town of southbury department of public works 2014
TRANSCRIPT
![Page 1: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/1.jpg)
SOUTHBURY ROAD PROGRAM
Town of SouthburyDepartment of Public Works
2014
![Page 2: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/2.jpg)
Southbury Road Program Annual Funding HistoryFiscal Year Appropriation Amount
2001-2002 $800,000
2002-2003 $800,000
2003-2004 $465,000
2004-2005 $465,000
2005-2006 $465,000
2006-2007 $1,500,000
2007-2008 $2,148,000
2008-2009 $2,485,620
2009-2010 $2,243,096
2010-2011 $1,700,000
2011-2012 $2,000,000
2012-2013 $2,000,000
2013-2014 $2,000,000
2014-2015 $2,069,000
![Page 3: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/3.jpg)
Road Maintenance Cost Analysis
![Page 4: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/4.jpg)
PAVEMENT MAINTENANCE METHODOLOGIES
1. Reconstruction: Most intrusive, most expensive, most time-
consuming Improves alignment issues, width, curves, humps,
cross section, etc. Usually requires total storm drainage system Replaces entire road structure, base and pavement
2. Reclamation: Grinds existing pavement into existing base Improves minor alignment issues Often involves minor drainage improvements Replaces entire pavement structure
![Page 5: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/5.jpg)
PAVEMENT MAINTENANCE METHODOLOGIES
3. Mill & Pave: Grinds off top pavement surface Maintains existing alignment Replaces tops on existing catch basins Replaces top course of pavement
4. Chip Seal Maintains entire pavement structure Adds asphalt seal coat embedded with stone
chips5. Crack Seal:
Maintains entire pavement structure Seals individual cracks with asphalt material
![Page 6: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/6.jpg)
GRAVEL ROAD MAINTENANCE METHODOLOGIES
1. Re-grade Gravel: Most time-consuming, highest maintenance Highly susceptible to wash outs Dust issues Difficult to maintain in winter
2. Bituminous Base Course & Chip Seal Provides many benefits of paving while
retaining feel and appearance of gravel Support of Planning Commission & Land Use
Office
![Page 7: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/7.jpg)
IWORQ SAMPLE
![Page 8: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/8.jpg)
![Page 9: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/9.jpg)
![Page 10: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/10.jpg)
ROAD WORK CARRIED INTO 2014 CONSTRUCTION SEASON
![Page 11: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/11.jpg)
• Bucks Hill Rd. Route 6 to I 84 Bridge
• Skyview Drive*• Beecher Rd.*• Sunburst Drive*• Settlers Hill Rd.*• Glen Lane*• Hidden Brook*• Greenwood Drive*• Hemlock Ridge• Pleasant Drive*
• Grasslands Rd.*• Low Bridge Rd.*• Stiles Rd.*• Heritage Rd.• New Wheeler Rd.• Sunset Ridge Rd.*• Stoney Corners Lane• Country Woods Rd.• Sachem Rd.
* Completed
Crack Sealing Schedule for 2014
![Page 12: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/12.jpg)
Chip Sealing Schedule for 2014
Bucks Hill Rd. Route 6 to I-84 Bridge Reservoir Rd. Old Woodbury Rd. Tuttle Rd. Judd Rd. High Point Rd. Flood Bridge Rd. East Flat Hill Rd. Spruce Brook Rd.
![Page 13: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/13.jpg)
Peter Road
Cobbler Lane
Forest Road
Wolf Pit Road
Ivy Hill Rd.
Flag Swamp Road
Hollow Swamp Road
Paving Schedule for 2014
![Page 14: Town of Southbury Department of Public Works 2014](https://reader035.vdocument.in/reader035/viewer/2022062712/56649c9d5503460f9495c877/html5/thumbnails/14.jpg)
Southbury Road Program Annual Funding HistoryFiscal Year Appropriation Amount
2001-2002 $800,000
2002-2003 $800,000
2003-2004 $465,000
2004-2005 $465,000
2005-2006 $465,000
2006-2007 $1,500,000
2007-2008 $2,148,000
2008-2009 $2,485,620
2009-2010 $2,243,096
2010-2011 $1,700,000
2011-2012 $2,000,000
2012-2013 $2,000,000
2013-2014 $2,000,000
2014-2015 $2,069,000