tracker summary alan bross mice cm october 10, 2007
TRANSCRIPT
Tracker Stations
12 of 15 complete (includes LED scan) Last three only require machine carbon-fiber support
frame station bundling connectorising gluing polishing =========================================================
5 done done done done 6 done done done done 7 done done done done 8 done done done done 9 done done done done 10 done done done done 11 done done done done 12 done done done done 13 done done done done 14 done done done done 15 done done done done 16 done done done done 17 done done done done 18 done done - - 19 done done - -
Station Light Yield QC
We are still working on LY QC procedure and data analysis. Will QC all stations for Tracker 1 before assembling
Source moves parallel to plane of station
Choice of Sr90 or Co57
Limited to straight lines (arbitrary angle & offset) for QA purposes
Absolute position reproducible to 2 μm
Source V
WX
V
W
X
Active Area
Motion Axis 1
Mot
ion
Axi
s 0
Source
Cross-section:
Tracker Station
Cryo and Readout
Production cryostats 1 and 2 are complete They have been fully characterized However, the AFE backplanes still need to be installed And final AFE electrical/power test (see slide)
Cryostat #3 is nearing completion. Should be ready for first cooldown in about 2 weeks
Cassettes have been released from D0 Cryostat #4 still needs cassettes. We have tentative agreement in place with D0 for the
additional 2 cassettes needed for Cryostat #4 George Ginther asked for a document detailing how the
cassettes will be operated, environmental conditions, fault analysis and safety precautions, personnel training, etc.
The first draft is complete and has been reviewed by George. Some issues were identified (crane operation in MICE Hall for example) and are being addressed. The document is being updated
Tracker Racks
The Wiener power supplies for the AFE boards have arrived and Bill Luebke and and John Fogelsong have developed a plan for power distribution. The cable runs and lengths for the power and LVDS cables have now been set
Assembly of the final rack(s) has begun LVDS Cables have been ordered (10m length) Components for power cabling (cables, fuse assemblies,
connectors) have been ordered. The plan is to fully test the racks (one for two
cryostats) at Fermilab to make sure that AFE operation is correct.
Power conversion will then have to occur when the equipment arrives in the UK
This is the critical path and will determine when the system can be shipped to RAL
AFEIIt Power Distribution
Weiner Power Supply(+5.5, +5, 12, +3.3)V
Trunk Line
Fuse Panel
Cryo 2 DropCryo 1 Drop
Schedule for Tracker Services Rack
Goal: Test Cryo 1 and 2 electrically as full system at Fermilab
All AFEIIts, LVSBs, Low-voltage power and distribution cables
Crate and ship to RAL Have at RAL by November 5, 2007 (1 week uncertainty at
the moment).
Tracker Readout ElectronicsPreparation for Cosmic Ray Test
Finish firmware by Oct. 5 (Still working on VLSB)
Run cryostat/AFE-IIt/VLSB tracker readout tests at FNAL from Oct. 8 – 19. (Set to start)
Ship tracker readout system by Oct. 29 (was Oct. 22)
Unpack tracker readout system at RAL by Nov. 5 (may slip to Nov. 12)
AFE-IIt Boards
8 boards for 2 cryostats fully tested and characterized.
4 boards assigned to 3rd cryostat, not yet tested and characterized
11 spare boards available, 4 of which will be assigned to 4th cryostat.
23 AFE-IIt boards available for MICE
VLSB Boards
Parts and boards are at FNAL.
Technicians have started stuffing boards.
First 1 or 2 boards may be done in ~ 1 week.
FNAL will test basic functionality of data registers.
Electronics Summary
Preliminary firmware package being set up for data readout tests at FNAL Some work still remaining
Cryostat characterization and VLSB board assembly ongoing
End in sight for full firmware for MICE (~ 600 triggers/ms)