TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE

CITYBULGARIA

Infrastructure Working Group Kiev, 11 May 2011

Page 2: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY

Page 3: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY

РУСЕ

Page 4: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

LocationThe city of Ruse is located on the Danube River and it is an

important intermodal junction with a unique strategic location, a significant trade, commercial and transport center;

An only railway terminal in North Bulgaria;

The terminal is within two European corridors :

-VII - - the rivers Rein – Main – Danube and

-IX - Guergevo–Ruse–Dimitrovgrad–Alexandrupolis /Istanbul;

The Port of Ruse is the biggest Bulgarian river port;

Ruse Railway Station is connected with the big Black Sea Port of Varna through the railway line Ruse – Varna, representing a very important connection for the intermodal transport

Page 5: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Scope of the project

Phase I - Technical Assistance for Construction of

Intermodal Terminal in the Region of Ruse City

Phase II - Construction of Intermodal Terminal in

the Region of Ruse City

Page 6: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Scope of the project

“Technical Assistance for Construction of Intermodal Terminal in the Region of Ruse City” project will be started with expected financing under Operational Programme on Transport

Activities:

Preparation of needs assessment and definition of the project;

Preparation of financial and economic “cost - benefit” analyses;

Preparation of a preliminary design for construction of intermodal terminal in Ruse;

Analysis of the options for public – private partnership for construction and operation of intermodal terminal in Ruse and preparation of PPP strategy;

Preparation of public procurements and tender documentation.

Page 7: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Project objectives Balancing of different transport modes to the advantage of

railway transport attracting transportations from road to railway transport;

Increase of international intermodal transportations with the countries from TRACECA region and Eastern and Central Europe;

Intermodality improvement in the South – East region of EU;

Increase of transport market competitiveness by improvement of railway services quality;

Development of reliable transport by integration of different transport modes and creation of conditions for development of intermodal cooperation.

Page 8: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Construction of IMT – area of 150 - 200 dca

railway Operative road

interaction water

Modality – vehicle wagon ship

Reliability – transfer of freight from road to railway transport with the purpose of decrease of harmful emissions in air

Save of traveling time - time stop shortening during border crossings results in freights delivery acceleration

Technical criteria

Page 9: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Forecast for the volumes of freight transportation through Ruse Railway

Junction

0

5000

10000

15000

20000

25000

2015

2020

2015 18700 12500

2020 22000 14700

от ИМТ към ж .п.мрежа от ж .п.мрежа към ИМТ

Page 10: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Economic criteriafrom a survey about private railway Operator

• Forecasted period 2025• Investment costs – 15 mln. euro

for construction of the terminal by NRIC• Construction duration - 24 months• Investment costs – 1.160 mln. euro

for equipment by a private railway operator • Current costs – 508 000/ per 1 year

(for maintenance and operation)• Terminal return period – over 40 years

on the basis of accounts for other terminals • Return period – 4.5 years

of the equipment in case of 25 years operation by the Operator

Page 11: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Economic criteria

The possibilities for application of PPP will be estimated during the last stage of the project for

technical assistance

Public partner partnership (PPP)

Page 12: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Environment

Decrease of harmful emissions;

Decrease of noise pollution by noise protection projects implementation in case of necessity;

Decrease of energy sources consumption.

Page 13: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Political criteria

The project is included in the following strategic documents: “Strategy for Integration of the Bulgarian Railway

Infrastructure into the European Network for Intermodal Transport”

“Strategy for Development of the Transport Infrastructure of Republic of Bulgaria until 2015”

The commencement and implementation of the project depend on the conclusion of “Technical Assistance for Construction of Intermodal Terminal in the Region of Ruse City” project.

Page 14: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Expected results Creation of conditions for development of intermodal

transportations; Improvement of the intermodal infrastructure, that results in

economic growth in the region through reliable transport freight services;

Increase of the working positions and standard of living in the region;

Increase of transport services quality; Achieved balance between the different transport modes, developed

intermodal transportation using «sea-railway-river» system; Increased trade between Bulgaria and Eastern and Central

European countries; Decrease of harmful emissions and motor-car accidents on

highways.

Page 15: TRACECA CONSTRUCTION OF INTERMODAL TERMINAL IN THE REGION OF RUSE CITY BULGARIA Infrastructure Working Group Kiev, 11 May 2011

Thank you for the attentionThank you for the attention ! !