius

    Trading transaction were affirmed, all the other awardsof damages for unfulfilled import of logs, attorney's fees

    and litigation expenses were deleted. The dispositive

    portion of the decision reads:

    "WHEREFORE, and in the light of all the foregoing, the

    appealed judgment is affirmed except the award of

    damages for 'unfulfilled import of logs,' moral damages

    and attorney's fees which are hereby denied and

    ordered deleted." (p. 354, Rollo)

    In this petition before Us, the petitioners Corporat

    and Henry Wee question the deletion of the awards

    unfulfilled import of logs, moral damages and attorn

    fees.

     We agree with the appellate court when it deleted

    award of P350,000.00 granted by the trial court

    actual damages allegedly incurred by petitioners for

    unfulfilled import of logs. It correctly held that th

     was no evidence to support such claim. This cla

    apparently refers to an alleged commitment to a cert

    Ching Kee Trading of Taiwan scheduled in June 1979

    distinguished from the claim for actual dama

    incurred in connection with its Aquarius Trad

    transaction. Henry Wee testified on the actual dama

    they incurred, as follows:

    "Q Let us go to the business of the corporation

     which you said that it has a contract for shipment

    logs, where are these contracts of shipments go (s

    LLpr

    "A The company has a commitment of export

    logs and wood products in foreign countries

    Hongkong and other foreign buyer on monthly ba

    and on that month on (sic) April to May, there wa

    contracted shipment of 1,500 anticipating to be hau by the services of the Willie Kho trucking, so that

    company has to reach their shipment on May 15, wh

     was fully contracted with the buyer.

    "Q I show to you this letter of Aquarius Trad

    Company, duly confirmed and accepted by Consolida

    Plywood Industries by Mr. Henry Wee, president, ple

    tell the Court what relation has this to the commitm

    of the shipment of logs?

    "A This is the commitment of shipment of logs1,400 on May 15, for Aquarius Trading.

    "Q Other than this commitment, do you have ot

    commitment to other buyer?

    "A Yes, we have commitment to Ching Kee Trad

    in Taiwan scheduled on June (TSN, 12 Jan. 1982,

    45-48: pp. 158-160, Rollo).

  • 8/16/2019 TORTS SAMPLE CASES IN FULL TEXT

    21/76

    Page 21 of 76

    The commitment to Aquarius Trading was sufficiently

    substantiated by documents (Exhs. "H" and "I").

    Petitioners were able to present the papers evidencing

    their transaction with said entity including the amount

    demanded from them as reimbursement for damages it

    incurred due to by petitioners' failure to ship theordered logs on time. In contrast, the alleged

    commitment of petitioner to Ching Kee Trading in

    Taiwan was not supported by evidence other than the

    self-serving statement of Wee. Nor did they present any

    other evidence which would show that they had other

    unfulfilled shipments for which they incurred damages

    because of the pull-out of private respondents' hauler

    trucks. But even granting for the sake of argument that

    there was in fact a commitment to Chingkee Trading,

    the shipment was scheduled some two (2) months afterthe private respondents pulled out their trucks from

    petitioners' jobsite on April 12, 1979. That would have

    left the petitioners with sufficient time to find other

    trucks which could be used for the job. Cdpr

    The petitioners insist that if the appellate court did not

    consider the P350,000.00 damages for unfulfilled

    shipments, it should have awarded this amount as a

    form of temperate or moderate damages.

    Article 2224 of the Civil Code provides: "Temperate ormoderate damages, which are more than nominal but

    less than compensatory damages, may be recovered

    when the Court finds that some pecuniary loss has

    been suffered but its amount can not, from the nature

    of the case, be proved with certainty." The grant thereof

    is proper under the provision of Article 2205 of the Civil

    Code, which provides that damages may be recovered.

    In this case however, there was no showing nor proof

    that petitioner was entitled to an award of this kind of

    damages in addition to the actual damages it sufferedas a direct consequence of private respondents' act. The

    nature of the contract between the parties is such that

    damages which the innocent party may have incurred

    can be substantiated by evidence.

    The Court, however, believes that petitioner is entitled

    to an award for moral damages. However, the award

    granted by the trial court in the amount of P200,000.00

    is excessive. It should be stated here that the hauling

    agreement between the petitioners and the private

    respondent had no fixed date of termination. It wa

     verbal agreement where the private respondents bou

    themselves until the loan with Equitable Bank in

    personal account of petitioners had been fully pa

     There was substantial compliance by the priv

    respondents of their obligations in the contract about a year. The record showed that the remain

     balance owing to the bank was only P30,000.00 wh

     was not due until one (1) year and five (5) months a

    the breach by the private respondents or on Septem

    4, 1980 (p. 109, Rollo). However, the trial court fou

    that private respondents acted with bad faith when

    surreptitiously pulled out their hauler trucks fr

    petitioner's jobsite before the termination of

    contract. The trial court held:

    "The act of defendants in suddenly and surreptitiou

     withdrawing its hauler trucks from the jobsite a

    abandoning its obligation of hauling the logs

    indubitably a wanton violation of its obligation, un

    the contract, a neglect to perform its obligation in b

    faith more particularly. In its stipulation to liquidate

    cash advance obtained from Equitable Bank, for the

     would not permit said defendants to enrich themsel

    at the expense of the plaintiffs." (p. 305, Rollo). prLL

     Thus, an award of P50,000.00 for moral damagessufficient.

     The award for attorneys fees by the trial court in

    amount of P20,000.00 is likewise proper. Petitioner w

    forced to litigate in court for the recovery of act

    damages incurred by him because the priv

    respondent ignored petitioners' letters demanding t

    they return to the area and perform their obligations

     ACCORDINGLY, the decision of the Court of Appeal

    MODIFIED. The award of P50,000.00 as moral dama

    and P20,000.00 as attorney's fees are hereby granted

    addition to the damages awarded by the appellate cou

    SO ORDERED.

    Griño