transcript for evidentiary hearing on 09.18.2013
TRANSCRIPT
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
1/285
STATE OF NEW YORK DEPARTMENT OF PUBLIC SERVICETHREE EMPIRE STATE PLAZA, ALBANY, NY 12223-1350
www.dps.ny.gov
PUBLIC SERVICE COMMISSION
AUDREY ZIBELMAN PETER McGOWANChair General CounselPATRICIA L. ACAMPORA
GARRY A. BROWN KATHLEEN H. BURGESSGREGG C. SAYRE Secretary
DIANE X. BURMANCommissioners
Re: Case 12-T-0248NYSEGColumbia County Transmission ProjectSeptember 18, 2013
** Please note this is a Preliminary transcript, subject to later edits when reviewed by the
Administrative Law Judges assigned to the cases.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
2/285
Page 342
1
2 STATE OF NEW YORKPUBLIC SERVICE COMMISSION
3
4 APPLICATION OF NEW YORK STATE ELECTRIC and GASCORPORATION FOR A CERTIFICATE OF ENVIRONMENTAL
5 COMPATIBILITY AND PUBLIC NEED FOR THE CONSTRUCTION OFTHE "COLUMBIA COUNTY TRANSMISSION PROJECT,"
6 APPROXIMATELY 11.1 MILES OF 115 KILOVOLT TRANSMISSIONLINES AND RELATED FACILITIES IN THE TOWNS OF CHATHAM,
7 GHENT, AND STOCKPORT, IN COLUMBIA COUNTY
8 CASE# 12-T-0248
9 Tuesday, September 18, 201310 9:30 a.m.
Third Floor Hearing Room11 Three Empire State Plaza
Albany, New York 12223-135012
13 A.L.J. ELEANOR STEINAdministrative Law Judge
14 Three Empire State PlazaAlbany, New York 12223-1350
15
16
17
18
19
20
21
22
23
24
25
26
27
28
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
3/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 343
1 Case 12-T-0248 - 9-18-20132 APPEARANCES:3 FOR PUBLIC SERVICE COMMISSION:
4 STEVEN BLOW, ESQ.STAFF COUNSEL
5 OFFICE OF GENERAL COUNSELNEW YORK STATE PUBLIC SERVICE COMMISSION
6 Three Empire State PlazaAlbany, New York 12223-1350
7ANDREW C. DAVIS
8 Utility SupervisorOffice of Energy Efficieny and the
9 Environment
NEW YORK STATE PUBLIC SERVICE COMMISSION10 Three Empire State PlazaAlbany, New York 12223-1350
11FOR DEPARTMENT OF STATE DEPARTMENT OF AGRICULTURE
12 AND MARKETS:13 CHRIS CUDDEBACK, ESQ.
SENIOR ATTORNEY14 108 Airline Drive
Albany, New York 1223515
MATTHEW J. BROWER16 Agricultural Resource SpecialistDivision of Land and Water Resources
17 108 Airline DriveAlbany, New York 12235
18NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL
19 CONSERVATION:20 LISA A. WILKINSON, ESQ.
Office of General Counsel21 625 Broadway 14th Floor
Albany, New York 12233-150022SARAH EVANS
23 DIVISION OF ENVIRONMENTAL PERMITS625 Broadway 14th Floor
24 Albany, New York 12233-150025262728
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
4/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 344
1 Case 12-T-0248 - 9-18-2013
2 NEW YORK STATE ELECTRIC AND GAS:
3 CULLEN and DYKMAN, LLPBY: DAVID T. METCALFE, ESQ.
4 ANGELA N. CASCIONE, ESQ.100 Quentin Roosevelt Blvd.
5 Garden City, New York 11530
6FOR TOWN OF GHENT:
7GREENBERG & GREENBERG
8 BY: MARK DAVID GREENBERGFour East Court Street
9 Hudson, New York 12534
10 FOR PROTECT GHENT:
11 GREENBERG TRAURIGBY: WILLIAM A. HURST, ESQ.
12 54 State Street, 6th FloorAlbany, New York 12207
13 PANEL:
14 Carol HowlandSarah Gilstrap
15 Dusty Werth16
17
18
19
20
21
22
23
24
25
26
27
28
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
5/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 345
1 Case 12-T-0248 - 9-18-2013
2 (The hearing resumed at 9:36
3 a.m.)
4 A.L.J. STEIN: Good Morning.
5 This is Judge Stein. We'll now pick up this
6 hearing where we left off yesterday.
7 I have circulated a revised
8 schedule for today's cross examination and we're
9 going to resume with cross examination of the
10 panel, consisting of Carol Howland, Sarah Gilstrap,
11 and Dusty Werth. And our first attorney will be
12 the representative for the Town of Ghent.
13 MR. GREENBERG: Thank you, Judge.
14 A.L.J. STEIN: Would you like
15 this exhibit marked for identification?
16 MR. GREENBERG: Yes, I would,
17 please, Judge.
18 A.L.J. STEIN: This will be
19 marked Exhibit Number Forty-six.
20 MR. GREENBERG: And I would just
21 describe that as a informational request and
22 response to Protect Ghent's response number --
23 request date August 29th, 2013, with response
24 number C.C.T.P. dash twelve dash zero seven two.
25 And this is Dusty Werth and Timothy -- Timothy
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
6/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 346
1 Case 12-T-0248 - 9-18-2013
2 Lynch.
3 A.L.J. STEIN: And this is a
4 two-page document. Thank you. That will be marked
5 as Exhibit Number Forty-six.
6 MR. GREENBERG: Thank you, Judge.
7 Well, good morning, Ms. Howland, Ms. Gilstrap, Mr.
8 Werth, your Honor.
9 Just a couple questions of the
10 panel, regarding the Town of Ghent Comprehensive
11 Plan.
12 CROSS EXAMINATION
13 BY MR. GREENBERG:
14 Q. I believe you made reference to
15 that yesterday. Is that correct?
16 A. (Werth) Yes.
17 Q. Now, did you review the Town of
18 Ghent Comprehensive Plan, in connection with your
19 route planning?
20 A. Yes.
21 Q. And that was both for the -- the
22 four alternative routes, as well as the four
23 thirty-four point five kV alternative routes?
24 A. Correct.
25 Q. And did you review the entire
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
7/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 347
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 Town of Ghent Comprehensive Plan?
3 A. We did.
4 Q. Thank you. Now, if you could
5 take a look at figure three dash four, which is
6 entitled Columbia County Transmission Project,
7 figure three dash four, NYSEG thirty-four point
8 five kV alternative. I believe that was part of
9 the response to the June 22nd, 2012 Appendix A,
10 information request?
11 Is that right, Mr. Metcalfe?
12 MR. METCALFE: That would be
13 correct. But more specifically, it was one of the
14 additional info -- information requests, and
15 specifically, B as in boy.
16 MR. GREENBERG: Thank you, sir.
17 A.L.J. STEIN: I'm sorry. What
18 are we looking at?
19 MR. GREENBERG: That's a map,
20 Judge, which is figure three dash four, which is a
21 map actually of the planned route for a thirty-four
22 kV alternative that was put together by NYSEG.
23 A.L.J. STEIN: And -- and where
24 is this in the record? Is this in --
25 MR. GREENBERG: It's in the
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
8/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 348
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 first --.
3 A.L.J. STEIN: -- the first
4 deficient?
5 MR. METCALFE: It -- it --
6 A.L.J. STEIN: First deficiency
7 letter?
8 MR. METCALFE: -- it is in the
9 first deficiency letter, the response -- the first
10 response to the deficiency letter.
11 A.L.J. STEIN: Thank you.
12 MR. GREENBERG: And -- and Judge,
13 it was the map that I put up yesterday, but
14 unfortunately it's very hard, I think, to be able
15 to see it in this room, posted up on the board like
16 that.
17 A.L.J. STEIN: Go ahead.
18 MR. GREENBERG: Thank you, Judge.
19 BY MR. GREENBERG: (Cont'g.)
20 Q. Panel, do you have that in front
21 of you?
22 A. (Werth) Yes.
23 Q. Was your panel involved in
24 connection with the production of figure three dash
25 four?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
9/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 349
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. Yes.
3 Q. Okay. Now, if I understand
4 correctly, you would have been given the two tap
5 points, the one to the right-hand side of the map
6 here, Nobletown Road, and the other tap went on the
7 left-hand side of the map, near Soller Heights, and
8 would have been asked to basically set up a route
9 that connected those tap points. Is that correct?
10 A. Correct.
11 Q. So, basically, it's not so much
12 putting together point A to B, but in this case
13 putting together the initial starting point near 9H
14 and then running a -- a thirty-four point five kV
15 line out to Nobletown Road, as well as one that
16 would be going down to Soller Heights; correct?
17 A. Correct.
18 Q. Now, could you just give a -- a
19 general description of how you went about doing
20 that? If I understand, it was done as
21 desk-topping, is that right?
22 A. Yes. It was done through a
23 desktop review of environmental and land use
24 constraints in the area.
25 Q. And -- and can you describe
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
10/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 350
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 exactly what a desktop review consists of?
3 A. It's reviewing publicly available
4 data and databases that can be loaded in to a
5 G.I.S., or Geographic Information System, to
6 provide mapping of all the constraints.
7 Q. And there were no site visits in
8 connection with the planning of NYSEG's thirty-four
9 point five kV alternative; were there?
10 A. Not specifically for this. There
11 was site visits in the area that also coincide with
12 the proposed one fifteen kV route.
13 Q. Okay. Do -- do you have any
14 estimate as to how many hours were spent, in
15 connection with the planning and development of
16 the -- the route for the thirty-four point five kV
17 alternative that is shown in figure three dash
18 four?
19 A. I don't, off the top of my head.
20 Q. Are -- are -- are you able to
21 give a rough estimate at all?
22 A. Not off the top of my head.
23 Q. Were you personally involved
24 in -- in -- in putting together the route for
25 NYSEG's thirty-four point five kV alternative?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
11/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 351
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. Yes.
3 Q. Now, some of the route that's
4 shown in thirty -- in figure three dash four runs
5 along existing roadways. Is that correct?
6 A. Yes.
7 Q. Okay. For -- for instance, if we
8 look towards the -- the east, there is an area that
9 it goes along Route 203, near where it's shown as
10 Chase Road and -- and Big Woods Road.
11 MS. HOWLAND: Dave, could we
12 possibly get a larger map?
13 (Off-the-record discussion)
14 A. Could you please repeat the
15 question?
16 BY MR. GREENBERG: (Cont'g.)
17 Q. Sure. If I could just bring your
18 attention to the route -- it's -- on the east --
19 it's east of the Taconic State Parkway. And if you
20 follow the route along, it then meets up with Route
21 203, near where it shows as Chase Road and Big
22 Woods Road. Do you see that?
23 A. (Werth) Yes.
24 Q. Okay. Now, the route that you
25 chose runs along Route 203 at that point; correct?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
12/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 352
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. For a short distance, yes.
3 Q. Right. And -- and are you
4 considering this to be a -- a transmission line, a
5 sub-transmission line, a distribution line, or
6 something else?
7 A. I believe it is a transmission
8 line.
9 Q. Okay.
10 A. Or sub-transmission line.
11 Q. Or both? Thirty-four point five
12 can be considered either a sub-transmission or a
13 transmission line; correct?
14 A. That would be a question for the
15 engineers, I believe.
16 Q. Okay. But in any case, the
17 thirty-four point five kV line, that you're running
18 can go along roadways; right?
19 A. In certain areas, yes.
20 Q. Okay. Well, what would be the
21 constraints of being able to run along a roadway in
22 one area, as compared to not being able to run
23 along a roadway in another area?
24 A. Having the available distance for
25 the right-of-way.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
13/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 353
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 Q. Okay. And -- and what would that
3 available distance for the right-of-way be?
4 A. One hundred feet.
5 Q. Well, that's NYSEG's
6 determination as to what the right-of-way should
7 be; correct?
8 A. We were instructed that it would
9 be a hundred foot right-of-way. I don't know what
10 goes into that.
11 Q. But you don't really require a
12 hundred foot right-of-way for a thirty-four point
13 five kV line; do you?
14 A. That's not my area of expertise.
15 Q. Okay. In fact, what you can do
16 is you can trim some of the trees along the roadway
17 to create enough space for that line. Isn't that
18 right?
19 A. Again, that's not my area.
20 Q. Okay. So, getting back to the
21 area of the route, where it runs along 203 and
22 picks up that short area near Chase Road and Big
23 Woods Road, now arguably, other than based on the
24 constraint that you just talked about, you could
25 run that line, for instance, all the way on 203, to
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
14/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 354
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 where it meets 22, and then run it all the way on
3 Route 22, down to Nobletown Road, is that right?
4 A. No.
5 Q. And why not?
6 A. There's not enough room for a
7 hundred-foot-wide right-of-way.
8 Q. Okay. So, the only reason that
9 you're saying you can't take that route along 203
10 and then 22 is because you would be requiring a
11 hundred-foot right-of-way?
12 A. I don't know that that is the
13 only reason that we couldn't, but that is the
14 primary reason that it was not an alternative.
15 Q. Based on the instructions that
16 you received?
17 A. Based on the need for a
18 hundred-foot right-of-way.
19 Q. And -- and who -- who directed
20 you that you required a hundred-foot right-of-way,
21 in connection with the creation of an alternative
22 thirty-four point five kV, for this project?
23 A. That would have come from the
24 NYSEG engineering.
25 Q. Okay. Do you know anyone in
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
15/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 355
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 particular? Did you speak with anyone? Do you
3 recall anyone in particular or is that written
4 correspondence?
5 A. I don't believe it was written
6 correspondence. I believe it came through the
7 NYSEG project manager at the time.
8 Q. And -- and with that have been
9 Mr. Bender?
10 A. Yes.
11 Q. And is Mr. Bender still the
12 project manager?
13 A. No.
14 Q. Who -- who took Mr. Bender's
15 place?
16 A. Ayo.
17 Q. Mr. Ayo or Ms. Ayo?
18 A. Mr. Ayo.
19 Q. Mr. Ayo?
20 MR. METCALFE: The name's Ayo
21 Jemiri.
22 MR. GREENBERG: Thank you.
23 MR. METCALFE: I -- I can point
24 out, too, that the engineering panel, the Mike
25 Barteck (phonetic spelling) Panel, scheduled for
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
16/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 356
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 next week, is very familiar with the company's
3 standards for right-of-way widths, so I'm happy to
4 steer you in that direction for better information
5 than Mr. Werth is able to give you.
6 MR. GREENBERG: Thank you, very
7 much, Mr. Metcalfe. I appreciate that.
8 A.L.J. STEIN: Just one moment.
9 (Off-the-record discussion)
10 A.L.J. STEIN: Please proceed.
11 BY MR. GREENBERG: (Cont'g.)
12 Q. Now, wouldn't it be true that the
13 route, if it were able to go along existing
14 roadways, would cause less environmental impact?
15 A. (Werth) It would depend on -- on
16 the route.
17 Q. Well, would it depend on the
18 route or would it depend on something on in
19 particular, in connection with the road at that one
20 area?
21 A. It would depend on the route and
22 what -- what resources are crossed.
23 Q. Well, wouldn't that roadway
24 already be crossing those resources? Or are you
25 concerned again with the hundred-foot right-of-way?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
17/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 357
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. It would be a hundred-foot
3 right-of-way and it would need to be outside of the
4 road.
5 Q. Okay. And when you say
6 hundred-foot right-of-way, are you looking at a
7 fifty feet on one side of the road and fifty feet
8 on the other side of the road, or something else?
9 A. No. It would need to be a
10 hundred foot, consecutive, fifty feet either side
11 of the center line.
12 Q. So, the hundred-foot right-of-way
13 is taken from -- fifty feet from the center line of
14 the roadway?
15 A. No. From the center line of the
16 transmission line.
17 Q. All right. So, if it ran along,
18 say, the west side of the roadway, it would have to
19 be fifty feet further to the west and then an
20 additional fifty feet to the east?
21 A. No.
22 Q. I'm confused.
23 A. It would be fifty feet either
24 side of the center line of the transmission line.
25 Q. Okay. And -- and part of that
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
18/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 358
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 would be in the roadway, most probably, and part of
3 it would be not in the roadway. Isn't that
4 correct?
5 A. I -- I don't know NYSEG's
6 standards, if they allow sharing of road
7 right-of-way or not.
8 Q. Now, looking again, at figure
9 three dash four, now over more towards the western
10 area, where the thirty-four point five kV line
11 connects into what would be the new one fifteen
12 substation, if you go eastward from there, your
13 alternative route makes a -- a -- a north -- a
14 northern turn and appears to basically go along the
15 same route that was provided with the alternatives
16 for the one fifteen kV line. Is that right?
17 A. That's correct.
18 Q. Now, did you consider continuing
19 east to hook into anything on County Route 22 at
20 that point?
21 A. No. We determined that County
22 Road -- or County Route 22 does not have adequate
23 space for a hundred-foot right-of-way.
24 Q. And -- and how did you make that
25 determination? Through -- what on your desktop
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
19/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 359
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 in -- allowed you to make that determination?
3 A. Well, in this area, we actually
4 had site visits, so we had more than just desktop.
5 But primarily it is the homes located along County
6 Route 22 do not allow for the hundred-foot
7 right-of-way.
8 Q. Okay. And if I could just direct
9 your attention to the exhibit that was just handed
10 up, which is Protect Ghent's P.G. Nine.
11 MR. GREENBERG: I'm sorry, your
12 Honor. I had forgot what number you had marked
13 that as.
14 A.L.J. STEIN: Forty-six.
15 BY MR. GREENBERG: (Cont'g.)
16 Q. Exhibit Number Forty-six, Mr.
17 Werth, you prepared this response?
18 A. (Werth) Yes.
19 Q. Okay. If I understand correctly,
20 this was served on Mr. Hurst, actually, during the
21 hearing yesterday. Is that correct?
22
23 A. I'm not sure when it was served.
24 Q. Well, what -- when did you --
25 when did you create this response?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
20/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 360
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. I don't believe --.
3 MR. METCALFE: I -- I'm going to
4 object because the -- the witness doesn't know --
5 MR. GREENBERG: Okay.
6 MR. METCALFE: -- the process
7 that occurred after he had signed off on the --
8 MR. GREENBERG: I'll ask him --
9 MR. METCALFE: -- I.R. --.
10 MR. GREENBERG: -- another way.
11 MR. METCALFE: Thank you.
12 MR. GREENBERG: I'll -- I'll
13 withdraw the question. Thank you, sir.
14 BY MR. GREENBERG: (Cont'g.)
15 Q. Do you know when you provided the
16 information in connection with this response,
17 Exhibit Number Forty-six?
18 A. (Werth) I believe it was last
19 week.
20 Q. Okay. Now, looking at response
21 number one, this states as a -- that no analysis or
22 studies have been completed for the potential use
23 of County Route 22 as an alternative, because it
24 was determined -- and I'm paraphrasing that, County
25 Route 22 has many residences that are less than a
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
21/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 361
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 hundred feet off of County Route 22, which would
3 require that a route along this route would have to
4 take homes or be required to cross the road
5 multiple times, if there are not residence on both
6 sides.
7 Is that information that you
8 provided, Mr. Werth?
9 A. Yes.
10 Q. Okay. How many residences are we
11 talking about?
12 A. I don't know off the top of my
13 head.
14 Q. Is it more than one or two?
15 A. Yes.
16 Q. Is it more than ten?
17 A. I -- I don't know.
18 Q. And when you say take homes, are
19 you talking about actually having to take homes by
20 eminent domain or destroy them to allow the line to
21 go through?
22 A. The houses would have to be
23 removed to allow for the hundred-foot right-of-way.
24 Q. Are there any existing lines
25 running along County Route 22?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
22/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 362
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A. I believe there are.
3 Q. And what type of lines currently
4 run along County Route 22?
5 A. I'm not sure, but I believe that
6 they would be distribution lines.
7 Q. Okay. And -- and those are
8 thirty-four point five distribution lines?
9 A. I do not know that.
10 Q. Okay. Now, I -- I guess it's --
11 again, is -- is it your panel's place to be able to
12 discuss whether a new thirty-four point five
13 kilovolt line could travel along the existing line
14 that's on Route 20 -- on County Route 22?
15 MR. METCALFE: I'd aim that at
16 the Mike Barteck Panel.
17 MR. GREENBERG: Thank you, sir.
18 BY MR. GREENBERG: (Cont'g.)
19 Q. Okay. Now, you also stated in
20 Exhibit Forty-six that the road would have to --
21 the line would have to cross the road multiple
22 times.
23 Now, did you consider, in
24 planning NYSEG's thirty-four point five kV
25 alternative, whether any portions of the line could
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
23/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 363
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 be undergrounded?
3 A. (Werth) No.
4 Q. When you were planning on the
5 four alternatives for the one fifteen kV line, did
6 you consider whether any portions of that line
7 could be undergrounded?
8 A. No. That was outside of the --
9 our scope of work.
10 Q. And -- and when you say outside
11 your scope of work, you're saying it was outside
12 your scope of direction from your principal. Is
13 that correct?
14 A. Yes. We were hired to route an
15 overhead transmission line.
16 Q. And it was made clear to you
17 that -- from the very start that none of it would
18 be undergrounded. Is that correct?
19 A. Like I said, we were hired to
20 route an overhead transmission line, not an
21 underground transmission line.
22 Q. Well, what about a partially
23 underground transmission line?
24 A. No. We were directed to site a
25 overhead transmission line.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
24/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 364
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 Q. Thank you very much.
3 MR. GREENBERG: I have no further
4 questions, Judge.
5 A.L.J. STEIN: Thank you.
6 For the Department of Environmental Conservation?
7 MS. WILKINSON: Your Honor, I'm
8 going to be handing out interrogatory responses.
9 And I'm going to hand them out. We had sixteen
10 questions, sixteen response -- sets of responses.
11 I'm going to hand them in packet of all sixteen
12 responses, if that's okay, for my exhibit. But I'm
13 going to ask questions on some of the individual
14 responses.
15 Or do you want to mark them
16 individually?
17 A.L.J. STEIN: I'm willing to
18 take them as a packet, if they -- do they have --
19 are -- have you numbered the pages?
20 MS. WILKINSON: We've numbered --
21 the responses are numbered and most of the
22 responses are one page, front and back. Some of
23 them are stapled. Anyone that's multiple pages,
24 I've stapled, but I also have a summary table of
25 each response and the number of pages.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
25/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 365
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 A.L.J. STEIN: Okay. I'm just
3 concerned that --.
4 MS. WILKINSON: I can do it
5 separately.
6 A.L.J. STEIN: I'm just concerned
7 that if parties want to refer to this in the
8 record --
9 MS. WILKINSON: Okay.
10 A.L.J. STEIN: -- there would be
11 no way to say Exhibit Forty-six, page twelve.
12 MS. WILKINSON: That's fine. I
13 can do -- we can do it separately.
14 I have -- I mean, I'm still going
15 to hand them out as packets, just because --
16 A.L.J. STEIN: That's fine.
17 MS. WILKINSON: -- that's how
18 they were. And because some of the responses have
19 voluminous attachments, I don't have copies of the
20 attachments. I did copy the question and response,
21 but not the attachment, as directed. So, I have
22 complete copies for you and the court reporter.
23 A.L.J. STEIN: Thank you.
24 MS. WILKINSON: Do you want -- so
25 I'll go through each one of them, individually,
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
26/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 366
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 then? I can do that.
3 A.L.J. STEIN: Yeah. But we'll
4 identify them collectively as Exhibit Number
5 Forty-six -- Forty-Seven. Sorry.
6 MS. WILKINSON: Okay.
7 (Off-the-record discussion)
8 MR. METCALFE: Lisa, does this
9 include -- you handed out four or five I.R.s
10 yesterday.
11 It's the whole batch?
12 MS. WILKINSON: It's the whole
13 batch.
14 MR. METCALFE: Great.
15 (Off-the-record discussion)
16 MR. BLOW: Your Honor, may I
17 inquire -- Ms. Wilkinson said that she is not
18 providing copies of the attachments, but the
19 attachments are -- have they been pre-filed?
20 MS. WILKINSON: Yes, they have.
21 MR. BLOW: So, the attachments
22 are a part of the exhibit --
23 MS. WILKINSON: Correct.
24 MR. BLOW: -- it's just they're
25 not being handed out in hard copy?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
27/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 367
1 Howland/Gilstrap/Werth - Cross - Greenberg
2 MS. WILKINSON: Correct.
3 I have a copy -- a hard copy for the judge and I
4 can supply a copy to the court reporter if you want
5 me to do that.
6 A.L.J. STEIN: You don't need to.
7 MS. WILKINSON: Okay.
8 MR. BLOW: Okay.
9 MS. WILKINSON: So, what I just
10 handed out --
11 MR. BLOW: Thanks.
12 MS. WILKINSON: -- were
13 interrogatory responses to D.E.C. One through
14 Sixteen.
15 A.L.J. STEIN: So this will be
16 Exhibit Number Forty-seven for identification. And
17 it consists of D.E.C. interrogatories and
18 responses, numbers One through Sixteen.
19 Is that correct, Ms. Wilkinson?
20 MS. WILKINSON: That's correct.
21 A.L.J. STEIN: Thank you.
22 CROSS EXAMINATION
23 BY MS. WILKINSON:
24 Q. Good morning.
25 A. (Howland) Good morning.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
28/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 368
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 Q. And I'll start by assuming that
3 there are no changes to the interrogatory responses
4 and the responses, as the authors are indicated,
5 are the same responses that you would give today?
6 A. That's correct.
7 Q. Okay. I'm going to start by
8 asking you about best management practices. In
9 D.E.C. One, we -- D.E.C. inquired whether NYSEG
10 would utilize the best management practices that
11 had been developed in the case of the Rochester
12 Reliability Project, whether those practices would
13 also be utilized for the Columbia County
14 Transmission Project?
15 A. Yes, they would.
16 Q. And today, you are not aware of
17 any changes to those practices that NYSEG has
18 implemented in the case of Rochester?
19 A. No. There's no changes to that
20 document.
21 Q. And there's no changes to the
22 practices that you've actually implemented to the
23 project? In other words, they may -- the document
24 may not have changed, but on the ground, have you
25 made any changes?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
29/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 369
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. Are you referring to this project
3 or the Rochester project?
4 Q. Well, I'm referring to the
5 Rochester project. In other words, are there --
6 have you made changes to the best management
7 practices, in the field, in implementation?
8 MR. METCALFE: Objection. That's
9 outside the scope of the --
10 MS. WILKINSON: Let me --
11 MR. METCALFE: -- company's --
12 MS. WILKINSON: -- rephrase it.
13 MR. METCALFE: -- direct case.
14 BY MS. WILKINSON: (Cont'g.)
15 Q. Have you made changes to the best
16 management practices in that project that you
17 believe would be appropriate for this project, that
18 would cause you to update the document for this
19 project?
20 A. (Howland) There have been no
21 changes to the document.
22 Q. And there's no -- there's --
23 you're not foreseeing any updates to the -- to the
24 document, as applied to this project?
25 A. No, I do not.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
30/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 370
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 Q. So, as far as -- so as far as we
3 know today, that document would govern this
4 project's best management practices, as applied to
5 terrestrial and wildlife resources?
6 A. The document would be used unless
7 there's a specific certificate condition that
8 overrode that.
9 Q. Okay. And that include -- so
10 that would apply to every single topic covered in
11 that document?
12 A. Correct. The -- our best
13 management practices are typical procedures to be
14 followed for the development of the environmental
15 management and construction plan. However, if
16 there's specific certificate conditions, they would
17 be followed first.
18 Q. Okay. So, turning to streams, in
19 section four point nine of the application, water
20 resources, which one of you prepared that
21 document -- or that section of Exhibit Four, in the
22 application?
23 A. I have written that text.
24 Q. Okay. And that was based on a
25 desktop analysis?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
31/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 371
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. Yes. That was based on
3 information we were able to find through D.E.C. and
4 other recourses.
5 Q. Ms. Howland and Mr. Werth, did
6 you review that section?
7 A. (Werth) Yes.
8 (Howland) Yes.
9 Q. Ms. Gilstrap, in preparing that
10 section, did you conduct any site visits?
11 A. (Ms. Gilstrap) No, I did not
12 conduct -- conduct any site visits.
13 Q. And as far as D.E.C. Ten is
14 concerned, I believe the response was prepared by
15 Mr. Werth and Ms. Howland.
16 Ms. Gilstrap, did you review that
17 response at all?
18 A. I was on maternity leave.
19 Q. Okay. Now, did any of the
20 witnesses consult with D.E.C. in preparing table
21 four point one five, which is the -- well, the
22 table in the application and also the -- as updated
23 in D.E.C. Ten, I believe. Prior to preparing that
24 table, did any of the witnesses consult with D.E.C.
25 staff?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
32/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 372
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. For the table in the application,
3 we did not consult with staff.
4 Q. And the table that was attached
5 to the response to D.E.C. Ten?
6 A. (Werth) No.
7 Q. No? Did anyone consult with
8 D.E.C., regarding the use of the National
9 Hydrologic Database?
10 A. No.
11 (Howland) No.
12 Q. And did anyone ask D.E.C. whether
13 that information was accurate?
14 A. (Werth) No.
15 Q. Ms. Gilstrap, so you did not go
16 on a site visit then, a few weeks ago, to see the
17 stream crossings?
18 A. (Ms. Gilstrap) No.
19 Q. But Mr. Werth was telling me you
20 had a site visit?
21 A. (Werth) Yes.
22 Q. And D.E.C. had listed four
23 crossing locations that were of particular
24 interest, I believe, right? Widows -- right, the
25 crossing at Widows Creek? There is a crossing at
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
33/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 373
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 Widows Creek; correct?
3 A. Correct.
4 Q. Now, you didn't actually see that
5 crossing on the site visit, but that was one of the
6 ones listed. And I believe D.E.C. also listed the
7 Kline Kill crossing.
8 A. Correct.
9 Q. Which we did see?
10 A. Correct.
11 Q. And D.E.C. also listed a crossing
12 at Fitting Creek?
13 A. Correct.
14 Q. Which we didn't see the -- we saw
15 the creek and a representative location of the
16 crossing, but we didn't see the actual crossing
17 point?
18 A. Correct.
19 Q. Have you or Ms. Howland seen --
20 have you seen the crossing point at Fitting Creek,
21 where the -- where the project is proposed to
22 cross?
23 A. No.
24 Q. Have you visited that location?
25 A. No. Just on the site visit with
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
34/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 374
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 you guys.
3 Q. Okay. And then the fourth, I
4 believe, was a crossing at the tributary to North
5 Creek, which I think was near the Haybed (phonetic
6 spelling) property, but we did make it on the site
7 visit. Is that correct?
8 A. Correct.
9 Q. And --.
10 A. (Howland) We have not gone on
11 private property for the routing.
12 Q. Okay. So, we did see the
13 crossing at Kline Kill, which is classified as a
14 C(T.S.) stream, indicating it supports trout
15 spawning. You know, based on your site visit then,
16 were you able to assess the characteristics of the
17 stream?
18 A.L.J. STEIN: Let me just -- let
19 me just interject for one second. Is that C dash
20 T.S.?
21 MS. WILKINSON: It's -- I believe
22 it's C parenthesis T.S.
23 A.L.J. STEIN: Okay.
24 MS. WILKINSON: I will provide
25 that. I apologize --
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
35/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 375
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A.L.J. STEIN: Okay.
3 MS. WILKINSON: -- but I will
4 provide that. I think it's parenthesis T.S.
5 A.L.J. STEIN: Okay. If you
6 could just make it clear as you go, so the reporter
7 gets a clear --
8 MS. WILKINSON: Sure.
9 It's C -- it's C parenthesis T.S.
10 A.L.J. STEIN: Thanks.
11 MS. WILKINSON: Indicating trout
12 spawning.
13 BY MS. WILKINSON: (Cont'g.)
14 Q. And based on the site visit, were
15 you able to assess in -- whether it would be
16 possible to span that stream, rather than place
17 structures in the stream?
18 A. (Werth) Preliminary engineering
19 does not indicate any structures would be placed
20 within that stream.
21 Q. Or within a hundred feet of the
22 stream?
23 A. I believe that's the case, but I
24 need to check.
25 (Howland) The short answer is we -- we will not
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
36/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 376
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 place structures in the stream. Just how far back
3 we can go to span it, we're not sure. And Dusty's
4 trying to see on that.
5 Q. I mean, I believe if you look at
6 page four sixty-eight and four sixty-nine of the
7 application, I think that's where you discuss --.
8 A. (Howland) Four six eight and
9 four six nine.
10 (Werth) And the response to
11 D.P.S. Six, we did not identify a structure within
12 a hundred feet of that stream.
13 Q. Okay. So, as you know right now,
14 there would be -- there would be no need to place
15 structures in or within a hundred feet of that
16 stream?
17 A. Correct.
18 Q. Now, as far the tributary to
19 North Creek is concerned, which was not viewed, are
20 you aware of whether that -- that particular stream
21 supports trout?
22 A. According to the classification
23 from the D.E.C. data set that we received, it does
24 not.
25 Q. But did you check with D.E.C. to
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
37/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 377
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 see whether, in fact, that stream supports trout?
3 A. No, we did not.
4 Q. If -- if we look at the map and
5 the -- the two figures, figure -- figures four
6 point four and four point five, if -- well, four
7 point five, I believe --.
8 A. Is that four dash four and four
9 dash --?
10 Q. I -- I -- I apologize. Four dash
11 four and four dash five, it's in Exhibit Four of
12 the application. And if you look at the -- the
13 crossing, because you -- your application doesn't
14 overlay the streams and the wetlands, but looking
15 at the location of the North Creek crossing, and
16 if -- and I can point -- I can point that out to
17 you on -- I believe D.E.C., when we sent out our
18 requests for site visits, we included a map. We
19 actually drew it on figure four point five. I
20 don't know if that would help you. If you can tell
21 from figure four point five on the application, the
22 crossing at North Creek.
23 A. Yes.
24 Q. So, you see that general
25 location?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
38/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 378
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. Yes.
3 Q. Turning to figure four point
4 four, can you pinpoint relatively the same location
5 on that figure where the crossing would occur? Or
6 the vicinity?
7 A. Yes.
8 Q. So, it's -- the crossing occurs
9 in or near what's been marked as S.T. Eight or
10 Wetland Number Eight on the map?
11 A. I believe it would be south of
12 S.T. Eight. Is that correct?
13 Q. Slightly south, but the project
14 would cross S.T. Eight and then, not much further
15 than that, would cross the North Creek.
16 A.L.J. STEIN: I'm not sure I'm
17 seeing what you're seeing -- looking, but I'm not
18 sure I'm looking at the right -- you're looking at
19 figure four point four?
20 MS. WILKINSON: Right. Figure
21 four point four and S.T. Eight is -- it runs from
22 north to south, on the top of the page, to maybe
23 two-thirds down --
24 A.L.J. STEIN: Right.
25 MS. WILKINSON: -- heading east.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
39/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 379
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 And I'm looking where the project is crossing.
3 A.L.J. STEIN: Oh, I see. So,
4 sort of the eastern branch of S.T. Eight?
5 MS. WILKINSON: Right.
6 A.L.J. STEIN: I see. Thank you.
7 BY MS. WILKINSON: (Cont'g.)
8 Q. So, the crossing and the wetland
9 area are -- are relatively in close proximity,
10 would you say?
11 A. (Werth) I believe S.T. Eight
12 corresponds with Kline Kill, not North Creek.
13 Q. Okay. Okay. I apologize. But
14 the -- the -- the wetland and the -- and the stream
15 crossing are in fair -- are fairly close
16 proximity -- I apologize -- would you say?
17 A. It appears the crossing on North
18 Creek is approximately twenty-five hundred feet
19 south of the south end of S.T. eight.
20 Q. And the crossing of Kline Kill?
21 A. The cross -- the crossing of
22 Kline Kill crosses through S.T. eight there.
23 Q. Correct. So that crossing is a
24 crossing of both the stream -- this class C(T.S.)
25 stream and a class two wetland?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
40/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 380
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. That's -- if that's a class --
3 classification of S.T. eight.
4 Q. Okay. I believe it is.
5 Now, turning to the application, in terms of
6 construction related in-stream work, do you
7 anticipate installing structures or need to install
8 structures within any of the four stream locations
9 that D.E.C. identified on the site visit? Do you
10 anticipate needing to install structures within the
11 stream during construction?
12 A. (Howland) Are you talking about
13 utility poles or temporary stream poles?
14 Q. No -- no. I'm talking about
15 temporary crossings, vehicular --.
16 A.L.J. STEIN: Excuse me --
17 excuse me. You really -- you really need to be
18 right on the microphone.
19 MS. HOWLAND: Okay. I'm sorry.
20 A.L.J. STEIN: And make sure it's
21 on. Thanks.
22 MS. HOWLAND: Okay.
23 BY MS. WILKINSON: (Cont'g.)
24 Q. Vehicular access, you know,
25 anything that would be necessary for construction.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
41/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 381
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. (Howland) The one we looked at
3 near the conservation area, we believe we don't
4 have to cross with equipment. We could probably
5 come in from both sides. The other streams will be
6 looked at during the preparation of environmental
7 management and construction plan.
8 Q. So on -- so at this point, you
9 can't say for sure that there would not be
10 structures placed within the stream during
11 construction?
12 A. There may be temporary stream
13 crossings.
14 Q. And on pages four sixty-eight and
15 four sixty-nine of the application, it mentions the
16 utilization of swamp mats and other minimally
17 evasive bridge materials.
18 A. We would refer to the D.E.C.'s
19 erosion -- their standard specifications for stream
20 crossings. The -- they -- in D.E.C.'s blue book,
21 there's stream crossings techniques and we would
22 refer to them.
23 But any stream crossing method
24 would be in environmental management and
25 construction plan, which would go to the D.E.C. for
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
42/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 382
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 approval before it's finalized.
3 Q. Correct. And -- and the
4 application noted that swamp mats may be utilized.
5 And I believe that was also referenced in D.E.C.
6 ten -- in the response to D.E.C. Ten.
7 A.L.J. STEIN: Excuse me. Are
8 you saying swamp mats?
9 MS. WILKINSON: Swamp -- yeah,
10 S-W-A-M-P M-A-T.
11 A.L.J. STEIN: Okay. Thank you.
12 What's a swamp mat?
13 MS. WILKINSON: That's what I'm
14 going to ask.
15 A.L.J. STEIN: Okay.
16 BY MS. WILKINSON: (Cont'g.)
17 Q. So, we -- we can start with -- I
18 guess, we can start with swamp mats, but the
19 application mentions the use of swamp mats and
20 other minimally invasive bridge materials. Can you
21 describe what a swamp mat is?
22 A. (Werth) It's typically a timber
23 mat used to limit soil compaction and erosion and
24 that type of stuff in wetland areas.
25 Q. Okay. And -- and so the -- the
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
43/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 383
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 reference in the application on, I believe, page
3 four sixty-eight and four sixty-nine to the use of
4 swamp mats and minimally invasive bridge materials,
5 would a swamp mat be a minimally evasive bridge
6 material? Is that what you're characterizing it
7 as?
8 A. I believe so.
9 Q. Is it something that would be
10 installed in the stream or would it be installed
11 over the stream?
12 A. (Howland) It would be --
13 typically, it's either installed over the stream.
14 They might put like a culvert in a bridge-type
15 thing. But it's all going to be site specific.
16 What the stream, how wide it is, what are the
17 characteristics of the stream.
18 So, those are -- you know, we
19 will refer to the D.E.C.'s blue book for stream
20 crossing techniques for those streams that we have
21 identified, that -- that we will be out in. When
22 we can get out in the field, on to these
23 properties, to see what the characteristics of the
24 stream are, then we can propose a stream crossing
25 technique, if needed.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
44/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 384
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 First, we'll seek to come in from
3 both sides to avoid stream crossings. But if we
4 cannot do that, we'll have to propose a stream
5 crossing technique.
6 Q. And Ms. Howland, you're aware of
7 the D.E.C. -- what's known as construction windows?
8 A. Yes, we are. Yes.
9 Q. And -- and the purpose of those
10 is to ensure that the fisheries are protected?
11 A. Correct.
12 Q. Particularly cold water fisheries
13 that support trout.
14 A. We're aware of the limitations.
15 Q. Right. And in response to the
16 question from D.E.C., whether you would be willing
17 to adhere to those construction windows, I believe
18 you said on the assumption -- and this is D.E.C.
19 Ten, question five response. On the assumption
20 that installing matted crossings is not in-stream
21 construction, you would be agreeable to, you know,
22 following construction windows for streams that
23 support trout and trout spawning.
24 A. Correct.
25 Q. But --
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
45/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 385
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. It --.
3 Q. -- you can see where installing
4 a -- a mat in the stream would -- would actually --
5 you know, a -- a structure in the stream could
6 inhibit the movement of trout in a stream, or could
7 hinder trout during those sensitive time periods?
8 A. And we wouldn't install mats in
9 those type of streams.
10 Q. Okay. So, for trout and trout
11 streams, we wouldn't be looking at the matted
12 crossings?
13 A. No. We would work with the
14 D.E.C. on the appropriate method for crossing those
15 streams.
16 Q. Okay.
17 A. (Ms. Gilstrap) I would like to
18 add that the use of a swamp mat in a stream would
19 probably, typically, be used if the stream was dry
20 during that time of year. So, there's -- there
21 would be no water flowing, but we would still want
22 to protect the -- the bed and bank of the stream,
23 then you could utilize a swamp mat.
24 Q. Okay. But we wouldn't be doing
25 that during the sensitive time periods for trout?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
46/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 386
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. Correct.
3 Q. Okay. Turning to wetlands,
4 because we're going to do the confidential
5 questions later, so skipping to wetlands, in the
6 application, table four point ten, and I believe
7 that's on page four forty-eight, indicates that one
8 point eight acres of D.E.C. regulated wetlands
9 would be impacted -- would be within the project
10 corridor and this would be cleared for -- there
11 would be some clearing in that -- in those wetlands
12 for construction. Is that correct?
13 A. (Werth) That's correct.
14 Q. And those -- those wetlands are
15 all forested wetlands, so the -- the clearing would
16 permanently convert them from a forested wetland to
17 a different type of wetland. Is that correct?
18 A. (Ms. Gilstrap) I would like to
19 add that in this document, the -- the database that
20 we looked at, the D.E.C. database that we pulled
21 these wetlands from, they did not assign cover
22 types.
23 A.L.J. STEIN: Please -- please
24 use the microphone.
25 A. (Cont'g.) Did not assign cover
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
47/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 387
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 types to these wetlands. And so, we assigned them
3 based on N.W.I., National Wetland Inventory
4 wetlands.
5 So, the -- the cover type would
6 have to be verified in the field or by D.E.C.
7 BY MS. WILKINSON: (Cont'g.)
8 Q. Okay. But assuming that it is
9 forest -- it is a forested wetland, that would be a
10 permanent conversion to a different wetland type?
11 A. (Werth) Correct.
12 (Howland) Yes. Along just the
13 right-of-way corridor.
14 Q. And I think the application also
15 indicates that there is one point one acres of
16 adjacent area within the project corridor. So
17 that -- that would be the most similarly impacted.
18 A. (Ms. Gilstrap) That -- the
19 adjacent area in the corridor, yes, would be
20 impacted.
21 Q. Okay. And so at this point,
22 other than the wetlands and the existing
23 right-of-way, there's been no field delineations or
24 assessment of the wetlands in the project; right?
25 A. (Howland) There was a field
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
48/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 388
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 delineation done where we had access along our
3 existing corridor.
4 Q. Right.
5 A. And that was provided as a
6 supplement. Beyond that, we have not gone on the
7 new right-of-way section to field delineate the
8 wetlands.
9 Q. So, as part of this project, you
10 would be doing that then? You would be delineating
11 the wetlands?
12 A. Correct. The -- for the new
13 right-of-way, we would go out and field delineate
14 the wetlands.
15 Q. And as part of the delineation,
16 you would be looking into the wetland functions,
17 that would be impacted by the project. Is that
18 correct?
19 A. That is correct.
20 Q. You would agree the functions
21 are, you know, what we consider like physical,
22 chemical, and biological processes occurring in and
23 making up the ecosystem of the wetlands, roughly?
24 A. We would evaluate the functions.
25 But I'm not sure if I understood --
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
49/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 389
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 Q. If you understood all of that.
3 A. -- all of what you said.
4 Q. Well, you would understand -- you
5 know, what is the -- in other words, do the
6 wetlands provide habitat, what is the -- the water
7 flow, how are they connected to other water
8 systems.
9 But at this point, we can't say
10 for sure what those wetland functions are of the
11 wetlands that would be impacted. Is that true?
12 A. That's correct.
13 Q. So, in -- in forested wetland
14 areas, you're going to evaluate the forest habitat
15 and dependent uses and that would be considered
16 part of, you know, the impact that you're going to
17 note in the E.M. and C.P. Is that correct?
18 A. That's correct. We'll evaluate
19 the functions and values of the wetlands.
20 Q. And you would evaluate potential
21 forest fragmentation that might occur from
22 construction of a right-of-way through a forested
23 wetland. Is that correct?
24 A. Yes, we'll evaluate. It'll be a
25 conversion of a forested wetland to a shrub-type
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
50/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 390
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 wetland.
3 Q. And you would evaluate any impact
4 on fisheries, you know, particularly where the
5 wetland crossings are in the vicinity of cold water
6 streams that might be impacted by the removal of
7 vegetation? I mean, it --.
8 A. I guess you could put in a
9 specific request of the list of what you would like
10 evaluated in a wetland -- in the wetland --
11 Q. Well, we're -- we're --
12 A. -- delineation.
13 Q. -- we're -- I mean, for example
14 in the Kline Kill area, we're talking about
15 crossing of a C(T.S.) stream in a -- you know, in
16 an area that's a forested wetland, so we want to be
17 sure and have a commitment that there will be an
18 evaluation of that stream crossing and that -- and
19 that wetland crossing, and the habitat in and
20 around that area.
21 A. Before we go out to do any field
22 work, I suggest -- we will have the biologist
23 coordinate with your staff to make sure we get
24 everything --
25 Q. Okay.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
51/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 391
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. -- that you would like.
3 Q. Okay. And we appreciate that.
4 We -- that's what we're here for the record,
5 building the record and we appreciate that.
6 As far as access roads in, you
7 know, sensitive environmental areas, do you
8 contemplate constructing access roads? Is it
9 possible you will construct an access road in a
10 wetland area, or over a stream?
11 A. There may be temporary access
12 roads if needed. If there is a wetland we could
13 span, there would be no -- and we could come in
14 from both directions, there would be no need to put
15 a temporary access road. However, if we do need to
16 cross that wetland, we would put in a temporary
17 access road across it.
18 Q. Now, I know you mentioned and I
19 think it was in response to D.P.S. Six, that you
20 talked about the possibility of grading certain
21 areas so you could move equipment through them and
22 leaving it as an unimproved access road. Would
23 wetland crossings be different? You know, access
24 roads and wetlands, would they be different than
25 grading an area and making it as an unimproved
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
52/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 392
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 access road?
3 A. Yes. We -- we would not -- all
4 of the wetlands from our preliminary engineering
5 would all be temporary access. We're not proposing
6 permanent access roads for any of the D.E.C.
7 regulated wetlands.
8 (Werth) Right. And it's called
9 out in section four point five point two point
10 three, is Exhibit Four, access roads would be
11 temporary in wetlands.
12 Q. Okay. And they would be -- and
13 then the area would be restored -- would be
14 completely restored to --
15 A. Yeah.
16 Q. -- to the wetland area --
17 A. Yes. They --
18 Q. -- after this?
19 A. -- will be restored --
20 (Howland) That's correct.
21 (Werth) -- to preconstruction --
22 Q. It wouldn't be left --
23 A. -- condition.
24 Q. -- as a graded -- as a graded
25 area or whatever?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
53/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 393
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 A. No.
3 Q. No? Okay.
4 A.L.J. STEIN: Please -- please
5 let the witness finish --
6 MS. WILKINSON: I'm sorry.
7 A.L.J. STEIN: -- their
8 responses. Thank you.
9 BY MS. WILKINSON: (Cont'g.)
10 Q. You're familiar with D.E.C.'s
11 wetland mitigation policy?
12 A. (Howland) Yes, I am.
13 Q. And you would agree, as part of
14 this, to prepare a wetland mitigation plan?
15 A. Yes, we would.
16 MS. WILKINSON: Your Honor,
17 just -- just for the record, I would like to enter
18 a pre-file D.E.C. exhibit, Freshwater Wetlands
19 Regulation Guidelines on Compensatory Mitigation.
20 A.L.J. STEIN: I will take this
21 as Exhibit Number Forty-eight for identification.
22 Can you give a copy to the
23 reporter, as well?
24 (Off-the-record discussion)
25 A.L.J. STEIN: And this is a
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
54/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 394
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 fifteen-page document -- fourteen-page document
3 entitled Freshwater Wetlands Regulation Guidelines
4 on Compensatory Mitigation, Department of
5 Environmental Conservation.
6 BY MS. WILKINSON: (Cont'g.)
7 Q. Ms. Howland, is Exhibit -- I
8 believe Forty-seven, which I just handed out, is
9 that what you understand to be the D.E.C. policy of
10 wetlands --?
11 A.L.J. STEIN: This is
12 Forty-eight.
13 BY MS. WILKINSON: (Cont'g.)
14 Q. Oh, I'm sorry. Forty-eight, is
15 that what you recognize as a D.E.C. policy on
16 wetlands mitigation?
17 A. (Howland) Yes. It's their --
18 your guidelines -- guidelines on wetland --
19 Q. Okay.
20 A. -- mitigation.
21 Q. Thank you.
22 MS. WILKINSON: No further
23 questions at this time, your Honor.
24 A.L.J. STEIN: Thank you very
25 much. *2.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
55/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 395
1 Howland/Gilstrap/Werth - Cross - Wilkinson
2 MR. BLOW: I have one follow-up
3 on the wetlands, which might be helpful if we did
4 it in the same area, rather than -- but I can wait,
5 if you want me to.
6 A.L.J. STEIN: No. Go ahead.
7 CROSS EXAMINATION
8 BY MR. BLOW:
9 Q. In -- are you aware of the -- of
10 the wetland weighing standards in -- I believe it's
11 part six sixty-three of D.E.C.'s regulations?
12 A. (Howland) I'm not familiar with
13 that section.
14 Q. Are you aware that there are
15 class one through four wetlands and that different
16 standards apply to when you can cross each of those
17 wetlands?
18 MS. WILKINSON: Your Honor, I'm
19 going to object because this is asking for a legal
20 conclusion and it's --
21 MR. BLOW: No, it's not.
22 MS. WILKINSON: -- it's -- it's
23 ready -- she said she's not familiar with the
24 standards.
25 A. I -- I -- I'm familiar that
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
56/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 396
1 Howland/Gilstrap/Werth - Cross - Blow
2 there's four classes of wetlands. As far as when
3 they can be crossed, I'm not familiar with that.
4 BY MR. BLOW: (Cont'g.)
5 Q. So, in your -- in the routing of
6 this -- of -- of -- in -- in deciding upon a route
7 for the project, are you saying that you did not
8 look at the wetland weighing standards? You did
9 not apply them in -- in figuring out the conditions
10 under which the wetlands can be crossed?
11 A. (Howland) The D.E.C. wetlands
12 that would be in the project right-of-way, we
13 identified the classes of those wetlands. I'm
14 sorry. I just lost my train of thought.
15 Q. All right. You -- you identified
16 the classes of the wetlands to be crossed?
17 A. Yes, which is --.
18 Q. But you're not aware that there
19 are -- that -- that associated with each of the
20 classes, there are characteristics and -- and
21 conditions in the wetland weighing standards that
22 specify when those condition -- when those wetlands
23 can be crossed, or the conditions under which those
24 wetlands can be crossed? Is -- is that correct?
25 MR. METCALFE: I'm going to
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
57/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 397
1 Howland/Gilstrap/Werth - Cross - Blow
2 object. I think the witnesses have testified only
3 that they're not familiar with the D.E.C.
4 regulations. And it sounds like Mr. Blow is
5 turning that in to a broader scope than what they
6 testified to.
7 A.L.J. STEIN: Can you rephrase
8 the question?
9 MR. BLOW: Well, I -- if they're
10 not aware of it, then I think they have a bigger
11 problem. So I -- I'm -- I think --.
12 MR. METCALFE: Well, they may not
13 be aware of it by citation and that might have been
14 what was --.
15 BY MR. BLOW: (Cont'g.)
16 Q. Well, I don't have the -- I don't
17 have the wetland weighing standards in my head, as
18 to -- there are certain wetland -- if -- if I
19 remember correctly, there are certain standards
20 that -- a -- a class one wetland can only be
21 crossed if there's no other reasonable alternative.
22 I believe that's it.
23 Ms. Wilkinson could help me out
24 here, but there are different standards for when
25 a -- a class two wetland weighing -- a class two
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
58/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 398
1 Howland/Gilstrap/Werth - Cross - Blow
2 wetland can only be crossed if a -- certain other
3 characteristics apply to it.
4 As -- as you get down to a class
5 four wetland, it's -- it can be crossed pretty
6 much -- you know, there's -- there's -- there are
7 less stringent standards as to when a wetland can
8 be crossed, depending on which class you're --
9 you're talking about, whether you go from class
10 one, two, three, and four.
11 Are you aware of those -- that
12 there are -- are you aware that there are less
13 stringent standards as you proceed for -- for --
14 when wetlands can be crossed, as you proceed from
15 class one through class four?
16 MS. WILKINSON: Your Honor, Mr.
17 Metcalfe had an objection and I echo his objection
18 because I think the weighing and balancing
19 standards in regulation go beyond the expertise of
20 this particular panel, because they take into
21 account social and economic and other
22 considerations. It's a very broad --
23 MR. BLOW: And I would ask --
24 MS. WILKINSON: -- way of
25 balancing.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
59/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 399
1 Howland/Gilstrap/Werth - Cross - Blow
2 MR. BLOW: -- then I would ask
3 Mr. Metcalfe to tell me which panel I can ask this
4 question to, because this -- this line of
5 questioning goes to whether, in the routing of this
6 line, state law is being applied. The wetland
7 weighing standards are state law, under Section
8 126.1(f) of the Public Service Law, State Law must
9 be complied with.
10 MS. WILKINSON: I agree, Mr.
11 Blow. But I think that --
12 MR. BLOW: Right. So, I don't --
13 MS. WILKINSON: -- I think the
14 condition is going to be --
15 MR. BLOW: -- I'm not sure why
16 you're --
17 MS. WILKINSON: -- applying it.
18 A.L.J. STEIN: Wait.
19 MR. BLOW: -- objecting to my
20 line of question.
21 MS. WILKINSON: Because the
22 condition --.
23 A.L.J. STEIN: Wait -- wait --
24 wait -- wait. Order in the court, please. One
25 person at a time.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
60/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 400
1 Howland/Gilstrap/Werth - Cross - Blow
2 Let me follow on Mr. Blow's
3 suggestion and check with Mr. Metcalfe as to --
4 will there be a subsequent panel that is qualified
5 to respond to these questions?
6 MR. METCALFE: Well, I don't know
7 that this panel is not qualified to respond, your
8 Honor.
9 I took it that his initial
10 question was focused on the citation for the D.E.C.
11 regulations. And their answer was there were --
12 they were not familiar with that citation.
13 He -- if he were to ask questions
14 about their familiar -- familiarity with the
15 weighing standards themselves and their application
16 here, that might be more helpful.
17 MR. BLOW: I believe I did and I
18 believe that the only person that objected to that
19 line was Ms. Wilkinson.
20 MR. METCALFE: And I didn't
21 object to that line.
22 MR. BLOW: Thank you.
23 A.L.J. STEIN: And as -- since
24 it's Mr. Metcalfe's witness, I think it's up to him
25 to make the objections.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
61/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 401
1 Howland/Gilstrap/Werth - Cross - Blow
2 So, if you could restate the
3 questions along the lines Mr. Metcalfe just
4 indicated, you can put it back to this panel.
5 MR. BLOW: Sure.
6 BY MR. BLOW: (Cont'g.)
7 Q. Are you aware, that as you go
8 from a class one wetland to a class four wetland,
9 the -- the reasons -- the allowable reasons for
10 crossing or the -- or the characteristics, what you
11 have to show in order to cross a wetland changes
12 and becomes less stringent, as you move from class
13 one to class four?
14 A. (Ms. Gilstrap) I am aware that
15 the class -- as you proceed from class one to class
16 four, that the wetlands become less valuable, that
17 class one wetlands are -- are the most valuable
18 wetlands, yes.
19 Q. And are you aware that the
20 allowable reasons or characteristics for crossing,
21 when -- when you decide whether you need to cross a
22 wetland, the showing that you have to make for a
23 class one wetland is different and higher than the
24 cross -- than the -- than the showing that one has
25 to make in crossing a class four wetland?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
62/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 402
1 Howland/Gilstrap/Werth - Cross - Blow
2 A. I am aware that the -- the
3 standards and protocol for class -- for crossing
4 class one wetlands are more stringent than crossing
5 class four wetlands.
6 Q. And in the routing of the -- of
7 the -- of the -- proposed routing of the project,
8 did -- did you -- do you believe that the
9 characteristics and the reasons and the showings
10 that are required to cross the various wetlands
11 have been made in your application?
12 A. We -- we have noted in our
13 application the classes of each of the wetlands --
14 D.E.C. wetlands that are located in the project
15 corridor.
16 There is one class three wetland
17 and three class two wetlands, located inside the
18 project right-of-way.
19 MR. BLOW: I think I'll leave it
20 there.
21 A.L.J. STEIN: Thank you.
22 For the Department of Agriculture and Markets?
23 MR. CUDDEBACK: Good morning,
24 your Honor.
25 A.L.J. STEIN: You need a
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
63/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 403
1 Howland/Gilstrap/Werth - Cross - Blow
2 microphone.
3 MR. CUDDEBACK: Thank you. Good
4 morning, your Honor.
5 We're proposing to enter three exhibits into
6 evidence. The first would be an information
7 request and response, D.P.S. Nine, requested April
8 19th, 2013, and replied May the 2nd, 2013.
9 A.L.J. STEIN: And this is a
10 one-page document?
11 MR. CUDDEBACK: It is.
12 A.L.J. STEIN: And --
13 MR. CUDDEBACK: Yes.
14 A.L.J. STEIN: -- we will take it
15 as Exhibit Number Forty-nine, for identification.
16 MR. CUDDEBACK: Okay. And the
17 second exhibit is also an information request,
18 D.P.S. Four, dated April 19th and responded May
19 2nd, 2013.
20 A.L.J. STEIN: Just a second.
21 And this is a three-page document?
22 MR. CUDDEBACK: It's a three-page
23 document, with one -- four attachments.
24 A.L.J. STEIN: And we'll take
25 that as Exhibit Number Fifty for identification.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
64/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 404
1 Howland/Gilstrap/Werth - Cross - Blow
2 MR. CUDDEBACK: Thank you. And
3 the third document is also an information request
4 and response, D.P.S. Number Thirty-nine, requested
5 August 29th, 2013, and replied September 13th,
6 2013.
7 A.L.J. STEIN: And that will be
8 marked as Exhibit Number Fifty-one.
9 MR. CUDDEBACK: Yes. That's two
10 pages and one attachment.
11 A.L.J. STEIN: Thank you.
12 MR. CUDDEBACK: Thank you.
13 CROSS EXAMINATION
14 BY MR. CUDDEBACK:
15 Q. Good morning. I want to direct
16 your attention to D.P.S. Nine, which has been
17 marked as Exhibit Forty-nine. Are you familiar
18 with that?
19 A. (Werth) Yes.
20 Q. In that exhibit, you indicated
21 that in creating the proposed transmission route
22 and switching station location, NYSEG has attempted
23 to balance impacts to open space, agricultural
24 fields and forested lands, to maximize -- to the
25 maximum extent practical. Is that true?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
65/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 405
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 A. Yes.
3 Q. Okay. You also had indicated
4 that NYSEG has maximized the use of field
5 boundaries and property boundaries, and that by
6 citing facility along natural corridors, such as
7 fields and property boundaries, the line avoids
8 bisecting properties and open spaces, while also
9 balancing impacts to the forest and agricultural
10 resources. Is that correct?
11 A. Yes.
12 Q. Please, if you would, turn your
13 attention to D.P.S. -- to the response to D.P.S.'s
14 information request, Number Four, which has been
15 marked as Exhibit Fifty.
16 If you go to the back of that
17 document, to the attachment, the last attachment,
18 which is a map labeled attachment three to that --
19 to your response, do you see the map?
20 A. Yes.
21 (Howland) Yes.
22 Q. So, the map appears to show the
23 proposed site for the Ghent switching station and a
24 portion of the National Grid trunk fifteen
25 extension loops. Is that correct?
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
66/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 406
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 A. (Werth) Yes.
3 Q. Looking at that map, it appears
4 that the switching station and extension loops are
5 located entirely on an agricultural field. Is that
6 correct?
7 A. Within the boundaries of this
8 map, yes.
9 Q. And in fact, it appears that the
10 extension loops bisect that particular agricultural
11 field. Is that correct?
12 A. They're located towards the
13 northern boundary of the field.
14 Q. Okay. According to NYSEG's
15 application, Exhibit Four Point Two Point One --
16 A. Okay.
17 Q. -- it states that the following
18 construction -- following construction of the
19 switching station, agricultural activities will not
20 resume on the site. Is that still accurate?
21 A. Within the boundaries of the --
22 of the switching station, yes.
23 Q. And the extension loop -- loops?
24 A. No. Underneath the transmission
25 lines, agricultural use will be permitted.
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
67/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 407
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 Q. Okay. Yesterday, you mentioned,
3 I think, in your testimony, that the -- the
4 switching station would take roughly six percent of
5 the agricultural field --
6 A. Yes.
7 Q. -- operation? Thank you. Now,
8 in that calculation, do you -- did you take into
9 account any structures on the field?
10 A. No. There was not the -- the
11 transmission lines. That was the switching station
12 site.
13 Q. Okay. And did that calculation
14 also take into account any access roads?
15 A. The access road has not been
16 designed, so we don't know the exact impact of
17 that.
18 Q. So do we know if construction
19 will -- construction of the switching station will
20 affect a larger area than the two-acre footprint of
21 that site?
22 A. If construction will?
23 Q. Would -- would the siting --
24 well, withdrawn.
25 Will the construction activities
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
68/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 408
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 affect a larger area than the two-acre footprint on
3 that site?
4 MR. METCALFE: Clarification.
5 Construction activities for the switching station
6 or the transmission line, or both?
7 BY MR. CUDDEBACK: (Cont'g.)
8 Q. Concerning the switching station.
9 A. (Werth) There may be additional
10 areas required for construction. I believe that
11 would be a better question directed towards the
12 engineers.
13 Q. Okay. Thank you.
14 A. (Howland) There should be a
15 temporary impact on construction.
16 A.L.J. STEIN: Can you repeat
17 your answer with the microphone?
18 A. (Cont'g.) That would be -- I
19 just noted if it was beyond the footprint of the
20 Ghent -- proposed Ghent switching station, that
21 would be a temporary impact for -- during
22 construction only.
23 BY MR. CUDDEBACK: (Cont'g.)
24 Q. So, there may be a need for
25 additional area -- a construction staging area
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
69/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 409
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 then, in relation to the construction of the
3 switching station here, as shown as on this map?
4 A. (Howland) There may be need for
5 additional temporary impacts for -- along with in
6 and out of that, to construct a station, I don't
7 believe we would put in a staging area. The
8 staging areas would probably be -- we would look
9 for other areas -- you know, that's what they --
10 you know, when we're bringing equipment in, you
11 know there may be a temporary spot for equipment
12 specific to the Ghent switching station, but we are
13 not proposing that that area will be a staging area
14 for the entire construction activities.
15 Q. Okay. Thank you. Do you know if
16 NYSEG is proposing to strip and then stockpile
17 topsoil from the areas affected by the construction
18 of the switching station and access road?
19 A. That hasn't been determined yet.
20 Q. Okay. When -- when -- when is
21 that normally determined?
22 A. During the preparation of
23 environmental management and construction plan.
24 Q. Okay. Thank you. Typically,
25 when you do strip and stockpile the topsoil, where
-
7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013
70/285
800.523.7887 Associated Reporters Int'l., Inc.
Associated Reporters Int'l., Inc. 800.523.7887
Page 410
1 Howland/Gilstrap/Werth - Cross - Cuddeback
2 do you -- where do you put that in temporary
3 storage?
4 A. If there's -- I'm having trouble
5 with your question because I look at when we strip
6 topsoil, it's for a different type of facility.
7 Q. Okay.
8 A. Now, this is going to be a
9 permanent facility, so you know, that has not been
10 determined.
11 Q. Okay. Thank you. So, it's --
12 it's conceivable then that the stockpiled topsoil