transforming ireland’s electric power systemhourly average wind (mw) over 1 week (week ending...
TRANSCRIPT
Dermot Byrne, Chief Executive, EirGrid plc
ESI Seminar 18th June 2010
Transforming Ireland’s
Electric Power System
Transforming the Power System
Deregulation
Competition and
Customer Choice
Smart Grids
Renewables Integration
and Grid Development
Carbon Neutrality
Electrification of Transport
and Heating Sectors
Time
Industry Value Chain
Generation Distribution Suppliers/
Customers
Evolution of Value Chain:
1. Competition in generation and supply
2. Introduction of Independent Regulatory Authority
3. Network Businesses remain as „natural monopolies‟, but regulated
4. Independence of Transmission System Operators
5. Evolution of Wholesale Power Markets
6. Strategic push towards regional markets (EU)
Transmission
EirGrid
– Ireland’s Independent Transmission System Operator and Operator of the Wholesale Power Market
– Commercial State owned Company
– Separate from all parties in the electricity market
– Established by statute as TSO and licensed by Commission for Energy Regulation
– Annual turnover of approximately €300m
EirGrid’s Role
• To develop, maintain and operate a safe, secure, reliable, economical and efficient transmission system for the benefit of our customers
• To deliver quality transmission and market services
• To advise the Regulator (CER) in relation to security of supply
EirGrid’s Role in the Value Chain (Now)
Generation
Transmission
System Operator
Distribution Suppliers/
Customers
Wholesale Electricity Market
Key Elements of Role:
1. Grid Development
2. Power System Operation
3. Transmission Access
4. Power Market Settlement
EirGrid’s independence from all
market participants is critical
Transmission
Asset Owner
EirGrid’s Role in the Value Chain (Future)
Generation Transmission
Grid CompanyDistribution Suppliers/
Customers
Wholesale Electricity Market
Key Elements of Role:
1. Grid Development
2. Power System Operation
3. Transmission Access
4. Power Market Settlement
EirGrid’s independence from all
market participants is critical
Transmission Grid
• High capacity, efficient,
reliable link between
– Generation
– Demand centres
– Interconnections to other
systems
• Equivalent to “broadband”
power or motorways
400 kV 220 kV 110 kV440 km 4000 km1830 km
2,250
2,750
3,250
3,750
4,250
00:00 06:00 12:00 18:00 00:00
Time
MW
Typical Saturday in February
Ireland v England - 24 February 2007
THE IRELAND V ENGLAND RUGBY MATCH ALTERED THE USAGE OF
ELECTRICITY ACROSS THE WHOLE COUNTRY
The anthems
Ireland England
Croke Park, 24 February 2007
43 : 13
Full time
23 : 3
Half time
43 : 13
EirGrid – An All-Island Energy Company
Transmission Projects in Progress
400 kV / 220 kV/ 110 kV
No. of New Stations 16
Overhead Line 610 km
Underground Cable 33.1 km
No. of New Transformers 17
No. of New Capacitor Banks 12
Uprates 582 km
Refurbishments 83 km
Transforming the Power System
Deregulation
Competition and
Customer Choice
Smart Grids
Renewables Integration
and Grid Development
Carbon Neutrality
Electrification of Transport
and Heating Sectors
Time
Power System Transformation – Two Dimensions
Investment Dimension
The major Infrastructural Building Blocks
The ‘Hardware’
1
2 Operational Dimension Policies, procedures, controls etc
The ‘Software’
Ireland’s Renewable Policy Target
0% 5% 10% 15% 20% 25% 30% 35% 40%
Slovenia
Czech Republic
Hungary
Estonia
Belgium
Cyprus
Finland
Italy
Slovak Republic
Austria
Netherlands
France
Bulgaria
Sweden
Malta
Poland
Spain
UK
Greece
Germany
Portugal
Denmark
Ireland
Wind as a Percentage of Total Electricity (2020 Target) - Select EU Countries
1 Investment Dimension – the ‘Hardware’
ON TARGET FOR 2012
2,200 km Upgrades
1,150 km New Build
€4 billion
€4 bn
Developing the Grid - Grid25
Dublin Area
Cork Area
Planned
Transmission
System
400kV, 220kV &
110 kV
GH
COOKSTOWN
MACETOWNRB
275kV
CATHALEEN'S
FALL CLIFF
SLIGO
TAWNAGHMORE
MOY
CASTLEBAR
PLATIN
NAVAN
MULLINGAR
ATHLONE
CASHLA
GALWAY
ENNIS
DALLOW
TURLOUGH
HILL
ARKLOWSHELTON
ABBEYCARLOW
KILKENNY
THURLES
CAHIR
DOON
ANNERBALLYDINE
GREAT ISLAND
BARRYMORE
MALLOW
CHARLEVILLE
BANDON
DUNMANWAY
MACROOM
KNOCKEARAGH
RATHKEALE
MONEYPOINT
TARBERT
CARRICK
-ON-
SHANNON
LANESBORO
BRINNY
THORNSBERRY
KELLIS
TO TANDRAGEE
TO STRABANE
BUTLERSTOWN
DUNGARVAN
DRYBRIDGE
BLAKE
SHANKILL
LISDRUM
LOUTH
DUNDALK
BELLACORICK
TULLABRACK
MUNGRET
MONETEEN
GRANGE
MAYNOOTH
FASSAROE
AUGHINISH
POLLAPHUCA
CLOON
TO ENNISKILLEN
KNOCKRAHA
KILBARRY
SOMERSET
RAFFEEN
AGHADA
GOLAGH
WATERFORD
GILRA
IKERRIN
NORTHERN
IRELAND
NORTH WALL
POOLBEG
SHELLYBANKS
KILTEEL
LISHEEN
GORTAWEE
OUGHTRAGH
CUSHALING
ARVA
MULLAGHARLIN
SHANNONBRIDGE
ARIGNA
TRILLICK
IRISHTOWN
CARRIGADROHID
COOLROE
TRABEG
INNISCARRA
MARINA
DUNFIRTH
STRATFORD
KINNEGAD
BALLYLICKEY
DALTON
CORRACLASSY
OLDSTREET
CLASHAVOON
BALLYBEG
CUNGHILL
KILLOTERANCULLENAGH
TIPPERARY
HUNTSTOWN
GLENLARA
ARDNACRUSHA
KILMORE
FINGLASCOLLEGE
PARKDERRYIRON
SEE
DUBLIN
AREA
TRALEE
TRIEN
PROSPECT
DRUMLINE
GLASMORE
AHANE
WOODLAND
CASTLEFARM
SEALROCK
CORDERRY
BALLYWATER
GORMAN
DERRYBRIEN
AGANNYGAL
CLONKEEN
COOMAGEARLAHY
BOOLTIAGH
SORNE
HILL
RATRUSSAN
GLANLEE
Transmission System400 kV, 220 kV and 110 kV
January 2008
BARODANEWBRIDGE
MONREAD
CORDUFF
CRANE
KILTOY
LETTERKENNY
MEENTYCAT
DRUMKEEN
BINBANE
TYNAGH
LIMERICK
PORTLAOISE
DUNSTOWN
RINAWADE
INCHICORE
CARRICKMINES
WEXFORD
KILLONAN
KNOCKUMBER
MEATH
HILLTONROE
FLAGFORD
RICHMOND
WHITEGATE
Existing Transmission Network in South
GH
COOKSTOWN
MACETOWNRB
275kV
CATHALEEN'S
FALL CLIFF
SLIGO
TAWNAGHMORE
MOY
CASTLEBAR
PLATIN
NAVAN
MULLINGAR
ATHLONE
CASHLA
GALWAY
ENNIS
DALLOW
TURLOUGH
HILL
ARKLOWSHELTON
ABBEYCARLOW
KILKENNY
THURLES
CAHIR
DOON
ANNERBALLYDINE
GREAT ISLAND
BARRYMORE
MALLOW
CHARLEVILLE
BANDON
DUNMANWAY
MACROOM
KNOCKEARAGH
RATHKEALE
MONEYPOINT
TARBERT
CARRICK
-ON-
SHANNON
LANESBORO
BRINNY
THORNSBERRY
KELLIS
TO TANDRAGEE
TO STRABANE
BUTLERSTOWN
DUNGARVAN
DRYBRIDGE
BLAKE
SHANKILL
LISDRUM
LOUTH
DUNDALK
BELLACORICK
TULLABRACK
MUNGRET
MONETEEN
GRANGE
MAYNOOTH
FASSAROE
AUGHINISH
POLLAPHUCA
CLOON
TO ENNISKILLEN
KNOCKRAHA
KILBARRY
SOMERSET
RAFFEEN
AGHADA
GOLAGH
WATERFORD
GILRA
IKERRIN
NORTHERN
IRELAND
NORTH WALL
POOLBEG
SHELLYBANKS
KILTEEL
LISHEEN
GORTAWEE
OUGHTRAGH
CUSHALING
ARVA
MULLAGHARLIN
SHANNONBRIDGE
ARIGNA
TRILLICK
IRISHTOWN
CARRIGADROHID
COOLROE
TRABEG
INNISCARRA
MARINA
DUNFIRTH
STRATFORD
KINNEGAD
BALLYLICKEY
DALTON
CORRACLASSY
OLDSTREET
CLASHAVOON
BALLYBEG
CUNGHILL
KILLOTERANCULLENAGH
TIPPERARY
HUNTSTOWN
GLENLARA
ARDNACRUSHA
KILMORE
FINGLASCOLLEGE
PARKDERRYIRON
SEE
DUBLIN
AREA
TRALEE
TRIEN
PROSPECT
DRUMLINE
GLASMORE
AHANE
WOODLAND
CASTLEFARM
SEALROCK
CORDERRY
BALLYWATER
GORMAN
DERRYBRIEN
AGANNYGAL
CLONKEEN
COOMAGEARLAHY
BOOLTIAGH
SORNE
HILL
RATRUSSAN
GLANLEE
Transmission System400 kV, 220 kV and 110 kV
January 2008
BARODANEWBRIDGE
MONREAD
CORDUFF
CRANE
KILTOY
LETTERKENNY
MEENTYCAT
DRUMKEEN
BINBANE
TYNAGH
LIMERICK
PORTLAOISE
DUNSTOWN
RINAWADE
INCHICORE
CARRICKMINES
WEXFORD
KILLONAN
KNOCKUMBER
MEATH
HILLTONROE
FLAGFORD
RICHMOND
WHITEGATE
Ballyvouskil
Kishkeam
Knockanure
CORDAL
KNOCKACUMMER
GARROW
KILGARVAN
KERRY
CLAHANE
BARNADEVINE
CLOUGHBOOLA
ATHEA
KIPPALOCK
TOEM
BOGGERAGH
700MW
305MW
520MW
280MW
DROMADA
Kilpaddogue
GRID25 Network Development South
*
Primary Corridors for ReinforcementInvestigation
Construction Challenge
Getting the Balance Right:
• Reliability
• Cost
• Impact
0
100
200
300
400
500
600
700
800
900
1 25 49 73 97 121 145
MW
Hours
Hourly Average Wind (MW) over 1
week (week ending March 15th 2009)
Hourly Average Wind (MW) over 1 week (week ending March 15th 2009)
0
100
200
300
400
500
600
700
800
900
1 25 49 73 97 121 145
Hours
MW
Challenges
• Resource Intermittency
• System Stability
• Uncertainty
• Complexity
• Portfolio Performance
Smart GridResponses
• ICT
• Customer responsiveness
• Decision support tools
• Codes / Protocols
• Smart Meters
Operational Dimension – the ‘Software’2
TSO Renewable Facilitation Studies
Objectives:
• Increase our understanding of the behaviour of the power system with large amounts of renewable generation
• Identify any potential technical issues
• Develop mitigation measures
• Wrap it all up in a comprehensive strategy for the operation of the power system with large amounts of renewables
Studies:
• 4000 Frequency response studies 5000 Transient Stability studies
• 1000 Short Circuit Level studies Analysis of Wind patterns
First comprehensive study of its kind in the World
Transforming the Power System
Deregulation
Competition and
Customer Choice
Smart Grids
Renewables Integration
and Grid Development
Carbon Neutrality
Electrification of Transport
and Heating Sectors
Time
Case for further interconnection
• This confirms the very strong economic case for the
East-West Interconnector.
• Further interconnection between AI and GB is
economically attractive.
• Interconnection from Ireland to France also appears
beneficial, but further detailed work is required to verify
this and evaluate this against Ireland – Great Britain
interconnectors.
• Interconnection assists in integration of more wind on
the system, particularly for export.
EirGrid Off-Shore Grid Study
Study Objectives:
•Develop optimised off-shore grid
development strategies
•Utilise that strategy to inform the TSO
offshore functional designs and policies
Scenarios:
•3/5/7GW off-shore.
•Study Period out to 2030
•Part A: off-shore Ireland only
•Part B: incorporating links to rest of
Europe
Will feed into other broader-based
studies (ENTSO-E, SEI etc.)
Future Generation Portfolio Options
Objectives:
• Dramatic reduction in Carbon Intensity
• Identify technology options
• Contribute to informed debate
Study:
• Year 2035 selected
• Six Balanced Portfolios identified
• Detailed modelling performed
• Results presented
3
Context
• Moneypoint, peat and oil plants set to close: fuel diversity issue.
• Debate should now progress to longer term policy
• Goal will be a transition to a low carbon electricity system.
• Wide range of options have development potential in this timeframe.
Summary
• Significant emissions reductions can be achieved in all portfolios
• All portfolios have higher capital costs and lower running costs relative to today.
• Under current policies the gas portfolio is the most likely outcome and could be viewed as a transitional step towards carbon neutrality by 2050.
• Coal CCS, nuclear, high renewables, storage and interconnection are all able to further reduce emission levels, however a number of technical, environmental and cost issues would need to be overcome
Conclusion
• The purpose of this report is to contribute to a debate on energy policy.
• It builds on, and is complementary to, the Joint Committee’s previous consultation and report on Electricity Needs post 2020.
• There are no simple or easy choices in this complex area.
Transforming the Power System
Deregulation
Competition and
Customer Choice
Smart Grids
Renewables Integration
and Grid Development
Carbon Neutrality
Electrification of Transport
and Heating Sectors
Time