tracker summary alan bross mice cm october 10, 2007

14
Tracker Summary Alan Bross MICE CM October 10, 2007

Upload: berniece-webster

Post on 04-Jan-2016

229 views

Category:

Documents


3 download

TRANSCRIPT

Tracker Summary

Alan BrossMICE CM

October 10, 2007

Tracker Stations

12 of 15 complete (includes LED scan) Last three only require machine carbon-fiber support

frame station bundling connectorising gluing polishing =========================================================

5 done done done done 6 done done done done 7 done done done done 8 done done done done 9 done done done done 10 done done done done 11 done done done done 12 done done done done 13 done done done done 14 done done done done 15 done done done done 16 done done done done 17 done done done done 18 done done - - 19 done done - -

Station Light Yield QC

We are still working on LY QC procedure and data analysis. Will QC all stations for Tracker 1 before assembling

Source moves parallel to plane of station

Choice of Sr90 or Co57

Limited to straight lines (arbitrary angle & offset) for QA purposes

Absolute position reproducible to 2 μm

Source V

WX

V

W

X

Active Area

Motion Axis 1

Mot

ion

Axi

s 0

Source

Cross-section:

Tracker Station

Tracker 1 Assembly

Cryo and Readout

Production cryostats 1 and 2 are complete They have been fully characterized However, the AFE backplanes still need to be installed And final AFE electrical/power test (see slide)

Cryostat #3 is nearing completion. Should be ready for first cooldown in about 2 weeks

Cassettes have been released from D0 Cryostat #4 still needs cassettes. We have tentative agreement in place with D0 for the

additional 2 cassettes needed for Cryostat #4 George Ginther asked for a document detailing how the

cassettes will be operated, environmental conditions, fault analysis and safety precautions, personnel training, etc.

The first draft is complete and has been reviewed by George. Some issues were identified (crane operation in MICE Hall for example) and are being addressed. The document is being updated

Tracker Racks

The Wiener power supplies for the AFE boards have arrived and Bill Luebke and and John Fogelsong have developed a plan for power distribution. The cable runs and lengths for the power and LVDS cables have now been set

Assembly of the final rack(s) has begun LVDS Cables have been ordered (10m length) Components for power cabling (cables, fuse assemblies,

connectors) have been ordered. The plan is to fully test the racks (one for two

cryostats) at Fermilab to make sure that AFE operation is correct.

Power conversion will then have to occur when the equipment arrives in the UK

This is the critical path and will determine when the system can be shipped to RAL

AFEIIt Power Distribution

AFEIIt Power Distribution

Weiner Power Supply(+5.5, +5, 12, +3.3)V

Trunk Line

Fuse Panel

Cryo 2 DropCryo 1 Drop

Schedule for Tracker Services Rack

Goal: Test Cryo 1 and 2 electrically as full system at Fermilab

All AFEIIts, LVSBs, Low-voltage power and distribution cables

Crate and ship to RAL Have at RAL by November 5, 2007 (1 week uncertainty at

the moment).

Tracker Readout ElectronicsPreparation for Cosmic Ray Test

Finish firmware by Oct. 5 (Still working on VLSB)

Run cryostat/AFE-IIt/VLSB tracker readout tests at FNAL from Oct. 8 – 19. (Set to start)

Ship tracker readout system by Oct. 29 (was Oct. 22)

Unpack tracker readout system at RAL by Nov. 5 (may slip to Nov. 12)

AFE-IIt Boards

8 boards for 2 cryostats fully tested and characterized.

4 boards assigned to 3rd cryostat, not yet tested and characterized

11 spare boards available, 4 of which will be assigned to 4th cryostat.

23 AFE-IIt boards available for MICE

VLSB Boards

Parts and boards are at FNAL.

Technicians have started stuffing boards.

First 1 or 2 boards may be done in ~ 1 week.

FNAL will test basic functionality of data registers.

Electronics Summary

Preliminary firmware package being set up for data readout tests at FNAL Some work still remaining

Cryostat characterization and VLSB board assembly ongoing

End in sight for full firmware for MICE (~ 600 triggers/ms)

R8 Cosmic Ray Test

We are on track to start full system test (Tracker, CKOV, TOF, KL, DAQ, L1 Trigger) in second half of November

Top plate

Patch Panel

M24 screwed rod

~484mm~2630mm