transcript for evidentiary hearing on 09.18.2013

Upload: protectghent

Post on 14-Apr-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    1/285

    STATE OF NEW YORK DEPARTMENT OF PUBLIC SERVICETHREE EMPIRE STATE PLAZA, ALBANY, NY 12223-1350

    www.dps.ny.gov

    PUBLIC SERVICE COMMISSION

    AUDREY ZIBELMAN PETER McGOWANChair General CounselPATRICIA L. ACAMPORA

    GARRY A. BROWN KATHLEEN H. BURGESSGREGG C. SAYRE Secretary

    DIANE X. BURMANCommissioners

    Re: Case 12-T-0248NYSEGColumbia County Transmission ProjectSeptember 18, 2013

    ** Please note this is a Preliminary transcript, subject to later edits when reviewed by the

    Administrative Law Judges assigned to the cases.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    2/285

    Page 342

    1

    2 STATE OF NEW YORKPUBLIC SERVICE COMMISSION

    3

    4 APPLICATION OF NEW YORK STATE ELECTRIC and GASCORPORATION FOR A CERTIFICATE OF ENVIRONMENTAL

    5 COMPATIBILITY AND PUBLIC NEED FOR THE CONSTRUCTION OFTHE "COLUMBIA COUNTY TRANSMISSION PROJECT,"

    6 APPROXIMATELY 11.1 MILES OF 115 KILOVOLT TRANSMISSIONLINES AND RELATED FACILITIES IN THE TOWNS OF CHATHAM,

    7 GHENT, AND STOCKPORT, IN COLUMBIA COUNTY

    8 CASE# 12-T-0248

    9 Tuesday, September 18, 201310 9:30 a.m.

    Third Floor Hearing Room11 Three Empire State Plaza

    Albany, New York 12223-135012

    13 A.L.J. ELEANOR STEINAdministrative Law Judge

    14 Three Empire State PlazaAlbany, New York 12223-1350

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    3/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 343

    1 Case 12-T-0248 - 9-18-20132 APPEARANCES:3 FOR PUBLIC SERVICE COMMISSION:

    4 STEVEN BLOW, ESQ.STAFF COUNSEL

    5 OFFICE OF GENERAL COUNSELNEW YORK STATE PUBLIC SERVICE COMMISSION

    6 Three Empire State PlazaAlbany, New York 12223-1350

    7ANDREW C. DAVIS

    8 Utility SupervisorOffice of Energy Efficieny and the

    9 Environment

    NEW YORK STATE PUBLIC SERVICE COMMISSION10 Three Empire State PlazaAlbany, New York 12223-1350

    11FOR DEPARTMENT OF STATE DEPARTMENT OF AGRICULTURE

    12 AND MARKETS:13 CHRIS CUDDEBACK, ESQ.

    SENIOR ATTORNEY14 108 Airline Drive

    Albany, New York 1223515

    MATTHEW J. BROWER16 Agricultural Resource SpecialistDivision of Land and Water Resources

    17 108 Airline DriveAlbany, New York 12235

    18NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL

    19 CONSERVATION:20 LISA A. WILKINSON, ESQ.

    Office of General Counsel21 625 Broadway 14th Floor

    Albany, New York 12233-150022SARAH EVANS

    23 DIVISION OF ENVIRONMENTAL PERMITS625 Broadway 14th Floor

    24 Albany, New York 12233-150025262728

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    4/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 344

    1 Case 12-T-0248 - 9-18-2013

    2 NEW YORK STATE ELECTRIC AND GAS:

    3 CULLEN and DYKMAN, LLPBY: DAVID T. METCALFE, ESQ.

    4 ANGELA N. CASCIONE, ESQ.100 Quentin Roosevelt Blvd.

    5 Garden City, New York 11530

    6FOR TOWN OF GHENT:

    7GREENBERG & GREENBERG

    8 BY: MARK DAVID GREENBERGFour East Court Street

    9 Hudson, New York 12534

    10 FOR PROTECT GHENT:

    11 GREENBERG TRAURIGBY: WILLIAM A. HURST, ESQ.

    12 54 State Street, 6th FloorAlbany, New York 12207

    13 PANEL:

    14 Carol HowlandSarah Gilstrap

    15 Dusty Werth16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    5/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 345

    1 Case 12-T-0248 - 9-18-2013

    2 (The hearing resumed at 9:36

    3 a.m.)

    4 A.L.J. STEIN: Good Morning.

    5 This is Judge Stein. We'll now pick up this

    6 hearing where we left off yesterday.

    7 I have circulated a revised

    8 schedule for today's cross examination and we're

    9 going to resume with cross examination of the

    10 panel, consisting of Carol Howland, Sarah Gilstrap,

    11 and Dusty Werth. And our first attorney will be

    12 the representative for the Town of Ghent.

    13 MR. GREENBERG: Thank you, Judge.

    14 A.L.J. STEIN: Would you like

    15 this exhibit marked for identification?

    16 MR. GREENBERG: Yes, I would,

    17 please, Judge.

    18 A.L.J. STEIN: This will be

    19 marked Exhibit Number Forty-six.

    20 MR. GREENBERG: And I would just

    21 describe that as a informational request and

    22 response to Protect Ghent's response number --

    23 request date August 29th, 2013, with response

    24 number C.C.T.P. dash twelve dash zero seven two.

    25 And this is Dusty Werth and Timothy -- Timothy

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    6/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 346

    1 Case 12-T-0248 - 9-18-2013

    2 Lynch.

    3 A.L.J. STEIN: And this is a

    4 two-page document. Thank you. That will be marked

    5 as Exhibit Number Forty-six.

    6 MR. GREENBERG: Thank you, Judge.

    7 Well, good morning, Ms. Howland, Ms. Gilstrap, Mr.

    8 Werth, your Honor.

    9 Just a couple questions of the

    10 panel, regarding the Town of Ghent Comprehensive

    11 Plan.

    12 CROSS EXAMINATION

    13 BY MR. GREENBERG:

    14 Q. I believe you made reference to

    15 that yesterday. Is that correct?

    16 A. (Werth) Yes.

    17 Q. Now, did you review the Town of

    18 Ghent Comprehensive Plan, in connection with your

    19 route planning?

    20 A. Yes.

    21 Q. And that was both for the -- the

    22 four alternative routes, as well as the four

    23 thirty-four point five kV alternative routes?

    24 A. Correct.

    25 Q. And did you review the entire

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    7/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 347

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 Town of Ghent Comprehensive Plan?

    3 A. We did.

    4 Q. Thank you. Now, if you could

    5 take a look at figure three dash four, which is

    6 entitled Columbia County Transmission Project,

    7 figure three dash four, NYSEG thirty-four point

    8 five kV alternative. I believe that was part of

    9 the response to the June 22nd, 2012 Appendix A,

    10 information request?

    11 Is that right, Mr. Metcalfe?

    12 MR. METCALFE: That would be

    13 correct. But more specifically, it was one of the

    14 additional info -- information requests, and

    15 specifically, B as in boy.

    16 MR. GREENBERG: Thank you, sir.

    17 A.L.J. STEIN: I'm sorry. What

    18 are we looking at?

    19 MR. GREENBERG: That's a map,

    20 Judge, which is figure three dash four, which is a

    21 map actually of the planned route for a thirty-four

    22 kV alternative that was put together by NYSEG.

    23 A.L.J. STEIN: And -- and where

    24 is this in the record? Is this in --

    25 MR. GREENBERG: It's in the

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    8/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 348

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 first --.

    3 A.L.J. STEIN: -- the first

    4 deficient?

    5 MR. METCALFE: It -- it --

    6 A.L.J. STEIN: First deficiency

    7 letter?

    8 MR. METCALFE: -- it is in the

    9 first deficiency letter, the response -- the first

    10 response to the deficiency letter.

    11 A.L.J. STEIN: Thank you.

    12 MR. GREENBERG: And -- and Judge,

    13 it was the map that I put up yesterday, but

    14 unfortunately it's very hard, I think, to be able

    15 to see it in this room, posted up on the board like

    16 that.

    17 A.L.J. STEIN: Go ahead.

    18 MR. GREENBERG: Thank you, Judge.

    19 BY MR. GREENBERG: (Cont'g.)

    20 Q. Panel, do you have that in front

    21 of you?

    22 A. (Werth) Yes.

    23 Q. Was your panel involved in

    24 connection with the production of figure three dash

    25 four?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    9/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 349

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. Yes.

    3 Q. Okay. Now, if I understand

    4 correctly, you would have been given the two tap

    5 points, the one to the right-hand side of the map

    6 here, Nobletown Road, and the other tap went on the

    7 left-hand side of the map, near Soller Heights, and

    8 would have been asked to basically set up a route

    9 that connected those tap points. Is that correct?

    10 A. Correct.

    11 Q. So, basically, it's not so much

    12 putting together point A to B, but in this case

    13 putting together the initial starting point near 9H

    14 and then running a -- a thirty-four point five kV

    15 line out to Nobletown Road, as well as one that

    16 would be going down to Soller Heights; correct?

    17 A. Correct.

    18 Q. Now, could you just give a -- a

    19 general description of how you went about doing

    20 that? If I understand, it was done as

    21 desk-topping, is that right?

    22 A. Yes. It was done through a

    23 desktop review of environmental and land use

    24 constraints in the area.

    25 Q. And -- and can you describe

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    10/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 350

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 exactly what a desktop review consists of?

    3 A. It's reviewing publicly available

    4 data and databases that can be loaded in to a

    5 G.I.S., or Geographic Information System, to

    6 provide mapping of all the constraints.

    7 Q. And there were no site visits in

    8 connection with the planning of NYSEG's thirty-four

    9 point five kV alternative; were there?

    10 A. Not specifically for this. There

    11 was site visits in the area that also coincide with

    12 the proposed one fifteen kV route.

    13 Q. Okay. Do -- do you have any

    14 estimate as to how many hours were spent, in

    15 connection with the planning and development of

    16 the -- the route for the thirty-four point five kV

    17 alternative that is shown in figure three dash

    18 four?

    19 A. I don't, off the top of my head.

    20 Q. Are -- are -- are you able to

    21 give a rough estimate at all?

    22 A. Not off the top of my head.

    23 Q. Were you personally involved

    24 in -- in -- in putting together the route for

    25 NYSEG's thirty-four point five kV alternative?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    11/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 351

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. Yes.

    3 Q. Now, some of the route that's

    4 shown in thirty -- in figure three dash four runs

    5 along existing roadways. Is that correct?

    6 A. Yes.

    7 Q. Okay. For -- for instance, if we

    8 look towards the -- the east, there is an area that

    9 it goes along Route 203, near where it's shown as

    10 Chase Road and -- and Big Woods Road.

    11 MS. HOWLAND: Dave, could we

    12 possibly get a larger map?

    13 (Off-the-record discussion)

    14 A. Could you please repeat the

    15 question?

    16 BY MR. GREENBERG: (Cont'g.)

    17 Q. Sure. If I could just bring your

    18 attention to the route -- it's -- on the east --

    19 it's east of the Taconic State Parkway. And if you

    20 follow the route along, it then meets up with Route

    21 203, near where it shows as Chase Road and Big

    22 Woods Road. Do you see that?

    23 A. (Werth) Yes.

    24 Q. Okay. Now, the route that you

    25 chose runs along Route 203 at that point; correct?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    12/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 352

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. For a short distance, yes.

    3 Q. Right. And -- and are you

    4 considering this to be a -- a transmission line, a

    5 sub-transmission line, a distribution line, or

    6 something else?

    7 A. I believe it is a transmission

    8 line.

    9 Q. Okay.

    10 A. Or sub-transmission line.

    11 Q. Or both? Thirty-four point five

    12 can be considered either a sub-transmission or a

    13 transmission line; correct?

    14 A. That would be a question for the

    15 engineers, I believe.

    16 Q. Okay. But in any case, the

    17 thirty-four point five kV line, that you're running

    18 can go along roadways; right?

    19 A. In certain areas, yes.

    20 Q. Okay. Well, what would be the

    21 constraints of being able to run along a roadway in

    22 one area, as compared to not being able to run

    23 along a roadway in another area?

    24 A. Having the available distance for

    25 the right-of-way.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    13/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 353

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 Q. Okay. And -- and what would that

    3 available distance for the right-of-way be?

    4 A. One hundred feet.

    5 Q. Well, that's NYSEG's

    6 determination as to what the right-of-way should

    7 be; correct?

    8 A. We were instructed that it would

    9 be a hundred foot right-of-way. I don't know what

    10 goes into that.

    11 Q. But you don't really require a

    12 hundred foot right-of-way for a thirty-four point

    13 five kV line; do you?

    14 A. That's not my area of expertise.

    15 Q. Okay. In fact, what you can do

    16 is you can trim some of the trees along the roadway

    17 to create enough space for that line. Isn't that

    18 right?

    19 A. Again, that's not my area.

    20 Q. Okay. So, getting back to the

    21 area of the route, where it runs along 203 and

    22 picks up that short area near Chase Road and Big

    23 Woods Road, now arguably, other than based on the

    24 constraint that you just talked about, you could

    25 run that line, for instance, all the way on 203, to

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    14/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 354

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 where it meets 22, and then run it all the way on

    3 Route 22, down to Nobletown Road, is that right?

    4 A. No.

    5 Q. And why not?

    6 A. There's not enough room for a

    7 hundred-foot-wide right-of-way.

    8 Q. Okay. So, the only reason that

    9 you're saying you can't take that route along 203

    10 and then 22 is because you would be requiring a

    11 hundred-foot right-of-way?

    12 A. I don't know that that is the

    13 only reason that we couldn't, but that is the

    14 primary reason that it was not an alternative.

    15 Q. Based on the instructions that

    16 you received?

    17 A. Based on the need for a

    18 hundred-foot right-of-way.

    19 Q. And -- and who -- who directed

    20 you that you required a hundred-foot right-of-way,

    21 in connection with the creation of an alternative

    22 thirty-four point five kV, for this project?

    23 A. That would have come from the

    24 NYSEG engineering.

    25 Q. Okay. Do you know anyone in

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    15/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 355

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 particular? Did you speak with anyone? Do you

    3 recall anyone in particular or is that written

    4 correspondence?

    5 A. I don't believe it was written

    6 correspondence. I believe it came through the

    7 NYSEG project manager at the time.

    8 Q. And -- and with that have been

    9 Mr. Bender?

    10 A. Yes.

    11 Q. And is Mr. Bender still the

    12 project manager?

    13 A. No.

    14 Q. Who -- who took Mr. Bender's

    15 place?

    16 A. Ayo.

    17 Q. Mr. Ayo or Ms. Ayo?

    18 A. Mr. Ayo.

    19 Q. Mr. Ayo?

    20 MR. METCALFE: The name's Ayo

    21 Jemiri.

    22 MR. GREENBERG: Thank you.

    23 MR. METCALFE: I -- I can point

    24 out, too, that the engineering panel, the Mike

    25 Barteck (phonetic spelling) Panel, scheduled for

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    16/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 356

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 next week, is very familiar with the company's

    3 standards for right-of-way widths, so I'm happy to

    4 steer you in that direction for better information

    5 than Mr. Werth is able to give you.

    6 MR. GREENBERG: Thank you, very

    7 much, Mr. Metcalfe. I appreciate that.

    8 A.L.J. STEIN: Just one moment.

    9 (Off-the-record discussion)

    10 A.L.J. STEIN: Please proceed.

    11 BY MR. GREENBERG: (Cont'g.)

    12 Q. Now, wouldn't it be true that the

    13 route, if it were able to go along existing

    14 roadways, would cause less environmental impact?

    15 A. (Werth) It would depend on -- on

    16 the route.

    17 Q. Well, would it depend on the

    18 route or would it depend on something on in

    19 particular, in connection with the road at that one

    20 area?

    21 A. It would depend on the route and

    22 what -- what resources are crossed.

    23 Q. Well, wouldn't that roadway

    24 already be crossing those resources? Or are you

    25 concerned again with the hundred-foot right-of-way?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    17/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 357

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. It would be a hundred-foot

    3 right-of-way and it would need to be outside of the

    4 road.

    5 Q. Okay. And when you say

    6 hundred-foot right-of-way, are you looking at a

    7 fifty feet on one side of the road and fifty feet

    8 on the other side of the road, or something else?

    9 A. No. It would need to be a

    10 hundred foot, consecutive, fifty feet either side

    11 of the center line.

    12 Q. So, the hundred-foot right-of-way

    13 is taken from -- fifty feet from the center line of

    14 the roadway?

    15 A. No. From the center line of the

    16 transmission line.

    17 Q. All right. So, if it ran along,

    18 say, the west side of the roadway, it would have to

    19 be fifty feet further to the west and then an

    20 additional fifty feet to the east?

    21 A. No.

    22 Q. I'm confused.

    23 A. It would be fifty feet either

    24 side of the center line of the transmission line.

    25 Q. Okay. And -- and part of that

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    18/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 358

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 would be in the roadway, most probably, and part of

    3 it would be not in the roadway. Isn't that

    4 correct?

    5 A. I -- I don't know NYSEG's

    6 standards, if they allow sharing of road

    7 right-of-way or not.

    8 Q. Now, looking again, at figure

    9 three dash four, now over more towards the western

    10 area, where the thirty-four point five kV line

    11 connects into what would be the new one fifteen

    12 substation, if you go eastward from there, your

    13 alternative route makes a -- a -- a north -- a

    14 northern turn and appears to basically go along the

    15 same route that was provided with the alternatives

    16 for the one fifteen kV line. Is that right?

    17 A. That's correct.

    18 Q. Now, did you consider continuing

    19 east to hook into anything on County Route 22 at

    20 that point?

    21 A. No. We determined that County

    22 Road -- or County Route 22 does not have adequate

    23 space for a hundred-foot right-of-way.

    24 Q. And -- and how did you make that

    25 determination? Through -- what on your desktop

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    19/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 359

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 in -- allowed you to make that determination?

    3 A. Well, in this area, we actually

    4 had site visits, so we had more than just desktop.

    5 But primarily it is the homes located along County

    6 Route 22 do not allow for the hundred-foot

    7 right-of-way.

    8 Q. Okay. And if I could just direct

    9 your attention to the exhibit that was just handed

    10 up, which is Protect Ghent's P.G. Nine.

    11 MR. GREENBERG: I'm sorry, your

    12 Honor. I had forgot what number you had marked

    13 that as.

    14 A.L.J. STEIN: Forty-six.

    15 BY MR. GREENBERG: (Cont'g.)

    16 Q. Exhibit Number Forty-six, Mr.

    17 Werth, you prepared this response?

    18 A. (Werth) Yes.

    19 Q. Okay. If I understand correctly,

    20 this was served on Mr. Hurst, actually, during the

    21 hearing yesterday. Is that correct?

    22

    23 A. I'm not sure when it was served.

    24 Q. Well, what -- when did you --

    25 when did you create this response?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    20/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 360

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. I don't believe --.

    3 MR. METCALFE: I -- I'm going to

    4 object because the -- the witness doesn't know --

    5 MR. GREENBERG: Okay.

    6 MR. METCALFE: -- the process

    7 that occurred after he had signed off on the --

    8 MR. GREENBERG: I'll ask him --

    9 MR. METCALFE: -- I.R. --.

    10 MR. GREENBERG: -- another way.

    11 MR. METCALFE: Thank you.

    12 MR. GREENBERG: I'll -- I'll

    13 withdraw the question. Thank you, sir.

    14 BY MR. GREENBERG: (Cont'g.)

    15 Q. Do you know when you provided the

    16 information in connection with this response,

    17 Exhibit Number Forty-six?

    18 A. (Werth) I believe it was last

    19 week.

    20 Q. Okay. Now, looking at response

    21 number one, this states as a -- that no analysis or

    22 studies have been completed for the potential use

    23 of County Route 22 as an alternative, because it

    24 was determined -- and I'm paraphrasing that, County

    25 Route 22 has many residences that are less than a

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    21/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 361

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 hundred feet off of County Route 22, which would

    3 require that a route along this route would have to

    4 take homes or be required to cross the road

    5 multiple times, if there are not residence on both

    6 sides.

    7 Is that information that you

    8 provided, Mr. Werth?

    9 A. Yes.

    10 Q. Okay. How many residences are we

    11 talking about?

    12 A. I don't know off the top of my

    13 head.

    14 Q. Is it more than one or two?

    15 A. Yes.

    16 Q. Is it more than ten?

    17 A. I -- I don't know.

    18 Q. And when you say take homes, are

    19 you talking about actually having to take homes by

    20 eminent domain or destroy them to allow the line to

    21 go through?

    22 A. The houses would have to be

    23 removed to allow for the hundred-foot right-of-way.

    24 Q. Are there any existing lines

    25 running along County Route 22?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    22/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 362

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A. I believe there are.

    3 Q. And what type of lines currently

    4 run along County Route 22?

    5 A. I'm not sure, but I believe that

    6 they would be distribution lines.

    7 Q. Okay. And -- and those are

    8 thirty-four point five distribution lines?

    9 A. I do not know that.

    10 Q. Okay. Now, I -- I guess it's --

    11 again, is -- is it your panel's place to be able to

    12 discuss whether a new thirty-four point five

    13 kilovolt line could travel along the existing line

    14 that's on Route 20 -- on County Route 22?

    15 MR. METCALFE: I'd aim that at

    16 the Mike Barteck Panel.

    17 MR. GREENBERG: Thank you, sir.

    18 BY MR. GREENBERG: (Cont'g.)

    19 Q. Okay. Now, you also stated in

    20 Exhibit Forty-six that the road would have to --

    21 the line would have to cross the road multiple

    22 times.

    23 Now, did you consider, in

    24 planning NYSEG's thirty-four point five kV

    25 alternative, whether any portions of the line could

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    23/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 363

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 be undergrounded?

    3 A. (Werth) No.

    4 Q. When you were planning on the

    5 four alternatives for the one fifteen kV line, did

    6 you consider whether any portions of that line

    7 could be undergrounded?

    8 A. No. That was outside of the --

    9 our scope of work.

    10 Q. And -- and when you say outside

    11 your scope of work, you're saying it was outside

    12 your scope of direction from your principal. Is

    13 that correct?

    14 A. Yes. We were hired to route an

    15 overhead transmission line.

    16 Q. And it was made clear to you

    17 that -- from the very start that none of it would

    18 be undergrounded. Is that correct?

    19 A. Like I said, we were hired to

    20 route an overhead transmission line, not an

    21 underground transmission line.

    22 Q. Well, what about a partially

    23 underground transmission line?

    24 A. No. We were directed to site a

    25 overhead transmission line.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    24/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 364

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 Q. Thank you very much.

    3 MR. GREENBERG: I have no further

    4 questions, Judge.

    5 A.L.J. STEIN: Thank you.

    6 For the Department of Environmental Conservation?

    7 MS. WILKINSON: Your Honor, I'm

    8 going to be handing out interrogatory responses.

    9 And I'm going to hand them out. We had sixteen

    10 questions, sixteen response -- sets of responses.

    11 I'm going to hand them in packet of all sixteen

    12 responses, if that's okay, for my exhibit. But I'm

    13 going to ask questions on some of the individual

    14 responses.

    15 Or do you want to mark them

    16 individually?

    17 A.L.J. STEIN: I'm willing to

    18 take them as a packet, if they -- do they have --

    19 are -- have you numbered the pages?

    20 MS. WILKINSON: We've numbered --

    21 the responses are numbered and most of the

    22 responses are one page, front and back. Some of

    23 them are stapled. Anyone that's multiple pages,

    24 I've stapled, but I also have a summary table of

    25 each response and the number of pages.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    25/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 365

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 A.L.J. STEIN: Okay. I'm just

    3 concerned that --.

    4 MS. WILKINSON: I can do it

    5 separately.

    6 A.L.J. STEIN: I'm just concerned

    7 that if parties want to refer to this in the

    8 record --

    9 MS. WILKINSON: Okay.

    10 A.L.J. STEIN: -- there would be

    11 no way to say Exhibit Forty-six, page twelve.

    12 MS. WILKINSON: That's fine. I

    13 can do -- we can do it separately.

    14 I have -- I mean, I'm still going

    15 to hand them out as packets, just because --

    16 A.L.J. STEIN: That's fine.

    17 MS. WILKINSON: -- that's how

    18 they were. And because some of the responses have

    19 voluminous attachments, I don't have copies of the

    20 attachments. I did copy the question and response,

    21 but not the attachment, as directed. So, I have

    22 complete copies for you and the court reporter.

    23 A.L.J. STEIN: Thank you.

    24 MS. WILKINSON: Do you want -- so

    25 I'll go through each one of them, individually,

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    26/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 366

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 then? I can do that.

    3 A.L.J. STEIN: Yeah. But we'll

    4 identify them collectively as Exhibit Number

    5 Forty-six -- Forty-Seven. Sorry.

    6 MS. WILKINSON: Okay.

    7 (Off-the-record discussion)

    8 MR. METCALFE: Lisa, does this

    9 include -- you handed out four or five I.R.s

    10 yesterday.

    11 It's the whole batch?

    12 MS. WILKINSON: It's the whole

    13 batch.

    14 MR. METCALFE: Great.

    15 (Off-the-record discussion)

    16 MR. BLOW: Your Honor, may I

    17 inquire -- Ms. Wilkinson said that she is not

    18 providing copies of the attachments, but the

    19 attachments are -- have they been pre-filed?

    20 MS. WILKINSON: Yes, they have.

    21 MR. BLOW: So, the attachments

    22 are a part of the exhibit --

    23 MS. WILKINSON: Correct.

    24 MR. BLOW: -- it's just they're

    25 not being handed out in hard copy?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    27/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 367

    1 Howland/Gilstrap/Werth - Cross - Greenberg

    2 MS. WILKINSON: Correct.

    3 I have a copy -- a hard copy for the judge and I

    4 can supply a copy to the court reporter if you want

    5 me to do that.

    6 A.L.J. STEIN: You don't need to.

    7 MS. WILKINSON: Okay.

    8 MR. BLOW: Okay.

    9 MS. WILKINSON: So, what I just

    10 handed out --

    11 MR. BLOW: Thanks.

    12 MS. WILKINSON: -- were

    13 interrogatory responses to D.E.C. One through

    14 Sixteen.

    15 A.L.J. STEIN: So this will be

    16 Exhibit Number Forty-seven for identification. And

    17 it consists of D.E.C. interrogatories and

    18 responses, numbers One through Sixteen.

    19 Is that correct, Ms. Wilkinson?

    20 MS. WILKINSON: That's correct.

    21 A.L.J. STEIN: Thank you.

    22 CROSS EXAMINATION

    23 BY MS. WILKINSON:

    24 Q. Good morning.

    25 A. (Howland) Good morning.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    28/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 368

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 Q. And I'll start by assuming that

    3 there are no changes to the interrogatory responses

    4 and the responses, as the authors are indicated,

    5 are the same responses that you would give today?

    6 A. That's correct.

    7 Q. Okay. I'm going to start by

    8 asking you about best management practices. In

    9 D.E.C. One, we -- D.E.C. inquired whether NYSEG

    10 would utilize the best management practices that

    11 had been developed in the case of the Rochester

    12 Reliability Project, whether those practices would

    13 also be utilized for the Columbia County

    14 Transmission Project?

    15 A. Yes, they would.

    16 Q. And today, you are not aware of

    17 any changes to those practices that NYSEG has

    18 implemented in the case of Rochester?

    19 A. No. There's no changes to that

    20 document.

    21 Q. And there's no changes to the

    22 practices that you've actually implemented to the

    23 project? In other words, they may -- the document

    24 may not have changed, but on the ground, have you

    25 made any changes?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    29/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 369

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. Are you referring to this project

    3 or the Rochester project?

    4 Q. Well, I'm referring to the

    5 Rochester project. In other words, are there --

    6 have you made changes to the best management

    7 practices, in the field, in implementation?

    8 MR. METCALFE: Objection. That's

    9 outside the scope of the --

    10 MS. WILKINSON: Let me --

    11 MR. METCALFE: -- company's --

    12 MS. WILKINSON: -- rephrase it.

    13 MR. METCALFE: -- direct case.

    14 BY MS. WILKINSON: (Cont'g.)

    15 Q. Have you made changes to the best

    16 management practices in that project that you

    17 believe would be appropriate for this project, that

    18 would cause you to update the document for this

    19 project?

    20 A. (Howland) There have been no

    21 changes to the document.

    22 Q. And there's no -- there's --

    23 you're not foreseeing any updates to the -- to the

    24 document, as applied to this project?

    25 A. No, I do not.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    30/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 370

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 Q. So, as far as -- so as far as we

    3 know today, that document would govern this

    4 project's best management practices, as applied to

    5 terrestrial and wildlife resources?

    6 A. The document would be used unless

    7 there's a specific certificate condition that

    8 overrode that.

    9 Q. Okay. And that include -- so

    10 that would apply to every single topic covered in

    11 that document?

    12 A. Correct. The -- our best

    13 management practices are typical procedures to be

    14 followed for the development of the environmental

    15 management and construction plan. However, if

    16 there's specific certificate conditions, they would

    17 be followed first.

    18 Q. Okay. So, turning to streams, in

    19 section four point nine of the application, water

    20 resources, which one of you prepared that

    21 document -- or that section of Exhibit Four, in the

    22 application?

    23 A. I have written that text.

    24 Q. Okay. And that was based on a

    25 desktop analysis?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    31/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 371

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. Yes. That was based on

    3 information we were able to find through D.E.C. and

    4 other recourses.

    5 Q. Ms. Howland and Mr. Werth, did

    6 you review that section?

    7 A. (Werth) Yes.

    8 (Howland) Yes.

    9 Q. Ms. Gilstrap, in preparing that

    10 section, did you conduct any site visits?

    11 A. (Ms. Gilstrap) No, I did not

    12 conduct -- conduct any site visits.

    13 Q. And as far as D.E.C. Ten is

    14 concerned, I believe the response was prepared by

    15 Mr. Werth and Ms. Howland.

    16 Ms. Gilstrap, did you review that

    17 response at all?

    18 A. I was on maternity leave.

    19 Q. Okay. Now, did any of the

    20 witnesses consult with D.E.C. in preparing table

    21 four point one five, which is the -- well, the

    22 table in the application and also the -- as updated

    23 in D.E.C. Ten, I believe. Prior to preparing that

    24 table, did any of the witnesses consult with D.E.C.

    25 staff?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    32/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 372

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. For the table in the application,

    3 we did not consult with staff.

    4 Q. And the table that was attached

    5 to the response to D.E.C. Ten?

    6 A. (Werth) No.

    7 Q. No? Did anyone consult with

    8 D.E.C., regarding the use of the National

    9 Hydrologic Database?

    10 A. No.

    11 (Howland) No.

    12 Q. And did anyone ask D.E.C. whether

    13 that information was accurate?

    14 A. (Werth) No.

    15 Q. Ms. Gilstrap, so you did not go

    16 on a site visit then, a few weeks ago, to see the

    17 stream crossings?

    18 A. (Ms. Gilstrap) No.

    19 Q. But Mr. Werth was telling me you

    20 had a site visit?

    21 A. (Werth) Yes.

    22 Q. And D.E.C. had listed four

    23 crossing locations that were of particular

    24 interest, I believe, right? Widows -- right, the

    25 crossing at Widows Creek? There is a crossing at

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    33/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 373

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 Widows Creek; correct?

    3 A. Correct.

    4 Q. Now, you didn't actually see that

    5 crossing on the site visit, but that was one of the

    6 ones listed. And I believe D.E.C. also listed the

    7 Kline Kill crossing.

    8 A. Correct.

    9 Q. Which we did see?

    10 A. Correct.

    11 Q. And D.E.C. also listed a crossing

    12 at Fitting Creek?

    13 A. Correct.

    14 Q. Which we didn't see the -- we saw

    15 the creek and a representative location of the

    16 crossing, but we didn't see the actual crossing

    17 point?

    18 A. Correct.

    19 Q. Have you or Ms. Howland seen --

    20 have you seen the crossing point at Fitting Creek,

    21 where the -- where the project is proposed to

    22 cross?

    23 A. No.

    24 Q. Have you visited that location?

    25 A. No. Just on the site visit with

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    34/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 374

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 you guys.

    3 Q. Okay. And then the fourth, I

    4 believe, was a crossing at the tributary to North

    5 Creek, which I think was near the Haybed (phonetic

    6 spelling) property, but we did make it on the site

    7 visit. Is that correct?

    8 A. Correct.

    9 Q. And --.

    10 A. (Howland) We have not gone on

    11 private property for the routing.

    12 Q. Okay. So, we did see the

    13 crossing at Kline Kill, which is classified as a

    14 C(T.S.) stream, indicating it supports trout

    15 spawning. You know, based on your site visit then,

    16 were you able to assess the characteristics of the

    17 stream?

    18 A.L.J. STEIN: Let me just -- let

    19 me just interject for one second. Is that C dash

    20 T.S.?

    21 MS. WILKINSON: It's -- I believe

    22 it's C parenthesis T.S.

    23 A.L.J. STEIN: Okay.

    24 MS. WILKINSON: I will provide

    25 that. I apologize --

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    35/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 375

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A.L.J. STEIN: Okay.

    3 MS. WILKINSON: -- but I will

    4 provide that. I think it's parenthesis T.S.

    5 A.L.J. STEIN: Okay. If you

    6 could just make it clear as you go, so the reporter

    7 gets a clear --

    8 MS. WILKINSON: Sure.

    9 It's C -- it's C parenthesis T.S.

    10 A.L.J. STEIN: Thanks.

    11 MS. WILKINSON: Indicating trout

    12 spawning.

    13 BY MS. WILKINSON: (Cont'g.)

    14 Q. And based on the site visit, were

    15 you able to assess in -- whether it would be

    16 possible to span that stream, rather than place

    17 structures in the stream?

    18 A. (Werth) Preliminary engineering

    19 does not indicate any structures would be placed

    20 within that stream.

    21 Q. Or within a hundred feet of the

    22 stream?

    23 A. I believe that's the case, but I

    24 need to check.

    25 (Howland) The short answer is we -- we will not

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    36/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 376

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 place structures in the stream. Just how far back

    3 we can go to span it, we're not sure. And Dusty's

    4 trying to see on that.

    5 Q. I mean, I believe if you look at

    6 page four sixty-eight and four sixty-nine of the

    7 application, I think that's where you discuss --.

    8 A. (Howland) Four six eight and

    9 four six nine.

    10 (Werth) And the response to

    11 D.P.S. Six, we did not identify a structure within

    12 a hundred feet of that stream.

    13 Q. Okay. So, as you know right now,

    14 there would be -- there would be no need to place

    15 structures in or within a hundred feet of that

    16 stream?

    17 A. Correct.

    18 Q. Now, as far the tributary to

    19 North Creek is concerned, which was not viewed, are

    20 you aware of whether that -- that particular stream

    21 supports trout?

    22 A. According to the classification

    23 from the D.E.C. data set that we received, it does

    24 not.

    25 Q. But did you check with D.E.C. to

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    37/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 377

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 see whether, in fact, that stream supports trout?

    3 A. No, we did not.

    4 Q. If -- if we look at the map and

    5 the -- the two figures, figure -- figures four

    6 point four and four point five, if -- well, four

    7 point five, I believe --.

    8 A. Is that four dash four and four

    9 dash --?

    10 Q. I -- I -- I apologize. Four dash

    11 four and four dash five, it's in Exhibit Four of

    12 the application. And if you look at the -- the

    13 crossing, because you -- your application doesn't

    14 overlay the streams and the wetlands, but looking

    15 at the location of the North Creek crossing, and

    16 if -- and I can point -- I can point that out to

    17 you on -- I believe D.E.C., when we sent out our

    18 requests for site visits, we included a map. We

    19 actually drew it on figure four point five. I

    20 don't know if that would help you. If you can tell

    21 from figure four point five on the application, the

    22 crossing at North Creek.

    23 A. Yes.

    24 Q. So, you see that general

    25 location?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    38/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 378

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. Yes.

    3 Q. Turning to figure four point

    4 four, can you pinpoint relatively the same location

    5 on that figure where the crossing would occur? Or

    6 the vicinity?

    7 A. Yes.

    8 Q. So, it's -- the crossing occurs

    9 in or near what's been marked as S.T. Eight or

    10 Wetland Number Eight on the map?

    11 A. I believe it would be south of

    12 S.T. Eight. Is that correct?

    13 Q. Slightly south, but the project

    14 would cross S.T. Eight and then, not much further

    15 than that, would cross the North Creek.

    16 A.L.J. STEIN: I'm not sure I'm

    17 seeing what you're seeing -- looking, but I'm not

    18 sure I'm looking at the right -- you're looking at

    19 figure four point four?

    20 MS. WILKINSON: Right. Figure

    21 four point four and S.T. Eight is -- it runs from

    22 north to south, on the top of the page, to maybe

    23 two-thirds down --

    24 A.L.J. STEIN: Right.

    25 MS. WILKINSON: -- heading east.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    39/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 379

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 And I'm looking where the project is crossing.

    3 A.L.J. STEIN: Oh, I see. So,

    4 sort of the eastern branch of S.T. Eight?

    5 MS. WILKINSON: Right.

    6 A.L.J. STEIN: I see. Thank you.

    7 BY MS. WILKINSON: (Cont'g.)

    8 Q. So, the crossing and the wetland

    9 area are -- are relatively in close proximity,

    10 would you say?

    11 A. (Werth) I believe S.T. Eight

    12 corresponds with Kline Kill, not North Creek.

    13 Q. Okay. Okay. I apologize. But

    14 the -- the -- the wetland and the -- and the stream

    15 crossing are in fair -- are fairly close

    16 proximity -- I apologize -- would you say?

    17 A. It appears the crossing on North

    18 Creek is approximately twenty-five hundred feet

    19 south of the south end of S.T. eight.

    20 Q. And the crossing of Kline Kill?

    21 A. The cross -- the crossing of

    22 Kline Kill crosses through S.T. eight there.

    23 Q. Correct. So that crossing is a

    24 crossing of both the stream -- this class C(T.S.)

    25 stream and a class two wetland?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    40/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 380

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. That's -- if that's a class --

    3 classification of S.T. eight.

    4 Q. Okay. I believe it is.

    5 Now, turning to the application, in terms of

    6 construction related in-stream work, do you

    7 anticipate installing structures or need to install

    8 structures within any of the four stream locations

    9 that D.E.C. identified on the site visit? Do you

    10 anticipate needing to install structures within the

    11 stream during construction?

    12 A. (Howland) Are you talking about

    13 utility poles or temporary stream poles?

    14 Q. No -- no. I'm talking about

    15 temporary crossings, vehicular --.

    16 A.L.J. STEIN: Excuse me --

    17 excuse me. You really -- you really need to be

    18 right on the microphone.

    19 MS. HOWLAND: Okay. I'm sorry.

    20 A.L.J. STEIN: And make sure it's

    21 on. Thanks.

    22 MS. HOWLAND: Okay.

    23 BY MS. WILKINSON: (Cont'g.)

    24 Q. Vehicular access, you know,

    25 anything that would be necessary for construction.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    41/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 381

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. (Howland) The one we looked at

    3 near the conservation area, we believe we don't

    4 have to cross with equipment. We could probably

    5 come in from both sides. The other streams will be

    6 looked at during the preparation of environmental

    7 management and construction plan.

    8 Q. So on -- so at this point, you

    9 can't say for sure that there would not be

    10 structures placed within the stream during

    11 construction?

    12 A. There may be temporary stream

    13 crossings.

    14 Q. And on pages four sixty-eight and

    15 four sixty-nine of the application, it mentions the

    16 utilization of swamp mats and other minimally

    17 evasive bridge materials.

    18 A. We would refer to the D.E.C.'s

    19 erosion -- their standard specifications for stream

    20 crossings. The -- they -- in D.E.C.'s blue book,

    21 there's stream crossings techniques and we would

    22 refer to them.

    23 But any stream crossing method

    24 would be in environmental management and

    25 construction plan, which would go to the D.E.C. for

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    42/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 382

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 approval before it's finalized.

    3 Q. Correct. And -- and the

    4 application noted that swamp mats may be utilized.

    5 And I believe that was also referenced in D.E.C.

    6 ten -- in the response to D.E.C. Ten.

    7 A.L.J. STEIN: Excuse me. Are

    8 you saying swamp mats?

    9 MS. WILKINSON: Swamp -- yeah,

    10 S-W-A-M-P M-A-T.

    11 A.L.J. STEIN: Okay. Thank you.

    12 What's a swamp mat?

    13 MS. WILKINSON: That's what I'm

    14 going to ask.

    15 A.L.J. STEIN: Okay.

    16 BY MS. WILKINSON: (Cont'g.)

    17 Q. So, we -- we can start with -- I

    18 guess, we can start with swamp mats, but the

    19 application mentions the use of swamp mats and

    20 other minimally invasive bridge materials. Can you

    21 describe what a swamp mat is?

    22 A. (Werth) It's typically a timber

    23 mat used to limit soil compaction and erosion and

    24 that type of stuff in wetland areas.

    25 Q. Okay. And -- and so the -- the

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    43/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 383

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 reference in the application on, I believe, page

    3 four sixty-eight and four sixty-nine to the use of

    4 swamp mats and minimally invasive bridge materials,

    5 would a swamp mat be a minimally evasive bridge

    6 material? Is that what you're characterizing it

    7 as?

    8 A. I believe so.

    9 Q. Is it something that would be

    10 installed in the stream or would it be installed

    11 over the stream?

    12 A. (Howland) It would be --

    13 typically, it's either installed over the stream.

    14 They might put like a culvert in a bridge-type

    15 thing. But it's all going to be site specific.

    16 What the stream, how wide it is, what are the

    17 characteristics of the stream.

    18 So, those are -- you know, we

    19 will refer to the D.E.C.'s blue book for stream

    20 crossing techniques for those streams that we have

    21 identified, that -- that we will be out in. When

    22 we can get out in the field, on to these

    23 properties, to see what the characteristics of the

    24 stream are, then we can propose a stream crossing

    25 technique, if needed.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    44/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 384

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 First, we'll seek to come in from

    3 both sides to avoid stream crossings. But if we

    4 cannot do that, we'll have to propose a stream

    5 crossing technique.

    6 Q. And Ms. Howland, you're aware of

    7 the D.E.C. -- what's known as construction windows?

    8 A. Yes, we are. Yes.

    9 Q. And -- and the purpose of those

    10 is to ensure that the fisheries are protected?

    11 A. Correct.

    12 Q. Particularly cold water fisheries

    13 that support trout.

    14 A. We're aware of the limitations.

    15 Q. Right. And in response to the

    16 question from D.E.C., whether you would be willing

    17 to adhere to those construction windows, I believe

    18 you said on the assumption -- and this is D.E.C.

    19 Ten, question five response. On the assumption

    20 that installing matted crossings is not in-stream

    21 construction, you would be agreeable to, you know,

    22 following construction windows for streams that

    23 support trout and trout spawning.

    24 A. Correct.

    25 Q. But --

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    45/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 385

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. It --.

    3 Q. -- you can see where installing

    4 a -- a mat in the stream would -- would actually --

    5 you know, a -- a structure in the stream could

    6 inhibit the movement of trout in a stream, or could

    7 hinder trout during those sensitive time periods?

    8 A. And we wouldn't install mats in

    9 those type of streams.

    10 Q. Okay. So, for trout and trout

    11 streams, we wouldn't be looking at the matted

    12 crossings?

    13 A. No. We would work with the

    14 D.E.C. on the appropriate method for crossing those

    15 streams.

    16 Q. Okay.

    17 A. (Ms. Gilstrap) I would like to

    18 add that the use of a swamp mat in a stream would

    19 probably, typically, be used if the stream was dry

    20 during that time of year. So, there's -- there

    21 would be no water flowing, but we would still want

    22 to protect the -- the bed and bank of the stream,

    23 then you could utilize a swamp mat.

    24 Q. Okay. But we wouldn't be doing

    25 that during the sensitive time periods for trout?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    46/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 386

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. Correct.

    3 Q. Okay. Turning to wetlands,

    4 because we're going to do the confidential

    5 questions later, so skipping to wetlands, in the

    6 application, table four point ten, and I believe

    7 that's on page four forty-eight, indicates that one

    8 point eight acres of D.E.C. regulated wetlands

    9 would be impacted -- would be within the project

    10 corridor and this would be cleared for -- there

    11 would be some clearing in that -- in those wetlands

    12 for construction. Is that correct?

    13 A. (Werth) That's correct.

    14 Q. And those -- those wetlands are

    15 all forested wetlands, so the -- the clearing would

    16 permanently convert them from a forested wetland to

    17 a different type of wetland. Is that correct?

    18 A. (Ms. Gilstrap) I would like to

    19 add that in this document, the -- the database that

    20 we looked at, the D.E.C. database that we pulled

    21 these wetlands from, they did not assign cover

    22 types.

    23 A.L.J. STEIN: Please -- please

    24 use the microphone.

    25 A. (Cont'g.) Did not assign cover

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    47/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 387

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 types to these wetlands. And so, we assigned them

    3 based on N.W.I., National Wetland Inventory

    4 wetlands.

    5 So, the -- the cover type would

    6 have to be verified in the field or by D.E.C.

    7 BY MS. WILKINSON: (Cont'g.)

    8 Q. Okay. But assuming that it is

    9 forest -- it is a forested wetland, that would be a

    10 permanent conversion to a different wetland type?

    11 A. (Werth) Correct.

    12 (Howland) Yes. Along just the

    13 right-of-way corridor.

    14 Q. And I think the application also

    15 indicates that there is one point one acres of

    16 adjacent area within the project corridor. So

    17 that -- that would be the most similarly impacted.

    18 A. (Ms. Gilstrap) That -- the

    19 adjacent area in the corridor, yes, would be

    20 impacted.

    21 Q. Okay. And so at this point,

    22 other than the wetlands and the existing

    23 right-of-way, there's been no field delineations or

    24 assessment of the wetlands in the project; right?

    25 A. (Howland) There was a field

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    48/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 388

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 delineation done where we had access along our

    3 existing corridor.

    4 Q. Right.

    5 A. And that was provided as a

    6 supplement. Beyond that, we have not gone on the

    7 new right-of-way section to field delineate the

    8 wetlands.

    9 Q. So, as part of this project, you

    10 would be doing that then? You would be delineating

    11 the wetlands?

    12 A. Correct. The -- for the new

    13 right-of-way, we would go out and field delineate

    14 the wetlands.

    15 Q. And as part of the delineation,

    16 you would be looking into the wetland functions,

    17 that would be impacted by the project. Is that

    18 correct?

    19 A. That is correct.

    20 Q. You would agree the functions

    21 are, you know, what we consider like physical,

    22 chemical, and biological processes occurring in and

    23 making up the ecosystem of the wetlands, roughly?

    24 A. We would evaluate the functions.

    25 But I'm not sure if I understood --

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    49/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 389

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 Q. If you understood all of that.

    3 A. -- all of what you said.

    4 Q. Well, you would understand -- you

    5 know, what is the -- in other words, do the

    6 wetlands provide habitat, what is the -- the water

    7 flow, how are they connected to other water

    8 systems.

    9 But at this point, we can't say

    10 for sure what those wetland functions are of the

    11 wetlands that would be impacted. Is that true?

    12 A. That's correct.

    13 Q. So, in -- in forested wetland

    14 areas, you're going to evaluate the forest habitat

    15 and dependent uses and that would be considered

    16 part of, you know, the impact that you're going to

    17 note in the E.M. and C.P. Is that correct?

    18 A. That's correct. We'll evaluate

    19 the functions and values of the wetlands.

    20 Q. And you would evaluate potential

    21 forest fragmentation that might occur from

    22 construction of a right-of-way through a forested

    23 wetland. Is that correct?

    24 A. Yes, we'll evaluate. It'll be a

    25 conversion of a forested wetland to a shrub-type

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    50/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 390

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 wetland.

    3 Q. And you would evaluate any impact

    4 on fisheries, you know, particularly where the

    5 wetland crossings are in the vicinity of cold water

    6 streams that might be impacted by the removal of

    7 vegetation? I mean, it --.

    8 A. I guess you could put in a

    9 specific request of the list of what you would like

    10 evaluated in a wetland -- in the wetland --

    11 Q. Well, we're -- we're --

    12 A. -- delineation.

    13 Q. -- we're -- I mean, for example

    14 in the Kline Kill area, we're talking about

    15 crossing of a C(T.S.) stream in a -- you know, in

    16 an area that's a forested wetland, so we want to be

    17 sure and have a commitment that there will be an

    18 evaluation of that stream crossing and that -- and

    19 that wetland crossing, and the habitat in and

    20 around that area.

    21 A. Before we go out to do any field

    22 work, I suggest -- we will have the biologist

    23 coordinate with your staff to make sure we get

    24 everything --

    25 Q. Okay.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    51/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 391

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. -- that you would like.

    3 Q. Okay. And we appreciate that.

    4 We -- that's what we're here for the record,

    5 building the record and we appreciate that.

    6 As far as access roads in, you

    7 know, sensitive environmental areas, do you

    8 contemplate constructing access roads? Is it

    9 possible you will construct an access road in a

    10 wetland area, or over a stream?

    11 A. There may be temporary access

    12 roads if needed. If there is a wetland we could

    13 span, there would be no -- and we could come in

    14 from both directions, there would be no need to put

    15 a temporary access road. However, if we do need to

    16 cross that wetland, we would put in a temporary

    17 access road across it.

    18 Q. Now, I know you mentioned and I

    19 think it was in response to D.P.S. Six, that you

    20 talked about the possibility of grading certain

    21 areas so you could move equipment through them and

    22 leaving it as an unimproved access road. Would

    23 wetland crossings be different? You know, access

    24 roads and wetlands, would they be different than

    25 grading an area and making it as an unimproved

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    52/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 392

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 access road?

    3 A. Yes. We -- we would not -- all

    4 of the wetlands from our preliminary engineering

    5 would all be temporary access. We're not proposing

    6 permanent access roads for any of the D.E.C.

    7 regulated wetlands.

    8 (Werth) Right. And it's called

    9 out in section four point five point two point

    10 three, is Exhibit Four, access roads would be

    11 temporary in wetlands.

    12 Q. Okay. And they would be -- and

    13 then the area would be restored -- would be

    14 completely restored to --

    15 A. Yeah.

    16 Q. -- to the wetland area --

    17 A. Yes. They --

    18 Q. -- after this?

    19 A. -- will be restored --

    20 (Howland) That's correct.

    21 (Werth) -- to preconstruction --

    22 Q. It wouldn't be left --

    23 A. -- condition.

    24 Q. -- as a graded -- as a graded

    25 area or whatever?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    53/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 393

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 A. No.

    3 Q. No? Okay.

    4 A.L.J. STEIN: Please -- please

    5 let the witness finish --

    6 MS. WILKINSON: I'm sorry.

    7 A.L.J. STEIN: -- their

    8 responses. Thank you.

    9 BY MS. WILKINSON: (Cont'g.)

    10 Q. You're familiar with D.E.C.'s

    11 wetland mitigation policy?

    12 A. (Howland) Yes, I am.

    13 Q. And you would agree, as part of

    14 this, to prepare a wetland mitigation plan?

    15 A. Yes, we would.

    16 MS. WILKINSON: Your Honor,

    17 just -- just for the record, I would like to enter

    18 a pre-file D.E.C. exhibit, Freshwater Wetlands

    19 Regulation Guidelines on Compensatory Mitigation.

    20 A.L.J. STEIN: I will take this

    21 as Exhibit Number Forty-eight for identification.

    22 Can you give a copy to the

    23 reporter, as well?

    24 (Off-the-record discussion)

    25 A.L.J. STEIN: And this is a

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    54/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 394

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 fifteen-page document -- fourteen-page document

    3 entitled Freshwater Wetlands Regulation Guidelines

    4 on Compensatory Mitigation, Department of

    5 Environmental Conservation.

    6 BY MS. WILKINSON: (Cont'g.)

    7 Q. Ms. Howland, is Exhibit -- I

    8 believe Forty-seven, which I just handed out, is

    9 that what you understand to be the D.E.C. policy of

    10 wetlands --?

    11 A.L.J. STEIN: This is

    12 Forty-eight.

    13 BY MS. WILKINSON: (Cont'g.)

    14 Q. Oh, I'm sorry. Forty-eight, is

    15 that what you recognize as a D.E.C. policy on

    16 wetlands mitigation?

    17 A. (Howland) Yes. It's their --

    18 your guidelines -- guidelines on wetland --

    19 Q. Okay.

    20 A. -- mitigation.

    21 Q. Thank you.

    22 MS. WILKINSON: No further

    23 questions at this time, your Honor.

    24 A.L.J. STEIN: Thank you very

    25 much. *2.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    55/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 395

    1 Howland/Gilstrap/Werth - Cross - Wilkinson

    2 MR. BLOW: I have one follow-up

    3 on the wetlands, which might be helpful if we did

    4 it in the same area, rather than -- but I can wait,

    5 if you want me to.

    6 A.L.J. STEIN: No. Go ahead.

    7 CROSS EXAMINATION

    8 BY MR. BLOW:

    9 Q. In -- are you aware of the -- of

    10 the wetland weighing standards in -- I believe it's

    11 part six sixty-three of D.E.C.'s regulations?

    12 A. (Howland) I'm not familiar with

    13 that section.

    14 Q. Are you aware that there are

    15 class one through four wetlands and that different

    16 standards apply to when you can cross each of those

    17 wetlands?

    18 MS. WILKINSON: Your Honor, I'm

    19 going to object because this is asking for a legal

    20 conclusion and it's --

    21 MR. BLOW: No, it's not.

    22 MS. WILKINSON: -- it's -- it's

    23 ready -- she said she's not familiar with the

    24 standards.

    25 A. I -- I -- I'm familiar that

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    56/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 396

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 there's four classes of wetlands. As far as when

    3 they can be crossed, I'm not familiar with that.

    4 BY MR. BLOW: (Cont'g.)

    5 Q. So, in your -- in the routing of

    6 this -- of -- of -- in -- in deciding upon a route

    7 for the project, are you saying that you did not

    8 look at the wetland weighing standards? You did

    9 not apply them in -- in figuring out the conditions

    10 under which the wetlands can be crossed?

    11 A. (Howland) The D.E.C. wetlands

    12 that would be in the project right-of-way, we

    13 identified the classes of those wetlands. I'm

    14 sorry. I just lost my train of thought.

    15 Q. All right. You -- you identified

    16 the classes of the wetlands to be crossed?

    17 A. Yes, which is --.

    18 Q. But you're not aware that there

    19 are -- that -- that associated with each of the

    20 classes, there are characteristics and -- and

    21 conditions in the wetland weighing standards that

    22 specify when those condition -- when those wetlands

    23 can be crossed, or the conditions under which those

    24 wetlands can be crossed? Is -- is that correct?

    25 MR. METCALFE: I'm going to

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    57/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 397

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 object. I think the witnesses have testified only

    3 that they're not familiar with the D.E.C.

    4 regulations. And it sounds like Mr. Blow is

    5 turning that in to a broader scope than what they

    6 testified to.

    7 A.L.J. STEIN: Can you rephrase

    8 the question?

    9 MR. BLOW: Well, I -- if they're

    10 not aware of it, then I think they have a bigger

    11 problem. So I -- I'm -- I think --.

    12 MR. METCALFE: Well, they may not

    13 be aware of it by citation and that might have been

    14 what was --.

    15 BY MR. BLOW: (Cont'g.)

    16 Q. Well, I don't have the -- I don't

    17 have the wetland weighing standards in my head, as

    18 to -- there are certain wetland -- if -- if I

    19 remember correctly, there are certain standards

    20 that -- a -- a class one wetland can only be

    21 crossed if there's no other reasonable alternative.

    22 I believe that's it.

    23 Ms. Wilkinson could help me out

    24 here, but there are different standards for when

    25 a -- a class two wetland weighing -- a class two

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    58/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 398

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 wetland can only be crossed if a -- certain other

    3 characteristics apply to it.

    4 As -- as you get down to a class

    5 four wetland, it's -- it can be crossed pretty

    6 much -- you know, there's -- there's -- there are

    7 less stringent standards as to when a wetland can

    8 be crossed, depending on which class you're --

    9 you're talking about, whether you go from class

    10 one, two, three, and four.

    11 Are you aware of those -- that

    12 there are -- are you aware that there are less

    13 stringent standards as you proceed for -- for --

    14 when wetlands can be crossed, as you proceed from

    15 class one through class four?

    16 MS. WILKINSON: Your Honor, Mr.

    17 Metcalfe had an objection and I echo his objection

    18 because I think the weighing and balancing

    19 standards in regulation go beyond the expertise of

    20 this particular panel, because they take into

    21 account social and economic and other

    22 considerations. It's a very broad --

    23 MR. BLOW: And I would ask --

    24 MS. WILKINSON: -- way of

    25 balancing.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    59/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 399

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 MR. BLOW: -- then I would ask

    3 Mr. Metcalfe to tell me which panel I can ask this

    4 question to, because this -- this line of

    5 questioning goes to whether, in the routing of this

    6 line, state law is being applied. The wetland

    7 weighing standards are state law, under Section

    8 126.1(f) of the Public Service Law, State Law must

    9 be complied with.

    10 MS. WILKINSON: I agree, Mr.

    11 Blow. But I think that --

    12 MR. BLOW: Right. So, I don't --

    13 MS. WILKINSON: -- I think the

    14 condition is going to be --

    15 MR. BLOW: -- I'm not sure why

    16 you're --

    17 MS. WILKINSON: -- applying it.

    18 A.L.J. STEIN: Wait.

    19 MR. BLOW: -- objecting to my

    20 line of question.

    21 MS. WILKINSON: Because the

    22 condition --.

    23 A.L.J. STEIN: Wait -- wait --

    24 wait -- wait. Order in the court, please. One

    25 person at a time.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    60/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 400

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 Let me follow on Mr. Blow's

    3 suggestion and check with Mr. Metcalfe as to --

    4 will there be a subsequent panel that is qualified

    5 to respond to these questions?

    6 MR. METCALFE: Well, I don't know

    7 that this panel is not qualified to respond, your

    8 Honor.

    9 I took it that his initial

    10 question was focused on the citation for the D.E.C.

    11 regulations. And their answer was there were --

    12 they were not familiar with that citation.

    13 He -- if he were to ask questions

    14 about their familiar -- familiarity with the

    15 weighing standards themselves and their application

    16 here, that might be more helpful.

    17 MR. BLOW: I believe I did and I

    18 believe that the only person that objected to that

    19 line was Ms. Wilkinson.

    20 MR. METCALFE: And I didn't

    21 object to that line.

    22 MR. BLOW: Thank you.

    23 A.L.J. STEIN: And as -- since

    24 it's Mr. Metcalfe's witness, I think it's up to him

    25 to make the objections.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    61/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 401

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 So, if you could restate the

    3 questions along the lines Mr. Metcalfe just

    4 indicated, you can put it back to this panel.

    5 MR. BLOW: Sure.

    6 BY MR. BLOW: (Cont'g.)

    7 Q. Are you aware, that as you go

    8 from a class one wetland to a class four wetland,

    9 the -- the reasons -- the allowable reasons for

    10 crossing or the -- or the characteristics, what you

    11 have to show in order to cross a wetland changes

    12 and becomes less stringent, as you move from class

    13 one to class four?

    14 A. (Ms. Gilstrap) I am aware that

    15 the class -- as you proceed from class one to class

    16 four, that the wetlands become less valuable, that

    17 class one wetlands are -- are the most valuable

    18 wetlands, yes.

    19 Q. And are you aware that the

    20 allowable reasons or characteristics for crossing,

    21 when -- when you decide whether you need to cross a

    22 wetland, the showing that you have to make for a

    23 class one wetland is different and higher than the

    24 cross -- than the -- than the showing that one has

    25 to make in crossing a class four wetland?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    62/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 402

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 A. I am aware that the -- the

    3 standards and protocol for class -- for crossing

    4 class one wetlands are more stringent than crossing

    5 class four wetlands.

    6 Q. And in the routing of the -- of

    7 the -- of the -- proposed routing of the project,

    8 did -- did you -- do you believe that the

    9 characteristics and the reasons and the showings

    10 that are required to cross the various wetlands

    11 have been made in your application?

    12 A. We -- we have noted in our

    13 application the classes of each of the wetlands --

    14 D.E.C. wetlands that are located in the project

    15 corridor.

    16 There is one class three wetland

    17 and three class two wetlands, located inside the

    18 project right-of-way.

    19 MR. BLOW: I think I'll leave it

    20 there.

    21 A.L.J. STEIN: Thank you.

    22 For the Department of Agriculture and Markets?

    23 MR. CUDDEBACK: Good morning,

    24 your Honor.

    25 A.L.J. STEIN: You need a

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    63/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 403

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 microphone.

    3 MR. CUDDEBACK: Thank you. Good

    4 morning, your Honor.

    5 We're proposing to enter three exhibits into

    6 evidence. The first would be an information

    7 request and response, D.P.S. Nine, requested April

    8 19th, 2013, and replied May the 2nd, 2013.

    9 A.L.J. STEIN: And this is a

    10 one-page document?

    11 MR. CUDDEBACK: It is.

    12 A.L.J. STEIN: And --

    13 MR. CUDDEBACK: Yes.

    14 A.L.J. STEIN: -- we will take it

    15 as Exhibit Number Forty-nine, for identification.

    16 MR. CUDDEBACK: Okay. And the

    17 second exhibit is also an information request,

    18 D.P.S. Four, dated April 19th and responded May

    19 2nd, 2013.

    20 A.L.J. STEIN: Just a second.

    21 And this is a three-page document?

    22 MR. CUDDEBACK: It's a three-page

    23 document, with one -- four attachments.

    24 A.L.J. STEIN: And we'll take

    25 that as Exhibit Number Fifty for identification.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    64/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 404

    1 Howland/Gilstrap/Werth - Cross - Blow

    2 MR. CUDDEBACK: Thank you. And

    3 the third document is also an information request

    4 and response, D.P.S. Number Thirty-nine, requested

    5 August 29th, 2013, and replied September 13th,

    6 2013.

    7 A.L.J. STEIN: And that will be

    8 marked as Exhibit Number Fifty-one.

    9 MR. CUDDEBACK: Yes. That's two

    10 pages and one attachment.

    11 A.L.J. STEIN: Thank you.

    12 MR. CUDDEBACK: Thank you.

    13 CROSS EXAMINATION

    14 BY MR. CUDDEBACK:

    15 Q. Good morning. I want to direct

    16 your attention to D.P.S. Nine, which has been

    17 marked as Exhibit Forty-nine. Are you familiar

    18 with that?

    19 A. (Werth) Yes.

    20 Q. In that exhibit, you indicated

    21 that in creating the proposed transmission route

    22 and switching station location, NYSEG has attempted

    23 to balance impacts to open space, agricultural

    24 fields and forested lands, to maximize -- to the

    25 maximum extent practical. Is that true?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    65/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 405

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 A. Yes.

    3 Q. Okay. You also had indicated

    4 that NYSEG has maximized the use of field

    5 boundaries and property boundaries, and that by

    6 citing facility along natural corridors, such as

    7 fields and property boundaries, the line avoids

    8 bisecting properties and open spaces, while also

    9 balancing impacts to the forest and agricultural

    10 resources. Is that correct?

    11 A. Yes.

    12 Q. Please, if you would, turn your

    13 attention to D.P.S. -- to the response to D.P.S.'s

    14 information request, Number Four, which has been

    15 marked as Exhibit Fifty.

    16 If you go to the back of that

    17 document, to the attachment, the last attachment,

    18 which is a map labeled attachment three to that --

    19 to your response, do you see the map?

    20 A. Yes.

    21 (Howland) Yes.

    22 Q. So, the map appears to show the

    23 proposed site for the Ghent switching station and a

    24 portion of the National Grid trunk fifteen

    25 extension loops. Is that correct?

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    66/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 406

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 A. (Werth) Yes.

    3 Q. Looking at that map, it appears

    4 that the switching station and extension loops are

    5 located entirely on an agricultural field. Is that

    6 correct?

    7 A. Within the boundaries of this

    8 map, yes.

    9 Q. And in fact, it appears that the

    10 extension loops bisect that particular agricultural

    11 field. Is that correct?

    12 A. They're located towards the

    13 northern boundary of the field.

    14 Q. Okay. According to NYSEG's

    15 application, Exhibit Four Point Two Point One --

    16 A. Okay.

    17 Q. -- it states that the following

    18 construction -- following construction of the

    19 switching station, agricultural activities will not

    20 resume on the site. Is that still accurate?

    21 A. Within the boundaries of the --

    22 of the switching station, yes.

    23 Q. And the extension loop -- loops?

    24 A. No. Underneath the transmission

    25 lines, agricultural use will be permitted.

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    67/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 407

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 Q. Okay. Yesterday, you mentioned,

    3 I think, in your testimony, that the -- the

    4 switching station would take roughly six percent of

    5 the agricultural field --

    6 A. Yes.

    7 Q. -- operation? Thank you. Now,

    8 in that calculation, do you -- did you take into

    9 account any structures on the field?

    10 A. No. There was not the -- the

    11 transmission lines. That was the switching station

    12 site.

    13 Q. Okay. And did that calculation

    14 also take into account any access roads?

    15 A. The access road has not been

    16 designed, so we don't know the exact impact of

    17 that.

    18 Q. So do we know if construction

    19 will -- construction of the switching station will

    20 affect a larger area than the two-acre footprint of

    21 that site?

    22 A. If construction will?

    23 Q. Would -- would the siting --

    24 well, withdrawn.

    25 Will the construction activities

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    68/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 408

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 affect a larger area than the two-acre footprint on

    3 that site?

    4 MR. METCALFE: Clarification.

    5 Construction activities for the switching station

    6 or the transmission line, or both?

    7 BY MR. CUDDEBACK: (Cont'g.)

    8 Q. Concerning the switching station.

    9 A. (Werth) There may be additional

    10 areas required for construction. I believe that

    11 would be a better question directed towards the

    12 engineers.

    13 Q. Okay. Thank you.

    14 A. (Howland) There should be a

    15 temporary impact on construction.

    16 A.L.J. STEIN: Can you repeat

    17 your answer with the microphone?

    18 A. (Cont'g.) That would be -- I

    19 just noted if it was beyond the footprint of the

    20 Ghent -- proposed Ghent switching station, that

    21 would be a temporary impact for -- during

    22 construction only.

    23 BY MR. CUDDEBACK: (Cont'g.)

    24 Q. So, there may be a need for

    25 additional area -- a construction staging area

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    69/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 409

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 then, in relation to the construction of the

    3 switching station here, as shown as on this map?

    4 A. (Howland) There may be need for

    5 additional temporary impacts for -- along with in

    6 and out of that, to construct a station, I don't

    7 believe we would put in a staging area. The

    8 staging areas would probably be -- we would look

    9 for other areas -- you know, that's what they --

    10 you know, when we're bringing equipment in, you

    11 know there may be a temporary spot for equipment

    12 specific to the Ghent switching station, but we are

    13 not proposing that that area will be a staging area

    14 for the entire construction activities.

    15 Q. Okay. Thank you. Do you know if

    16 NYSEG is proposing to strip and then stockpile

    17 topsoil from the areas affected by the construction

    18 of the switching station and access road?

    19 A. That hasn't been determined yet.

    20 Q. Okay. When -- when -- when is

    21 that normally determined?

    22 A. During the preparation of

    23 environmental management and construction plan.

    24 Q. Okay. Thank you. Typically,

    25 when you do strip and stockpile the topsoil, where

  • 7/29/2019 Transcript for Evidentiary Hearing on 09.18.2013

    70/285

    800.523.7887 Associated Reporters Int'l., Inc.

    Associated Reporters Int'l., Inc. 800.523.7887

    Page 410

    1 Howland/Gilstrap/Werth - Cross - Cuddeback

    2 do you -- where do you put that in temporary

    3 storage?

    4 A. If there's -- I'm having trouble

    5 with your question because I look at when we strip

    6 topsoil, it's for a different type of facility.

    7 Q. Okay.

    8 A. Now, this is going to be a

    9 permanent facility, so you know, that has not been

    10 determined.

    11 Q. Okay. Thank you. So, it's --

    12 it's conceivable then that the stockpiled topsoil