1 Bond Buyer: Transportation P3 Conf. Bond Buyer: Transportation P3 Conf. Transit P3 Transit P3 s s - - DBOMs DBOMs , , Facility Facility Providers & Long Term Payments Providers & Long Term Payments By: Chris Kane, P.E., J.D., By: Chris Kane, P.E., J.D., Vice President Project Development Vice President Project Development Washington Group International, Inc. Washington Group International, Inc. October 19, 2007 October 19, 2007 October 19, 2007

Upload: others

Post on 13-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

1

Bond Buyer: Transportation P3 Conf.Bond Buyer: Transportation P3 Conf.

Transit P3Transit P3’’s s -- DBOMsDBOMs,, Facility Facility Providers & Long Term Payments Providers & Long Term Payments

By: Chris Kane, P.E., J.D., By: Chris Kane, P.E., J.D., Vice President Project DevelopmentVice President Project Development Washington Group International, Inc.Washington Group International, Inc.

October 19, 2007October 19, 2007October 19, 2007

Page 2: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

2

Project Delivery ContinuumProject Delivery Continuum

DesignBid

Build

PrivateContract

FeeServices

DesignBuild

DesignBuild

OperateMaintain(DBOM)

LongTermLease

Agreement

DesignBuild

FinanceOperate(DBFO)

DesignBuildOwn

Operate(BOO)

Public Projects Concessions/Privatizations

Public Pays

Tax Exempt Financing

Public Control

Public Equity

User Pays

Taxable Financing

Private Control

Private Equity

Public Private Partnerships

Page 3: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

3

Typical PPP StructureTypical PPP StructureTypical PPP Structure

Comprehensive

Funding $$Fare Box / Tolls

Tax Improvement DistrictJoint Development

Sweat Equity

“Owner”

Public Agency

Funding $$(State, Federal)

“Contractor”Private Consortium

Design-Build ContractDevelopmentContract

Operations & MaintenanceContract

Parent Guarantees(from SPC Members)Performance

Bonds

Agreement

• Environment• Right-of-way• PE• Finance Plan

• Final Design• Right-of-way Acquisition• Construction• Startup Turnover

• Infrastructure/R.O.W. Maintenance

• Equipment/Car Maintenance• Toll Facility/Transit Operations

IssuingEntity

Page 4: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

4

Hudson-Bergen Light RailHudsonHudson--Bergen Light RailBergen Light Rail

Description:20 miles double-track light rail transit with 23 stationsOver $1 billion in Design-Build Construction15-yr Operations & Maintenance contractIncludes manufacture of 43 light rail vehicles

Achievements:Opened April 2000 for Phase 1 revenue service with 5 years of highly successful on time and safe operationsFirst Phase Design Build Completion with no claims, on time and on budget

Client: New Jersey TransitLocation: Hudson & Bergen Counties, NJContract Value: $1.9 BillionContract Type: PPP Design-Build- Operate-Maintain

Performed as: 21st Century Rail Corp.(Washington Group, Kinkisharyo/Itochu)

Page 5: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

5

Hudson-Bergen Light Rail (DBOM)HudsonHudson--Bergen Light Rail (DBOM)Bergen Light Rail (DBOM)

Comprehensive

Funding $$Fare Box / Tolls

Tax Improvement DistrictJoint Development

Sweat Equity

NJ TransitPublic Agency

Funding $$(State, Federal)

21st CenturySpecial Purpose Co.

Design-Build ContractDevelopmentContract

Operations & MaintenanceContract

Parent Guarantees(from SPC Members)Performance

Bonds

Agreement

• Environment• Right-of-way• PE• Finance Plan

• Final Design• Right-of-way Acquisition• Construction• Startup Turnover

• Infrastructure/R.O.W. Maintenance

• Equipment/Car Maintenance• Toll Facility/Transit Operations

IssuingEntity

Page 6: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

6

Process Time Savings ….Equals Project Cost Savings Process Time Savings Process Time Savings …….Equals Project Cost Savings.Equals Project Cost Savings

1 2 3 4 5 6 7 8 9 10 11

1,200,000

1,000,000

800,000

600,000

400,000

200,000

0

Years

Traditional129 Month Schedule$1,054.4M Cost

PPP – Bid: D/B103 Month Schedule$748.6M Cost

PPP – Prog. D/B88 Month Schedule$641.7M Cost

Traditional D-B-B

BID: Design-Build (PPP)

Progressive Design-Build (PPP)

Revenue Ready

$ x M

illion

Page 7: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

7

Design-Build (DB) vs. DBOMDesignDesign--Build (DB) vs. DBOMBuild (DB) vs. DBOM

Warranty (15 Year)Turn-Back

Safety Certification

Design-BuildWarranty

(1 Year)

Acceptance

Safety Certification

Owner Operate & Maintain

Design-Build / Owner Operation (D/B)

Design-Build-Operate-Maintain (DBOM)

Start-up

Design-Build Contractor Operate & MaintainStart-up

Acceptance

Page 8: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

8

DB vs DBOM Comparison -Transition to Operations DB DB vsvs DBOM Comparison DBOM Comparison --Transition to OperationsTransition to Operations

D/B w/ Owner Operation

2-3 major participants

Limited warranty period

Little life cycle cost benefit

Owner safety certification

Fragmented responsibilities

Design-Build and OPERATE

Single-source responsibility

Extended warranty period

Integrated life-cycle costing

Contractor safety certification

Direct contract schedule & cost benefits

Page 9: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

9

Dulles Metrorail ProjectDulles Metrorail ProjectDulles Metrorail Project

Description:Heavy rail system extension22 miles, 11 stationsLargest US PPP ever undertaken

Achievements:Private development investment

Over $10 million pre-contract investment $15 million cost sharing during development phase

Early Value Planning efforts identified nearly $200 million is savings

Client: Virginia Dept. of Rail / Public TransportLocation: Fairfax & Loudoun Counties, VAProject Value: $4.5 BillionContract Type: Completed Development and PE; D/B Contract in process

Performed as: Dulles Transit Partners, LLC(Washington Group, Bechtel Infrastructure)

Page 10: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

10

Dulles Metrorail (Develop and DB)Dulles Metrorail (Develop and DB)Dulles Metrorail (Develop and DB)

Comprehensive

Funding $$Fare Box / Tolls

Tax Improvement DistrictJoint Development

Sweat Equity

MWAA/Virginia DRPT

Public Agency

Funding $$(State, Federal)

Dulles Transit Partners

Special Purpose Co.

Design-Build ContractDevelopmentContract

Operations & MaintenanceContract

Parent Guarantees(from SPC Members)Performance

Bonds

Agreement

• Environment• Right-of-way• PE• Finance Plan

• Final Design• Right-of-way Acquisition• Construction• Startup Turnover

• Infrastructure/R.O.W. Maintenance

• Equipment/Car Maintenance• Toll Facility/Transit Operations

IssuingEntity

Page 11: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

11

Dulles Metrorail Innovative Finance Phase I Dulles MetrorailDulles Metrorail Innovative Finance Phase IInnovative Finance Phase I

Funding Source Funding ShareFederal Sources—FTA New Starts 36%Non-Federal Sources 64%

Virginia Transportation Act of 2000 2.1%Dulles Toll Road Revenues 36.9%

Fairfax County Dulles Tax Districts 16.1%Loudon County License Fees 4.8%MWAA Passenger Facility Charges 4.1%

Total 100%

Page 12: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

12

Value Planning Identifying Savings Early Value Planning Value Planning Identifying Savings EarlyIdentifying Savings Early

Time

HighAbility to make changes

Degree ofChange

LowPlanning Design Construction

Cost of making changes

Best Opportunity for Improvement

Page 13: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

13

Value Planning (Dulles Metrorail) Value Planning Value Planning (Dulles Metrorail)(Dulles Metrorail)

First activity in development services

Involved all project participants

Took 4 months and cost $400K – Developed 180 proposals

– Recommended 35, of which 13 were chosen

The 13 identified = $190 million in savings

Simple alignment change in tunneling area can save $71 million alone

Page 14: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

14

Greenfield Transit / Toll Road (DBOMF)Greenfield Transit / Toll Road (DBOMF)Greenfield Transit / Toll Road (DBOMF)

Comprehensive

Funding $$Fare Box / Tolls

Tax Improvement DistrictJoint Development

Sweat Equity

Public Agency Funding $$(State, Federal)

Special Purpose Company

Design-Build ContractDevelopmentContract

Operations & MaintenanceContract

Parent Guarantees(from SPC Members)Performance

Bonds

Agreement

• Environment• Right-of-way• PE• Finance Plan

• Final Design• Right-of-way Acquisition• Construction• Startup Turnover

• Infrastructure/R.O.W. Maintenance

• Equipment/Car Maintenance• Toll Facility/Transit Operations

IssuingEntity

Page 15: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

15

Houston METRO – Facility Provider Framework (in negotiation) Houston METRO Houston METRO –– Facility Provider Framework Facility Provider Framework (in negotiation)(in negotiation)

• Progress Design• Cost Estimate• Plan of Finance• Scope to Budget• Phase 2 Proposal

Project Development

RemediationContract

Design-BuildContract

VehicleProcurement

O&MContract

Facility Provider

• Grip Price• Remediation Closure• Insurance• Performance• Coordination

• Cost & Schedule• Utility Relocation• Performance Guarantees• D-B Revenue Ready Status• D-B Warranty

• Cost & Schedule• Revenue Ready Status -

Vehicles• Vehicle Warranty• Performance Guarantees• Vehicle Performance

• Maintenance Cost• Operation Cost• System Availability• System Performance• Capital Asset

Replacement Program

Page 16: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

16

Houston METRO - Value Added ProposalHouston METRO Houston METRO -- Value Added ProposalValue Added Proposal

Houston METRO Funding Restraints:

– Dedicated sales tax

– FTA funding possible for 2 segments

– Bonding limitation of $640M

– Would limit project to bus rapid transit

Washington Group Proposal

– Vehicles, property, terminal to separate funding

– Use long term DB payments(40 year)

– FP rights to DB receivables sold to a Securitization Trust (ST)

– ST issues debt based on general credit of Houston METRO (estimated $1.8 billion)

Page 17: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value:

17

Houston METRO - Facility Provider Finance (in negotiation) Houston METRO Houston METRO -- Facility Provider Finance Facility Provider Finance (in negotiation)(in negotiation)

Bond Holders

Funding $$State & Federal Grants

Sales TaxFare Box

Joint Development

Facility Provider (FP)Securitization Trust (ST)($$ Construction fund/Reserves)

Design-Build Contractor

Deferred Payments (FPA)35 - 40 Year Term

Deferred Payments Assignments

Progress Payments

Bond Proceeds

Interest & Principal

Deferred Payments (FPA)

Vehicles Procurement Remediation Contract

Page 18: Transit P3’s - - DBOMs, , Facility Providers & Long Term ... - screen pr… · Virginia Dept. of Rail / Public Transport. Location: Fairfax & Loudoun Counties, VA. Project Value: