training r&m of boilers
TRANSCRIPT
-
7/31/2019 Training R&M of Boilers
1/45
23 May 2012 PMI Revision 00 1
Renovation &
Modernisation of
Boiler
-
7/31/2019 Training R&M of Boilers
2/45
23 May 2012 PMI Revision 00 2
When to do R&M of Boiler?R&M of Steam Generator is to be taken up under thefollowing conditions:
1.The unit has logged more than 200,000 hours of operation,i.e. its design life
2.RLA report has indicated requirements of major
replacements
3.The boiler is failure prone; e.g. frequent tube leakages
4.The boiler is not able to generate rated load
5.There is major off design performance; e.g. high metaltemperatures, high flue gas exit temperature, high unburntcarbon
6.On grounds of environmental or safety considerations
-
7/31/2019 Training R&M of Boilers
3/45
23 May 2012 PMI Revision 00 3
Inputs for R&M
1.Condition Assessment (CA) & Residual LifeAssessment (RLA) Studies
2.Thermal Performance Test (TPT), If Necessary
-
7/31/2019 Training R&M of Boilers
4/45
23 May 2012 PMI Revision 00 4
CA & RLA Studies
-
7/31/2019 Training R&M of Boilers
5/45
23 May 2012 PMI Revision 00 5
Intent of RLA
Restoration / up-rating of Generation capacity on a
continuous, safe and reliable basis. To increase unit availability and reliability on Sustainable
basis to meet the current requirements like ABT.
Achieving rated or better efficiency of the unit so that the
COG remains competitive. Achieving an extended competitive plant-life of another 15
years at least.
To improve safety of plant and personnel.
To meet current statutory and environmental norms.
-
7/31/2019 Training R&M of Boilers
6/45
23 May 2012 PMI Revision 00 6
CA & RLA
REVIEW OF OPERATIONAL HISTORY OF EQUIPMENTS:
Details of start up and Shut down Operational Regime Maintained Duration and extent of parameter escalation
Steam temperature and water Chemistry Observation During Planned Shut downs Replacements during routine maintenance and forced
outages Detailed Metallurgical Analysis
Analysis/Reports on premature failures
-
7/31/2019 Training R&M of Boilers
7/45
23 May 2012 PMI Revision 00 7
CA & RLA
Pre Outage Planning and Survey: Record nameplate details & general description of all
equipments Compilation of design details Review of these compiled data and assess the present
condition of equipment /system
Hot Walk down Survey Survey of the equipment / system while in operation Reference marking to be made in piping system, hangers &
supports, buckstays,etc Identify and prepare a list of missing items in equipment /
system
Cold Walk down Survey Inspection for detection of any visible abnormalities Measurement of steam flow path, thermal clearance, fitting
clearance, etc
-
7/31/2019 Training R&M of Boilers
8/45
23 May 2012 PMI Revision 00 8
CA & RLA
Visual Examination: To detect signs of overheating of tubes, for swelling, blistering
and warping To identify signs of corrosion or erosion To examine convection pass tube banks for detection of
misalignment of tubes To assess condition of all headers for ligament cracks etc. To determine the condition of components in the penthouse
including header supports and structural members To determine boiler setting integrity Examination of drum internals
Dimensional Measurement:
The components liable for deformation or distortion due towear / creep namely, headers, pipes, hangers, supportstructures etc. are to be thoroughly cleaned and dimensionsto be measured to compare with original / previous record.
-
7/31/2019 Training R&M of Boilers
9/45
23 May 2012 PMI Revision 00 9
CA & RLA
Videoscopic Inspection:
Videoscopic examination of all header internals. Digitalphotographs are taken of each header internal surface andeach header / stub connection. Videoscopic examinationdetermines the following:a) Internal cracks on headers/nipples/stubs/ ligamentsb) Condition of internal cleanliness
c) Oxide scale
Non-Destructive Tests: Dye- penetrant Examination (DPT) Dye-penetrant examination using fluorescent dye are used for
detection of surface crack / porosity / discontinuity of headerligament joints, pipe weld joints, attachment weld joints, valvebody / spindle / seal etc.
-
7/31/2019 Training R&M of Boilers
10/45
23 May 2012 PMI Revision 00 10
CA & RLA
Non-Destructive Tests(Contd.): Magnetic Particle Inspection (MPI)
Magnetic particle inspection using wet fluorescent methodshall be employed for detection of surface and sub-surfacecrack / discontinuity of header ligament joints, pipe weld
joints, attachment weld joints, valve body / spindle / seal etc.In case of detection of any crack, the depth shall bemeasured with the help of crack depth meter based on
electrical potential drop principle or ultrasonic principle
Ultrasonic Examination (UT) Ultrasonic Examination method shall be employed for
detection of sub-surface crack, loose bonding, stress crackingor any kind of discontinuity mainly in the longitudinal and
circumferential seams of the boiler drum, girdling loops of allhigh temperature tube panels, butt weld joints, attachmentwelds and stub joints of the steam & water headers & pipesetc.
-
7/31/2019 Training R&M of Boilers
11/45
23 May 2012 PMI Revision 00 11
CA & RLA
Non-Destructive Tests(Contd.): In situ oxide scale measurement
It is a high frequency ultrasonic method which is to be carriedout at various locations, especially in the tubes where themetal temperatures are maximum, in the platen & finalsuperheater and reheater assemblies.
Furnace Corrosion & Thickness Mapping
Continuous tube OD scanning method based on lowfrequency electro-magnetic principle to carry out the detailthickness and corrosion mapping of all the accessible tubesin the furnace zone
Metallographic Replication (RPL)
Metallographic examination by portable optical microscopeand surface replication technique are carried out to assessthe present microstructure condition of the componentssubjected to damage due to creep, temper embrittlement,stress corrosion cracking and thermal fatigue (low cyclefatigue).
-
7/31/2019 Training R&M of Boilers
12/45
23 May 2012 PMI Revision 00 12
CA & RLA
Non-Destructive Tests(Contd.): Hardness Testing
Hardness testing of tubes, weld joints, headers, pipes etc. arecarried out, wherever required, to ascertain any change inmetallography and to find out residual stresses. Hardnessmeasurement are to be compulsorily taken at the spots wherereplica has been taken
In-Situ Chemical Analysis (CA) In-situ chemical analysis is to be employed for determining
and categorizing the steel grade of various superheater andreheater coils with the help of instruments based on eitherOptical Emission Spectroscopy (OES) principle orradioisotope excited x-ray fluorescence analyzer.
-
7/31/2019 Training R&M of Boilers
13/45
23 May 2012 PMI Revision 00 13
CA & RLA
Destructive Tests: Tube samples and tube deposits from various boiler locationsalong with boiler drum deposit are collected for destructivetests. These are analyzed at reputed laboratories for:
Stress rupture test for mechanical properties Microstructure evaluation to find out metallurgical degradation
Chemical analysis of deposits
-
7/31/2019 Training R&M of Boilers
14/45
23 May 2012 PMI Revision 00 14
After collection of the various data asdiscussed and analysis thereof remaining
life of the boiler is calculated &recommendations are given accordingly.
-
7/31/2019 Training R&M of Boilers
15/45
23 May 2012 PMI Revision 00 15
Thermal Performance Test
The broad objectives of the TPT can be summarized as
follows: To evaluate the present thermal efficiency of the unit
To establish the steam, water and flue gas temperatureprofile and heat balance over different sections of theboiler
To establish flue gas velocity profile over differentsections of the boiler
To establish excess air and air ingress levels at differentsections in the boiler, particularly air heater leakage.
To analyze the data collected and compare withpredicted performance data
To identify shortfalls in performance and causes for thesame.
-
7/31/2019 Training R&M of Boilers
16/45
23 May 2012 PMI Revision 00 16
R&M of Boiler
-
7/31/2019 Training R&M of Boilers
17/45
23 May 2012 PMI Revision 00 17
Boiler Downtime Matrix(A typical case)
Pressure Parts Failure Pattern of a Typical
Boiler
Re heater
13%
Sec. Conv.Sections
8%Water Wall
11%
Economiser
26%
Pri S/H7% Platen S/H
7%
Sec S/H
28%
-
7/31/2019 Training R&M of Boilers
18/45
23 May 2012 PMI Revision 00 18
Interactive IssuesCoal Quality
Deterioratio
Mill
Capacity
Coal
Requirement
Higher
Economizer
erosion
Burner
Effectiveness
Reduced
Boiler
Efficienc
Steam
Throughput
Tube Metal
Tem .Hi h
Tube Failures
Major Boiler Issues
Secondary
Combustion
Air Ingress
Air Preheater
Erosion
Secondary
S/ H & other
Pr. Parts
Gas Temp.
High
PA Fan
Capacity
SA - PA Air
Mismatch
Flue Gas Velocities
Higher
Reheater Temp.
Control Dampers
Gas Q uantity High
C S
-
7/31/2019 Training R&M of Boilers
19/45
23 May 2012 PMI Revision 00 19
Issues PoorAvailability /
Reliability
Lower Efficiency Inadequate
Steaming
Parameters
Higher Generation cost Increased Emission
Levels & SPM
Areas * Pr. Parts * Operating
Parameters
* Milling System * Operation &
Maintenance practices
* ESP
* Spares
Inventory
* Boiler Losses * Health of Pr. Parts * Turbine steam demand * Burners
* Fan Margins
Reasons * ObsoleteTechnology
* Higher unburnt * Coal Quality * Unavailability of genuine
spares / OEM spares
* Completed
Design Life
* Increased
Moisture in coal
* Air Ingress * Quality of spurious
spares
* Increase dry gas
loss / air ingress
*Ageing of Pr. Parts * Design deficiency in
Turbine
* Wear & Tear of
Components
Remedies * Replacement /repair of worn out
parts
* Replacement of
furnace with
membrane panels
* Milling system
upgradation
* Switch over to new
technology
* Addition of more fields in
ESP
* Pent house
sealing with
* Replacement of Pr.
Parts with new design
* O&M Management
system
* Increasing the height of
fields / adding parallel
*Turbine Retrofit * Installtions of improved
burners / Low Nox burners
Achievements
post R&M
* Increased
avalbty.
* Improved
Efficiency
* Restoration of
Design Parameters
* Reduced downtime and
maintenance
* Reduced emission levels
* Improved PLF &
PUF
* Reduction in generation
cost
* Life extension
Issues, Causes & Solution
-
7/31/2019 Training R&M of Boilers
20/45
23 May 2012 PMI Revision 00 20
Issue Life ExtensionComponent Typical
Life
LimitingFactor
Lead TimeFor
Ordering
Outage Requiredfor Installation
Headers-Superheater &
ReheaterPipes MS &RH
Creep ,Thermal
fatigue
2 3 years 13 weeks (largeheaders),6-9
weeks (smallheaders)
Tubes-Furnace
wall,Superheater &Reheater
Fireside
corrosion,Creep,overheating
18 months 10-12 weeks (for
completesuperheater orReheater units)
-
7/31/2019 Training R&M of Boilers
21/45
23 May 2012 PMI Revision 00 21
Issue Life Extension
Component Typical
LifeLimitingFactor
Lead Time
ForOrdering
Outage Required
for Installation
Tubes
Economisercoils, S-paneletc.
Ash
erosion
18 months 10-12 weeks (for
completeEconomiser, Spanel etc.)
High Pressure
Valves
Creep ,
Thermalfatigue
18 months 3-4 weeks
-
7/31/2019 Training R&M of Boilers
22/45
23 May 2012 PMI Revision 00 22
Issue: Inadequate SteamingParameters
AREAS
Milling System Health of Pressure Parts Fan Margins System/ Process / Turbine demand
continue
-
7/31/2019 Training R&M of Boilers
23/45
23 May 2012 PMI Revision 00 23
Issue: Inadequate SteamingParameters
Reasons Restricted mill capacity to handle the increased coal
demand due to poor coal quality
Poor health of Pr. Parts not permitting operation at
the rated parameters / capacity
Inadequate fan margins to cater increased coaldemand
Lower system demand
Continue
-
7/31/2019 Training R&M of Boilers
24/45
23 May 2012 PMI Revision 00 24
Issue: Inadequate SteamingParameters
Remedies Up gradation of Milling system
Re- Design of Boiler / Replacement of Pr. Parts withimproved design taking advantage of improved
technology & materials Replacement of tangent / spaced tube construction
with membrane panel
Repair / Replacement / upgradation of Fans
Arresting air ingress Addition of heating surface in equipment like
economizer and APH
continue
-
7/31/2019 Training R&M of Boilers
25/45
23 May 2012 PMI Revision 00 25
Issue: Low Efficiency
Areas
Improper design of boiler
Milling System
Burners
Air Preheaters Furnace sealing
-
7/31/2019 Training R&M of Boilers
26/45
23 May 2012 PMI Revision 00 26
Issue: Low EfficiencyReasons
Improper heat pick up design resulting in high exitflue gas temperature
Operational restrictions like metal temperaturerestrictions causing loss of Rankin efficiency
Poor coal fineness due to milling systemunderperformance
Improper mixing of air & fuel in burners resulting incarbon loss
Poor performance of air preheaters resulting in highflue gas exit temperature (FGET)
Air ingress into the furnace leading to high flue gasloss
-
7/31/2019 Training R&M of Boilers
27/45
23 May 2012 PMI Revision 00 27
Issue: Low EfficiencyRemedies
Redesign of boiler pressure parts based on TPTresults: Addition / deletion of heat transfer surface invarious pressure parts sections / APH
Change in metallurgy to allow higher tube metaltemperatures
Upgradation of milling system
Improved burner design
Renovation of furnace sealing including penthouse
Upgradation of Fans if Fans are underperforming
-
7/31/2019 Training R&M of Boilers
28/45
23 May 2012 PMI Revision 00 28
AREAS & CAUSES
Poor coal quality Combustion Technology Burners and operating
constraints on fans
Fuel fineness Milling capacity & internals ESP Sizing constraints due to fuel quality Continue
Issue: Increased Emission & SPM
-
7/31/2019 Training R&M of Boilers
29/45
23 May 2012 PMI Revision 00 29
Issue: Increased Emission & SPM
REMEDIES
Installation of Low Nox Burners ESP
Addition of new fields in ESP Increasing the height of existing fields
Addition of parallel stream Installation of latest controllers like EPIC II Introduction of Bag filters
ACHIEVEMENTS POST R&M Reduction in the Nox level Reduction in particulate matter
-
7/31/2019 Training R&M of Boilers
30/45
23 May 2012 PMI Revision 00 30
A Case Study:
R&M & LEP - DPL, Durgapur
-
7/31/2019 Training R&M of Boilers
31/45
23 May 2012 PMI Revision 00 31
R&M & LEP - DPL, Durgapur
DPL has 5 boilers (2 x 30 MW and 3 x 75MW) whichare almost 30 years old. The boilers were unable toachieve the rated parameters, mainly due to thefollowing reasons:
Deteriorated coal quality (High ash & Moisture, LowerGCV).
Improper combustion Ageing of boiler Pressure & non Pressure Parts.
DPL Durgapur
-
7/31/2019 Training R&M of Boilers
32/45
23 May 2012 PMI Revision 00 32
DPL, Durgapur Major Objectives
Improvement in Boiler Efficiency
Restoration of Rated Evaporation
Restoration of Steaming parameters Arresting Air Ingress
Reduction in downtime
DPL D
-
7/31/2019 Training R&M of Boilers
33/45
23 May 2012 PMI Revision 00 33
DPL, Durgapur Major Activities
Super heater - Improved Metallurgy to cater theupset conditions during operation. BB tubes - leading tubes diameter reduced and
protective shield provided before and after cavity toreduce erosion.
Economizer Additional loops added to reducebackend. Erosion protection shield provided.
Tubular APH Ferrules at gas entry point to reduce erosion
Changing of Staggered tubes to inline (U#1&2) FD fan reconditioned, ID fan replaced to get required
margin.continue
DPL D
-
7/31/2019 Training R&M of Boilers
34/45
23 May 2012 PMI Revision 00 34
DPL, Durgapur Major Activities
Milling System
U#1 & 2 mills replaced with mills & PA fans ofunits # 3&4
3 nos. New mills provided for U # 3 & 4 (Oneold mill retained)along with hot PA fans
Reconditioning of suction mill of U#5 Mill loading reduced to 80% at Max. load to
take care of burner heat input New Civil foundation and PF pipes for all units
Wind Box New Wind Box of improved designprovided for all units.
DPL Durgapur
-
7/31/2019 Training R&M of Boilers
35/45
23 May 2012 PMI Revision 00 35
DPL, Durgapur Performance Post R&M
Performance of Boilers achieved during PG Test
Sl.
No.
Description Unit Guarante
ed
Achiev
ed
Guarante
ed
Achiev
ed
Guarante
ed
Achiev
ed1 Thermal Efficiency
(Corrected)
% 86.11 89.91 86.7 88.62 84.95 88.34
2 Steam Generation TPH 124.9 137.06 253 270.34 258 259.46
Boiler # 1 Boiler # 3 Boiler # 5
-
7/31/2019 Training R&M of Boilers
36/45
23 May 2012 PMI Revision 00 36
bl
-
7/31/2019 Training R&M of Boilers
37/45
23 May 2012 PMI Revision 00 37
Summary Table
Component Visual
Ultrasonic
testing
Mag
neticparticle
inspec
tion.
Liquid
Dye
Penetrant
inspe
ction
Replication
Sampling
Depo
sitAnal
ysis
Out
side
Dia-metre
and
thick
ness
Fibre
Opticinspec
tion
Hardness
Others
1 2 3 4 5 6 7 8 9 10 11 12
Drum (Steam) Yes Yes No Yes Yes No Yes Yes No Yes
Water drum Yes Yes No Yes Yes No Yes Yes No Yes
Low tempe-
rature headerYes No No Yes No No No Yes Yes Yes
Attempertion
headerYes Yes No Yes Yes No No Yes Yes Yes
Swell
measure
ment
High
temperature
economiser
tubes
Yes No No No No Yes No Yes No No
Low
temperature
economiser
tubes
Yes No No No No Yes No Yes No No
Convection
superheater
coils
Yes No No No No Yes Yes Yes No Yes
Primary
superheater
coils
Yes No No No No Yes No Yes No Yes
Non-
destructive
oxide
thickness
inspection
-
7/31/2019 Training R&M of Boilers
38/45
23 May 2012 PMI Revision 00 38
Prefinal
superheater
coils
Yes No No No No Yes No Yes No Yes
Final
superheater
coils
Yes No No No No Yes No Yes No Yes
Reheater
coils
Yes No No No No Yes No Yes No Yes
High
temperature
headers
Yes Yes No Yes Yes No No Yes Yes Yes
Final
superheater
header
Yes Yes No Yes Yes No No Yes Yes Yes
Swell
measure
ment
Reheater
headersYes Yes No Yes Yes No No Yes Yes Yes
Swell
measure
ment
Main steam
pipingYes No No No Yes No No Yes No Yes
Platen
superheater
header
Yes Yes No Yes Yes No No Yes No Yes
Primary
superheater
headers
Yes Yes No Yes Yes No No Yes Yes Yes
Economiser
header Yes No No Yes No No No Yes No Yes
Auxilliaries Yes No No No No No No Yes No No
Boiler bank
tubesYes No No No No No No Yes No No
Waterwall Yes No No No No Yes No Yes No No
Furnace
waterwallsYes No No No No Yes No Yes No No
-
7/31/2019 Training R&M of Boilers
39/45
23 May 2012 PMI Revision 00 39
Sl.
No.Component VE DC ME & H TM DPT MPI UT / IOT
Visual
Examinatio
n
6 locations
along the
length
4 spots of
longitudinal seam
weld & 4 spots of
circumferencial
seam welds - 8
No.
6 locations
along the length
On two
longitudinal
and four
circumferencial
welds, at all
tap off stub
joints
(sat.steam-
raiser tube dia
127 mm stubs
: 89nos.,safety
valve -6, Down
comer-6, Feed
nozzle-3 &
other tap off-
34
FMPI on two
longitudinal
and four
circumferencial
welds.
MPI at(sat.steam-
raiser tube dia
127 mm stubs
: 89nos.,safety
valve -6, Down
comer-6, Feed
nozzle-3 &
other tap off-
34)
On two
longitudinal and
four
circumferencial
welds, at all tap
off stub joints/Butt joints
(sat.steam-raiser
tube dia 127 mm
stubs :
89nos.,safety
valve -6, Down
comer-6, Feed
nozzle-3 & other
tap off-34)
6 locations 8 locations 6 spots 144 welds 144 welds 144 welds
Visual
Examinatio
n
At burners,
soot blowers,
bottom ash
hopper, Z panel
and goose
neck area
at burners, soot
blowers, bottom
ash hopper, Z
panel and goose
neck area on 10
tube samples
at burners, soot
blowers, bottom
ash hopper, Z
panel and
goose neck
area
At twentylocations
attachment
welds at
burners, wind
box, wall
blowers at
accessible
locations
At accessible
locations -20
tubes
10 Samples 1000 spots At 20 locations
Visual
Examinatio
n
On all water
wall hanger and
screen tubes
One sample each
from hanger tube
& screen tube
At six locations
along the length
on attachment
welds at
random
236 tubes 2 samples 1416 spots 10 locations
1
2
3
500 MW BOILER - RESIDUAL LIFE ASSESSMENT - EXTENT & QUANTUM OF TESTS
Water wall
Water wall
hanger &
Screen Tubes
Steam Drum
-
7/31/2019 Training R&M of Boilers
40/45
23 May 2012 PMI Revision 00 40
Visual
Examinatio
n
3 locations
along the
length for each
header
Total -4 Nos10 locations
along the length
on 8
circumferencial
welds
on 8
circumferencial
welds
on 8
circumferencial
welds
12 locations 4 locations 10 locations 8 welds 8 welds 8 welds
Visual
Examinatio
n
W.W outlet -
8, SCW outlet-
6, Raiser tubes-
20
Hardsness on
46spots,Replicas
SCW -4, WW- 2.
10 locations
along the length
On
circumferencial
welds at WW
outlet -12,
SCW outlet-9,
Raiser tube -
20, & Stubs &
lugs: 150 Total
191 Nos.
On
circumferencial
welds at WW
outlet -12,
SCW outlet-9,
Raiser tube -
20, Total 41
Nos.
On
circumferencial
welds at WW
outlet -12, SCW
outlet-9, Raiser
tube -20, Total 41
Nos.
34 locations
Replica-6 spots
Hardness-46
spots
10 191 welds 41 welds 41 welds
Visual
Examinatio
n
on two tube
samples
on attachment
welds at
random
2 Samples 20 locations
Visual
Examinatio
n
Eco inlet
header - 3 ,
Eco outlet
header - 3
Eco inlet header -
2 , Eco outlet
header - 2
Eco inletheader - 2,
Eco outlet
header - 2,
Eco outlet
tubes - 6
On
circumferencialwelds at Eco
inlet - 4, Eco
outlet -6, Eco
Header stubs
& gamma
plugs-100 Nos
at Random
On
circumferencialwelds at Eco
inlet - 4, Eco
outlet -6, Eco
Header stubs -
100 Nos at
Random
On
circumferencial
welds at Eco
inlet - 4, Eco
outlet -6,
6 locations 4 welds (min)10
locations(min)110 welds 110 welds 10 welds
4
5
6
Water wall
ring headers
Water wall
outlet
headers,
steam cooled
wall headers
and riser
tubes
Economiser
assemblies
Econimiser
inlet and
outlet header
7
-
7/31/2019 Training R&M of Boilers
41/45
23 May 2012 PMI Revision 00 41
Visual
Examinatio
n
one tube on
each coil -118
Nos
at two locations
by sampling
on all coils
along the length
at six locations -
1416 Nos
on all
attachment
welds near roof
and crown
plate welds at
Random 20%
Internal oxide
scale
measurement
covering all coils
and terminal
tubes (Top &
Bottom
elevations) - 708
s ots
118 tubes (min) 2 samples 1416 spots(min)
25 crownplates of 6
tubes each
708 spots
Visual
Examinatio
n
6 locations
along the
length at LTSH
outlet Header
LTSH inlet -2
,LTSH Outlet -2
LTSH inlet -2,
SCW inlet - 4
On
circumferencial
welds at LTSH
inlet -2, LTSH
outlet -4 and
gamma plugs.
Stubs :
200nos.
Circumferencia
l welds at
LTSH inlet -2,
LTSH outlet-4
Circumferencial
welds at LTSH
inlet -2, LTSH
outlet-4
6 locations 4 locations 6 locations 206 welds 6 welds 6 welds
Visual
Examinatio
n
6 locations
along the
length
Replica-2Nos6 locations
along the length
Circ.weld:Desu
perheater-
8,spray tube -
2, thermowells -
6,100% on all
liner bolt welds
& gamma plug
Desuperheater-
8,spray tube -
2, thermowells
-6,100% on all
liner bolt welds
& gamma plug
Circ.weld:Desupe
rheater-8,spray
tube -2,
thermowells -6
6 locations 2 locations 6 locations 30 welds 30 welds 16 welds
Visual
Examinatio
n
Radiant roof
headers -2,
LTSH support
header -4, Eco
support header -
8
Radiant roof
headers -2, LTSH
support header -
2, Eco support
header - 2
Radiant roof -
4,LTSH support
header 4, Eco
support header -
8
Radiant roof -
7,LTSH
support
header/ Eco
support header
-8 & Stubs :
200nos.
Radiant roof
header-7,LTSHsupport header-
4,ECO support
header-8,
Flourscent
MPI on Eco
support header
stub-1096 stub
joints
Radiant roof -
7,LTSH support
header 4, Eco
support header -8
14 locations 6 locations 16 lcoations 215 welds1120 welds
(min)19 welds
LTSH coils
and terminal
tubes
LTSH inlet
and Outlet
header
LTSH
Desuperheate
r links
11
Radiant roof
header,
Economiser
and LTSH
support
headers
8
9
10
-
7/31/2019 Training R&M of Boilers
42/45
23 May 2012 PMI Revision 00 42
Divisional
superheater
panels
Visual
Examinatio
n
On all panels-
444 Nosby sampling -
on all the six
panels- 888
Nos including
bends at pent
house
on DMW
joints, roof seal
band weld and
crown plate
welds at roof at
Random 20%.
in penthouse
at identified
locations
1.Institu oxide
scale
measurements
covering all
panels 400 spots
in penthouse& in
furnace. 2. UT of
girdling loops 12
No. for checking
stress cracking
444 tubes 2 samples 888 spots
50 butt
welds,crown
plates of two
panels
444 bends400 spots & UT
of 12 girdling loop
Visual
Examinatio
n
On all panels -
432 Nos
by sampling-2
Nos
on all tubes and
covering all
coils-864 Nos
on DMW
welds, roof
seal band
welds, crown
plate welds at
roof and
attachmentwelds -
Random 20%
Insitu oxides
scale - 200 Nos,
on 24 girdling
loops for stress
cracking and 6
binding loops
432 tubes 2 samples 864 spots
30 butt welds,
crown plates of
6 panels
230 locations
Platen
superheater
inlet and
outlet headers
VisualExaminatio
n
6 locations
along the
length,
including swell
measurements
outlet header -
4, inlet header -
2
SH InletHeader -2,SH outlet
Header -4
SH InletHeader -2,SH outlet
Header -4
A)On 200 stub
jointsB)Circumf
erential weld at
Inlet header -6,
outlet header-
10, SHDP toplaten
connection-5,
Drains and
vents stub-4
and gamma
plugs
A)On 200 stub
jointsB)Circum
ferential weld
at Inlet header -
6, outlet
header-10,
SHDP to
platen
connection-5,
Drains and
vents stub-4
and gamma
plugs
A)Circumferential
weld at Inlet
header -6, outlet
header-10, SHDP
to platen
connection-5,
Drains and vents
stub-4 and
gamma plugs
6 spots 6 spots 6 spots 225 welds 225 welds 25 welds
13
Platen
superheater
coils
12
14
-
7/31/2019 Training R&M of Boilers
43/45
23 May 2012 PMI Revision 00 43
Visual
Examinatio
n
Final RH -736,
HalfRH- 184,
covering all
panels
by sampling-6
Nos. Hardness
measurement on
Final RH coils :
100 nos.
Final RH-1472,
Half RH- 1472
covering all
panels
On 50 DMW
joints,
attachment
welds and
crown plate
welding 20% at
random
on girdling loops
for stress
cracking at
random , Insitu
oxide scale
analysis 1400
points
920 tubes
6 samples and
100 hardnessspots.
2944 spots
50 butt
welds,crown
plates of 10panels of full &
half RH
1400 locations
Visual
Examinatio
n
Division Panel
inlet-12, DP
outlet-12,Wall
RH inlet-2,RH
Platen inlet-
14,RH outlet-4,
RH links-4
Div.SH Inlet : 2 &
Outlet : 2
RHInlet header-4 ,
outlet -4
Division Panel
inlet-12, DP
outlet-12,Wall
RH inlet-2,RH
Platen inlet-
14,RH outlet-4,
RH links-4
On circ. weld
joints at SHDP
inlet -6, SHDP
outlet-8,Wall
RH inlet-4,RH
Platen inlet-
12,RH outlet-
10 and 400
nipple welds &
gamma plugs
On circ. weld
joints at SHDP
inlet -6, SHDP
outlet-8,Wall
RH inlet-4,RH
Platen inlet-
12,RH outlet-
10 and 400
nipple welds &
gamma plugs
On circ. weld
joints at SHDP
inlet -6, SHDP
outlet-8,Wall RH
inlet-4,RH Platen
inlet-14,RH outlet-
12
36 spots 12 spots 36 spots
40 butt welds
and 400 nipple
welds
40 butt welds
and 400 nipple
welds
44 butt welds
Visual
Examinatio
n
Minimum one
on each
integral piping
Replica-2 Nos
Minimum one
on each integral
piping
At
circumferential
welds
At
circumferential
welds
At circumferential
welds
12 locations 2 spots 12 spots 12 welds 12 welds 12 welds
Visual
Examinatio
n
MS -4 Nos
At SH connecting
link-2 Nos, MS
piping from boiler
to stop valve-
4Nos
MS -4Nos
MS-4,
Thermowell
stub-4, safety
valve / ERV
stub -14
MS-4,
Thermowell
stub-4, safety
valve / ERV
stub -14
MS-4,
Thermowell stub-
4, safety valve /
ERV stub -14
4 locations 6 spots 4 spots 22 welds 22 welds 22 welds
18
Boiler integral
piping(alloy
steel including
MS upto stop
valve)
17
Boiler integral
piping (carbonsteel) and
down comer
15
Reheater
Panels-Final
Reheater,Half
Reheater
16
Divisional
superheater
headers and
reheater
headers (
inlet,
intermediate
and outlet
headers)
-
7/31/2019 Training R&M of Boilers
44/45
23 May 2012 PMI Revision 00 44
Visual
Examinatio
n
MS-6,HRH-
14,CRH-5,Feed
water-2
,Suction
manifold-3, CC
pump
discharge-6
,Eco links- 6
At three spots on
each piping -18
Nos
MS-6,HRH-
14,CRH-5,Feed
water-2
,Suction
manifold-3, CC
pump discharge-
6 ,Eco links- 6
MS-6,HRH-
14,CRH-5,Feed
water-2
,Suction
manifold-3, CC
pump
discharge-6
,Eco links- 6
MS-6,HRH-
14,CRH-
5,Feed water-2
,Suction
manifold-3, CC
pump
discharge-6
,Eco links- 6
MS-6,HRH-
14,CRH-5,Feed
water-2 ,Suction
manifold-3, CC
pump discharge-
6 ,Eco links- 6
42 locations 18 spots 42 spots 42 welds 42 welds 42 welds
Boiler
Expansion
Visual
Examinatio
n
VE
DC
ME&H
TM
DPTMAGENETIC PARTICLE INSPECTION MPI
FMPI
UTRTFB
DA
20
19
,
Hot reheat
and cold
reheat piping
downcomers,
feedwater
piping, CC
pump suction
manifold &discharge
piping,
LEGEND
THICKNESS MEASUREMENT
DYE-PENETRANT TESTING
WET FLOURSCENT MAGNETIC
PARTICLE INSPECTION
DEPOSIT ANALYSIS
RADIOGRPAHIC TESTINGFIBRO SCOPE TESTING
VISUAL EXAMINATION
METALLOGRAPHIC EXAMINATION &
ULTRASONIC TESTING
DIMENSIONAL CHECKS
-
7/31/2019 Training R&M of Boilers
45/45